4. Açu Shipyard – Layout FPSO Dry dock and effluent treatment station Quays Electricity Substation 345 kV – 13.8 kV Jacket assembly area Administrative buildings ETA Green Curtain Module construction area Platform construction area Industrial unit 4 Administrative buildings with LEED Certification (US Green Building Council)
5. Shipyard– Licensing Schedule Oct-10 Jan-11 Jun-11 Jul-11 EIA/RIMA Filling Public Meetings Preliminary License (LP) Issuance Installation License (LI) Issuance Beginning of Construction Feb-11 5
6.
7. UCN – Construction Timeline 7 Packages Receipt of Proposals Contracting Mobilization Vegetation Supression March-11 2Q11 Installation License Issuance Ground Preparation May-11 3Q11 3Q11 North Quay and WHP area June-11 3Q11 4Q11 Dry dock June-11 3Q11 4Q11 South Quay and Respective Retro Area June-11 3Q11 4Q11 Industrial Buildings April-11 3Q11 4Q11 Utilities and Infrastructure May-11 3Q11 3Q11 Administrative Buildings (LEED) July-11 1Q12 1Q12 Administrative Buildings (Non LEED) Sepetember-11 4Q11 1Q12 Electromechanical Assembly August-11 1Q12 2Q12 Supervisory Support December-10 2Q11 2Q11 Contractor houses April-11 3Q11 3Q11
11. FPSO OSX-1 – Customization MODIFICATION WORK NEW INSTALLATION Hull / Engine Room Mod. Central Pipe Rack Mod. M430 Mod. M400 Mod. M310 N ew M280 Mod. M250 N ew M220 Mod. W140 Mod. F110 Mod. N130 Mod. N160 Mod. M350 N ew M2 0 0 N ew M320 Mod. M290 Mod. M260 Mod. M380 N ew M230 N ew 11