Simple example of EVM in action
© 2014 Planisware
The plan
• Our team has been tasked with planting the trees on
the plot of land behind our company’s new factory
• The plan:
– 30 batches of 20 trees (600 trees)
– 5 batches per day (100 trees)
– budgeted cost per tree 2.90$ (2.5$ per baby tree / 0.40$
for the slow release fertiliser)
→ total budget 1,740$
© 2014 Planisware 2
After the first day…
• 70 trees were planted (the team hit a patch with
stones that had to be removed before the trees
could be planted)
• Total cost was 350 $ (we had to rent a special
machine to help remove the stones which cost 147$
for the day)
• Simple EVM calculation:
– Earned Value = 70 trees planted  2.90$ = 203$
– Budgeted Cost = 100 trees planned per day  2.90$ = 290$
– Actual Cost = 70 trees planted  2.90$ + 147$ for the machine = 350$
© 2014 Planisware 3
Visually…
0
50
100
150
200
250
300
350
400
Start 1st day
Actual cost = 350$
Budgeted cost = 290$
Earned Value = 203$
© 2014 Planisware 4
Regarding cost…
0
50
100
150
200
250
300
350
400
Start 1st day
EV
AC
BC
© 2014 Planisware 5
We are here
Regarding cost…
0
50
100
150
200
250
300
350
400
Start 1st day
EV
AC
BC
© 2014 Planisware 6
We are here
We should have been here
Regarding cost…
0
50
100
150
200
250
300
350
400
Start 1st day
EV
AC
BC
© 2014 Planisware 7
Cost variance = EV – AC
= 203$ – 350$ = -147$ < 0
Regarding cost…
0
50
100
150
200
250
300
350
400
Start 1st day
EV
AC
BC
© 2014 Planisware 8
Cost variance = EV – AC
We’re over budget,
and have spent
203  350 = 58%
more budget than
anticipated (our cost
performance index)
= 203$ – 350$ = -147$ < 0
Regarding schedule…
0
50
100
150
200
250
300
350
400
Start 1st day
EV
AC
BC
© 2014 Planisware 9
We are here
Regarding schedule…
0
50
100
150
200
250
300
350
400
Start 1st day
EV
AC
BC
© 2014 Planisware 10
We are here
Which is where we
should have been then
Regarding schedule…
0
50
100
150
200
250
300
350
400
Start 1st day
EV
AC
BC
© 2014 Planisware 11
Schedule variance
in hours
Regarding schedule…
0
50
100
150
200
250
300
350
400
Start 1st day
EV
AC
BC
© 2014 Planisware 12
Schedule variance
in hours
= 203$ – 290$ = = -87$ < 0
Schedule variance
in dollars = EV – BC
Regarding schedule…
0
50
100
150
200
250
300
350
400
Start 1st day
EV
AC
BC
© 2014 Planisware 13
Schedule variance
in hours
We’re late and
have only performed
203/290 = 70% of
the work planned
(our schedule
performance index)
= 203$ – 290$ = = -87$ < 0
Schedule variance
in dollars = EV – BC
The consequences
0
500
1000
1500
2000
2500
3000
Start 1st 2nd 3rd 4th 5th 6th 7th 8th 9th
© 2014 Planisware 14
Earned Value
today
Estimate at Completion
EAC = 3,000$
Budget at Completion
BAC = 1,740$
Extending the
Actual Cost
into the future
gives us the end
result if we do
not modify the
performance of
the project
The consequences
0
500
1000
1500
2000
2500
3000
Start 1st 2nd 3rd 4th 5th 6th 7th 8th 9th
© 2014 Planisware 15
Earned Value
today
Estimate at Completion
EAC = 3,000$
Budget at Completion
BAC = 1,740$
Cost Overrun
The consequences
0
500
1000
1500
2000
2500
3000
Start 1st 2nd 3rd 4th 5th 6th 7th 8th 9th
© 2014 Planisware 16
Earned Value
today
Planned end date
= 6 days
Estimate at completion
= 8.57 days
Project Slip
Estimate at Completion
EAC = 3,000$
Budget at Completion
BAC = 1,740$
Cost Overrun
The consequences
→ If we continue at this rate, we will need: 1,740$  58% = 3,000 $
(cost estimate at completion)
and 6 days  70% = 8.57 days (schedule estimate at completion)
to finish the work.
→ If we want to finish on budget, we need to work at
(planned remaining budget)  (actual remaining budget)
(1,740 – 290)  (1740 – 350) = 104.3% of the originally planned
performance
→ If we want to finish on time, we need to work at
(actual remaining work)  (planned remaining work)
(600 – 70)  (600 – 100) = 106% of the originally planned
performance
© 2014 Planisware 17
In technical terms…
In real life, the elements we calculated have slightly
different names:
• The Actual Cost is usually referred to as the Actual
Cost of Works Performed (ACWP)
• The Planned Cost = Budgeted Cost for Work
Scheduled (BCWS)
• The Earned Value = Budgeted Cost for Work
Performed (BCWP)
© 2014 Planisware 18
Summary
© 2014 Planisware 19
today
time
cost
ACWP
(Actual Cost of
Work Performed)
BCWS
(Budgeted Cost of
Work Scheduled)
BCWP
(Budgeted Cost of
Work Performed)
completion
date
Budget at
Completion (BAC)
Estimate at
Completion (EAC)
Schedule variance in $
SV = BCWS - BCWP
Cost variance in $
CV = ACWP - BCWP
Cost Overrun
Project SlipSchedule variance
in hours
To learn more about EVM and tools to
help manage it, visit our glossary:
www.planisware.com/glossary/earned-
value-management
© 2014 Planisware 20

Mais conteúdo relacionado

Mais procurados

12 pmp procurement management exam
12 pmp procurement management exam12 pmp procurement management exam
12 pmp procurement management examJamil Faraj , PMP
 
08-Project-Control-ppt.ppt
08-Project-Control-ppt.ppt08-Project-Control-ppt.ppt
08-Project-Control-ppt.pptTecnicoItca
 
Case study 4 project cost management -- ppt slides
Case study 4   project cost management -- ppt slidesCase study 4   project cost management -- ppt slides
Case study 4 project cost management -- ppt slidesHarhar Caparida
 
Project cost management PMBOK 5th Edition
Project cost management PMBOK 5th EditionProject cost management PMBOK 5th Edition
Project cost management PMBOK 5th Editionpankajsh10
 
A simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementA simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementProPM Academy
 
EPC_EPCM Business process modelling rendition
EPC_EPCM Business process modelling renditionEPC_EPCM Business process modelling rendition
EPC_EPCM Business process modelling renditionJaswin Sood
 
Ch 9 project monitoring &amp; control updated
Ch 9 project monitoring &amp; control updatedCh 9 project monitoring &amp; control updated
Ch 9 project monitoring &amp; control updatedFarhana Rehman
 
Estimating Time & Costs
 Estimating Time & Costs Estimating Time & Costs
Estimating Time & Costsmairemic
 
Session T2 - Best Practice Project Controls with EcoSys
Session T2 - Best Practice Project Controls with EcoSysSession T2 - Best Practice Project Controls with EcoSys
Session T2 - Best Practice Project Controls with EcoSysProject Controls Expo
 

Mais procurados (20)

Cpm crashing example
Cpm crashing exampleCpm crashing example
Cpm crashing example
 
12 pmp procurement management exam
12 pmp procurement management exam12 pmp procurement management exam
12 pmp procurement management exam
 
08-Project-Control-ppt.ppt
08-Project-Control-ppt.ppt08-Project-Control-ppt.ppt
08-Project-Control-ppt.ppt
 
Case study 4 project cost management -- ppt slides
Case study 4   project cost management -- ppt slidesCase study 4   project cost management -- ppt slides
Case study 4 project cost management -- ppt slides
 
Procurement management
Procurement managementProcurement management
Procurement management
 
Project cost management PMBOK 5th Edition
Project cost management PMBOK 5th EditionProject cost management PMBOK 5th Edition
Project cost management PMBOK 5th Edition
 
A simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementA simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value Management
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
 
07 project cost management
07 project cost management07 project cost management
07 project cost management
 
EPC_EPCM Business process modelling rendition
EPC_EPCM Business process modelling renditionEPC_EPCM Business process modelling rendition
EPC_EPCM Business process modelling rendition
 
Project cost management
Project cost managementProject cost management
Project cost management
 
Ch 9 project monitoring &amp; control updated
Ch 9 project monitoring &amp; control updatedCh 9 project monitoring &amp; control updated
Ch 9 project monitoring &amp; control updated
 
EVA - Metrics.ppt
EVA - Metrics.pptEVA - Metrics.ppt
EVA - Metrics.ppt
 
WBS and OBS
WBS and OBSWBS and OBS
WBS and OBS
 
Estimating Time & Costs
 Estimating Time & Costs Estimating Time & Costs
Estimating Time & Costs
 
Session T2 - Best Practice Project Controls with EcoSys
Session T2 - Best Practice Project Controls with EcoSysSession T2 - Best Practice Project Controls with EcoSys
Session T2 - Best Practice Project Controls with EcoSys
 
11.7 Monitor Risks
11.7 Monitor Risks11.7 Monitor Risks
11.7 Monitor Risks
 
Project Control
Project ControlProject Control
Project Control
 
Adaptive Project Management
Adaptive Project ManagementAdaptive Project Management
Adaptive Project Management
 

Destaque (6)

Callidus
CallidusCallidus
Callidus
 
MICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIALMICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIAL
 
levelling and contouring
levelling and contouringlevelling and contouring
levelling and contouring
 
Earned Value Analysis - Basic Concepts
Earned Value Analysis  - Basic ConceptsEarned Value Analysis  - Basic Concepts
Earned Value Analysis - Basic Concepts
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Levelling in Surveying
Levelling in SurveyingLevelling in Surveying
Levelling in Surveying
 

Semelhante a A simple example of Earned Value Management (EVM) in action

EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...Fahad Ali
 
October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6
October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6
October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6HARDIK PARIKH
 
Homework chapter 7
Homework chapter 7Homework chapter 7
Homework chapter 7Miles Nowak
 
Culture Check on using Earned Value in Organization
Culture Check on using Earned Value in OrganizationCulture Check on using Earned Value in Organization
Culture Check on using Earned Value in OrganizationGhassan Kabbara
 
Earned value management
Earned value managementEarned value management
Earned value managementwhizkris
 
Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares Vivek Prakash
 
Earnvalue analysis in Software engineering
Earnvalue analysis in Software engineeringEarnvalue analysis in Software engineering
Earnvalue analysis in Software engineeringNitish Kumar
 
How Celoxis Helps in Budgeting & Costing
How Celoxis Helps in Budgeting & Costing How Celoxis Helps in Budgeting & Costing
How Celoxis Helps in Budgeting & Costing Nikhil Daddikar
 
Time value of money- TVM ( Discouting and Compounding)
Time value of money- TVM ( Discouting and Compounding)Time value of money- TVM ( Discouting and Compounding)
Time value of money- TVM ( Discouting and Compounding)Sweetp999
 
Earned Value Management - Project Controls - Schedule Only.pptx
Earned Value Management - Project Controls - Schedule Only.pptxEarned Value Management - Project Controls - Schedule Only.pptx
Earned Value Management - Project Controls - Schedule Only.pptxssuser5fc1e7
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)Ejaz Bhatti
 
Padgett.sam
Padgett.samPadgett.sam
Padgett.samNASAPMC
 
7.4 Forecasting Techniques
7.4 Forecasting Techniques7.4 Forecasting Techniques
7.4 Forecasting TechniquesDavidMcLachlan1
 
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPIProject Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPIDavidMcLachlan1
 
Webinar: Earned value management pure common sense
Webinar: Earned value management pure common senseWebinar: Earned value management pure common sense
Webinar: Earned value management pure common senseAli Zeeshan
 

Semelhante a A simple example of Earned Value Management (EVM) in action (20)

EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...
 
October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6
October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6
October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6
 
Homework chapter 7
Homework chapter 7Homework chapter 7
Homework chapter 7
 
Culture Check on using Earned Value in Organization
Culture Check on using Earned Value in OrganizationCulture Check on using Earned Value in Organization
Culture Check on using Earned Value in Organization
 
Chapter 9 q&p
Chapter 9 q&pChapter 9 q&p
Chapter 9 q&p
 
Earned value management
Earned value managementEarned value management
Earned value management
 
Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares
 
Earnvalue analysis in Software engineering
Earnvalue analysis in Software engineeringEarnvalue analysis in Software engineering
Earnvalue analysis in Software engineering
 
How Celoxis Helps in Budgeting & Costing
How Celoxis Helps in Budgeting & Costing How Celoxis Helps in Budgeting & Costing
How Celoxis Helps in Budgeting & Costing
 
Project Management EVM & SCBA
Project Management EVM & SCBAProject Management EVM & SCBA
Project Management EVM & SCBA
 
Basics of EVM.pdf
Basics of  EVM.pdfBasics of  EVM.pdf
Basics of EVM.pdf
 
Time value of money- TVM ( Discouting and Compounding)
Time value of money- TVM ( Discouting and Compounding)Time value of money- TVM ( Discouting and Compounding)
Time value of money- TVM ( Discouting and Compounding)
 
Earned Value Management - Project Controls - Schedule Only.pptx
Earned Value Management - Project Controls - Schedule Only.pptxEarned Value Management - Project Controls - Schedule Only.pptx
Earned Value Management - Project Controls - Schedule Only.pptx
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)
 
Padgett.sam
Padgett.samPadgett.sam
Padgett.sam
 
7.4 Forecasting Techniques
7.4 Forecasting Techniques7.4 Forecasting Techniques
7.4 Forecasting Techniques
 
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPIProject Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
 
Earned value management
Earned value managementEarned value management
Earned value management
 
Webinar: Earned value management pure common sense
Webinar: Earned value management pure common senseWebinar: Earned value management pure common sense
Webinar: Earned value management pure common sense
 
Project Control Process
Project Control ProcessProject Control Process
Project Control Process
 

Último

A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communicationskarancommunications
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsP&CO
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfPaul Menig
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLSeo
 
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...rajveerescorts2022
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsMichael W. Hawkins
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Centuryrwgiffor
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...amitlee9823
 

Último (20)

A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdf
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael Hawkins
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 

A simple example of Earned Value Management (EVM) in action

  • 1. Simple example of EVM in action © 2014 Planisware
  • 2. The plan • Our team has been tasked with planting the trees on the plot of land behind our company’s new factory • The plan: – 30 batches of 20 trees (600 trees) – 5 batches per day (100 trees) – budgeted cost per tree 2.90$ (2.5$ per baby tree / 0.40$ for the slow release fertiliser) → total budget 1,740$ © 2014 Planisware 2
  • 3. After the first day… • 70 trees were planted (the team hit a patch with stones that had to be removed before the trees could be planted) • Total cost was 350 $ (we had to rent a special machine to help remove the stones which cost 147$ for the day) • Simple EVM calculation: – Earned Value = 70 trees planted  2.90$ = 203$ – Budgeted Cost = 100 trees planned per day  2.90$ = 290$ – Actual Cost = 70 trees planted  2.90$ + 147$ for the machine = 350$ © 2014 Planisware 3
  • 4. Visually… 0 50 100 150 200 250 300 350 400 Start 1st day Actual cost = 350$ Budgeted cost = 290$ Earned Value = 203$ © 2014 Planisware 4
  • 5. Regarding cost… 0 50 100 150 200 250 300 350 400 Start 1st day EV AC BC © 2014 Planisware 5 We are here
  • 6. Regarding cost… 0 50 100 150 200 250 300 350 400 Start 1st day EV AC BC © 2014 Planisware 6 We are here We should have been here
  • 7. Regarding cost… 0 50 100 150 200 250 300 350 400 Start 1st day EV AC BC © 2014 Planisware 7 Cost variance = EV – AC = 203$ – 350$ = -147$ < 0
  • 8. Regarding cost… 0 50 100 150 200 250 300 350 400 Start 1st day EV AC BC © 2014 Planisware 8 Cost variance = EV – AC We’re over budget, and have spent 203  350 = 58% more budget than anticipated (our cost performance index) = 203$ – 350$ = -147$ < 0
  • 9. Regarding schedule… 0 50 100 150 200 250 300 350 400 Start 1st day EV AC BC © 2014 Planisware 9 We are here
  • 10. Regarding schedule… 0 50 100 150 200 250 300 350 400 Start 1st day EV AC BC © 2014 Planisware 10 We are here Which is where we should have been then
  • 11. Regarding schedule… 0 50 100 150 200 250 300 350 400 Start 1st day EV AC BC © 2014 Planisware 11 Schedule variance in hours
  • 12. Regarding schedule… 0 50 100 150 200 250 300 350 400 Start 1st day EV AC BC © 2014 Planisware 12 Schedule variance in hours = 203$ – 290$ = = -87$ < 0 Schedule variance in dollars = EV – BC
  • 13. Regarding schedule… 0 50 100 150 200 250 300 350 400 Start 1st day EV AC BC © 2014 Planisware 13 Schedule variance in hours We’re late and have only performed 203/290 = 70% of the work planned (our schedule performance index) = 203$ – 290$ = = -87$ < 0 Schedule variance in dollars = EV – BC
  • 14. The consequences 0 500 1000 1500 2000 2500 3000 Start 1st 2nd 3rd 4th 5th 6th 7th 8th 9th © 2014 Planisware 14 Earned Value today Estimate at Completion EAC = 3,000$ Budget at Completion BAC = 1,740$ Extending the Actual Cost into the future gives us the end result if we do not modify the performance of the project
  • 15. The consequences 0 500 1000 1500 2000 2500 3000 Start 1st 2nd 3rd 4th 5th 6th 7th 8th 9th © 2014 Planisware 15 Earned Value today Estimate at Completion EAC = 3,000$ Budget at Completion BAC = 1,740$ Cost Overrun
  • 16. The consequences 0 500 1000 1500 2000 2500 3000 Start 1st 2nd 3rd 4th 5th 6th 7th 8th 9th © 2014 Planisware 16 Earned Value today Planned end date = 6 days Estimate at completion = 8.57 days Project Slip Estimate at Completion EAC = 3,000$ Budget at Completion BAC = 1,740$ Cost Overrun
  • 17. The consequences → If we continue at this rate, we will need: 1,740$  58% = 3,000 $ (cost estimate at completion) and 6 days  70% = 8.57 days (schedule estimate at completion) to finish the work. → If we want to finish on budget, we need to work at (planned remaining budget)  (actual remaining budget) (1,740 – 290)  (1740 – 350) = 104.3% of the originally planned performance → If we want to finish on time, we need to work at (actual remaining work)  (planned remaining work) (600 – 70)  (600 – 100) = 106% of the originally planned performance © 2014 Planisware 17
  • 18. In technical terms… In real life, the elements we calculated have slightly different names: • The Actual Cost is usually referred to as the Actual Cost of Works Performed (ACWP) • The Planned Cost = Budgeted Cost for Work Scheduled (BCWS) • The Earned Value = Budgeted Cost for Work Performed (BCWP) © 2014 Planisware 18
  • 19. Summary © 2014 Planisware 19 today time cost ACWP (Actual Cost of Work Performed) BCWS (Budgeted Cost of Work Scheduled) BCWP (Budgeted Cost of Work Performed) completion date Budget at Completion (BAC) Estimate at Completion (EAC) Schedule variance in $ SV = BCWS - BCWP Cost variance in $ CV = ACWP - BCWP Cost Overrun Project SlipSchedule variance in hours
  • 20. To learn more about EVM and tools to help manage it, visit our glossary: www.planisware.com/glossary/earned- value-management © 2014 Planisware 20