SlideShare uma empresa Scribd logo
1 de 21
Baixar para ler offline
1 of 21
Estimating
-100%
0%
100%
Needs Define Design Test Deliver Support
Estimation Δ
Time
±50% ±20%
2 of 21
What is Estimating?
Roughly calculate or judge the value, number, quantity, or extent of
Oxford English Dictionary
The process of finding an estimate
– a value that is used because it is derived from the best information available
– even if input data is incomplete, uncertain, or unstable
Wikipedia
The process of combining the results of experience, metrics and measurements to arrive at
an approximate judgement of time, cost or effort
3 of 21
Good Estimating is Critical to Success
Good estimates enable
 Sound business decision making – is the project worth doing?
 Sound project planning – when will the project deliver? – what will it cost?
 Design optimisation – is this the optimum design and delivery strategy?
 Performance monitoring
 Cash flow management
20% into a project lifecycle
80% of the total cost
is already committed
Decisions based on early
estimates are critical
0%
100%
Define Design Test Deliver
Cost
Time
Committed Costs
Actual Costs
4 of 21
Estimating Best Practice
Association for Project Management
Planning, Scheduling, Monitoring & Control [2015] 
Project Management Institute
Practice Standard for Project Estimating [2010] 
UK Government
Ministry of Defence Acquisition System Guidance: Forecasting & Estimating
NASA
Cost Estimating Handbook, v4.0 [2008] 
5 of 21
Estimating Methods
Transparent
Box
Analogical
Group
Technologies
Knowledge
Based
Case Based
Reasoning
Detailed
Product
Attributes
Function
Costing
Feature
Costing
Accumulation
of Parts
Generative
Activity
Based
Reasoning
visible Black
Box
Statistical
Parametric
Neural
Network
Expert
Judgement
Source: Reference 1
Reasoning
hidden
Method
Group
Reference 2
6 of 21
Estimating Methods II
Transparent Box Advantages Limitations
Analogical
Group Technologies Compares the work to one or more similar but complete projects or parts thereof
Quick
Intuitive
Case bias
Large case history required
Poor for innovations
Knowledge Based Attempts to imitate the reasoning of experts to estimate
Visible logic
Structured
Knowledge obsolescence
Large database required
Case Based Reasoning An estimate based on similar situations from a library of previous cases
Quick
Collective memory
Large reliable case base
Poor for innovations
7 of 21
Estimating Methods III
Transparent Box Advantages Limitations
Detailed: Product Attributes
Function Costing A product or system is estimated directly from a specification of its performance
Integrates requirements with costs Need to allocate cost to function
Accuracy
Feature Costing The integration of CAD/CAM with cost information for cost estimation early in the
design process via feature-based modelling
Integrates with CAD/CAM
Can be automated
No feature consensus
Large database required
Detailed: Accumulation of Parts
Generative or Analytical Cost Estimation
Estimating by aggregating the processes involved to create the product
Can be accurate
Detail useful for negotiation
Time consuming
Detailed data may not be available
Activity Based or ABC (Activity Based Costing)
As Generative, but the overheads are allocated where they are incurred
Allocates costs to sources
String indication of profitability
Time consuming
Detailed data may not be available
Allocation of overheads
8 of 21
Estimating Methods IV
Black Box Advantages Limitations
Expert Judgement Domain expert uses previous similar experience
Delphi – several experts independent estimates rationalised to single result
Mini-Delphi – two experts independently estimate and then agree a single result
Quick
Flexible
Bias
Unstructured
Repeatability
Statistical
Parametric Uses Cost Estimating Relationships (CERs) and algorithms or logic
CERs are extracted from historical data for similar systems and define correlations
between cost drivers and other system parameters such as size or performance.
As defined in the Parametric Cost Estimating Handbook
Clear influences
Objective
Repeatable
Large database required to define CERs
Simplistic
Missing parameters
Neural Network Learns the impact of attributes on cost by automatic analysis of historical data
Accurate
Updateable
Hidden logic
Complex
Large database required
9 of 21
Estimating Psychology
Motivational Bias an estimate that serves the estimator more than it is objective
e.g. making a plan fit the desired target
Optimism Bias considering only positive previous experiences
people always under-estimate, even if aware (wishful thinking)
Cognitive Bias using heuristics to estimate sometimes leads to poor estimates
Heuristics, or mental shortcuts, often work but can lead to cognitive bias
e.g. Anchor heuristic: estimates are biased towards an early erroneous estimate
Availability heuristic: poor estimates as estimators remember a limited data set
Biases of different estimators can reinforce each other
Rule of Pi the actual time to do the work will be the time estimated multiplied by π
Student Syndrome only starting work towards the end of the estimated period
10 of 21
Expert Judgement: for both Top-Down & Bottom-up
High levels of innovation: no database of past estimates & results
Often little detail about the task being estimated & little time to do estimating
Mitigate expert judgement weaknesses
 Template to gather estimates – consistency between estimators & reduced bias
 Get buy-in by using experts from delivery team to estimate
 Use experts with domain knowledge
 Mini Delphi further reduces bias
 Give separate estimators the same information
 Estimate for normal conditions – work hours, seniority of staff
 Don’t allow for estimation uncertainty in individual estimates
11 of 21
Managing Estimation Uncertainty
Concurrency
Plans often feature concurrent tasks
 with minimal float, and
 single point (deterministic) estimates
Higher concurrency means greater
impact when some tasks finish late
Range Estimates
Analysis shows deterministic outcomes
have very low probability
Range estimates are more realistic
Even better, 3 points:
minimum, most likely, maximum
Dates and costs then become ranges
Difference in cost between outcomes
can be used to define case-by-case
estimation uncertainty contingency
Typical plan analysis:
Probability of achieving the deterministic cost
Reference 3
12 of 21
Potential Weakness of 3 Point Estimates
Outcomes may be pessimistic if most likely estimates are not 50% likely
Typical 3 point estimate
Probability of Most Likely estimate PML
PML = 2/(10-4) = 1/3 or 33% …NOT 50%!
Avoid this weakness by asking for the probability of the Most Likely estimate
Example: for PML = 70%
Create double triangle distribution
and calculate points A & B:
0.7 = 0.5*(6-4)*A so A = 0.7
0.3 = 0.5*(10-6)*B so B = 0.15
Area either side is not equal and will vary task by task as defined by the 4th point
In practice need only do this for 10 to 20 most critical tasks – found by sensitivity analysis
13 of 21
Selective 4 Point Estimation: Simulation Results
Result for 3 point estimates alone
Result including selected 4 point estimates:
Higher probability of deterministic outcome
Smaller, more realistic risk budget
Tornado Graph:
Sensitivity analysis to
select tasks to estimate
with 4 points
Risk Budget:
£21,125
Risk Budget:
£13,696
14 of 21
Estimation Uncertainty Contingency
One strategy:
Estimation uncertainty ‘project risk pot’ = 95% cost – deterministic cost
The business Risk Appetite can inform what probability to use, e.g.:
10% Team Target (likely risks do not occur)
50% Best Estimate (as many risks occur as not)
90% ‘Safe’ Estimate (several unlikely major risks occur)
Reward using less of this risk pot, but recognise that a proportion is likely to be required
This encourages behaviour that enhances results whilst recognising estimation uncertainty
and setting realistic expectations
PMs use project risk pot to drive delivery to the deterministic end date
Drives the right behaviour in the team – to deliver on their Most Likely estimates
Selective 4 point estimating maintains competitive pricing
15 of 21
Other Methods
Price to Win estimate based on supposition or knowledge of the budget
Do tailor the scope of work to suit a budget
Don’t force an estimate to fit a budget
Parkinson 'Work expands to fill the time available'
equates the estimate to available resources
These are not estimating methods – they are price and cost management methods
16 of 21
Estimating Process
Contingency
Zero Risk
(Deterministic)
Cost Held at project & programme level
Project
Risk Pot
Estimation
Uncertainty
Top-Down
Estimate
Rationalise
Estimates
PDP
Project
Delivery
Process
Product
Breakdown
Structure
Work
Breakdown
Structure
Work Packages
& Tasks
Bottom-up
3pt Estimates
I
N
F
O
R
M
Need
Strategy Opportunities
Enhancement
Tasks
Secondary
Risks
Inform / Offset
Threats
Mitigation
Tasks
Risk Register
Held at portfolio level
If cost effective
Contingency
For project risks other
than estimation
uncertainty
17 of 21
Practical Advice & Tips
Choose estimating method case-by-case to suit project and environment
 No perfect estimating method, suitable for all environments
 Many methods rely on a database or case history of past estimates and results
 Often need a combination of methods
 Risk Management for project risks other than estimation uncertainty
Use the proposed delivery team to create the estimates in order to get buy-in
Base estimates on normal conditions: 5 day week, 8 hour day
Use consistent time units
Do a reality check on the result and rationalise bottom-up with top-down
Range estimates are more realistic than single point (deterministic estimate)
Don’t pad individual estimates as a means to handle estimation uncertainty
If project type & environment always same
– use one-size-fits-all estimation uncertainty contingency
otherwise use 3 point estimating to derive estimation uncertainty contingency
18 of 21
Practical Advice & Tips II
Estimation uncertainty is a significant project risk, but not the only project risk
 Use Risk Management to handle the other types of project risk
Bottom-up estimating: avoid long tasks and tasks where progress hard to assess
Educated Guess: beware early estimates often based on little information
 Can become base against which future estimates are judged (anchor heuristic)
 Cautions delivered with that first estimate rarely remembered
Don’t confuse uncertainty with a lack of knowledge
 Large ranges generally indicate guessing
 Experience is required to estimate rather than guess
It’s still just an estimate
 Project starts late: provide estimates from time T0 rather than a fixed date
 Team members late to start: avoid ‘brick-wall’ starts where possible
 Incorrect assumptions: list assumptions, track changes & adjust plans
19 of 21
Summary
Estimating is a critical competence
Be aware of impact of estimator psychology
Significant innovation in projects limits useful estimation methods
Build historical data records (estimate & result) where possible
Combine estimation methods for best results
3 point range estimates offer case-by-case estimation uncertainty contingency
4 point estimates for few most influential tasks eradicates potential 3 point weakness
One-size-fits-all estimation uncertainty contingency suitable if projects all similar
Risk Management to handle project risk other than estimation uncertainty
20 of 21
1. Cost Estimation Method Selection:
Matching User Requirements and Knowledge Availability to Methods
DK Evans, Dr. JD Lanham, Dr. R Marsh, Paper for ICEC (International Cost Engineering Council), 2006
SEEDS (Systems Engineering Estimation for Decision Support),
AMRC (Aerospace Manufacturing Research Centre)
University of West of England, Bristol, UK
2. Delphi Estimation Method
Wikipedia
3. Tool used for planning and 3 & 4 point estimation uncertainty calculations:
Oracle Primavera Risk Analysis
or
Safran Risk
References
21 of 21
Author Profile
In my board role I led a team of 22 Project Managers and 5 Quality Engineers, and ensured Roke’s £79m
project portfolio delivered better than budget profit. I set-up and ran a virtual PMO and created REP,
the Roke Engineering Process, also managing the engineering tools to support it.
After 4 years as an electronics engineer for Siemens, achieving Chartered Engineer,
I moved into project management for 14 years, at Siemens and Roke Manor Research.
Successfully delivering Roke’s most challenging whole lifecycle product developments
on time and under budget led to a role as Director and board member for 6 years.
In 2013 I returned to hands-on project management as Programme Director at
Cambridge Consultants, founder member of the Cambridge Science Park.
Creator of the APM corporate accredited PM Excellence Programme,
I chaired a quarterly PM forum to share best practice and built a
supportive PM community. I coached seven PMs to RPP, five to PQ,
and all passed APMP.
These investments in PM professionalism led to a turn-around and
annual improvement in project results across a 400 project portfolio
and delivered an above budget performance in five consecutive years
with profits totalling £7.9m above budget.
Passionate advocate of PM professionalism, Fellow of the APM and
the IET and author of articles published in Project and PM Today.
Professional Development
Winning Project Work
Planning
Estimating
Risk Management
Earned Value Management
Change Control
Stakeholder Management
3 Steps to Professional Project Management: Case Study
ProjectManagementTopics

Mais conteúdo relacionado

Mais procurados

What kind of collaboration is right for you
What kind of collaboration is right for youWhat kind of collaboration is right for you
What kind of collaboration is right for youDr. Mohammad Obeidat
 
Fundamentals of project management
Fundamentals of project managementFundamentals of project management
Fundamentals of project managementMohamed Amin
 
Project feasibility study report
Project feasibility study report Project feasibility study report
Project feasibility study report Harish Satya
 
Design Thinking & Project Management
Design Thinking & Project ManagementDesign Thinking & Project Management
Design Thinking & Project ManagementBruce Gay, PMP
 
Project identification & screening
Project identification & screeningProject identification & screening
Project identification & screeningsachin kumar sharma
 
Sustainable innovations
Sustainable innovationsSustainable innovations
Sustainable innovationsAnusuya Nandi
 
Innovation and creativity 01 introduction and basic concepts
Innovation and creativity 01 introduction and basic conceptsInnovation and creativity 01 introduction and basic concepts
Innovation and creativity 01 introduction and basic conceptsKamal AL MASRI
 
Idea Generation Process for Startup Businesses
Idea Generation Process for Startup BusinessesIdea Generation Process for Startup Businesses
Idea Generation Process for Startup Businessestomiero
 
Examination of innovation types final
Examination of innovation types finalExamination of innovation types final
Examination of innovation types finalJeffrey Phillips
 
Project Management - Basic Concepts
Project Management - Basic ConceptsProject Management - Basic Concepts
Project Management - Basic ConceptsImran Jamil
 
Technology and Innovation Management
Technology and Innovation ManagementTechnology and Innovation Management
Technology and Innovation ManagementJamil AlKhatib
 
Factors to be considered for project selection
Factors to be considered for project selectionFactors to be considered for project selection
Factors to be considered for project selectionYuvaraj neelakandan
 
Commissioning Induction Re#1.ppt
Commissioning Induction Re#1.pptCommissioning Induction Re#1.ppt
Commissioning Induction Re#1.pptMahfutArdi
 
Lecture 01: Advanced Project Management-Introduction
Lecture 01: Advanced Project Management-IntroductionLecture 01: Advanced Project Management-Introduction
Lecture 01: Advanced Project Management-IntroductionFida Karim 🇵🇰
 
Project management
Project managementProject management
Project managementsatya pal
 

Mais procurados (20)

NalcoWateroverview
NalcoWateroverviewNalcoWateroverview
NalcoWateroverview
 
Technology for SME
Technology for SMETechnology for SME
Technology for SME
 
What kind of collaboration is right for you
What kind of collaboration is right for youWhat kind of collaboration is right for you
What kind of collaboration is right for you
 
Fundamentals of project management
Fundamentals of project managementFundamentals of project management
Fundamentals of project management
 
Project feasibility study report
Project feasibility study report Project feasibility study report
Project feasibility study report
 
Design Thinking & Project Management
Design Thinking & Project ManagementDesign Thinking & Project Management
Design Thinking & Project Management
 
Project identification & screening
Project identification & screeningProject identification & screening
Project identification & screening
 
Sustainable innovations
Sustainable innovationsSustainable innovations
Sustainable innovations
 
Innovation and creativity 01 introduction and basic concepts
Innovation and creativity 01 introduction and basic conceptsInnovation and creativity 01 introduction and basic concepts
Innovation and creativity 01 introduction and basic concepts
 
Idea Generation Process for Startup Businesses
Idea Generation Process for Startup BusinessesIdea Generation Process for Startup Businesses
Idea Generation Process for Startup Businesses
 
Examination of innovation types final
Examination of innovation types finalExamination of innovation types final
Examination of innovation types final
 
Innovation management
Innovation managementInnovation management
Innovation management
 
Co2
Co2Co2
Co2
 
Project Management - Basic Concepts
Project Management - Basic ConceptsProject Management - Basic Concepts
Project Management - Basic Concepts
 
Technology and Innovation Management
Technology and Innovation ManagementTechnology and Innovation Management
Technology and Innovation Management
 
Factors to be considered for project selection
Factors to be considered for project selectionFactors to be considered for project selection
Factors to be considered for project selection
 
Commissioning Induction Re#1.ppt
Commissioning Induction Re#1.pptCommissioning Induction Re#1.ppt
Commissioning Induction Re#1.ppt
 
Lecture 01: Advanced Project Management-Introduction
Lecture 01: Advanced Project Management-IntroductionLecture 01: Advanced Project Management-Introduction
Lecture 01: Advanced Project Management-Introduction
 
Project management
Project managementProject management
Project management
 
Data Envelopment Analysis
Data Envelopment AnalysisData Envelopment Analysis
Data Envelopment Analysis
 

Destaque

PM Final Assignment Report
PM Final Assignment ReportPM Final Assignment Report
PM Final Assignment ReportMelvin Lim
 
Estimating letters
Estimating lettersEstimating letters
Estimating lettersZIyeeTan
 
Measurement 4 Assignment Presentation
Measurement 4 Assignment PresentationMeasurement 4 Assignment Presentation
Measurement 4 Assignment PresentationHaziq1511
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment마 이환
 
Software Application Group Assignment
Software Application Group AssignmentSoftware Application Group Assignment
Software Application Group AssignmentHaziq1511
 
Pp group assignment
Pp group assignmentPp group assignment
Pp group assignmentwendyteosy
 
Measurement 4 ooompa loompa
Measurement 4   ooompa loompaMeasurement 4   ooompa loompa
Measurement 4 ooompa loompaHasif Alias
 
Professional practice 1 (QS)
Professional practice 1 (QS)Professional practice 1 (QS)
Professional practice 1 (QS)Hasif Alias
 
Professional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentProfessional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentHaziq1511
 
Management science assignment report.
Management science assignment report.Management science assignment report.
Management science assignment report.lucaschinsheng
 
Professional Practice 1 Assignment
Professional Practice 1 AssignmentProfessional Practice 1 Assignment
Professional Practice 1 AssignmentMelvin Lim
 
Estimating tender presentation
Estimating tender presentation Estimating tender presentation
Estimating tender presentation seenyeeyong
 
Assignment - Tender Documentation (Presentation Slide)
Assignment - Tender Documentation (Presentation Slide)Assignment - Tender Documentation (Presentation Slide)
Assignment - Tender Documentation (Presentation Slide)Kai Yun Pang
 
PP1 presentation slide.
PP1 presentation slide.PP1 presentation slide.
PP1 presentation slide.lucaschinsheng
 
Assignment 2 - Buildsoft Software
Assignment 2 - Buildsoft SoftwareAssignment 2 - Buildsoft Software
Assignment 2 - Buildsoft SoftwareKai Yun Pang
 
Estimating presentation
Estimating presentationEstimating presentation
Estimating presentationkohwenqi
 
Estimating presentation
Estimating presentationEstimating presentation
Estimating presentationHasif Alias
 
Estimating Presentation Slides - To Client
Estimating Presentation Slides - To ClientEstimating Presentation Slides - To Client
Estimating Presentation Slides - To ClientPang Khai Shuen
 

Destaque (20)

PM Final Assignment Report
PM Final Assignment ReportPM Final Assignment Report
PM Final Assignment Report
 
Estimating letters
Estimating lettersEstimating letters
Estimating letters
 
Measurement 4 Assignment Presentation
Measurement 4 Assignment PresentationMeasurement 4 Assignment Presentation
Measurement 4 Assignment Presentation
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment
 
Software Application Group Assignment
Software Application Group AssignmentSoftware Application Group Assignment
Software Application Group Assignment
 
Pp group assignment
Pp group assignmentPp group assignment
Pp group assignment
 
Measurement 4 ooompa loompa
Measurement 4   ooompa loompaMeasurement 4   ooompa loompa
Measurement 4 ooompa loompa
 
Professional practice 1 (QS)
Professional practice 1 (QS)Professional practice 1 (QS)
Professional practice 1 (QS)
 
Professional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentProfessional Practice 1 Group Assignment
Professional Practice 1 Group Assignment
 
Group Component
Group ComponentGroup Component
Group Component
 
Management science assignment report.
Management science assignment report.Management science assignment report.
Management science assignment report.
 
Professional Practice 1 Assignment
Professional Practice 1 AssignmentProfessional Practice 1 Assignment
Professional Practice 1 Assignment
 
Estimating tender presentation
Estimating tender presentation Estimating tender presentation
Estimating tender presentation
 
Assignment - Tender Documentation (Presentation Slide)
Assignment - Tender Documentation (Presentation Slide)Assignment - Tender Documentation (Presentation Slide)
Assignment - Tender Documentation (Presentation Slide)
 
PP1 presentation slide.
PP1 presentation slide.PP1 presentation slide.
PP1 presentation slide.
 
M4 presentation slides
M4 presentation slidesM4 presentation slides
M4 presentation slides
 
Assignment 2 - Buildsoft Software
Assignment 2 - Buildsoft SoftwareAssignment 2 - Buildsoft Software
Assignment 2 - Buildsoft Software
 
Estimating presentation
Estimating presentationEstimating presentation
Estimating presentation
 
Estimating presentation
Estimating presentationEstimating presentation
Estimating presentation
 
Estimating Presentation Slides - To Client
Estimating Presentation Slides - To ClientEstimating Presentation Slides - To Client
Estimating Presentation Slides - To Client
 

Semelhante a Estimating

Estimating & Control - Reliable Estimates for Realistic Projects - PMI NL cha...
Estimating & Control - Reliable Estimates for Realistic Projects - PMI NL cha...Estimating & Control - Reliable Estimates for Realistic Projects - PMI NL cha...
Estimating & Control - Reliable Estimates for Realistic Projects - PMI NL cha...Frank Vogelezang
 
Integrating risk with earned value
Integrating risk with earned valueIntegrating risk with earned value
Integrating risk with earned valueGlen Alleman
 
PM685 - Kwon
PM685 - KwonPM685 - Kwon
PM685 - KwonUAAPMD
 
Estimating IT projects - Guest lecture University of Twente
Estimating IT projects - Guest lecture University of TwenteEstimating IT projects - Guest lecture University of Twente
Estimating IT projects - Guest lecture University of TwenteFrank Vogelezang
 
Notes on IT programmatic risk in 5 not so easy pieces
Notes on IT programmatic risk in 5 not so easy piecesNotes on IT programmatic risk in 5 not so easy pieces
Notes on IT programmatic risk in 5 not so easy piecesGlen Alleman
 
PM Estimation techniques
PM Estimation techniquesPM Estimation techniques
PM Estimation techniquesChander Parkash
 
QA_Chapter_01_Dr_B_Dayal_Overview.pptx
QA_Chapter_01_Dr_B_Dayal_Overview.pptxQA_Chapter_01_Dr_B_Dayal_Overview.pptx
QA_Chapter_01_Dr_B_Dayal_Overview.pptxTeshome62
 
QM-037-Using DFSS tool
QM-037-Using DFSS toolQM-037-Using DFSS tool
QM-037-Using DFSS toolhandbook
 
8 project planning
8 project planning8 project planning
8 project planningrandhirlpu
 
Chap 5 Estimating Project Times
Chap 5 Estimating Project TimesChap 5 Estimating Project Times
Chap 5 Estimating Project Timesproject management
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value ManagementGlen Alleman
 
Software Test Estimation
Software Test EstimationSoftware Test Estimation
Software Test EstimationJatin Kochhar
 
Test Estimation Techniques
Test Estimation TechniquesTest Estimation Techniques
Test Estimation TechniquesNishant Worah
 
PMP preparation and PMI Framework
PMP preparation and PMI FrameworkPMP preparation and PMI Framework
PMP preparation and PMI FrameworkUzma Khan
 
Software Project Estimation
Software Project EstimationSoftware Project Estimation
Software Project EstimationFrank Vogelezang
 
Estimation guidelines and templates
Estimation guidelines and templatesEstimation guidelines and templates
Estimation guidelines and templatesHoa PN Thaycacac
 

Semelhante a Estimating (20)

Estimating & Control - Reliable Estimates for Realistic Projects - PMI NL cha...
Estimating & Control - Reliable Estimates for Realistic Projects - PMI NL cha...Estimating & Control - Reliable Estimates for Realistic Projects - PMI NL cha...
Estimating & Control - Reliable Estimates for Realistic Projects - PMI NL cha...
 
Integrating risk with earned value
Integrating risk with earned valueIntegrating risk with earned value
Integrating risk with earned value
 
PM685 - Kwon
PM685 - KwonPM685 - Kwon
PM685 - Kwon
 
Estimating IT projects - Guest lecture University of Twente
Estimating IT projects - Guest lecture University of TwenteEstimating IT projects - Guest lecture University of Twente
Estimating IT projects - Guest lecture University of Twente
 
Notes on IT programmatic risk in 5 not so easy pieces
Notes on IT programmatic risk in 5 not so easy piecesNotes on IT programmatic risk in 5 not so easy pieces
Notes on IT programmatic risk in 5 not so easy pieces
 
Chap005
Chap005Chap005
Chap005
 
Risk Adjusted Estimating Techniques
Risk Adjusted Estimating TechniquesRisk Adjusted Estimating Techniques
Risk Adjusted Estimating Techniques
 
PM Estimation techniques
PM Estimation techniquesPM Estimation techniques
PM Estimation techniques
 
QA_Chapter_01_Dr_B_Dayal_Overview.pptx
QA_Chapter_01_Dr_B_Dayal_Overview.pptxQA_Chapter_01_Dr_B_Dayal_Overview.pptx
QA_Chapter_01_Dr_B_Dayal_Overview.pptx
 
Estimation
EstimationEstimation
Estimation
 
QM-037-Using DFSS tool
QM-037-Using DFSS toolQM-037-Using DFSS tool
QM-037-Using DFSS tool
 
8 project planning
8 project planning8 project planning
8 project planning
 
Chap 5 Estimating Project Times
Chap 5 Estimating Project TimesChap 5 Estimating Project Times
Chap 5 Estimating Project Times
 
Project Management
Project ManagementProject Management
Project Management
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value Management
 
Software Test Estimation
Software Test EstimationSoftware Test Estimation
Software Test Estimation
 
Test Estimation Techniques
Test Estimation TechniquesTest Estimation Techniques
Test Estimation Techniques
 
PMP preparation and PMI Framework
PMP preparation and PMI FrameworkPMP preparation and PMI Framework
PMP preparation and PMI Framework
 
Software Project Estimation
Software Project EstimationSoftware Project Estimation
Software Project Estimation
 
Estimation guidelines and templates
Estimation guidelines and templatesEstimation guidelines and templates
Estimation guidelines and templates
 

Mais de Russell Taylor BEng CEng FAPM FIET (7)

Change Control
Change ControlChange Control
Change Control
 
Winning Project Work
Winning Project WorkWinning Project Work
Winning Project Work
 
Stakeholder Management
Stakeholder ManagementStakeholder Management
Stakeholder Management
 
Planning
PlanningPlanning
Planning
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
PM Professional Development
PM Professional DevelopmentPM Professional Development
PM Professional Development
 

Último

CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceanilsa9823
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceDelhi Call girls
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, MumbaiPooja Nehwal
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Pooja Nehwal
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607dollysharma2066
 
Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024Alex Marques
 
Does Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptxDoes Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptxSaqib Mansoor Ahmed
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxalinstan901
 
operational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementoperational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementTulsiDhidhi1
 
CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyHafizMuhammadAbdulla5
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptxAss.Prof. Dr. Mogeeb Mosleh
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Hedda Bird
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampPLCLeadershipDevelop
 
situational leadership theory by Misba Fathima S
situational leadership theory by Misba Fathima Ssituational leadership theory by Misba Fathima S
situational leadership theory by Misba Fathima Smisbafathima9940
 
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...Pooja Nehwal
 

Último (20)

CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
 
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote SpeakerLeadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
 
Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024
 
Does Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptxDoes Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptx
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptx
 
operational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementoperational plan ppt.pptx nursing management
operational plan ppt.pptx nursing management
 
CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biography
 
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg PartnershipUnlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
 
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICECall Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
 
Peak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian DugmorePeak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian Dugmore
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptx
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC Bootcamp
 
Intro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptxIntro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptx
 
situational leadership theory by Misba Fathima S
situational leadership theory by Misba Fathima Ssituational leadership theory by Misba Fathima S
situational leadership theory by Misba Fathima S
 
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
 

Estimating

  • 1. 1 of 21 Estimating -100% 0% 100% Needs Define Design Test Deliver Support Estimation Δ Time ±50% ±20%
  • 2. 2 of 21 What is Estimating? Roughly calculate or judge the value, number, quantity, or extent of Oxford English Dictionary The process of finding an estimate – a value that is used because it is derived from the best information available – even if input data is incomplete, uncertain, or unstable Wikipedia The process of combining the results of experience, metrics and measurements to arrive at an approximate judgement of time, cost or effort
  • 3. 3 of 21 Good Estimating is Critical to Success Good estimates enable  Sound business decision making – is the project worth doing?  Sound project planning – when will the project deliver? – what will it cost?  Design optimisation – is this the optimum design and delivery strategy?  Performance monitoring  Cash flow management 20% into a project lifecycle 80% of the total cost is already committed Decisions based on early estimates are critical 0% 100% Define Design Test Deliver Cost Time Committed Costs Actual Costs
  • 4. 4 of 21 Estimating Best Practice Association for Project Management Planning, Scheduling, Monitoring & Control [2015]  Project Management Institute Practice Standard for Project Estimating [2010]  UK Government Ministry of Defence Acquisition System Guidance: Forecasting & Estimating NASA Cost Estimating Handbook, v4.0 [2008] 
  • 5. 5 of 21 Estimating Methods Transparent Box Analogical Group Technologies Knowledge Based Case Based Reasoning Detailed Product Attributes Function Costing Feature Costing Accumulation of Parts Generative Activity Based Reasoning visible Black Box Statistical Parametric Neural Network Expert Judgement Source: Reference 1 Reasoning hidden Method Group Reference 2
  • 6. 6 of 21 Estimating Methods II Transparent Box Advantages Limitations Analogical Group Technologies Compares the work to one or more similar but complete projects or parts thereof Quick Intuitive Case bias Large case history required Poor for innovations Knowledge Based Attempts to imitate the reasoning of experts to estimate Visible logic Structured Knowledge obsolescence Large database required Case Based Reasoning An estimate based on similar situations from a library of previous cases Quick Collective memory Large reliable case base Poor for innovations
  • 7. 7 of 21 Estimating Methods III Transparent Box Advantages Limitations Detailed: Product Attributes Function Costing A product or system is estimated directly from a specification of its performance Integrates requirements with costs Need to allocate cost to function Accuracy Feature Costing The integration of CAD/CAM with cost information for cost estimation early in the design process via feature-based modelling Integrates with CAD/CAM Can be automated No feature consensus Large database required Detailed: Accumulation of Parts Generative or Analytical Cost Estimation Estimating by aggregating the processes involved to create the product Can be accurate Detail useful for negotiation Time consuming Detailed data may not be available Activity Based or ABC (Activity Based Costing) As Generative, but the overheads are allocated where they are incurred Allocates costs to sources String indication of profitability Time consuming Detailed data may not be available Allocation of overheads
  • 8. 8 of 21 Estimating Methods IV Black Box Advantages Limitations Expert Judgement Domain expert uses previous similar experience Delphi – several experts independent estimates rationalised to single result Mini-Delphi – two experts independently estimate and then agree a single result Quick Flexible Bias Unstructured Repeatability Statistical Parametric Uses Cost Estimating Relationships (CERs) and algorithms or logic CERs are extracted from historical data for similar systems and define correlations between cost drivers and other system parameters such as size or performance. As defined in the Parametric Cost Estimating Handbook Clear influences Objective Repeatable Large database required to define CERs Simplistic Missing parameters Neural Network Learns the impact of attributes on cost by automatic analysis of historical data Accurate Updateable Hidden logic Complex Large database required
  • 9. 9 of 21 Estimating Psychology Motivational Bias an estimate that serves the estimator more than it is objective e.g. making a plan fit the desired target Optimism Bias considering only positive previous experiences people always under-estimate, even if aware (wishful thinking) Cognitive Bias using heuristics to estimate sometimes leads to poor estimates Heuristics, or mental shortcuts, often work but can lead to cognitive bias e.g. Anchor heuristic: estimates are biased towards an early erroneous estimate Availability heuristic: poor estimates as estimators remember a limited data set Biases of different estimators can reinforce each other Rule of Pi the actual time to do the work will be the time estimated multiplied by π Student Syndrome only starting work towards the end of the estimated period
  • 10. 10 of 21 Expert Judgement: for both Top-Down & Bottom-up High levels of innovation: no database of past estimates & results Often little detail about the task being estimated & little time to do estimating Mitigate expert judgement weaknesses  Template to gather estimates – consistency between estimators & reduced bias  Get buy-in by using experts from delivery team to estimate  Use experts with domain knowledge  Mini Delphi further reduces bias  Give separate estimators the same information  Estimate for normal conditions – work hours, seniority of staff  Don’t allow for estimation uncertainty in individual estimates
  • 11. 11 of 21 Managing Estimation Uncertainty Concurrency Plans often feature concurrent tasks  with minimal float, and  single point (deterministic) estimates Higher concurrency means greater impact when some tasks finish late Range Estimates Analysis shows deterministic outcomes have very low probability Range estimates are more realistic Even better, 3 points: minimum, most likely, maximum Dates and costs then become ranges Difference in cost between outcomes can be used to define case-by-case estimation uncertainty contingency Typical plan analysis: Probability of achieving the deterministic cost Reference 3
  • 12. 12 of 21 Potential Weakness of 3 Point Estimates Outcomes may be pessimistic if most likely estimates are not 50% likely Typical 3 point estimate Probability of Most Likely estimate PML PML = 2/(10-4) = 1/3 or 33% …NOT 50%! Avoid this weakness by asking for the probability of the Most Likely estimate Example: for PML = 70% Create double triangle distribution and calculate points A & B: 0.7 = 0.5*(6-4)*A so A = 0.7 0.3 = 0.5*(10-6)*B so B = 0.15 Area either side is not equal and will vary task by task as defined by the 4th point In practice need only do this for 10 to 20 most critical tasks – found by sensitivity analysis
  • 13. 13 of 21 Selective 4 Point Estimation: Simulation Results Result for 3 point estimates alone Result including selected 4 point estimates: Higher probability of deterministic outcome Smaller, more realistic risk budget Tornado Graph: Sensitivity analysis to select tasks to estimate with 4 points Risk Budget: £21,125 Risk Budget: £13,696
  • 14. 14 of 21 Estimation Uncertainty Contingency One strategy: Estimation uncertainty ‘project risk pot’ = 95% cost – deterministic cost The business Risk Appetite can inform what probability to use, e.g.: 10% Team Target (likely risks do not occur) 50% Best Estimate (as many risks occur as not) 90% ‘Safe’ Estimate (several unlikely major risks occur) Reward using less of this risk pot, but recognise that a proportion is likely to be required This encourages behaviour that enhances results whilst recognising estimation uncertainty and setting realistic expectations PMs use project risk pot to drive delivery to the deterministic end date Drives the right behaviour in the team – to deliver on their Most Likely estimates Selective 4 point estimating maintains competitive pricing
  • 15. 15 of 21 Other Methods Price to Win estimate based on supposition or knowledge of the budget Do tailor the scope of work to suit a budget Don’t force an estimate to fit a budget Parkinson 'Work expands to fill the time available' equates the estimate to available resources These are not estimating methods – they are price and cost management methods
  • 16. 16 of 21 Estimating Process Contingency Zero Risk (Deterministic) Cost Held at project & programme level Project Risk Pot Estimation Uncertainty Top-Down Estimate Rationalise Estimates PDP Project Delivery Process Product Breakdown Structure Work Breakdown Structure Work Packages & Tasks Bottom-up 3pt Estimates I N F O R M Need Strategy Opportunities Enhancement Tasks Secondary Risks Inform / Offset Threats Mitigation Tasks Risk Register Held at portfolio level If cost effective Contingency For project risks other than estimation uncertainty
  • 17. 17 of 21 Practical Advice & Tips Choose estimating method case-by-case to suit project and environment  No perfect estimating method, suitable for all environments  Many methods rely on a database or case history of past estimates and results  Often need a combination of methods  Risk Management for project risks other than estimation uncertainty Use the proposed delivery team to create the estimates in order to get buy-in Base estimates on normal conditions: 5 day week, 8 hour day Use consistent time units Do a reality check on the result and rationalise bottom-up with top-down Range estimates are more realistic than single point (deterministic estimate) Don’t pad individual estimates as a means to handle estimation uncertainty If project type & environment always same – use one-size-fits-all estimation uncertainty contingency otherwise use 3 point estimating to derive estimation uncertainty contingency
  • 18. 18 of 21 Practical Advice & Tips II Estimation uncertainty is a significant project risk, but not the only project risk  Use Risk Management to handle the other types of project risk Bottom-up estimating: avoid long tasks and tasks where progress hard to assess Educated Guess: beware early estimates often based on little information  Can become base against which future estimates are judged (anchor heuristic)  Cautions delivered with that first estimate rarely remembered Don’t confuse uncertainty with a lack of knowledge  Large ranges generally indicate guessing  Experience is required to estimate rather than guess It’s still just an estimate  Project starts late: provide estimates from time T0 rather than a fixed date  Team members late to start: avoid ‘brick-wall’ starts where possible  Incorrect assumptions: list assumptions, track changes & adjust plans
  • 19. 19 of 21 Summary Estimating is a critical competence Be aware of impact of estimator psychology Significant innovation in projects limits useful estimation methods Build historical data records (estimate & result) where possible Combine estimation methods for best results 3 point range estimates offer case-by-case estimation uncertainty contingency 4 point estimates for few most influential tasks eradicates potential 3 point weakness One-size-fits-all estimation uncertainty contingency suitable if projects all similar Risk Management to handle project risk other than estimation uncertainty
  • 20. 20 of 21 1. Cost Estimation Method Selection: Matching User Requirements and Knowledge Availability to Methods DK Evans, Dr. JD Lanham, Dr. R Marsh, Paper for ICEC (International Cost Engineering Council), 2006 SEEDS (Systems Engineering Estimation for Decision Support), AMRC (Aerospace Manufacturing Research Centre) University of West of England, Bristol, UK 2. Delphi Estimation Method Wikipedia 3. Tool used for planning and 3 & 4 point estimation uncertainty calculations: Oracle Primavera Risk Analysis or Safran Risk References
  • 21. 21 of 21 Author Profile In my board role I led a team of 22 Project Managers and 5 Quality Engineers, and ensured Roke’s £79m project portfolio delivered better than budget profit. I set-up and ran a virtual PMO and created REP, the Roke Engineering Process, also managing the engineering tools to support it. After 4 years as an electronics engineer for Siemens, achieving Chartered Engineer, I moved into project management for 14 years, at Siemens and Roke Manor Research. Successfully delivering Roke’s most challenging whole lifecycle product developments on time and under budget led to a role as Director and board member for 6 years. In 2013 I returned to hands-on project management as Programme Director at Cambridge Consultants, founder member of the Cambridge Science Park. Creator of the APM corporate accredited PM Excellence Programme, I chaired a quarterly PM forum to share best practice and built a supportive PM community. I coached seven PMs to RPP, five to PQ, and all passed APMP. These investments in PM professionalism led to a turn-around and annual improvement in project results across a 400 project portfolio and delivered an above budget performance in five consecutive years with profits totalling £7.9m above budget. Passionate advocate of PM professionalism, Fellow of the APM and the IET and author of articles published in Project and PM Today. Professional Development Winning Project Work Planning Estimating Risk Management Earned Value Management Change Control Stakeholder Management 3 Steps to Professional Project Management: Case Study ProjectManagementTopics