5. N-2933 – Estrutura simplificada
1. Requisitos Gerais da Automação de Sistemas Elétricos
2. Requisitos de Hardware e Software
3. Requisitos para o Projeto
4. Documentação da Automação de Sistemas Elétricos
5. Montagem, Condicionamento e Comissionamento
6. Testes e Critérios de Aceitação
7. Requisitos de Treinamentos
• Anexos:
• A– Lista de Atividades para Determinação de Escopo
• B- Práticas Recomendadas
• C- LDs para cada fase do projeto
• D- Diagramas Lógicos Típicos
• E- LNs Típicos
6. I-ET-3010.00-5140-797-P4X-001 – ELECTRICAL
SYSTEM AUTOMATION ARCHITECTURE
1. Electrical System Automation
2. Electrical System Automation Main Components
3. Automation of Electrical Equipment
4. Interface Between Electrical System Automation and
Process Automation (A&C)
5. Interface of Electrical System Automation Between Hull
and Topside
6. Interface Between Electrical System Automation and
Remote Onshore Operation Center
7. Testing
8. Training
7. Requisitos Gerais
Confiabilidade
“...não deve haver uma falha de um
único equipamento, dispositivo ou
componente que torne o sistema
elétrico inoperável ou sem
controle.”
Disponibilidade
“A classe de disponibilidade
(availability) dos componentes do
sistema deve ser A3 de acordo com
a IEC 60870-4.”
8. Requisitos Gerais
Sincronismo de Tempo
SNTP com resolução mínima de 1,0 ms
PTP com resolução mínima de 4 μs
Redundância
“The Electrical System Automation equipment shall be fed by
redundant UPS feeders according with the document EMERGENCY
LOADS LIST.”
9. Equipamentos - Servidores
“Cada servidor deve ser constituído por unidades de
armazenamento extraíveis pelo frontal do equipamento com
facilidades para troca a quente (“hot-swap”).”
“Topside Electrical System Automation RTDSs shall include OPC
Clients and Servers compatible with PMS, TGCP and HGCP OPC
Clients and Servers in order to be capable of reading and writing
all data.
10. Equipamentos - Workstations
“The remote operating and monitoring of all the electrical
equipment shall be, at least, according with I-LI-3010.00-5140-
797-P4X-001 - ELECTRICAL SYSTEM AUTOMATION INTERFACE
SIGNALS LIST.”
“Deve ser elaborada na estação de engenharia uma tela de
interface para a parametrização de todos os sistemas e
funcionalidades da automação do sistema elétrico.”
11. Equipamentos - Switches
“All switches belonging to the Electrical System Automation
Networks shall be manageable switches.”
“Switches connecting equipment according to standard IEC 61850
shall be certified for this network protocol.”
12. Equipamentos – Dispositivos Portáteis
“The Electrical System Automation Operational Portable Device
shall follow the hazardous area requirements for equipment that
shall be kept operating during emergency shutdown ESD-3P and
ESD-3T”
“The Electrical System Automation Operational Portable Device
shall include a QR Code reader in order to read QR Codes from
electrical equipment.”
“Different access levels protected through different passwords
shall be granted for operation and monitoring of Electrical System
equipment. Historical report with discrimination of users’ access
and actions, such as commands, shall be stored for all operations.
Access levels shall be equal to the ones of ESA Operational
Workstations.”
18. Referências
• N-2933 – Automação de Sistemas Elétricos – Requisitos de Projeto,
Equipamentos, Testes e Comissionamento
• N-2900 – Gerenciamento de Alarmes
• I-ET-3010.00-5140-797-P4X-001 – ELECTRICAL SYSTEM AUTOMATION
ARCHITECTURE
• I-DE-3010.00-5140-797-P4X-001 – ELECTRICAL SYSTEM AUTOMATION
ARCHITECTURE DIAGRAM
• LOPES, Yona et al. Smart Grid e IEC 61850: Novos Desafios em
Redes e Telecomunicações para o Sistema Elétrico. In: XXX
Simpósio Brasileiro de Telecomunicações, 2012, Brasília. Minicurso
para o SBrT'2012. Brasília. 2012.
• IEC 62439-3 – Industrial Communication Networks – High Availability
Automation Networks. 2016.
https://canalfornecedor.petrobras.com.br/pt/regras-de-
contratacao/catalogo-de-padronizacao/#especificacoes-tecnicas