2. The failure rate is an example of which of the following?
A. Quality metrics
B. Process metrics
C. Quality checklists
D. Quality control measurements
HINT: Note that failure rate is a product attribute.
QUESTION:
3. The correct answer is A.
Quality metrics are usually about a project or product attributes and used in both quality
assurance and quality control to ensure the project meets the quality objectives such as
on-time milestones, failure rate, or requirement stability. While quality control
measurements and process metrics are about the process indicators, a quality checklist is
a list used to verify that a set of steps has been performed.
ANSWER: