Manage Team
Coincides with PMBOK 9.5
Process Group and Knowledge Area Mapping
Knowledge Areas Initiating Planning Process Group Executing Process Group Monitoring and Controlling Process Group Closing Process Group
4. Project Integration
Management
4.1 Develop Project Charter
4.2 Develop Project Management
Plan
4.3 Direct and Manage Project Work
4.4 Manage Project Knowledge
4.5 Monitor and Control Project Work
4.6 Perform Integrated Change Control
4.7 Close Project or Phase
5. Project Scope
Management
5.1 Plan Scope Management
5.2 Collect Requirements
5.3 Define Scope
5.4 Create WBS
5.5 Validate Scope
5.6 Control Scope
6. Project Schedule
Management
6.1 Plan Schedule Management
6.2 Define Activities
6.3 Sequence Activities
6.4 Estimate Activity Durations
6.5 Develop Schedule
6.6 Control Schedule
7. Project Cost Management
7.1 Plan Cost Management
7.2 Estimate Costs
7.3 Determine Budget
7.4 Control Costs
8. Project Quality
Management
8.1 Plan Quality Management 8.2 Manage Quality 8.3 Control Quality
9. Project Resource
Management
9.1 Plan Resource Management
9.2 Estimate Activity Resources
9.3 Acquire Resources
9.4 Develop Team
9.5 Manage Team
9.6 Control Resources
10. Project Communications
Management
10.1 Plan Communications
Management
10.2 Manage Communications 10.3 Monitor Communications
11. Project Risk
Management
11.1 Plan Risk Management
11.2 Identify Risks
11.3 Perform Qualitative Risk Analysis
11.4 Perform Quantitative Risk
Analysis
11.5 Plan Risk Responses
11.6 Implement Risk Responses 11.7 Monitor Risks
12. Project Procurement
Management
12.1 Plan Procurement Management 12.2 Conduct Procurements 12.3 Control Procurements
13. Project Stakeholder
Management
13.1 Identify Stakeholders 13.2 Plan Stakeholder Engagement
13.3 Manage Stakeholder
Engagement
13.4 Monitor Stakeholder Engagement
Manage Team
What is it?
Manage Team is the process of tracking team member performance,
providing feedback, resolving issues, and managing team changes to
optimize project performance.
Why?
The key benefit of this process is that it influences team behaviour,
manages conflict, and resolves issues.
Manage Team
Coincides with PMBOK 9.5
Manage Team
Coincides with PMBOK 9.5
Inputs Tools & Techniques Outputs
1. Project management plan
• Resource management plan
2. Project documents
• Issue Log
• Lessons learned register
• Project team assignments
• Team charter
3. Work performance reports
4. Team performance assessments
5. Enterprise environmental factors
6. Organizational process assets
1. Interpersonal and team
skills
• Conflict management
• Decision making
• Emotional intelligence
• Influencing
• Leadership
2. Project management
information system
1. Change requests
2. Project management plan updates
• Resource management plan
• Schedule baseline
• Cost baseline
3. Project documents updates
• Issue log
• Lessons learned register
• Project team assignments
4. Enterprise environmental
factors updates
Inputs, Tools & Techniques, Outputs
Coincides with PMBOK 9.5
9.5 Manage
Team
Project
Management
Plan
Enterprise/Orga
nization
• Resource
management plan
• Enterprise
environmental factors
• Organizational
process assets
Project Documents
Project Documents
Manage Team
4.6 Perform
Integrated
Change Control
Enterprise/Orga
nization
Project
Management
Plan
• Enterprise environmental factors update
• Change requests
9.4 Develop
Team
4.5 Monitor
and Control
Project Work
• Team Performance
Assessments
• Work Performance
Reports
• Issue Log
• Lessons Learned
Register
• Project Team
Assignments
• Team Charter
• Issue Log
• Lessons Learned Register
• Project Team Assignments
• Resource management plan
• Schedule baseline
• Cost baseline
Overview
Coincides with PMBOK 9.5
Manage Team
Managing the project team requires a variety of management and leadership skills
for fostering teamwork and integrating the efforts of team members to create high-
performance teams. Team management involves a combination of skills:
• Special emphasis on communication
• conflict management
• Negotiation
• leadership
Manage Team - Inputs
Coincides with PMBOK 9.5
Project Management Plan
Project management plan components include but are not limited to the resource
management plan. The resource management plan provides guidance on how project
team resources should be managed and eventually released.
Coincides with PMBOK 9.5
Project Documents
Project documents that can be considered as inputs for this process include:
• Issue Log
• Lessons learned register
• Project team assignments
• Team charter
Manage Team - Inputs
Coincides with PMBOK 9.5
Work Performance Report
Work performance reports are the physical or electronic representation of work
performance information intended to generate decisions, actions, or awareness.
Performance reports that can help with project team management include results
from:
• Schedule control
• Cost control
• Quality control
• Scope validation
Manage Team - Inputs
Coincides with PMBOK 9.5
Team Performance Assessments
The project management team makes ongoing formal or informal assessments of the
project team’s performance. By continually assessing the project team’s performance,
actions can be taken to resolve issues, modify communication, address conflict, and
improve team interaction.
Manage Team - Inputs
Enterprise Environmental Factors
The enterprise environmental factors that can influence the Manage
Team process include, human resource management policies.
Coincides with PMBOK 9.5
Manage Team - Inputs
Organisational Process Assets
The organizational process assets that can influence the Manage Team process
include:
• Certificates of appreciation
• Corporate apparel
• Other organizational perquisites
Coincides with PMBOK 9.5
Manage Team - Inputs
Manage Team - Tools & Techniques
Coincides with PMBOK 9.5
Interpersonal and Team Skills – Conflict Management
Successful conflict management results in greater productivity and positive working
relationships. There are five general techniques for resolving conflict:
• Withdraw/avoid - Retreating from an actual or potential conflict situation
• Smooth/accommodate - Emphasizing areas of agreement rather than areas of difference
• Compromise/reconcile - Searching for solutions that bring some degree of satisfaction to all
parties in order to temporarily or partially resolve the conflict
• Force/direct - Pushing one’s viewpoint at the expense of others
• Collaborate/problem solve - Incorporating multiple viewpoints and insights from differing
perspectives
Manage Team - Tools & Techniques
Coincides with PMBOK 9.5
Interpersonal and Team Skills – Decision Making
Decision making involves the ability to negotiate and influence the organization and
the project management team. Some guidelines for decision making include:
• Focus on goals to be served
• Follow a decision-making process
• Study the environmental factors
• Analyse available information
• Stimulate team creativity
• Account for risk.
Manage Team - Tools & Techniques
Coincides with PMBOK 9.5
Interpersonal and Team Skills – Influencing
Project managers often have little or no direct authority over team members in a
matrix environment, their ability to influence stakeholders on a timely basis is critical
to project success. Key influencing skills include:
• Ability to be persuasive
Clearly articulating points and positions
• High levels of active and effective listening skills
• Awareness of, and consideration for, the various perspectives in any situation
• Gathering relevant information to address issues and reach agreements while
maintaining mutual trust.
Manage Team - Tools & Techniques
Coincides with PMBOK 9.5
Interpersonal and Team Skills
Other Interpersonal and Team skills include:
• Leadership
• Emotional Intelligence
Manage Team - Tools & Techniques
Coincides with PMBOK 9.5
Project Management Information System
Project management information systems can include:
• Resource management software
• Scheduling software
Coincides with PMBOK 9.5
Change Requests
When change requests occur as a result of carrying out the Manage Team process or
when recommended corrective or preventive actions impact any of the components
of the project management plan or project documents, the project manager needs to
submit a change request. Change requests are processed for review and disposition
through the Perform Integrated Change Control process.
Manage Team – Outputs
Coincides with PMBOK 9.5
Project Management Plan Updates
Any change to the project management plan goes through the organization’s change
control process via a change request. Components of the project management plan
that may require a change request for the project management plan include:
• Resource management plan
• Schedule baseline
• Cost baseline
Manage Team – Outputs
Coincides with PMBOK 9.5
Project Document Updates
Project documents that may be updated as a result of carrying out this process
include:
• Lessons learned register
• Project schedule
• Project team assignments
• Resource calendars
• Team charter
Manage Team – Outputs
Coincides with PMBOK 9.5
Enterprise Environmental Factors
Enterprise environmental factors that are updated as a result of the Manage Team
process include:
• Input to organizational performance appraisals
• Personnel skill
Manage Team – Outputs

Mais conteúdo relacionado

Mais procurados

Mais procurados (20)

7.2 Estimate Cost
7.2 Estimate Cost7.2 Estimate Cost
7.2 Estimate Cost
 
Resource Management Knowledge Area
Resource Management Knowledge AreaResource Management Knowledge Area
Resource Management Knowledge Area
 
Project Scope Management Knowledge Area
Project Scope Management Knowledge AreaProject Scope Management Knowledge Area
Project Scope Management Knowledge Area
 
Procurement Management Knowledge Area
Procurement Management Knowledge AreaProcurement Management Knowledge Area
Procurement Management Knowledge Area
 
Quality Management Knowledge Area
Quality Management Knowledge AreaQuality Management Knowledge Area
Quality Management Knowledge Area
 
Project / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes GroupsProject / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes Groups
 
10.1 Plan Communication Management
10.1 Plan Communication Management10.1 Plan Communication Management
10.1 Plan Communication Management
 
Project Management Presentation material
Project Management Presentation material Project Management Presentation material
Project Management Presentation material
 
Project Management slide 2
Project Management slide 2Project Management slide 2
Project Management slide 2
 
7.0 Delivering in an Agile Environment
7.0 Delivering in an Agile Environment7.0 Delivering in an Agile Environment
7.0 Delivering in an Agile Environment
 
12.1 Plan Procurement Management
12.1 Plan Procurement Management12.1 Plan Procurement Management
12.1 Plan Procurement Management
 
Project Resource Management - PMBOK6
Project Resource Management - PMBOK6Project Resource Management - PMBOK6
Project Resource Management - PMBOK6
 
CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4
 
6.5 Develop Schedule
6.5 Develop Schedule6.5 Develop Schedule
6.5 Develop Schedule
 
Project Quality Management - PMBOK6
Project Quality Management - PMBOK6Project Quality Management - PMBOK6
Project Quality Management - PMBOK6
 
Project Scope Management
Project Scope ManagementProject Scope Management
Project Scope Management
 
7.4 Control Costs
7.4 Control Costs7.4 Control Costs
7.4 Control Costs
 
9.6 Control Resources
9.6 Control Resources9.6 Control Resources
9.6 Control Resources
 
13.3 Manage Stakeholder Engagement
13.3 Manage Stakeholder Engagement13.3 Manage Stakeholder Engagement
13.3 Manage Stakeholder Engagement
 
Practical project management 12 feb 2014
Practical project management 12 feb 2014Practical project management 12 feb 2014
Practical project management 12 feb 2014
 

Semelhante a 9.5 Manage Team

Semelhante a 9.5 Manage Team (20)

9.4 Develop Team
9.4 Develop Team9.4 Develop Team
9.4 Develop Team
 
9.0 Project Resource Management Overview
9.0 Project Resource Management Overview9.0 Project Resource Management Overview
9.0 Project Resource Management Overview
 
The Art Of Project Management
The Art Of Project ManagementThe Art Of Project Management
The Art Of Project Management
 
9.1 Plan Resource Management
9.1 Plan Resource Management9.1 Plan Resource Management
9.1 Plan Resource Management
 
7.1 Plan Cost Management
7.1 Plan Cost Management7.1 Plan Cost Management
7.1 Plan Cost Management
 
05 project scope management
05 project scope management05 project scope management
05 project scope management
 
PMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration ManagementPMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration Management
 
Fundamentals of Project Management
Fundamentals of Project Management Fundamentals of Project Management
Fundamentals of Project Management
 
05 project scope management
05 project scope management05 project scope management
05 project scope management
 
Fundamentalsof PM.pptx
Fundamentalsof PM.pptxFundamentalsof PM.pptx
Fundamentalsof PM.pptx
 
7.0 Project Cost Management Overview
7.0 Project Cost Management Overview7.0 Project Cost Management Overview
7.0 Project Cost Management Overview
 
11.6 Implement Risk Responses
11.6 Implement Risk Responses11.6 Implement Risk Responses
11.6 Implement Risk Responses
 
04 projectintegrationmanagement
04 projectintegrationmanagement04 projectintegrationmanagement
04 projectintegrationmanagement
 
PMP Prep Handout_Integration
PMP Prep Handout_IntegrationPMP Prep Handout_Integration
PMP Prep Handout_Integration
 
9.3 Acquire Resources
9.3 Acquire Resources9.3 Acquire Resources
9.3 Acquire Resources
 
11.7 Monitor Risks
11.7 Monitor Risks11.7 Monitor Risks
11.7 Monitor Risks
 
PMP as per PMBOK 6
PMP as per PMBOK 6PMP as per PMBOK 6
PMP as per PMBOK 6
 
Atppmp1ov1
Atppmp1ov1Atppmp1ov1
Atppmp1ov1
 
Undestand PMBok 5th, Section 4
Undestand PMBok 5th, Section 4Undestand PMBok 5th, Section 4
Undestand PMBok 5th, Section 4
 
10.3 Monitor Communication
10.3 Monitor Communication10.3 Monitor Communication
10.3 Monitor Communication
 

Mais de DavidMcLachlan1

Mais de DavidMcLachlan1 (17)

12.1 Procurement Contracts
12.1 Procurement Contracts12.1 Procurement Contracts
12.1 Procurement Contracts
 
12.2 Conduct Procurements
12.2 Conduct Procurements12.2 Conduct Procurements
12.2 Conduct Procurements
 
12.3 Control Procurements
12.3 Control Procurements12.3 Control Procurements
12.3 Control Procurements
 
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPIProject Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
 
Scenario - Project Management Processes | 2 of 2
Scenario - Project Management Processes | 2 of 2Scenario - Project Management Processes | 2 of 2
Scenario - Project Management Processes | 2 of 2
 
Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2
 
Scenario - The Project Management Environment
Scenario - The Project Management EnvironmentScenario - The Project Management Environment
Scenario - The Project Management Environment
 
Agile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile EnvironmentAgile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile Environment
 
Agile Scenarios - Core Practices
Agile Scenarios - Core PracticesAgile Scenarios - Core Practices
Agile Scenarios - Core Practices
 
Agile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave PlanningAgile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave Planning
 
6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean Frameworks6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean Frameworks
 
5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean Frameworks5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean Frameworks
 
4.0 The Agile Core Practices
4.0 The Agile Core Practices4.0 The Agile Core Practices
4.0 The Agile Core Practices
 
3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principles3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principles
 
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
 
7.3 Determine Budget
7.3 Determine Budget7.3 Determine Budget
7.3 Determine Budget
 
13.4 Monitor Stakeholder Engagement
13.4 Monitor Stakeholder Engagement13.4 Monitor Stakeholder Engagement
13.4 Monitor Stakeholder Engagement
 

Último

1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
QucHHunhnh
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
PECB
 

Último (20)

Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdf
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writing
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpin
 
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
 
General AI for Medical Educators April 2024
General AI for Medical Educators April 2024General AI for Medical Educators April 2024
General AI for Medical Educators April 2024
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room service
 

9.5 Manage Team

  • 2. Coincides with PMBOK 9.5 Process Group and Knowledge Area Mapping Knowledge Areas Initiating Planning Process Group Executing Process Group Monitoring and Controlling Process Group Closing Process Group 4. Project Integration Management 4.1 Develop Project Charter 4.2 Develop Project Management Plan 4.3 Direct and Manage Project Work 4.4 Manage Project Knowledge 4.5 Monitor and Control Project Work 4.6 Perform Integrated Change Control 4.7 Close Project or Phase 5. Project Scope Management 5.1 Plan Scope Management 5.2 Collect Requirements 5.3 Define Scope 5.4 Create WBS 5.5 Validate Scope 5.6 Control Scope 6. Project Schedule Management 6.1 Plan Schedule Management 6.2 Define Activities 6.3 Sequence Activities 6.4 Estimate Activity Durations 6.5 Develop Schedule 6.6 Control Schedule 7. Project Cost Management 7.1 Plan Cost Management 7.2 Estimate Costs 7.3 Determine Budget 7.4 Control Costs 8. Project Quality Management 8.1 Plan Quality Management 8.2 Manage Quality 8.3 Control Quality 9. Project Resource Management 9.1 Plan Resource Management 9.2 Estimate Activity Resources 9.3 Acquire Resources 9.4 Develop Team 9.5 Manage Team 9.6 Control Resources 10. Project Communications Management 10.1 Plan Communications Management 10.2 Manage Communications 10.3 Monitor Communications 11. Project Risk Management 11.1 Plan Risk Management 11.2 Identify Risks 11.3 Perform Qualitative Risk Analysis 11.4 Perform Quantitative Risk Analysis 11.5 Plan Risk Responses 11.6 Implement Risk Responses 11.7 Monitor Risks 12. Project Procurement Management 12.1 Plan Procurement Management 12.2 Conduct Procurements 12.3 Control Procurements 13. Project Stakeholder Management 13.1 Identify Stakeholders 13.2 Plan Stakeholder Engagement 13.3 Manage Stakeholder Engagement 13.4 Monitor Stakeholder Engagement Manage Team
  • 3. What is it? Manage Team is the process of tracking team member performance, providing feedback, resolving issues, and managing team changes to optimize project performance. Why? The key benefit of this process is that it influences team behaviour, manages conflict, and resolves issues. Manage Team Coincides with PMBOK 9.5
  • 4. Manage Team Coincides with PMBOK 9.5 Inputs Tools & Techniques Outputs 1. Project management plan • Resource management plan 2. Project documents • Issue Log • Lessons learned register • Project team assignments • Team charter 3. Work performance reports 4. Team performance assessments 5. Enterprise environmental factors 6. Organizational process assets 1. Interpersonal and team skills • Conflict management • Decision making • Emotional intelligence • Influencing • Leadership 2. Project management information system 1. Change requests 2. Project management plan updates • Resource management plan • Schedule baseline • Cost baseline 3. Project documents updates • Issue log • Lessons learned register • Project team assignments 4. Enterprise environmental factors updates Inputs, Tools & Techniques, Outputs
  • 5. Coincides with PMBOK 9.5 9.5 Manage Team Project Management Plan Enterprise/Orga nization • Resource management plan • Enterprise environmental factors • Organizational process assets Project Documents Project Documents Manage Team 4.6 Perform Integrated Change Control Enterprise/Orga nization Project Management Plan • Enterprise environmental factors update • Change requests 9.4 Develop Team 4.5 Monitor and Control Project Work • Team Performance Assessments • Work Performance Reports • Issue Log • Lessons Learned Register • Project Team Assignments • Team Charter • Issue Log • Lessons Learned Register • Project Team Assignments • Resource management plan • Schedule baseline • Cost baseline
  • 6. Overview Coincides with PMBOK 9.5 Manage Team Managing the project team requires a variety of management and leadership skills for fostering teamwork and integrating the efforts of team members to create high- performance teams. Team management involves a combination of skills: • Special emphasis on communication • conflict management • Negotiation • leadership
  • 7. Manage Team - Inputs Coincides with PMBOK 9.5 Project Management Plan Project management plan components include but are not limited to the resource management plan. The resource management plan provides guidance on how project team resources should be managed and eventually released.
  • 8. Coincides with PMBOK 9.5 Project Documents Project documents that can be considered as inputs for this process include: • Issue Log • Lessons learned register • Project team assignments • Team charter Manage Team - Inputs
  • 9. Coincides with PMBOK 9.5 Work Performance Report Work performance reports are the physical or electronic representation of work performance information intended to generate decisions, actions, or awareness. Performance reports that can help with project team management include results from: • Schedule control • Cost control • Quality control • Scope validation Manage Team - Inputs
  • 10. Coincides with PMBOK 9.5 Team Performance Assessments The project management team makes ongoing formal or informal assessments of the project team’s performance. By continually assessing the project team’s performance, actions can be taken to resolve issues, modify communication, address conflict, and improve team interaction. Manage Team - Inputs
  • 11. Enterprise Environmental Factors The enterprise environmental factors that can influence the Manage Team process include, human resource management policies. Coincides with PMBOK 9.5 Manage Team - Inputs
  • 12. Organisational Process Assets The organizational process assets that can influence the Manage Team process include: • Certificates of appreciation • Corporate apparel • Other organizational perquisites Coincides with PMBOK 9.5 Manage Team - Inputs
  • 13. Manage Team - Tools & Techniques Coincides with PMBOK 9.5 Interpersonal and Team Skills – Conflict Management Successful conflict management results in greater productivity and positive working relationships. There are five general techniques for resolving conflict: • Withdraw/avoid - Retreating from an actual or potential conflict situation • Smooth/accommodate - Emphasizing areas of agreement rather than areas of difference • Compromise/reconcile - Searching for solutions that bring some degree of satisfaction to all parties in order to temporarily or partially resolve the conflict • Force/direct - Pushing one’s viewpoint at the expense of others • Collaborate/problem solve - Incorporating multiple viewpoints and insights from differing perspectives
  • 14. Manage Team - Tools & Techniques Coincides with PMBOK 9.5 Interpersonal and Team Skills – Decision Making Decision making involves the ability to negotiate and influence the organization and the project management team. Some guidelines for decision making include: • Focus on goals to be served • Follow a decision-making process • Study the environmental factors • Analyse available information • Stimulate team creativity • Account for risk.
  • 15. Manage Team - Tools & Techniques Coincides with PMBOK 9.5 Interpersonal and Team Skills – Influencing Project managers often have little or no direct authority over team members in a matrix environment, their ability to influence stakeholders on a timely basis is critical to project success. Key influencing skills include: • Ability to be persuasive Clearly articulating points and positions • High levels of active and effective listening skills • Awareness of, and consideration for, the various perspectives in any situation • Gathering relevant information to address issues and reach agreements while maintaining mutual trust.
  • 16. Manage Team - Tools & Techniques Coincides with PMBOK 9.5 Interpersonal and Team Skills Other Interpersonal and Team skills include: • Leadership • Emotional Intelligence
  • 17. Manage Team - Tools & Techniques Coincides with PMBOK 9.5 Project Management Information System Project management information systems can include: • Resource management software • Scheduling software
  • 18. Coincides with PMBOK 9.5 Change Requests When change requests occur as a result of carrying out the Manage Team process or when recommended corrective or preventive actions impact any of the components of the project management plan or project documents, the project manager needs to submit a change request. Change requests are processed for review and disposition through the Perform Integrated Change Control process. Manage Team – Outputs
  • 19. Coincides with PMBOK 9.5 Project Management Plan Updates Any change to the project management plan goes through the organization’s change control process via a change request. Components of the project management plan that may require a change request for the project management plan include: • Resource management plan • Schedule baseline • Cost baseline Manage Team – Outputs
  • 20. Coincides with PMBOK 9.5 Project Document Updates Project documents that may be updated as a result of carrying out this process include: • Lessons learned register • Project schedule • Project team assignments • Resource calendars • Team charter Manage Team – Outputs
  • 21. Coincides with PMBOK 9.5 Enterprise Environmental Factors Enterprise environmental factors that are updated as a result of the Manage Team process include: • Input to organizational performance appraisals • Personnel skill Manage Team – Outputs

Notas do Editor

  1. This process is performed throughout the project.
  2. Project managers should provide challenging assignments to team members and provide recognition for high performance. The project manager needs to be sensitive to both the willingness and the ability of team members to perform their work and adjust their management and leadership styles accordingly.
  3. Issue log - Issues arise in the course of managing the project team. An issue log can be used to document and monitor who is responsible for resolving specific issues by a target date. Lessons learned register - Lessons learned earlier in the project can be applied to later phases in the project to improve the efficiency and effectiveness of managing the team. Project team assignments - Project team assignments identify the team member roles and responsibilities. Team charter -The team charter provides guidance for how the team will make decisions, conduct meetings, and resolve conflict.
  4. The information from performance reports and related forecasts assists in determining future team resource requirements, recognition and rewards, and updates to the resource management plan.
  5. Sources of conflict include scarce resources, scheduling priorities, and personal work styles. Team ground rules, group norms, and solid project management practices, like communication planning and role definition, reduce the amount of conflict. When managed properly, differences of opinion can lead to increased creativity and better decision making. Conflict should be addressed early and usually in private, using a direct, collaborative approach. If disruptive conflict continues, formal procedures may be used, including disciplinary actions. Different project managers may use different conflict resolution methods. Factors that influence conflict resolution methods include: Importance and intensity of the conflict Time pressure for resolving the conflict Relative power of the people involved in the conflict Importance of maintaining a good relationship Motivation to resolve conflict on a long-term or short-term basis
  6. Emotional intelligence is the ability to identify, assess, and manage the personal emotions of oneself and other people, as well as the collective emotions of groups of people. Leadership is the ability to lead a team and inspire them to do their jobs well. It encompasses a wide range of skills, abilities and actions.
  7. Resource Management Plan - The resource management plan is updated to reflect actual experience in managing the project team. Schedule baseline - Changes to the project schedule may be required to reflect the way the team is performing. Cost Baseline - Changes to the project cost baseline may be required to reflect the way the team is performing.
  8. Issue log - New issues raised as a result of this process are recorded in the issue log. Lessons learned register - The lessons learned register is updated with information on challenges encountered and how they could have been avoided as well as approaches that worked well for the managing the team. Project team assignments - If changes to the team are required, those changes are recorded in the project team assignments documentation.