Crane Lifting Plan
LIFTING OPERATION
METHOD STATEMENT/LIFT PLAN & RISK ASSESSMENT
DETAILS FOR THE PROVISION OF A LIFT OPERATION IN
COMPLIANCE WITH
BS7121 – PARTS 1 & 3 AND LOLER REGULATIONS
Please tick as appropriate:
 Completed by appointed person for crane hired by Weston Homes, or
 Completed by contractor who has hired a crane as part of their work
Client Weston Homes Plc
Project
Site Address
Date of Operation
Time on Site
Client/Site Contact
Contact Number
Appointed Person
Contact Number
Appointed Person’s Acceptance of Responsibilities:
I confirm that the lifts in the Method Statement have been planned and will be carried out in accordance with current
legislation and British Standard 7121 and that I accept responsibility for the preparation of this Method Statement and Risk
Assessment. I accept that it is my responsibility as the Appointed Person to ensure that the Lift Supervisor is adequately
briefed on the contents of this Method Statement.
Signed Date
CONTENTS
Page Page
Introduction 28 Crane Set Up Procedure 37
General Conditions 29 Lift Procedure 37
Weather Conditions 29 Crane De-Rig Procedure 39
Ground Conditions 29 On Site Changes 39
Operation Outline 30 Risk Assessment 40
Site Details 31 Site Register & Toolbox
Talk
43
Load & Radius Details 32 Drawings Attached
Crane & Lift Information 34
1 INTRODUCTION
1.1 It is the aim of this Method Statement to define and describe the equipment and safety procedures which are to be employed
by the crane lifting company to carry out the lifting operation. The operation will be carried out in accordance with the following
Legislation & Approved Codes of Practice.
BS7121 Safe Use of Cranes (part 1) 2006 General & (part 3) 2000 Mobile Cranes
Lifting Operations & Lifting Equipment Regulations 1998 (LOLER)
Health & Safety at Work Act 1974 - Provision and Use of Work Equipment Regulations (PUWER) 1998
Manual Handling Operations Regulations 1992 - Noise at Work Regulations 2006
Control of Substances Hazardous to Health Regulations 2002 (COSHH)
Construction Design and Management Regulations 2007 - Working at Height Regulations 2007
1.2 THE LIFT
The lift will be carried out in line with the guidance contained in BS7121.
1.3 SITE INSPECTION
The Appointed Person shall carry out a detailed site inspection to ascertain the full requirements of the Site Manager and
determine the required crane capacity and make an assessment as far as possible/practicable of any other site issues such as
access, ground conditions, overhead obstructions, local authority interaction etc.
1.4 THE APPOINTED PERSON
The Appointed Person who has prepared the Method Statement carries full responsibility for the safe completion of all works
carried out during the operation. It is the responsibility of the Appointed Person to ensure that the Crane Supervisor is
adequately briefed on the contents of this Method Statement.
1.5 THE CRANE SUPERVISOR
Prior to the commencement of the works, the Crane Supervisor must ensure that all site personnel are adequately briefed on
the contents of this Method Statement. This briefing shall take the form of a short ‘Toolbox Talk’. The Crane Supervisor must
liaise with the Appointed Person should site circumstances require material change to the methods to be employed during the
operation.
1.6 THE CRANE OPERATOR or OPERATORS
All lifting operators or any operators working on behalf of the lifting company shall be fully trained and competent on the
machines they operate and will have undergone full manufactures induction and training.
1.7 PERSONNEL
All lifting personnel or any personnel working on behalf of the lifting company will be fully trained and hold the relevant
certification for the role they undertake on the day of operation. Any non lift company personnel or personnel supplied by the
client that will be involved in the lifting operation and taking on a specified role will be required to produce the relevant
certification to the Appointed Person or Crane Supervisor prior to the commencement of the operation. Failure to produce the
required certification will result in the suspension and possible cancellation of the lifting operation.
1.8 PERSONAL PROTECTIVE EQUIPMENT
All lifting personnel will be supplied with standard PPE which consists of, Hard Hat, Safety Boots, Overalls, Gloves, Hi-Vis (and
Safety Goggles if required).
The Site Manager must inform all Personnel of any specific requirements in advance of the operation date.
1.9 CERTIFICATION
Copies of statutory test certification and inspection reports will be available for inspection prior to the lifting operation taking
place.
2 GENERAL CONDITIONS
2.1 The Site Manager will provide details of all items to be lifted, including weights, dimensions and any specific lifting tackle
requirements. The Site Manager is responsible for the structural integrity of all loads to be lifted including any specified lifting
points or slinging recommendations.
2.2 The Site Manager must ensure safe access to and egress from site for all lifting personnel and vehicles, and also ensure that the
working area is clear of all obstructions to allow the safe assembly and working of the crane. The Site Manager will be
responsible for supplying suitable floodlighting where necessary or when required.
The Site Manager must carry out any enabling works required prior to crane arrival.
2.3 The Site Manager must ensure that the area where the crane is to stand/operate is firm and level and this it is capable of
withstanding the expected loadings that will be imposed upon it.
2.4 The Site Manager must ensure that any Traffic Management (not supplied by the lift company) is in place prior to the
positioning of the crane.
2.5 Any personnel not directly concerned with the lift must be kept out of the crane assembly and working area. The working area
should be cordoned off with barrier tape, temporary fencing or otherwise secured, to prevent non lift associated personnel or
the general public from entering the lifting area.
2.6 The Crane Supervisor shall make himself known to all relevant personnel on site, and conduct a ‘Toolbox Talk’ prior to
commencing operations. The Site Manager should arrange for a site specific induction for the lifting personnel prior to the
commencement of work. The Site Managers Site Risk Assessment, which identified any site hazards should be made available
and brought to the attention of the lifting personnel.
2.7 All cranes to be left unattended for a period, shall be left in safe condition (jib retracted or laid down if possible), with not load
on the crane hook. Cranes shall be shut down and isolated as per manufacturer’s instructions, secured and locked. Under no
circumstances shall the crane be moved for lifting purposes if not under the instruction of the Crane Supervisor.
2.8 In the event that specified cranes or lifting tackle, cannot be supplied on the day of operation due to operational issues,
breakdown or any unforeseen circumstances. The lift company has the discretion to supply cranes or equipment that is of a
suitable alternative to that detailed in this Method Statement, (at no extra cost to the client). In the event of this situation
arising, the Appointed Person and the Site Manager will be notified. The AP/Crane Supervisor will ensure that any changes do
not infringe on the factors or safety within this method statement.
3 WEATHER CONDITIONS
3.1 In the event of extreme weather conditions the lift company may need to suspend the lifting operation until such time as it is
safe to proceed. Although the safe workable wind speed varies from crane to crane, as a guide, the maximum wind speed at
which lifting operations can take place is 10 metres per second, (22mph).
In the event that man riding duties are required the maximum workable wind speed reduces to 7 metres per second, (16mph).
Please note that local conditions and the safety of personnel may dictate the Crane Supervisor and Crane Operator have to
suspend lifting operations at a lower wind speed than specified in this Method Statement. In addition, lifting operations must
stop during storms or when there is a risk of lightning strikes.
4 GROUND CONDITIONS
4.1 The lift company will endeavour to advise the client regarding ground conditions, after a visual inspection (or where
necessary/provided, perusal of a client ground survey report) and supply suitable plates, mats where required. The Client is
required to advise the lifting company of any known underground services, voids or vaults as state in BS7121. Safe Use of
Cranes.
5 OPERATION OUTLINE
5.1 LIFT CLASSIFICATION
LIFT CLASSIFICATION
Basic Lift Standard Lift Complex Lift
Full Contract Lift Supervisor Only Contract
Lift
Note:
If a “Supervisor Only Contract Lift” is the chosen option, it is imperative that any personnel supplied by the client, be fully
trained, competent and experienced in lifting operations and hold current, valid and legislatively required certification, which
must be available for our Appointed Person or Crane Supervisor to inspect prior to commencement of the lifting operation.
Any personnel supplied by the Site Manager must work under the instruction of the Appointed Person or Crane Supervisor.
Failure to comply with the above will results in the suspension of lifting until the aforementioned is adhered to.
5.2 PERSONNEL
The following numbers of personnel for this lift are needed:
Crane Operator Crane
Supervisor
Slinger/Signaller
5.3 COMMUNICATIONS
Communications between the lifting crew and Crane Operator/s shall be maintained by means of
Two-Way
Radios Supplied
by the Crane
Company
Two-Way
Radios
Supplied by
Site Manager
Hand
Signals
5.4 WEATHER CONDITIONS
Maximum Workable Wind Speed for
the Crane is:
Weather forecast to be obtained on morning of lift, confirming wind
direction and strength. Wind speed forecast 15.6mph.
Guide: 10 metres per second (22mph) for load lifting. 7 metres per
second (16mph) for man riding duties.
5.5 BRIEF SCOPE OF WORK/NOTABLE FEATURES OF THIS LIFTING OPERATION
6 SITE DETAILS
6.1 ENABLING WORKS
Any enabling works discussed and agreed to at the site inspection, should be carried out prior to arrival of the crane.
Are any enabling works required
6.2 ACCESS & EGRESS
The Site Manager shall ensure that the crane and all associated vehicles have safe and unimpeded access and egress to and
from site.
Details of site access & egress
6.3 GROUND CONDITIONS – including any underground services, voids or vaults.
Details of ground conditions
6.4 OVERHEAD CABLES, OBSTRUCTIONS OR REGULATIONS & ANY SLEWING RESTRICTIONS
Details of any overhead or slewing
restrictions
6.5 TRAFFIC AND PEDESTRIAN MANAGEMENT
Traffic Management Required Pedestrian
Management
Required
Arranged by
Details of any Restrictions & Local Authorities Concerned
7 LOAD & RADIUS DETAILS
7.1 LOAD DETAILS (to be provided by The Site Manager)
In the event of there being multiple lifts of different weights and dimensions, only the details of the maximum required lifts will
be shown.
Description Dimensions Weight
7.2 LIFTING POINTS
It is the Site Managers/Plant Managers responsibility to ensure that any manufactured Lifting Points are certified & tested for
lifting purposes. This also applies to specified slinging methods where no lifting points are provided.
Does the load have Manufactured Lifting Points or Manufacturer guidance for the method
of lifting that has been approved for use by the Site Manager?
If “No” to the above:
Has the Appointed Person assessed and agreed a method of slinging with the Site
Manager?
Has the Centre of Gravity been taken into account for all proposed lifts?
Have the lifting points and/or the lifting method been approved for
use by the Appointed Person?
7.3 LIFTING TACKLE
Please Note:
In the event that the specified lifting tackle cannot be supplied on the day of operation due to operational changes, breakdown
or any unforeseen circumstances. The crane company can supply and use lifting tackle/equipment that is of a suitable
alternative to that detailed above. In the event of this situations arising, the Appointed Person and Site Manager should be
notified. The AP/Crane Supervisor will ensure that any changes do not infringe on the factors of safety within this Method
Statement.
All Lifting Tackle certification to be available on site.
The Crane Supervisor shall inspect all Lifting Tackle prior to each use.
Any Lifting Tackle supplied by the Site Manager to be fit for purpose, fully certified and in good condition.
Any damaged tackle shall be marked “Not For Use” and returned to the depot for disposal.
Nylon Slings must be protected from sharp edges using sling guards or suitable packaging.
7.4 CALCULATED MAXIMUM LIFT WEIGHTS
In the event of there being multiple lifts of different weights, only the details of the maximum required lift/s will be shown.
Weight of Load
Weight of Hook Block
Weight of Lifting Tackle
Weight of Fly/S-Lift on Boom
7.5 CALCULATED MAXIMUM RADIUS
Maximum Required Radius
7.6 MAXIMUM CALCULATED LIFTS
Gross lift weight
In the event that any loads (lighter than the maximum load) are required to be lifted to a greater radius than the maximum
loads, see below:
Maximum required radius
Gross Lift Weight
To be lifted to a radius of
Weight to be lifted at max
radius
8 CRANE & LIFT INFORMATION
8.1 CRANE/S DETAIL
CRANE
Crane (make & model)
Registration and/or
Plant No.
4 Yearly Test and
Thorough Examination
12 Month Thorough
Examination (6 Months
if Crane is used for
Lifting People)
Weekly Crane
Inspection
YES NO
Certificate Expiry Date YES NO
8.2 REQUIRED WEIGHT & RADIUS
Gross Lift Weight
Required Radius
SWL of Crane at Required
Radius
Safety Margin
In the event that any loads (lighter than the maximum load) are required to be lifted to a greater radius than the maximum
loads, see below:
LOAD
Maximum Required Radius
Gross Weight at Max Radius
SWL of Crane
Safety Margin
8.3 OUTRIGGER LOADINGS & MATS
Outrigger Point Load
Mat Size
Mat Area Provided
Please Note that the Site Manager is responsible for ensuring that the ground conditions are suitable to accept the above
loadings and pressures.
REGISTER OF LIFTING EQUIPMENT – TO BE COMPLETED BY CRANE SUPERVISOR
Project:
Lifting equipment (e.g. chains or strops)
Description ID No. /
Reg.
Supplier: Test Cert.
Expiry Date:
12 Monthly
Thorough
Examination
Expiry Date:
Used for lifting
persons? Y/N.
(If so, 6 Monthly
Thorough Exam’n?)
Weekly
Inspections
carried out by:
THIS PAGE IS INTENTIONALLY BLANK
CRANE & LIFT INFORMATION (Continued)
9 CRANE SET UP PROCEDURE
THE CRANE TEAM
Crane Supervisor:
CITB CTA Card Expiry Date:
Appointed Person:
Slinger/Signaller(s):
CITB CTA Card Expiry Date:
Crane Driver:
9.1 The crane, together with the associated operating crew will arrive on site at the specified and agreed
date and time.
9.2 Crane Supervisor will meet the Site Manager and carry out “Toolbox Talk” with all personnel involved in
the lifting operation. Once this has been completed, all involved in the lifting operation must sign the
register for this Method Statement. Any site inductions that are required will also be carried out.
9.3 Any traffic management, ancillary pans, mats or temporary roadways etc that are required to be
positioned by hi-ab or other means, prior to the crane or cranes manoeuvring into position, will be
done under the instruction of the Crane Supervisor.
9.4 The crane will then manoeuvre into position as shown on attached drawing. All manoeuvring to be
carried out under the guidance of a member of the lifting crew.
9.5 The crane will then commence set-up procedure and rig to the configuration stated in section 8.1. All
personnel assisting with rigging will be under the guidance of the crane operator, at all times. The set-
up procedure will be carried out as per crane manufactures manual.
9.6 Upon completion of the rigging procedure, the crane operator will carry out procedural safety and
computer checks, implementing any specific operational requirements, i.e. slewing restrictions, short
rig configurations or fly jib configurations.
9.7 The Crane Supervisor will then carry out a radio communications check between the crane operator
and the lifting crew.
9.8 Hook block of crane will then be lowered and required lifting tackle placed on the hook, Lift Supervisor
will ensure that the correct lifting tackle has been selected.
9.9 The crane operator will then be instructed to hoist lifting tackle clear of any obstructions and position
the crane ready for the first required lift. Any delivery/removal vehicles will now be positioned adjacent
to the crane as per attached drawings, ready for work to commence.
10 LIFTING PROCEDURE
10.1 Slinger/Signallers will issue instructions via hand signals or two-way radios to the crane operator to
position the crane over first required lift, Slinger/Signallers will plumb the boom head, directly over the
load or set short to allow for jib deflection where necessary.
10.2 The Slinger/Signallers will instruct crane operator, the lower the hooks with lifting tackle to allow
Slinger/Signaller to attach lifting tackle to load.
LIFTING PROCEDURE (Continued)
10.3 All slinging will be carried out by fully trained, certificated and experienced slingers.
Slinging methods adopted will be as specified by load manufacturers, using specified lifting points or, in
the event that no manufacturer instruction or lifting points are provided, our Slingers will work to the
Appointed Persons recommendations and to Health & Safety executives guidelines for safe slinging for
lifting loads, (see section 7.2 & 7.3).
The lifting tackle used, will be as stated in section 7.3 and will have current test certification available.
10.4 Upon completion of the attachment of the lifting tackle to the load, the Slinger/Signaller will instruct
the operator by hand signals or radios, to hoist up to take the slack out of the lifting tackle. Once the
lifting tackle has started to take the weight and has tightened the Slinger/Signaller will instruct operator
or operators to stop hoisting. The Slinger/Signaller will then carry out a check around the load to ensure
that the lifting tackle is sitting correctly, angled correctly and also check any lifting points for security
and correct operation.
10.5 Once lifting tackle check has been carried out the Slinger/Signaller will instruct the crane operator or
operators, to hoist the load to a height that allows the lifting tackle to take the full weight of the load
and again instruct the operator to stop hoisting when the load is just airborne to allow a final check of
the lifting tackle and lifting points and also check the structural integrity of the load.
10.6 Once the Slinger/Signaller is confident that the lifting tackle and the load are secure, any tag lines that
may be required will be attached to the load. Instructions will then be given to the crane operator or
operators to hoist the load clear of any obstructions, ensuring that any site specific risks are monitored
throughout the hoisting procedure.
10.7 Once the load is clear of all obstructions, the Slinger/signaller will give instructions to the crane
operator to manoeuvre the load as required for railing, or manoeuvre to the required landing area for
single crane lifts.
10.8 In the event that the landing area is at a different level or should access not permit, the Slinger/Signaller
will pass control of the crane signalling to a second strategically placed Slinger/Signaller at the landing
area.
10.9 The landing area Slinger/Signaller will then commence giving instructions to the crane operator or
operators to manoeuvre and lower the load to the required landing point, ensuring that any site specific
risks are monitored throughout the landing procedure.
10.10 The Slinger/Signaller will guide the load to the correct orientation as the load becomes contactable by
hand or by attached tag lines.
10.11 The Slinger/Signaller will instruct the crane operator to lower the load to just above the landing position
and then instruct the operator to stop lowering to allow the Site Manager to confirm position and
orientation of load prior to landing.
10.12 Once the position is confirmed by the Site Manager, the Slinger/Signaller will instruct the operator to
slowly lower load into position. Once landed, a final position check will be made before the
Slinger/Signaller instructs the operator to lower off all load weight.
10.13 Slinger/Signaller will instruct the operator to lower off, to allow lifting tackle to be released from the
load. In the event that any load is too large or high for safe access by ladder, powered access
equipment or a lifted man basket will be used to remove slings from loads.
10.14 Once lifting tackle is detached from the load, the Slinger/Signaller will instruct the operator to slowly
hoist the lifting tackle clear of the load and any site specific risks ensuring that no snagging occurs.
10.15 Once the lifting tackle is clear of all obstructions the Slinger/signaller will instruct the crane operator to
manoeuvre the crane ready for any further lifts that may be required and had over to another
Slinger/Signaller were required.
10.16 All other required lifts will be carried out as stated in sections 11.1 to 11.5. The Lift Supervisor will
ensure that all lifting and operational procedures are followed as per the Appointed Persons
recommendations and that any queries or deviation from this Method Statement are notified
immediately to the Site Manager and the Appointed Person.
11 DE-RIG PROCEDURE
11.1 Upon completion of the lifting operation, the Crane Supervisor will instruct the crane operator to load
any ancillary equipment or heavy lifting tackle onto relevant transport ready for removal from site.
11.2 The Crane Supervisor will then instruct the crane operator to lower all lifting tackle to the ground to
allow removal from hook.
11.3 The crane operator will then instigate the removal of any lifting tackle stored on the crane and then
commence the de-rig procedure.
11.4 All personnel assisting with de-rigging will be under the guidance of the crane operator at all times.
The de-rig procedure will be carried out as per crane manufacturers manual.
11.5 Once the crane has been de-rigged and all safety checks for road travel have been carried out the crane
operator will manoeuvre the crane/s off site, under the guidance of a member of the lifting crew. The
crane will then proceed on its way.
11.6 The remaining members of the lifting crew will ensure that any ancillary mats or equipment etc are
removed from site or placed in an appropriate position ready for collection prior to them leaving site.
11.7 Any traffic or pedestrian management arranged by the lift company will be unimplemented and
removed.
11.8 The Crane Supervisor will inform the Site Manager or site representative of the completion of the
operation and address any issues that may be raised and inform of any equipment left on site for later
collection.
12 ON SITE CHANGES/ADDITIONAL LIFTS
12.1 Any changes to this Method Statement & Lifting Plan must be notified to and approved by the
Appointed Person. Any crane position changes or amendments to drawings must also be notified and
approved by the Appointed Person.
Amendment Details
1)
2)
3)
4)
5)
6)
7)
8)
9)
10)
Changed discussed with and approved by the Appointed Person
Crane
Supervisor
Date
(Sign & Print)
13 RISK ASSESSMENT
The aim of this risk assessment is to highlight any possible hazards that are likely to occur during the lifting
operation.
Upon its completion with either a “High, Medium, Low or N/A” in the Risk Rating Box and either a “” or
“N/A” in the Risk Managed box, the document coverts to a site specific assessment.
Identified
Hazards
Risk
Risk
rating
Prevention Measures
Risk
Managed
Access to and
Egress from
Site
Interaction with public highway and
members of the public. Interaction
with other site operations and
operatives. Interaction with delivery
vehicles.
Risk to: Public/ Operators/ Site
Operatives
High Banksman with hi-vis to control traffic and
public while crane manoeuvring into site.
Flashing amber lights and audible alarms
when reversing.
Site management to be aware of intended
route on site.
All other site operatives to be made aware
of crane movement.

Low
Medium
Low
N/A
Ground
Conditions
Crane travelling over unprepared or
uneven ground possible damage to
ground surface and or crane and
property.
Ground collapse beneath outriggers
causing possible overturning.
Risk to: Public/ Operators/ Site
Operatives
High
Ground to be assessed at time of site
inspection. Ground improvement to be
implemented where needed.
Operator/Crane Supervisor to inspect on
day of operation.
Outrigger pans to be used with additional
heavy duty mats where needed. Client to
inform the crane company of any known
risks

Low
Medium
Low
N/A
Underground
Services
Damage to sub-surface service lines
causing possible flooding, explosion,
High
A full assessment and mapping of the

asphyxiation or electrocution.
Risk to: Public/ Operators/ Site
Operatives
Medium
travelling and working area of the crane
will be made at the site inspection.
The Site Manager to make the crane
operator aware of any known risk.
Permit to work in place where applicable.
Operator/ Crane Supervisor to check on day
of operation for any new or unseen risks.
Low
Low
N/A
Crane
Positioning
-
Set up
Procedure
-
De-rig
Procedure
Crane positioned incorrectly for
required lift.
Possible damage to crane or property
during set up or de-rig procedure.
Risk to: Public/ Operators/ Site
Operatives
High
Crane working position clearly identified in
Method Statement drawings and made
known to crane operators and marked out
where required.
Crane manufacturer’s instructions for set
up and de-rig procedure followed. Only
trained and competent personnel to
operate and assist with rigging. No one but
lift associated personnel within crane set
up area.

Low
Medium
Low
N/A
Plant
Operations
Crane operation, causing damage to
property or injury to personnel.
Mechanical breakdown or structural
damage.
Risk to: Public/ Operators/ Site
Operatives
High
Trained, certified and competent crane
operators.
Cranes fully maintained with full service
and testing history.
Manufacturer’s instructions adhered to at
all times.

Low
Medium
Low
N/A
Identified
Hazards
Risk
Risk
rating
Prevention Measures
Risk
Managed
Manual
Handling
-
Sling of Loads
-
Signalling
-
Tailing
Operations
-
Multiple
Crane
Operations
Incorrect slinging of loads.
Unsuitable lifting equipment used.
Failure of lifting equipment.
Incorrect signals give to crane
operator causing damage to loads,
property or injury to personnel. Crane
operator lifting unseen loads.
Risk to: Public/ Operators/ Site
Operatives
High
Trained, certified and competent Slingers to
sling all loads. Only specified lifting tackle
and lifting tackle with current and valid
certification to be used. Visual inspection to
be carried out on all lifting tackle prior to
use. Qualified Signallers to use recognised
hand signals or radio commands to
communicate with crane operators.
Radios used for unsighted lifts.

Low
Medium
Low
N/A
Working at
Height
-
Ladders
-
Scaffolding
-
Access
Platforms
-
Man Baskets
Personnel falling from height during
crane assembly and or lifting
operations.
Personnel falling from delivery
vehicles during slinging of loads.
Operation of mechanical platforms.
Personnel working from man Baskets.
Risk to: Public/ Operators/ Site
Operatives
High Operators to work from footed ladders for
crane assembly.
Slingers to work from footed ladders for
slinging loads where reasonably
practicable.
Work platforms or lifted man basket to be
used where a height risk is deemed
excessive. Access operators to be IPAF
trained.
Site to ensure all working areas at height
are safe with suitable guard rails. Harnesses
to be worn where required / practicable. All
scaffolds to be certified for working use.

Low
Medium
Low
N/A
Protection of
Public & Site
Operatives
-
Falling
Objects
Injury to public or site personnel from
falling objects or materials.
Damage to vehicles or property during
lifting operations. Risk from
suspended loads.
Risk to: Public/ Operators/ Site
Operatives
High Work area to be cordoned off as an
exclusion zone.
Sufficient barrier & signage to be in place to
warn non lift associated persons of
overhead & ground level risks. All over-sail
to be addressed, monitored and evacuation
implemented where practicable. Lift crew
to be aware of all lifting operations.

Low
Medium
Low
N/A
Traffic
Pedestrian
Management
Damage to property or plant. Risk of
responsibility for collision or injury.
Protection of personnel during works.
Risk to: Public/ Operators/ Site
Operatives
High Full assessment of required restrictions on
public highways, service roads or private
roads to be made at site inspection. Any
Traffic Management contractors supplied
by site or the crane company will be fully
certified and competent. Traffic
Management supplied by the site should be
set up prior to arrival of crane.

Low
Medium
Low
N/A
Adverse
Weather
Conditions
Crane operation, load stability and
control.
Risk of injury to personnel and
damage to property.
Risk of lightning strike. Bad visibility.
Risk to: Public/ Operators/ Site
High Weather reports obtained before and
during lifting operations.
Crane operator to monitor wind speed
equipment.
Suspension of lifting operation until risk
subsides.

Low
Medium
Low
Operatives
N/A
Identified
Hazards
Risk
Risk
rating
Prevention Measures
Risk
Managed
Overhead or
slewing
Obstructions
or
Restrictions
-
Low
Headroom
Damage to crane or property if crane
boom or superstructure comes into
contact with any restriction.
Infringement of unauthorised air
space. Working in restricted work
space.
Risk to: Public/ Operators/ Site
Operatives
High Full assessment of any risks made and
addressed at site inspection. Safe system of
work adhered to where implemented.
Work to zone alarms where implemented.
Implement crane swl computer working
restrictions.
All relevant authorities contacted and
advised and any restrictions adhered to.

Low
Medium
Low
N/A
ADDITIONAL SITE SPECIFIC RISKS
ADDITIONAL RISKS IDENTIFIED ON DAY OF OPERATIONS
ADDITIONAL RISKS DUE TO ON SITE CHANGES
Identified
Hazards
Risk Risk
Rating
Prevention Measures Risk
Managed
14 SITE REGISTER/TOOLBOX TALK
All operational staff involved in this lifting operation must read this method Statement or have had the
contents of it explained in detail to them prior to commencing work.
All persons involved in this lifting operation are to sign below in acceptance that a detailed briefing of this
operation has been given and understood.
All certification has been checked and verified prior to the lifting operation commencing.
Crane Supervisor’s Acceptance of Responsibilities:
I confirm that I have been fully briefed on the contents of this Method Statement and Risk Assessment and that I
accept the duty of ensuring that the lift/s will be carried out in accordance with the Methods and Procedures set
out in this Document.
Signed Date
Print Name Position Signature Date
Site Manager Acceptance of this Method Statement
I confirm that I have read and understood this Method Statement and Risk Assessment and that I
accept the responsibilities of the site management with respect to Safe Use of Cranes (part 1) 2006
General and (part 3) 2000 Mobile Cranes.
Signed Date
SUMMARY
Crane Detail Site
ManagerCrane
Site
Project
Detail
Req Radius
SWL SES
Point Load Date Issue No
THIS PAGE IS INTENTIONALLY BLANK

Mais conteúdo relacionado

Mais procurados

12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templates12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templatesDwarika Bhushan Sharma
 
Risk Assessment Example.pdf
Risk Assessment Example.pdfRisk Assessment Example.pdf
Risk Assessment Example.pdfBalamuruganD26
 
9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templates9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templatesDwarika Bhushan Sharma
 
10. lifting-plan-checklist-and-method-statement-2
10. lifting-plan-checklist-and-method-statement-210. lifting-plan-checklist-and-method-statement-2
10. lifting-plan-checklist-and-method-statement-2Sergio Augusto Esteves
 
Liftingproedure
LiftingproedureLiftingproedure
LiftingproedureZhai Rull
 
Overhead crane risk assessment
Overhead crane risk assessmentOverhead crane risk assessment
Overhead crane risk assessmentSimba Zhao
 
TOOLBOX TALK | lifting & rigging operations
TOOLBOX TALK | lifting & rigging operationsTOOLBOX TALK | lifting & rigging operations
TOOLBOX TALK | lifting & rigging operationsAlan Bassett
 
11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templates11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templatesDwarika Bhushan Sharma
 
A Part 6 Lifting Operations
A  Part 6 Lifting OperationsA  Part 6 Lifting Operations
A Part 6 Lifting OperationsJames McCann
 
15 formwork (temporary works) risk assessment templates
15 formwork (temporary works) risk assessment templates15 formwork (temporary works) risk assessment templates
15 formwork (temporary works) risk assessment templatesDwarika Bhushan Sharma
 
Rigger signalman handbook
Rigger  signalman handbookRigger  signalman handbook
Rigger signalman handbooknhivan
 
Risk assessment for testing & commissioning of cranes
Risk assessment for  testing & commissioning of cranesRisk assessment for  testing & commissioning of cranes
Risk assessment for testing & commissioning of cranesAzmeel Contracting Company
 

Mais procurados (20)

Lifting & Rigging Safety.pptx
Lifting & Rigging Safety.pptxLifting & Rigging Safety.pptx
Lifting & Rigging Safety.pptx
 
Lifting practices for engineers
Lifting practices for engineersLifting practices for engineers
Lifting practices for engineers
 
12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templates12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templates
 
Risk Assessment Example.pdf
Risk Assessment Example.pdfRisk Assessment Example.pdf
Risk Assessment Example.pdf
 
9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templates9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templates
 
10. lifting-plan-checklist-and-method-statement-2
10. lifting-plan-checklist-and-method-statement-210. lifting-plan-checklist-and-method-statement-2
10. lifting-plan-checklist-and-method-statement-2
 
Liftingproedure
LiftingproedureLiftingproedure
Liftingproedure
 
Overhead Crane Operators by
Overhead  Crane Operators byOverhead  Crane Operators by
Overhead Crane Operators by
 
Overhead crane risk assessment
Overhead crane risk assessmentOverhead crane risk assessment
Overhead crane risk assessment
 
TOOLBOX TALK | lifting & rigging operations
TOOLBOX TALK | lifting & rigging operationsTOOLBOX TALK | lifting & rigging operations
TOOLBOX TALK | lifting & rigging operations
 
11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templates11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templates
 
A Part 6 Lifting Operations
A  Part 6 Lifting OperationsA  Part 6 Lifting Operations
A Part 6 Lifting Operations
 
Rigging Presentation
Rigging PresentationRigging Presentation
Rigging Presentation
 
December -15 Daily Observation Report
December -15 Daily Observation ReportDecember -15 Daily Observation Report
December -15 Daily Observation Report
 
15 formwork (temporary works) risk assessment templates
15 formwork (temporary works) risk assessment templates15 formwork (temporary works) risk assessment templates
15 formwork (temporary works) risk assessment templates
 
Lifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptxLifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptx
 
Operating practices
Operating practicesOperating practices
Operating practices
 
Rigger signalman handbook
Rigger  signalman handbookRigger  signalman handbook
Rigger signalman handbook
 
Rigging & slinging
Rigging & slingingRigging & slinging
Rigging & slinging
 
Risk assessment for testing & commissioning of cranes
Risk assessment for  testing & commissioning of cranesRisk assessment for  testing & commissioning of cranes
Risk assessment for testing & commissioning of cranes
 

Semelhante a Lifting plan

2000 08 safe use of mobile cranes in construction sites
2000 08 safe use of mobile cranes in construction sites2000 08 safe use of mobile cranes in construction sites
2000 08 safe use of mobile cranes in construction sitesPrastowo Priyatmoko
 
Rig Move Management and Logistics Plan.doc
Rig Move Management and Logistics Plan.docRig Move Management and Logistics Plan.doc
Rig Move Management and Logistics Plan.docYasserAbdulkareem1
 
Crane Safety Awareness by University of Texas Arlington
Crane Safety Awareness by University of Texas ArlingtonCrane Safety Awareness by University of Texas Arlington
Crane Safety Awareness by University of Texas ArlingtonAtlantic Training, LLC.
 
Truck crane training bill brown
Truck crane training bill brownTruck crane training bill brown
Truck crane training bill brownBill Brown
 
JHA LIFTING ERECTION OF VESSEL EQUIPMENT.pdf
JHA LIFTING ERECTION OF VESSEL EQUIPMENT.pdfJHA LIFTING ERECTION OF VESSEL EQUIPMENT.pdf
JHA LIFTING ERECTION OF VESSEL EQUIPMENT.pdfHaroon AbdulRahim
 
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docxDwarika Bhushan Sharma
 
Safety Tip: 10 Steps to Safer Crane Operation
Safety Tip: 10 Steps to Safer Crane OperationSafety Tip: 10 Steps to Safer Crane Operation
Safety Tip: 10 Steps to Safer Crane OperationComplianceSigns, LLC
 
TRA%20of%20Lifting.Tail.docx
TRA%20of%20Lifting.Tail.docxTRA%20of%20Lifting.Tail.docx
TRA%20of%20Lifting.Tail.docxPriyaRavirajan
 
Crane-Safety-PowerPoint-Presentation.pptx
Crane-Safety-PowerPoint-Presentation.pptxCrane-Safety-PowerPoint-Presentation.pptx
Crane-Safety-PowerPoint-Presentation.pptxVikasMore37
 
construction macheinery Safety.pdf
construction macheinery Safety.pdfconstruction macheinery Safety.pdf
construction macheinery Safety.pdfBimal Chandra Das
 
Pr 1709 - lifting and hoisting procedure lift planning execution
Pr 1709 - lifting and hoisting procedure lift planning executionPr 1709 - lifting and hoisting procedure lift planning execution
Pr 1709 - lifting and hoisting procedure lift planning executionSergio Augusto Esteves
 
JHA HEAVY LIFTING OF VESSEL.pdf
JHA HEAVY LIFTING OF VESSEL.pdfJHA HEAVY LIFTING OF VESSEL.pdf
JHA HEAVY LIFTING OF VESSEL.pdfHaroon AbdulRahim
 

Semelhante a Lifting plan (20)

SDV-20253 VALVE MOD 9 lift plan 1
SDV-20253 VALVE MOD 9 lift plan 1SDV-20253 VALVE MOD 9 lift plan 1
SDV-20253 VALVE MOD 9 lift plan 1
 
2000 08 safe use of mobile cranes in construction sites
2000 08 safe use of mobile cranes in construction sites2000 08 safe use of mobile cranes in construction sites
2000 08 safe use of mobile cranes in construction sites
 
Rigger safety .pdf
Rigger safety                        .pdfRigger safety                        .pdf
Rigger safety .pdf
 
Rigging Course .pdf
Rigging Course                       .pdfRigging Course                       .pdf
Rigging Course .pdf
 
Rig Move Management and Logistics Plan.doc
Rig Move Management and Logistics Plan.docRig Move Management and Logistics Plan.doc
Rig Move Management and Logistics Plan.doc
 
2015 CRW - New Crane Rules = New Compliance Directives
 2015 CRW - New Crane Rules = New Compliance Directives 2015 CRW - New Crane Rules = New Compliance Directives
2015 CRW - New Crane Rules = New Compliance Directives
 
Crane Safety Awareness by University of Texas Arlington
Crane Safety Awareness by University of Texas ArlingtonCrane Safety Awareness by University of Texas Arlington
Crane Safety Awareness by University of Texas Arlington
 
Liffting supervisor
Liffting supervisorLiffting supervisor
Liffting supervisor
 
Truck crane training bill brown
Truck crane training bill brownTruck crane training bill brown
Truck crane training bill brown
 
PA PIPE WORK 14 inch spool TH11177-06-PI-10-004-5
PA PIPE WORK 14 inch spool TH11177-06-PI-10-004-5PA PIPE WORK 14 inch spool TH11177-06-PI-10-004-5
PA PIPE WORK 14 inch spool TH11177-06-PI-10-004-5
 
update 20feb1
update 20feb1update 20feb1
update 20feb1
 
JHA LIFTING ERECTION OF VESSEL EQUIPMENT.pdf
JHA LIFTING ERECTION OF VESSEL EQUIPMENT.pdfJHA LIFTING ERECTION OF VESSEL EQUIPMENT.pdf
JHA LIFTING ERECTION OF VESSEL EQUIPMENT.pdf
 
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
 
Safety Tip: 10 Steps to Safer Crane Operation
Safety Tip: 10 Steps to Safer Crane OperationSafety Tip: 10 Steps to Safer Crane Operation
Safety Tip: 10 Steps to Safer Crane Operation
 
TRA%20of%20Lifting.Tail.docx
TRA%20of%20Lifting.Tail.docxTRA%20of%20Lifting.Tail.docx
TRA%20of%20Lifting.Tail.docx
 
Crane-Safety-PowerPoint-Presentation.pptx
Crane-Safety-PowerPoint-Presentation.pptxCrane-Safety-PowerPoint-Presentation.pptx
Crane-Safety-PowerPoint-Presentation.pptx
 
construction macheinery Safety.pdf
construction macheinery Safety.pdfconstruction macheinery Safety.pdf
construction macheinery Safety.pdf
 
Pr 1709 - lifting and hoisting procedure lift planning execution
Pr 1709 - lifting and hoisting procedure lift planning executionPr 1709 - lifting and hoisting procedure lift planning execution
Pr 1709 - lifting and hoisting procedure lift planning execution
 
GTC546 HSE PPT
GTC546 HSE PPTGTC546 HSE PPT
GTC546 HSE PPT
 
JHA HEAVY LIFTING OF VESSEL.pdf
JHA HEAVY LIFTING OF VESSEL.pdfJHA HEAVY LIFTING OF VESSEL.pdf
JHA HEAVY LIFTING OF VESSEL.pdf
 

Último

Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfRagavanV2
 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Christo Ananth
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxfenichawla
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
Vivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design SpainVivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design Spaintimesproduction05
 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLManishPatel169454
 

Último (20)

Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Vivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design SpainVivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design Spain
 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
 

Lifting plan

  • 1. Crane Lifting Plan LIFTING OPERATION METHOD STATEMENT/LIFT PLAN & RISK ASSESSMENT DETAILS FOR THE PROVISION OF A LIFT OPERATION IN COMPLIANCE WITH BS7121 – PARTS 1 & 3 AND LOLER REGULATIONS Please tick as appropriate:  Completed by appointed person for crane hired by Weston Homes, or  Completed by contractor who has hired a crane as part of their work Client Weston Homes Plc Project Site Address Date of Operation Time on Site Client/Site Contact Contact Number Appointed Person Contact Number Appointed Person’s Acceptance of Responsibilities: I confirm that the lifts in the Method Statement have been planned and will be carried out in accordance with current legislation and British Standard 7121 and that I accept responsibility for the preparation of this Method Statement and Risk Assessment. I accept that it is my responsibility as the Appointed Person to ensure that the Lift Supervisor is adequately briefed on the contents of this Method Statement. Signed Date CONTENTS Page Page Introduction 28 Crane Set Up Procedure 37 General Conditions 29 Lift Procedure 37 Weather Conditions 29 Crane De-Rig Procedure 39 Ground Conditions 29 On Site Changes 39 Operation Outline 30 Risk Assessment 40 Site Details 31 Site Register & Toolbox Talk 43 Load & Radius Details 32 Drawings Attached Crane & Lift Information 34
  • 2. 1 INTRODUCTION 1.1 It is the aim of this Method Statement to define and describe the equipment and safety procedures which are to be employed by the crane lifting company to carry out the lifting operation. The operation will be carried out in accordance with the following Legislation & Approved Codes of Practice. BS7121 Safe Use of Cranes (part 1) 2006 General & (part 3) 2000 Mobile Cranes Lifting Operations & Lifting Equipment Regulations 1998 (LOLER) Health & Safety at Work Act 1974 - Provision and Use of Work Equipment Regulations (PUWER) 1998 Manual Handling Operations Regulations 1992 - Noise at Work Regulations 2006 Control of Substances Hazardous to Health Regulations 2002 (COSHH) Construction Design and Management Regulations 2007 - Working at Height Regulations 2007 1.2 THE LIFT The lift will be carried out in line with the guidance contained in BS7121. 1.3 SITE INSPECTION The Appointed Person shall carry out a detailed site inspection to ascertain the full requirements of the Site Manager and determine the required crane capacity and make an assessment as far as possible/practicable of any other site issues such as access, ground conditions, overhead obstructions, local authority interaction etc. 1.4 THE APPOINTED PERSON The Appointed Person who has prepared the Method Statement carries full responsibility for the safe completion of all works carried out during the operation. It is the responsibility of the Appointed Person to ensure that the Crane Supervisor is adequately briefed on the contents of this Method Statement. 1.5 THE CRANE SUPERVISOR Prior to the commencement of the works, the Crane Supervisor must ensure that all site personnel are adequately briefed on the contents of this Method Statement. This briefing shall take the form of a short ‘Toolbox Talk’. The Crane Supervisor must liaise with the Appointed Person should site circumstances require material change to the methods to be employed during the operation. 1.6 THE CRANE OPERATOR or OPERATORS All lifting operators or any operators working on behalf of the lifting company shall be fully trained and competent on the machines they operate and will have undergone full manufactures induction and training. 1.7 PERSONNEL All lifting personnel or any personnel working on behalf of the lifting company will be fully trained and hold the relevant certification for the role they undertake on the day of operation. Any non lift company personnel or personnel supplied by the client that will be involved in the lifting operation and taking on a specified role will be required to produce the relevant certification to the Appointed Person or Crane Supervisor prior to the commencement of the operation. Failure to produce the required certification will result in the suspension and possible cancellation of the lifting operation. 1.8 PERSONAL PROTECTIVE EQUIPMENT All lifting personnel will be supplied with standard PPE which consists of, Hard Hat, Safety Boots, Overalls, Gloves, Hi-Vis (and Safety Goggles if required). The Site Manager must inform all Personnel of any specific requirements in advance of the operation date. 1.9 CERTIFICATION Copies of statutory test certification and inspection reports will be available for inspection prior to the lifting operation taking place.
  • 3. 2 GENERAL CONDITIONS 2.1 The Site Manager will provide details of all items to be lifted, including weights, dimensions and any specific lifting tackle requirements. The Site Manager is responsible for the structural integrity of all loads to be lifted including any specified lifting points or slinging recommendations. 2.2 The Site Manager must ensure safe access to and egress from site for all lifting personnel and vehicles, and also ensure that the working area is clear of all obstructions to allow the safe assembly and working of the crane. The Site Manager will be responsible for supplying suitable floodlighting where necessary or when required. The Site Manager must carry out any enabling works required prior to crane arrival. 2.3 The Site Manager must ensure that the area where the crane is to stand/operate is firm and level and this it is capable of withstanding the expected loadings that will be imposed upon it. 2.4 The Site Manager must ensure that any Traffic Management (not supplied by the lift company) is in place prior to the positioning of the crane. 2.5 Any personnel not directly concerned with the lift must be kept out of the crane assembly and working area. The working area should be cordoned off with barrier tape, temporary fencing or otherwise secured, to prevent non lift associated personnel or the general public from entering the lifting area. 2.6 The Crane Supervisor shall make himself known to all relevant personnel on site, and conduct a ‘Toolbox Talk’ prior to commencing operations. The Site Manager should arrange for a site specific induction for the lifting personnel prior to the commencement of work. The Site Managers Site Risk Assessment, which identified any site hazards should be made available and brought to the attention of the lifting personnel. 2.7 All cranes to be left unattended for a period, shall be left in safe condition (jib retracted or laid down if possible), with not load on the crane hook. Cranes shall be shut down and isolated as per manufacturer’s instructions, secured and locked. Under no circumstances shall the crane be moved for lifting purposes if not under the instruction of the Crane Supervisor. 2.8 In the event that specified cranes or lifting tackle, cannot be supplied on the day of operation due to operational issues, breakdown or any unforeseen circumstances. The lift company has the discretion to supply cranes or equipment that is of a suitable alternative to that detailed in this Method Statement, (at no extra cost to the client). In the event of this situation arising, the Appointed Person and the Site Manager will be notified. The AP/Crane Supervisor will ensure that any changes do not infringe on the factors or safety within this method statement. 3 WEATHER CONDITIONS 3.1 In the event of extreme weather conditions the lift company may need to suspend the lifting operation until such time as it is safe to proceed. Although the safe workable wind speed varies from crane to crane, as a guide, the maximum wind speed at which lifting operations can take place is 10 metres per second, (22mph). In the event that man riding duties are required the maximum workable wind speed reduces to 7 metres per second, (16mph). Please note that local conditions and the safety of personnel may dictate the Crane Supervisor and Crane Operator have to suspend lifting operations at a lower wind speed than specified in this Method Statement. In addition, lifting operations must stop during storms or when there is a risk of lightning strikes. 4 GROUND CONDITIONS 4.1 The lift company will endeavour to advise the client regarding ground conditions, after a visual inspection (or where necessary/provided, perusal of a client ground survey report) and supply suitable plates, mats where required. The Client is required to advise the lifting company of any known underground services, voids or vaults as state in BS7121. Safe Use of Cranes.
  • 4. 5 OPERATION OUTLINE 5.1 LIFT CLASSIFICATION LIFT CLASSIFICATION Basic Lift Standard Lift Complex Lift Full Contract Lift Supervisor Only Contract Lift Note: If a “Supervisor Only Contract Lift” is the chosen option, it is imperative that any personnel supplied by the client, be fully trained, competent and experienced in lifting operations and hold current, valid and legislatively required certification, which must be available for our Appointed Person or Crane Supervisor to inspect prior to commencement of the lifting operation. Any personnel supplied by the Site Manager must work under the instruction of the Appointed Person or Crane Supervisor. Failure to comply with the above will results in the suspension of lifting until the aforementioned is adhered to. 5.2 PERSONNEL The following numbers of personnel for this lift are needed: Crane Operator Crane Supervisor Slinger/Signaller 5.3 COMMUNICATIONS Communications between the lifting crew and Crane Operator/s shall be maintained by means of Two-Way Radios Supplied by the Crane Company Two-Way Radios Supplied by Site Manager Hand Signals 5.4 WEATHER CONDITIONS Maximum Workable Wind Speed for the Crane is: Weather forecast to be obtained on morning of lift, confirming wind direction and strength. Wind speed forecast 15.6mph. Guide: 10 metres per second (22mph) for load lifting. 7 metres per second (16mph) for man riding duties. 5.5 BRIEF SCOPE OF WORK/NOTABLE FEATURES OF THIS LIFTING OPERATION
  • 5. 6 SITE DETAILS 6.1 ENABLING WORKS Any enabling works discussed and agreed to at the site inspection, should be carried out prior to arrival of the crane. Are any enabling works required 6.2 ACCESS & EGRESS The Site Manager shall ensure that the crane and all associated vehicles have safe and unimpeded access and egress to and from site. Details of site access & egress 6.3 GROUND CONDITIONS – including any underground services, voids or vaults. Details of ground conditions 6.4 OVERHEAD CABLES, OBSTRUCTIONS OR REGULATIONS & ANY SLEWING RESTRICTIONS Details of any overhead or slewing restrictions
  • 6. 6.5 TRAFFIC AND PEDESTRIAN MANAGEMENT Traffic Management Required Pedestrian Management Required Arranged by Details of any Restrictions & Local Authorities Concerned 7 LOAD & RADIUS DETAILS 7.1 LOAD DETAILS (to be provided by The Site Manager) In the event of there being multiple lifts of different weights and dimensions, only the details of the maximum required lifts will be shown. Description Dimensions Weight 7.2 LIFTING POINTS It is the Site Managers/Plant Managers responsibility to ensure that any manufactured Lifting Points are certified & tested for lifting purposes. This also applies to specified slinging methods where no lifting points are provided. Does the load have Manufactured Lifting Points or Manufacturer guidance for the method of lifting that has been approved for use by the Site Manager? If “No” to the above: Has the Appointed Person assessed and agreed a method of slinging with the Site Manager? Has the Centre of Gravity been taken into account for all proposed lifts? Have the lifting points and/or the lifting method been approved for use by the Appointed Person?
  • 7. 7.3 LIFTING TACKLE Please Note: In the event that the specified lifting tackle cannot be supplied on the day of operation due to operational changes, breakdown or any unforeseen circumstances. The crane company can supply and use lifting tackle/equipment that is of a suitable alternative to that detailed above. In the event of this situations arising, the Appointed Person and Site Manager should be notified. The AP/Crane Supervisor will ensure that any changes do not infringe on the factors of safety within this Method Statement. All Lifting Tackle certification to be available on site. The Crane Supervisor shall inspect all Lifting Tackle prior to each use. Any Lifting Tackle supplied by the Site Manager to be fit for purpose, fully certified and in good condition. Any damaged tackle shall be marked “Not For Use” and returned to the depot for disposal. Nylon Slings must be protected from sharp edges using sling guards or suitable packaging. 7.4 CALCULATED MAXIMUM LIFT WEIGHTS In the event of there being multiple lifts of different weights, only the details of the maximum required lift/s will be shown. Weight of Load Weight of Hook Block Weight of Lifting Tackle Weight of Fly/S-Lift on Boom 7.5 CALCULATED MAXIMUM RADIUS Maximum Required Radius 7.6 MAXIMUM CALCULATED LIFTS Gross lift weight In the event that any loads (lighter than the maximum load) are required to be lifted to a greater radius than the maximum loads, see below: Maximum required radius Gross Lift Weight To be lifted to a radius of Weight to be lifted at max radius
  • 8. 8 CRANE & LIFT INFORMATION 8.1 CRANE/S DETAIL CRANE Crane (make & model) Registration and/or Plant No. 4 Yearly Test and Thorough Examination 12 Month Thorough Examination (6 Months if Crane is used for Lifting People) Weekly Crane Inspection YES NO Certificate Expiry Date YES NO 8.2 REQUIRED WEIGHT & RADIUS Gross Lift Weight Required Radius SWL of Crane at Required Radius Safety Margin In the event that any loads (lighter than the maximum load) are required to be lifted to a greater radius than the maximum loads, see below: LOAD Maximum Required Radius Gross Weight at Max Radius SWL of Crane Safety Margin 8.3 OUTRIGGER LOADINGS & MATS Outrigger Point Load Mat Size Mat Area Provided Please Note that the Site Manager is responsible for ensuring that the ground conditions are suitable to accept the above loadings and pressures.
  • 9. REGISTER OF LIFTING EQUIPMENT – TO BE COMPLETED BY CRANE SUPERVISOR Project: Lifting equipment (e.g. chains or strops) Description ID No. / Reg. Supplier: Test Cert. Expiry Date: 12 Monthly Thorough Examination Expiry Date: Used for lifting persons? Y/N. (If so, 6 Monthly Thorough Exam’n?) Weekly Inspections carried out by:
  • 10. THIS PAGE IS INTENTIONALLY BLANK
  • 11. CRANE & LIFT INFORMATION (Continued) 9 CRANE SET UP PROCEDURE THE CRANE TEAM Crane Supervisor: CITB CTA Card Expiry Date: Appointed Person: Slinger/Signaller(s): CITB CTA Card Expiry Date: Crane Driver: 9.1 The crane, together with the associated operating crew will arrive on site at the specified and agreed date and time. 9.2 Crane Supervisor will meet the Site Manager and carry out “Toolbox Talk” with all personnel involved in the lifting operation. Once this has been completed, all involved in the lifting operation must sign the register for this Method Statement. Any site inductions that are required will also be carried out. 9.3 Any traffic management, ancillary pans, mats or temporary roadways etc that are required to be positioned by hi-ab or other means, prior to the crane or cranes manoeuvring into position, will be done under the instruction of the Crane Supervisor. 9.4 The crane will then manoeuvre into position as shown on attached drawing. All manoeuvring to be carried out under the guidance of a member of the lifting crew. 9.5 The crane will then commence set-up procedure and rig to the configuration stated in section 8.1. All personnel assisting with rigging will be under the guidance of the crane operator, at all times. The set- up procedure will be carried out as per crane manufactures manual. 9.6 Upon completion of the rigging procedure, the crane operator will carry out procedural safety and computer checks, implementing any specific operational requirements, i.e. slewing restrictions, short rig configurations or fly jib configurations. 9.7 The Crane Supervisor will then carry out a radio communications check between the crane operator and the lifting crew. 9.8 Hook block of crane will then be lowered and required lifting tackle placed on the hook, Lift Supervisor will ensure that the correct lifting tackle has been selected. 9.9 The crane operator will then be instructed to hoist lifting tackle clear of any obstructions and position the crane ready for the first required lift. Any delivery/removal vehicles will now be positioned adjacent to the crane as per attached drawings, ready for work to commence. 10 LIFTING PROCEDURE 10.1 Slinger/Signallers will issue instructions via hand signals or two-way radios to the crane operator to position the crane over first required lift, Slinger/Signallers will plumb the boom head, directly over the load or set short to allow for jib deflection where necessary.
  • 12. 10.2 The Slinger/Signallers will instruct crane operator, the lower the hooks with lifting tackle to allow Slinger/Signaller to attach lifting tackle to load. LIFTING PROCEDURE (Continued) 10.3 All slinging will be carried out by fully trained, certificated and experienced slingers. Slinging methods adopted will be as specified by load manufacturers, using specified lifting points or, in the event that no manufacturer instruction or lifting points are provided, our Slingers will work to the Appointed Persons recommendations and to Health & Safety executives guidelines for safe slinging for lifting loads, (see section 7.2 & 7.3). The lifting tackle used, will be as stated in section 7.3 and will have current test certification available. 10.4 Upon completion of the attachment of the lifting tackle to the load, the Slinger/Signaller will instruct the operator by hand signals or radios, to hoist up to take the slack out of the lifting tackle. Once the lifting tackle has started to take the weight and has tightened the Slinger/Signaller will instruct operator or operators to stop hoisting. The Slinger/Signaller will then carry out a check around the load to ensure that the lifting tackle is sitting correctly, angled correctly and also check any lifting points for security and correct operation. 10.5 Once lifting tackle check has been carried out the Slinger/Signaller will instruct the crane operator or operators, to hoist the load to a height that allows the lifting tackle to take the full weight of the load and again instruct the operator to stop hoisting when the load is just airborne to allow a final check of the lifting tackle and lifting points and also check the structural integrity of the load. 10.6 Once the Slinger/Signaller is confident that the lifting tackle and the load are secure, any tag lines that may be required will be attached to the load. Instructions will then be given to the crane operator or operators to hoist the load clear of any obstructions, ensuring that any site specific risks are monitored throughout the hoisting procedure. 10.7 Once the load is clear of all obstructions, the Slinger/signaller will give instructions to the crane operator to manoeuvre the load as required for railing, or manoeuvre to the required landing area for single crane lifts. 10.8 In the event that the landing area is at a different level or should access not permit, the Slinger/Signaller will pass control of the crane signalling to a second strategically placed Slinger/Signaller at the landing area. 10.9 The landing area Slinger/Signaller will then commence giving instructions to the crane operator or operators to manoeuvre and lower the load to the required landing point, ensuring that any site specific risks are monitored throughout the landing procedure. 10.10 The Slinger/Signaller will guide the load to the correct orientation as the load becomes contactable by hand or by attached tag lines. 10.11 The Slinger/Signaller will instruct the crane operator to lower the load to just above the landing position and then instruct the operator to stop lowering to allow the Site Manager to confirm position and orientation of load prior to landing. 10.12 Once the position is confirmed by the Site Manager, the Slinger/Signaller will instruct the operator to slowly lower load into position. Once landed, a final position check will be made before the Slinger/Signaller instructs the operator to lower off all load weight. 10.13 Slinger/Signaller will instruct the operator to lower off, to allow lifting tackle to be released from the load. In the event that any load is too large or high for safe access by ladder, powered access equipment or a lifted man basket will be used to remove slings from loads. 10.14 Once lifting tackle is detached from the load, the Slinger/Signaller will instruct the operator to slowly hoist the lifting tackle clear of the load and any site specific risks ensuring that no snagging occurs.
  • 13. 10.15 Once the lifting tackle is clear of all obstructions the Slinger/signaller will instruct the crane operator to manoeuvre the crane ready for any further lifts that may be required and had over to another Slinger/Signaller were required. 10.16 All other required lifts will be carried out as stated in sections 11.1 to 11.5. The Lift Supervisor will ensure that all lifting and operational procedures are followed as per the Appointed Persons recommendations and that any queries or deviation from this Method Statement are notified immediately to the Site Manager and the Appointed Person. 11 DE-RIG PROCEDURE 11.1 Upon completion of the lifting operation, the Crane Supervisor will instruct the crane operator to load any ancillary equipment or heavy lifting tackle onto relevant transport ready for removal from site. 11.2 The Crane Supervisor will then instruct the crane operator to lower all lifting tackle to the ground to allow removal from hook. 11.3 The crane operator will then instigate the removal of any lifting tackle stored on the crane and then commence the de-rig procedure. 11.4 All personnel assisting with de-rigging will be under the guidance of the crane operator at all times. The de-rig procedure will be carried out as per crane manufacturers manual. 11.5 Once the crane has been de-rigged and all safety checks for road travel have been carried out the crane operator will manoeuvre the crane/s off site, under the guidance of a member of the lifting crew. The crane will then proceed on its way. 11.6 The remaining members of the lifting crew will ensure that any ancillary mats or equipment etc are removed from site or placed in an appropriate position ready for collection prior to them leaving site. 11.7 Any traffic or pedestrian management arranged by the lift company will be unimplemented and removed. 11.8 The Crane Supervisor will inform the Site Manager or site representative of the completion of the operation and address any issues that may be raised and inform of any equipment left on site for later collection. 12 ON SITE CHANGES/ADDITIONAL LIFTS 12.1 Any changes to this Method Statement & Lifting Plan must be notified to and approved by the Appointed Person. Any crane position changes or amendments to drawings must also be notified and approved by the Appointed Person. Amendment Details
  • 14. 1) 2) 3) 4) 5) 6) 7) 8) 9) 10) Changed discussed with and approved by the Appointed Person Crane Supervisor Date (Sign & Print) 13 RISK ASSESSMENT The aim of this risk assessment is to highlight any possible hazards that are likely to occur during the lifting operation. Upon its completion with either a “High, Medium, Low or N/A” in the Risk Rating Box and either a “” or “N/A” in the Risk Managed box, the document coverts to a site specific assessment. Identified Hazards Risk Risk rating Prevention Measures Risk Managed Access to and Egress from Site Interaction with public highway and members of the public. Interaction with other site operations and operatives. Interaction with delivery vehicles. Risk to: Public/ Operators/ Site Operatives High Banksman with hi-vis to control traffic and public while crane manoeuvring into site. Flashing amber lights and audible alarms when reversing. Site management to be aware of intended route on site. All other site operatives to be made aware of crane movement.  Low Medium Low N/A Ground Conditions Crane travelling over unprepared or uneven ground possible damage to ground surface and or crane and property. Ground collapse beneath outriggers causing possible overturning. Risk to: Public/ Operators/ Site Operatives High Ground to be assessed at time of site inspection. Ground improvement to be implemented where needed. Operator/Crane Supervisor to inspect on day of operation. Outrigger pans to be used with additional heavy duty mats where needed. Client to inform the crane company of any known risks  Low Medium Low N/A Underground Services Damage to sub-surface service lines causing possible flooding, explosion, High A full assessment and mapping of the 
  • 15. asphyxiation or electrocution. Risk to: Public/ Operators/ Site Operatives Medium travelling and working area of the crane will be made at the site inspection. The Site Manager to make the crane operator aware of any known risk. Permit to work in place where applicable. Operator/ Crane Supervisor to check on day of operation for any new or unseen risks. Low Low N/A Crane Positioning - Set up Procedure - De-rig Procedure Crane positioned incorrectly for required lift. Possible damage to crane or property during set up or de-rig procedure. Risk to: Public/ Operators/ Site Operatives High Crane working position clearly identified in Method Statement drawings and made known to crane operators and marked out where required. Crane manufacturer’s instructions for set up and de-rig procedure followed. Only trained and competent personnel to operate and assist with rigging. No one but lift associated personnel within crane set up area.  Low Medium Low N/A Plant Operations Crane operation, causing damage to property or injury to personnel. Mechanical breakdown or structural damage. Risk to: Public/ Operators/ Site Operatives High Trained, certified and competent crane operators. Cranes fully maintained with full service and testing history. Manufacturer’s instructions adhered to at all times.  Low Medium Low N/A
  • 16. Identified Hazards Risk Risk rating Prevention Measures Risk Managed Manual Handling - Sling of Loads - Signalling - Tailing Operations - Multiple Crane Operations Incorrect slinging of loads. Unsuitable lifting equipment used. Failure of lifting equipment. Incorrect signals give to crane operator causing damage to loads, property or injury to personnel. Crane operator lifting unseen loads. Risk to: Public/ Operators/ Site Operatives High Trained, certified and competent Slingers to sling all loads. Only specified lifting tackle and lifting tackle with current and valid certification to be used. Visual inspection to be carried out on all lifting tackle prior to use. Qualified Signallers to use recognised hand signals or radio commands to communicate with crane operators. Radios used for unsighted lifts.  Low Medium Low N/A Working at Height - Ladders - Scaffolding - Access Platforms - Man Baskets Personnel falling from height during crane assembly and or lifting operations. Personnel falling from delivery vehicles during slinging of loads. Operation of mechanical platforms. Personnel working from man Baskets. Risk to: Public/ Operators/ Site Operatives High Operators to work from footed ladders for crane assembly. Slingers to work from footed ladders for slinging loads where reasonably practicable. Work platforms or lifted man basket to be used where a height risk is deemed excessive. Access operators to be IPAF trained. Site to ensure all working areas at height are safe with suitable guard rails. Harnesses to be worn where required / practicable. All scaffolds to be certified for working use.  Low Medium Low N/A Protection of Public & Site Operatives - Falling Objects Injury to public or site personnel from falling objects or materials. Damage to vehicles or property during lifting operations. Risk from suspended loads. Risk to: Public/ Operators/ Site Operatives High Work area to be cordoned off as an exclusion zone. Sufficient barrier & signage to be in place to warn non lift associated persons of overhead & ground level risks. All over-sail to be addressed, monitored and evacuation implemented where practicable. Lift crew to be aware of all lifting operations.  Low Medium Low N/A Traffic Pedestrian Management Damage to property or plant. Risk of responsibility for collision or injury. Protection of personnel during works. Risk to: Public/ Operators/ Site Operatives High Full assessment of required restrictions on public highways, service roads or private roads to be made at site inspection. Any Traffic Management contractors supplied by site or the crane company will be fully certified and competent. Traffic Management supplied by the site should be set up prior to arrival of crane.  Low Medium Low N/A Adverse Weather Conditions Crane operation, load stability and control. Risk of injury to personnel and damage to property. Risk of lightning strike. Bad visibility. Risk to: Public/ Operators/ Site High Weather reports obtained before and during lifting operations. Crane operator to monitor wind speed equipment. Suspension of lifting operation until risk subsides.  Low Medium Low
  • 18. Identified Hazards Risk Risk rating Prevention Measures Risk Managed Overhead or slewing Obstructions or Restrictions - Low Headroom Damage to crane or property if crane boom or superstructure comes into contact with any restriction. Infringement of unauthorised air space. Working in restricted work space. Risk to: Public/ Operators/ Site Operatives High Full assessment of any risks made and addressed at site inspection. Safe system of work adhered to where implemented. Work to zone alarms where implemented. Implement crane swl computer working restrictions. All relevant authorities contacted and advised and any restrictions adhered to.  Low Medium Low N/A ADDITIONAL SITE SPECIFIC RISKS ADDITIONAL RISKS IDENTIFIED ON DAY OF OPERATIONS ADDITIONAL RISKS DUE TO ON SITE CHANGES Identified Hazards Risk Risk Rating Prevention Measures Risk Managed
  • 19. 14 SITE REGISTER/TOOLBOX TALK All operational staff involved in this lifting operation must read this method Statement or have had the contents of it explained in detail to them prior to commencing work. All persons involved in this lifting operation are to sign below in acceptance that a detailed briefing of this operation has been given and understood. All certification has been checked and verified prior to the lifting operation commencing. Crane Supervisor’s Acceptance of Responsibilities: I confirm that I have been fully briefed on the contents of this Method Statement and Risk Assessment and that I accept the duty of ensuring that the lift/s will be carried out in accordance with the Methods and Procedures set out in this Document. Signed Date Print Name Position Signature Date Site Manager Acceptance of this Method Statement I confirm that I have read and understood this Method Statement and Risk Assessment and that I accept the responsibilities of the site management with respect to Safe Use of Cranes (part 1) 2006 General and (part 3) 2000 Mobile Cranes. Signed Date SUMMARY Crane Detail Site ManagerCrane Site Project Detail Req Radius SWL SES Point Load Date Issue No