SlideShare uma empresa Scribd logo
1 de 44
Operations Management: Millau Viaduct
Group 6, SYBBA B
Millau Viaduct
The Millau Viaduct is in southern France and crosses the River
            Tarn in the Massif Central mountains.
  It was designed by the British architect Lord Foster and at
   300m (984 feet) it is the highest road bridge in the world,
                  weighing 36,000 tonnes.
 The central pillar is higher than the famous French icon, the
                           Eiffel Tower.
 The Bridge opened in December 2004 and is possibly one of
          the most breath taking bridges ever built.
•   The bridge towers above
    the Tarn Valley and the aim
    of Lord Foster was to
    design a bridge with the
    ‘delicacy of a butter fly’.
•   Lord Foster designed a
    bridge that enhances the
    natural beauty of the valley,
    with the environment
    dominating the scene
    rather than the bridge.
•   The bridge appears to float
    on the clouds despite the
    fact that it has seven pillars
    and a roadway of 1½ miles
    in length.
The bridge was opened by President Jacques Chirac.

In his speech he praised the design saying that it was
a ‘monument to French engineering genius’ and ‘a
miracle of equilibrium’. 

The aim is to cut the travelling time to southern
France, removing the bottle neck at Millau, through
the completion of the motorway between Paris and
the Mediterranean.
The bridge was entirely
privately financed and cost 394
million euros (272 million
pounds, 524 million dollars).
The builders, Eiffage, financed
the construction in return for a
concession to collect the tolls
for 75 years, until 2080.
However, if the concession is
very profitable, the French
government can assume control
of the bridge in 2044.
Construction of Millau Viaduct
Steel deck with multiple sub-bended
spans.


Steel deck with continuous spans
 of constant depth.


Steel or concrete deck with multiple
cables-stayed spans


Concrete bridge including an arch with
an opening 600m wide over the River Tarn

Viaduct with continuous spans
 of variable depth in concrete or
composite material
7 piers P1 to P7
2 abutments C0 & C8
6 spans 342 m long
2 side -spans 204 m long
6 STAGES OF CONSTRUCTION
1.   Raising the piers
2.   Throwing the deck
3.   Joining the deck

4.   Installing the pylons

5.   The stays
6.   Finishings
Raising the Piers
Piers - The piers are the towering part of the structure with the tallest
one reaching over 245 meters tall. The piers hold the road way and
the pylons.
1. The piers were constructed using reinforced concrete. The piers
   have the design of tapering down from top to bottom. The seven
   piers are identical except for the length due to the valley bottom.
2. The piers have been constructed using an automatic rail climbing
   system or ACS. The system required the bottom section the pier be
   constructed then the climbing system attached to rail secured to
   the pier. Allowing the system to move up the piers independently .
3. The ACS would pour 4 meter sections of concrete at a time
   allowing accurate pours and ensuring structural stability.
4. The ACS enabled the piers to be built on schedule. The system
   allowed for a correct pour each time it moved up the pier.
Pier Design


                                            The pier design : flexible
                                           piers at their base =strong
                                              distortion of the deck




Pier design : piers with flexural
   rigidity at their base=Less
      distortion of the deck
Actual Pier   Pier 2
Throwing the deck
Usage of Temporary Piers
1.   Once these temporary piers were erected, placement of the 36,000-ton (32,659 t)
     prefabricated deck began.

1.   Placing the deck began in late February 2003. By March 26, 2004, the deck had
     progressed to the third pier. During the evenings of April 4 and 5, 2004, the deck
     arrived at the second pier with the last launch accomplished on May 28, 2004.

1.   Decks were placed with the help of hydraulics from Enerpac.

1.   Simply pushing this enormous weight over the top of the venerable piers would bring
     them crashing to the ground. The construction team made a launching system in
     which they use a series of launching systems to jack up the deck and inch it forward
     each system uses two wedge shape block on each side of the deck. the upper wedge
     is pulled forward by hydraulic system its slides up the slope of the lower wedge
     same time lifting the deck from it supports and advancing it 600 mm. the lower
     wedge then retracts dropping the deck to its support the upper wedge returns to its
     original position and the whole cycles begins again. Four of these devices are placed
     on each piers all programmed to work exactly at a same time. The result is they pick
     up the entire road way and move it forward. Every 4 minutes the deck advances 6mm
     across the valley.
Joining the deck
Moving the deck could be
accomplished three ways:
manual, semi-automatic and
automatic.

Manual mode was used for
adjustments and any necessary
instant corrections.

In the semi-automatic mode, each
movement was made step by
step, or, in other words, raise,
push, lower, and then withdraw.

Automatic mode completed each
entire launch cycle.
The technically advanced hydraulic
system was designed to push the
27,35 m wide deck (with a capacity for
six lanes plus hard shoulders) from
both sides onto the seven concrete
piers.

During the launching process, the
deck will be supported by seven
temporary metal piers.

The enormous yet at the same time
“light” deck was pushed by means of
hydraulic launching devices on each
pier, which first lift and then push the
deck.

An adjustable nose structure at the
end of the deck, allows the deck to
land on each pier as it approaches it.
In all, 18 launches — six from
the north side of the bridge and
12 from the south — were
required to position the deck,
with      the    last     launch
accomplished on May 28, 2004.
Installing
the pylons
Seven pylons had to be raised

Each of these steel pylons takes the form of an
inverted Y, 77 metres high and weighing 650
tonnes.

They were prefabricated on site and then
raised

this was quicker and reduced not only the risk
of interruption because of strong winds but also
the problems of safety

Once the assembly and welding work was
complete, the pylon is transported flat onto the
viaduct deck by means of a special multi-axle
lowered Kamag trailer weighing 200 tonnes.

The pylon is manoeuvred into a vertical
position using lifting towers rather than mobile
cranes because of its speed, narrow confines
of the deck, weather risks and safety
requirements.
The time taken to lift a pylon
is around 6-7 hours.

All the operations involving
the pylon, including loading,
transportation, lifting and
welding to the deck, and the
lifting tower and putting it in
position was at the rate of one
pylon per week.
THE STAYS
Each pylon of the viaduct is equipped with a
monoaxial layer of eleven pairs of stays laid
face to face.

Depending on their length, the stays were
made of 55 to 91 high tensile steel cables, or
strands, themselves formed of seven strands of
steel

Each strand has triple protection against
corrosion and the stay-cables weight about
1,500 tons

The exterior envelope of the stays is itself
coated along its entire length with a double
helical weatherstrip. The idea is to avoid
running water which, in high winds, could
cause vibration in the stays and compromise
the stability of the viaduct.

The stays were installed using a well-tried
technique. After threading one strand in the
outer protective sheath, it is pulled up on to the
pylon to its final location.

The strand is then fixed in the upper and lower
anchorage points. A 'shuttle' then brings the
other strands one by one, and they are then
stretched to tension."
FINISHINGS
The surface (the covering of the road) of the millau viaduct is the result of several months of research. It was designed to withstand
any distortion of deck & provide the necessary qualities for comfortable motorway driving. It took less than four days work to lay it.
Final finishing touches: electric lighting, signposts, operating systems, final road covering.
To make the world’s tallest bridge
Material Handling
What is material handling ?


 Material Handling is the movement, storage, control and
protection of materials, goods and products throughout the
 process of manufacturing, distribution, consumption and
                          disposal.

   The focus is on the methods, mechanical equipment,
   systems and related controls used to achieve these
                        functions.

Material handling is an integral part of any industrial activity
 as greater emphasis is laid on productivity, profitability as
well as resource conservation and ecological preservation.

  Material handling plays a very crucial role in sustaining
      efficiency in financial and human resources.
Millau Bridge


 -Weight   242000 tonnes

 -Estimated   life 120 years
MAJOR MATERIALS :

                               1. STEEL :



     Steel is used in many places where concrete was earlier used

The cost of steel and concrete was about 390 million euros (520 million
                               dollars).

The project required about 19,000 metric tons of steel for the reinforced
concrete, and 5,000 metric tons of pre-stressed steel for the cables and
                               shrouds. 

The bridge is constructed out of 2,078 steel pieces made by the EIFFEL
  Company, the successor of the company that built the Eiffel Tower

The deck and pylons are made of steel sheets of grade S355 and S460.
•   All steel components were welded
    together, assembled and painted
    at ground level, and in many cases
    even in an indoor workshop.

•    This had a favorable effect on the
    quality of the finished pieces, on
    the safety of the workforce and on
    cost as steel is a recyclable metal
2. CONCRETE :

           The project required about 127,000 m³ of concrete.

The concrete of the abutments and piles amounted to 85 000 m3, 40 times
                              the Eiffel Tower

  The massive piers are made from type B60 concrete, a high-strength
      concrete with durability characteristics more than its mechanical
                                 resistance.

   During construction of the bridge concrete pours were made 4m tall
3. Stay Cable material :

The stay cables are made from T15 strands of class 1,860MPa which are
               super-galvanized, sheathed, and waxed.

The cables are protected by a white, aerodynamic sheath made from non-
               injected PEHD (high-density polyethylene)

   Developed by through a collaboration between Buonomo, Servant,
              Virlogeux, Cremer, Goyet and Del Forno
ENVIRONMENT FRIENDLY USE OF MATERIALS



Steel was used in most places instead of concrete which reduced the use
                                of trucks.

Included a system for collecting and processing rainwater and other waste
            which would be accumulated during road washing

Excess construction materials were carefully stored to use them for other
                              operations

                       - wood was sent to paper mills

                 - oil and lubricants were sent for recycling

 Various sites of production zones had been selected with an intention to
               keep hedge and bush felling to the minimum
PROBLEMS ENCOUNTERED
IDEA
•The Millau Viaduct being one of the most extensive projects ever
tackled by the construction industry faced huge challenges
particularly due its location and enormous size.



•CivilEngineer Michel Virlogeux ,was attempting to push the limits of
engineering and create something that had never been done before
when he came up with his idea for the design of the Millau Viaduct.
With architect Sir Norman Foster he created a sweeping elegant
design for the structure that would also be structurally sound.
•Thefinal design was without a doubt one of the most
appealing ever before created and proved that “big doesn’t
always have to look brawny.”



•After   14 years of intense planning the construction began.
CONSTRUCTION
                       MAJOR CHALLENGES:




1.   Build the tallest bridge piers in the world.

2.   Put a 36000 ton free way on top of them.

3.   Erect 7 steel pylons each weights 700 tons.

4.   Land
1. PIERS
•   There are 7 piers that are numbered from the northern end of the valley. Number 1 was to
    cause problems because of steep slope. Number 2 was the tallest across the river number
    3 was not much shorter from no. 2. Then 4, 5, 6 and 7 found the genital slope to the south.



•    16000 tons of steel bars are used. The shape of each pair is complicated as a result each
    time they removed the section of red steel sheltering they have to change the shape of the
    mold to fit the profile of the next 4 meter section man handling these steel panels way up
    to 15 tons of piece is no picnic. And with the combine height of 7 piers totaling well over a
    kilometer they had to change the shape of the mold over 250 times.



•   Every 3 days each team on each pair went through this whole cycle then they repeated the
    process but it was time consuming.Month after month the piers climbed higher finally by
    November 2003 they reached their full height. At 245 meters pair 2 becomes the highest
    bridge pier in the world. The piers were exactly on the location where it had to be with 2cm
    deviation.
2. Free way on top of them.

•   Second problem was putting a 36000 ton free way on top of the piers. Working
    at these heights could be lethal. Around 235 people died in the process.

•   Therefore the team decided to fabricate the entire rope deck on the safety of
    solid grounds instead of concrete, steel was used for the deck which in theory
    would be much safer then lifting concrete sections hundreds of meters in the
    position. EIFFEL, the steel firm took up the challenge.

•   This involved manufacturing 2200 separate sections weighing up to 90 tons and
    some of them 22 meters long. Their accuracy was measured with laser to within
    a fraction of a millimeter. The triangular side panel were welded on either side
    to create width for a 4 lane high way. They automated the manufacturing with a
    two headed welding robot and a plasma cutting machine each cutting pattern or
    template was programmed in to the computer then the machine automatically
    blazes its way through the steel.
3. Erect the steel pylons
•   Another problem faced with construction was the need to eliminate error in
    position.
•   The pylons were of such enormous heights that being off even the
    slightest at the bottom of the pylon could spell disaster at the top of the
    pylon in the form of meters off the intended mark.
•    When considering the pylons, other challenges faced included: pouring
    the cement in a timely manner as to prevent from setting, hurricane grade
    winds faced by workers, and the intricate design of each pylon moving to
    the overall construction of the bridge.
•    This made constructing the platform a challenge all its own. Spans of this
    great length in the past have spelled disaster in the form of collapse of the
    structure and death of workers.
•    The road spans also would be at the highest point putting the winds at
    even larger velocities. Placing the 700 ton pylons atop the bridge and
    adding even more weight to the roadways also served as challenges that
    could result in the destruction and abrupt end of the Millau Viaduct.
4. LAND
•Another challenge to overcome was the need to drill and bury the
foundations of the massive pylons deep into the bed rock.

•The challenge here was that there are cavities throughout the
country side that have fractured the limestone. These cavities are
necessary to the survival of the local cheese industry. This terrain is
responsible for containing the bacteria responsible for the blue
mold necessary to make Roquefort cheese.

•The cracked limestone meant one thing, landslides! Not far into the
project this problem became a reality, with a landslide pushing rock
and dirt into the first pylon. This landslide however, did not hurt the
pylon.
THANK YOU!
              Mihir Mandrekar B030

                Surbhi Mehta B032

         Abhilasha Mohan Ram B034

                  Rohan Negi B035

               Dhawal Pasad B037

Mais conteúdo relacionado

Mais procurados

Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Rajesh Prasad
 
Calculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridgeCalculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridgeMohammed Abdelkawy
 
Suspension bridge
Suspension bridgeSuspension bridge
Suspension bridgeMohit Kumar
 
Dubai burj al-arab hotel2 copy
Dubai burj al-arab hotel2 copyDubai burj al-arab hotel2 copy
Dubai burj al-arab hotel2 copyChyi Ong
 
Research paper of leaning tower of pisa
Research paper of leaning tower of pisaResearch paper of leaning tower of pisa
Research paper of leaning tower of pisaRushabh shah
 
Burj Khalifa - Design & construction technologies
Burj Khalifa - Design & construction technologiesBurj Khalifa - Design & construction technologies
Burj Khalifa - Design & construction technologiesAkshey Sharma
 
DMRC REPORT ON UNDERGROUND CONSTRUCTION
DMRC REPORT ON UNDERGROUND CONSTRUCTIONDMRC REPORT ON UNDERGROUND CONSTRUCTION
DMRC REPORT ON UNDERGROUND CONSTRUCTIONMd Shadab
 
62617938 launching-girder
62617938 launching-girder62617938 launching-girder
62617938 launching-girderlotuseye
 
Submerged tunnel technical seminar
Submerged tunnel technical seminarSubmerged tunnel technical seminar
Submerged tunnel technical seminarPrashant Ojha
 
Slip form Construction Technology
Slip form Construction TechnologySlip form Construction Technology
Slip form Construction TechnologyDarshit
 
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONatchitect and design
 
Foundation Failure
Foundation FailureFoundation Failure
Foundation Failureguest70cc59
 
Bandra+worli+sea+link
Bandra+worli+sea+linkBandra+worli+sea+link
Bandra+worli+sea+linkASHOK KUMAR
 
Presentation Rev.A 17-Sep-2015 Revision 3
Presentation Rev.A 17-Sep-2015 Revision 3Presentation Rev.A 17-Sep-2015 Revision 3
Presentation Rev.A 17-Sep-2015 Revision 3Shobhit Shekhar
 
Construction of Eiffel tower
Construction of Eiffel towerConstruction of Eiffel tower
Construction of Eiffel towerDeyaa Adi
 
Contour Crafting
Contour CraftingContour Crafting
Contour CraftingTemy Peter
 
Cofferdams_Advanced Construction Technology
Cofferdams_Advanced Construction TechnologyCofferdams_Advanced Construction Technology
Cofferdams_Advanced Construction TechnologyA Makwana
 

Mais procurados (20)

Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...
 
Calculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridgeCalculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridge
 
Suspension bridge
Suspension bridgeSuspension bridge
Suspension bridge
 
Dubai burj al-arab hotel2 copy
Dubai burj al-arab hotel2 copyDubai burj al-arab hotel2 copy
Dubai burj al-arab hotel2 copy
 
Research paper of leaning tower of pisa
Research paper of leaning tower of pisaResearch paper of leaning tower of pisa
Research paper of leaning tower of pisa
 
Burj Khalifa - Design & construction technologies
Burj Khalifa - Design & construction technologiesBurj Khalifa - Design & construction technologies
Burj Khalifa - Design & construction technologies
 
Metro Work
Metro WorkMetro Work
Metro Work
 
DMRC REPORT ON UNDERGROUND CONSTRUCTION
DMRC REPORT ON UNDERGROUND CONSTRUCTIONDMRC REPORT ON UNDERGROUND CONSTRUCTION
DMRC REPORT ON UNDERGROUND CONSTRUCTION
 
golden gate bridge
golden gate bridgegolden gate bridge
golden gate bridge
 
62617938 launching-girder
62617938 launching-girder62617938 launching-girder
62617938 launching-girder
 
Bandra worli sea link
Bandra worli sea linkBandra worli sea link
Bandra worli sea link
 
Submerged tunnel technical seminar
Submerged tunnel technical seminarSubmerged tunnel technical seminar
Submerged tunnel technical seminar
 
Slip form Construction Technology
Slip form Construction TechnologySlip form Construction Technology
Slip form Construction Technology
 
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
 
Foundation Failure
Foundation FailureFoundation Failure
Foundation Failure
 
Bandra+worli+sea+link
Bandra+worli+sea+linkBandra+worli+sea+link
Bandra+worli+sea+link
 
Presentation Rev.A 17-Sep-2015 Revision 3
Presentation Rev.A 17-Sep-2015 Revision 3Presentation Rev.A 17-Sep-2015 Revision 3
Presentation Rev.A 17-Sep-2015 Revision 3
 
Construction of Eiffel tower
Construction of Eiffel towerConstruction of Eiffel tower
Construction of Eiffel tower
 
Contour Crafting
Contour CraftingContour Crafting
Contour Crafting
 
Cofferdams_Advanced Construction Technology
Cofferdams_Advanced Construction TechnologyCofferdams_Advanced Construction Technology
Cofferdams_Advanced Construction Technology
 

Semelhante a Operations Management: Millau Viaduct - Floating Bridge on Clouds

Millau via duct presentation full analysis
Millau via duct presentation full analysisMillau via duct presentation full analysis
Millau via duct presentation full analysisMohammad Ali
 
California Orthotropic-October-2005 & Millau Normandie France Mangus LinkedIn
California Orthotropic-October-2005 & Millau Normandie France Mangus LinkedInCalifornia Orthotropic-October-2005 & Millau Normandie France Mangus LinkedIn
California Orthotropic-October-2005 & Millau Normandie France Mangus LinkedInAlfred Mangus
 
Presentation on Millau viaduct
Presentation on Millau viaductPresentation on Millau viaduct
Presentation on Millau viaductJayanta Sen
 
Suspension bridge (modern const. tech)
Suspension bridge (modern const. tech)Suspension bridge (modern const. tech)
Suspension bridge (modern const. tech)Vivek Chauhan
 
Conwy Tubular Railway Bridge
Conwy Tubular Railway BridgeConwy Tubular Railway Bridge
Conwy Tubular Railway BridgeVanessa Masters
 
Cable stayed bridges of prestressed concrete.
Cable stayed bridges of prestressed concrete.Cable stayed bridges of prestressed concrete.
Cable stayed bridges of prestressed concrete.Franco Bontempi
 
Petronas tower - Malaysia (Theory of Structures)
Petronas tower - Malaysia  (Theory of Structures)Petronas tower - Malaysia  (Theory of Structures)
Petronas tower - Malaysia (Theory of Structures)RADHIKASARDA8
 
Case study on signature bridge ppt (1)
Case study on signature bridge ppt (1)Case study on signature bridge ppt (1)
Case study on signature bridge ppt (1)varun km
 
Eiffle Tower | Elevator | History of Architecture
Eiffle Tower | Elevator | History of ArchitectureEiffle Tower | Elevator | History of Architecture
Eiffle Tower | Elevator | History of ArchitectureAkshit Charan
 
Mo utilizado en la fabricación de gruas
Mo utilizado en la fabricación de gruasMo utilizado en la fabricación de gruas
Mo utilizado en la fabricación de gruasDaniel García
 
Cast in situ bridge superstracture
Cast in situ bridge superstractureCast in situ bridge superstracture
Cast in situ bridge superstracturekhushal tadas
 
The Akashi Kaikyo bridge - longest suspension bridge in the world
The Akashi Kaikyo bridge - longest suspension bridge in the worldThe Akashi Kaikyo bridge - longest suspension bridge in the world
The Akashi Kaikyo bridge - longest suspension bridge in the worldADARSH _
 
Gaurav-Jhalani-Seminar-ppt.pptx
Gaurav-Jhalani-Seminar-ppt.pptxGaurav-Jhalani-Seminar-ppt.pptx
Gaurav-Jhalani-Seminar-ppt.pptxSanjeevGupta660170
 
Busan geoje fixed link
Busan   geoje fixed linkBusan   geoje fixed link
Busan geoje fixed linkVicky Matwan
 
4.2 Offshore platform.pptx
4.2 Offshore platform.pptx4.2 Offshore platform.pptx
4.2 Offshore platform.pptxVijayalakshmiR64
 
Cn tower.. a detailed study
Cn tower.. a detailed studyCn tower.. a detailed study
Cn tower.. a detailed studyMelbin Biju
 

Semelhante a Operations Management: Millau Viaduct - Floating Bridge on Clouds (20)

Millau via duct presentation full analysis
Millau via duct presentation full analysisMillau via duct presentation full analysis
Millau via duct presentation full analysis
 
California Orthotropic-October-2005 & Millau Normandie France Mangus LinkedIn
California Orthotropic-October-2005 & Millau Normandie France Mangus LinkedInCalifornia Orthotropic-October-2005 & Millau Normandie France Mangus LinkedIn
California Orthotropic-October-2005 & Millau Normandie France Mangus LinkedIn
 
Presentation on Millau viaduct
Presentation on Millau viaductPresentation on Millau viaduct
Presentation on Millau viaduct
 
Suspension bridge (modern const. tech)
Suspension bridge (modern const. tech)Suspension bridge (modern const. tech)
Suspension bridge (modern const. tech)
 
Puente izable
Puente izablePuente izable
Puente izable
 
Conwy Tubular Railway Bridge
Conwy Tubular Railway BridgeConwy Tubular Railway Bridge
Conwy Tubular Railway Bridge
 
Cable stayed bridges of prestressed concrete.
Cable stayed bridges of prestressed concrete.Cable stayed bridges of prestressed concrete.
Cable stayed bridges of prestressed concrete.
 
Petronas tower - Malaysia (Theory of Structures)
Petronas tower - Malaysia  (Theory of Structures)Petronas tower - Malaysia  (Theory of Structures)
Petronas tower - Malaysia (Theory of Structures)
 
Case study on signature bridge ppt (1)
Case study on signature bridge ppt (1)Case study on signature bridge ppt (1)
Case study on signature bridge ppt (1)
 
Eiffle Tower | Elevator | History of Architecture
Eiffle Tower | Elevator | History of ArchitectureEiffle Tower | Elevator | History of Architecture
Eiffle Tower | Elevator | History of Architecture
 
Mo utilizado en la fabricación de gruas
Mo utilizado en la fabricación de gruasMo utilizado en la fabricación de gruas
Mo utilizado en la fabricación de gruas
 
Cast in situ bridge superstracture
Cast in situ bridge superstractureCast in situ bridge superstracture
Cast in situ bridge superstracture
 
THE CONSTRUCTION PROCEDURE AND ADVANTAGE OF THE RAIL CABLE-LIFTING CONSTRUCTI...
THE CONSTRUCTION PROCEDURE AND ADVANTAGE OF THE RAIL CABLE-LIFTING CONSTRUCTI...THE CONSTRUCTION PROCEDURE AND ADVANTAGE OF THE RAIL CABLE-LIFTING CONSTRUCTI...
THE CONSTRUCTION PROCEDURE AND ADVANTAGE OF THE RAIL CABLE-LIFTING CONSTRUCTI...
 
Suspension Bridges
Suspension BridgesSuspension Bridges
Suspension Bridges
 
Training
TrainingTraining
Training
 
The Akashi Kaikyo bridge - longest suspension bridge in the world
The Akashi Kaikyo bridge - longest suspension bridge in the worldThe Akashi Kaikyo bridge - longest suspension bridge in the world
The Akashi Kaikyo bridge - longest suspension bridge in the world
 
Gaurav-Jhalani-Seminar-ppt.pptx
Gaurav-Jhalani-Seminar-ppt.pptxGaurav-Jhalani-Seminar-ppt.pptx
Gaurav-Jhalani-Seminar-ppt.pptx
 
Busan geoje fixed link
Busan   geoje fixed linkBusan   geoje fixed link
Busan geoje fixed link
 
4.2 Offshore platform.pptx
4.2 Offshore platform.pptx4.2 Offshore platform.pptx
4.2 Offshore platform.pptx
 
Cn tower.. a detailed study
Cn tower.. a detailed studyCn tower.. a detailed study
Cn tower.. a detailed study
 

Mais de Rohan Negi

Mark zuckerberg
Mark zuckerbergMark zuckerberg
Mark zuckerbergRohan Negi
 
Subprime Crisis(Brief)
Subprime Crisis(Brief)Subprime Crisis(Brief)
Subprime Crisis(Brief)Rohan Negi
 
Toyota: Analysis of Vision Statement, Corporate Level Strategies & SWOT
Toyota: Analysis of Vision Statement, Corporate Level Strategies & SWOTToyota: Analysis of Vision Statement, Corporate Level Strategies & SWOT
Toyota: Analysis of Vision Statement, Corporate Level Strategies & SWOTRohan Negi
 
Toyota: Analysis of Vision Statement, Corporate Level Strategies & SWOT
Toyota: Analysis of Vision Statement, Corporate Level Strategies & SWOTToyota: Analysis of Vision Statement, Corporate Level Strategies & SWOT
Toyota: Analysis of Vision Statement, Corporate Level Strategies & SWOTRohan Negi
 
A Report on PepsiCo
A Report on PepsiCoA Report on PepsiCo
A Report on PepsiCoRohan Negi
 
Bonds and Debentures
Bonds and DebenturesBonds and Debentures
Bonds and DebenturesRohan Negi
 
Nike defense strategies
Nike defense strategies Nike defense strategies
Nike defense strategies Rohan Negi
 
ICICI-An HR perspective
ICICI-An HR perspectiveICICI-An HR perspective
ICICI-An HR perspectiveRohan Negi
 
Consumer protection act,1986
Consumer protection act,1986Consumer protection act,1986
Consumer protection act,1986Rohan Negi
 
Coke recall current scenarios,conclusion,self-learning
Coke recall current scenarios,conclusion,self-learningCoke recall current scenarios,conclusion,self-learning
Coke recall current scenarios,conclusion,self-learningRohan Negi
 

Mais de Rohan Negi (10)

Mark zuckerberg
Mark zuckerbergMark zuckerberg
Mark zuckerberg
 
Subprime Crisis(Brief)
Subprime Crisis(Brief)Subprime Crisis(Brief)
Subprime Crisis(Brief)
 
Toyota: Analysis of Vision Statement, Corporate Level Strategies & SWOT
Toyota: Analysis of Vision Statement, Corporate Level Strategies & SWOTToyota: Analysis of Vision Statement, Corporate Level Strategies & SWOT
Toyota: Analysis of Vision Statement, Corporate Level Strategies & SWOT
 
Toyota: Analysis of Vision Statement, Corporate Level Strategies & SWOT
Toyota: Analysis of Vision Statement, Corporate Level Strategies & SWOTToyota: Analysis of Vision Statement, Corporate Level Strategies & SWOT
Toyota: Analysis of Vision Statement, Corporate Level Strategies & SWOT
 
A Report on PepsiCo
A Report on PepsiCoA Report on PepsiCo
A Report on PepsiCo
 
Bonds and Debentures
Bonds and DebenturesBonds and Debentures
Bonds and Debentures
 
Nike defense strategies
Nike defense strategies Nike defense strategies
Nike defense strategies
 
ICICI-An HR perspective
ICICI-An HR perspectiveICICI-An HR perspective
ICICI-An HR perspective
 
Consumer protection act,1986
Consumer protection act,1986Consumer protection act,1986
Consumer protection act,1986
 
Coke recall current scenarios,conclusion,self-learning
Coke recall current scenarios,conclusion,self-learningCoke recall current scenarios,conclusion,self-learning
Coke recall current scenarios,conclusion,self-learning
 

Último

How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpinRaunakKeshri1
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactPECB
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 

Último (20)

How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpin
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 

Operations Management: Millau Viaduct - Floating Bridge on Clouds

  • 1. Operations Management: Millau Viaduct Group 6, SYBBA B
  • 2. Millau Viaduct The Millau Viaduct is in southern France and crosses the River Tarn in the Massif Central mountains. It was designed by the British architect Lord Foster and at 300m (984 feet) it is the highest road bridge in the world, weighing 36,000 tonnes. The central pillar is higher than the famous French icon, the Eiffel Tower. The Bridge opened in December 2004 and is possibly one of the most breath taking bridges ever built.
  • 3. The bridge towers above the Tarn Valley and the aim of Lord Foster was to design a bridge with the ‘delicacy of a butter fly’. • Lord Foster designed a bridge that enhances the natural beauty of the valley, with the environment dominating the scene rather than the bridge. • The bridge appears to float on the clouds despite the fact that it has seven pillars and a roadway of 1½ miles in length.
  • 4. The bridge was opened by President Jacques Chirac. In his speech he praised the design saying that it was a ‘monument to French engineering genius’ and ‘a miracle of equilibrium’.  The aim is to cut the travelling time to southern France, removing the bottle neck at Millau, through the completion of the motorway between Paris and the Mediterranean.
  • 5. The bridge was entirely privately financed and cost 394 million euros (272 million pounds, 524 million dollars). The builders, Eiffage, financed the construction in return for a concession to collect the tolls for 75 years, until 2080. However, if the concession is very profitable, the French government can assume control of the bridge in 2044.
  • 7. Steel deck with multiple sub-bended spans. Steel deck with continuous spans of constant depth. Steel or concrete deck with multiple cables-stayed spans Concrete bridge including an arch with an opening 600m wide over the River Tarn Viaduct with continuous spans of variable depth in concrete or composite material
  • 8. 7 piers P1 to P7 2 abutments C0 & C8 6 spans 342 m long 2 side -spans 204 m long
  • 9. 6 STAGES OF CONSTRUCTION 1. Raising the piers 2. Throwing the deck 3. Joining the deck 4. Installing the pylons 5. The stays 6. Finishings
  • 11. Piers - The piers are the towering part of the structure with the tallest one reaching over 245 meters tall. The piers hold the road way and the pylons. 1. The piers were constructed using reinforced concrete. The piers have the design of tapering down from top to bottom. The seven piers are identical except for the length due to the valley bottom. 2. The piers have been constructed using an automatic rail climbing system or ACS. The system required the bottom section the pier be constructed then the climbing system attached to rail secured to the pier. Allowing the system to move up the piers independently . 3. The ACS would pour 4 meter sections of concrete at a time allowing accurate pours and ensuring structural stability. 4. The ACS enabled the piers to be built on schedule. The system allowed for a correct pour each time it moved up the pier.
  • 12. Pier Design The pier design : flexible piers at their base =strong distortion of the deck Pier design : piers with flexural rigidity at their base=Less distortion of the deck
  • 13. Actual Pier Pier 2
  • 16. 1. Once these temporary piers were erected, placement of the 36,000-ton (32,659 t) prefabricated deck began. 1. Placing the deck began in late February 2003. By March 26, 2004, the deck had progressed to the third pier. During the evenings of April 4 and 5, 2004, the deck arrived at the second pier with the last launch accomplished on May 28, 2004. 1. Decks were placed with the help of hydraulics from Enerpac. 1. Simply pushing this enormous weight over the top of the venerable piers would bring them crashing to the ground. The construction team made a launching system in which they use a series of launching systems to jack up the deck and inch it forward each system uses two wedge shape block on each side of the deck. the upper wedge is pulled forward by hydraulic system its slides up the slope of the lower wedge same time lifting the deck from it supports and advancing it 600 mm. the lower wedge then retracts dropping the deck to its support the upper wedge returns to its original position and the whole cycles begins again. Four of these devices are placed on each piers all programmed to work exactly at a same time. The result is they pick up the entire road way and move it forward. Every 4 minutes the deck advances 6mm across the valley.
  • 18. Moving the deck could be accomplished three ways: manual, semi-automatic and automatic. Manual mode was used for adjustments and any necessary instant corrections. In the semi-automatic mode, each movement was made step by step, or, in other words, raise, push, lower, and then withdraw. Automatic mode completed each entire launch cycle.
  • 19. The technically advanced hydraulic system was designed to push the 27,35 m wide deck (with a capacity for six lanes plus hard shoulders) from both sides onto the seven concrete piers. During the launching process, the deck will be supported by seven temporary metal piers. The enormous yet at the same time “light” deck was pushed by means of hydraulic launching devices on each pier, which first lift and then push the deck. An adjustable nose structure at the end of the deck, allows the deck to land on each pier as it approaches it.
  • 20. In all, 18 launches — six from the north side of the bridge and 12 from the south — were required to position the deck, with the last launch accomplished on May 28, 2004.
  • 22. Seven pylons had to be raised Each of these steel pylons takes the form of an inverted Y, 77 metres high and weighing 650 tonnes. They were prefabricated on site and then raised this was quicker and reduced not only the risk of interruption because of strong winds but also the problems of safety Once the assembly and welding work was complete, the pylon is transported flat onto the viaduct deck by means of a special multi-axle lowered Kamag trailer weighing 200 tonnes. The pylon is manoeuvred into a vertical position using lifting towers rather than mobile cranes because of its speed, narrow confines of the deck, weather risks and safety requirements.
  • 23. The time taken to lift a pylon is around 6-7 hours. All the operations involving the pylon, including loading, transportation, lifting and welding to the deck, and the lifting tower and putting it in position was at the rate of one pylon per week.
  • 25. Each pylon of the viaduct is equipped with a monoaxial layer of eleven pairs of stays laid face to face. Depending on their length, the stays were made of 55 to 91 high tensile steel cables, or strands, themselves formed of seven strands of steel Each strand has triple protection against corrosion and the stay-cables weight about 1,500 tons The exterior envelope of the stays is itself coated along its entire length with a double helical weatherstrip. The idea is to avoid running water which, in high winds, could cause vibration in the stays and compromise the stability of the viaduct. The stays were installed using a well-tried technique. After threading one strand in the outer protective sheath, it is pulled up on to the pylon to its final location. The strand is then fixed in the upper and lower anchorage points. A 'shuttle' then brings the other strands one by one, and they are then stretched to tension."
  • 26. FINISHINGS The surface (the covering of the road) of the millau viaduct is the result of several months of research. It was designed to withstand any distortion of deck & provide the necessary qualities for comfortable motorway driving. It took less than four days work to lay it. Final finishing touches: electric lighting, signposts, operating systems, final road covering.
  • 27. To make the world’s tallest bridge
  • 29. What is material handling ? Material Handling is the movement, storage, control and protection of materials, goods and products throughout the process of manufacturing, distribution, consumption and disposal. The focus is on the methods, mechanical equipment, systems and related controls used to achieve these functions. Material handling is an integral part of any industrial activity as greater emphasis is laid on productivity, profitability as well as resource conservation and ecological preservation. Material handling plays a very crucial role in sustaining efficiency in financial and human resources.
  • 30. Millau Bridge -Weight 242000 tonnes -Estimated life 120 years
  • 31. MAJOR MATERIALS : 1. STEEL : Steel is used in many places where concrete was earlier used The cost of steel and concrete was about 390 million euros (520 million dollars). The project required about 19,000 metric tons of steel for the reinforced concrete, and 5,000 metric tons of pre-stressed steel for the cables and shrouds.  The bridge is constructed out of 2,078 steel pieces made by the EIFFEL Company, the successor of the company that built the Eiffel Tower The deck and pylons are made of steel sheets of grade S355 and S460.
  • 32. All steel components were welded together, assembled and painted at ground level, and in many cases even in an indoor workshop. • This had a favorable effect on the quality of the finished pieces, on the safety of the workforce and on cost as steel is a recyclable metal
  • 33. 2. CONCRETE : The project required about 127,000 m³ of concrete. The concrete of the abutments and piles amounted to 85 000 m3, 40 times the Eiffel Tower The massive piers are made from type B60 concrete, a high-strength concrete with durability characteristics more than its mechanical resistance. During construction of the bridge concrete pours were made 4m tall
  • 34. 3. Stay Cable material : The stay cables are made from T15 strands of class 1,860MPa which are super-galvanized, sheathed, and waxed. The cables are protected by a white, aerodynamic sheath made from non- injected PEHD (high-density polyethylene) Developed by through a collaboration between Buonomo, Servant, Virlogeux, Cremer, Goyet and Del Forno
  • 35. ENVIRONMENT FRIENDLY USE OF MATERIALS Steel was used in most places instead of concrete which reduced the use of trucks. Included a system for collecting and processing rainwater and other waste which would be accumulated during road washing Excess construction materials were carefully stored to use them for other operations - wood was sent to paper mills - oil and lubricants were sent for recycling Various sites of production zones had been selected with an intention to keep hedge and bush felling to the minimum
  • 37. IDEA •The Millau Viaduct being one of the most extensive projects ever tackled by the construction industry faced huge challenges particularly due its location and enormous size. •CivilEngineer Michel Virlogeux ,was attempting to push the limits of engineering and create something that had never been done before when he came up with his idea for the design of the Millau Viaduct. With architect Sir Norman Foster he created a sweeping elegant design for the structure that would also be structurally sound.
  • 38. •Thefinal design was without a doubt one of the most appealing ever before created and proved that “big doesn’t always have to look brawny.” •After 14 years of intense planning the construction began.
  • 39. CONSTRUCTION MAJOR CHALLENGES: 1. Build the tallest bridge piers in the world. 2. Put a 36000 ton free way on top of them. 3. Erect 7 steel pylons each weights 700 tons. 4. Land
  • 40. 1. PIERS • There are 7 piers that are numbered from the northern end of the valley. Number 1 was to cause problems because of steep slope. Number 2 was the tallest across the river number 3 was not much shorter from no. 2. Then 4, 5, 6 and 7 found the genital slope to the south. • 16000 tons of steel bars are used. The shape of each pair is complicated as a result each time they removed the section of red steel sheltering they have to change the shape of the mold to fit the profile of the next 4 meter section man handling these steel panels way up to 15 tons of piece is no picnic. And with the combine height of 7 piers totaling well over a kilometer they had to change the shape of the mold over 250 times. • Every 3 days each team on each pair went through this whole cycle then they repeated the process but it was time consuming.Month after month the piers climbed higher finally by November 2003 they reached their full height. At 245 meters pair 2 becomes the highest bridge pier in the world. The piers were exactly on the location where it had to be with 2cm deviation.
  • 41. 2. Free way on top of them. • Second problem was putting a 36000 ton free way on top of the piers. Working at these heights could be lethal. Around 235 people died in the process. • Therefore the team decided to fabricate the entire rope deck on the safety of solid grounds instead of concrete, steel was used for the deck which in theory would be much safer then lifting concrete sections hundreds of meters in the position. EIFFEL, the steel firm took up the challenge. • This involved manufacturing 2200 separate sections weighing up to 90 tons and some of them 22 meters long. Their accuracy was measured with laser to within a fraction of a millimeter. The triangular side panel were welded on either side to create width for a 4 lane high way. They automated the manufacturing with a two headed welding robot and a plasma cutting machine each cutting pattern or template was programmed in to the computer then the machine automatically blazes its way through the steel.
  • 42. 3. Erect the steel pylons • Another problem faced with construction was the need to eliminate error in position. • The pylons were of such enormous heights that being off even the slightest at the bottom of the pylon could spell disaster at the top of the pylon in the form of meters off the intended mark. • When considering the pylons, other challenges faced included: pouring the cement in a timely manner as to prevent from setting, hurricane grade winds faced by workers, and the intricate design of each pylon moving to the overall construction of the bridge. • This made constructing the platform a challenge all its own. Spans of this great length in the past have spelled disaster in the form of collapse of the structure and death of workers. • The road spans also would be at the highest point putting the winds at even larger velocities. Placing the 700 ton pylons atop the bridge and adding even more weight to the roadways also served as challenges that could result in the destruction and abrupt end of the Millau Viaduct.
  • 43. 4. LAND •Another challenge to overcome was the need to drill and bury the foundations of the massive pylons deep into the bed rock. •The challenge here was that there are cavities throughout the country side that have fractured the limestone. These cavities are necessary to the survival of the local cheese industry. This terrain is responsible for containing the bacteria responsible for the blue mold necessary to make Roquefort cheese. •The cracked limestone meant one thing, landslides! Not far into the project this problem became a reality, with a landslide pushing rock and dirt into the first pylon. This landslide however, did not hurt the pylon.
  • 44. THANK YOU! Mihir Mandrekar B030 Surbhi Mehta B032 Abhilasha Mohan Ram B034 Rohan Negi B035 Dhawal Pasad B037

Notas do Editor

  1. A Pier , in architecture, is an upright support for a structure or superstructure, such as an arch or bridge. Sections of structural walls between openings (bays) can function as piers.
  2. The height of these piers range from 254 ft. (77.6 m) up, the second and third rising to approximately 837 ft. (255 m) and 725 ft. (22l m), respectively. The tallest point of the bridge reaches a level approximately 4 percent higher than the Eiffel Tower. This was a multi-national project overseen by Eiffage du Viaduct de Millau. Automatic Rail Climbing SystemUse  The use of the ACS gave the construction crews the ability to work faster and more efficient.  The use of the ACS allowed the workers to repeat the same results every time they poured the concrete on the seven piers.
  3. Deck InstallationPre-fabricated road deck The pre-fabricated road deck saved time and allowed the bridge to be built on time.  A hydraulic system that was used to lift the pre-fabricated deck and move it slowly forward using GPS and laser alignment to ensure that the bridge was in the correct place during each phase of moving the decks closer together.  AdvantagesUsing the ENERPAC system saved time and money instead of building the road deck on to the piers.