PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
0. Introduction
1. Plan Cost Management
2. Estimate Costs
3. Determine Budget
4. Control Costs
Lecture 07 : Project Cost Management (1/18)
Contents
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Lecture 07 : Project Cost Management (2/18)
Introduction
Direct vs. Indirect Cost
1. Direct Cost: Directly attributable to project work. ‫المشروع‬ ‫بأعمال‬ ‫مباشرة‬ ‫تتأثر‬
2. Indirect cost: Such as overhead, benefits, and costs incurred for more than
project like equipments. ‫المشاريع‬ ‫بين‬ ‫المشتركة‬ ‫التكاليف‬ ‫و‬ ‫االرباح‬ ‫و‬ ‫العامة‬ ‫النفقات‬ ‫مثل‬
Fixed vs. Variable Cost
1. Fixed cost: Costs that are not changed with production such as setup cost
and rental cost ‫االنتاج‬ ‫مع‬ ‫تتغير‬ ‫ال‬ ‫تكاليف‬
2. Variable cost: Costs that are changed with production such as material and
labors. ‫الخام‬ ‫المواد‬ ‫و‬ ‫العمالة‬ ‫تكاليف‬ ‫مثل‬ ‫االنتاج‬ ‫مع‬ ‫تتغير‬ ‫التي‬ ‫التكاليف‬
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Lecture 07 : Project Cost Management (3/18)
Introduction
Definitions :
 Life Cycle Cost : Looking at the whole life cost.
(Ex: Don’t pay less for lower quality then pay more for maintenance.
‫المنتج‬ ‫حياة‬ ‫دورة‬ ‫تكاليف‬:‫المنتج‬ ‫عمر‬ ‫مراحل‬ ‫جميع‬ ‫في‬ ‫التكاليف‬ ‫دراسة‬ ‫يتم‬
‫مثال‬:‫الصيانة‬ ‫و‬ ‫التشغيل‬ ‫مراحل‬ ‫في‬ ً‫ا‬‫كثير‬ ‫تدفع‬ ‫ثم‬ ‫ضعيفة‬ ‫جودة‬ ‫معايير‬ ‫باختيار‬ ‫بالتوفير‬ ‫تقوم‬ ‫ال‬
 Value Analysis (value engineering) : Finding a less costly way to perform
the same work. ‫القيمة‬ ‫تحليل‬:‫األعمال‬ ‫نفس‬ ‫النجاز‬ ‫تكلفة‬ ‫اقل‬ ‫طرق‬ ‫ايجاد‬ ‫عن‬ ‫عبارة‬
Lecture 07 : Project Cost Management (4/18)
1.Plan Cost Management (Planning)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
C o s t M a n a g e m e n t
7.1 Plan Cost Management
Inputs :
 Project Management Plan
 Project Charter
 Enterprise Environmental Factors
 Organizational Process Assets
Tools and Techniques :
 Expert Judgment
 Analytical Techniques
 Meetings
Outputs :
 Cost Management Plan
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Analytical Techniques
• Strategic options to fund the project
o Self-funding,
o Funding with equity, (Ex: Stocks) ‫التمويل‬‫خالل‬ ‫من‬‫باألسهم‬ ‫كما‬ ‫المشاركة‬
o Funding with debt (Ex: Bonds) ‫بالسندات‬ ‫كما‬ ‫االقتراض‬ ‫خالل‬ ‫من‬ ‫التمويل‬
• Project resources Finance
o Making,
o Purchasing,
o Renting (Short Term),
o Leasing (Long Term).
• Financial analysis techniques:
o payback period,
o Return on investment (value),
o Internal rate of return,
o Net present value.
Lecture 07 : Project Cost Management (5/18)
1.Plan Cost Management (Planning)
TT
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Cost Management Plan : ‫التكاليف‬ ‫إدارة‬ ‫خطة‬
• Establish the criteria for planning, structuring, estimating, budgeting, and
control project cost. ‫المشروع‬ ‫تكاليف‬ ‫مراقبة‬ ‫و‬ ‫موازنة‬ ‫و‬ ‫تقدير‬ ‫و‬ ‫هيكلة‬ ‫و‬ ‫تخطيط‬ ‫معايير‬ ‫تأسيس‬
• Cost management plan may includes: ‫على‬ ‫الخطة‬ ‫تحتوي‬ ‫ان‬ ‫يمكن‬
1. Units of measure ( ex: staff hours) ‫القياس‬ ‫وحدات‬
2. Level of Precision (rounding up or down, ex: $125.3  $125)
3. Level of Accuracy (ex: ± 5%)
4. Organizational Links (with accounting systems)
5. Control thresholds ( level at which an action needs to be taken)
6. Rules of performance measurement (Procedures)
7. Reporting formats
Lecture 07 : Project Cost Management (6/18)
1.Plan Cost Management (Planning)
O
Lecture 07 : Project Cost Management (7/18)
2.Estimate Costs (Planning)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
C o s t M a n a g e m e n t
7 . 2 E s t i m a t e C o s t s
Inputs :
 Cost Management Plan ■ Scope Baseline
 Human Resource Management Plan ■ Project Schedule
 Risk Register ■ Enterprise Environmental Factors
 Organizational Process Assets
Tools and Techniques :
 Expert Judgment ■ Analogous Estimating
 Parametric Estimating ■ Bottom-Up Estimating
 Three-Point Estimates ■ Reserve Analysis
 Cost of Quality ■ Project Management Software
 Group Decision-Making Techniques ■ Vendor Bid Analysis
Outputs :
 Activity Cost Estimates
 Basis of Estimates
 Project Document Updates
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Lecture 07 : Project Cost Management (8/18)
2.Estimate Costs (Planning)
Cost of Quality:
• All costs incurred in preventing nonconformance, apprising, or rework. This
will be illustrated later in Quality Management.
Vendor Bid Analysis:
• Analysis of cost estimate based on responsive bids from qualified vendors.
Cost Estimates:
Costs are estimated for all resources such as:
• Direct Cost (Labor, materials, equipment, services, facilities, IT)
• Cost of financing (interest), inflation allowance, exchange rates.
• Contingency reserve.
• Insurance fees.
• Taxes
• Overhead (Site overhead and main office)
TT
O
TT
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Lecture 07 : Project Cost Management (9/18)
2.Estimate Costs (Planning)
Basis of Estimates :
• Supporting documentation which provides understanding of how the cost
estimate was derived.
• This may includes:
• Assumptions.
• Constraints.
• Ranges of accuracy (ex:± 5%).
• Confidence level of the final cost estimate.
O
Lecture 07 : Project Cost Management (10/18)
3.Determine Budget (Planning)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
C o s t M a n a g e m e n t
7 . 3 D e t e r m i n e B u d g e t
Inputs :
 Cost Management Plan ■ Scope Baseline
 Activity Cost Estimates ■ Basis of Estimates
 Project Schedule ■ Resource Calendars
 Risk Register ■ Agreements
 Organizational Process Assets
Tools and Techniques :
 Cost Aggregation
 Reserve Analysis
 Expert Judgment
 Historical Relationships
 Funding Limit Reconciliation ‫توفيق‬
Outputs :
 Cost Baseline
 Project Funding Requirements
 Project Document Updates
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Lecture 07 : Project Cost Management (11/18)
3.Determine Budget (Planning)
Cost Aggregation :
• Cost Estimates are aggregated within activities and rolled up to work
package then rolled up to control accounts then rolled up to entire project.
‫بالكامل‬ ‫المشروع‬ ‫الى‬ ‫ثم‬ ‫التحكم‬ ‫حسابات‬ ‫الى‬ ‫ثم‬ ‫العمل‬ ‫حزم‬ ‫الى‬ ‫األنشطة‬ ‫مستوى‬ ‫من‬ ‫التكاليف‬ ‫تجميع‬
Reserve Analysis :
1. Contingency Reserve : Allowances for
unplanned changes result from identified risks.
2. Management Reserve : Budgets reserved for
unplanned changes to scope and cost.
Cost estimates
Contingency Reserve
Management Reserve
CostBudget
CostBaseline
TT
TT
Historical Relationships:
• Historical Relationships involve the use of project characteristics
(parameters) to develop mathematical models to predict total project costs.
• This results in parametric estimates or analogous estimates.
TT
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Lecture 07 : Project Cost Management (12/18)
3.Determine Budget (Planning)
Funding Limit Reconciliation : ‫التمويل‬ ‫لقيود‬ ‫طبقا‬ ‫المعالجة‬
• Sometimes funds are not available when needed and you have to
reschedule the activities. ‫االنشطة‬ ‫جدولة‬ ‫اعادة‬ ‫الي‬ ‫يضطرك‬ ‫مما‬ ‫تمويل‬ ‫يوجد‬ ‫ال‬ ‫احيانا‬
• Expenditures should be reconciled with any funding limits
‫التمويل‬ ‫على‬ ‫موجودة‬ ‫قيود‬ ‫ألي‬ ‫طبقا‬ ‫االنفاق‬ ‫خطة‬ ‫توفيق‬ ‫و‬ ‫معالجة‬ ‫من‬ ‫بد‬ ‫ال‬
• Example : Funds for the project will be available on two batches :
$50 millions today and $40 millions in the beginning of the next year.
Cost Baseline : ‫التكلفة‬ ‫أساس‬ ‫خط‬
• The planned costs over project time. It’s used to
control cost performance in the project. ‫التكاليف‬
‫المخطط‬‫انفاقها‬‫عبر‬‫زمن‬‫المشروع‬
Project Funding Requirements : ‫المشروع‬ ‫تمويل‬ ‫متطلبات‬
• It can be derived from cost baseline. Funding
often occurs in incremental amounts.
‫دفعات‬ ‫على‬ ‫تكون‬ ‫ما‬ ‫غالبا‬ ‫و‬ ‫التكلفة‬ ‫أساس‬ ‫خط‬ ‫من‬ ‫استنتاجها‬ ‫يمكن‬
TT
O
O
Lecture 07 : Project Cost Management (13/18)
4.Control Costs (M/C)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
C o s t M a n a g e m e n t
7 . 4 C o n t r o l C o s t s
Inputs :
 Project Management Plan
 Project Funding Requirements
 Work Performance Information Data
 Organizational Process Assets
Tools and Techniques :
 Earned Value Management
 Forecasting
 To Complete Performance Index (TCPI)
 Performance Reviews
 Project Management Software
 Reserve Analysis
Outputs :
 Work Performance Information ■ Cost Forecasts
 Project Management Plan Updates ■ Change Requests
 Organizational Process Assets Updates ■ Project Document Updates
Lecture 07 : Project Cost Management (14/18)
4.Control Costs (M/C)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Earned Value Management : ‫المكتسبة‬ ‫القيمة‬ ‫ادارة‬
• Planned Value (PV) = Budgeted cost for work scheduled (BCWS)
‫محددة‬ ‫زمنية‬ ‫نقطة‬ ‫عند‬ ‫تنفيذها‬ ‫المخطط‬ ‫األعمال‬ ‫قيمة‬
• Earned value (EV) = Budgeted cost for work performed (BCWP)
‫محددة‬ ‫زمنية‬ ‫نقطة‬ ‫عند‬ ‫فعلية‬ ‫اعمال‬ ‫تنفيذ‬ ‫من‬ ‫المكتسبة‬ ‫القيمة‬
• Actual Cost (AC) = Actual cost for work performed (ACWP)
‫تنفيذها‬ ‫تم‬ ‫التي‬ ‫لالعمال‬ ‫الفعلية‬ ‫التكاليف‬
• Schedule Variance (SV) = EV – PV ‫انحراف‬(‫تباين‬)‫الزمني‬ ‫الجدول‬
• Cost Variance (CV) = EV – AC ‫التكلفة‬ ‫انحراف‬
• Schedule Performance Index (SPI) = EV / PV ‫الزمني‬ ‫الجدول‬ ‫أداء‬ ‫مؤشر‬
• Cost Performance Index (CPI) = EV / AC ‫التكلفة‬ ‫أداء‬ ‫مؤشر‬
Behind Schedule ‫متأخر‬‫الجدول‬ ‫عن‬SV < 0
On Schedule ‫الجدول‬ ‫مع‬SV = 0
Ahead of Schedule ‫الجدول‬ ‫سابق‬SV > 0
Over Budget ‫الميزانية‬ ‫تعدى‬CV < 0
On Budget ‫الميزانية‬ ‫مع‬CV = 0
Under Budget ‫الميزانية‬ ‫نطاق‬ ‫داخل‬CV > 0
Behind ScheduleSPI < 1
On ScheduleSPI = 1
Ahead of ScheduleSPI > 1
Over Budget ‫الميزانية‬ ‫تعدى‬CPI < 1
On Budget ‫الميزانية‬ ‫مع‬CPI = 1
Under Budget ‫الميزانية‬ ‫نطاق‬ ‫داخل‬CPI > 1
TT
Lecture 07 : Project Cost Management (15/18)
4.Control Costs (M/C)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Example :
PV (BCWS) =1000x120 = 120,000.00
EV (BCWP) =1000x130 = 130,000.00
AC (ACWP) =1200*130 = 156,000.00
Variance :
SV = EV - PV = 130'000 - 120'000 = 10'000 (Ahead of Schedule)
CV = EV - AC = 130'000 - 156'000 = -26'000 (Over Budget)
Performance Index
SPI = EV / PV = 130'000 / 120'000 = 1.083 (Ahead of Schedule)
CVI = EV / AC = 130'000 / 156'000 = 0.833 (Over Budget)
Cost/Unit Quantity
Budget 1000 120
Actual 1200 130
Lecture 07 : Project Cost Management (16/18)
4.Control Costs (M/C)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Time
Cost
Lecture 07 : Project Cost Management (17/18)
4.Control Costs (M/C)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Forecasting : ‫معايير‬ ‫خالل‬ ‫من‬ ‫التوقع‬
• Estimate at Completion (EAC) = Actual Cost+ Estimate to Complete (ETC).
‫المشروع‬ ‫نهاية‬ ‫في‬ ‫المتوقعة‬ ‫القيمة‬=‫اآلن‬ ‫حتى‬ ‫الفعلية‬ ‫القيمة‬+‫المشروع‬ ‫النهاء‬ ‫المتوقع‬
• There are various methods to calculate the Estimate to Complete (ETC)
‫المشروع‬ ‫النهاء‬ ‫المتوقعة‬ ‫القيمة‬ ‫لحساب‬ ‫طرق‬ ‫عدة‬ ‫يوجد‬
1- At the budgeted rate :
EAC = AC + (BAC – EV)
2- Considering CPI :
EAC = AC + [ (BAC – EV) / CPI ] = AC + BAC/CPI – EV/CPI
= AC + BAC/CPI – AC = BAC / CPI
3- Considering CPI and SPI :
EAC = AC + [ (BAC – EV) / (CPI x SPI) ]
TT
Lecture 07 : Project Cost Management (18/18)
4.Control Costs (M/C)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
To Complete Performance Index (TCPI) : ‫المشروع‬ ‫إلكمال‬ ‫المطلوبة‬ ‫للقيمة‬ ‫اآلداء‬ ‫مؤشر‬
• It’s the cost performance that must be achieved on the remaining work to
meet a specified goal like BAC or EAC ‫القادمة‬ ‫الفترة‬ ‫في‬ ‫تحقيقه‬ ‫المطلوب‬ ‫المالي‬ ‫االداء‬
• It represents the ratio between remaining works and remaining funds.
‫المتبقي‬ ‫التمويل‬ ‫قيمة‬ ‫و‬ ‫المتبقية‬ ‫االعمال‬ ‫قيمة‬ ‫بين‬ ‫النسبة‬ ‫تمثل‬
• TCPI = (BAC-EV) / (BAC – AC)
Or TCPI = (BAC-EV) / (EAC – AC) “If the BAC is no longer valid”
• Ex :
BAC = 500’000.00 , EV = 200’000.00, AC= 250’000.00
TCPI = (300’000.00 ) / (250’000.00) = 1.2
TT
Performance Reviews :
• Variance at completion (VAC) = BAC – EAC
• Trend Analysis: Graphical analysis examines project performance over time.
• EVM
TT

Mais conteúdo relacionado

Mais procurados

Chapter23 projectreviewandadministrativeaspects
Chapter23 projectreviewandadministrativeaspectsChapter23 projectreviewandadministrativeaspects
Chapter23 projectreviewandadministrativeaspectsAKSHAYA0000
 
Construction project management
Construction project managementConstruction project management
Construction project managementsaif hasan
 
PMP 1600 Questions by TechFAQ360
PMP 1600 Questions by TechFAQ360PMP 1600 Questions by TechFAQ360
PMP 1600 Questions by TechFAQ360Artonline Home
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time AnalysisFarhan Moosa
 
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessPlanning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessAlberto Sanchez
 
Cmgt 410 ver.13 entire class
Cmgt 410 ver.13 entire classCmgt 410 ver.13 entire class
Cmgt 410 ver.13 entire classLaynevine
 
Project Management and Organization
Project Management and OrganizationProject Management and Organization
Project Management and OrganizationAndriani Nikodemou
 
Project evaluation and implementation notes and questions
Project evaluation and implementation   notes and questionsProject evaluation and implementation   notes and questions
Project evaluation and implementation notes and questionsAnirban Chakraborty
 
Project Controls Processes
Project Controls ProcessesProject Controls Processes
Project Controls ProcessesPMA Consultants
 
Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsSHAZEBALIKHAN1
 

Mais procurados (18)

Project Mangement
Project MangementProject Mangement
Project Mangement
 
Chapter23 projectreviewandadministrativeaspects
Chapter23 projectreviewandadministrativeaspectsChapter23 projectreviewandadministrativeaspects
Chapter23 projectreviewandadministrativeaspects
 
04 project cost managment
04 project cost managment04 project cost managment
04 project cost managment
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
PMP 1600 Questions by TechFAQ360
PMP 1600 Questions by TechFAQ360PMP 1600 Questions by TechFAQ360
PMP 1600 Questions by TechFAQ360
 
50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
 
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessPlanning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning Process
 
Cmgt 410 ver.13 entire class
Cmgt 410 ver.13 entire classCmgt 410 ver.13 entire class
Cmgt 410 ver.13 entire class
 
Scope creep - cylfe campain
Scope creep - cylfe campainScope creep - cylfe campain
Scope creep - cylfe campain
 
Project Management and Organization
Project Management and OrganizationProject Management and Organization
Project Management and Organization
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
 
Project evaluation and implementation notes and questions
Project evaluation and implementation   notes and questionsProject evaluation and implementation   notes and questions
Project evaluation and implementation notes and questions
 
Self test engine PSP-PMI-SP
Self test engine PSP-PMI-SPSelf test engine PSP-PMI-SP
Self test engine PSP-PMI-SP
 
Project Controls Processes
Project Controls ProcessesProject Controls Processes
Project Controls Processes
 
PMP_Economic Selection Criteria
PMP_Economic Selection CriteriaPMP_Economic Selection Criteria
PMP_Economic Selection Criteria
 
Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management Terms
 
I07 Simulation
I07 SimulationI07 Simulation
I07 Simulation
 

Semelhante a PMP Preparation - 07 Cost Management

7 cost managmenet
7 cost managmenet7 cost managmenet
7 cost managmenetAla Ibrahim
 
Pm deep dive cost management
Pm deep dive   cost managementPm deep dive   cost management
Pm deep dive cost managementNiraj Agarwal
 
ادارة تكلفة المشروع
ادارة تكلفة المشروع ادارة تكلفة المشروع
ادارة تكلفة المشروع Mohamed Dahi
 
Software Project Cost Management and estimation
Software Project Cost Management and estimationSoftware Project Cost Management and estimation
Software Project Cost Management and estimationssuser9d62d6
 
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
4. PAE AcFn621Ch-4a Project Alaysis and Selection.pptProfDrAnbalaganChinn
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1reddvise
 
L03 integration management
L03 integration managementL03 integration management
L03 integration managementAsa Chan
 
L06 cost management
L06 cost managementL06 cost management
L06 cost managementAsa Chan
 
Preparing cost estimation
Preparing cost estimationPreparing cost estimation
Preparing cost estimationSomashekar S.M
 
1 ch 1 Project CM.pptx ggggggggggggggggg
1 ch 1 Project CM.pptx ggggggggggggggggg1 ch 1 Project CM.pptx ggggggggggggggggg
1 ch 1 Project CM.pptx gggggggggggggggggadabotor7
 
Project Management C8 -cost_estimation_and_budgeting
Project Management C8  -cost_estimation_and_budgetingProject Management C8  -cost_estimation_and_budgeting
Project Management C8 -cost_estimation_and_budgetingIzah Asmadi
 
Tracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value ManagementTracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value ManagementIRJET Journal
 
8. implementation (2) cost management
8. implementation (2)   cost management8. implementation (2)   cost management
8. implementation (2) cost managementDania Abdel-aziz
 
Ch 2 project planning and control
Ch 2 project planning and controlCh 2 project planning and control
Ch 2 project planning and controlJanak Singh Chauhan
 
Vanessa.jeff
Vanessa.jeffVanessa.jeff
Vanessa.jeffNASAPMC
 

Semelhante a PMP Preparation - 07 Cost Management (20)

PMP Session 3
PMP Session 3PMP Session 3
PMP Session 3
 
7 cost managmenet
7 cost managmenet7 cost managmenet
7 cost managmenet
 
Pm deep dive cost management
Pm deep dive   cost managementPm deep dive   cost management
Pm deep dive cost management
 
ادارة تكلفة المشروع
ادارة تكلفة المشروع ادارة تكلفة المشروع
ادارة تكلفة المشروع
 
Software Project Cost Management and estimation
Software Project Cost Management and estimationSoftware Project Cost Management and estimation
Software Project Cost Management and estimation
 
Project cost management
Project cost management Project cost management
Project cost management
 
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
 
L03 integration management
L03 integration managementL03 integration management
L03 integration management
 
L06 cost management
L06 cost managementL06 cost management
L06 cost management
 
Preparing cost estimation
Preparing cost estimationPreparing cost estimation
Preparing cost estimation
 
1 ch 1 Project CM.pptx ggggggggggggggggg
1 ch 1 Project CM.pptx ggggggggggggggggg1 ch 1 Project CM.pptx ggggggggggggggggg
1 ch 1 Project CM.pptx ggggggggggggggggg
 
Project Management C8 -cost_estimation_and_budgeting
Project Management C8  -cost_estimation_and_budgetingProject Management C8  -cost_estimation_and_budgeting
Project Management C8 -cost_estimation_and_budgeting
 
Pm assignment
Pm assignmentPm assignment
Pm assignment
 
Tracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value ManagementTracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value Management
 
8. implementation (2) cost management
8. implementation (2)   cost management8. implementation (2)   cost management
8. implementation (2) cost management
 
Ch 2 project planning and control
Ch 2 project planning and controlCh 2 project planning and control
Ch 2 project planning and control
 
Session 9 4th edition PMP
Session 9 4th edition PMPSession 9 4th edition PMP
Session 9 4th edition PMP
 
Vanessa.jeff
Vanessa.jeffVanessa.jeff
Vanessa.jeff
 
Chapter 2.ppt
Chapter 2.pptChapter 2.ppt
Chapter 2.ppt
 

Mais de Mohamed ElSaadany, PMP, CCP, PMI-RMP, SCE-PE (11)

مكتب إدارة المشاريع. الفرص والتحديات
مكتب إدارة المشاريع. الفرص والتحدياتمكتب إدارة المشاريع. الفرص والتحديات
مكتب إدارة المشاريع. الفرص والتحديات
 
PMP Preparation - 10 Communication Management
PMP Preparation - 10 Communication ManagementPMP Preparation - 10 Communication Management
PMP Preparation - 10 Communication Management
 
PMP Preparation - 11 Risk Management
PMP Preparation - 11 Risk ManagementPMP Preparation - 11 Risk Management
PMP Preparation - 11 Risk Management
 
PMP Preparation - 09 Human Resource Management
PMP Preparation - 09 Human Resource ManagementPMP Preparation - 09 Human Resource Management
PMP Preparation - 09 Human Resource Management
 
PMP Preparation - 08 Quality Management
PMP Preparation - 08 Quality ManagementPMP Preparation - 08 Quality Management
PMP Preparation - 08 Quality Management
 
PMP Preparation - 06 Time Management
PMP Preparation - 06 Time ManagementPMP Preparation - 06 Time Management
PMP Preparation - 06 Time Management
 
PMP Preparation - 05 Scope Management
PMP Preparation - 05 Scope ManagementPMP Preparation - 05 Scope Management
PMP Preparation - 05 Scope Management
 
PMP Preparation - 02 FAQ
PMP Preparation - 02 FAQPMP Preparation - 02 FAQ
PMP Preparation - 02 FAQ
 
PMP Preparation - 03 Framework
PMP Preparation - 03 FrameworkPMP Preparation - 03 Framework
PMP Preparation - 03 Framework
 
PMP Preparation - 01 Get Ready
PMP Preparation - 01 Get ReadyPMP Preparation - 01 Get Ready
PMP Preparation - 01 Get Ready
 
Project Management Applications Using Google Documents
Project Management Applications Using Google DocumentsProject Management Applications Using Google Documents
Project Management Applications Using Google Documents
 

Último

Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfagholdier
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...PsychoTech Services
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfAyushMahapatra5
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...christianmathematics
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhikauryashika82
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 

Último (20)

Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdf
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
Advance Mobile Application Development class 07
Advance Mobile Application Development class 07Advance Mobile Application Development class 07
Advance Mobile Application Development class 07
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 

PMP Preparation - 07 Cost Management

  • 1. PMP Lectures Prepared By: Eng. Mohamed ElSaadany 0. Introduction 1. Plan Cost Management 2. Estimate Costs 3. Determine Budget 4. Control Costs Lecture 07 : Project Cost Management (1/18) Contents
  • 2. PMP Lectures Prepared By: Eng. Mohamed ElSaadany Lecture 07 : Project Cost Management (2/18) Introduction Direct vs. Indirect Cost 1. Direct Cost: Directly attributable to project work. ‫المشروع‬ ‫بأعمال‬ ‫مباشرة‬ ‫تتأثر‬ 2. Indirect cost: Such as overhead, benefits, and costs incurred for more than project like equipments. ‫المشاريع‬ ‫بين‬ ‫المشتركة‬ ‫التكاليف‬ ‫و‬ ‫االرباح‬ ‫و‬ ‫العامة‬ ‫النفقات‬ ‫مثل‬ Fixed vs. Variable Cost 1. Fixed cost: Costs that are not changed with production such as setup cost and rental cost ‫االنتاج‬ ‫مع‬ ‫تتغير‬ ‫ال‬ ‫تكاليف‬ 2. Variable cost: Costs that are changed with production such as material and labors. ‫الخام‬ ‫المواد‬ ‫و‬ ‫العمالة‬ ‫تكاليف‬ ‫مثل‬ ‫االنتاج‬ ‫مع‬ ‫تتغير‬ ‫التي‬ ‫التكاليف‬
  • 3. PMP Lectures Prepared By: Eng. Mohamed ElSaadany Lecture 07 : Project Cost Management (3/18) Introduction Definitions :  Life Cycle Cost : Looking at the whole life cost. (Ex: Don’t pay less for lower quality then pay more for maintenance. ‫المنتج‬ ‫حياة‬ ‫دورة‬ ‫تكاليف‬:‫المنتج‬ ‫عمر‬ ‫مراحل‬ ‫جميع‬ ‫في‬ ‫التكاليف‬ ‫دراسة‬ ‫يتم‬ ‫مثال‬:‫الصيانة‬ ‫و‬ ‫التشغيل‬ ‫مراحل‬ ‫في‬ ً‫ا‬‫كثير‬ ‫تدفع‬ ‫ثم‬ ‫ضعيفة‬ ‫جودة‬ ‫معايير‬ ‫باختيار‬ ‫بالتوفير‬ ‫تقوم‬ ‫ال‬  Value Analysis (value engineering) : Finding a less costly way to perform the same work. ‫القيمة‬ ‫تحليل‬:‫األعمال‬ ‫نفس‬ ‫النجاز‬ ‫تكلفة‬ ‫اقل‬ ‫طرق‬ ‫ايجاد‬ ‫عن‬ ‫عبارة‬
  • 4. Lecture 07 : Project Cost Management (4/18) 1.Plan Cost Management (Planning) PMP Lectures Prepared By: Eng. Mohamed ElSaadany C o s t M a n a g e m e n t 7.1 Plan Cost Management Inputs :  Project Management Plan  Project Charter  Enterprise Environmental Factors  Organizational Process Assets Tools and Techniques :  Expert Judgment  Analytical Techniques  Meetings Outputs :  Cost Management Plan
  • 5. PMP Lectures Prepared By: Eng. Mohamed ElSaadany Analytical Techniques • Strategic options to fund the project o Self-funding, o Funding with equity, (Ex: Stocks) ‫التمويل‬‫خالل‬ ‫من‬‫باألسهم‬ ‫كما‬ ‫المشاركة‬ o Funding with debt (Ex: Bonds) ‫بالسندات‬ ‫كما‬ ‫االقتراض‬ ‫خالل‬ ‫من‬ ‫التمويل‬ • Project resources Finance o Making, o Purchasing, o Renting (Short Term), o Leasing (Long Term). • Financial analysis techniques: o payback period, o Return on investment (value), o Internal rate of return, o Net present value. Lecture 07 : Project Cost Management (5/18) 1.Plan Cost Management (Planning) TT
  • 6. PMP Lectures Prepared By: Eng. Mohamed ElSaadany Cost Management Plan : ‫التكاليف‬ ‫إدارة‬ ‫خطة‬ • Establish the criteria for planning, structuring, estimating, budgeting, and control project cost. ‫المشروع‬ ‫تكاليف‬ ‫مراقبة‬ ‫و‬ ‫موازنة‬ ‫و‬ ‫تقدير‬ ‫و‬ ‫هيكلة‬ ‫و‬ ‫تخطيط‬ ‫معايير‬ ‫تأسيس‬ • Cost management plan may includes: ‫على‬ ‫الخطة‬ ‫تحتوي‬ ‫ان‬ ‫يمكن‬ 1. Units of measure ( ex: staff hours) ‫القياس‬ ‫وحدات‬ 2. Level of Precision (rounding up or down, ex: $125.3  $125) 3. Level of Accuracy (ex: ± 5%) 4. Organizational Links (with accounting systems) 5. Control thresholds ( level at which an action needs to be taken) 6. Rules of performance measurement (Procedures) 7. Reporting formats Lecture 07 : Project Cost Management (6/18) 1.Plan Cost Management (Planning) O
  • 7. Lecture 07 : Project Cost Management (7/18) 2.Estimate Costs (Planning) PMP Lectures Prepared By: Eng. Mohamed ElSaadany C o s t M a n a g e m e n t 7 . 2 E s t i m a t e C o s t s Inputs :  Cost Management Plan ■ Scope Baseline  Human Resource Management Plan ■ Project Schedule  Risk Register ■ Enterprise Environmental Factors  Organizational Process Assets Tools and Techniques :  Expert Judgment ■ Analogous Estimating  Parametric Estimating ■ Bottom-Up Estimating  Three-Point Estimates ■ Reserve Analysis  Cost of Quality ■ Project Management Software  Group Decision-Making Techniques ■ Vendor Bid Analysis Outputs :  Activity Cost Estimates  Basis of Estimates  Project Document Updates
  • 8. PMP Lectures Prepared By: Eng. Mohamed ElSaadany Lecture 07 : Project Cost Management (8/18) 2.Estimate Costs (Planning) Cost of Quality: • All costs incurred in preventing nonconformance, apprising, or rework. This will be illustrated later in Quality Management. Vendor Bid Analysis: • Analysis of cost estimate based on responsive bids from qualified vendors. Cost Estimates: Costs are estimated for all resources such as: • Direct Cost (Labor, materials, equipment, services, facilities, IT) • Cost of financing (interest), inflation allowance, exchange rates. • Contingency reserve. • Insurance fees. • Taxes • Overhead (Site overhead and main office) TT O TT
  • 9. PMP Lectures Prepared By: Eng. Mohamed ElSaadany Lecture 07 : Project Cost Management (9/18) 2.Estimate Costs (Planning) Basis of Estimates : • Supporting documentation which provides understanding of how the cost estimate was derived. • This may includes: • Assumptions. • Constraints. • Ranges of accuracy (ex:± 5%). • Confidence level of the final cost estimate. O
  • 10. Lecture 07 : Project Cost Management (10/18) 3.Determine Budget (Planning) PMP Lectures Prepared By: Eng. Mohamed ElSaadany C o s t M a n a g e m e n t 7 . 3 D e t e r m i n e B u d g e t Inputs :  Cost Management Plan ■ Scope Baseline  Activity Cost Estimates ■ Basis of Estimates  Project Schedule ■ Resource Calendars  Risk Register ■ Agreements  Organizational Process Assets Tools and Techniques :  Cost Aggregation  Reserve Analysis  Expert Judgment  Historical Relationships  Funding Limit Reconciliation ‫توفيق‬ Outputs :  Cost Baseline  Project Funding Requirements  Project Document Updates
  • 11. PMP Lectures Prepared By: Eng. Mohamed ElSaadany Lecture 07 : Project Cost Management (11/18) 3.Determine Budget (Planning) Cost Aggregation : • Cost Estimates are aggregated within activities and rolled up to work package then rolled up to control accounts then rolled up to entire project. ‫بالكامل‬ ‫المشروع‬ ‫الى‬ ‫ثم‬ ‫التحكم‬ ‫حسابات‬ ‫الى‬ ‫ثم‬ ‫العمل‬ ‫حزم‬ ‫الى‬ ‫األنشطة‬ ‫مستوى‬ ‫من‬ ‫التكاليف‬ ‫تجميع‬ Reserve Analysis : 1. Contingency Reserve : Allowances for unplanned changes result from identified risks. 2. Management Reserve : Budgets reserved for unplanned changes to scope and cost. Cost estimates Contingency Reserve Management Reserve CostBudget CostBaseline TT TT Historical Relationships: • Historical Relationships involve the use of project characteristics (parameters) to develop mathematical models to predict total project costs. • This results in parametric estimates or analogous estimates. TT
  • 12. PMP Lectures Prepared By: Eng. Mohamed ElSaadany Lecture 07 : Project Cost Management (12/18) 3.Determine Budget (Planning) Funding Limit Reconciliation : ‫التمويل‬ ‫لقيود‬ ‫طبقا‬ ‫المعالجة‬ • Sometimes funds are not available when needed and you have to reschedule the activities. ‫االنشطة‬ ‫جدولة‬ ‫اعادة‬ ‫الي‬ ‫يضطرك‬ ‫مما‬ ‫تمويل‬ ‫يوجد‬ ‫ال‬ ‫احيانا‬ • Expenditures should be reconciled with any funding limits ‫التمويل‬ ‫على‬ ‫موجودة‬ ‫قيود‬ ‫ألي‬ ‫طبقا‬ ‫االنفاق‬ ‫خطة‬ ‫توفيق‬ ‫و‬ ‫معالجة‬ ‫من‬ ‫بد‬ ‫ال‬ • Example : Funds for the project will be available on two batches : $50 millions today and $40 millions in the beginning of the next year. Cost Baseline : ‫التكلفة‬ ‫أساس‬ ‫خط‬ • The planned costs over project time. It’s used to control cost performance in the project. ‫التكاليف‬ ‫المخطط‬‫انفاقها‬‫عبر‬‫زمن‬‫المشروع‬ Project Funding Requirements : ‫المشروع‬ ‫تمويل‬ ‫متطلبات‬ • It can be derived from cost baseline. Funding often occurs in incremental amounts. ‫دفعات‬ ‫على‬ ‫تكون‬ ‫ما‬ ‫غالبا‬ ‫و‬ ‫التكلفة‬ ‫أساس‬ ‫خط‬ ‫من‬ ‫استنتاجها‬ ‫يمكن‬ TT O O
  • 13. Lecture 07 : Project Cost Management (13/18) 4.Control Costs (M/C) PMP Lectures Prepared By: Eng. Mohamed ElSaadany C o s t M a n a g e m e n t 7 . 4 C o n t r o l C o s t s Inputs :  Project Management Plan  Project Funding Requirements  Work Performance Information Data  Organizational Process Assets Tools and Techniques :  Earned Value Management  Forecasting  To Complete Performance Index (TCPI)  Performance Reviews  Project Management Software  Reserve Analysis Outputs :  Work Performance Information ■ Cost Forecasts  Project Management Plan Updates ■ Change Requests  Organizational Process Assets Updates ■ Project Document Updates
  • 14. Lecture 07 : Project Cost Management (14/18) 4.Control Costs (M/C) PMP Lectures Prepared By: Eng. Mohamed ElSaadany Earned Value Management : ‫المكتسبة‬ ‫القيمة‬ ‫ادارة‬ • Planned Value (PV) = Budgeted cost for work scheduled (BCWS) ‫محددة‬ ‫زمنية‬ ‫نقطة‬ ‫عند‬ ‫تنفيذها‬ ‫المخطط‬ ‫األعمال‬ ‫قيمة‬ • Earned value (EV) = Budgeted cost for work performed (BCWP) ‫محددة‬ ‫زمنية‬ ‫نقطة‬ ‫عند‬ ‫فعلية‬ ‫اعمال‬ ‫تنفيذ‬ ‫من‬ ‫المكتسبة‬ ‫القيمة‬ • Actual Cost (AC) = Actual cost for work performed (ACWP) ‫تنفيذها‬ ‫تم‬ ‫التي‬ ‫لالعمال‬ ‫الفعلية‬ ‫التكاليف‬ • Schedule Variance (SV) = EV – PV ‫انحراف‬(‫تباين‬)‫الزمني‬ ‫الجدول‬ • Cost Variance (CV) = EV – AC ‫التكلفة‬ ‫انحراف‬ • Schedule Performance Index (SPI) = EV / PV ‫الزمني‬ ‫الجدول‬ ‫أداء‬ ‫مؤشر‬ • Cost Performance Index (CPI) = EV / AC ‫التكلفة‬ ‫أداء‬ ‫مؤشر‬ Behind Schedule ‫متأخر‬‫الجدول‬ ‫عن‬SV < 0 On Schedule ‫الجدول‬ ‫مع‬SV = 0 Ahead of Schedule ‫الجدول‬ ‫سابق‬SV > 0 Over Budget ‫الميزانية‬ ‫تعدى‬CV < 0 On Budget ‫الميزانية‬ ‫مع‬CV = 0 Under Budget ‫الميزانية‬ ‫نطاق‬ ‫داخل‬CV > 0 Behind ScheduleSPI < 1 On ScheduleSPI = 1 Ahead of ScheduleSPI > 1 Over Budget ‫الميزانية‬ ‫تعدى‬CPI < 1 On Budget ‫الميزانية‬ ‫مع‬CPI = 1 Under Budget ‫الميزانية‬ ‫نطاق‬ ‫داخل‬CPI > 1 TT
  • 15. Lecture 07 : Project Cost Management (15/18) 4.Control Costs (M/C) PMP Lectures Prepared By: Eng. Mohamed ElSaadany Example : PV (BCWS) =1000x120 = 120,000.00 EV (BCWP) =1000x130 = 130,000.00 AC (ACWP) =1200*130 = 156,000.00 Variance : SV = EV - PV = 130'000 - 120'000 = 10'000 (Ahead of Schedule) CV = EV - AC = 130'000 - 156'000 = -26'000 (Over Budget) Performance Index SPI = EV / PV = 130'000 / 120'000 = 1.083 (Ahead of Schedule) CVI = EV / AC = 130'000 / 156'000 = 0.833 (Over Budget) Cost/Unit Quantity Budget 1000 120 Actual 1200 130
  • 16. Lecture 07 : Project Cost Management (16/18) 4.Control Costs (M/C) PMP Lectures Prepared By: Eng. Mohamed ElSaadany Time Cost
  • 17. Lecture 07 : Project Cost Management (17/18) 4.Control Costs (M/C) PMP Lectures Prepared By: Eng. Mohamed ElSaadany Forecasting : ‫معايير‬ ‫خالل‬ ‫من‬ ‫التوقع‬ • Estimate at Completion (EAC) = Actual Cost+ Estimate to Complete (ETC). ‫المشروع‬ ‫نهاية‬ ‫في‬ ‫المتوقعة‬ ‫القيمة‬=‫اآلن‬ ‫حتى‬ ‫الفعلية‬ ‫القيمة‬+‫المشروع‬ ‫النهاء‬ ‫المتوقع‬ • There are various methods to calculate the Estimate to Complete (ETC) ‫المشروع‬ ‫النهاء‬ ‫المتوقعة‬ ‫القيمة‬ ‫لحساب‬ ‫طرق‬ ‫عدة‬ ‫يوجد‬ 1- At the budgeted rate : EAC = AC + (BAC – EV) 2- Considering CPI : EAC = AC + [ (BAC – EV) / CPI ] = AC + BAC/CPI – EV/CPI = AC + BAC/CPI – AC = BAC / CPI 3- Considering CPI and SPI : EAC = AC + [ (BAC – EV) / (CPI x SPI) ] TT
  • 18. Lecture 07 : Project Cost Management (18/18) 4.Control Costs (M/C) PMP Lectures Prepared By: Eng. Mohamed ElSaadany To Complete Performance Index (TCPI) : ‫المشروع‬ ‫إلكمال‬ ‫المطلوبة‬ ‫للقيمة‬ ‫اآلداء‬ ‫مؤشر‬ • It’s the cost performance that must be achieved on the remaining work to meet a specified goal like BAC or EAC ‫القادمة‬ ‫الفترة‬ ‫في‬ ‫تحقيقه‬ ‫المطلوب‬ ‫المالي‬ ‫االداء‬ • It represents the ratio between remaining works and remaining funds. ‫المتبقي‬ ‫التمويل‬ ‫قيمة‬ ‫و‬ ‫المتبقية‬ ‫االعمال‬ ‫قيمة‬ ‫بين‬ ‫النسبة‬ ‫تمثل‬ • TCPI = (BAC-EV) / (BAC – AC) Or TCPI = (BAC-EV) / (EAC – AC) “If the BAC is no longer valid” • Ex : BAC = 500’000.00 , EV = 200’000.00, AC= 250’000.00 TCPI = (300’000.00 ) / (250’000.00) = 1.2 TT Performance Reviews : • Variance at completion (VAC) = BAC – EAC • Trend Analysis: Graphical analysis examines project performance over time. • EVM TT