Welcome To Demand Flow
Technology Workshop
Principles of Lean Manufacturing
Objectives
 Develop the knowledge of what the
philosophies and techniques are and why
they are important
 Total picture of the the demand flow
technology business strategy
 Understand and establish how to perform the
techniques and skills learned
 Exercises and feedback
 Technical information and examples
Cycle Time
One of the most noteworthy
accomplishments in keeping the price of
Ford products low is the gradual
shortening of the production cycle. The
longer an article is in the process of
manufacture and the more it is moved
about, the greater is its ultimate cost.
WHAT IS DFT ANYWAY?
Lean Is Market Driven
Every morning in Africa, a gazelle wakes up. It
knows it must run faster than the fastest lion
or it will be killed. Every morning a lion wakes
up. It knows it must outrun the slowest
gazelle or it will starve to death.
It doesn’t matter whether you are a lion or a
gazelle – when the sun comes up, you had
better be running.
Defining DFT
DFT has been defined in many different
ways:
A systematic approach to identifying
and eliminating waste (non-value-
added-activities) through continuous
improvement by flowing the product at
the pull of the customer in pursuit of
perfection.
Defining DFT
A manufacturing technology that focuses
an aggressive flow process that seeks
to eliminate or minimize non-value
added work in the production process
while emphasizing quality throughout
the process.
Primary Objective
to build a HIGH QUALITY product in the
SHORTEST PRODUCTION time and at
the LOWEST POSSIBLE COST
What are the advantages of DFT
 People – the number of people needed
to produce the daily rate is calculated
daily
 Processes and quality checks are
documented (A.I., OMS & SOE’s)
 Quality built into the product
 Kanban
 Less material in WIP and RIP
What are the advantages of DFT
 Component kanban – two-bin system
 NVA work is minimized or eliminated
 Processes are in a constant continuous
improvement state
 Speed-to-market
 Next day
 Customer Responsiveness
Cost Distribution
 Labor – 10%
 Pay Cut
 Layoff
 Work Harder
 Overhead – 20%
 Benefits
 Utilities
 Training & Education
 Material – 70%
 Eliminate Scrap
 Eliminate Inventory
 Demand Flow Business Strategy
70%
20%
10%
 Station 1
 One-Down Operation
 Out-of-Box
 FG’s
 Customer
Cost to the Company
Defect Found At …..
Traditional Mfg. Vs. Demand Flow Mfg.
 Scheduling techniques
 Fabrication &
subassembly
production
 Departmental build
 Schedule, queue and
batch work time
 Material movement
 External Inspection
 Mathematical
technology
 Mixed-model flow
process
 Flow line design
 Build the product in total
work content time or
less
 Minimum material
movement
 TQC & verify
Product Synchronization
A relationship of the processes in a flow to
produce a product.
Product Synch
Teams
DFT Activity Sheet Transports MP-3 Stacker-2 Depositor Key/edplt MMD Divert Divert-Tran PPM IDM CASSETTE Bins Prt-A
Develop DFT Implementation Sch. X X X X X X X X X X X X X
Train Personal in DFT Concept X X X X X X X X X X X X X
Develop Product Sync X X X X X X X X X X X X X
Establish Takt X X X x X X X X X
Completed SOE'S ( Timing) X X X X X X X X X X X X
Develop Oms's X X X X X
Balance Line X X X X X X X X X
Set IPK's x X X X X X X X X
Calculate OPR & Manning X X X X X X X X X
Trained and Certify Operatios X X X X X X X X X X X X X
Perform Pull Sequence Audit X X X X X X X X X
Wet Line X X X X X X X X X X X X X
TPCt X X X X X X X X X
Flow Rate X X X X X X X X X
Teams Attacking TPCt X X X X X X X X X
Process Mapping
Matrix of products across the top and
processes along the side
Process Mapping Build Base MMD Team MP-B,C Divert line Trans/Div TQC MMD is Ship to
Place on pushes cart place dual place Div is place on checks TQC'd for finish goods
cart to MP-B,C Picker on on top of top of Div. are done wiring Unit
line cart to Picker, tightens on all is tested
Divert Line tightens latches, & modules recorded
MMD latches& add belt. CCA brd on test log
Module add belt. Cart is is added
Cart pushed pushed to wire are
to Trans/Div MMD line routed &
line log is
filled out.
00100264F14A * * * * * * *
00100264F24B * * * * * *
00100264F24A * * * * *
00102716F14A * * * * * * *
00102716F14B * * * * * * *
00102170F14A * * * * * *
00101070F14D * * * * * *
00101070F13A * * * * * *
00101070F24A * * * * * *
00101070F21A * * * * * *
00101070F21B * * * * *
Sequence of Events
Defines quality criteria against each work
element, value-added steps and time
estimates.
SOE
Part Number: 49-006633-000D SEQUENCE of EVENTS Date: 3/9/01
SEQ Task Description VA SET-UP MACHINE LABOR MOVE TQC INFORMATION
# M L M L
Station 1
10 Position floor brace into T-22586. * 0:02
20 Place floor in T-22586 (on top of Floor * 0:04 Verify- The minimum/maximum floor
Brace). width from end to end at the bend line
30 Insert rivets into 4 holes. Seat the rivets * 0:26 using T-28598, at least 1 per hour.
by using the trigger on the gun. Verify- 4 Studs are present on floor
40 Insert the stand-offs into the tool. Place * 0:30 assembly.
into the tool. Apply Loctite onto the Verify- Rivets are flush and floor brace
screws and secure to stand-offs. is tight.
Remove floor from tool.
50 Prepare surface of floor by cleaning the * 0:07
spring mounting area with alcohol and
water solution. Verify- The surface is thoroughly dry
60 Repeat steps 1 through 5 for second 1:09 before preceeding.
floor.
Total time for station = 2:18
Operational Method Sheet
(OMS)
A “colored” graphic representation of
quality criteria and work content
defined by the S.O.E. to be performed
at an operation
Work Content
TQC – check someone else work
Verify – check your own work
Demand at Capacity - Dc
The highest targeted volume output of
products that is planned to be achieved
by a demand flow manufacturing
process
Dc
Dc = Pv
Wd
100 units per month
20 days =
5 units/day
Dc = Designed Daily Rate
He = Effective Work Hours
S = Shifts per day
400 units per month
20 days =
20 units/day
Total Product Cycle Time (TPCT)
The calculated work content through the
longest path of the processes required
to build a product
Money Picker (6633D) = 30 min/prs 0.5
Stacker (7835H) = 42 min/prs 0.7
Transport (7836B) = 23min/prs 0.383
Printer (1670A) = 40 min/prs 0.66
TAKT
The calculated target of work content time
to be performed independently by a
person or machine in a demand flow
line
TAKT Conversion
100’s or Minutes
 7.66/5 = 1.532 hr/unit (IDM)
92 min/unit
7.66/20 = 0.383 hr/unit (R/L transport)
23 min/unit
 7.66/111 = 0.069 (Picker)
4.14 min/unit
Stations
Actual Time
TAKT Time
Money Picker
30 minutes assembly time
4.14 TAKT
= 7.24
= 7 stations
Resources
Resources can be:
Operations – labor
Machines
Pieces – batch equipment
People - flexible
Flexible Employees
 Employees in a DFT line have a
minimum flexibility of three operations:
 Primary
 One up-stream
 One down-stream
People (Dr)
Resources are
calculated daily to
determine the
requirement to
produce the daily
rate
Dc x L
H x S
Money picker
50 x .50
(8) X (1)
=3.125
3 people
Line Balancing Tools
Tools used when actual time at an operation
exceed TAKT
 Relocate work
 Reduce or eliminate non-value added work
content
 Add resources or duplicate resources
 Move inventory and time (Kanban)
Certification
 Meet TAKT
 Train others
 Meet quality criteria
 Flex
In-Process Kanban (IPK)
A visual signal that identifies when work
needs to be performed in a line
Kanban Card
A card used as a communications signal
to pull material based on demand
Pull Sequence
Every part that is kanban pulled must
have a definable path that identifies the
supply and consumption points
(e.g Line, Rip, Wip, FG’s)
Mixed Model Line
A primary goal of demand flow manufacturing is
to design flow lines to produce families of
similar products. The mixed model line has
the ability to build a range of volumes of any
product, any day, based on the direction of
actual customer demand.
Backflush
The method used to relieve RIP (Raw in
Process) inventory of a product’s bill of
material quantity when a product is
complete
Communication Lights
Management Light – A light that can be
seen from a wide area to identify if
action needs to be taken on the line
e.g Andon
Measuring Linearity
Example: during a nine-day period the production
rate is (4) per day:
4+4+4+4+4+4+4+4+4=36
Actual production was:
3+4+5+3+4+5+3+4+5=36
Traditionally we would say this is o.k.
Actually the sum of the total deviation is 6 or 84%
Suggested Goal = 90%
Formula Recap
Daily Capacity
Dc Pv
Wd
People Dr x L
H x S
TAKT H x S
Dc
Stations Actual Time
TAKT
QUESTIONS???

Mais conteúdo relacionado

Semelhante a Demand Flow Technology workshop - Lean manufacturing

Value Stream Mapping -The Concept
Value Stream Mapping -The ConceptValue Stream Mapping -The Concept
Value Stream Mapping -The ConceptSubhrajyoti Parida
 
PALCO INDUSTRY USING VALUE STREAM MAPPING
PALCO INDUSTRY USING VALUE STREAM MAPPINGPALCO INDUSTRY USING VALUE STREAM MAPPING
PALCO INDUSTRY USING VALUE STREAM MAPPINGFuratAj
 
Chapter5-Facility Layout_POM.ppt
Chapter5-Facility Layout_POM.pptChapter5-Facility Layout_POM.ppt
Chapter5-Facility Layout_POM.pptKuvaneshWaran
 
BIM, Lean & Advanced Work Packaging - How do they fit together?
BIM, Lean & Advanced Work Packaging - How do they fit together? BIM, Lean & Advanced Work Packaging - How do they fit together?
BIM, Lean & Advanced Work Packaging - How do they fit together? CCT International
 
Process selection for manufacturing fms
Process selection for manufacturing fmsProcess selection for manufacturing fms
Process selection for manufacturing fmsKinshook Chaturvedi
 
Quintiq SCM CIO Seminar -20120922-1
Quintiq SCM CIO Seminar -20120922-1Quintiq SCM CIO Seminar -20120922-1
Quintiq SCM CIO Seminar -20120922-1Ralph Yin
 
IRJET-Productivity Improvement in a Pressure Vessel using Lean Principles
IRJET-Productivity Improvement in a Pressure Vessel using Lean PrinciplesIRJET-Productivity Improvement in a Pressure Vessel using Lean Principles
IRJET-Productivity Improvement in a Pressure Vessel using Lean PrinciplesIRJET Journal
 
Tieghi Anipla 20 04 2010 Come Possiamo Essere Sicuri Che Tutti Seguano Le Pro...
Tieghi Anipla 20 04 2010 Come Possiamo Essere Sicuri Che Tutti Seguano Le Pro...Tieghi Anipla 20 04 2010 Come Possiamo Essere Sicuri Che Tutti Seguano Le Pro...
Tieghi Anipla 20 04 2010 Come Possiamo Essere Sicuri Che Tutti Seguano Le Pro...Enzo M. Tieghi
 
12 theory of cost and estimation
12 theory of cost and estimation12 theory of cost and estimation
12 theory of cost and estimationmalikjameel1986
 
Automobile parts design diploma mechanical engineering
Automobile parts design diploma mechanical engineeringAutomobile parts design diploma mechanical engineering
Automobile parts design diploma mechanical engineeringlovely467637
 

Semelhante a Demand Flow Technology workshop - Lean manufacturing (20)

Value Stream Mapping -The Concept
Value Stream Mapping -The ConceptValue Stream Mapping -The Concept
Value Stream Mapping -The Concept
 
PALCO INDUSTRY USING VALUE STREAM MAPPING
PALCO INDUSTRY USING VALUE STREAM MAPPINGPALCO INDUSTRY USING VALUE STREAM MAPPING
PALCO INDUSTRY USING VALUE STREAM MAPPING
 
Chapter5-Facility Layout_POM.ppt
Chapter5-Facility Layout_POM.pptChapter5-Facility Layout_POM.ppt
Chapter5-Facility Layout_POM.ppt
 
BIM, Lean & Advanced Work Packaging - How do they fit together?
BIM, Lean & Advanced Work Packaging - How do they fit together? BIM, Lean & Advanced Work Packaging - How do they fit together?
BIM, Lean & Advanced Work Packaging - How do they fit together?
 
13. value stream mapping
13. value stream mapping13. value stream mapping
13. value stream mapping
 
Process selection for manufacturing fms
Process selection for manufacturing fmsProcess selection for manufacturing fms
Process selection for manufacturing fms
 
Work measurement
Work measurementWork measurement
Work measurement
 
om
omom
om
 
Quintiq SCM CIO Seminar -20120922-1
Quintiq SCM CIO Seminar -20120922-1Quintiq SCM CIO Seminar -20120922-1
Quintiq SCM CIO Seminar -20120922-1
 
IRJET-Productivity Improvement in a Pressure Vessel using Lean Principles
IRJET-Productivity Improvement in a Pressure Vessel using Lean PrinciplesIRJET-Productivity Improvement in a Pressure Vessel using Lean Principles
IRJET-Productivity Improvement in a Pressure Vessel using Lean Principles
 
Lean Tools
Lean ToolsLean Tools
Lean Tools
 
Layout
LayoutLayout
Layout
 
Tieghi Anipla 20 04 2010 Come Possiamo Essere Sicuri Che Tutti Seguano Le Pro...
Tieghi Anipla 20 04 2010 Come Possiamo Essere Sicuri Che Tutti Seguano Le Pro...Tieghi Anipla 20 04 2010 Come Possiamo Essere Sicuri Che Tutti Seguano Le Pro...
Tieghi Anipla 20 04 2010 Come Possiamo Essere Sicuri Che Tutti Seguano Le Pro...
 
12 theory of cost and estimation
12 theory of cost and estimation12 theory of cost and estimation
12 theory of cost and estimation
 
What is-six-sigma69
What is-six-sigma69What is-six-sigma69
What is-six-sigma69
 
Scheduling Dedicated
Scheduling DedicatedScheduling Dedicated
Scheduling Dedicated
 
Design notes5
Design notes5Design notes5
Design notes5
 
Design notes5
Design notes5Design notes5
Design notes5
 
Chapter4EN.PDF.pdf
Chapter4EN.PDF.pdfChapter4EN.PDF.pdf
Chapter4EN.PDF.pdf
 
Automobile parts design diploma mechanical engineering
Automobile parts design diploma mechanical engineeringAutomobile parts design diploma mechanical engineering
Automobile parts design diploma mechanical engineering
 

Último

Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixCIToolkit
 
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchRashtriya Kisan Manch
 
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证jdkhjh
 
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...AgileNetwork
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Roomdivyansh0kumar0
 
Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsCIToolkit
 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentationcraig524401
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Nehwal
 
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramBeyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramCIToolkit
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Reviewthomas851723
 
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)jennyeacort
 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insightWayne Abrahams
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineeringthomas851723
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sectorthomas851723
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentationmintusiprd
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingCIToolkit
 

Último (17)

Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
 
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
 
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
 
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
 
Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield Metrics
 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentation
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
 
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramBeyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
 
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Servicesauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Review
 
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insight
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineering
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sector
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentation
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
 

Demand Flow Technology workshop - Lean manufacturing

  • 1. Welcome To Demand Flow Technology Workshop Principles of Lean Manufacturing
  • 2. Objectives  Develop the knowledge of what the philosophies and techniques are and why they are important  Total picture of the the demand flow technology business strategy  Understand and establish how to perform the techniques and skills learned  Exercises and feedback  Technical information and examples
  • 3. Cycle Time One of the most noteworthy accomplishments in keeping the price of Ford products low is the gradual shortening of the production cycle. The longer an article is in the process of manufacture and the more it is moved about, the greater is its ultimate cost.
  • 4. WHAT IS DFT ANYWAY?
  • 5. Lean Is Market Driven Every morning in Africa, a gazelle wakes up. It knows it must run faster than the fastest lion or it will be killed. Every morning a lion wakes up. It knows it must outrun the slowest gazelle or it will starve to death. It doesn’t matter whether you are a lion or a gazelle – when the sun comes up, you had better be running.
  • 6. Defining DFT DFT has been defined in many different ways: A systematic approach to identifying and eliminating waste (non-value- added-activities) through continuous improvement by flowing the product at the pull of the customer in pursuit of perfection.
  • 7. Defining DFT A manufacturing technology that focuses an aggressive flow process that seeks to eliminate or minimize non-value added work in the production process while emphasizing quality throughout the process.
  • 8. Primary Objective to build a HIGH QUALITY product in the SHORTEST PRODUCTION time and at the LOWEST POSSIBLE COST
  • 9. What are the advantages of DFT  People – the number of people needed to produce the daily rate is calculated daily  Processes and quality checks are documented (A.I., OMS & SOE’s)  Quality built into the product  Kanban  Less material in WIP and RIP
  • 10. What are the advantages of DFT  Component kanban – two-bin system  NVA work is minimized or eliminated  Processes are in a constant continuous improvement state  Speed-to-market  Next day  Customer Responsiveness
  • 11. Cost Distribution  Labor – 10%  Pay Cut  Layoff  Work Harder  Overhead – 20%  Benefits  Utilities  Training & Education  Material – 70%  Eliminate Scrap  Eliminate Inventory  Demand Flow Business Strategy 70% 20% 10%
  • 12.  Station 1  One-Down Operation  Out-of-Box  FG’s  Customer Cost to the Company Defect Found At …..
  • 13. Traditional Mfg. Vs. Demand Flow Mfg.  Scheduling techniques  Fabrication & subassembly production  Departmental build  Schedule, queue and batch work time  Material movement  External Inspection  Mathematical technology  Mixed-model flow process  Flow line design  Build the product in total work content time or less  Minimum material movement  TQC & verify
  • 14. Product Synchronization A relationship of the processes in a flow to produce a product.
  • 15. Product Synch Teams DFT Activity Sheet Transports MP-3 Stacker-2 Depositor Key/edplt MMD Divert Divert-Tran PPM IDM CASSETTE Bins Prt-A Develop DFT Implementation Sch. X X X X X X X X X X X X X Train Personal in DFT Concept X X X X X X X X X X X X X Develop Product Sync X X X X X X X X X X X X X Establish Takt X X X x X X X X X Completed SOE'S ( Timing) X X X X X X X X X X X X Develop Oms's X X X X X Balance Line X X X X X X X X X Set IPK's x X X X X X X X X Calculate OPR & Manning X X X X X X X X X Trained and Certify Operatios X X X X X X X X X X X X X Perform Pull Sequence Audit X X X X X X X X X Wet Line X X X X X X X X X X X X X TPCt X X X X X X X X X Flow Rate X X X X X X X X X Teams Attacking TPCt X X X X X X X X X
  • 16. Process Mapping Matrix of products across the top and processes along the side
  • 17. Process Mapping Build Base MMD Team MP-B,C Divert line Trans/Div TQC MMD is Ship to Place on pushes cart place dual place Div is place on checks TQC'd for finish goods cart to MP-B,C Picker on on top of top of Div. are done wiring Unit line cart to Picker, tightens on all is tested Divert Line tightens latches, & modules recorded MMD latches& add belt. CCA brd on test log Module add belt. Cart is is added Cart pushed pushed to wire are to Trans/Div MMD line routed & line log is filled out. 00100264F14A * * * * * * * 00100264F24B * * * * * * 00100264F24A * * * * * 00102716F14A * * * * * * * 00102716F14B * * * * * * * 00102170F14A * * * * * * 00101070F14D * * * * * * 00101070F13A * * * * * * 00101070F24A * * * * * * 00101070F21A * * * * * * 00101070F21B * * * * *
  • 18. Sequence of Events Defines quality criteria against each work element, value-added steps and time estimates.
  • 19. SOE Part Number: 49-006633-000D SEQUENCE of EVENTS Date: 3/9/01 SEQ Task Description VA SET-UP MACHINE LABOR MOVE TQC INFORMATION # M L M L Station 1 10 Position floor brace into T-22586. * 0:02 20 Place floor in T-22586 (on top of Floor * 0:04 Verify- The minimum/maximum floor Brace). width from end to end at the bend line 30 Insert rivets into 4 holes. Seat the rivets * 0:26 using T-28598, at least 1 per hour. by using the trigger on the gun. Verify- 4 Studs are present on floor 40 Insert the stand-offs into the tool. Place * 0:30 assembly. into the tool. Apply Loctite onto the Verify- Rivets are flush and floor brace screws and secure to stand-offs. is tight. Remove floor from tool. 50 Prepare surface of floor by cleaning the * 0:07 spring mounting area with alcohol and water solution. Verify- The surface is thoroughly dry 60 Repeat steps 1 through 5 for second 1:09 before preceeding. floor. Total time for station = 2:18
  • 20. Operational Method Sheet (OMS) A “colored” graphic representation of quality criteria and work content defined by the S.O.E. to be performed at an operation Work Content TQC – check someone else work Verify – check your own work
  • 21. Demand at Capacity - Dc The highest targeted volume output of products that is planned to be achieved by a demand flow manufacturing process
  • 22. Dc Dc = Pv Wd 100 units per month 20 days = 5 units/day Dc = Designed Daily Rate He = Effective Work Hours S = Shifts per day 400 units per month 20 days = 20 units/day
  • 23. Total Product Cycle Time (TPCT) The calculated work content through the longest path of the processes required to build a product Money Picker (6633D) = 30 min/prs 0.5 Stacker (7835H) = 42 min/prs 0.7 Transport (7836B) = 23min/prs 0.383 Printer (1670A) = 40 min/prs 0.66
  • 24. TAKT The calculated target of work content time to be performed independently by a person or machine in a demand flow line
  • 25. TAKT Conversion 100’s or Minutes  7.66/5 = 1.532 hr/unit (IDM) 92 min/unit 7.66/20 = 0.383 hr/unit (R/L transport) 23 min/unit  7.66/111 = 0.069 (Picker) 4.14 min/unit
  • 26. Stations Actual Time TAKT Time Money Picker 30 minutes assembly time 4.14 TAKT = 7.24 = 7 stations
  • 27. Resources Resources can be: Operations – labor Machines Pieces – batch equipment People - flexible
  • 28. Flexible Employees  Employees in a DFT line have a minimum flexibility of three operations:  Primary  One up-stream  One down-stream
  • 29. People (Dr) Resources are calculated daily to determine the requirement to produce the daily rate Dc x L H x S Money picker 50 x .50 (8) X (1) =3.125 3 people
  • 30. Line Balancing Tools Tools used when actual time at an operation exceed TAKT  Relocate work  Reduce or eliminate non-value added work content  Add resources or duplicate resources  Move inventory and time (Kanban)
  • 31. Certification  Meet TAKT  Train others  Meet quality criteria  Flex
  • 32. In-Process Kanban (IPK) A visual signal that identifies when work needs to be performed in a line
  • 33. Kanban Card A card used as a communications signal to pull material based on demand
  • 34. Pull Sequence Every part that is kanban pulled must have a definable path that identifies the supply and consumption points (e.g Line, Rip, Wip, FG’s)
  • 35. Mixed Model Line A primary goal of demand flow manufacturing is to design flow lines to produce families of similar products. The mixed model line has the ability to build a range of volumes of any product, any day, based on the direction of actual customer demand.
  • 36. Backflush The method used to relieve RIP (Raw in Process) inventory of a product’s bill of material quantity when a product is complete
  • 37. Communication Lights Management Light – A light that can be seen from a wide area to identify if action needs to be taken on the line e.g Andon
  • 38. Measuring Linearity Example: during a nine-day period the production rate is (4) per day: 4+4+4+4+4+4+4+4+4=36 Actual production was: 3+4+5+3+4+5+3+4+5=36 Traditionally we would say this is o.k. Actually the sum of the total deviation is 6 or 84% Suggested Goal = 90%
  • 39. Formula Recap Daily Capacity Dc Pv Wd People Dr x L H x S TAKT H x S Dc Stations Actual Time TAKT