Canal Regulation
&
Cross Drainage Works
Unit-V
BTCI09007
Syllabus
• Canal Regulation Works
• Canal Fall- Necessity and Location- Types of
Falls- Cross Regulator and Distributory Head
Regulator- Their Functions, Silt Control
Devices, Canal Escapes- Types of Escapes.
• Cross Drainage Works: Types- selection of
suitable type of CD works- aqueduct and
Siphon aqueduct
What is Canal Fall?
• Whenever the available natural ground slope
is steep than the designed bed slope of the
channel, the difference is adjusted by
constructing vertical ‘falls’ or ‘drops’ in the canal
bed at suitable intervals, as shown in figure
below. Such a drop in a natural canal bed will not
be stable and, therefore, in order to retain this
drop, a masonry structure is constructed. Such a
structure is called a Canal Fall or a Canal drop.
Canal Fall
Canal Fall
Irrigation canals are designed for a prescribed bed slope
so that velocity becomes non silting or non scouring.
But if the ground topography is such that in order to
maintain the canal designed slope, indefinite filling
from falling ground level is to be made. This indefinite
filling is avoided by constructing a hydraulic structure
in the place of sudden bed level. This hydraulic
structure is called canal fall or drop. Beyond the canal
fall, canal again maintains its designed slope.
Canal Fall
• Thus, a canal fall or drop is an irrigation structure
constructed across a canal to lower down its bed level
to maintain the designed slope when there is a change
of ground level to maintain the designed slope when
there is change of ground level. This falling water at
the fall has some surplus energy. The fall is
constructed in such a way that it can destroy this
surplus energy.
Necessity of Canal Falls
• When the slope of the ground suddenly changes
to steeper slope, the permissible bed slope can
not be maintained. It requires excessive earthwork
in filling to maintain the slope. In such a case falls
are provided to avoid excessive earth work in filling
Necessity of Canal Falls
Necessity of Canal Falls
• When the slope of the ground is more or
less uniform and the slope is greater than the
permissible bed slope of canal.
Necessity of Canal Falls
• In cross-drainage works, when the difference
between bed level of canal and that of
drainage is small or when the F.S.L of the
canal is above the bed level of drainage
then the canal fall is necessary to carry the
canal water below the stream or drainage.
Necessity of Canal Falls
Types of Canal Fall
• Depending on the ground level conditions and shape of
the fall the various types of fall are:
Ogee Fall
• The ogee fall was constructed by Sir Proby Cautley on
the Ganga Canal. This type of fall has gradual convex
and concave surfaces i.e. in the ogee form. The gradual
convex and concave surface is provided with an aim to
provide smooth transition and to reduce disturbance
and impact. A hydraulic jump is formed which
dissipates a part of kinetic energy. Upstream and
downstream of the fall is provided by Stone Pitching.
Ogee Fall
Types of Canal Fall
Stepped Fall
• It consists of a series of vertical drops in the form of
steps. This steps is suitable in places where sloping
ground is very long and require a long glacis to connect
the higher bed level u/s with lower bed level d/s. it is
practically a modification of rapid fall. The sloping
glacis is divided into a number drops to bring down the
canal bed step by step to protect the canal bed and sides
from damage by erosion. Brick walls are provided at
each drop. The bed of the canal within the fall is
protected by rubble masonry with surface finishing by
rich cement mortar.
Stepped Fall
Types of Canal Fall
Vertical Fall (Sarda Fall)
• In the simple type, canal u/s bed is on the level of
upstream curtain wall, canal u/s bed level is
below the crest of curtain wall. In both the
cases, a cistern is formed to act as water cushion.
Floor is made of concrete u/s and d/s side stone
pitching with cement grouting is provided. This
type of fall is used in Sarda Canal UP and
therefore, it is also called Sarda Fall.
Vertical Fall
Types of Canal Fall
Rapid Fall
• When the natural ground level is even and
rapid, this rapid fall is suitable. It consists of
long sloping glacis. Curtain walls are provided
on both u/s and d/s sides. Rubble masonry with
cement grouting is provided from u/s curtain
wall to d/s curtain wall. Masonry surface is
finished with a rich cement mortar.
Rapid Fall
Types of Canal Fall
Straight Glacis Fall
• It consists of a straight glacis provided with a
crest wall. For dissipation of energy of flowing
water, a water cushion is provided. Curtain
walls are provided at toe and heel. Stone
pitching is required at upstream and
downstream of the fall.
Straight Glacis Fall
Types of Canal Fall
Trapezoidal Notch Fall
• It was designed by Reid in 1894. In this type a
body or foundation wall across the channel
consisting of several trapezoidal notches between
side pier and intermediate pier is constructed. The
sill of the notches are kept at upstream bed level
of the canal. The body wall is made of concrete.
An impervious floor is provided to resist the
scouring effect of falling water. Upstream and
downstream side of the fall is protected by stone
pitching finished with cement grouting
Trapezoidal Notch Fall
Types of Canal Fall
Well or Cylinder Notch Fall
• In this type, water of canal from higher level is
thrown in a well or a cylinder from where it
escapes from bottom. Energy is dissipated in
the well in turbulence. They are suitable for
low discharges and are economical also.
Types of Canal Fall
Montague Type Fall
• In the straight glacis type profile, energy
dissipation is not complete. Therefore,
montague developed this type of profile where
energy dissipation takes place. His profile is
parabolic and is given by the following
equation,
Montague Type Fall
Types of Canal Fall
Inglis or Baffle Fall
• Here glacis is straight and sloping, but baffle
wall provided on the downstream floor
dissipate the energy. Main body of glacis is
made of concrete. Curtain walls both at toe and
heel are provided. Stone pitching are essential
both at u/s and d/s ends
Inglis or Baffle Fall
Canal Escape
• It is a side channel constructed to remove surplus
water from an irrigation channel (main canal,
branch canal, or distributary etc.) into a natural
drain.
• The water in the irrigation channel may become
surplus due to -
• Mistake
• Difficulty in regulation at the head
• Excessive rainfall in the upper reaches
• Outlets being closed by cultivators as they find
the demand of water is over
Canal Escape
• It is the structure required to dispose of surplus or
excess water from canal from time to time. Thus, a
canal escape serves as safety valve for canal system. It
provides protection to the canal from possible damage
due to excess supply which may be due to mistake in
releasing water at head regulator or heavy rainfall that
makes sudden regular demand of water. The excess
supply makes the canal banks vulnerable to failure due
to overtopping or dangerous leaks. Therefore, provision
for disposing this surplus water in form of canal
escapes at suitable intervals along the canal is essential.
Moreover emptying canal for repair and maintenance
and removal of sediment deposited in the canal can also
be achieved with the help of canal escapes.
Escapes are usually of the following
three types.
Surplus Escape
• It is also called regulator type. In this type sill
of the escape is kept at canal bed level and the
flow is controlled by a gate. This type of
escapes are preferred now-a-days as they give
better control and can be used for employing
the canal for maintenance.
Surplus Escape
Surplus Escape
Escapes are usually of the following
three types.
Tail Escape
• A tail escape is provided at the tail end of the
canal and is useful in maintaining the required
FSL in the tail reaches of the canal and
hence, they are called tail escape.
Tail Escape
Escapes are usually of the following
three types.
Scouring Escape
• This escape is constructed for the purpose of scouring
of excess silt deposited in the head reaches from time to
time. Hence, it is called scouring escape. Here the sill
of the regulator is kept at about 0.3 m below the canal
bed level at escape site. When deposited silt to be
scoured, a higher discharge than the FSL is allowed to
enter the canal from the head works. The gate of the
escape is raised so as to produce scouring velocity
which remove the deposited silt. This type of Escape
has become obsolete as silt ejector provided in the
canal can produce better efficiency.
Scouring Escape
Head Regulator
• Regulators Constructed at the off taking point are called head
regulators. When it is constructed at the head of main canal it
is known as canal head regulator. And when it is constructed at
the head of distributary, it is called distributary head regulator.
• Function:
• To control the entry of water either from the reservoir or from
the main canal.
• To control the entry of silt into off taking or main canal.
• To serve as a meter for measuring discharge of water.
Head Regulator
• Construction: The components of head regulator
depends upon the size of canal and location of head
regulator. It consists of one or more gated research
openings with barrels running through the bank. For
large canals head regulators are flumed to facilitate
the measurement of discharge.
Head Regulator
Cross Regulator
• Cross Regulator
• A Regulator Constructed in the main canal or parent
canal downstream of an off take canal is called cross-
regulator.
• It is generally constructed at a distance of 9 to 12 km
along the main canal and 6 to 10 km along branch
canal.
• Functions:
• (i) To Control the flow of water in canal system
• (ii) To feed the off taking Canals
• (iii) To enable closing of the canal breaches on the d/s
• (iv) To provide roadway for vehicular traffic
Cross Regulator
Cross Regulator
Construction: For Cross Regulators abutments
with grooves and piers are constructed parallel to
the parent canal. The sill of regulation is kept
little higher than the u/s bed level of canal across
which it is constructed. Vertical lift gates are
fitted in the grooves. The gates can be operate
from the road.
Canal regulators
Canal regulators
Cross Regulator
Head Regulator
Silt Control Devices
• Scouring Sluices or Under sluices, silt pocket and silt
excluders
• The above three components are employed for silt
control at the head work. Divide wall creates a silt
pocket. Silt excluder consists of a number under tunnels
resting on the floor pocket. Top floor of the tunnel is at
the level of sill of the head regulator.
• Various tunnels of different lengths are made. The
tunnel near the head regulator is of same length of head
regulator and successive tunnels towards the divide
wall are short. Velocity near the silt laden water is
disposed downstream through tunnels and under
sluices.
Silt Control Devices
• Silt Excluder: The silt excluder is located on
the u/s of diversion weir and in front of the
head regulator. The object is to remove silt that
has entered in the stilling basin through
scouring sluices.
• Silt Ejector: Silt Ejector is located in the canal
take off from the diversion weir at 6 to 10 km
in the canal reach. It ejects the silt that has
entered in the canal
Silt Control Devices
Silt Excluder
Silt Control Devices
Silt Ejector
Silt Control Devices
Canal Outlet/modules
• A canal outlet or a module is a small
structure built at the head of the water
course so as to connect it with a minor or a
distributary channel.
• It acts as a connecting link between the
system manager and the farmers.
Canal Outlet/modules
Non-Modular Modules
• Non-modular modules are those through which the
discharge depends upon the head difference between
the distributary and the water course.
Common examples are:
(i) Open sluice
(ii) Drowned pipe outlet
Types of Outlet/modules
• Non-modular modules
Semi-Modules or Flexible
modules
• Due to construction, a super-critical velocity is ensured
in the throat and thereby allowing the formation of a
jump in the expanding flume.
• The formation of hydraulic jump makes the outlet
discharge independent of the water level in water
course, thus making it a semi module. Semi-modules or
flexible modules are those through which the discharge
is independent of the water level of the water course but
depends only upon the water level of the distributary so
long as a minimum working head is available.
• Examples are pipe outlet, open flume type etc.
Semi-Modules or Flexible
modules
Rigid Modules or Modular
Outlets
• Rigid modules or modular outlets are those through
which discharge is constant and fixed within
limits, irrespective of the fluctuations of the water
levels of either the distributary or of the water course
or both.
• An example is Gibb’s module:
Gibb’s Module
Cross Drainage Works
• Irrigational Canals while carrying water from
headworks to crop field, have to cross few natural
drainage streams, nallaha, etc.. To cross those
drainages safely by the canals, some suitable
structures are required to construct. Works
required to construct, to cross the drainage are
called Cross Drainage Works (CDWs). At the
meeting point of canals and drainages, bed levels
may not be same. Depending on their bed
levels, different structures are constructed and
accordingly they are designated by different
names.
Necessity of Cross Drainage Works
• The water-shed canals do not cross natural drainages.
But in actual orientation of the canal network, this ideal
condition may not be available and the obstacles like
natural drainages may be present across the canal.
So, the cross drainage works must be provided for
running the irrigation system.
• At the crossing point, the water of the canal and the
drainage get intermixed. So, for the smooth running of the
canal with its design discharge the cross drainage works are
required.
• The site condition of the crossing point may be such
that without any suitable structure, the water of the canal
and drainage can not be diverted to their natural
directions. So, the cross drainage works must be provided
to maintain their natural direction of flow.
Necessity of Cross Drainage Works
Types of Cross Drainage Works
• Type I (Irrigation canal passes over the drainage)
• (a) Aqueduct
• (b) Siphon Aqueduct
• Type II (Drainage passes over the irrigation canal)
• (a) Super passage
• (b) Siphon super passage
• Type III (Drainage and canal intersection each other
of the same level)
• (a) Level crossing
• (b) Inlet and outlet
Selection of Type of Cross Drainage
Works
• Relative bed levels
• Availability of suitable foundation
• Economical consideration
• Discharge of the drainage
• Construction problems
Types of Cross Drainage Works
• Type-I Irrigation canal Passes over the
Drainage: This condition involves the
construction of following:
• Aqueduct
• The hydraulic structure in which the irrigation
canal is taken over the drainage (such as
river, stream etc..) is known as aqueduct. This
structure is suitable when bed level of canal is
above the highest flood level of drainage. In this
case, the drainage water passes clearly below the
canal.
Aqueduct
Aqueduct
Aqueduct
Siphon Aqueduct
• In a hydraulic structure where the canal is
taken over the drainage, but the drainage water
cannot pass clearly below the canal. It flows
under siphonic action. So, it is known as
siphon aqueduct. This structure is suitable
when the bed level of canal is below the
highest flood level.
Siphon Aqueduct
Siphon Aqueduct
Types of Cross Drainage Works
• Type-II Drainage Passes Over the irrigation
Canal.
• Super Passage
• The hydraulic structure in which the drainage
is taken over the irrigation canal is known as
super passage. The structure is suitable when
the bed level of drainage is above the full
supply level of the canal. The water of the
canal passes clearly below the drainage.
Super Passage
Super Passage
Siphon Super Passage
• The hydraulic structure in which the drainage
is taken over the irrigation canal, but the canal
water passes below the drainage under
siphonic action is known as siphon super
passage. This structure is suitable when the
bed level of drainage is below the full supply
level of the canal.
Siphon Super Passage
Siphon Super Passage
Types of Cross Drainage Works
• Type III Drainage and Canal Intersect each
other at the same level.
• Level Crossings
• When the bed level of canal and the stream are
approximately the same and quality of water in canal
and stream is not much different, the cross drainage
work constructed is called level crossing where water
of canal and stream is allowed to mix. With the help of
regulators both in canal and stream, water is disposed
through canal and stream in required quantity. Level
crossing consists of following components (i) crest wall
(ii) Stream regulator (iii) Canal regulator.
Level Crossings
Level Crossing
Types of Cross Drainage Works
• Inlet and Outlet
• When irrigation canal meets a small stream or
drain at same level, drain is allowed to enter the
canal as in inlet. At some distance from this inlet
point, a part of water is allowed to drain as outlet
which eventually meets the original stream. Stone
pitching is required at the inlet and outlet. The
bed and banks between inlet and outlet are also
protected by stone pitching. This type of CDW is
called Inlet and Outlet.
Inlet and Outlet
Selection of Type of Cross Drainage
Work
• The following factors should be considered:
• (i) Relative Bed Level
• According to the relative bed levels of the canal and the river or
drainage, the type of cross drainage work are generally selected
which has been discussed earlier. But some problems may come at
the crossing point
• The following points should be remembered while
recommending the type of work,
• (a) The crossing should be at right angle to each other,
• (b) Well defined cross-section of the river or drainage should be
available.
• (c) At the crossing point the drainage should be straight for a
considerable length.
• (d) The width of the drainage should be narrow as far as possible.
• Considering the above points The C/s can be shifted to the
downstream or upstream.
Selection of Type of Cross Drainage
Work
Availability of Suitable Foundation
• For the construction of cross drainage works
suitable foundation is required. By boring
test, if suitable foundation is not
available, then the type of cross drainage work
should be selected to site Condition.
Selection of Type of Cross Drainage
Work
Economic Consideration
• The cost of construction of cross drainage
works should be justified with respect to the
project cost and overall benefits of the project.
So, the type of works should be selected
considering the economical point of view.
Selection of Type of Cross Drainage
Work
Discharge of the drainage
Practically the discharge of the drainage is very
uncertain in rainy season. So, the structure
should be carefully selected so that it may not be
destroyed due to unexpected heavy discharge of
the river or drainage.
Selection of Type of Cross Drainage
Work
Construction of Problems
• Different types of constructional problems may arise
at the site such as sub soil water, construction
materials, communication, availability of land etc. So
the type of works should be selected according to the
site condition.
Questions
• What do you understand by a fall in
canal? Why it is necessary?
• What are the functions of a canal head
regulator?
• Explain functions of cross regulator and
distributory head regulator.
• Write a S.N. on Types of Canal Falls
References
• Irrigation Engineering & Hydraulic Structures
– By Prof. Santosh Kumar Garg
– Khanna Publishers
• Internet Websites
• http://www.uap-bd.edu/
• Lecture Notes By: Dr. M. R. Kabir
• Professor and Head, Department of Civil Engineering
Department
• University of Asia Pacific (UAP), Dhaka
Thanks…

Mais conteúdo relacionado

Mais procurados (20)

Cross Drainage Works
Cross Drainage WorksCross Drainage Works
Cross Drainage Works
 
Canal falls and its classification
Canal falls and its classificationCanal falls and its classification
Canal falls and its classification
 
Irrigation Channels
Irrigation ChannelsIrrigation Channels
Irrigation Channels
 
weir & barrage
weir & barrageweir & barrage
weir & barrage
 
Canal headworks
Canal headworksCanal headworks
Canal headworks
 
Canal Fall
Canal FallCanal Fall
Canal Fall
 
Khosla theory
Khosla theoryKhosla theory
Khosla theory
 
Spillways components and types
Spillways components and typesSpillways components and types
Spillways components and types
 
Canal irrigation
Canal irrigationCanal irrigation
Canal irrigation
 
Diversion headworks
Diversion headworksDiversion headworks
Diversion headworks
 
Dams and spillways
Dams and spillwaysDams and spillways
Dams and spillways
 
Design of Hydraulic Structures
Design of Hydraulic StructuresDesign of Hydraulic Structures
Design of Hydraulic Structures
 
Gravity Dam
Gravity DamGravity Dam
Gravity Dam
 
Cross section of the canal, balancing depth and canal fsl
Cross section of the canal, balancing depth  and canal fslCross section of the canal, balancing depth  and canal fsl
Cross section of the canal, balancing depth and canal fsl
 
Design of gravity dams
Design of gravity damsDesign of gravity dams
Design of gravity dams
 
Canal of design
Canal of designCanal of design
Canal of design
 
Hydraulic jump
Hydraulic jumpHydraulic jump
Hydraulic jump
 
Design of Canal (Kennedy & Lacey Theory) & Diversion Headwork
Design of Canal (Kennedy & Lacey Theory) & Diversion HeadworkDesign of Canal (Kennedy & Lacey Theory) & Diversion Headwork
Design of Canal (Kennedy & Lacey Theory) & Diversion Headwork
 
Theory for impervious floor
Theory for impervious floorTheory for impervious floor
Theory for impervious floor
 
Weir and barrage lecture
Weir and barrage lectureWeir and barrage lecture
Weir and barrage lecture
 

Semelhante a Canal Regulation & Cross Drainage Works

Canal Regulation Works
Canal Regulation WorksCanal Regulation Works
Canal Regulation WorksSANJEEV Wazir
 
MODULE 4 REGULATING AND CROSS DRAINAGE WORKS.pptx
MODULE 4 REGULATING AND CROSS DRAINAGE WORKS.pptxMODULE 4 REGULATING AND CROSS DRAINAGE WORKS.pptx
MODULE 4 REGULATING AND CROSS DRAINAGE WORKS.pptxSilasChaudhari
 
Canal MASONRY WORK
Canal MASONRY WORKCanal MASONRY WORK
Canal MASONRY WORKSAGAR RAUT
 
hydraulic structures in civil engineering
hydraulic structures in civil engineeringhydraulic structures in civil engineering
hydraulic structures in civil engineeringBittuRajkumar
 
Diversionheadworks 150327075328-conversion-gate01
Diversionheadworks 150327075328-conversion-gate01Diversionheadworks 150327075328-conversion-gate01
Diversionheadworks 150327075328-conversion-gate01saibabu48
 
diversionheadworks-150327075328-conversion-gate01.pdf
diversionheadworks-150327075328-conversion-gate01.pdfdiversionheadworks-150327075328-conversion-gate01.pdf
diversionheadworks-150327075328-conversion-gate01.pdfShrutiLotliker
 
Unit 3 spillway
Unit 3 spillwayUnit 3 spillway
Unit 3 spillwayMood Naik
 
Chapter Five-CANAL APPURTENANT STRUCTURES.pdf
Chapter Five-CANAL APPURTENANT STRUCTURES.pdfChapter Five-CANAL APPURTENANT STRUCTURES.pdf
Chapter Five-CANAL APPURTENANT STRUCTURES.pdfAbdanurJihad
 
Diversion of headwork
Diversion of headwork Diversion of headwork
Diversion of headwork Jay Khoradiya
 
Spillways, Spillway capacity, flood routing through spillways, different type...
Spillways, Spillway capacity, flood routing through spillways, different type...Spillways, Spillway capacity, flood routing through spillways, different type...
Spillways, Spillway capacity, flood routing through spillways, different type...Denish Jangid
 
CANAL IRRIGATION
CANAL IRRIGATIONCANAL IRRIGATION
CANAL IRRIGATIONkannan1407
 
Presentation1 hydro;ogy-SKK.pdf
Presentation1 hydro;ogy-SKK.pdfPresentation1 hydro;ogy-SKK.pdf
Presentation1 hydro;ogy-SKK.pdfShrutiLotliker
 

Semelhante a Canal Regulation & Cross Drainage Works (20)

Canal Regulation Works
Canal Regulation WorksCanal Regulation Works
Canal Regulation Works
 
MODULE 4 REGULATING AND CROSS DRAINAGE WORKS.pptx
MODULE 4 REGULATING AND CROSS DRAINAGE WORKS.pptxMODULE 4 REGULATING AND CROSS DRAINAGE WORKS.pptx
MODULE 4 REGULATING AND CROSS DRAINAGE WORKS.pptx
 
Canal MASONRY WORK
Canal MASONRY WORKCanal MASONRY WORK
Canal MASONRY WORK
 
Canal falls
Canal fallsCanal falls
Canal falls
 
hydraulic structures in civil engineering
hydraulic structures in civil engineeringhydraulic structures in civil engineering
hydraulic structures in civil engineering
 
12. Canal Head Regulation.1.pdf
12. Canal Head Regulation.1.pdf12. Canal Head Regulation.1.pdf
12. Canal Head Regulation.1.pdf
 
Diversion head work
Diversion head workDiversion head work
Diversion head work
 
Diversionheadworks 150327075328-conversion-gate01
Diversionheadworks 150327075328-conversion-gate01Diversionheadworks 150327075328-conversion-gate01
Diversionheadworks 150327075328-conversion-gate01
 
diversionheadworks-150327075328-conversion-gate01.pdf
diversionheadworks-150327075328-conversion-gate01.pdfdiversionheadworks-150327075328-conversion-gate01.pdf
diversionheadworks-150327075328-conversion-gate01.pdf
 
Unit 3 spillway
Unit 3 spillwayUnit 3 spillway
Unit 3 spillway
 
Chapter Five-CANAL APPURTENANT STRUCTURES.pdf
Chapter Five-CANAL APPURTENANT STRUCTURES.pdfChapter Five-CANAL APPURTENANT STRUCTURES.pdf
Chapter Five-CANAL APPURTENANT STRUCTURES.pdf
 
Canal structures
Canal structuresCanal structures
Canal structures
 
Canal structures
Canal structuresCanal structures
Canal structures
 
Cross drainage work
Cross drainage workCross drainage work
Cross drainage work
 
Diversion of headwork
Diversion of headwork Diversion of headwork
Diversion of headwork
 
Spillways, Spillway capacity, flood routing through spillways, different type...
Spillways, Spillway capacity, flood routing through spillways, different type...Spillways, Spillway capacity, flood routing through spillways, different type...
Spillways, Spillway capacity, flood routing through spillways, different type...
 
CANAL IRRIGATION
CANAL IRRIGATIONCANAL IRRIGATION
CANAL IRRIGATION
 
Presentation1 hydro;ogy-SKK.pdf
Presentation1 hydro;ogy-SKK.pdfPresentation1 hydro;ogy-SKK.pdf
Presentation1 hydro;ogy-SKK.pdf
 
Spillway
SpillwaySpillway
Spillway
 
design of weirs
design of weirsdesign of weirs
design of weirs
 

Mais de GAURAV. H .TANDON

Suicide Prevention through Architecture (Building) and City Planning
Suicide Prevention through  Architecture (Building) and City PlanningSuicide Prevention through  Architecture (Building) and City Planning
Suicide Prevention through Architecture (Building) and City PlanningGAURAV. H .TANDON
 
Suicide Prevention through Architecture (Building) and City Planning
Suicide Prevention through  Architecture (Building) and City PlanningSuicide Prevention through  Architecture (Building) and City Planning
Suicide Prevention through Architecture (Building) and City PlanningGAURAV. H .TANDON
 
Digital Detoxing in Smart Cities
Digital Detoxing in Smart CitiesDigital Detoxing in Smart Cities
Digital Detoxing in Smart CitiesGAURAV. H .TANDON
 
Digital Detoxing in Smart Cities
Digital Detoxing in Smart CitiesDigital Detoxing in Smart Cities
Digital Detoxing in Smart CitiesGAURAV. H .TANDON
 
Crash for Cash-Organized Crime (COC).pptx
Crash for Cash-Organized Crime (COC).pptxCrash for Cash-Organized Crime (COC).pptx
Crash for Cash-Organized Crime (COC).pptxGAURAV. H .TANDON
 
Ecological Footprint (1).pptx
Ecological Footprint (1).pptxEcological Footprint (1).pptx
Ecological Footprint (1).pptxGAURAV. H .TANDON
 
The unethical practice of gift giving to doctors by pharma companies
The unethical practice of gift giving to doctors by pharma companiesThe unethical practice of gift giving to doctors by pharma companies
The unethical practice of gift giving to doctors by pharma companiesGAURAV. H .TANDON
 
Gamification of Smart Cities
Gamification of Smart Cities Gamification of Smart Cities
Gamification of Smart Cities GAURAV. H .TANDON
 
Collusion and Fraud Detection on Electronic Energy Meters
Collusion and Fraud Detection on Electronic Energy Meters Collusion and Fraud Detection on Electronic Energy Meters
Collusion and Fraud Detection on Electronic Energy Meters GAURAV. H .TANDON
 
Cyber Security in Smart Buildings
Cyber Security in Smart Buildings Cyber Security in Smart Buildings
Cyber Security in Smart Buildings GAURAV. H .TANDON
 

Mais de GAURAV. H .TANDON (20)

Suicide Prevention through Architecture (Building) and City Planning
Suicide Prevention through  Architecture (Building) and City PlanningSuicide Prevention through  Architecture (Building) and City Planning
Suicide Prevention through Architecture (Building) and City Planning
 
Suicide Prevention through Architecture (Building) and City Planning
Suicide Prevention through  Architecture (Building) and City PlanningSuicide Prevention through  Architecture (Building) and City Planning
Suicide Prevention through Architecture (Building) and City Planning
 
Digital Detoxing in Smart Cities
Digital Detoxing in Smart CitiesDigital Detoxing in Smart Cities
Digital Detoxing in Smart Cities
 
Digital Detoxing in Smart Cities
Digital Detoxing in Smart CitiesDigital Detoxing in Smart Cities
Digital Detoxing in Smart Cities
 
Premerital Sceening .pptx
Premerital Sceening .pptxPremerital Sceening .pptx
Premerital Sceening .pptx
 
Polymath(Renaissance man)
Polymath(Renaissance man)Polymath(Renaissance man)
Polymath(Renaissance man)
 
Crash for Cash-Organized Crime (COC).pptx
Crash for Cash-Organized Crime (COC).pptxCrash for Cash-Organized Crime (COC).pptx
Crash for Cash-Organized Crime (COC).pptx
 
Voting Age .pptx
Voting Age .pptxVoting Age .pptx
Voting Age .pptx
 
Ecological Footprint (1).pptx
Ecological Footprint (1).pptxEcological Footprint (1).pptx
Ecological Footprint (1).pptx
 
Urban Heat Island Effect
Urban Heat Island EffectUrban Heat Island Effect
Urban Heat Island Effect
 
Communication Skills
Communication SkillsCommunication Skills
Communication Skills
 
The unethical practice of gift giving to doctors by pharma companies
The unethical practice of gift giving to doctors by pharma companiesThe unethical practice of gift giving to doctors by pharma companies
The unethical practice of gift giving to doctors by pharma companies
 
Compassionate Cities
Compassionate CitiesCompassionate Cities
Compassionate Cities
 
Gamification of Smart Cities
Gamification of Smart Cities Gamification of Smart Cities
Gamification of Smart Cities
 
Anti-Microbial Copper
Anti-Microbial Copper Anti-Microbial Copper
Anti-Microbial Copper
 
Smart Forest City
Smart Forest City Smart Forest City
Smart Forest City
 
Smart forest cities
Smart forest cities Smart forest cities
Smart forest cities
 
Automotive Hacking
Automotive Hacking Automotive Hacking
Automotive Hacking
 
Collusion and Fraud Detection on Electronic Energy Meters
Collusion and Fraud Detection on Electronic Energy Meters Collusion and Fraud Detection on Electronic Energy Meters
Collusion and Fraud Detection on Electronic Energy Meters
 
Cyber Security in Smart Buildings
Cyber Security in Smart Buildings Cyber Security in Smart Buildings
Cyber Security in Smart Buildings
 

Último

social pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajansocial pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajanpragatimahajan3
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpinRaunakKeshri1
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...Sapna Thakur
 
Disha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfDisha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfchloefrazer622
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfAyushMahapatra5
 
General AI for Medical Educators April 2024
General AI for Medical Educators April 2024General AI for Medical Educators April 2024
General AI for Medical Educators April 2024Janet Corral
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104misteraugie
 
9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room servicediscovermytutordmt
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 

Último (20)

social pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajansocial pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajan
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpin
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
 
Disha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfDisha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdf
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdf
 
General AI for Medical Educators April 2024
General AI for Medical Educators April 2024General AI for Medical Educators April 2024
General AI for Medical Educators April 2024
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room service
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 

Canal Regulation & Cross Drainage Works

  • 1. Canal Regulation & Cross Drainage Works Unit-V BTCI09007
  • 2. Syllabus • Canal Regulation Works • Canal Fall- Necessity and Location- Types of Falls- Cross Regulator and Distributory Head Regulator- Their Functions, Silt Control Devices, Canal Escapes- Types of Escapes. • Cross Drainage Works: Types- selection of suitable type of CD works- aqueduct and Siphon aqueduct
  • 3. What is Canal Fall? • Whenever the available natural ground slope is steep than the designed bed slope of the channel, the difference is adjusted by constructing vertical ‘falls’ or ‘drops’ in the canal bed at suitable intervals, as shown in figure below. Such a drop in a natural canal bed will not be stable and, therefore, in order to retain this drop, a masonry structure is constructed. Such a structure is called a Canal Fall or a Canal drop.
  • 5. Canal Fall Irrigation canals are designed for a prescribed bed slope so that velocity becomes non silting or non scouring. But if the ground topography is such that in order to maintain the canal designed slope, indefinite filling from falling ground level is to be made. This indefinite filling is avoided by constructing a hydraulic structure in the place of sudden bed level. This hydraulic structure is called canal fall or drop. Beyond the canal fall, canal again maintains its designed slope.
  • 6. Canal Fall • Thus, a canal fall or drop is an irrigation structure constructed across a canal to lower down its bed level to maintain the designed slope when there is a change of ground level to maintain the designed slope when there is change of ground level. This falling water at the fall has some surplus energy. The fall is constructed in such a way that it can destroy this surplus energy.
  • 7. Necessity of Canal Falls • When the slope of the ground suddenly changes to steeper slope, the permissible bed slope can not be maintained. It requires excessive earthwork in filling to maintain the slope. In such a case falls are provided to avoid excessive earth work in filling
  • 9. Necessity of Canal Falls • When the slope of the ground is more or less uniform and the slope is greater than the permissible bed slope of canal.
  • 10. Necessity of Canal Falls • In cross-drainage works, when the difference between bed level of canal and that of drainage is small or when the F.S.L of the canal is above the bed level of drainage then the canal fall is necessary to carry the canal water below the stream or drainage.
  • 12. Types of Canal Fall • Depending on the ground level conditions and shape of the fall the various types of fall are: Ogee Fall • The ogee fall was constructed by Sir Proby Cautley on the Ganga Canal. This type of fall has gradual convex and concave surfaces i.e. in the ogee form. The gradual convex and concave surface is provided with an aim to provide smooth transition and to reduce disturbance and impact. A hydraulic jump is formed which dissipates a part of kinetic energy. Upstream and downstream of the fall is provided by Stone Pitching.
  • 14. Types of Canal Fall Stepped Fall • It consists of a series of vertical drops in the form of steps. This steps is suitable in places where sloping ground is very long and require a long glacis to connect the higher bed level u/s with lower bed level d/s. it is practically a modification of rapid fall. The sloping glacis is divided into a number drops to bring down the canal bed step by step to protect the canal bed and sides from damage by erosion. Brick walls are provided at each drop. The bed of the canal within the fall is protected by rubble masonry with surface finishing by rich cement mortar.
  • 16. Types of Canal Fall Vertical Fall (Sarda Fall) • In the simple type, canal u/s bed is on the level of upstream curtain wall, canal u/s bed level is below the crest of curtain wall. In both the cases, a cistern is formed to act as water cushion. Floor is made of concrete u/s and d/s side stone pitching with cement grouting is provided. This type of fall is used in Sarda Canal UP and therefore, it is also called Sarda Fall.
  • 18. Types of Canal Fall Rapid Fall • When the natural ground level is even and rapid, this rapid fall is suitable. It consists of long sloping glacis. Curtain walls are provided on both u/s and d/s sides. Rubble masonry with cement grouting is provided from u/s curtain wall to d/s curtain wall. Masonry surface is finished with a rich cement mortar.
  • 20. Types of Canal Fall Straight Glacis Fall • It consists of a straight glacis provided with a crest wall. For dissipation of energy of flowing water, a water cushion is provided. Curtain walls are provided at toe and heel. Stone pitching is required at upstream and downstream of the fall.
  • 22. Types of Canal Fall Trapezoidal Notch Fall • It was designed by Reid in 1894. In this type a body or foundation wall across the channel consisting of several trapezoidal notches between side pier and intermediate pier is constructed. The sill of the notches are kept at upstream bed level of the canal. The body wall is made of concrete. An impervious floor is provided to resist the scouring effect of falling water. Upstream and downstream side of the fall is protected by stone pitching finished with cement grouting
  • 24. Types of Canal Fall Well or Cylinder Notch Fall • In this type, water of canal from higher level is thrown in a well or a cylinder from where it escapes from bottom. Energy is dissipated in the well in turbulence. They are suitable for low discharges and are economical also.
  • 25. Types of Canal Fall Montague Type Fall • In the straight glacis type profile, energy dissipation is not complete. Therefore, montague developed this type of profile where energy dissipation takes place. His profile is parabolic and is given by the following equation,
  • 27. Types of Canal Fall Inglis or Baffle Fall • Here glacis is straight and sloping, but baffle wall provided on the downstream floor dissipate the energy. Main body of glacis is made of concrete. Curtain walls both at toe and heel are provided. Stone pitching are essential both at u/s and d/s ends
  • 29. Canal Escape • It is a side channel constructed to remove surplus water from an irrigation channel (main canal, branch canal, or distributary etc.) into a natural drain. • The water in the irrigation channel may become surplus due to - • Mistake • Difficulty in regulation at the head • Excessive rainfall in the upper reaches • Outlets being closed by cultivators as they find the demand of water is over
  • 30. Canal Escape • It is the structure required to dispose of surplus or excess water from canal from time to time. Thus, a canal escape serves as safety valve for canal system. It provides protection to the canal from possible damage due to excess supply which may be due to mistake in releasing water at head regulator or heavy rainfall that makes sudden regular demand of water. The excess supply makes the canal banks vulnerable to failure due to overtopping or dangerous leaks. Therefore, provision for disposing this surplus water in form of canal escapes at suitable intervals along the canal is essential. Moreover emptying canal for repair and maintenance and removal of sediment deposited in the canal can also be achieved with the help of canal escapes.
  • 31. Escapes are usually of the following three types. Surplus Escape • It is also called regulator type. In this type sill of the escape is kept at canal bed level and the flow is controlled by a gate. This type of escapes are preferred now-a-days as they give better control and can be used for employing the canal for maintenance.
  • 34. Escapes are usually of the following three types. Tail Escape • A tail escape is provided at the tail end of the canal and is useful in maintaining the required FSL in the tail reaches of the canal and hence, they are called tail escape.
  • 36. Escapes are usually of the following three types. Scouring Escape • This escape is constructed for the purpose of scouring of excess silt deposited in the head reaches from time to time. Hence, it is called scouring escape. Here the sill of the regulator is kept at about 0.3 m below the canal bed level at escape site. When deposited silt to be scoured, a higher discharge than the FSL is allowed to enter the canal from the head works. The gate of the escape is raised so as to produce scouring velocity which remove the deposited silt. This type of Escape has become obsolete as silt ejector provided in the canal can produce better efficiency.
  • 38. Head Regulator • Regulators Constructed at the off taking point are called head regulators. When it is constructed at the head of main canal it is known as canal head regulator. And when it is constructed at the head of distributary, it is called distributary head regulator. • Function: • To control the entry of water either from the reservoir or from the main canal. • To control the entry of silt into off taking or main canal. • To serve as a meter for measuring discharge of water.
  • 39. Head Regulator • Construction: The components of head regulator depends upon the size of canal and location of head regulator. It consists of one or more gated research openings with barrels running through the bank. For large canals head regulators are flumed to facilitate the measurement of discharge.
  • 41. Cross Regulator • Cross Regulator • A Regulator Constructed in the main canal or parent canal downstream of an off take canal is called cross- regulator. • It is generally constructed at a distance of 9 to 12 km along the main canal and 6 to 10 km along branch canal. • Functions: • (i) To Control the flow of water in canal system • (ii) To feed the off taking Canals • (iii) To enable closing of the canal breaches on the d/s • (iv) To provide roadway for vehicular traffic
  • 43. Cross Regulator Construction: For Cross Regulators abutments with grooves and piers are constructed parallel to the parent canal. The sill of regulation is kept little higher than the u/s bed level of canal across which it is constructed. Vertical lift gates are fitted in the grooves. The gates can be operate from the road.
  • 48. Silt Control Devices • Scouring Sluices or Under sluices, silt pocket and silt excluders • The above three components are employed for silt control at the head work. Divide wall creates a silt pocket. Silt excluder consists of a number under tunnels resting on the floor pocket. Top floor of the tunnel is at the level of sill of the head regulator. • Various tunnels of different lengths are made. The tunnel near the head regulator is of same length of head regulator and successive tunnels towards the divide wall are short. Velocity near the silt laden water is disposed downstream through tunnels and under sluices.
  • 49. Silt Control Devices • Silt Excluder: The silt excluder is located on the u/s of diversion weir and in front of the head regulator. The object is to remove silt that has entered in the stilling basin through scouring sluices. • Silt Ejector: Silt Ejector is located in the canal take off from the diversion weir at 6 to 10 km in the canal reach. It ejects the silt that has entered in the canal
  • 53. Canal Outlet/modules • A canal outlet or a module is a small structure built at the head of the water course so as to connect it with a minor or a distributary channel. • It acts as a connecting link between the system manager and the farmers.
  • 55. Non-Modular Modules • Non-modular modules are those through which the discharge depends upon the head difference between the distributary and the water course. Common examples are: (i) Open sluice (ii) Drowned pipe outlet
  • 56. Types of Outlet/modules • Non-modular modules
  • 57. Semi-Modules or Flexible modules • Due to construction, a super-critical velocity is ensured in the throat and thereby allowing the formation of a jump in the expanding flume. • The formation of hydraulic jump makes the outlet discharge independent of the water level in water course, thus making it a semi module. Semi-modules or flexible modules are those through which the discharge is independent of the water level of the water course but depends only upon the water level of the distributary so long as a minimum working head is available. • Examples are pipe outlet, open flume type etc.
  • 59. Rigid Modules or Modular Outlets • Rigid modules or modular outlets are those through which discharge is constant and fixed within limits, irrespective of the fluctuations of the water levels of either the distributary or of the water course or both. • An example is Gibb’s module:
  • 61. Cross Drainage Works • Irrigational Canals while carrying water from headworks to crop field, have to cross few natural drainage streams, nallaha, etc.. To cross those drainages safely by the canals, some suitable structures are required to construct. Works required to construct, to cross the drainage are called Cross Drainage Works (CDWs). At the meeting point of canals and drainages, bed levels may not be same. Depending on their bed levels, different structures are constructed and accordingly they are designated by different names.
  • 62. Necessity of Cross Drainage Works • The water-shed canals do not cross natural drainages. But in actual orientation of the canal network, this ideal condition may not be available and the obstacles like natural drainages may be present across the canal. So, the cross drainage works must be provided for running the irrigation system. • At the crossing point, the water of the canal and the drainage get intermixed. So, for the smooth running of the canal with its design discharge the cross drainage works are required. • The site condition of the crossing point may be such that without any suitable structure, the water of the canal and drainage can not be diverted to their natural directions. So, the cross drainage works must be provided to maintain their natural direction of flow.
  • 63. Necessity of Cross Drainage Works
  • 64. Types of Cross Drainage Works • Type I (Irrigation canal passes over the drainage) • (a) Aqueduct • (b) Siphon Aqueduct • Type II (Drainage passes over the irrigation canal) • (a) Super passage • (b) Siphon super passage • Type III (Drainage and canal intersection each other of the same level) • (a) Level crossing • (b) Inlet and outlet
  • 65. Selection of Type of Cross Drainage Works • Relative bed levels • Availability of suitable foundation • Economical consideration • Discharge of the drainage • Construction problems
  • 66. Types of Cross Drainage Works • Type-I Irrigation canal Passes over the Drainage: This condition involves the construction of following: • Aqueduct • The hydraulic structure in which the irrigation canal is taken over the drainage (such as river, stream etc..) is known as aqueduct. This structure is suitable when bed level of canal is above the highest flood level of drainage. In this case, the drainage water passes clearly below the canal.
  • 70. Siphon Aqueduct • In a hydraulic structure where the canal is taken over the drainage, but the drainage water cannot pass clearly below the canal. It flows under siphonic action. So, it is known as siphon aqueduct. This structure is suitable when the bed level of canal is below the highest flood level.
  • 73. Types of Cross Drainage Works • Type-II Drainage Passes Over the irrigation Canal. • Super Passage • The hydraulic structure in which the drainage is taken over the irrigation canal is known as super passage. The structure is suitable when the bed level of drainage is above the full supply level of the canal. The water of the canal passes clearly below the drainage.
  • 76. Siphon Super Passage • The hydraulic structure in which the drainage is taken over the irrigation canal, but the canal water passes below the drainage under siphonic action is known as siphon super passage. This structure is suitable when the bed level of drainage is below the full supply level of the canal.
  • 79. Types of Cross Drainage Works • Type III Drainage and Canal Intersect each other at the same level. • Level Crossings • When the bed level of canal and the stream are approximately the same and quality of water in canal and stream is not much different, the cross drainage work constructed is called level crossing where water of canal and stream is allowed to mix. With the help of regulators both in canal and stream, water is disposed through canal and stream in required quantity. Level crossing consists of following components (i) crest wall (ii) Stream regulator (iii) Canal regulator.
  • 82. Types of Cross Drainage Works • Inlet and Outlet • When irrigation canal meets a small stream or drain at same level, drain is allowed to enter the canal as in inlet. At some distance from this inlet point, a part of water is allowed to drain as outlet which eventually meets the original stream. Stone pitching is required at the inlet and outlet. The bed and banks between inlet and outlet are also protected by stone pitching. This type of CDW is called Inlet and Outlet.
  • 84. Selection of Type of Cross Drainage Work • The following factors should be considered: • (i) Relative Bed Level • According to the relative bed levels of the canal and the river or drainage, the type of cross drainage work are generally selected which has been discussed earlier. But some problems may come at the crossing point • The following points should be remembered while recommending the type of work, • (a) The crossing should be at right angle to each other, • (b) Well defined cross-section of the river or drainage should be available. • (c) At the crossing point the drainage should be straight for a considerable length. • (d) The width of the drainage should be narrow as far as possible. • Considering the above points The C/s can be shifted to the downstream or upstream.
  • 85. Selection of Type of Cross Drainage Work Availability of Suitable Foundation • For the construction of cross drainage works suitable foundation is required. By boring test, if suitable foundation is not available, then the type of cross drainage work should be selected to site Condition.
  • 86. Selection of Type of Cross Drainage Work Economic Consideration • The cost of construction of cross drainage works should be justified with respect to the project cost and overall benefits of the project. So, the type of works should be selected considering the economical point of view.
  • 87. Selection of Type of Cross Drainage Work Discharge of the drainage Practically the discharge of the drainage is very uncertain in rainy season. So, the structure should be carefully selected so that it may not be destroyed due to unexpected heavy discharge of the river or drainage.
  • 88. Selection of Type of Cross Drainage Work Construction of Problems • Different types of constructional problems may arise at the site such as sub soil water, construction materials, communication, availability of land etc. So the type of works should be selected according to the site condition.
  • 89. Questions • What do you understand by a fall in canal? Why it is necessary? • What are the functions of a canal head regulator? • Explain functions of cross regulator and distributory head regulator. • Write a S.N. on Types of Canal Falls
  • 90. References • Irrigation Engineering & Hydraulic Structures – By Prof. Santosh Kumar Garg – Khanna Publishers • Internet Websites • http://www.uap-bd.edu/ • Lecture Notes By: Dr. M. R. Kabir • Professor and Head, Department of Civil Engineering Department • University of Asia Pacific (UAP), Dhaka