Metro Line 4 - Public and Private
       Partnership (PPP)
    Project’s Basic Details
São Paulo Line 4 - Features
São Paulo Line 4 - Features
          Overview
               The exploration term for exploring passenger transportation of São Paulo
             Yellow Line 4 is 30 years. The extension is of 12.8 km and crosses Butantã,
             Pinheiros, Faria Lima, Paulista, República and Luz stations (Phase I);
             Fradique Coutinho, Oscar Freire, Higienópolis. Maintenance station Vila
             Sônia and systems (Phase II).
                The operation will be complemented from Vila Sônia to Taboão da Serra,
             trough Bus with no additional tariff.

V. Sonia station




  0.9 km                                                                  12.9 km                                                                       0.5 km




                                                                                                Oscar
                                                                                                Freire
                                                            Faria Lima




                                                                                                                                            República




                                                                                                                                                        Luz
                                                                          Fr. Coutinho




                                                                                                         Paulista
                                                Pinheiros




                                                                                                                              Higien.
                                Butantã
                     Morumbi
        Vila Sonia




                                          PHASE I              PHASE II                  VENTILATION                Operational stretch –
                                                                                                                      Phase1 8.9 km
São Paulo Metro Line 4
Main Features
  Concessionaire’s Capital Expenditures: Rolling material and signalization
systems (courtyard control; central control and supervision, voice and data
mobile communication);
  Estimated Capex
         Phase 1: US$ 234 million
         Phase 2: US$ 211 million
  Source of revenues: Tariff, Other Revenues and Counter payment
 Tariff: R$ 2.08 (February 2005)
      Pass: Line 4: 100% tariff
      Pass: Integration Metro/CPTM: 50% tariff
  Annual Readjustment : 50 IGPM + 50% IPC (15 years) – after that 100% IPC
  Centralized Collecting System
São Paulo Metro Line 4
Main Features (cont.)
  Counter payment from Granting Authority in the Amount of R$ 75 million
 Guarantor of Counter payment, fines and indemnification – CPP
 Share demand risk – up to 10% is a concessionaire risk. Above 10% is a
 shared risk (profit and loss)
 Consortium: CCR – 68%, RATP – 1%, BRT – 1% and Montgomery – 30%

More Related Content

Viewers also liked (11)

Presentation 4 t10 english
Presentation 4 t10   englishPresentation 4 t10   english
Presentation 4 t10 english
 
Brazil’s ccr announces agreement to acquire via oeste
Brazil’s ccr announces agreement to acquire via oesteBrazil’s ccr announces agreement to acquire via oeste
Brazil’s ccr announces agreement to acquire via oeste
 
Ccr day2 presentation
Ccr day2 presentationCcr day2 presentation
Ccr day2 presentation
 
Ccr day 3 presentation
Ccr day 3 presentationCcr day 3 presentation
Ccr day 3 presentation
 
Ubs warburg conferência ceo brasil 2003
Ubs warburg conferência ceo brasil 2003Ubs warburg conferência ceo brasil 2003
Ubs warburg conferência ceo brasil 2003
 
Presentation 3Q15 - CCR
Presentation 3Q15 - CCRPresentation 3Q15 - CCR
Presentation 3Q15 - CCR
 
3Q11 Earnings Results
3Q11 Earnings Results3Q11 Earnings Results
3Q11 Earnings Results
 
CCR DAY 11_Eng
CCR DAY 11_EngCCR DAY 11_Eng
CCR DAY 11_Eng
 
Presentation 4Q15 CCR
Presentation 4Q15 CCRPresentation 4Q15 CCR
Presentation 4Q15 CCR
 
Apimec – 1 q07 results
Apimec – 1 q07 resultsApimec – 1 q07 results
Apimec – 1 q07 results
 
Presentation 1Q16
Presentation 1Q16Presentation 1Q16
Presentation 1Q16
 

More from CCR Relações com Investidores (20)

CCR PRESENTATION 4Q18
CCR PRESENTATION 4Q18CCR PRESENTATION 4Q18
CCR PRESENTATION 4Q18
 
Apresentação de Resultado- CCR 4T18
Apresentação de Resultado- CCR 4T18Apresentação de Resultado- CCR 4T18
Apresentação de Resultado- CCR 4T18
 
Apresentação 2T18
Apresentação 2T18Apresentação 2T18
Apresentação 2T18
 
2Q18 Presentation
2Q18 Presentation2Q18 Presentation
2Q18 Presentation
 
1Q18 Presentation
1Q18 Presentation1Q18 Presentation
1Q18 Presentation
 
Apresentação 1T18
Apresentação 1T18Apresentação 1T18
Apresentação 1T18
 
4Q17 Earnings Presentation
4Q17 Earnings Presentation4Q17 Earnings Presentation
4Q17 Earnings Presentation
 
Apresentação 4T17
Apresentação 4T17Apresentação 4T17
Apresentação 4T17
 
CCR Day 13 Presentation
CCR Day 13 Presentation CCR Day 13 Presentation
CCR Day 13 Presentation
 
CCR Day 13
CCR Day 13 CCR Day 13
CCR Day 13
 
Presentation 3Q17
Presentation 3Q17  Presentation 3Q17
Presentation 3Q17
 
Apresentação 3T17
Apresentação 3T17Apresentação 3T17
Apresentação 3T17
 
Presentations 2Q17
Presentations 2Q17Presentations 2Q17
Presentations 2Q17
 
Apresentação 2T17
Apresentação 2T17Apresentação 2T17
Apresentação 2T17
 
Presentation 2Q17
Presentation 2Q17Presentation 2Q17
Presentation 2Q17
 
Apresentação 2 t17
Apresentação 2 t17Apresentação 2 t17
Apresentação 2 t17
 
Presentation 1Q17
Presentation 1Q17 Presentation 1Q17
Presentation 1Q17
 
Apresentação 1T17
Apresentação 1T17Apresentação 1T17
Apresentação 1T17
 
Presentation 4Q16
Presentation 4Q16   Presentation 4Q16
Presentation 4Q16
 
Apresentação 4 t16
Apresentação 4 t16  Apresentação 4 t16
Apresentação 4 t16
 

São paulo subway line 4

  • 1. Metro Line 4 - Public and Private Partnership (PPP) Project’s Basic Details
  • 2. São Paulo Line 4 - Features
  • 3. São Paulo Line 4 - Features Overview The exploration term for exploring passenger transportation of São Paulo Yellow Line 4 is 30 years. The extension is of 12.8 km and crosses Butantã, Pinheiros, Faria Lima, Paulista, República and Luz stations (Phase I); Fradique Coutinho, Oscar Freire, Higienópolis. Maintenance station Vila Sônia and systems (Phase II). The operation will be complemented from Vila Sônia to Taboão da Serra, trough Bus with no additional tariff. V. Sonia station 0.9 km 12.9 km 0.5 km Oscar Freire Faria Lima República Luz Fr. Coutinho Paulista Pinheiros Higien. Butantã Morumbi Vila Sonia PHASE I PHASE II VENTILATION Operational stretch – Phase1 8.9 km
  • 4. São Paulo Metro Line 4 Main Features Concessionaire’s Capital Expenditures: Rolling material and signalization systems (courtyard control; central control and supervision, voice and data mobile communication); Estimated Capex Phase 1: US$ 234 million Phase 2: US$ 211 million Source of revenues: Tariff, Other Revenues and Counter payment Tariff: R$ 2.08 (February 2005) Pass: Line 4: 100% tariff Pass: Integration Metro/CPTM: 50% tariff Annual Readjustment : 50 IGPM + 50% IPC (15 years) – after that 100% IPC Centralized Collecting System
  • 5. São Paulo Metro Line 4 Main Features (cont.) Counter payment from Granting Authority in the Amount of R$ 75 million Guarantor of Counter payment, fines and indemnification – CPP Share demand risk – up to 10% is a concessionaire risk. Above 10% is a shared risk (profit and loss) Consortium: CCR – 68%, RATP – 1%, BRT – 1% and Montgomery – 30%