SlideShare uma empresa Scribd logo
1 de 42
Baixar para ler offline
SCHOOL OF ARCHITECTURE, BUILDING AND DESIGN
BACHELOR OF QUANTITY SURVEYING (HONOURS)
AUGUST 2018
BUILDING ECONOMICS ASSIGNMENT
Lecturer : Sr Shirley Chin Ai Ling
Pn. Nurulhuda Hashim
Submission Date : 19th November 2018
Group Members :
NO. STUDENT NAME STUDENT ID
1 YEAP PHAY SHIAN 0322243
2 TAN VIN NIE 0323706
3 TEY CHENG FERN 0323912
4 TAN JIA SAN 0322406
5 TIO CHONG ZHI 0328134
6 KENNETH TAN SIN KWANG 0322482
7 NG SHENG ZHE 0323830
8 TEOH ZI WEI 0323372
TABLE OF CONTENTS
NO. CONTENT PAGE
1.0 Introduction
1.1 Location of the Site 1
1.2 Benchmark Project 3
1.3 Proposed Building Design 6
1.4 Construction Technology, Methodology & Techniques 10
1.5 Architectural Features 16
2.0 Preliminary Cost Appraisal
2.1 Definition of Areas 21
2.2 Cost Plan 23
3.0 Construction Cost
3.1 Overall Construction Cost Analysis 24
3.2 Basement 30
3.3 Podium 32
3.4 Tower A & B 34
4.0 Conclusion 37
5.0 References 39
6.0 Appendices
1.0 Introduction
1.1 Location
The proposed site is located at Lot 160, Jalan Robson, Jalan Syed Putra, Kuala Lumpur where
it is chosen by the client in the center of Kuala Lumpur. It is strategically located at the prestigious
location at Seputeh. The site covers an area of 1.43 acres of freehold land. The immediate vicinity
is a residential area of mixed proportion between low-rise and high-rise construction. Most of the
land used is dedicated to low rise construction and low density apartments. However, observations
show that the residency is in proximity to Jalan Syed Putra where existing roads to and fro the site,
therefore no temporary roadways have to be built. This proposed project is expected to be a vibrant,
environmental friendly and economic development.
The proposed site has existing roads, and this will ease the process of starting the project as
there is already an entry and exit to the site. Therefore, there is no need to construct temporary roads.
The proposed site has a lot of residential areas around so the working hours for the construction must
be considered for the project. This is to ensure that the residents are not being disturbed during odd
hours.
As for facilities around the site, the site is generally placed in a strategic location. There are
a number of schools namely, SJK(C) Kuen Cheng and Global Indian International School. Besides
schools, there are a variety of restaurants nearby which is convenient for the future residents. Apart
from that, a well-known event space that is The Glasshouse @ Seputeh is around the site. For
shopping malls, Mid Valley Megamall, a famous shopping mall in Klang Valley is nearby the site.
Thean Hou Temple is also nearby. It is one of the oldest and largest temples in Southeast Asia.
.
1.
Lastly, there is a lot of public transportation such as LRT, MRT and KTM. The site is just
few minutes away from The KL Sentral KTM Station and also Chan Sow Lin LRT Station. Other
than public transportation, the proposed site also has a great accessibility via the major highways in
Malaysia.
Figure 1.1.1 The proposed site labels in red as shown in the picture above
2.
1.2 Benchmark project
The benchmark project will be Sentral Suites @ KL Sentral, which also known as “Garden
in the city”. It has been selected due to a lot of similarities with our proposed project and it also in
line with our concept which to provide residents a modern city lifestyle and as a lush nature’s
sanctuary amidst the busy city. The developer of this project, MRCD invigorating their idea of
Transit Oriented Development (TOD) in developing this leading urban landmark.
Figure 1.2.1 shows the façade view of Sentral Suites
Figure 1.2.2 shows the aerial view of Sentral Suites
3.
Sentral Suites is a residential complex which completed by three apartment blocks and with
an area of 4.92 acres. The commencement date of this project is 3rd quarter of 2016 and the estimated
duration for overall project is about 5 years which mean will be complete on 1st quarter of 2021.
The first and second block will be the same which consist of 458 units while the third block consists
of 518 units and the bottom of residence will hold 41 retail units. The total of 1434 units of three
blocks in 43 floors will have 10 different types of unit to meet the demand of the public and it is
expected to be completed within 54 months.
Figure 1.2.3 shows the floor plans of different type of units
Sentral Suites has a strategic location which only takes five minutes of walking distance to
reach KL Sentral and can easily access to the major roads such as NPE, Federal Highway and
Mahameru. Other than that, it also surrounded by few major cities such as Bangsar, Petaling Jaya
and the city center which the residents can easily travel. Besides that, it also balanced all the elements
where workers and residents can have some entertainment such as shopping due to it is located
between several shopping malls and corporate office towers.
To meets the concept of a lush nature’s sanctuary, the developer has provided various
facilities in Sentral Suites. Besides of the themed and pocket garden feature, the residents are
4.
rewarded with various facilities such as jogging track, swimming pool, outdoor Jacuzzi, sauna, dance
studio, billiard room, multipurpose halls, Taichi deck, barbeque area, study room and basketball
court to fulfil the recreational needs of the residents. Not only adult, there also some outdoor game
facilities are provided for the children in the garden.
Figure 1.2.4 shows the podium facilities plan
The approximate price of this leasehold property is about RM1000 per square feet and the
listing price of the unit starts from RM730,000. After that, they also charge for maintenance fee
which is expected to be RM0.39 per square feet, including the sinking fund which is considered as
a reasonable charges provided with the density and the size of each unit.
In a nutshell, Sentral Suites is selected as out benchmark project due to the building concept
and also the strategic locations which are quite similar to our project. Both projects are surrounded
by commercial buildings and just a short distance to the public transport station. The easy access to
East-West Highway and Federal Highway also convenience to the residents of both condominiums.
5.
1.3 Proposed Building Design
The proposed building is a service apartment consists of 2 towers which are tower A and
tower B. The building has a total of 38 storeys and it is approximately 162m tall. The total GFA for
tower A is 23,721.71 m2 while tower B is 23,451.14 m2. It has a total of 404 residential units formed
by 188 typical units and 14 duplex units in each tower. Typical units are located from Level 8 to
Level 34 while duplex units are located from Level 35 to 38. There are 7 types of residential units
in each floor of both tower. The average GFA for tower A is 743m2 and Tower B is 734m2. The
floor to floor height for Level 8 to Level 37 is 3.4m high while Level 34 and Level 38 are 4.0m high.
Each floor contains 3 lift and 1 Bomba Lift. A refuse bin room and M&E room are provided on each
floor either.
The building consists of 7 levels of podium, 1 ground floor and 2 levels of basement. Podium
1 to Podium 6 are car park while Podium 7 are for facilities. Podium 1 to 6 and Basement 1 to 2 are
mainly for parking. The average GFA for each basement floor is approximately 3897m2 while the
podiums are approximately 3411m2 respectively. There are 477 parking lots from ground floor to
Podium 6 and 179 parking lots in Basement 1 and 2. The amount of parking lot should be sufficient
enough to meet the demand of the residents. At the ground floor level, water feature and water curtain
are provided for aesthetic purpose. Besides, lounge area is provided for the residents to relax and
enjoy themselves. There is a guard post to ensure the safety of the residents. There is also a refuse
collection point, nursery room, fire pump room along with other M&E rooms at the ground floor.
Podium 7 is the facilities level aims to provide entertainment and fun activities to the
residents. The facilities available are games room, playground, café, meeting room, audiovisual
room, sky jacuzzi, infinity pool, yoga deck, convenience store and more. The infinity pool is the
main highlight as it provides a very nice scenery of the surrounding landscape by creating a visual
effect of pool with no boundary. The residents can also relax at the café during tea time. While the
adults are busy, the children may enjoy themselves at the games room and playground designed
specifically for children. A convenience store is also provided so the residents do not have to go far
to buy some daily products.
7.
6.
At the roof facilities level, a roof garden, sky lounge and audiovisual room are provided at
each tower. The roof garden is provided for recreational and agricultural purposes. The roof garden
is a good place for the residents to relax while enjoying the greenery. Besides, the sky lounge
provides the residents a good place to grab a drink and enjoy the gorgeous landscape view
surrounding the building. As for the audiovisual room, residents may book the room earlier to stream
movies or to hold activities that requires broadcast services.
Podium & Basement Car Park Lounge area
Playground
8.
Cafe
Audiovisual room Sky Jacuzzi
Infinity pool Yoga deck
Roof garden Sky lounge
9.
1.4 Construction Technology, Methodology and Technique
1.4.1 Bored Pile
The type of piling proposed is bored pile as our building has no high rise building
surrounding it but there are still residential houses nearby. As our proposed building consists of an
average GFA for tower A is 743m2 and Tower B is 736m2, 2 level basement, one ground level, 6
podium and both towers have 38 storeys, so bored pile is suitable to be used in order to carry the
immense load of the vertical structure of the proposed building. As there are residential houses and
commercial buildings nearby, by using bored pile method, it creates less disruption to adjacent
structure as it reduces the vibrations and noise during installation of the pile. Therefore, bored pile
is very environmental friendly and is also widely used in urban area.
Figure 1.4.1 Bored Pile Stages
10.
1.4.2 Contiguous Bored Pile
As the proposed building has two levels of basement there it requires high support of
foundation. Therefore, contiguous bored pile is needed as closely spaced bored piles can be used to
form a retaining wall. This type of bored pile wall can be both temporary or permanent wall for
excavation where the advantages of contiguous bored pile is lower cost and speed in construction
for temporary and permanent wall where drilling conditions are conducive. Contiguous piles are
suitable in crowded urban areas, where traditional retaining methods would otherwise encroach the
adjoining properties, these piles restrict ground movements on the backfill side.
Figure 1.4.2 Contiguous Bored Pile
11.
1.4.3 Post-Tensioned Slab
In order to support the huge load form the podium levels, using post-tensioned slab can help
by withstanding the vast load. In simple words, Post tension slabs are normal slabs in which stresses
opposite to loads are introduced so that it can take more load than before. The advantages of post-
tensioned slab is that it helps in improving crack control and waterproofing properties – especially
beneficial for parking space and balconies. In addition, post-tensioned slabs are excellent way to
construct stronger structures at an affordable price where it can reduce the construction cost by
reducing the slab thickness. In view of life time cycle, it allows lower overall maintenance and life
cycle costs of the structure.
Figure 1.4.3 Post-tensioned Slab
12.
1.4.4 Plastic Formwork
The type of formwork proposed for our building is plastic formwork. Plastic formwork is
manufactured from specific grade of plastic. This formwork does not occur any chemical reactions
between poured materials and the plastic form therefore there will be no any patch or honeycomb
on the surface of reinforced concrete element. Plastic formwork is useful and suitable for large,
complex shape and special features. Additionally, it is light and any damages on the formwork can
be easily repaired. Nailing and oiling the formwork plates are not required prior as the auto leveling
of plugging system will make plates level automatically and it takes about 30% lesser time during
installing and dismantling compared with conventional form.
Besides that, it is water resistant and will not experience any deformation condition. It has
excellent corrosion resistant and if carefully transported and used, the availability time for plastic
formwork can be more than 100 times which makes it highly economical.
Figure 1.4.4 Plastic Formwork
1.4.5 Clay Façade
13.
In order to enhance the value and design aspect of building structure and offer building an
everlasting appeal at the same time, clay façade is an ideal choice. Clay façade is environmental
friendly and is known as a tough modern façade. This type of façade not only have beautiful
appearance but also have many advantages over other façade materials.
Clay façade can be the best fit material to build sustainable buildings as the concept of green
building is fast catching in nowadays construction industry. It has high energy efficient due to the
properties of thermal insulation that helps to keep heat away from entering inside the building and
maintain a comfort indoor temperature. Clay façade is also maintenance free and can easily prevent
rattling of the panels. Easy fixing is one of the characteristics of clay façade since there is no usage
of rout or sealants which helps in overcoming uneven surfaces and any appearance of cracks on the
walls.
Figure 1.4.5 Clay façade
1.4.6 Rainwater Harvesting System 14.
Water is an essential component in our daily life but we often taken for granted. In Malaysia,
we are blessed with an amply of water thanks to abundant rain, however, consumers only realize its
importance when there is water cut or water shortage incidents. Malaysian Government introduced
and implemented rainwater harvesting system to prevent crisis of water shortage happened in Klang
Valley in 1998.
Rainwater Harvesting System works by capturing water from both landscaped areas through
surface infiltration as from roof areas. The clean water is retained within the storage area away from
sunlight and heat, the water is readily for reuse. Rainwater harvesting system provides several
benefits such as it is easy to maintain as maintenance works require little time and lesser energy.
Secondly, the overall cost of installation and operation is much cheaper if compared to water
purifying and pumping system. Furthermore, this system reduces the demand on groundwater. The
population increase has led to depletion of groundwater gone significantly to low level in some areas
where will contribute to the problem of water scarcity.
Figure 1.4.6 Rainwater Harvesting System
1.5 Architectural Features 15.
1.5.1 Finishes for Basement/Podium
Description Floor Wall Ceiling
Driveway/Car Park PU Paint 19mm thick Plaster
and Emulsion Paint
Skim coat with Paint
Finish
M&E room 25mm thick Cement
Render
19mm thick Plaster
and Emulsion Paint
Skim coat with Paint
Finish
Loading area / BOH 25mm thick Cement
Render
19mm thick Plaster
and Emulsion Paint
Skim coat with Paint
Finish
Lounge 800mm x 800mm
Granite
800mm x 800mm
Granite
12mm thick
Moisture Resistant
Plaster Glass Board
Lift Lobby 800mm x 800mm
Granite
800mm x 800mm
Granite
12mm thick Fibrous
Plaster Glass Boards
Staircase 25mm thick Cement
Render with Nosing
Tiles
19mm thick Plaster
and Emulsion Paint
Skim coat with Paint
Finish
Staircase Lobby 300mm x 600mm
Homogeneous Tiles
19mm thick Plaster
and Emulsion Paint
Skim coat with Paint
Finish
1.5.2 Finishes for Tower A & B (Service Apartment)
16.
Service Apartment - Common Area
Description Floor Wall Ceiling
Loading Bay PU Paint 19mm thick Plaster
and Emulsion Paint
Skim coat with Paint
Finish
M&E room 25mm thick Cement
Render
19mm thick Plaster
and Emulsion Paint
Skim coat with Paint
Finish
BOH 25mm thick Cement
Render
19mm thick Plaster
and Emulsion Paint
Skim coat with Paint
Finish
Lounge 800mm x 800mm
Granite
800mm x 800mm
Granite
12mm thick Fibrous
Plaster Glass Boards
Lift Lobby 800mm x 800mm
Granite
800mm x 800mm
Granite
12mm thick Fibrous
Plaster Glass Boards
Staircase 25mm thick Cement
Render with Nosing
Tiles
19mm thick Plaster
and Emulsion Paint
Skim coat with Paint
Finish
17.
1.5.2 Finishes for Tower A & B (Service Apartment) (Cont’d)
Service Apartment - Unit
Description Floor Wall Ceiling
Living/Dining Timber Strips 19mm thick Plaster
and Emulsion Paint
12mm thick Fibrous
Plaster Glass Boards
Bedrooms Timber Strips 19mm thick Plaster
and Emulsion Paint
12mm thick Fibrous
Plaster Glass Boards
Bathrooms 800mm x 800mm
Granite
800mm x 800mm
Granite
12mm thick
Moisture Resistant
Plaster Glass Board
Yard 300mm x 600mm
Homogeneous Tiles
19mm thick Plaster
and Emulsion Paint
12mm thick Fibrous
Plaster Glass Boards
Kitchen 300mm x 600mm
Homogeneous Tiles
300mm x 600mm
Homogeneous Tiles
12mm thick Fibrous
Plaster Glass Boards
Maid Room Timber Strips 19mm thick Plaster
and Emulsion Paint
12mm thick Fibrous
Plaster Glass Boards
Powder Room 800mm x 800mm
Granite
800mm x 800mm
Granite
12mm thick
Moisture Resistant
Plaster Glass Board
Study Room Timber Strips 19mm thick Plaster
and Emulsion Paint
12mm thick Fibrous
Plaster Glass Boards
18.
PU Paint Cement Render Granite Tiles
Timber Strip Homogeneous Tiles
Above: Example of types of floor finishes used in this projects
Plaster & Paint Granite Tiles
Above: Example of types of wall finishes used in this projects
Skim coat & Paint Finish Moisture Resistant Plaster Glass Board Fibrous Plaster Glass Board
Above: Example of types of ceiling finishes used in this projects
19.
Summary of Construction Technology, Methodology and Technique
Bored Pile
● Suitable to carry
load of vertical
structure
● Less disruption to
adjacent
structures
● Environmental
friendly
Contiguous Bored Pile
● Suitable in crowded
urban area
● Restricts ground
movement at backfill
side
● Low cost and high
speed in construction
Post-Tensioned Slab
● Able to withstand vast
load
● Good in crack control
and waterproofing
● Lower maintenance
and life cycle cost
● Construction cost
based on slab thickness
Plastic Formwork
● For large, complex
shape and special
features
● Light and resist to
water and corrosion
● Quick installing and
dismantling
Clay Façade
● Environmental friendly
● High energy efficiency
● Low maintenance cost
● Can be fix easily
Rainwater Harvesting
System
● Easy to maintain
● Overall cost lower than
other system
● Free from scarcity of
water
20.
2.0 Preliminary Cost Appraisal
2.1 Definition of Areas
2.1.1 Construction Floor Area (CFA)
Construction Floor Area (CFA) generally covers areas of a building that are to be
constructed. CFA is measured to the outer face of the external walls of the building. CFA is measured
for the purpose of estimating the construction costs of a building.
2.1.2 Gross Floor Areas (GFA)
Gross Floor Area (GFA) is the total of all enclosed spaces fulfilling the functional
requirements of the building measured to the internal face of the enclosing walls. It includes areas
occupied by partitions, columns, internal structural or party walls, stairwells, lift wells etc.
Moreover, GFA also includes lift, plant, tank rooms etc. The sloping surfaces such as staircases and
ramps should be measured flat on plan. On the other hand, areas fulfilling the functional
requirements of the building which are not enclosed spaces, for instance open ground floors, open
covered ways, rooftop car parks, etc. are excluded and should be shown separately under
‘Unenclosed Spaces’.
2.1.3 Net Floor Area (NFA)
Net Floor Area (NFA) is known as the total of all saleable areas. NFA is measured within
the internal face of the enclosing wall. Areas such as common use area, services areas and circulation
areas are excluded from net floor area.
21.
Summary of Areas
LEVEL CFA (m2) GFA (m2) NFA (m2)
Basement Carpark 8,051.97 7,793.45 7,418.21
Podium Carpark 28,389.94 25,360.89 24,306.07
Tower A 26,509.71 23,721.71 21,601.73
Tower B 26,295.07 23,451.14 21,373.34
TOTAL 89,246.69 80,327.19 74,699.34
22.
2.2 Cost Plan
The cost plan is categorized into four parts, that are Basement Carpark, Podium Carpark,
Tower A and Tower B. Furthermore, cost plans for external works and ancillary works were also
prepared. The external works and ancillary works include road work, surface water drainage,
sewerage, water reticulation, fencing, hard and soft landscaping, refuse compactor, gym equipment,
water feature, playground, guard house, swimming pool, tennis and squash courts, sauna room and
vinyl decking.
In addition, the estimated construction cost of each element in the cost plan is build up by
multiplying the cost per GFA of the previous similar project and the total GFA of this project. The
total GFA for this project was obtained through measurement, using the BIM software, Glodon. For
the rates which are not in the previous similar project, the rates are build up from other previous
project BQ. The previous similar project is our benchmark project, that is a mid-end apartment
comprising of three blocks of 34-storey high apartment, along with 7-storey high podium carpark
and double storey basement carpark.
23.
3.0 Construction Cost
3.1 Overall Construction Cost Analysis
The estimated construction cost for the main building works is about RM137,570,726.91 excluding
the cost of the external works, preliminaries and contingencies. The summary for the cost allocation
at different part of the building is illustrated in the table and pie charts in the following:
Building CFA
(m2)
Cost per m2
of CFA
(RM/m2)
Estimated
Construction Cost
(RM)
Basement 8,052 1,650.44 13,289,377.88
Podium 28,390 9,38.85 26,653,922.64
Tower A 26,510 1,848.82 49,011,600.44
Tower B 26,295 1,848.86 48,615,825.95
Sub-Total
(Excluding External
Works, Preliminaries
and Contingencies)
89,246 1,541.47 137,570,726.91
Above: Cost summary for the Main Building Work.
24.
Above: Pie chart showing the percentage of cost allocation for Main Building Work
The pie chart above shows that the building has a higher amount of construction cost allocation (%)
for both of the towers, which is about 35.63% and 35.34%. The basement has a construction floor
area (CFA) of 8,052 m2 that amounts to 9.66% of the overall construction cost with a rate of
RM1,650.44 per m2 of CFA. The podium has the largest area of 28,390 m2 with a cost of RM938.85
per m2 of CFA. Tower A costs RM49 million while Tower B costs RM48.6 millionB due to the
Tower A has a bigger construction area around 200 m2 compare to Tower B.
25.
The total construction cost for the project is estimated to be about RM168,474,954.60 inclusive of
allowances made for external works, preliminaries, contingencies and cost escalation as shown in
the table below.
Item Estimated
Construction Cost
(RM)
Main Building Work 137,570,726.91
External Works & Landscape 1,953,045.00
Preliminaries (10%) 13,952,377.19
Contingencies (5%) 6,976,188.60
Sub-total 160,452,337.70
Cost Escalation 8,022,616.88
Total Estimated
Construction Cost
168,474,954.60
Above: Cost allocation for total development
26.
Above: Pie chart showing the percentage of cost allocation from total construction cost
According to the pie chart above, the main building works have occupied about 81.6% of the total
estimated construction cost which also constitute as the greatest portion. The allowances for external
works & landscape has contributes around 1.16% of the construction cost at RM1,953,045. Next, the
cost escalation of the project is estimated to be about RM8,022,616.88 based on a inflation rate of 5%
and assuming the tender would be called in one year’s time. Other than that, the preliminaries and
contingencies are allowed at approximately 8% and 4% respectively of the total construction cost. The
total development cost is estimated to be approximately RM168 million.
27.
Functional Elements Cost per m2 of
CFA (RM/m2)
Estimated Construction Cost
(RM)
Substructure 109.45 9,768,304.28
Structural Frame 558.50 49,843,878.75
Total Structural Cost 667.95 59,612,183.03
External Walling and Finishes 34.51 3,079,569.93
Roof covering and etc 10.63 948,471.45
Internal Walling 115.45 10,303,773.23
Internal Finishes 220.59 19,687,062.01
Fittings and etc 33.65 3,002,713.61
Total Architectural Cost 414.82 37,021,590.23
Services 458.69 40,936,953.65
Total M&E Cost 458.69 40,936,953.65
Total Estimated Construction Cost 1,541.47 137,570,726.91
Above: Table showing the estimated cost allocation for functional elements of the entire
building.
28.
Above: Pie chart showing the percentage of cost allocation for the entire building.
According to the pie chart above, structural works has the highest percentage of the total
estimated construction cost, which is 43.33% (substructure 7.10% and structural frame 36.23%).
The structural cost is high when compared to the architectural and M&E cost because the project
consists of elements such as contiguous bored piles, bored pile foundation, post-tensioned slab
system which consume a huge portion of construction cost. Besides, the pie chart shows that the
building has a very close amount of construction cost allocation (%) for both the architectural works
and services, which are 26.91% and 29.76% respectively.
29.
3.2 Basement
Functional Elements Cost per m2 of
CFA (RM/m2)
Estimated Construction Cost
(RM)
Substructure 717.00 5,773,271.92
Structural Frame 453.03 3,647,773.42
Total Structural Cost 1170.03 9,421,045.34
External Walling and Finishes 0.39 3,168.33
Roof covering and etc 6.56 52,820.34
Internal Walling 46.23 372,243.96
Internal Finishes 75.24 605,862.53
Fittings and etc 11.46 92,281.73
Total Architectural Cost 139.88 1,126,376.89
Services 340.53 2,741,955.64
Total M&E Cost 340.53 2,741,955.64
Total Estimated Construction Cost 1650.44 13,289,377.87
Above: Table showing the estimated cost allocation for functional elements of basement.
30.
Above: Pie chart showing the percentage of cost allocation for Basement.
For the distribution cost of a basement, the cost of structural works would generally be the
highest, followed by M&E and architectural works.
Based on the pie chart, the largest percentage is represented by the cost of structural works
which is about 70% (43.44% for substructure and 27.45% for structural frame). Structural works has
the highest cost due to the need to support the entire building and the construction of contiguous
bored piles. The architectural works took up 8.47% as it does not have any external finishes in the
basement so it is only the internal finishes for the car parks and driveways. Apart from that, the cost
percentage for M&E works is 20.63%.
31.
3.3 Podium
Functional Elements Cost per m2 of
CFA (RM/m2)
Estimated Construction Cost
(RM)
Substructure 140.72 3,995,032.36
Structural Frame 321.96 9,140,350.96
Total Structural Cost 462.68 13,135,383.32
External Walling and Finishes 19.08 541,772.15
Roof covering and etc 9.34 265,162.04
Internal Walling 62.11 1,763,157.85
Internal Finishes 103.95 2,951,002.86
Fittings and etc 11.31 321,219.33
Total Architectural Cost 205.79 5,842,314.23
Services 269.87 7,676,225.09
Total M&E Cost 269.87 7,676,225.09
Total Estimated Construction Cost 938.34 26,652,922.64
Above: Table showing the estimated cost allocation for functional elements of podium.
32.
Above: Pie chart showing the percentage of cost allocation for Podium.
As shown in the pie chart, among the total substructure element, substructure occupies
14.99% and structural frame consists 34.29%. Total architectural works and M&E works have nearly
the same amount of construction work.
21.92% of construction work is allocated to architectural cost and the rest of 28.80% of
construction cost used as M&E works as every podium level consists ancillary areas such as lift
lobby, service lift and riser rooms.
33.
3.4 Towers
Functional
Elements
Tower A Tower B
Cost per m2 of
CFA (RM/m2)
Estimated
Construction Cost
(RM)
Cost per m2 of
CFA (RM/m2)
Estimated
Construction
Cost (RM)
Substructure - - - -
Structural Frame 701.75 18,603,188.99 701.75 18,452,565.37
Total Structural
Cost
701.75 18,603,188.99 701.75 18,452,565.37
External Walling
and Finishes
48.00 1,272,466.08 48.00 1,262,163.36
Roof covering
and etc
11.94 316,525.94 11.94 313,963.14
Internal Walling 154.69 4,100,787.04 154.69 4,067,584.38
Internal Finishes 305.47 8,097,841.58 305.47 8,032,355.03
Fittings and etc 49.02 1,299,440.29 49.53 1,289,772.27
Total
Architectural
Cost
569.12 15,087,060.93 569.63 14,965,838.18
Services 577.95 15,321,350.52 577.96 15,197,422.40
Total M&E Cost 577.95 15,321,350.52 577.96 15,197,422.40
Total Estimated
Construction
Cost
1848.82 49,011,600.44 1849.34 48,615,825.95
Above: Table showing the estimated cost allocation for functional elements of Tower A and
Tower B.
34.
Above: Pie chart showing the percentage of cost allocation for Tower A.
35.
Above: Pie chart showing the percentage of cost allocation for Tower B.
Referring to the two pie charts above, both Tower A and Tower B occupy 37.96% for
structural frame. The construction cost allocated to architectural works and M&E works of both
tower occupy 30.79% and 31.26% respectively.
4.0 Conclusion 36.
No. Item CFA (m2) Rate (RM/m2) Total (RM)
1 Basement 8,052 1,650.44 13,289,377.88
2 Podium 28,390 9,38.85 26,653,922.64
3 Tower A 26,510 1,848.82 49,011,600.44
4 Tower B 26,295 1,848.86 48,615,825.95
Subtotal (No 1-4) 89,246 1,541.47 137,570,726.91
5 External Works &
Landscape
- - 1,953,045.00
6 Preliminaries - - 13,952,377.19
7 Contingencies - - 6,976,188.60
Subtotal (No 1-7) - - 160,452,337.70
8 Cost Escalation - - 8,022,616.88
Grand Total (1-8) - - 168,474,954.60
As a summary, the cost plan shown above shows the cost distributions for the various
portions of the building for easy analysis. The proposed project consists of 2 levels of basement car
park, 1 level of ground floor services floor, 6 levels of podium car park, 1 level of recreational
facilities and 2 blocks of 31 levels of serviced apartments. There are a total of 404 residential units
for each tower. There are also 477 parking lots from ground floor to Podium 6 and 179 parking lots
in Basement 1 and 2. The facilities provided in the building are games room, playground, café,
meeting room, audiovisual room, sky jacuzzi, infinity pool, yoga deck, convenience store and more.
37.
The total of CFA for entire construction project which consists of basement, podium, Tower
A and B is 89,246.69 m2 coming up to a total cost of RM137,570,726.91. With the addition of
external works and landscape, preliminaries and contingencies, the entire const adds up to
RM160,452,337.70. After adding up the cost escalation, the total cost of the entire construction
project is RM168,474,954,60.
In conclusion, with the strategic location, facilities and entertainment filled residences, along
with the high efficiency rate of the proposed project which is 93%, we conclude that this project is
very worth investing, promising in a high return in the future.
38.
5.0 References
Concrete Formwork & Types of Formwork |Shuttering | CivilDigital |. (2017, March 15). Retrieved
November 10, 2018, from https://civildigital.com/concrete-formwork-types-of-formwork/
Collins, M. (2000).Contiguous Bored Pile. Retrieved November 4, 2018, from
http://www.concrete.org.uk/fingertips-document.asp?id=351
Editor. (2015, November 27). Clay Facades over Exterior paints & Glass? Retrieved November 10,
2018, from http://gosmartbricks.com/why-clay-facades/
Formwork in Construction|Types|Applications of Shuttering | CivilDigital |. (2017, March 16).
Retrieved November 10, 2018, from https://civildigital.com/formwork-construction-types-
applications-shuttering/
Hamakareem, M. I. (2018, October 08). Plastic Formworks for Concrete Construction -
Applications and Advantage. Retrieved November 10, 2018, from
https://theconstructor.org/building/plastic-formworks-concrete-construction/15885/
Holmes. (2018). Bored Piles. Retrieved November 4, 2018, from
https://www.designingbuildings.co.uk/wiki/Bored_piles`
Keller (n.d.). Contiguous Bored Piles and Secant Piles. Retrieved November 4, 2018, from
http://resource-piling.com.sg/what-we-do/contiguous-bored-piles-and-secant-piles/
MPA(n.d.)Post-Tensioned(PT) Slab.. Retrieved November 4, 2018, from
https://www.concretecentre.com/Building-Elements/Floors/Post-Tension-(PT)-Slabs.aspx
39.
Ravishankar, R. (2015, March 18). Formwork construction in structures. Retrieved November 10,
2018, from https://www.slideshare.net/rithikarockingravishankar/formwork-construction-in-
structures
Rainwater Harvesting. (n.d.). Retrieved November 10, 2018, from
https://www.ecooutdoor.com.my/rainwater-harvesting/
Roger. (2008). Post-Tensioned Slab. Retrieved November 4, 2018, from
https://www.concreteconstruction.net/how-to/construction/post-tensioned-slabs_o
Sharma, S. (2017, August 21). Different Types Of Building Façade Cladding Systems To Know
About. Retrieved November 10, 2018, from http://gosmartbricks.com/different-types-of-building-
facade-cladding-systems-to-know-about/
40.

Mais conteúdo relacionado

Mais procurados

Building services report
Building services report Building services report
Building services report Soh Shing
 
Eca presentation-compile
Eca presentation-compileEca presentation-compile
Eca presentation-compileTimun Loh
 
Group Assignment:IBS System
Group Assignment:IBS SystemGroup Assignment:IBS System
Group Assignment:IBS System마 이환
 
Petronas twin towers malaysia
Petronas twin towers malaysiaPetronas twin towers malaysia
Petronas twin towers malaysiahumayoun shah
 
Construction Contract in Malaysia
Construction Contract in MalaysiaConstruction Contract in Malaysia
Construction Contract in MalaysiaDayat Mohamad
 
Measurement 4 Tender Document
Measurement 4 Tender Document Measurement 4 Tender Document
Measurement 4 Tender Document xingxin_GOh
 
High rise Office Building Technical Design Guidelines in Malaysia
High rise Office Building Technical Design Guidelines in MalaysiaHigh rise Office Building Technical Design Guidelines in Malaysia
High rise Office Building Technical Design Guidelines in MalaysiaZhao Wei Kim
 
Measurement II BQ
Measurement II BQMeasurement II BQ
Measurement II BQashleyyeap
 
Architecture Museum Malacca Dilapidation Report
Architecture Museum Malacca Dilapidation ReportArchitecture Museum Malacca Dilapidation Report
Architecture Museum Malacca Dilapidation ReportNaqiuddin Johari
 
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMAnep Botak
 
Building technology 1 "Industrialized Building System" IBS
Building technology 1 "Industrialized Building System" IBSBuilding technology 1 "Industrialized Building System" IBS
Building technology 1 "Industrialized Building System" IBSDigital Space Consultancy Ltd
 
Final Bills of Quantity
Final Bills of QuantityFinal Bills of Quantity
Final Bills of QuantityArissa Loh
 
HOW CONSERVATION WORKS TAKE PLACE IN MALAYSIA
HOW CONSERVATION WORKS TAKE PLACE IN MALAYSIAHOW CONSERVATION WORKS TAKE PLACE IN MALAYSIA
HOW CONSERVATION WORKS TAKE PLACE IN MALAYSIAFakhrul Afifi
 
Assignment - Preliminary Cost Appraisal
Assignment - Preliminary Cost AppraisalAssignment - Preliminary Cost Appraisal
Assignment - Preliminary Cost AppraisalKai Yun Pang
 
Construction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's UniversityConstruction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's UniversityPang Khai Shuen
 
Passive Fire Protection According to UBBL Malaysia
Passive Fire Protection According to UBBL MalaysiaPassive Fire Protection According to UBBL Malaysia
Passive Fire Protection According to UBBL MalaysiaZhao Wei Kim
 

Mais procurados (20)

Building services report
Building services report Building services report
Building services report
 
Eca presentation-compile
Eca presentation-compileEca presentation-compile
Eca presentation-compile
 
Group Assignment:IBS System
Group Assignment:IBS SystemGroup Assignment:IBS System
Group Assignment:IBS System
 
Petronas twin towers malaysia
Petronas twin towers malaysiaPetronas twin towers malaysia
Petronas twin towers malaysia
 
bs:copbs101
bs:copbs101bs:copbs101
bs:copbs101
 
Construction Contract in Malaysia
Construction Contract in MalaysiaConstruction Contract in Malaysia
Construction Contract in Malaysia
 
Measurement 4 Tender Document
Measurement 4 Tender Document Measurement 4 Tender Document
Measurement 4 Tender Document
 
High rise Office Building Technical Design Guidelines in Malaysia
High rise Office Building Technical Design Guidelines in MalaysiaHigh rise Office Building Technical Design Guidelines in Malaysia
High rise Office Building Technical Design Guidelines in Malaysia
 
Measurement II BQ
Measurement II BQMeasurement II BQ
Measurement II BQ
 
ECA form
ECA formECA form
ECA form
 
Architecture Museum Malacca Dilapidation Report
Architecture Museum Malacca Dilapidation ReportArchitecture Museum Malacca Dilapidation Report
Architecture Museum Malacca Dilapidation Report
 
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
 
Building technology 1 "Industrialized Building System" IBS
Building technology 1 "Industrialized Building System" IBSBuilding technology 1 "Industrialized Building System" IBS
Building technology 1 "Industrialized Building System" IBS
 
Final Bills of Quantity
Final Bills of QuantityFinal Bills of Quantity
Final Bills of Quantity
 
HOW CONSERVATION WORKS TAKE PLACE IN MALAYSIA
HOW CONSERVATION WORKS TAKE PLACE IN MALAYSIAHOW CONSERVATION WORKS TAKE PLACE IN MALAYSIA
HOW CONSERVATION WORKS TAKE PLACE IN MALAYSIA
 
Boq piling works
Boq   piling worksBoq   piling works
Boq piling works
 
Assignment - Preliminary Cost Appraisal
Assignment - Preliminary Cost AppraisalAssignment - Preliminary Cost Appraisal
Assignment - Preliminary Cost Appraisal
 
Construction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's UniversityConstruction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's University
 
Passive Fire Protection According to UBBL Malaysia
Passive Fire Protection According to UBBL MalaysiaPassive Fire Protection According to UBBL Malaysia
Passive Fire Protection According to UBBL Malaysia
 
UBBL 1984 pdf
UBBL 1984 pdfUBBL 1984 pdf
UBBL 1984 pdf
 

Semelhante a Building Economics Assignment Report

Building economic
Building economicBuilding economic
Building economictfkc1212
 
Building Economics Cost Plan Report
Building Economics Cost Plan ReportBuilding Economics Cost Plan Report
Building Economics Cost Plan ReportFarah Sham
 
Top hills midwest avenue simplified sales kit ver1.1
Top hills midwest avenue simplified sales kit ver1.1Top hills midwest avenue simplified sales kit ver1.1
Top hills midwest avenue simplified sales kit ver1.1Tophills Realty
 
Compiled report
Compiled reportCompiled report
Compiled reportlohwenjun
 
Project Management and Development Economics Project (PM)
Project Management and Development Economics Project (PM)Project Management and Development Economics Project (PM)
Project Management and Development Economics Project (PM)Pang Khai Shuen
 
Be cost appraisal
Be cost appraisalBe cost appraisal
Be cost appraisalLwj Welson
 
BE cost appraisal
BE cost appraisalBE cost appraisal
BE cost appraisalDoreen Yeo
 
Final submission be 2.0
Final submission be 2.0Final submission be 2.0
Final submission be 2.0ahmong4
 
Building Economics Report
Building Economics Report Building Economics Report
Building Economics Report Lin Hui
 
Be final report (1)
Be final report (1)Be final report (1)
Be final report (1)Jessyca Than
 
ICI Final Project
ICI Final ProjectICI Final Project
ICI Final ProjectLek Yuen
 
Mesiniaga final
Mesiniaga finalMesiniaga final
Mesiniaga finaladamtys
 
Mesiniaga final
Mesiniaga finalMesiniaga final
Mesiniaga finalYq Chong
 
Building economics final assignment report
Building economics final assignment reportBuilding economics final assignment report
Building economics final assignment reportlucaschinsheng
 
2016-0116_JShim Personal
2016-0116_JShim Personal2016-0116_JShim Personal
2016-0116_JShim PersonalJai Seong Shim
 
CENTRAL PARK - III SOHNA ROAD
CENTRAL PARK - III SOHNA ROAD CENTRAL PARK - III SOHNA ROAD
CENTRAL PARK - III SOHNA ROAD Md Alam Hashmi
 

Semelhante a Building Economics Assignment Report (20)

Building economic
Building economicBuilding economic
Building economic
 
Building Economics Cost Plan Report
Building Economics Cost Plan ReportBuilding Economics Cost Plan Report
Building Economics Cost Plan Report
 
BE Compiled
BE Compiled BE Compiled
BE Compiled
 
Top hills midwest avenue simplified sales kit ver1.1
Top hills midwest avenue simplified sales kit ver1.1Top hills midwest avenue simplified sales kit ver1.1
Top hills midwest avenue simplified sales kit ver1.1
 
Compiled report
Compiled reportCompiled report
Compiled report
 
Compiled report
Compiled reportCompiled report
Compiled report
 
Project Management and Development Economics Project (PM)
Project Management and Development Economics Project (PM)Project Management and Development Economics Project (PM)
Project Management and Development Economics Project (PM)
 
Be cost appraisal
Be cost appraisalBe cost appraisal
Be cost appraisal
 
BE cost appraisal
BE cost appraisalBE cost appraisal
BE cost appraisal
 
Final submission be 2.0
Final submission be 2.0Final submission be 2.0
Final submission be 2.0
 
Pm final
Pm finalPm final
Pm final
 
UHBC
UHBCUHBC
UHBC
 
Building Economics Report
Building Economics Report Building Economics Report
Building Economics Report
 
Be final report (1)
Be final report (1)Be final report (1)
Be final report (1)
 
ICI Final Project
ICI Final ProjectICI Final Project
ICI Final Project
 
Mesiniaga final
Mesiniaga finalMesiniaga final
Mesiniaga final
 
Mesiniaga final
Mesiniaga finalMesiniaga final
Mesiniaga final
 
Building economics final assignment report
Building economics final assignment reportBuilding economics final assignment report
Building economics final assignment report
 
2016-0116_JShim Personal
2016-0116_JShim Personal2016-0116_JShim Personal
2016-0116_JShim Personal
 
CENTRAL PARK - III SOHNA ROAD
CENTRAL PARK - III SOHNA ROAD CENTRAL PARK - III SOHNA ROAD
CENTRAL PARK - III SOHNA ROAD
 

Mais de ashleyyeap

CSI JOURNAL cover page
CSI JOURNAL cover pageCSI JOURNAL cover page
CSI JOURNAL cover pageashleyyeap
 
Fm group assignment
Fm group assignment Fm group assignment
Fm group assignment ashleyyeap
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-finalashleyyeap
 
PP2 final account assignment calculations
PP2 final account assignment calculationsPP2 final account assignment calculations
PP2 final account assignment calculationsashleyyeap
 
Fm august 2018 group assignment brief
Fm august 2018 group assignment briefFm august 2018 group assignment brief
Fm august 2018 group assignment briefashleyyeap
 
Building Economics Preliminary Cost Appraisal
Building Economics Preliminary Cost Appraisal Building Economics Preliminary Cost Appraisal
Building Economics Preliminary Cost Appraisal ashleyyeap
 
PP2 Seminar Presentation
PP2 Seminar PresentationPP2 Seminar Presentation
PP2 Seminar Presentationashleyyeap
 
Pp2 final account assignment excel
Pp2 final account assignment excelPp2 final account assignment excel
Pp2 final account assignment excelashleyyeap
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-finalashleyyeap
 
Pp2 coursework 2 201808
Pp2 coursework 2   201808Pp2 coursework 2   201808
Pp2 coursework 2 201808ashleyyeap
 
Measurement Assignment
Measurement AssignmentMeasurement Assignment
Measurement Assignmentashleyyeap
 
Professional Practice 1 Tutorial 3
Professional Practice 1 Tutorial 3Professional Practice 1 Tutorial 3
Professional Practice 1 Tutorial 3ashleyyeap
 
Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7ashleyyeap
 
Professional Practice I Assignment Slides
Professional Practice I Assignment SlidesProfessional Practice I Assignment Slides
Professional Practice I Assignment Slidesashleyyeap
 
Professional Practice I Assignment
Professional Practice I AssignmentProfessional Practice I Assignment
Professional Practice I Assignmentashleyyeap
 
Estimating Assignment
Estimating Assignment Estimating Assignment
Estimating Assignment ashleyyeap
 
Software Assignment
Software AssignmentSoftware Assignment
Software Assignmentashleyyeap
 
Management Science Assignment
Management Science Assignment Management Science Assignment
Management Science Assignment ashleyyeap
 
People Dynamics Individual Assignment - Case Study
People Dynamics Individual Assignment - Case StudyPeople Dynamics Individual Assignment - Case Study
People Dynamics Individual Assignment - Case Studyashleyyeap
 

Mais de ashleyyeap (20)

CSI JOURNAL cover page
CSI JOURNAL cover pageCSI JOURNAL cover page
CSI JOURNAL cover page
 
CSI JOURNAL
CSI JOURNALCSI JOURNAL
CSI JOURNAL
 
Fm group assignment
Fm group assignment Fm group assignment
Fm group assignment
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-final
 
PP2 final account assignment calculations
PP2 final account assignment calculationsPP2 final account assignment calculations
PP2 final account assignment calculations
 
Fm august 2018 group assignment brief
Fm august 2018 group assignment briefFm august 2018 group assignment brief
Fm august 2018 group assignment brief
 
Building Economics Preliminary Cost Appraisal
Building Economics Preliminary Cost Appraisal Building Economics Preliminary Cost Appraisal
Building Economics Preliminary Cost Appraisal
 
PP2 Seminar Presentation
PP2 Seminar PresentationPP2 Seminar Presentation
PP2 Seminar Presentation
 
Pp2 final account assignment excel
Pp2 final account assignment excelPp2 final account assignment excel
Pp2 final account assignment excel
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-final
 
Pp2 coursework 2 201808
Pp2 coursework 2   201808Pp2 coursework 2   201808
Pp2 coursework 2 201808
 
Measurement Assignment
Measurement AssignmentMeasurement Assignment
Measurement Assignment
 
Professional Practice 1 Tutorial 3
Professional Practice 1 Tutorial 3Professional Practice 1 Tutorial 3
Professional Practice 1 Tutorial 3
 
Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7
 
Professional Practice I Assignment Slides
Professional Practice I Assignment SlidesProfessional Practice I Assignment Slides
Professional Practice I Assignment Slides
 
Professional Practice I Assignment
Professional Practice I AssignmentProfessional Practice I Assignment
Professional Practice I Assignment
 
Estimating Assignment
Estimating Assignment Estimating Assignment
Estimating Assignment
 
Software Assignment
Software AssignmentSoftware Assignment
Software Assignment
 
Management Science Assignment
Management Science Assignment Management Science Assignment
Management Science Assignment
 
People Dynamics Individual Assignment - Case Study
People Dynamics Individual Assignment - Case StudyPeople Dynamics Individual Assignment - Case Study
People Dynamics Individual Assignment - Case Study
 

Último

The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhikauryashika82
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfAyushMahapatra5
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingTeacherCyreneCayanan
 
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...Sapna Thakur
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room servicediscovermytutordmt
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsTechSoup
 
General AI for Medical Educators April 2024
General AI for Medical Educators April 2024General AI for Medical Educators April 2024
General AI for Medical Educators April 2024Janet Corral
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactPECB
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxVishalSingh1417
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 

Último (20)

Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdf
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writing
 
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room service
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
General AI for Medical Educators April 2024
General AI for Medical Educators April 2024General AI for Medical Educators April 2024
General AI for Medical Educators April 2024
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 

Building Economics Assignment Report

  • 1. SCHOOL OF ARCHITECTURE, BUILDING AND DESIGN BACHELOR OF QUANTITY SURVEYING (HONOURS) AUGUST 2018 BUILDING ECONOMICS ASSIGNMENT Lecturer : Sr Shirley Chin Ai Ling Pn. Nurulhuda Hashim Submission Date : 19th November 2018 Group Members : NO. STUDENT NAME STUDENT ID 1 YEAP PHAY SHIAN 0322243 2 TAN VIN NIE 0323706 3 TEY CHENG FERN 0323912 4 TAN JIA SAN 0322406 5 TIO CHONG ZHI 0328134 6 KENNETH TAN SIN KWANG 0322482 7 NG SHENG ZHE 0323830 8 TEOH ZI WEI 0323372
  • 2. TABLE OF CONTENTS NO. CONTENT PAGE 1.0 Introduction 1.1 Location of the Site 1 1.2 Benchmark Project 3 1.3 Proposed Building Design 6 1.4 Construction Technology, Methodology & Techniques 10 1.5 Architectural Features 16 2.0 Preliminary Cost Appraisal 2.1 Definition of Areas 21 2.2 Cost Plan 23 3.0 Construction Cost 3.1 Overall Construction Cost Analysis 24 3.2 Basement 30 3.3 Podium 32 3.4 Tower A & B 34 4.0 Conclusion 37 5.0 References 39 6.0 Appendices
  • 3. 1.0 Introduction 1.1 Location The proposed site is located at Lot 160, Jalan Robson, Jalan Syed Putra, Kuala Lumpur where it is chosen by the client in the center of Kuala Lumpur. It is strategically located at the prestigious location at Seputeh. The site covers an area of 1.43 acres of freehold land. The immediate vicinity is a residential area of mixed proportion between low-rise and high-rise construction. Most of the land used is dedicated to low rise construction and low density apartments. However, observations show that the residency is in proximity to Jalan Syed Putra where existing roads to and fro the site, therefore no temporary roadways have to be built. This proposed project is expected to be a vibrant, environmental friendly and economic development. The proposed site has existing roads, and this will ease the process of starting the project as there is already an entry and exit to the site. Therefore, there is no need to construct temporary roads. The proposed site has a lot of residential areas around so the working hours for the construction must be considered for the project. This is to ensure that the residents are not being disturbed during odd hours. As for facilities around the site, the site is generally placed in a strategic location. There are a number of schools namely, SJK(C) Kuen Cheng and Global Indian International School. Besides schools, there are a variety of restaurants nearby which is convenient for the future residents. Apart from that, a well-known event space that is The Glasshouse @ Seputeh is around the site. For shopping malls, Mid Valley Megamall, a famous shopping mall in Klang Valley is nearby the site. Thean Hou Temple is also nearby. It is one of the oldest and largest temples in Southeast Asia. . 1.
  • 4. Lastly, there is a lot of public transportation such as LRT, MRT and KTM. The site is just few minutes away from The KL Sentral KTM Station and also Chan Sow Lin LRT Station. Other than public transportation, the proposed site also has a great accessibility via the major highways in Malaysia. Figure 1.1.1 The proposed site labels in red as shown in the picture above 2.
  • 5. 1.2 Benchmark project The benchmark project will be Sentral Suites @ KL Sentral, which also known as “Garden in the city”. It has been selected due to a lot of similarities with our proposed project and it also in line with our concept which to provide residents a modern city lifestyle and as a lush nature’s sanctuary amidst the busy city. The developer of this project, MRCD invigorating their idea of Transit Oriented Development (TOD) in developing this leading urban landmark. Figure 1.2.1 shows the façade view of Sentral Suites Figure 1.2.2 shows the aerial view of Sentral Suites 3.
  • 6. Sentral Suites is a residential complex which completed by three apartment blocks and with an area of 4.92 acres. The commencement date of this project is 3rd quarter of 2016 and the estimated duration for overall project is about 5 years which mean will be complete on 1st quarter of 2021. The first and second block will be the same which consist of 458 units while the third block consists of 518 units and the bottom of residence will hold 41 retail units. The total of 1434 units of three blocks in 43 floors will have 10 different types of unit to meet the demand of the public and it is expected to be completed within 54 months. Figure 1.2.3 shows the floor plans of different type of units Sentral Suites has a strategic location which only takes five minutes of walking distance to reach KL Sentral and can easily access to the major roads such as NPE, Federal Highway and Mahameru. Other than that, it also surrounded by few major cities such as Bangsar, Petaling Jaya and the city center which the residents can easily travel. Besides that, it also balanced all the elements where workers and residents can have some entertainment such as shopping due to it is located between several shopping malls and corporate office towers. To meets the concept of a lush nature’s sanctuary, the developer has provided various facilities in Sentral Suites. Besides of the themed and pocket garden feature, the residents are 4.
  • 7. rewarded with various facilities such as jogging track, swimming pool, outdoor Jacuzzi, sauna, dance studio, billiard room, multipurpose halls, Taichi deck, barbeque area, study room and basketball court to fulfil the recreational needs of the residents. Not only adult, there also some outdoor game facilities are provided for the children in the garden. Figure 1.2.4 shows the podium facilities plan The approximate price of this leasehold property is about RM1000 per square feet and the listing price of the unit starts from RM730,000. After that, they also charge for maintenance fee which is expected to be RM0.39 per square feet, including the sinking fund which is considered as a reasonable charges provided with the density and the size of each unit. In a nutshell, Sentral Suites is selected as out benchmark project due to the building concept and also the strategic locations which are quite similar to our project. Both projects are surrounded by commercial buildings and just a short distance to the public transport station. The easy access to East-West Highway and Federal Highway also convenience to the residents of both condominiums. 5.
  • 8.
  • 9. 1.3 Proposed Building Design The proposed building is a service apartment consists of 2 towers which are tower A and tower B. The building has a total of 38 storeys and it is approximately 162m tall. The total GFA for tower A is 23,721.71 m2 while tower B is 23,451.14 m2. It has a total of 404 residential units formed by 188 typical units and 14 duplex units in each tower. Typical units are located from Level 8 to Level 34 while duplex units are located from Level 35 to 38. There are 7 types of residential units in each floor of both tower. The average GFA for tower A is 743m2 and Tower B is 734m2. The floor to floor height for Level 8 to Level 37 is 3.4m high while Level 34 and Level 38 are 4.0m high. Each floor contains 3 lift and 1 Bomba Lift. A refuse bin room and M&E room are provided on each floor either. The building consists of 7 levels of podium, 1 ground floor and 2 levels of basement. Podium 1 to Podium 6 are car park while Podium 7 are for facilities. Podium 1 to 6 and Basement 1 to 2 are mainly for parking. The average GFA for each basement floor is approximately 3897m2 while the podiums are approximately 3411m2 respectively. There are 477 parking lots from ground floor to Podium 6 and 179 parking lots in Basement 1 and 2. The amount of parking lot should be sufficient enough to meet the demand of the residents. At the ground floor level, water feature and water curtain are provided for aesthetic purpose. Besides, lounge area is provided for the residents to relax and enjoy themselves. There is a guard post to ensure the safety of the residents. There is also a refuse collection point, nursery room, fire pump room along with other M&E rooms at the ground floor. Podium 7 is the facilities level aims to provide entertainment and fun activities to the residents. The facilities available are games room, playground, café, meeting room, audiovisual room, sky jacuzzi, infinity pool, yoga deck, convenience store and more. The infinity pool is the main highlight as it provides a very nice scenery of the surrounding landscape by creating a visual effect of pool with no boundary. The residents can also relax at the café during tea time. While the adults are busy, the children may enjoy themselves at the games room and playground designed specifically for children. A convenience store is also provided so the residents do not have to go far to buy some daily products. 7. 6.
  • 10. At the roof facilities level, a roof garden, sky lounge and audiovisual room are provided at each tower. The roof garden is provided for recreational and agricultural purposes. The roof garden is a good place for the residents to relax while enjoying the greenery. Besides, the sky lounge provides the residents a good place to grab a drink and enjoy the gorgeous landscape view surrounding the building. As for the audiovisual room, residents may book the room earlier to stream movies or to hold activities that requires broadcast services. Podium & Basement Car Park Lounge area Playground 8. Cafe
  • 11. Audiovisual room Sky Jacuzzi Infinity pool Yoga deck Roof garden Sky lounge 9.
  • 12. 1.4 Construction Technology, Methodology and Technique 1.4.1 Bored Pile The type of piling proposed is bored pile as our building has no high rise building surrounding it but there are still residential houses nearby. As our proposed building consists of an average GFA for tower A is 743m2 and Tower B is 736m2, 2 level basement, one ground level, 6 podium and both towers have 38 storeys, so bored pile is suitable to be used in order to carry the immense load of the vertical structure of the proposed building. As there are residential houses and commercial buildings nearby, by using bored pile method, it creates less disruption to adjacent structure as it reduces the vibrations and noise during installation of the pile. Therefore, bored pile is very environmental friendly and is also widely used in urban area. Figure 1.4.1 Bored Pile Stages 10.
  • 13. 1.4.2 Contiguous Bored Pile As the proposed building has two levels of basement there it requires high support of foundation. Therefore, contiguous bored pile is needed as closely spaced bored piles can be used to form a retaining wall. This type of bored pile wall can be both temporary or permanent wall for excavation where the advantages of contiguous bored pile is lower cost and speed in construction for temporary and permanent wall where drilling conditions are conducive. Contiguous piles are suitable in crowded urban areas, where traditional retaining methods would otherwise encroach the adjoining properties, these piles restrict ground movements on the backfill side. Figure 1.4.2 Contiguous Bored Pile 11.
  • 14. 1.4.3 Post-Tensioned Slab In order to support the huge load form the podium levels, using post-tensioned slab can help by withstanding the vast load. In simple words, Post tension slabs are normal slabs in which stresses opposite to loads are introduced so that it can take more load than before. The advantages of post- tensioned slab is that it helps in improving crack control and waterproofing properties – especially beneficial for parking space and balconies. In addition, post-tensioned slabs are excellent way to construct stronger structures at an affordable price where it can reduce the construction cost by reducing the slab thickness. In view of life time cycle, it allows lower overall maintenance and life cycle costs of the structure. Figure 1.4.3 Post-tensioned Slab 12.
  • 15. 1.4.4 Plastic Formwork The type of formwork proposed for our building is plastic formwork. Plastic formwork is manufactured from specific grade of plastic. This formwork does not occur any chemical reactions between poured materials and the plastic form therefore there will be no any patch or honeycomb on the surface of reinforced concrete element. Plastic formwork is useful and suitable for large, complex shape and special features. Additionally, it is light and any damages on the formwork can be easily repaired. Nailing and oiling the formwork plates are not required prior as the auto leveling of plugging system will make plates level automatically and it takes about 30% lesser time during installing and dismantling compared with conventional form. Besides that, it is water resistant and will not experience any deformation condition. It has excellent corrosion resistant and if carefully transported and used, the availability time for plastic formwork can be more than 100 times which makes it highly economical. Figure 1.4.4 Plastic Formwork 1.4.5 Clay Façade 13.
  • 16. In order to enhance the value and design aspect of building structure and offer building an everlasting appeal at the same time, clay façade is an ideal choice. Clay façade is environmental friendly and is known as a tough modern façade. This type of façade not only have beautiful appearance but also have many advantages over other façade materials. Clay façade can be the best fit material to build sustainable buildings as the concept of green building is fast catching in nowadays construction industry. It has high energy efficient due to the properties of thermal insulation that helps to keep heat away from entering inside the building and maintain a comfort indoor temperature. Clay façade is also maintenance free and can easily prevent rattling of the panels. Easy fixing is one of the characteristics of clay façade since there is no usage of rout or sealants which helps in overcoming uneven surfaces and any appearance of cracks on the walls. Figure 1.4.5 Clay façade 1.4.6 Rainwater Harvesting System 14.
  • 17. Water is an essential component in our daily life but we often taken for granted. In Malaysia, we are blessed with an amply of water thanks to abundant rain, however, consumers only realize its importance when there is water cut or water shortage incidents. Malaysian Government introduced and implemented rainwater harvesting system to prevent crisis of water shortage happened in Klang Valley in 1998. Rainwater Harvesting System works by capturing water from both landscaped areas through surface infiltration as from roof areas. The clean water is retained within the storage area away from sunlight and heat, the water is readily for reuse. Rainwater harvesting system provides several benefits such as it is easy to maintain as maintenance works require little time and lesser energy. Secondly, the overall cost of installation and operation is much cheaper if compared to water purifying and pumping system. Furthermore, this system reduces the demand on groundwater. The population increase has led to depletion of groundwater gone significantly to low level in some areas where will contribute to the problem of water scarcity. Figure 1.4.6 Rainwater Harvesting System 1.5 Architectural Features 15.
  • 18. 1.5.1 Finishes for Basement/Podium Description Floor Wall Ceiling Driveway/Car Park PU Paint 19mm thick Plaster and Emulsion Paint Skim coat with Paint Finish M&E room 25mm thick Cement Render 19mm thick Plaster and Emulsion Paint Skim coat with Paint Finish Loading area / BOH 25mm thick Cement Render 19mm thick Plaster and Emulsion Paint Skim coat with Paint Finish Lounge 800mm x 800mm Granite 800mm x 800mm Granite 12mm thick Moisture Resistant Plaster Glass Board Lift Lobby 800mm x 800mm Granite 800mm x 800mm Granite 12mm thick Fibrous Plaster Glass Boards Staircase 25mm thick Cement Render with Nosing Tiles 19mm thick Plaster and Emulsion Paint Skim coat with Paint Finish Staircase Lobby 300mm x 600mm Homogeneous Tiles 19mm thick Plaster and Emulsion Paint Skim coat with Paint Finish 1.5.2 Finishes for Tower A & B (Service Apartment) 16.
  • 19. Service Apartment - Common Area Description Floor Wall Ceiling Loading Bay PU Paint 19mm thick Plaster and Emulsion Paint Skim coat with Paint Finish M&E room 25mm thick Cement Render 19mm thick Plaster and Emulsion Paint Skim coat with Paint Finish BOH 25mm thick Cement Render 19mm thick Plaster and Emulsion Paint Skim coat with Paint Finish Lounge 800mm x 800mm Granite 800mm x 800mm Granite 12mm thick Fibrous Plaster Glass Boards Lift Lobby 800mm x 800mm Granite 800mm x 800mm Granite 12mm thick Fibrous Plaster Glass Boards Staircase 25mm thick Cement Render with Nosing Tiles 19mm thick Plaster and Emulsion Paint Skim coat with Paint Finish 17.
  • 20. 1.5.2 Finishes for Tower A & B (Service Apartment) (Cont’d) Service Apartment - Unit Description Floor Wall Ceiling Living/Dining Timber Strips 19mm thick Plaster and Emulsion Paint 12mm thick Fibrous Plaster Glass Boards Bedrooms Timber Strips 19mm thick Plaster and Emulsion Paint 12mm thick Fibrous Plaster Glass Boards Bathrooms 800mm x 800mm Granite 800mm x 800mm Granite 12mm thick Moisture Resistant Plaster Glass Board Yard 300mm x 600mm Homogeneous Tiles 19mm thick Plaster and Emulsion Paint 12mm thick Fibrous Plaster Glass Boards Kitchen 300mm x 600mm Homogeneous Tiles 300mm x 600mm Homogeneous Tiles 12mm thick Fibrous Plaster Glass Boards Maid Room Timber Strips 19mm thick Plaster and Emulsion Paint 12mm thick Fibrous Plaster Glass Boards Powder Room 800mm x 800mm Granite 800mm x 800mm Granite 12mm thick Moisture Resistant Plaster Glass Board Study Room Timber Strips 19mm thick Plaster and Emulsion Paint 12mm thick Fibrous Plaster Glass Boards 18.
  • 21. PU Paint Cement Render Granite Tiles Timber Strip Homogeneous Tiles Above: Example of types of floor finishes used in this projects Plaster & Paint Granite Tiles Above: Example of types of wall finishes used in this projects Skim coat & Paint Finish Moisture Resistant Plaster Glass Board Fibrous Plaster Glass Board Above: Example of types of ceiling finishes used in this projects 19.
  • 22. Summary of Construction Technology, Methodology and Technique Bored Pile ● Suitable to carry load of vertical structure ● Less disruption to adjacent structures ● Environmental friendly Contiguous Bored Pile ● Suitable in crowded urban area ● Restricts ground movement at backfill side ● Low cost and high speed in construction Post-Tensioned Slab ● Able to withstand vast load ● Good in crack control and waterproofing ● Lower maintenance and life cycle cost ● Construction cost based on slab thickness Plastic Formwork ● For large, complex shape and special features ● Light and resist to water and corrosion ● Quick installing and dismantling Clay Façade ● Environmental friendly ● High energy efficiency ● Low maintenance cost ● Can be fix easily Rainwater Harvesting System ● Easy to maintain ● Overall cost lower than other system ● Free from scarcity of water 20.
  • 23. 2.0 Preliminary Cost Appraisal 2.1 Definition of Areas 2.1.1 Construction Floor Area (CFA) Construction Floor Area (CFA) generally covers areas of a building that are to be constructed. CFA is measured to the outer face of the external walls of the building. CFA is measured for the purpose of estimating the construction costs of a building. 2.1.2 Gross Floor Areas (GFA) Gross Floor Area (GFA) is the total of all enclosed spaces fulfilling the functional requirements of the building measured to the internal face of the enclosing walls. It includes areas occupied by partitions, columns, internal structural or party walls, stairwells, lift wells etc. Moreover, GFA also includes lift, plant, tank rooms etc. The sloping surfaces such as staircases and ramps should be measured flat on plan. On the other hand, areas fulfilling the functional requirements of the building which are not enclosed spaces, for instance open ground floors, open covered ways, rooftop car parks, etc. are excluded and should be shown separately under ‘Unenclosed Spaces’. 2.1.3 Net Floor Area (NFA) Net Floor Area (NFA) is known as the total of all saleable areas. NFA is measured within the internal face of the enclosing wall. Areas such as common use area, services areas and circulation areas are excluded from net floor area. 21.
  • 24. Summary of Areas LEVEL CFA (m2) GFA (m2) NFA (m2) Basement Carpark 8,051.97 7,793.45 7,418.21 Podium Carpark 28,389.94 25,360.89 24,306.07 Tower A 26,509.71 23,721.71 21,601.73 Tower B 26,295.07 23,451.14 21,373.34 TOTAL 89,246.69 80,327.19 74,699.34 22.
  • 25. 2.2 Cost Plan The cost plan is categorized into four parts, that are Basement Carpark, Podium Carpark, Tower A and Tower B. Furthermore, cost plans for external works and ancillary works were also prepared. The external works and ancillary works include road work, surface water drainage, sewerage, water reticulation, fencing, hard and soft landscaping, refuse compactor, gym equipment, water feature, playground, guard house, swimming pool, tennis and squash courts, sauna room and vinyl decking. In addition, the estimated construction cost of each element in the cost plan is build up by multiplying the cost per GFA of the previous similar project and the total GFA of this project. The total GFA for this project was obtained through measurement, using the BIM software, Glodon. For the rates which are not in the previous similar project, the rates are build up from other previous project BQ. The previous similar project is our benchmark project, that is a mid-end apartment comprising of three blocks of 34-storey high apartment, along with 7-storey high podium carpark and double storey basement carpark. 23.
  • 26. 3.0 Construction Cost 3.1 Overall Construction Cost Analysis The estimated construction cost for the main building works is about RM137,570,726.91 excluding the cost of the external works, preliminaries and contingencies. The summary for the cost allocation at different part of the building is illustrated in the table and pie charts in the following: Building CFA (m2) Cost per m2 of CFA (RM/m2) Estimated Construction Cost (RM) Basement 8,052 1,650.44 13,289,377.88 Podium 28,390 9,38.85 26,653,922.64 Tower A 26,510 1,848.82 49,011,600.44 Tower B 26,295 1,848.86 48,615,825.95 Sub-Total (Excluding External Works, Preliminaries and Contingencies) 89,246 1,541.47 137,570,726.91 Above: Cost summary for the Main Building Work. 24.
  • 27. Above: Pie chart showing the percentage of cost allocation for Main Building Work The pie chart above shows that the building has a higher amount of construction cost allocation (%) for both of the towers, which is about 35.63% and 35.34%. The basement has a construction floor area (CFA) of 8,052 m2 that amounts to 9.66% of the overall construction cost with a rate of RM1,650.44 per m2 of CFA. The podium has the largest area of 28,390 m2 with a cost of RM938.85 per m2 of CFA. Tower A costs RM49 million while Tower B costs RM48.6 millionB due to the Tower A has a bigger construction area around 200 m2 compare to Tower B. 25.
  • 28. The total construction cost for the project is estimated to be about RM168,474,954.60 inclusive of allowances made for external works, preliminaries, contingencies and cost escalation as shown in the table below. Item Estimated Construction Cost (RM) Main Building Work 137,570,726.91 External Works & Landscape 1,953,045.00 Preliminaries (10%) 13,952,377.19 Contingencies (5%) 6,976,188.60 Sub-total 160,452,337.70 Cost Escalation 8,022,616.88 Total Estimated Construction Cost 168,474,954.60 Above: Cost allocation for total development 26.
  • 29. Above: Pie chart showing the percentage of cost allocation from total construction cost According to the pie chart above, the main building works have occupied about 81.6% of the total estimated construction cost which also constitute as the greatest portion. The allowances for external works & landscape has contributes around 1.16% of the construction cost at RM1,953,045. Next, the cost escalation of the project is estimated to be about RM8,022,616.88 based on a inflation rate of 5% and assuming the tender would be called in one year’s time. Other than that, the preliminaries and contingencies are allowed at approximately 8% and 4% respectively of the total construction cost. The total development cost is estimated to be approximately RM168 million. 27.
  • 30. Functional Elements Cost per m2 of CFA (RM/m2) Estimated Construction Cost (RM) Substructure 109.45 9,768,304.28 Structural Frame 558.50 49,843,878.75 Total Structural Cost 667.95 59,612,183.03 External Walling and Finishes 34.51 3,079,569.93 Roof covering and etc 10.63 948,471.45 Internal Walling 115.45 10,303,773.23 Internal Finishes 220.59 19,687,062.01 Fittings and etc 33.65 3,002,713.61 Total Architectural Cost 414.82 37,021,590.23 Services 458.69 40,936,953.65 Total M&E Cost 458.69 40,936,953.65 Total Estimated Construction Cost 1,541.47 137,570,726.91 Above: Table showing the estimated cost allocation for functional elements of the entire building. 28.
  • 31. Above: Pie chart showing the percentage of cost allocation for the entire building. According to the pie chart above, structural works has the highest percentage of the total estimated construction cost, which is 43.33% (substructure 7.10% and structural frame 36.23%). The structural cost is high when compared to the architectural and M&E cost because the project consists of elements such as contiguous bored piles, bored pile foundation, post-tensioned slab system which consume a huge portion of construction cost. Besides, the pie chart shows that the building has a very close amount of construction cost allocation (%) for both the architectural works and services, which are 26.91% and 29.76% respectively. 29.
  • 32. 3.2 Basement Functional Elements Cost per m2 of CFA (RM/m2) Estimated Construction Cost (RM) Substructure 717.00 5,773,271.92 Structural Frame 453.03 3,647,773.42 Total Structural Cost 1170.03 9,421,045.34 External Walling and Finishes 0.39 3,168.33 Roof covering and etc 6.56 52,820.34 Internal Walling 46.23 372,243.96 Internal Finishes 75.24 605,862.53 Fittings and etc 11.46 92,281.73 Total Architectural Cost 139.88 1,126,376.89 Services 340.53 2,741,955.64 Total M&E Cost 340.53 2,741,955.64 Total Estimated Construction Cost 1650.44 13,289,377.87 Above: Table showing the estimated cost allocation for functional elements of basement. 30.
  • 33. Above: Pie chart showing the percentage of cost allocation for Basement. For the distribution cost of a basement, the cost of structural works would generally be the highest, followed by M&E and architectural works. Based on the pie chart, the largest percentage is represented by the cost of structural works which is about 70% (43.44% for substructure and 27.45% for structural frame). Structural works has the highest cost due to the need to support the entire building and the construction of contiguous bored piles. The architectural works took up 8.47% as it does not have any external finishes in the basement so it is only the internal finishes for the car parks and driveways. Apart from that, the cost percentage for M&E works is 20.63%. 31.
  • 34. 3.3 Podium Functional Elements Cost per m2 of CFA (RM/m2) Estimated Construction Cost (RM) Substructure 140.72 3,995,032.36 Structural Frame 321.96 9,140,350.96 Total Structural Cost 462.68 13,135,383.32 External Walling and Finishes 19.08 541,772.15 Roof covering and etc 9.34 265,162.04 Internal Walling 62.11 1,763,157.85 Internal Finishes 103.95 2,951,002.86 Fittings and etc 11.31 321,219.33 Total Architectural Cost 205.79 5,842,314.23 Services 269.87 7,676,225.09 Total M&E Cost 269.87 7,676,225.09 Total Estimated Construction Cost 938.34 26,652,922.64 Above: Table showing the estimated cost allocation for functional elements of podium. 32.
  • 35. Above: Pie chart showing the percentage of cost allocation for Podium. As shown in the pie chart, among the total substructure element, substructure occupies 14.99% and structural frame consists 34.29%. Total architectural works and M&E works have nearly the same amount of construction work. 21.92% of construction work is allocated to architectural cost and the rest of 28.80% of construction cost used as M&E works as every podium level consists ancillary areas such as lift lobby, service lift and riser rooms. 33.
  • 36. 3.4 Towers Functional Elements Tower A Tower B Cost per m2 of CFA (RM/m2) Estimated Construction Cost (RM) Cost per m2 of CFA (RM/m2) Estimated Construction Cost (RM) Substructure - - - - Structural Frame 701.75 18,603,188.99 701.75 18,452,565.37 Total Structural Cost 701.75 18,603,188.99 701.75 18,452,565.37 External Walling and Finishes 48.00 1,272,466.08 48.00 1,262,163.36 Roof covering and etc 11.94 316,525.94 11.94 313,963.14 Internal Walling 154.69 4,100,787.04 154.69 4,067,584.38 Internal Finishes 305.47 8,097,841.58 305.47 8,032,355.03 Fittings and etc 49.02 1,299,440.29 49.53 1,289,772.27 Total Architectural Cost 569.12 15,087,060.93 569.63 14,965,838.18 Services 577.95 15,321,350.52 577.96 15,197,422.40 Total M&E Cost 577.95 15,321,350.52 577.96 15,197,422.40 Total Estimated Construction Cost 1848.82 49,011,600.44 1849.34 48,615,825.95 Above: Table showing the estimated cost allocation for functional elements of Tower A and Tower B. 34.
  • 37. Above: Pie chart showing the percentage of cost allocation for Tower A. 35.
  • 38. Above: Pie chart showing the percentage of cost allocation for Tower B. Referring to the two pie charts above, both Tower A and Tower B occupy 37.96% for structural frame. The construction cost allocated to architectural works and M&E works of both tower occupy 30.79% and 31.26% respectively. 4.0 Conclusion 36.
  • 39. No. Item CFA (m2) Rate (RM/m2) Total (RM) 1 Basement 8,052 1,650.44 13,289,377.88 2 Podium 28,390 9,38.85 26,653,922.64 3 Tower A 26,510 1,848.82 49,011,600.44 4 Tower B 26,295 1,848.86 48,615,825.95 Subtotal (No 1-4) 89,246 1,541.47 137,570,726.91 5 External Works & Landscape - - 1,953,045.00 6 Preliminaries - - 13,952,377.19 7 Contingencies - - 6,976,188.60 Subtotal (No 1-7) - - 160,452,337.70 8 Cost Escalation - - 8,022,616.88 Grand Total (1-8) - - 168,474,954.60 As a summary, the cost plan shown above shows the cost distributions for the various portions of the building for easy analysis. The proposed project consists of 2 levels of basement car park, 1 level of ground floor services floor, 6 levels of podium car park, 1 level of recreational facilities and 2 blocks of 31 levels of serviced apartments. There are a total of 404 residential units for each tower. There are also 477 parking lots from ground floor to Podium 6 and 179 parking lots in Basement 1 and 2. The facilities provided in the building are games room, playground, café, meeting room, audiovisual room, sky jacuzzi, infinity pool, yoga deck, convenience store and more. 37.
  • 40. The total of CFA for entire construction project which consists of basement, podium, Tower A and B is 89,246.69 m2 coming up to a total cost of RM137,570,726.91. With the addition of external works and landscape, preliminaries and contingencies, the entire const adds up to RM160,452,337.70. After adding up the cost escalation, the total cost of the entire construction project is RM168,474,954,60. In conclusion, with the strategic location, facilities and entertainment filled residences, along with the high efficiency rate of the proposed project which is 93%, we conclude that this project is very worth investing, promising in a high return in the future. 38.
  • 41. 5.0 References Concrete Formwork & Types of Formwork |Shuttering | CivilDigital |. (2017, March 15). Retrieved November 10, 2018, from https://civildigital.com/concrete-formwork-types-of-formwork/ Collins, M. (2000).Contiguous Bored Pile. Retrieved November 4, 2018, from http://www.concrete.org.uk/fingertips-document.asp?id=351 Editor. (2015, November 27). Clay Facades over Exterior paints & Glass? Retrieved November 10, 2018, from http://gosmartbricks.com/why-clay-facades/ Formwork in Construction|Types|Applications of Shuttering | CivilDigital |. (2017, March 16). Retrieved November 10, 2018, from https://civildigital.com/formwork-construction-types- applications-shuttering/ Hamakareem, M. I. (2018, October 08). Plastic Formworks for Concrete Construction - Applications and Advantage. Retrieved November 10, 2018, from https://theconstructor.org/building/plastic-formworks-concrete-construction/15885/ Holmes. (2018). Bored Piles. Retrieved November 4, 2018, from https://www.designingbuildings.co.uk/wiki/Bored_piles` Keller (n.d.). Contiguous Bored Piles and Secant Piles. Retrieved November 4, 2018, from http://resource-piling.com.sg/what-we-do/contiguous-bored-piles-and-secant-piles/ MPA(n.d.)Post-Tensioned(PT) Slab.. Retrieved November 4, 2018, from https://www.concretecentre.com/Building-Elements/Floors/Post-Tension-(PT)-Slabs.aspx 39.
  • 42. Ravishankar, R. (2015, March 18). Formwork construction in structures. Retrieved November 10, 2018, from https://www.slideshare.net/rithikarockingravishankar/formwork-construction-in- structures Rainwater Harvesting. (n.d.). Retrieved November 10, 2018, from https://www.ecooutdoor.com.my/rainwater-harvesting/ Roger. (2008). Post-Tensioned Slab. Retrieved November 4, 2018, from https://www.concreteconstruction.net/how-to/construction/post-tensioned-slabs_o Sharma, S. (2017, August 21). Different Types Of Building Façade Cladding Systems To Know About. Retrieved November 10, 2018, from http://gosmartbricks.com/different-types-of-building- facade-cladding-systems-to-know-about/ 40.