Project cost management
Chapter 9
Horror stories of project failures due to extraordinary
cost overruns are reported in the business press on
almost a daily basis
As a general rule, management and customers
are always concerned with how much a project is
going to cost in relation to how much a project is
going to earn
Project cost management
• Includes processes involved in planning,
estimating, budgeting, financing, funding,
managing, and controlling costs so that the project
can be completed within the approved budget
Why Do We Manage Cost?
• Part of triple constraint, can’t manage one without
the others (scope, time, and quality)
• Plots of cost and scope against plan can help spot
problems early
Cumulative
Value
Time
Planned
Value (PV)
Actual
Costs (AC)
Earned
Value (EV)
Today
Is this project
over/under budget?
Is it ahead of/behind
schedule?
Project cost management processes
• Plan cost management—establishes the policies,
procedures, and documentation for planning,
managing, expending, and controlling project costs
• Estimate costs—an approximation of the monetary
resources needed to complete project activities
• Determine budget— aggregating the estimated costs
of individual activities or work packages to establish
an authorized cost baseline
• Control costs—monitoring the status of the project to
update the project costs and managing changes to
the cost baseline
Importance of cost estimation
• Provides standard against which actual expenditures
incurred during the course of a project can be
compared, and serve as the basis for cost control
• They provide the mechanism for managing cash flow
during the course of the project
• They give the project manager a framework for
allocating scarce resources as the project progresses
Errors during project progress
Potential for errors in estimates during the various stages of
the project progress
Classification of project costs
• Direct Vs. Indirect
• Recurring Vs. Nonrecurring
• Fixed Vs. Variable
• Normal Vs. Expedited
Direct Vs. Indirect
• Direct costs- can be directly charged against the
project; for example, the costs of personnel who
are directly involved in the project, or the costs of
materials directly used for project work
• Indirect costs- include overhead, as well as
selling and administrative expenses
Examples of overhead costs include costs associated
with taxes, insurance, utilities, and so forth. Costs
associated with selling and administrative expenses,
commissions, advertising, etc
Recurring Vs. Nonrecurring
• Recurring costs- such as labor and materials,
are repeatedly incurred throughout the project
life cycle
• Nonrecurring costs- are one-time costs that are
typically incurred at the beginning or at the end
of the project, such as market research and
labor training
Fixed Vs. Variable
• Fixed costs- do not vary with usage. Example,
costs incurred in the purchase of capital
equipment remain fixed, regardless of the extent
of equipment use
• Variable costs- vary directly with usage. They are
typically associated with labor and materials
Normal Vs. Expedited
• Normal costs- are incurred when project tasks are
completed according to the original planned
duration
• Expedited costs- or crash costs are unplanned
costs incurred as a result of steps taken to
accelerate project completion
Example, costs associated with using additional overtime
or hiring additional workers specifically to hasten project
completion can be regarded as expedited costs
Cost classifications
Direct labor X X X X
Building lease X X X X
Expedite X X X X
Material X X X X
Direct
Indirect
Fixed
Recurring
Variable
Normal
Expedited
Costs
Non-recurring
Cost estimating methods
• Ballpark estimates
• Feasibility estimates
• Definitive estimates
• Comparative estimates
Ballpark estimates
• Also known as ‘‘order of magnitude’’ estimates,
often used when there is not sufficient information
or time available
• Typically, used for making competitive bids for
project contracts, or for initial rough-cut estimates
of resources needed for a project
• As a general rule, ballpark estimates should
attempt an accuracy of ±30 percent
Feasibility estimates
• Are developed after preliminary project design
work is completed
• Are often used in construction projects, where
published information on material costs is widely
available
• As more relevant information becomes available
further down the project life cycle, the ±10 percent
margin of error
Definitive estimates
• Can be developed only after the completion of
most design work
• Clear understanding of the scope and capabilities
of the project, changes to project specifications
are virtually nonexistent
• Developed further down the project life cycle with
more accurate information and fewer project
uncertainties, provide a much more accurate
expected cost of the project at completion, with a
±5 percent margin of error
Comparative estimates
• Uses historical data from previous project activities
as the frame of reference for current estimates
• One of the method is parametric estimation-most
projects are similar to previous projects by way of
similar features or parameters and, therefore, are
likely to incur similar costs. Steps:
– Identifying the features/parameters of an older or well-known
project that can be directly related to the cost of the current
project
– Defining the mathematical nature of that relationship
Use of learning curves in estimation
• Human performance usually improves
when a task is repeated
• This happens by a fixed percent each
time the production doubles
• Percentage is called the learning rate
Learning curve calculations
( )
∑=
=
=
=
N
n
r
r
n
nT
rate
r
nTT
1
1
1
timeTotal
2log
log
Tn = Time for nth unit
T1 = Time for first unit
N = Number of units
R = log decimal rate/log 2
One worker will be tasked to produce all 25 units of air filters. In
addition, after production of the 20th unit, there is no significant
time reduction associated with learning, and production reaches
a steady state of 70 hours. Learning rate is 85%. Time to
complete the first activity?
r = log 0.85/ log 2
r= −0.1626/0.693
r= −0.235
70 hours = T1 ( 20)-0.235
T1= 141.3 hours
Cost estimation and budgeting
• Cost estimation and project budgeting are
closely linked
• Without reasonable cost estimation, project
budgets are essentially useless, and without
accurate budgeting, cost estimation is a
wasted exercise
Budgeting
• A plan for the costs of project resources
• A budget implies constraints
• Thus, it implies that managers will not
get everything they want or need
Budgeting
• The budget for an activity also implies
management support for that activity
• Higher the budget, relative to cost, higher
the managerial support
• The budget is also a control mechanism
• Many organizations have controls in place
that prohibit exceeding the budget
• Comparisons are against the budget
Issues in project budgeting
• A project budget identifies the project’s
allocated resources, goals, and the schedule
that allows the organization to achieve those
goals
• Developing a project budget requires not only a
knowledge of the resources needed, but also
information regarding how many will be needed
and when, as well as how much they will cost
Estimating project budgets
• On most projects
– Material + Labor + Equipment + Capital +
Overhead + Profits = Bid
• In other words
– Resources + Profits = Bid
• So we are left with the task of forecasting
resources
Estimating project budgets
• Like any forecast, this includes some
uncertainty
• There is uncertainty regarding usage
and price
– Especially true for material and labor
• The more standardized the project and
components, the lower the uncertainty
• The more experienced the cost
estimator, the lower the uncertainty
Rule of thumb
• Some estimates are prepared by rules
of thumb
• Construction cost by square feet
• Printing cost by number of pages
• Lawn care cost by square feet of lawn
• These rules of thumb may be adjusted
for special conditions
• However, this is still easier than starting
the estimate from scratch
Difficulties
• There may not be as much historical
data or none at all
• Even with similar projects, there may
be significant differences
• Many people have input and some
control over the budget
Difficulties
• There is more “flexibility” regarding the
estimates of inputs (material and labor)
• The accounting system may not be set
up to track project data
• Usage of labor and material is very
lumpy over time
Types of budgeting
• Top-down
• Bottom-up
• Negotiated
• Activity based costing
Top-down
• Top managers estimate/decide on the
overall budget for the project
• These trickle down through the
organization where the estimates are
broken down into greater detail at each
lower level
• The process continues to the bottom
level
Advantages
• Overall project budgets can be set/controlled very
accurately
• Management has more control over budgets
Disadvantages
• More difficult to get buy in
• Leads to low level competition for larger shares of
budget
Bottom-up budgeting
• Project is broken down into work packages
• Low level managers price out each work
package
• Overhead and profits are added to develop
the budget
Advantages
• Greater buy in by low level managers
• More likely to catch unusual expenses
• People tend to overstate their budget
requirements
• Management tends to cut the budget
Disadvantages
An iterative budgeting process–
negotiation-in-action
• Most projects use some combination of
top-down and bottom-up budgeting
• Both are prepared and compared
• Any differences are negotiated
Snapshot
from practice
How do you estimate the
cost of a nuclear power
plant?
Activity based costing
• Activity-based costing (ABC) is frequently
used for project budgeting. The basis of
activity-based costing is that projects
consume activities, and activities consume
resources
Steps in activity-based costing
• Assign costs to activities that use resources
(costs are assigned to each work package)
• Identify cost drivers associated with this
activity( like human resource in many cases)
• Compute a cost rate per cost driver unit or
transaction (cost of labor per hour)
• Multiply the cost driver rate times the volume of
cost driver units used by the project
Rs50/hour 100 hours = Rs5,000.00∗
Budget contingencies
• The allocation of extra funds to cover uncertainties
and improve the chance of finishing on time
• It is an important aspect of project finance,
because it provides a certain amount of protection
against unknown and uncertain elements that can
derail a project
Contingencies are needed because
• Project scope may change
• Murphy’s Law is present
“If anything can go wrong, it will”
• Cost estimation must anticipate interaction costs
Hidden cost
• Normal conditions are rarely encountered
Benefits to include contingency
• Recognizes that the future is uncertain, and
that unexpected problems can increase
overall project costs
• Contingency estimates make explicit
provisions for potential and unexpected cost
increase in project plans and budgets
• The use of contingency funds provides an
early warning signal of potential cost overruns
More on Project Cost
Management
Cost Management Key Terms
• PV - Planned Value, estimated value of the planned work
• EV – Earned Value, estimated value of work done
• AC – Actual Cost, what you paid
• BAC – Budget at Completion, the budget for the total job
• EAC –Estimate at Completion, what is the total job
expected to cost?
• ETC – Estimate to Complete, forecasted costs to complete
job
• VAC – Variance at Completion, how much over/under
budget do we expect to be?
How Do We Manage Cost?
• Three processes
– Estimate Costs
– Determine Budget
– Control Costs
Estimate
Costs
Determine
Budget
Control
Costs
Estimate Costs
Enterprise
Environmental
Factors
Organizational
Process Assets
Project Scope
Statement
Analogous estimating
Determine resource cost
rates
Bottom up estimating
Parametric estimating
Project management
software
Vendor bid analysis
Reserve analysis
Cost of quality
Inputs
OutputsTools & Techniques
Work Breakdown
Structure
WBS Dictionary
Project
Management Plan
•Schedule Mgmt Pln
•Staffing Mgmt Pln
•Risk Register
Activity Cost
Estimates
Activity Cost
Estimates
Supporting Detail
Requested Changes
Cost Management
Plan Updates
Estimate
Costs
Determine
Budget
Control
Costs
Other Estimating Methods
• Parametric estimating – Use mathematical model
(i.e. cost per sq ft). [accuracy varies] Two types:
• Regression analysis – based on analysis of multiple
data points
• Learning Curve – The first unit costs more than the
100th
, forecasts efficiency gains
• Vendor Bid Analysis – Estimating using bids +
allowances for gaps in bid scope [slow, accuracy
depends on gaps]
• Reserve Analysis – Adding contingency to each
activity cost estimates as zero duration item [slow,
overstates cost]
Determine Budget
Project Scope Statement
Cost aggregation
Reserve analysis
Parametric estimating
Funding limit reconciliationInputs
Outputs
Tools & Techniques
Cost Baseline
Project Funding
Requirements
Cost Management
Plan Updates
Requested Changes
Work Breakdown Structure
WBS Dictionary
Activity Cost Estimates
Activity Cost Estimates
Supporting Detail
Project Schedule
Resource Calendars
Contract
Cost Management Plan
Estimate
Costs
Determine
Budget
Control
Costs
Determine Budget
• Budgeting is allocating costs to work
packages to establish a cost baseline to
measure project performance
• Remember Contingency items are for
unplanned but required changes it is not to
cover things such as:
– Price escalation
– Scope & Quality Changes
• Funding Limit Reconciliation – Smoothing out
the project spend to meet management
expectations
Control Costs
Cost Baseline
Project Funding
Requirements
Performance
Reports
Cost change control system
Performance measurement
analysis
Forecasting
Project performance reviews
Project management
software
Variance management
Inputs
OutputsTools & Techniques
Work Performance
Information
Approved Change
Requests
Project
Management Plan
Cost Estimate
Updates
Cost Baseline
Updates
Performance
Measurements
Forecasted
Completion
Requested Changes
Recommended
Corrective Actions
Organizational
Process Assets
Updates
Project Management
Plan Updates
Estimate
Costs
Determine
Budget
Control
Costs
Earned Value
• Progress is compared against the
baseline to determine whether
project is ahead of or behind plan
• Percent complete can be difficult to
measure, some managers use
rules
– 50/50 Rule – Assumed 50% complete
when task started, final 50% at
completion
– 20/80 Rule – 20% at start
– 0/100 Rule – No credit until complete
• Planned Value
(PV) – Budgeted
Cost
• Earned Value
(EV) – Actual
work completed
• Actual Cost (AC)
– Costs incurred
• Estimate to
Complete (ETC)
– What’s Left
• Estimate at
Completion
(EAC) – What
final cost will be
Earned
Value
Graph
Variance at
Completion
(VAC)
Target
Cost &
Schedule
Schedule
Variance
(Time)
Planned
Value
(PV)
Earned
Value
(EV)
Earned Value Formulas
NAME FORMULA NOTES
Cost Variance (CV) EV-AC Negative = Over budget
Positive = Under budget
Schedule Variance
(SV)
EV-PV Negative = Behind Schedule
Positive = Ahead of Schedule
Cost Performance
Index (CPI)
EV/AC How much are we getting for every
dollar we spend?
Schedule Perform
Index (SPI)
EV/PV Progress as % against plan
Estimate to Complete
(ETC)
EAC-AC How much more do we have to
spend?
Variance at
Completion (VAC)
BAC-EAC At the end of the day, how close will
we be to plan?
Estimate at
Completion (EAC)
See following slide
Earned Value Formulas (Cont’d)
NAME FORMULA NOTES
Estimate at
Completion (EAC)
•BAC/CPI Use if no variances from
BAC have occurred
•AC+ATC Use when original
estimate was bad. Actuals
+ New estimate
•AC+BAC-EV Use when current
variances are not expected
to be there in the future
•AC+(BAC-EV)/CPI Use when current
variances are expected to
continue
Tricks for Earned Value
• EV is always first
• Variance = EV minus something
• Index = EV divided by something
• If the formula relates to cost use AC
• If the formula relates to schedule use PV
• Interpreting results: negative is bad and positive is
good
• Interpreting results: greater than one is good, less
than one is bad
PV
AC ETC
EAC
BAC
Project
Start
Current
Status
Terms to Remember
• Present Value
• Net Present Value (NPV)
• Internal Rate of Return
(IRR)
• Payback Period
• Benefit Cost Ratio =
BCR>1, Payback is greater
than the cost
• Opportunity Cost
• Sunk Cost
• Working Capital
• Straight Line Depreciation
• Accelerated Depreciation
• Double Declining Balance
• Sum of Years Digits
• Value Analysis (Value
Engineering)
• To illustrate the concept of EVM and all the
formulas, assume a project that has exactly
one task. The task was baselined at 8 hours,
but 11 hours have been spent and the
estimate to complete is 1 additional hour. The
task would have been completed already.
Assume an Hourly Rate of $100 per hour.
• Budget at Completion
(BAC) is the total budget
allocated to the project.
• Estimate to Complete
(ETC) is the estimated
cost required to complete
the remainder of the
project.
• Estimate at Completion
(EAC) is the estimated
cost of the project at the
end of the project.
• Variance at completion
(VAC) is the variance on
the total budget at the end
of the project.
Appendices
Sample project
activity cost
estimating sheet
Sample budget showing planned and
actual activity costs and variances
Sample of a time-phased budget
Calculating direct labor costs

Mais conteúdo relacionado

Mais procurados

Project Planning and Management
Project Planning and Management Project Planning and Management
Project Planning and Management PiyushKumar621
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk ManagementKaustubh Gupta
 
Project monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoringProject monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoringSandeep Kumar
 
6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource SmoothingDavidMcLachlan1
 
8. (lecture 6) Project Cost Control.ppt
8. (lecture 6) Project Cost Control.ppt8. (lecture 6) Project Cost Control.ppt
8. (lecture 6) Project Cost Control.pptPedadaSaikumar
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULEAjeesh Mk
 
Project management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areasProject management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areasMazen Zbib
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost managementImran Jamil
 
06. Project Management Process Groups
06. Project Management Process Groups06. Project Management Process Groups
06. Project Management Process GroupsBhuWan Khadka
 
Challenges Of Project Management
Challenges Of Project ManagementChallenges Of Project Management
Challenges Of Project Managementashutoshsachan
 
Project Stakeholder Management - PMBOK6
Project Stakeholder Management - PMBOK6Project Stakeholder Management - PMBOK6
Project Stakeholder Management - PMBOK6Agus Suhanto
 
Fundamentals of project management
Fundamentals of project managementFundamentals of project management
Fundamentals of project managementMohamed Amin
 
Project Management
Project ManagementProject Management
Project ManagementMark Roman
 
Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management A Makwana
 
Project management tools and techniques
Project management tools and techniquesProject management tools and techniques
Project management tools and techniquesTata Dinyuy
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniquesShivangi Saini
 

Mais procurados (20)

Project Management Tools and Techniques
Project Management Tools and TechniquesProject Management Tools and Techniques
Project Management Tools and Techniques
 
Project Planning and Management
Project Planning and Management Project Planning and Management
Project Planning and Management
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
project management
project managementproject management
project management
 
Project monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoringProject monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoring
 
6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing
 
8. (lecture 6) Project Cost Control.ppt
8. (lecture 6) Project Cost Control.ppt8. (lecture 6) Project Cost Control.ppt
8. (lecture 6) Project Cost Control.ppt
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Project management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areasProject management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areas
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 
06. Project Management Process Groups
06. Project Management Process Groups06. Project Management Process Groups
06. Project Management Process Groups
 
Challenges Of Project Management
Challenges Of Project ManagementChallenges Of Project Management
Challenges Of Project Management
 
Project Stakeholder Management - PMBOK6
Project Stakeholder Management - PMBOK6Project Stakeholder Management - PMBOK6
Project Stakeholder Management - PMBOK6
 
Project cost management
Project cost managementProject cost management
Project cost management
 
Project Planning & Management
Project Planning & ManagementProject Planning & Management
Project Planning & Management
 
Fundamentals of project management
Fundamentals of project managementFundamentals of project management
Fundamentals of project management
 
Project Management
Project ManagementProject Management
Project Management
 
Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management
 
Project management tools and techniques
Project management tools and techniquesProject management tools and techniques
Project management tools and techniques
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 

Semelhante a 09. Project Cost Management

9-180307064518 (1).pptx
9-180307064518 (1).pptx9-180307064518 (1).pptx
9-180307064518 (1).pptxRenvic
 
Unit 3 Project management PPT documentss
Unit 3 Project management PPT documentssUnit 3 Project management PPT documentss
Unit 3 Project management PPT documentss19UBCA020HARIHARANK
 
Chapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxChapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxssusercf695b
 
Monitoring and information systems
Monitoring and information systemsMonitoring and information systems
Monitoring and information systemsLibra chudry
 
Preparing cost estimation
Preparing cost estimationPreparing cost estimation
Preparing cost estimationSomashekar S.M
 
Software Project Cost Management and estimation
Software Project Cost Management and estimationSoftware Project Cost Management and estimation
Software Project Cost Management and estimationssuser9d62d6
 
Session 04 - Project Planning II
Session 04 - Project Planning IISession 04 - Project Planning II
Session 04 - Project Planning IIRakeshSinhaPMP
 
CISA_WK_3.pptx
CISA_WK_3.pptxCISA_WK_3.pptx
CISA_WK_3.pptxdotco
 
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
4. PAE AcFn621Ch-4a Project Alaysis and Selection.pptProfDrAnbalaganChinn
 
GOLL+-+Practical+Project+Management+for+Clinical-Biomedical+Engineering.pdf
GOLL+-+Practical+Project+Management+for+Clinical-Biomedical+Engineering.pdfGOLL+-+Practical+Project+Management+for+Clinical-Biomedical+Engineering.pdf
GOLL+-+Practical+Project+Management+for+Clinical-Biomedical+Engineering.pdfKarthikaSampathkumar2
 
Mba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management aMba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management aRai University
 
7 Project planning for software engineering.pptx
7 Project planning for software engineering.pptx7 Project planning for software engineering.pptx
7 Project planning for software engineering.pptxgezaegebre1
 

Semelhante a 09. Project Cost Management (20)

9-180307064518 (1).pptx
9-180307064518 (1).pptx9-180307064518 (1).pptx
9-180307064518 (1).pptx
 
Unit 3 Project management PPT documentss
Unit 3 Project management PPT documentssUnit 3 Project management PPT documentss
Unit 3 Project management PPT documentss
 
Project Cost Management for IEM talk on 13 January 2018.
Project Cost Management  for IEM talk on 13 January 2018.Project Cost Management  for IEM talk on 13 January 2018.
Project Cost Management for IEM talk on 13 January 2018.
 
test
testtest
test
 
Budgeting
BudgetingBudgeting
Budgeting
 
Chapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxChapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptx
 
Monitoring and information systems
Monitoring and information systemsMonitoring and information systems
Monitoring and information systems
 
Preparing cost estimation
Preparing cost estimationPreparing cost estimation
Preparing cost estimation
 
Software Project Cost Management and estimation
Software Project Cost Management and estimationSoftware Project Cost Management and estimation
Software Project Cost Management and estimation
 
PEEM 4.pptx
PEEM 4.pptxPEEM 4.pptx
PEEM 4.pptx
 
MandC.pdf
MandC.pdfMandC.pdf
MandC.pdf
 
Session 04 - Project Planning II
Session 04 - Project Planning IISession 04 - Project Planning II
Session 04 - Project Planning II
 
Project management
Project managementProject management
Project management
 
CISA_WK_3.pptx
CISA_WK_3.pptxCISA_WK_3.pptx
CISA_WK_3.pptx
 
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
 
4.Cost management
4.Cost management4.Cost management
4.Cost management
 
GOLL+-+Practical+Project+Management+for+Clinical-Biomedical+Engineering.pdf
GOLL+-+Practical+Project+Management+for+Clinical-Biomedical+Engineering.pdfGOLL+-+Practical+Project+Management+for+Clinical-Biomedical+Engineering.pdf
GOLL+-+Practical+Project+Management+for+Clinical-Biomedical+Engineering.pdf
 
Mba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management aMba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management a
 
ATCO Engineering - Process Evaluation
ATCO Engineering - Process EvaluationATCO Engineering - Process Evaluation
ATCO Engineering - Process Evaluation
 
7 Project planning for software engineering.pptx
7 Project planning for software engineering.pptx7 Project planning for software engineering.pptx
7 Project planning for software engineering.pptx
 

Mais de BhuWan Khadka

04. Project Management
04. Project Management04. Project Management
04. Project ManagementBhuWan Khadka
 
14. Developing Custom Processes For IT Projects
14. Developing Custom Processes For IT Projects14. Developing Custom Processes For IT Projects
14. Developing Custom Processes For IT ProjectsBhuWan Khadka
 
13. Project Procurement Management
13. Project Procurement Management13. Project Procurement Management
13. Project Procurement ManagementBhuWan Khadka
 
12. Project Risk Management
12. Project Risk Management12. Project Risk Management
12. Project Risk ManagementBhuWan Khadka
 
11. Project Communication Management
11. Project Communication Management11. Project Communication Management
11. Project Communication ManagementBhuWan Khadka
 
10. Project Quality Management
10. Project Quality Management 10. Project Quality Management
10. Project Quality Management BhuWan Khadka
 
08. Project Time Management Upload
08. Project Time Management Upload08. Project Time Management Upload
08. Project Time Management UploadBhuWan Khadka
 
07. Project Integration Management
07. Project Integration Management07. Project Integration Management
07. Project Integration ManagementBhuWan Khadka
 
05. Project And Organizational Structure
05. Project And Organizational Structure05. Project And Organizational Structure
05. Project And Organizational StructureBhuWan Khadka
 
2. Project management body of knowledge
2. Project management body of knowledge2. Project management body of knowledge
2. Project management body of knowledgeBhuWan Khadka
 

Mais de BhuWan Khadka (11)

04. Project Management
04. Project Management04. Project Management
04. Project Management
 
14. Developing Custom Processes For IT Projects
14. Developing Custom Processes For IT Projects14. Developing Custom Processes For IT Projects
14. Developing Custom Processes For IT Projects
 
13. Project Procurement Management
13. Project Procurement Management13. Project Procurement Management
13. Project Procurement Management
 
12. Project Risk Management
12. Project Risk Management12. Project Risk Management
12. Project Risk Management
 
11. Project Communication Management
11. Project Communication Management11. Project Communication Management
11. Project Communication Management
 
10. Project Quality Management
10. Project Quality Management 10. Project Quality Management
10. Project Quality Management
 
08. Project Time Management Upload
08. Project Time Management Upload08. Project Time Management Upload
08. Project Time Management Upload
 
07. Project Integration Management
07. Project Integration Management07. Project Integration Management
07. Project Integration Management
 
05. Project And Organizational Structure
05. Project And Organizational Structure05. Project And Organizational Structure
05. Project And Organizational Structure
 
1. introduction
1. introduction1. introduction
1. introduction
 
2. Project management body of knowledge
2. Project management body of knowledge2. Project management body of knowledge
2. Project management body of knowledge
 

Último

microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...anjaliyadav012327
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDThiyagu K
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room servicediscovermytutordmt
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Disha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfDisha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfchloefrazer622
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 

Último (20)

microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room service
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Disha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfDisha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdf
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 

09. Project Cost Management

  • 2. Horror stories of project failures due to extraordinary cost overruns are reported in the business press on almost a daily basis
  • 3. As a general rule, management and customers are always concerned with how much a project is going to cost in relation to how much a project is going to earn
  • 4. Project cost management • Includes processes involved in planning, estimating, budgeting, financing, funding, managing, and controlling costs so that the project can be completed within the approved budget
  • 5. Why Do We Manage Cost? • Part of triple constraint, can’t manage one without the others (scope, time, and quality) • Plots of cost and scope against plan can help spot problems early Cumulative Value Time Planned Value (PV) Actual Costs (AC) Earned Value (EV) Today Is this project over/under budget? Is it ahead of/behind schedule?
  • 6. Project cost management processes • Plan cost management—establishes the policies, procedures, and documentation for planning, managing, expending, and controlling project costs • Estimate costs—an approximation of the monetary resources needed to complete project activities • Determine budget— aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline • Control costs—monitoring the status of the project to update the project costs and managing changes to the cost baseline
  • 7. Importance of cost estimation • Provides standard against which actual expenditures incurred during the course of a project can be compared, and serve as the basis for cost control • They provide the mechanism for managing cash flow during the course of the project • They give the project manager a framework for allocating scarce resources as the project progresses
  • 8. Errors during project progress Potential for errors in estimates during the various stages of the project progress
  • 9. Classification of project costs • Direct Vs. Indirect • Recurring Vs. Nonrecurring • Fixed Vs. Variable • Normal Vs. Expedited
  • 10. Direct Vs. Indirect • Direct costs- can be directly charged against the project; for example, the costs of personnel who are directly involved in the project, or the costs of materials directly used for project work • Indirect costs- include overhead, as well as selling and administrative expenses Examples of overhead costs include costs associated with taxes, insurance, utilities, and so forth. Costs associated with selling and administrative expenses, commissions, advertising, etc
  • 11. Recurring Vs. Nonrecurring • Recurring costs- such as labor and materials, are repeatedly incurred throughout the project life cycle • Nonrecurring costs- are one-time costs that are typically incurred at the beginning or at the end of the project, such as market research and labor training
  • 12. Fixed Vs. Variable • Fixed costs- do not vary with usage. Example, costs incurred in the purchase of capital equipment remain fixed, regardless of the extent of equipment use • Variable costs- vary directly with usage. They are typically associated with labor and materials
  • 13. Normal Vs. Expedited • Normal costs- are incurred when project tasks are completed according to the original planned duration • Expedited costs- or crash costs are unplanned costs incurred as a result of steps taken to accelerate project completion Example, costs associated with using additional overtime or hiring additional workers specifically to hasten project completion can be regarded as expedited costs
  • 14. Cost classifications Direct labor X X X X Building lease X X X X Expedite X X X X Material X X X X Direct Indirect Fixed Recurring Variable Normal Expedited Costs Non-recurring
  • 15. Cost estimating methods • Ballpark estimates • Feasibility estimates • Definitive estimates • Comparative estimates
  • 16. Ballpark estimates • Also known as ‘‘order of magnitude’’ estimates, often used when there is not sufficient information or time available • Typically, used for making competitive bids for project contracts, or for initial rough-cut estimates of resources needed for a project • As a general rule, ballpark estimates should attempt an accuracy of ±30 percent
  • 17. Feasibility estimates • Are developed after preliminary project design work is completed • Are often used in construction projects, where published information on material costs is widely available • As more relevant information becomes available further down the project life cycle, the ±10 percent margin of error
  • 18. Definitive estimates • Can be developed only after the completion of most design work • Clear understanding of the scope and capabilities of the project, changes to project specifications are virtually nonexistent • Developed further down the project life cycle with more accurate information and fewer project uncertainties, provide a much more accurate expected cost of the project at completion, with a ±5 percent margin of error
  • 19. Comparative estimates • Uses historical data from previous project activities as the frame of reference for current estimates • One of the method is parametric estimation-most projects are similar to previous projects by way of similar features or parameters and, therefore, are likely to incur similar costs. Steps: – Identifying the features/parameters of an older or well-known project that can be directly related to the cost of the current project – Defining the mathematical nature of that relationship
  • 20. Use of learning curves in estimation • Human performance usually improves when a task is repeated • This happens by a fixed percent each time the production doubles • Percentage is called the learning rate
  • 21. Learning curve calculations ( ) ∑= = = = N n r r n nT rate r nTT 1 1 1 timeTotal 2log log Tn = Time for nth unit T1 = Time for first unit N = Number of units R = log decimal rate/log 2 One worker will be tasked to produce all 25 units of air filters. In addition, after production of the 20th unit, there is no significant time reduction associated with learning, and production reaches a steady state of 70 hours. Learning rate is 85%. Time to complete the first activity? r = log 0.85/ log 2 r= −0.1626/0.693 r= −0.235 70 hours = T1 ( 20)-0.235 T1= 141.3 hours
  • 22. Cost estimation and budgeting • Cost estimation and project budgeting are closely linked • Without reasonable cost estimation, project budgets are essentially useless, and without accurate budgeting, cost estimation is a wasted exercise
  • 23. Budgeting • A plan for the costs of project resources • A budget implies constraints • Thus, it implies that managers will not get everything they want or need
  • 24. Budgeting • The budget for an activity also implies management support for that activity • Higher the budget, relative to cost, higher the managerial support • The budget is also a control mechanism • Many organizations have controls in place that prohibit exceeding the budget • Comparisons are against the budget
  • 25. Issues in project budgeting • A project budget identifies the project’s allocated resources, goals, and the schedule that allows the organization to achieve those goals • Developing a project budget requires not only a knowledge of the resources needed, but also information regarding how many will be needed and when, as well as how much they will cost
  • 26. Estimating project budgets • On most projects – Material + Labor + Equipment + Capital + Overhead + Profits = Bid • In other words – Resources + Profits = Bid • So we are left with the task of forecasting resources
  • 27. Estimating project budgets • Like any forecast, this includes some uncertainty • There is uncertainty regarding usage and price – Especially true for material and labor • The more standardized the project and components, the lower the uncertainty • The more experienced the cost estimator, the lower the uncertainty
  • 28. Rule of thumb • Some estimates are prepared by rules of thumb • Construction cost by square feet • Printing cost by number of pages • Lawn care cost by square feet of lawn • These rules of thumb may be adjusted for special conditions • However, this is still easier than starting the estimate from scratch
  • 29. Difficulties • There may not be as much historical data or none at all • Even with similar projects, there may be significant differences • Many people have input and some control over the budget
  • 30. Difficulties • There is more “flexibility” regarding the estimates of inputs (material and labor) • The accounting system may not be set up to track project data • Usage of labor and material is very lumpy over time
  • 31. Types of budgeting • Top-down • Bottom-up • Negotiated • Activity based costing
  • 32. Top-down • Top managers estimate/decide on the overall budget for the project • These trickle down through the organization where the estimates are broken down into greater detail at each lower level • The process continues to the bottom level
  • 33. Advantages • Overall project budgets can be set/controlled very accurately • Management has more control over budgets Disadvantages • More difficult to get buy in • Leads to low level competition for larger shares of budget
  • 34. Bottom-up budgeting • Project is broken down into work packages • Low level managers price out each work package • Overhead and profits are added to develop the budget
  • 35. Advantages • Greater buy in by low level managers • More likely to catch unusual expenses • People tend to overstate their budget requirements • Management tends to cut the budget Disadvantages
  • 36. An iterative budgeting process– negotiation-in-action • Most projects use some combination of top-down and bottom-up budgeting • Both are prepared and compared • Any differences are negotiated
  • 37. Snapshot from practice How do you estimate the cost of a nuclear power plant?
  • 38. Activity based costing • Activity-based costing (ABC) is frequently used for project budgeting. The basis of activity-based costing is that projects consume activities, and activities consume resources
  • 39. Steps in activity-based costing • Assign costs to activities that use resources (costs are assigned to each work package) • Identify cost drivers associated with this activity( like human resource in many cases) • Compute a cost rate per cost driver unit or transaction (cost of labor per hour) • Multiply the cost driver rate times the volume of cost driver units used by the project Rs50/hour 100 hours = Rs5,000.00∗
  • 40. Budget contingencies • The allocation of extra funds to cover uncertainties and improve the chance of finishing on time • It is an important aspect of project finance, because it provides a certain amount of protection against unknown and uncertain elements that can derail a project
  • 41. Contingencies are needed because • Project scope may change • Murphy’s Law is present “If anything can go wrong, it will” • Cost estimation must anticipate interaction costs Hidden cost • Normal conditions are rarely encountered
  • 42. Benefits to include contingency • Recognizes that the future is uncertain, and that unexpected problems can increase overall project costs • Contingency estimates make explicit provisions for potential and unexpected cost increase in project plans and budgets • The use of contingency funds provides an early warning signal of potential cost overruns
  • 43. More on Project Cost Management
  • 44. Cost Management Key Terms • PV - Planned Value, estimated value of the planned work • EV – Earned Value, estimated value of work done • AC – Actual Cost, what you paid • BAC – Budget at Completion, the budget for the total job • EAC –Estimate at Completion, what is the total job expected to cost? • ETC – Estimate to Complete, forecasted costs to complete job • VAC – Variance at Completion, how much over/under budget do we expect to be?
  • 45. How Do We Manage Cost? • Three processes – Estimate Costs – Determine Budget – Control Costs Estimate Costs Determine Budget Control Costs
  • 46. Estimate Costs Enterprise Environmental Factors Organizational Process Assets Project Scope Statement Analogous estimating Determine resource cost rates Bottom up estimating Parametric estimating Project management software Vendor bid analysis Reserve analysis Cost of quality Inputs OutputsTools & Techniques Work Breakdown Structure WBS Dictionary Project Management Plan •Schedule Mgmt Pln •Staffing Mgmt Pln •Risk Register Activity Cost Estimates Activity Cost Estimates Supporting Detail Requested Changes Cost Management Plan Updates Estimate Costs Determine Budget Control Costs
  • 47. Other Estimating Methods • Parametric estimating – Use mathematical model (i.e. cost per sq ft). [accuracy varies] Two types: • Regression analysis – based on analysis of multiple data points • Learning Curve – The first unit costs more than the 100th , forecasts efficiency gains • Vendor Bid Analysis – Estimating using bids + allowances for gaps in bid scope [slow, accuracy depends on gaps] • Reserve Analysis – Adding contingency to each activity cost estimates as zero duration item [slow, overstates cost]
  • 48. Determine Budget Project Scope Statement Cost aggregation Reserve analysis Parametric estimating Funding limit reconciliationInputs Outputs Tools & Techniques Cost Baseline Project Funding Requirements Cost Management Plan Updates Requested Changes Work Breakdown Structure WBS Dictionary Activity Cost Estimates Activity Cost Estimates Supporting Detail Project Schedule Resource Calendars Contract Cost Management Plan Estimate Costs Determine Budget Control Costs
  • 49. Determine Budget • Budgeting is allocating costs to work packages to establish a cost baseline to measure project performance • Remember Contingency items are for unplanned but required changes it is not to cover things such as: – Price escalation – Scope & Quality Changes • Funding Limit Reconciliation – Smoothing out the project spend to meet management expectations
  • 50. Control Costs Cost Baseline Project Funding Requirements Performance Reports Cost change control system Performance measurement analysis Forecasting Project performance reviews Project management software Variance management Inputs OutputsTools & Techniques Work Performance Information Approved Change Requests Project Management Plan Cost Estimate Updates Cost Baseline Updates Performance Measurements Forecasted Completion Requested Changes Recommended Corrective Actions Organizational Process Assets Updates Project Management Plan Updates Estimate Costs Determine Budget Control Costs
  • 51. Earned Value • Progress is compared against the baseline to determine whether project is ahead of or behind plan • Percent complete can be difficult to measure, some managers use rules – 50/50 Rule – Assumed 50% complete when task started, final 50% at completion – 20/80 Rule – 20% at start – 0/100 Rule – No credit until complete • Planned Value (PV) – Budgeted Cost • Earned Value (EV) – Actual work completed • Actual Cost (AC) – Costs incurred • Estimate to Complete (ETC) – What’s Left • Estimate at Completion (EAC) – What final cost will be
  • 53. Earned Value Formulas NAME FORMULA NOTES Cost Variance (CV) EV-AC Negative = Over budget Positive = Under budget Schedule Variance (SV) EV-PV Negative = Behind Schedule Positive = Ahead of Schedule Cost Performance Index (CPI) EV/AC How much are we getting for every dollar we spend? Schedule Perform Index (SPI) EV/PV Progress as % against plan Estimate to Complete (ETC) EAC-AC How much more do we have to spend? Variance at Completion (VAC) BAC-EAC At the end of the day, how close will we be to plan? Estimate at Completion (EAC) See following slide
  • 54. Earned Value Formulas (Cont’d) NAME FORMULA NOTES Estimate at Completion (EAC) •BAC/CPI Use if no variances from BAC have occurred •AC+ATC Use when original estimate was bad. Actuals + New estimate •AC+BAC-EV Use when current variances are not expected to be there in the future •AC+(BAC-EV)/CPI Use when current variances are expected to continue
  • 55. Tricks for Earned Value • EV is always first • Variance = EV minus something • Index = EV divided by something • If the formula relates to cost use AC • If the formula relates to schedule use PV • Interpreting results: negative is bad and positive is good • Interpreting results: greater than one is good, less than one is bad PV AC ETC EAC BAC Project Start Current Status
  • 56. Terms to Remember • Present Value • Net Present Value (NPV) • Internal Rate of Return (IRR) • Payback Period • Benefit Cost Ratio = BCR>1, Payback is greater than the cost • Opportunity Cost • Sunk Cost • Working Capital • Straight Line Depreciation • Accelerated Depreciation • Double Declining Balance • Sum of Years Digits • Value Analysis (Value Engineering)
  • 57. • To illustrate the concept of EVM and all the formulas, assume a project that has exactly one task. The task was baselined at 8 hours, but 11 hours have been spent and the estimate to complete is 1 additional hour. The task would have been completed already. Assume an Hourly Rate of $100 per hour.
  • 58. • Budget at Completion (BAC) is the total budget allocated to the project. • Estimate to Complete (ETC) is the estimated cost required to complete the remainder of the project. • Estimate at Completion (EAC) is the estimated cost of the project at the end of the project. • Variance at completion (VAC) is the variance on the total budget at the end of the project.
  • 59.
  • 60.
  • 63. Sample budget showing planned and actual activity costs and variances
  • 64. Sample of a time-phased budget