SlideShare uma empresa Scribd logo
1 de 34
Baixar para ler offline
This presentation considers:
• the risk of track workers being struck by 
trains
• how well this risk is managed by rules and 
other risk controls
• barriers to improvements  
and
• suggests where we go from here
It is supported by a conference paper that contains 
everything in this presentation 
RSSB Safety Risk Model
Probability of an individual 
track worker being killed by a 
train is 1 in 15850 
Fatality risk from 
all causes is 1 in 
9860. Being 
struck by a train 
accounts for 63% 
of this risk
52 Fatalities ‐ 1990 to 2009  (SSoW failure only)
Successful campaign to emphasise rules compliance in early 90s
Is continuing this approach alone sufficient to eliminate fatalities?
Analysis by SSoW ‐ 1994 to 2009
• 32% of fatalities are those providing the SSoW
• Lookouts, when used, are 55% of fatalities   
• Some SSoW may present intolerable levels of risk
Safe                                   Role
System of Work
Total
COSS/
IWA
Lookout
Protection
Assistant
Machine  
Controller
Other 
Workforce
Established Possession 5 1 4
Possession Set Up 2 2
Open Line by Green Zone 3 3
Red Zone – Static 6 2 4
Red Zone – Mobile 7 4 3
None 2 1 1
Total 25 5 5 2 1 12
Immediate CausePre ‐ ConditionLatent Failures
“Many accidents are blamed on the actions or 
omissions of an individual who was directly involved in 
operational or maintenance work. This typical but 
short‐sighted response ignores the fundamental 
failures that led to the accident. These are usually 
rooted deeper in the organisation’s design, 
management and decision making functions”
“Everyone can make errors no matter how well 
trained and motivated they are. Sometimes we are 
“set up” by the system to fail. The challenge is to 
develop error‐tolerant systems and to prevent errors 
from occurring”Reducing error and influencing behaviour HSG 48
Underlying Cause
Rules for provision of  
“Morpeth” AWS magnets ‐
Morpeth North curve did not 
qualify
Lesson
Not always appropriate to 
prescribe rules
Morpeth 1984
Immediate Cause
Driver did not slow for 40 mph 
curve
• Rules are required for real time operations but are not 
always appropriate for planned work
• The Rule Book is the only Group Standard whose 
purpose and scope is not stated. Standards should  
have a defined purpose and scope 
• Group Standards are required for matters “which 
involve co‐operation between two or more rail duty 
holders”, so work under direct control of one Railway 
Group member should not be a Group Standard
• Network Rail is the employer of all those who 
undertake  infrastructure work and has the legal 
responsibility for track safety risk controls 
Management of Health and Safety at Work Regs
• Undertake a “suitable and sufficient risk 
assessment” to develop risk controls. Further risk 
assessment when circumstances change
• Provide comprehensible and relevant 
information on risk control measures
Construction(Design and Management) Regs
• Provide pre‐construction information needed for  
site safety
• Ensure design takes account of safety of those 
who will operate and maintain completed project
• Rules should be derived from risk assessment as 
required by MHASAW Regulations. A further risk 
assessment is required when circumstances 
change
• Rules are only one type of control measure. The 
risk assessment must also specify other risk 
control measures
• Rules and other risk controls cannot be 
considered in isolation from each other.  A 
cohesive approach by a single authority is needed 
AC AC – AC Electrified Lines
DC DC – Electrified Lines
OTP On Track Plant
T3 Possession of the line for engineering work
T11 Movement of engineering trains and on‐track plant 
under T3 arrangements
HB1 General duties and track safety for track worker
HB3 Duties of Lookout and site warden
HB6 General duties of an Individual Working Alone (IWA)
HB7 General duties of a Controller of Site Safety (COSS)
HB8 IWA, COSS or PC blocking a line
HB9 IWA or COSS setting up safe systems of work within 
possessions
AC AC – AC Electrified 
Lines
14 sections, COSS only concerned 
with  issue of OLE permit
OTP On Track Plant OTP movements, on & off tracking, 
safe operation of OTP
T3 Possession of the line 
for engineering work
Sets up the possession needed when 
work require train movements
T11 Movement of 
engineering trains and 
on‐track plant under T3
Movements once possession is set 
up. Does not include sideways 
movements into the possession
HB7 General duties of a 
Controller of Site Safety
No mention of possessions.  
Mandates COSS form, most of which 
is not relevant to possessions
HB9 IWA or COSS setting up 
safe systems of work 
within possessions
Explains how SSoW derived for open 
line are applied to possessions. 
1. Maximum speed in possession work‐sites
Not clear that the 5 mph required for a green zone only 
applies to COSS’s site of work. It does not apply to entire  
possession work‐site. With access points miles apart, a 5 
mile round trip from access to site of work is not untypical
2. Control of On‐track plant (OTP) movements
Rule Book requires ES to authorise each move. However  
there may be hundreds of individual OTP moves in a 
possession work‐site.  Custom and practice is for the ES to 
delegate movement authority to Machine Controller . 
Module T11 does consider how OTP enters possessions 
and there is no requirement to record this
3. Route setting in possessions
Although the route has been set incorrectly every time 
a point is run through, there is no defined process to 
set routes in possessions, as there is for a signal failure 
on open line. 
4. Red Zone working in possessions 
Lookouts are for unexpected trains at high speed. 
Workforce control of movements should be 
considered
5. Issue of isolation permits to COSSs rather than ES
This does not take account of ES authorising COSSs to 
start work and thus increases the number of 
communications before work can start.    
1. Situational Awareness 
Workforce must have a situational awareness of all aspects 
of the possession. Diagrams are an effective way of 
providing this especially as various limits being 
demarcated in different ways
Limit Demarcation
Possession Signals and / or points numbers
Possession work‐site Mileage
COSS’s Site of Work As agreed with ES, not documented
Isolation limits (AC) OLE  mast numbers
Access points Mileage
No specification for possession diagrams or process to 
provide employees or contractors with the information 
needed for such diagrams. 
1.   Situational awareness 
Example diagram with same information as on signaller’s panel
2. Controller of Site Safety (COSS)
•COSSs need to be able to set up many different safe systems of 
work (SSoW). On the open line this is a demanding role
•This is not so in an all lines blocked Possession as the SSoW has, 
in effect, already been established
•Many COSSs only work in all lines blocked possessions, but to 
do so they must have the full range of COSS competencies 
•A suitable COSS possession competency would thus reduce 
training requirement and eliminate risk of a COSS losing 
competence to set up open line SSoWs due to lack of practice 
•It is not feasible for many who supervise possession work to 
obtain the full COSS competency and so workgroups often have 
both a COSS and site supervisor managing their safety 
3.  Facilities for PICOP / ES
• Although simple possessions can be managed from a van 
by those who know their area, complex possessions need 
facilities to reduce risk of reliance on human memory e.g. 
an office, magnetic board with diagram and forms to track 
movements and on / off tracking
• “I’d rather control a complex work‐site with facilities such 
as this than a simple work‐site from the back of a van”
4.  Access points 
• Personnel and plant often travel miles along the railway 
from access point to site of work
• Opportunities to provide access points as part of projects 
are often lost with no standard requiring their provision 
5.  Authority to Work Communications 
• Possession rules are in various modules / handbooks 
and have been evolved from the need to control train 
movements with other rules “bolted on” in an ad hoc 
manner. They need to be better presented and 
enhanced to address issues not currently addressed 
• This could be resolved by a possession safety handbook 
which could be provided relatively quickly as there is 
little, if any, requirement to change existing rules
• Scope of this guide should be interfaces between the 
operational railway and between different principal 
contractors 
• The starting point for such a guide must be the 
requirements of the work rather than train movements
RIMINI 
A significant improvement in 2001 giving greater 
emphasis on work planning but:‐
• Does not specify T2 hierarchy (T2A  / T2D less 
prone to human error than detonator protection)
• Complex paperwork
• 9 years after RIMINI introduced, there is no 
process to provide asset information required for 
planning 
Lookout Operated Warning Systems (LOWS)
• Since 1994 there were 5 lookout 
fatalities (20% of total), 3 of which 
were mobile sites. Lookouts face 
greater risks than other track 
workers. Risk may be intolerable
• Lookout must be in a place of 
safety and have line of sight the 
workgroup and approaching 
trains. This is difficult to achieve 
when walking along the track
Lookout Operated Warning Systems (LOWS)
• LOWS does not require the lookout to be in sight of 
workgroup, so the lookout need not be close to the 
track 
• LOWS could eliminate the need for a lookout chain 
(site, intermediate and distant lookouts)
• Widespread use of LOWS could reduce risk to 
lookouts and provide cost savings
• Some LOWS trials but minimal use of LOWS
• LOWS systems used are cumbersome and cannot be 
used for mobile worksites. There is a need to develop 
easily used portable systems 
Track Circuit Operating Devices (TCODs)
• TCODs enable COSS on site to 
directly maintain a signal at danger
• Eliminates risk of 
miscommunication with signaller 
• Not widely used although popular 
with those who use them 
• Type approval issues
• Unclear where they can be used
• Fixed TCODs are switches that 
activate track circuits and is a low 
cost alteration to signalling system
Trackside facilities
• Although significant sums have been spend on 
access points, a strategy is required for the provision 
of assets to improve safety and possession efficiency
• This includes access points, remotely operated DEPs, 
track warning systems and lockouts
• Although these can be expensive to provide, cost can 
be minimal if specified at start of project design 
• CDM requires project designers to consider safety of 
those working on the track.  This applies to anyone 
taking a design decision (e.g. Project Sponsors who 
specify project requirements)
Despite report recommendations and improvement 
initiatives over many years there have been few track 
safety improvements
•Report into fatal On Track Plant accident at 
Hednesford in 2004 “a review of module T3 and T7 of 
the rule book should be undertaken to establish safe 
systems of work which accommodate multiple 
activities and train movements within worksites.”
•Rail Accident Investigation Branch bulletin on the 
Kentish Town 26.10.09 possession incident notes that 
its recommendations from the similar Acton 24.6.08 
incident have yet to be implemented
Why
• Rules culture – A great strength  but can lead to a blame culture 
that does not allow for genuine mistakes and masks the need to 
improve risk controls.
• Organisational culture ‐ Safety improvement requires a 
willingness to openly identify problems. Under reporting of 
hundreds of RIDDOR accidents is indicative of a culture that does 
not encourage this.
• Risk not understood ‐ Suitable performance indicators for track 
safety incidents are needed.  
• Reluctance to accept risks associated with changed risk controls.  
• Track safety rules are Group Standards subject to extensive 
stakeholder communications that are produced by RSSB 
committee whose focus is train movements. Only 3 of its 18 
members work for Network Rail.
• LOWS eliminates need for lookout chains
• No duplication of site supervisor and COSS
• Avoid points run throughs
• Reduced time to start from simplified possession 
communications
• Reduced travel time from access point to site of work
As well as reducing risk, suggestions in this presentation offer
productivity and cost savings. for example
Machine Controller
starting 2 mile walk 
to site of work 
in a freezing rain squall
ORR consider that NR’s infrastructure work 34% to 40% less 
efficient than in Europe, in part due to way possessions are 
undertaken.
• Network Rail, as the responsible employer, 
should take ownership of track safety at 
Director level to ensure a cohesive approach 
to rules and other risk controls, a culture that 
encourages safety improvement and a 
strategy for the provision of track safety 
assets and systems   
• This should be based on risk assessment, 
legislative requirements, address issues in this 
presentation and incorporate lessons from 
previous initiatives
Do Rules Keep Track Workers Safe

Mais conteúdo relacionado

Semelhante a Do Rules Keep Track Workers Safe

Project report for railway security monotorin system
Project report for railway security monotorin systemProject report for railway security monotorin system
Project report for railway security monotorin systemASWATHY VG
 
Eurocontrol Sqs
Eurocontrol SqsEurocontrol Sqs
Eurocontrol Sqsapcae
 
Vehicle to vehicle communication
Vehicle to vehicle communicationVehicle to vehicle communication
Vehicle to vehicle communicationVijayalakshmi Joger
 
Speaker 5 Capt D N Goswami
Speaker 5 Capt D N GoswamiSpeaker 5 Capt D N Goswami
Speaker 5 Capt D N Goswamicmmindia2017
 
SMS Fundamentals Module 1
SMS Fundamentals Module 1SMS Fundamentals Module 1
SMS Fundamentals Module 1Scott McCamish
 
Accident prediction models
Accident prediction modelsAccident prediction models
Accident prediction modelsAnton Budiharjo
 
Autonomous Driving, provable safety and scalability design principles - Erez ...
Autonomous Driving, provable safety and scalability design principles - Erez ...Autonomous Driving, provable safety and scalability design principles - Erez ...
Autonomous Driving, provable safety and scalability design principles - Erez ...Euro NCAP
 
P0333086093
P0333086093P0333086093
P0333086093theijes
 
24ESV-000453 Mitigating Drowsiness Linking Detection to Mitigation
24ESV-000453 Mitigating Drowsiness Linking Detection to Mitigation24ESV-000453 Mitigating Drowsiness Linking Detection to Mitigation
24ESV-000453 Mitigating Drowsiness Linking Detection to MitigationJulie J. Kang, Ph.D.
 
Chris Wraith: Elevating work platforms - an international perspective
Chris Wraith: Elevating work platforms - an international perspectiveChris Wraith: Elevating work platforms - an international perspective
Chris Wraith: Elevating work platforms - an international perspectiveNSW Environment and Planning
 
IRJET- Detection of Suspicious Lesions in Mammogram using Zebra Medical V...
IRJET-  	  Detection of Suspicious Lesions in Mammogram using Zebra Medical V...IRJET-  	  Detection of Suspicious Lesions in Mammogram using Zebra Medical V...
IRJET- Detection of Suspicious Lesions in Mammogram using Zebra Medical V...IRJET Journal
 
Aviation Training, Safety Management System
Aviation Training, Safety Management SystemAviation Training, Safety Management System
Aviation Training, Safety Management Systempghclearingsolutions
 
Theodora Calinescu, 2nd Auto Forum
Theodora Calinescu, 2nd Auto ForumTheodora Calinescu, 2nd Auto Forum
Theodora Calinescu, 2nd Auto ForumStarttech Ventures
 
NEN_SIL Platform_Risk matrix guide
NEN_SIL Platform_Risk matrix guideNEN_SIL Platform_Risk matrix guide
NEN_SIL Platform_Risk matrix guideRianne Boek
 
IMMI Florida Trucking Association
IMMI Florida Trucking AssociationIMMI Florida Trucking Association
IMMI Florida Trucking AssociationIMMI
 

Semelhante a Do Rules Keep Track Workers Safe (20)

Project report for railway security monotorin system
Project report for railway security monotorin systemProject report for railway security monotorin system
Project report for railway security monotorin system
 
Eurocontrol Sqs
Eurocontrol SqsEurocontrol Sqs
Eurocontrol Sqs
 
HARA ISO 26262: What is HARA and Why is it Required?
HARA ISO 26262: What is HARA and Why is it Required?HARA ISO 26262: What is HARA and Why is it Required?
HARA ISO 26262: What is HARA and Why is it Required?
 
rr1156.pdf
rr1156.pdfrr1156.pdf
rr1156.pdf
 
Vehicle to vehicle communication
Vehicle to vehicle communicationVehicle to vehicle communication
Vehicle to vehicle communication
 
ISA: The Research Evidence
ISA: The Research EvidenceISA: The Research Evidence
ISA: The Research Evidence
 
Speaker 5 Capt D N Goswami
Speaker 5 Capt D N GoswamiSpeaker 5 Capt D N Goswami
Speaker 5 Capt D N Goswami
 
SMS Fundamentals Module 1
SMS Fundamentals Module 1SMS Fundamentals Module 1
SMS Fundamentals Module 1
 
Accident prediction models
Accident prediction modelsAccident prediction models
Accident prediction models
 
Autonomous Driving, provable safety and scalability design principles - Erez ...
Autonomous Driving, provable safety and scalability design principles - Erez ...Autonomous Driving, provable safety and scalability design principles - Erez ...
Autonomous Driving, provable safety and scalability design principles - Erez ...
 
P0333086093
P0333086093P0333086093
P0333086093
 
24ESV-000453 Mitigating Drowsiness Linking Detection to Mitigation
24ESV-000453 Mitigating Drowsiness Linking Detection to Mitigation24ESV-000453 Mitigating Drowsiness Linking Detection to Mitigation
24ESV-000453 Mitigating Drowsiness Linking Detection to Mitigation
 
Chris Wraith: Elevating work platforms - an international perspective
Chris Wraith: Elevating work platforms - an international perspectiveChris Wraith: Elevating work platforms - an international perspective
Chris Wraith: Elevating work platforms - an international perspective
 
IRJET- Detection of Suspicious Lesions in Mammogram using Zebra Medical V...
IRJET-  	  Detection of Suspicious Lesions in Mammogram using Zebra Medical V...IRJET-  	  Detection of Suspicious Lesions in Mammogram using Zebra Medical V...
IRJET- Detection of Suspicious Lesions in Mammogram using Zebra Medical V...
 
Aviation Training, Safety Management System
Aviation Training, Safety Management SystemAviation Training, Safety Management System
Aviation Training, Safety Management System
 
Vehicle safety technologies - the human behind the wheel
Vehicle safety technologies - the human behind the wheelVehicle safety technologies - the human behind the wheel
Vehicle safety technologies - the human behind the wheel
 
Theodora Calinescu, 2nd Auto Forum
Theodora Calinescu, 2nd Auto ForumTheodora Calinescu, 2nd Auto Forum
Theodora Calinescu, 2nd Auto Forum
 
NEN_SIL Platform_Risk matrix guide
NEN_SIL Platform_Risk matrix guideNEN_SIL Platform_Risk matrix guide
NEN_SIL Platform_Risk matrix guide
 
IMMI Florida Trucking Association
IMMI Florida Trucking AssociationIMMI Florida Trucking Association
IMMI Florida Trucking Association
 
Vision Zero - A Global Project
Vision Zero - A Global ProjectVision Zero - A Global Project
Vision Zero - A Global Project
 

Do Rules Keep Track Workers Safe