SlideShare uma empresa Scribd logo
1 de 31
OPTIMIZATION OF WASTE HANDLING
IN SURFACE MINES
INTRODUCTION
 The prime objective of waste dump planning is to minimize the vertical
and horizontal distance between source and disposal area.
 Other factors like stability, availability of dumping area,
environmental hazards, types of equipments used etc. usually act
counter to above objective.
 Therefore, it is necessary to determine basic factors governing the
waste dump plan for an opencast mine
OBJECTIVE
(1) To study factors governing waste handling in
opencast mines.
(2) To optimize the waste handling capacity of an
opencast mine.
PARAMETERS AFFECTING WASTE HANDLING
CAPACITY OF A MINE
ECONOMIC PARAMETERS
1) Minimize the horizontal and vertical distance
of the source to disposal area ,
2) Deciding type of dumping ( in-pit or ex-pit)
3) cost of establishing a safe dump.
DESIGN PARAMETERS
 (1) Economic :-
I. Minimize vertical and horizontal distance,
II. Minimize the current haulage cost versus the
discounted future re-handling cost of in-pit dumps.
 (2) Non-economic:-
i. Stability,
ii. Political or surface rights,
iii. Environmental considerations,
iv. Physical configuration of dumps,
v. Method of placement,
vi. The planned development schedule.
GENERAL ENGINEERING
1) Swell factor of the run-of-mine,
2) Compaction ratio,
3) Angle of repose of the dump material,
4) Supportive surface strength of dump material,
5) Other factors
OTHER FACTORS
 Distribution at the time of a new dump,
 Notching of low levels of the dump,
 Removal of vegetation and other unconsolidated
material for obtaining a stable base,
 End dump from pit head for good draining pattern,
 Properly placing the drainage structures like culvert
pipes etc.
OPERATING CONSIDERATIONS
1) A slight positive gradient should be maintained at
the dump to ensure that the run off will drain away
from crest to natural ground.
2) Positive gradient is also good as the haul trucks
will have to power back to dump rather than roll
back.
3) In cases where the dump failure is serious, then
an alternative dump location will have to be used
until the situation is corrected.
4) For stabilizing dump failure we can put a layer of
lower dump on the toe of the failure
CASE STUDY
 Preparing a case study on the waste dumping
management of a mine having both in-pit and ex-pit
dumps.
 Finding sites for in-pit and ex- pit dumping in the
mine.
PROBLEM STATEMENT
Previously the mine had 2 box cuts, one in A block
and another one was in B block to reach the
requirement of 8Mtpa. Ex-Pit dump was placed in
North-West side of A block. With changes in mine
sequence (i.e. start of mine from B block with
5.0mtpa capacity) we need to find place of dumping
overburden.
INTRODUCTI
ON
 The combined area of the blocks is 7.81km2 .
 The topography over the coal bearing area is gently undulating ,
but rises steeply to the north from the block boundary.
 The coal seams are steeply dipping and the blocks are
intersected by several faults.
 There is total of over 20 named seams varying in thickness up
to 7 m, but generally 1 to 2 meters.
 Strip ratio is 5.16 bcm/t (bank cubic meters per tonnes)
 A and B blocks contain 2 blocks
 1) West block (A block)
 2) East block (pachmo)
INTRODUCTION OF KBP BLOCK
A- Block
B Block
B’s Nallah
A Block
B Block
Area - 865.63
Area -1065.89
STUDY OF TOPOGRAPHY OF KBP
BLOCK
B-Block
Rl-330
Rl-360
Rl-330
Rl-350
Rl-370
Rl-370
1. General Topography of Block is dipping down from West to east and North to South. RL
is varying fro n 330 min to 380 maximum.
2. There is no perennial nala within Pachmo block bout water may ingress from Northern
STUDY OF COAL BEARING AREA IN AND AROUND BLOCK
B-Block
Non Coal Bearing
area within block
Coal Bearing area
Coal Bearing area
of other mine
 EX-PIT DUMP
30M
30M 30M
30M30M
37.5˚
37.5˚
90
M28˚
• IN-PIT DUMP
30M
30M
30M
10M
37.5˚
40M
28˚
STUDY OF RULES AND
REGULATIONS
- EC condition
- Mining Plan
- By-Laws
Conceptual dump configuration
Terrace angle- 37.5
deg
Aver all dump Slopes-
28deg
PRODCUTION SCHEDULE FOR 5.0 MTPA COAL FROM
PACHMOY1 Y2 Y3 Y4 Y5 Y6 Y7 Y8 Y9 Y10 Y11 Y12 Y13 Total
Coal -mt 0.3 1.6 3.5 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 2.5 1.0 49.0
OB -
mbCuM 1.5 8.0 17.5 25.0 25.0 25.0 25.0 25.0 25.0 25.0 25.0 12.5 5.0 245.0
Terrace wise ROM Coal -MT
EBC 0.3 1.0 2.3 1.9 5.5
ET1 0.6 0.6 1.6 2.0 2.0 2.0 0.8 9.5
ET2 0.6 1.6 2.0 1.6 1.6 1.6 0.6 9.6
ET3 1.0 1.4 1.4 1.4 2.7 2.7 2.7 1.1 14.2
WT6 1.3 1.3 1.3 1.3 1.5 0.4 7.0
WT5 0.5 1.0 1.0 0.6 3.1
Total 0.3 1.6 3.5 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 2.5 1.0 49.0
Terrace wise OB-Mbcum
EBC 1.5 5.0 11.5 9.5 28.0
ET1 3.0 3.0 7.8 10.0 10.0 10.0 3.8 48.0
ET2 3.0 7.8 10.0 8.1 8.1 8.1 2.9 48.0
ET3 5.0 6.9 6.9 6.9 13.4 13.4 13.4 5.3 71.0
WT6 6.3 6.3 6.6 6.6 7.3 2.0 35.0
WT5 2.5 5.0 5.0 2.8 15.0
Total OB 1.5 8.0 17.5 25.0 25.0 25.0 25.0 25.0 25.0 25.0 25.0 12.5 4.8 244.0
•Total OB Generation will be 245 mbcum. ( 342 Loose MCuM )
•The overburden generated needs to be disposed either In-Pit or Ex-Pit
• Effort should be there to minimize ex-pit dumping and maximize in-pit
dumping
STUDY OF ULTIMATE PIT OF PACHMO
+10m
+190m
+280m
+330m
Non Coal Bearing Area=60
ha
Depth of Mine 290mtra
Width- NS 1.3 KM
Width EW- 2.4 KM
Rom reserves- 48 mt
+100m
B’s Nallah
Pit advance direction (East to West
A
B
Section Along - AB
B’s Nallah
EBC 5.5
ET1 9.5
ET2 9.6
ET3 14.2
WT6 7
WT5 3.05
Total 48.85
ROM reserves
STUDY OF TERRACE SEQUENCING
BCET
1
ET
2
WT-6
ET
3
WT-5
Pit advance direction (East to West
POSSIBLE LOCATIONS OF DUMPING WASTE
Dump-1: Dumping over coal bearing area located towards end of pit
Dump-2: Dumping over non-coal bearing area in North- East Part.
Dump-3: Dumping Ex-Pit along northern boundary.
Dump-4: In-Pit Dumping along with mining.
Dump-1
Dump-2
Dump-3
Dump-4
CRITERIA FOR IN-PIT DUMP
SEQUENCING
 1st In –Pit dumping can be done after the completion of Box-
Cut.
 Subsequent in-pit dumping is only possible after completion of
each terrace.
 There should be space of around 200mtrs from the toe of In
pit dump and bottom of pit
 Ultimate pit Geometry should be favorable for in-Pit Dumping.
45
deg
BC
T1T2
T3T4
200mtrs
DUMP SPACE AVAILABLE
Dump-1: 12.4 M CuM ( to be re-handled)
Dump-2: 16.8 M CuM
Dump-3: 202 MCuM + 12.4 MCuM
Dump-4: In- Pit Dump -1: 12.5 MCuM
In-Pit Dump-2 : 35.4 MCuM
In –Pit Dump-3 : 57 .6 MCuM
Dump-1
Dump-2
Dump-3
Dump-4
OVER BURDEN DUMPING
SEQUANCE
Y1 Y2 Y3 Y4 Y5 Y6 Y7 Y8 Y9 Y10 Y11 Y12 Y13 Total
Total Loose OB Mbcum 2.1 11.2 24.5 35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 17.5 6.7 342.0
AVAILABLE DUMP SPACE IN MBCUM
Dump-I 12.4
Dump-2 16.8 16.8
In-Pit BC dump 12.5 12.5
In-Pit T1 dump 35.4 35.4
In-Pit T1 dump 57.6 57.6
Total 29.1 12.5 35.4 57.6 122.2
Internal dumping-MCuM 2.1 11.2 15.8 12.5 35.0 35.0 27.5 139.1
External Dumping -
MCuM 8.7 35.0 22.5 35.0 35.0 35.0 7.5 17.5 6.7 202.8
PIT POSITION AT END OF BOX CUT ( Year -4
Dump-1 Completed
12.4 mCuM
Dump-2
Completed
16.2 mCuM
End of Box Cut
T-1, T2 & T3 in
operation
Ex-Pit Dump in
operation
44 mCuM
IN PIT DUMP-1 AFTER COMPLETION OF BOX
CUT
( Year -5)
T-1, T2 & T3 in
operation
Ex-Pit Dump in
operation
In Pit Dump-1
12.5 MCum
IN PIT DUMP-2 AFTER COMPLETION OF
TERRACE T-1 (Year -9)
T-2, T3 & WT6
in operation
Ex-Pit Dump in
operation
In Pit Dump-2
35.4 MCum
Dump-1 has
been re-handled
IN PIT DUMP-3 AFTER COMPLETION OF
TERRACE
T-2 (Year -10)
T-3, WT-6 & WT5
in operation
Ex-Pit Dump in
operation
In Pit Dump-3
57.57 MCum
ULTIMATE VOID AFTER -13 YEARS ( END OF LIFE OF
MINE)
T-3, WT-6 & WT5
in operation
Ex-Pit Dump in
operation
( 296 HA)
212 MCuM
In Pit Dump-1 ,2
,3
105 MCum
Total Void – 173
MCuM
CONCLUSIONS
1. Ex-Pit dumping space is essential for 5.0mtpa within 2
& ½ year.
2. Ex-Pit dump space should be acquired within 2 &1/2
year for sustaining production level.
2. The area required for ex-pit dumping space is 296
hector.
3. Due to faster rate of production big ultimate void is
formed.
2. However, ultimate void can be used if we continue
mining in KB Block.

Mais conteúdo relacionado

Mais procurados

Differnt technologies in oc mines
Differnt technologies in oc minesDiffernt technologies in oc mines
Differnt technologies in oc minesSATYANARAYANA I
 
Building a mega-power plant on liquefiable sands
Building a mega-power plant on liquefiable sandsBuilding a mega-power plant on liquefiable sands
Building a mega-power plant on liquefiable sandsInfocengrs63
 
Terra X Minerals Presentation March 2016
Terra X Minerals Presentation March 2016Terra X Minerals Presentation March 2016
Terra X Minerals Presentation March 2016Company Spotlight
 
Crescent Power Point
Crescent Power PointCrescent Power Point
Crescent Power PointKurt Hoffman
 
Coal Sccl
Coal ScclCoal Sccl
Coal ScclVR M
 
Concept of oc mine planning & design(final)
Concept  of oc mine planning & design(final)Concept  of oc mine planning & design(final)
Concept of oc mine planning & design(final)sou_suk_sou
 
HCK AJM Paper May 03 (Double Space)
HCK AJM Paper May 03 (Double Space)HCK AJM Paper May 03 (Double Space)
HCK AJM Paper May 03 (Double Space)John Coughlan
 
Portion of Gastar Investor Presentation for August 2015 Focused on Marcellus/...
Portion of Gastar Investor Presentation for August 2015 Focused on Marcellus/...Portion of Gastar Investor Presentation for August 2015 Focused on Marcellus/...
Portion of Gastar Investor Presentation for August 2015 Focused on Marcellus/...Marcellus Drilling News
 
New Pacific Metals Corporate Presentation
New Pacific Metals Corporate PresentationNew Pacific Metals Corporate Presentation
New Pacific Metals Corporate Presentationnewpacific
 
Presentation - July 4, 2011
Presentation - July 4, 2011Presentation - July 4, 2011
Presentation - July 4, 2011newpacificmetals
 
Blind Backfilling of Goaf and Coal Extraction below Built-up Areas / Surface ...
Blind Backfilling of Goaf and Coal Extraction below Built-up Areas / Surface ...Blind Backfilling of Goaf and Coal Extraction below Built-up Areas / Surface ...
Blind Backfilling of Goaf and Coal Extraction below Built-up Areas / Surface ...AMIT SAHU
 
Structural and stability assessment for ex-pit dump toe (final)
Structural and stability assessment for ex-pit dump toe (final)Structural and stability assessment for ex-pit dump toe (final)
Structural and stability assessment for ex-pit dump toe (final)John Latilla
 
Kombat Copper Corporate Presentation
Kombat Copper Corporate PresentationKombat Copper Corporate Presentation
Kombat Copper Corporate Presentationkombatcopper
 
TriMetals Mining Inc. april-2017-corporate-presentation
TriMetals Mining Inc. april-2017-corporate-presentationTriMetals Mining Inc. april-2017-corporate-presentation
TriMetals Mining Inc. april-2017-corporate-presentationChris Helweg
 

Mais procurados (17)

Differnt technologies in oc mines
Differnt technologies in oc minesDiffernt technologies in oc mines
Differnt technologies in oc mines
 
Building a mega-power plant on liquefiable sands
Building a mega-power plant on liquefiable sandsBuilding a mega-power plant on liquefiable sands
Building a mega-power plant on liquefiable sands
 
Utah
UtahUtah
Utah
 
Tipong report
Tipong report Tipong report
Tipong report
 
Terra X Minerals Presentation March 2016
Terra X Minerals Presentation March 2016Terra X Minerals Presentation March 2016
Terra X Minerals Presentation March 2016
 
Crescent Power Point
Crescent Power PointCrescent Power Point
Crescent Power Point
 
Coal Sccl
Coal ScclCoal Sccl
Coal Sccl
 
Concept of oc mine planning & design(final)
Concept  of oc mine planning & design(final)Concept  of oc mine planning & design(final)
Concept of oc mine planning & design(final)
 
HCK AJM Paper May 03 (Double Space)
HCK AJM Paper May 03 (Double Space)HCK AJM Paper May 03 (Double Space)
HCK AJM Paper May 03 (Double Space)
 
Portion of Gastar Investor Presentation for August 2015 Focused on Marcellus/...
Portion of Gastar Investor Presentation for August 2015 Focused on Marcellus/...Portion of Gastar Investor Presentation for August 2015 Focused on Marcellus/...
Portion of Gastar Investor Presentation for August 2015 Focused on Marcellus/...
 
New Pacific Metals Corporate Presentation
New Pacific Metals Corporate PresentationNew Pacific Metals Corporate Presentation
New Pacific Metals Corporate Presentation
 
Presentation - July 4, 2011
Presentation - July 4, 2011Presentation - July 4, 2011
Presentation - July 4, 2011
 
Blind Backfilling of Goaf and Coal Extraction below Built-up Areas / Surface ...
Blind Backfilling of Goaf and Coal Extraction below Built-up Areas / Surface ...Blind Backfilling of Goaf and Coal Extraction below Built-up Areas / Surface ...
Blind Backfilling of Goaf and Coal Extraction below Built-up Areas / Surface ...
 
Structural and stability assessment for ex-pit dump toe (final)
Structural and stability assessment for ex-pit dump toe (final)Structural and stability assessment for ex-pit dump toe (final)
Structural and stability assessment for ex-pit dump toe (final)
 
Kombat Copper Corporate Presentation
Kombat Copper Corporate PresentationKombat Copper Corporate Presentation
Kombat Copper Corporate Presentation
 
TriMetals Mining Inc. april-2017-corporate-presentation
TriMetals Mining Inc. april-2017-corporate-presentationTriMetals Mining Inc. april-2017-corporate-presentation
TriMetals Mining Inc. april-2017-corporate-presentation
 
Barapukuria
Barapukuria Barapukuria
Barapukuria
 

Semelhante a Optimization of waste handling in surface mines

Conversion of Underground Mine to Open Cast Mine
Conversion of Underground Mine to Open Cast MineConversion of Underground Mine to Open Cast Mine
Conversion of Underground Mine to Open Cast MineAbdul Mujeeb
 
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...Egyptian Engineers Association
 
Bandalup Magnesite Overview Public_jun 2015
Bandalup Magnesite Overview Public_jun 2015Bandalup Magnesite Overview Public_jun 2015
Bandalup Magnesite Overview Public_jun 2015Terry Butler-Blaxell
 
Methodology including all enclosures(modified 18-5-10)
Methodology including all enclosures(modified 18-5-10)Methodology including all enclosures(modified 18-5-10)
Methodology including all enclosures(modified 18-5-10)Gautam Sharma
 
Pillar design - a case study
Pillar design - a case studyPillar design - a case study
Pillar design - a case studyTIKESHWAR MAHTO
 
Extending Open Cast Mine to Underground Mine Planning
Extending Open Cast Mine to Underground Mine PlanningExtending Open Cast Mine to Underground Mine Planning
Extending Open Cast Mine to Underground Mine PlanningJasmeet Singh Saluja
 
African Diamonds corporate presentation 2006
African Diamonds corporate presentation 2006African Diamonds corporate presentation 2006
African Diamonds corporate presentation 2006James AH Campbell
 
2010 Blast Hole Slotting Conference Paper_Aug2010
2010 Blast Hole Slotting Conference Paper_Aug20102010 Blast Hole Slotting Conference Paper_Aug2010
2010 Blast Hole Slotting Conference Paper_Aug2010Matt Stockwell
 
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptxPPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptxAGNIVORAY1
 
Basics of openpit mining
Basics of openpit miningBasics of openpit mining
Basics of openpit miningSATYANARAYANA I
 
Turga PSP_Lower Dam.pptx
Turga PSP_Lower Dam.pptxTurga PSP_Lower Dam.pptx
Turga PSP_Lower Dam.pptxssuserde6364
 
Blasting and rock fragmentation
Blasting and rock fragmentationBlasting and rock fragmentation
Blasting and rock fragmentationAlex Demidov
 
Method of working of continuous miner in underground coal
Method of working of     continuous miner in underground coalMethod of working of     continuous miner in underground coal
Method of working of continuous miner in underground coalSafdar Ali
 
Kearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge ProjectKearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge ProjectJill Reeves
 

Semelhante a Optimization of waste handling in surface mines (20)

Conversion of Underground Mine to Open Cast Mine
Conversion of Underground Mine to Open Cast MineConversion of Underground Mine to Open Cast Mine
Conversion of Underground Mine to Open Cast Mine
 
Group 3 Presentation
Group 3 PresentationGroup 3 Presentation
Group 3 Presentation
 
Pillar design
Pillar designPillar design
Pillar design
 
Pillar design
Pillar designPillar design
Pillar design
 
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
 
Bandalup Magnesite Overview Public_jun 2015
Bandalup Magnesite Overview Public_jun 2015Bandalup Magnesite Overview Public_jun 2015
Bandalup Magnesite Overview Public_jun 2015
 
Methodology including all enclosures(modified 18-5-10)
Methodology including all enclosures(modified 18-5-10)Methodology including all enclosures(modified 18-5-10)
Methodology including all enclosures(modified 18-5-10)
 
Pillar design
Pillar designPillar design
Pillar design
 
Pillar design - a case study
Pillar design - a case studyPillar design - a case study
Pillar design - a case study
 
Extending Open Cast Mine to Underground Mine Planning
Extending Open Cast Mine to Underground Mine PlanningExtending Open Cast Mine to Underground Mine Planning
Extending Open Cast Mine to Underground Mine Planning
 
African Diamonds corporate presentation 2006
African Diamonds corporate presentation 2006African Diamonds corporate presentation 2006
African Diamonds corporate presentation 2006
 
2010 Blast Hole Slotting Conference Paper_Aug2010
2010 Blast Hole Slotting Conference Paper_Aug20102010 Blast Hole Slotting Conference Paper_Aug2010
2010 Blast Hole Slotting Conference Paper_Aug2010
 
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptxPPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
 
Basics of openpit mining
Basics of openpit miningBasics of openpit mining
Basics of openpit mining
 
WCL_March
WCL_MarchWCL_March
WCL_March
 
Internship report
Internship reportInternship report
Internship report
 
Turga PSP_Lower Dam.pptx
Turga PSP_Lower Dam.pptxTurga PSP_Lower Dam.pptx
Turga PSP_Lower Dam.pptx
 
Blasting and rock fragmentation
Blasting and rock fragmentationBlasting and rock fragmentation
Blasting and rock fragmentation
 
Method of working of continuous miner in underground coal
Method of working of     continuous miner in underground coalMethod of working of     continuous miner in underground coal
Method of working of continuous miner in underground coal
 
Kearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge ProjectKearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge Project
 

Mais de Safdar Ali

Safety in mines
Safety in minesSafety in mines
Safety in minesSafdar Ali
 
Explosives and accesories
Explosives and accesoriesExplosives and accesories
Explosives and accesoriesSafdar Ali
 
Role of management information systems in a mine.
Role of management information systems in a mine.Role of management information systems in a mine.
Role of management information systems in a mine.Safdar Ali
 
Pre requisites of marine operations
Pre requisites of marine operationsPre requisites of marine operations
Pre requisites of marine operationsSafdar Ali
 
Nuclear devices for mining
Nuclear devices for miningNuclear devices for mining
Nuclear devices for miningSafdar Ali
 
Mining of manganese nodules from sea floor
Mining of manganese nodules from sea floorMining of manganese nodules from sea floor
Mining of manganese nodules from sea floorSafdar Ali
 
Mine water risk in open pit slope stability
Mine water risk in open pit slope stabilityMine water risk in open pit slope stability
Mine water risk in open pit slope stabilitySafdar Ali
 
Innovations and trend in metal mining & tunnellng
Innovations and trend in metal mining & tunnellngInnovations and trend in metal mining & tunnellng
Innovations and trend in metal mining & tunnellngSafdar Ali
 
Lighting terminlologyand their units
Lighting terminlologyand their unitsLighting terminlologyand their units
Lighting terminlologyand their unitsSafdar Ali
 
Evaluation of slope stability for waste rock dumps in a mine
Evaluation of slope stability for waste rock dumps in a mineEvaluation of slope stability for waste rock dumps in a mine
Evaluation of slope stability for waste rock dumps in a mineSafdar Ali
 
Final grouting freezing
Final grouting freezingFinal grouting freezing
Final grouting freezingSafdar Ali
 
Digitization and 3d modelling of a mine plan
Digitization and 3d modelling of a mine planDigitization and 3d modelling of a mine plan
Digitization and 3d modelling of a mine planSafdar Ali
 
Variety of mine plans and sections & second schedule
Variety of mine plans and sections & second scheduleVariety of mine plans and sections & second schedule
Variety of mine plans and sections & second scheduleSafdar Ali
 
Statutory provisions for the preaparation of mine plans and sections
Statutory provisions for the preaparation of mine plans and sectionsStatutory provisions for the preaparation of mine plans and sections
Statutory provisions for the preaparation of mine plans and sectionsSafdar Ali
 
Gps & its applications in opencast mine surveying
Gps & its applications in opencast mine surveyingGps & its applications in opencast mine surveying
Gps & its applications in opencast mine surveyingSafdar Ali
 
Laser and its mining applications
Laser and its mining applicationsLaser and its mining applications
Laser and its mining applicationsSafdar Ali
 
Gyrotheodolite
GyrotheodoliteGyrotheodolite
GyrotheodoliteSafdar Ali
 

Mais de Safdar Ali (20)

Safety in mines
Safety in minesSafety in mines
Safety in mines
 
Tunneling
TunnelingTunneling
Tunneling
 
Explosives and accesories
Explosives and accesoriesExplosives and accesories
Explosives and accesories
 
Role of management information systems in a mine.
Role of management information systems in a mine.Role of management information systems in a mine.
Role of management information systems in a mine.
 
Basting
BastingBasting
Basting
 
Pre requisites of marine operations
Pre requisites of marine operationsPre requisites of marine operations
Pre requisites of marine operations
 
Nuclear devices for mining
Nuclear devices for miningNuclear devices for mining
Nuclear devices for mining
 
Mining of manganese nodules from sea floor
Mining of manganese nodules from sea floorMining of manganese nodules from sea floor
Mining of manganese nodules from sea floor
 
Mine water risk in open pit slope stability
Mine water risk in open pit slope stabilityMine water risk in open pit slope stability
Mine water risk in open pit slope stability
 
Innovations and trend in metal mining & tunnellng
Innovations and trend in metal mining & tunnellngInnovations and trend in metal mining & tunnellng
Innovations and trend in metal mining & tunnellng
 
Lighting terminlologyand their units
Lighting terminlologyand their unitsLighting terminlologyand their units
Lighting terminlologyand their units
 
Evaluation of slope stability for waste rock dumps in a mine
Evaluation of slope stability for waste rock dumps in a mineEvaluation of slope stability for waste rock dumps in a mine
Evaluation of slope stability for waste rock dumps in a mine
 
Final grouting freezing
Final grouting freezingFinal grouting freezing
Final grouting freezing
 
Digitization and 3d modelling of a mine plan
Digitization and 3d modelling of a mine planDigitization and 3d modelling of a mine plan
Digitization and 3d modelling of a mine plan
 
Variety of mine plans and sections & second schedule
Variety of mine plans and sections & second scheduleVariety of mine plans and sections & second schedule
Variety of mine plans and sections & second schedule
 
Statutory provisions for the preaparation of mine plans and sections
Statutory provisions for the preaparation of mine plans and sectionsStatutory provisions for the preaparation of mine plans and sections
Statutory provisions for the preaparation of mine plans and sections
 
Gps & its applications in opencast mine surveying
Gps & its applications in opencast mine surveyingGps & its applications in opencast mine surveying
Gps & its applications in opencast mine surveying
 
Laser and its mining applications
Laser and its mining applicationsLaser and its mining applications
Laser and its mining applications
 
Gyrotheodolite
GyrotheodoliteGyrotheodolite
Gyrotheodolite
 
Gps2
Gps2Gps2
Gps2
 

Último

Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...Sapna Thakur
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDThiyagu K
 
9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room servicediscovermytutordmt
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Disha Kariya
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpinRaunakKeshri1
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104misteraugie
 
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...fonyou31
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
General AI for Medical Educators April 2024
General AI for Medical Educators April 2024General AI for Medical Educators April 2024
General AI for Medical Educators April 2024Janet Corral
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 

Último (20)

Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 
9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room service
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpin
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
General AI for Medical Educators April 2024
General AI for Medical Educators April 2024General AI for Medical Educators April 2024
General AI for Medical Educators April 2024
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 

Optimization of waste handling in surface mines

  • 1.
  • 2. OPTIMIZATION OF WASTE HANDLING IN SURFACE MINES
  • 3. INTRODUCTION  The prime objective of waste dump planning is to minimize the vertical and horizontal distance between source and disposal area.  Other factors like stability, availability of dumping area, environmental hazards, types of equipments used etc. usually act counter to above objective.  Therefore, it is necessary to determine basic factors governing the waste dump plan for an opencast mine
  • 4. OBJECTIVE (1) To study factors governing waste handling in opencast mines. (2) To optimize the waste handling capacity of an opencast mine.
  • 5. PARAMETERS AFFECTING WASTE HANDLING CAPACITY OF A MINE
  • 6. ECONOMIC PARAMETERS 1) Minimize the horizontal and vertical distance of the source to disposal area , 2) Deciding type of dumping ( in-pit or ex-pit) 3) cost of establishing a safe dump.
  • 7. DESIGN PARAMETERS  (1) Economic :- I. Minimize vertical and horizontal distance, II. Minimize the current haulage cost versus the discounted future re-handling cost of in-pit dumps.
  • 8.  (2) Non-economic:- i. Stability, ii. Political or surface rights, iii. Environmental considerations, iv. Physical configuration of dumps, v. Method of placement, vi. The planned development schedule.
  • 9. GENERAL ENGINEERING 1) Swell factor of the run-of-mine, 2) Compaction ratio, 3) Angle of repose of the dump material, 4) Supportive surface strength of dump material, 5) Other factors
  • 10. OTHER FACTORS  Distribution at the time of a new dump,  Notching of low levels of the dump,  Removal of vegetation and other unconsolidated material for obtaining a stable base,  End dump from pit head for good draining pattern,  Properly placing the drainage structures like culvert pipes etc.
  • 11. OPERATING CONSIDERATIONS 1) A slight positive gradient should be maintained at the dump to ensure that the run off will drain away from crest to natural ground. 2) Positive gradient is also good as the haul trucks will have to power back to dump rather than roll back. 3) In cases where the dump failure is serious, then an alternative dump location will have to be used until the situation is corrected. 4) For stabilizing dump failure we can put a layer of lower dump on the toe of the failure
  • 12. CASE STUDY  Preparing a case study on the waste dumping management of a mine having both in-pit and ex-pit dumps.  Finding sites for in-pit and ex- pit dumping in the mine.
  • 13. PROBLEM STATEMENT Previously the mine had 2 box cuts, one in A block and another one was in B block to reach the requirement of 8Mtpa. Ex-Pit dump was placed in North-West side of A block. With changes in mine sequence (i.e. start of mine from B block with 5.0mtpa capacity) we need to find place of dumping overburden.
  • 14. INTRODUCTI ON  The combined area of the blocks is 7.81km2 .  The topography over the coal bearing area is gently undulating , but rises steeply to the north from the block boundary.  The coal seams are steeply dipping and the blocks are intersected by several faults.  There is total of over 20 named seams varying in thickness up to 7 m, but generally 1 to 2 meters.  Strip ratio is 5.16 bcm/t (bank cubic meters per tonnes)  A and B blocks contain 2 blocks  1) West block (A block)  2) East block (pachmo)
  • 15. INTRODUCTION OF KBP BLOCK A- Block B Block B’s Nallah A Block B Block Area - 865.63 Area -1065.89
  • 16. STUDY OF TOPOGRAPHY OF KBP BLOCK B-Block Rl-330 Rl-360 Rl-330 Rl-350 Rl-370 Rl-370 1. General Topography of Block is dipping down from West to east and North to South. RL is varying fro n 330 min to 380 maximum. 2. There is no perennial nala within Pachmo block bout water may ingress from Northern
  • 17. STUDY OF COAL BEARING AREA IN AND AROUND BLOCK B-Block Non Coal Bearing area within block Coal Bearing area Coal Bearing area of other mine
  • 18.  EX-PIT DUMP 30M 30M 30M 30M30M 37.5˚ 37.5˚ 90 M28˚ • IN-PIT DUMP 30M 30M 30M 10M 37.5˚ 40M 28˚ STUDY OF RULES AND REGULATIONS - EC condition - Mining Plan - By-Laws Conceptual dump configuration Terrace angle- 37.5 deg Aver all dump Slopes- 28deg
  • 19. PRODCUTION SCHEDULE FOR 5.0 MTPA COAL FROM PACHMOY1 Y2 Y3 Y4 Y5 Y6 Y7 Y8 Y9 Y10 Y11 Y12 Y13 Total Coal -mt 0.3 1.6 3.5 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 2.5 1.0 49.0 OB - mbCuM 1.5 8.0 17.5 25.0 25.0 25.0 25.0 25.0 25.0 25.0 25.0 12.5 5.0 245.0 Terrace wise ROM Coal -MT EBC 0.3 1.0 2.3 1.9 5.5 ET1 0.6 0.6 1.6 2.0 2.0 2.0 0.8 9.5 ET2 0.6 1.6 2.0 1.6 1.6 1.6 0.6 9.6 ET3 1.0 1.4 1.4 1.4 2.7 2.7 2.7 1.1 14.2 WT6 1.3 1.3 1.3 1.3 1.5 0.4 7.0 WT5 0.5 1.0 1.0 0.6 3.1 Total 0.3 1.6 3.5 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 2.5 1.0 49.0 Terrace wise OB-Mbcum EBC 1.5 5.0 11.5 9.5 28.0 ET1 3.0 3.0 7.8 10.0 10.0 10.0 3.8 48.0 ET2 3.0 7.8 10.0 8.1 8.1 8.1 2.9 48.0 ET3 5.0 6.9 6.9 6.9 13.4 13.4 13.4 5.3 71.0 WT6 6.3 6.3 6.6 6.6 7.3 2.0 35.0 WT5 2.5 5.0 5.0 2.8 15.0 Total OB 1.5 8.0 17.5 25.0 25.0 25.0 25.0 25.0 25.0 25.0 25.0 12.5 4.8 244.0 •Total OB Generation will be 245 mbcum. ( 342 Loose MCuM ) •The overburden generated needs to be disposed either In-Pit or Ex-Pit • Effort should be there to minimize ex-pit dumping and maximize in-pit dumping
  • 20. STUDY OF ULTIMATE PIT OF PACHMO +10m +190m +280m +330m Non Coal Bearing Area=60 ha Depth of Mine 290mtra Width- NS 1.3 KM Width EW- 2.4 KM Rom reserves- 48 mt +100m B’s Nallah Pit advance direction (East to West
  • 21. A B Section Along - AB B’s Nallah EBC 5.5 ET1 9.5 ET2 9.6 ET3 14.2 WT6 7 WT5 3.05 Total 48.85 ROM reserves STUDY OF TERRACE SEQUENCING BCET 1 ET 2 WT-6 ET 3 WT-5 Pit advance direction (East to West
  • 22. POSSIBLE LOCATIONS OF DUMPING WASTE Dump-1: Dumping over coal bearing area located towards end of pit Dump-2: Dumping over non-coal bearing area in North- East Part. Dump-3: Dumping Ex-Pit along northern boundary. Dump-4: In-Pit Dumping along with mining. Dump-1 Dump-2 Dump-3 Dump-4
  • 23. CRITERIA FOR IN-PIT DUMP SEQUENCING  1st In –Pit dumping can be done after the completion of Box- Cut.  Subsequent in-pit dumping is only possible after completion of each terrace.  There should be space of around 200mtrs from the toe of In pit dump and bottom of pit  Ultimate pit Geometry should be favorable for in-Pit Dumping. 45 deg BC T1T2 T3T4 200mtrs
  • 24. DUMP SPACE AVAILABLE Dump-1: 12.4 M CuM ( to be re-handled) Dump-2: 16.8 M CuM Dump-3: 202 MCuM + 12.4 MCuM Dump-4: In- Pit Dump -1: 12.5 MCuM In-Pit Dump-2 : 35.4 MCuM In –Pit Dump-3 : 57 .6 MCuM Dump-1 Dump-2 Dump-3 Dump-4
  • 25. OVER BURDEN DUMPING SEQUANCE Y1 Y2 Y3 Y4 Y5 Y6 Y7 Y8 Y9 Y10 Y11 Y12 Y13 Total Total Loose OB Mbcum 2.1 11.2 24.5 35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 17.5 6.7 342.0 AVAILABLE DUMP SPACE IN MBCUM Dump-I 12.4 Dump-2 16.8 16.8 In-Pit BC dump 12.5 12.5 In-Pit T1 dump 35.4 35.4 In-Pit T1 dump 57.6 57.6 Total 29.1 12.5 35.4 57.6 122.2 Internal dumping-MCuM 2.1 11.2 15.8 12.5 35.0 35.0 27.5 139.1 External Dumping - MCuM 8.7 35.0 22.5 35.0 35.0 35.0 7.5 17.5 6.7 202.8
  • 26. PIT POSITION AT END OF BOX CUT ( Year -4 Dump-1 Completed 12.4 mCuM Dump-2 Completed 16.2 mCuM End of Box Cut T-1, T2 & T3 in operation Ex-Pit Dump in operation 44 mCuM
  • 27. IN PIT DUMP-1 AFTER COMPLETION OF BOX CUT ( Year -5) T-1, T2 & T3 in operation Ex-Pit Dump in operation In Pit Dump-1 12.5 MCum
  • 28. IN PIT DUMP-2 AFTER COMPLETION OF TERRACE T-1 (Year -9) T-2, T3 & WT6 in operation Ex-Pit Dump in operation In Pit Dump-2 35.4 MCum Dump-1 has been re-handled
  • 29. IN PIT DUMP-3 AFTER COMPLETION OF TERRACE T-2 (Year -10) T-3, WT-6 & WT5 in operation Ex-Pit Dump in operation In Pit Dump-3 57.57 MCum
  • 30. ULTIMATE VOID AFTER -13 YEARS ( END OF LIFE OF MINE) T-3, WT-6 & WT5 in operation Ex-Pit Dump in operation ( 296 HA) 212 MCuM In Pit Dump-1 ,2 ,3 105 MCum Total Void – 173 MCuM
  • 31. CONCLUSIONS 1. Ex-Pit dumping space is essential for 5.0mtpa within 2 & ½ year. 2. Ex-Pit dump space should be acquired within 2 &1/2 year for sustaining production level. 2. The area required for ex-pit dumping space is 296 hector. 3. Due to faster rate of production big ultimate void is formed. 2. However, ultimate void can be used if we continue mining in KB Block.