Hello everyone! Test your PMP exam preparation and answer this Free PMP® Exam Sample Question of the week. For more of this free PMP exam sample question visit: https://free.pm-exam-simulator.com/free-pmp-exam-simulator
2. Ada, the project manager, is meeting with a customer for initial discussions about a software
implementation project. At the end of the meeting, the customer asks Ada for a general estimate
of the project duration. Based on experience with three similar projects with roughly the same
scope, Ada estimates an 8-10 month implementation time frame. What estimation technique is
Ada basing her duration projection on?
A. Expert judgment
B. Three-point estimating
C. Analogous estimating
D. Bottom-up estimating
HINT: Identify the estimating technique that compares a project to a previous, similar project.
Question
3. The correct answer is C.
Ada is using historical duration information from comparable projects to estimate the duration of
a future project. This gross value estimating approach is called analogous estimating and is
frequently used to provide a ballpark figure when there is a limited amount of detailed
information available about the project.
Answer
4. All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.
Stop by at free.pm-exam-simulator.com/ and try the
PM Exam Simulator free for 7 days.
We are a trusted and experienced education provider.