2. Introduction to me
2
■ I have been working in Oil and Gas Project Controls for almost 40 years
mostly on the Contractors side
■ I set up and worked on the largest project, of its type, ever built, the
Pearl GTL project that involved a number of very large Lump sum
elements worldwide. I also assured the Project Controls Set-up on
Gorgon, the largest ever LNG project
■ I am an EVM subject matter expert, presenting on this internationally
which is why I really enjoy this conference every year
■ I have been with Turner and Townsend T&T nearly 4 years and last year
I transferred to Texas from London and have already worked on two
mega project Shell Pennsylvania and Shell Lake Charles LNG
3. 3
Agenda
What is Contingency and Contingency Drawdown
Contingency drawdown methods
My preferred method
The separation between risk registers and contingency
Summary
Questions
4. 4
Contingency Drawdown definition
Oxford Dictionary – Contingency - A future event or circumstance which is
possible but cannot be predicted with certainty
Oxford Dictionary – Drawdown- An act of drawing on available funds or loan
facilities
■ Which basically means, stuff you expect to happen based on experience
but this is in itself in no way certain. Put another way, the method of
reducing contingency in line with the reduced risks through the project,
such that at the end there is nothing left
■ So put something away for that rainy day, but don’t hold on to it after the
rain stops, this presentation is to help you decide when the sun has come
out
Note: Opportunities are positive negative risks and vice versa. For this
presentation I’m assuming you know the methods of calculating
Contingency, i.e. Quantitive Cost Risk Assessment QCRA or QSRA Schediule
Risk analysis and how to create and use Risk registers.
5. 5
The Drawdown Curve
Surprisingly having a Drawdown curve is still state of the art for many
organisations. it shows the rate of drawdown of contingency and shows
at a glance the risk exposure over time.
This is a massive step up in Contingency Management but is still not a
required element in Risk Management in most organisations.
This presentation will help explain why you need ome and how to get one
7. 7
Run it down in line with forecast and scope increase
Every time something happens that changes a forecast use the contingency to cover
this
This is the method used most often but has obvious shortfalls
The amount drawn down is not necessarily proportional to the remaining risks or
allowed for in the Contingency
The total forecast never moves until the contingency is gone or the project
finishes
Risks are not routinely readdressed nor is change control prominent
It is not predictable, so no curve can be created
8. 8
Split the contingency into phases and draw this down
This is the next step in maturity and still runs down contingency
in line with forecast changes but;
Caps this at a cost per phase, e.g. Engineering 10%
Once the phase is finished the contingency can be released If you
can stop the bleed from one phase to another
The amount drawn down is not necessarily proportional to the
remaining risks or allowed for in the Contingency
No forecast movement until gone or over.
Risks are not routinely readdressed & the change control
mechanism is ignored
It is not predictable so no curve can be generated, just perhaps a
step
9. 9
Run it down in line with progress achieved
This method assumes the contingency drops in line with
progress
As progress is achieved contingency is drawn down in line with
this except for a percentage retention of contingency
This method assumes risk is propositional to progress and of
course the progress reported is correct
It will not automatically address new risks or remove old ones
or be led by Change Control
This method leaves a residue of unused contingency which
could have been used elsewhere
It does however generate a curve for comparison purposes
10. 10
Plan to draw it down in line with a manual perception and
key milestones
This involves looking at the key risks, the key milestone dates
that match these and then manually creating the drawdown
curve
This is usually carried out at staged workshops
Due to this being a workshop it is surprisingly the next step up
in maturity even though it is largely manual, because it
Involves a periodic review of contingency
Potentially changes the forecast final cost
Includes the change process
Allows a contingency rundown curve to be drawn and a forecast
made as to the remaining values
11. 11
Run it down by running QCRA in set periods by artificially
advancing the schedule
This assumes the typical ranging and Monte Carlo type risk
modelling has taken place using the budget
This will produce stand P value models
What can be done next is to theoretically advance the project
10% of its duration, review the risk ranges in a workshop (plus
deleting those expired) to calculate new P values
Repeat this until you get to 100% and thus no contingency
Plot The result
Once you start you will need to re-run the model with ranges to
keep the forecast evergreen
But beware this is the early curve and assumes we stick to the
schedule
12. 12
Run it down by linking it to the risk register
This is the most mature method as it uses the Risk Register
it involves linking the Risk register of events to the contingency
value generated by QCRA
To use this method, take the contingency generated and
allocate it across the top risks on an estimated/prorated basis
Doing this split will help identify if the risk provision is enough
Decide the start and end date of these identified risk and spread
the costs across these periods
Make sure new risks are addressed in the model
Plot the results as a rundown curve and continually reforecast
13. 13
The separation between Risk register and QCRA
■ It seems amazing 30 years on from the birth of real Risk management
there is typically no link between the risk register and the QCRA
■ The risk register is normally a time intensive exercise to generate the top
risks and then it is typically filed away as the QCRA takes front stage
■ The QCRA is carried out sometimes without this risk register being
reviewed
■ Sometimes different teams will generate each one! So it is unsurprising
that a consistent answer is not generated
■ There needs to be a link between these which is why I strongly
recommend that contingency drawdown is driven by an updated Risk
register and the value of contingency is reviewed or even recalculated and
plotted on a regular basis
14. 14
Preferred/recommended approach
■ Create a Risk Register and keep it ever green recognise that the top risks
will not always be the top risks
■ Create a QCRA based on P50 + risks and P90 – opportunities and decide
a value in between as your contingency
■ Only drawdown the contingency that matches the event that took place
■ Plot this contingency drawdown on a monthly basis and compare it to the
plan and take action if needed
■ Carry out QCRA’s on remaining scope on a regular basis don’t be afraid if
this is more than is left, just make sure you understand it and allow for it!
■ Spread this remaining contingency across the remaining risks and time
profile this
■ Replot the run down curve as a forecast
15. 15
Summary
Contingency and Risk Management is not a one off calculation it is
ongoing
Risk registers do not belong in desks
Not all cost increases are covered by contingency
It is acceptable to have an overrun forecast and still have contingency in
place
Know the plan for using contingency and use it when appropriate,
remember it is more important to know the remaining risk than to know
what’s has gone
Having a rundown plan can stop the race to take contingency and the
opposite a sandbagging approach
Have an organisation that allows contingency to be given as well as taken
16. 16
Questions
Mike Younger
Director of Major Programs
Turner & Townsend
10777 Westheimer, Suite 1160
Houston, TX 77042
t: +1:281-536-1064|
www.turnerandtownsend.com