SlideShare uma empresa Scribd logo
1 de 15
Project crashingProject crashing
Project crashingProject crashing
• It is common in project management that
additional resources are used to either speed up
some activities to get the project back on
schedule or to reduce the project completion
time.
• Crashing an activity refers to the speeding up or
shortening of the duration of an activity by using
additional resources. These include overtime,
hiring temporary staff, renting more efficient
equipment, and other measures.
Project crashingProject crashing
• Project crashing refers to the process of
shortening the duration of the project by
crashing the duration of a number of activities.
• Since it generally results in an increase of the
overall project costs, the challenge faced by the
project manager is to identify the activities to
crash and the duration reduction for each
activity such that as the project crashing is done
in the least expensive manner possible.
Project crashingProject crashing
• The normal time refers to the estimated activity
duration used with CPM or PERT in the
computation of earliest (latest) start or finish
times.
• The normal cost refers to the activity cost under
the normal activity time.
•
Project crashingProject crashing
• The crash time refers to the shortest possible time to
complete an activity with additional resources.
• The crashing cost refers to the activity cost under the
crashing activity time. This relationship is assumed to
be linear. Hence, for each activity a crash cost per
period (e.g.,per week) can be derived as follows:
• crash cost per period = (Crash cost - Normal Cost)/
(Normal time - Crash time)
Project crashingProject crashing
• the cost to crash per period assumes that the
relationship between adding more money to
the activity and reducing the time is linear.
Spend half of the money, and get half the time
reduction, spend _ of the money and get _
time reduction. This is not always true in
practice, but works alright for a rough
planning technique
THE GENERAL RELATIONSHIP OF TIMETHE GENERAL RELATIONSHIP OF TIME
AND COSTAND COST
• Crashing costs increase as project durationCrashing costs increase as project duration
decreases.decreases.
• Indirect costs increase as productionIndirect costs increase as production
duration increases.duration increases.
• Reduce project length as long as crashingReduce project length as long as crashing
costs are less than indirect costs.costs are less than indirect costs.
Conti….Conti….
Conti….Conti….
• The objective of crashing was to reduce theThe objective of crashing was to reduce the
scheduled completion time to reap thescheduled completion time to reap the
results of the projects sooner.results of the projects sooner.
• However, there may be other reasons forHowever, there may be other reasons for
reducing project time.reducing project time.
• There also may be direct financial penaltiesThere also may be direct financial penalties
for not completing a project on time.for not completing a project on time.
What criteria should it be based onWhat criteria should it be based on
when deciding to crashing criticalwhen deciding to crashing critical
times?times?
The critical path is 1-2-3, the completion time =11The critical path is 1-2-3, the completion time =11
How? Path: 1-2-3 = 5+6=11 weeksHow? Path: 1-2-3 = 5+6=11 weeks
Path: 1-3 = 5 weeksPath: 1-3 = 5 weeks
Now, how many days can we “crash” it?Now, how many days can we “crash” it?
1
3
25 (1) 6(3)
Conti…Conti…
• The maximum time that can be crashed for:The maximum time that can be crashed for:
Path 1-2-3 = 1 + 3 = 4Path 1-2-3 = 1 + 3 = 4
Path 1-3 = 0Path 1-3 = 0
• ShouldShould we use up all these 4 weeks?we use up all these 4 weeks?
1
3
25 (1) 6(3)
5(0)
• If we used all 4 days, then path 1-2-3 has
(5-1) + (6-3) = 7 completion weeks
Now, we need to check if the completion time for path 1-3
has lesser than 7 weeks (why?)
Now, path 1-3 has (5-0) = 5 weeks
Since path 1-3 still shorter than 7 weeks, we used up all 4
crashed weeks
• Question: What if path 1-3 has, say 8 weeks completion
time?
1
3
2
5 (1)
6(3)
5(0)
4(0) 3(0)
• Now, we cannot use all 4 days (Why?)
Because path 1-2-3 will not be critical path anymore
path 1-3 would now has longest hour to finish
• Rule: When a path is a critical path, it will not stay as
a critical path
• So, we can only reduce the path 1-2-3 completion
time to the same time
• as path 1-3. (HOW?)
1 3
25 (1) 6(3)
8(0)
• We can only reduce total time for path 1-2-3 =We can only reduce total time for path 1-2-3 =
path 1-path 1-33,,
that is 8 weeksthat is 8 weeks
If the cost for path 1-2 and path 2-3 is the sameIf the cost for path 1-2 and path 2-3 is the same
thenthen
We can random pick them to crash so that itsWe can random pick them to crash so that its
completioncompletion
Time is 8 weeksTime is 8 weeks
1
3
25 (1) 6(3)
8(0)
1
3
25 (1)5 (1) 6(3)6(3)
8(0)8(0)
1
2
3
5 (1)5 (1)
6(3)6(3)
8(0)8(0)
OR
4(0)4(0) 4(1)4(1)
3(0)3(0)

Mais conteúdo relacionado

Mais procurados

PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULEAjeesh Mk
 
Difference between PERT and CPM
Difference between PERT and CPMDifference between PERT and CPM
Difference between PERT and CPMMunaf Dayee
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTS.Vijaya Bhaskar
 
Project planning and Scheduling
Project planning and SchedulingProject planning and Scheduling
Project planning and Schedulingsaurabmi2
 
Project management PPT
Project management  PPTProject management  PPT
Project management PPTRaj Sampat
 
Project crashing and job sequencing
Project crashing and job sequencingProject crashing and job sequencing
Project crashing and job sequencingBuha Payal
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Akaresh Jose Kaviyil JY
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisAsif Sultan Razu
 
Contracts and Types (Project Management)
Contracts and Types (Project Management) Contracts and Types (Project Management)
Contracts and Types (Project Management) Habib Rahman
 
Critical Path Ppt
Critical Path PptCritical Path Ppt
Critical Path PptJeff Hilton
 
Resource Scheduling
Resource SchedulingResource Scheduling
Resource SchedulingNicola2903
 
PERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSPERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSZulfiquer Ahmed Amin
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost ManagementBhuWan Khadka
 

Mais procurados (20)

PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Crashing in Project Management
Crashing in Project ManagementCrashing in Project Management
Crashing in Project Management
 
Difference between PERT and CPM
Difference between PERT and CPMDifference between PERT and CPM
Difference between PERT and CPM
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
 
Project planning and Scheduling
Project planning and SchedulingProject planning and Scheduling
Project planning and Scheduling
 
Project management PPT
Project management  PPTProject management  PPT
Project management PPT
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Per tand project crashing
Per tand project crashingPer tand project crashing
Per tand project crashing
 
Project crashing and job sequencing
Project crashing and job sequencingProject crashing and job sequencing
Project crashing and job sequencing
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network Analysis
 
Contracts and Types (Project Management)
Contracts and Types (Project Management) Contracts and Types (Project Management)
Contracts and Types (Project Management)
 
Critical Path Ppt
Critical Path PptCritical Path Ppt
Critical Path Ppt
 
Project Management PERT and CPM
Project Management PERT and CPMProject Management PERT and CPM
Project Management PERT and CPM
 
Resource Scheduling
Resource SchedulingResource Scheduling
Resource Scheduling
 
PERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSPERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLS
 
Project planning and control
Project planning and controlProject planning and control
Project planning and control
 
Critical path method
Critical path methodCritical path method
Critical path method
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost Management
 

Semelhante a crashing of project

Resource-Allocation.ppt
Resource-Allocation.pptResource-Allocation.ppt
Resource-Allocation.pptTecnicoItca
 
Software Project Scheduling Diagrams
Software Project Scheduling DiagramsSoftware Project Scheduling Diagrams
Software Project Scheduling DiagramsSaqib Raza
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..pptPedadaSaikumar
 
Criticalchainprojectmanagement
CriticalchainprojectmanagementCriticalchainprojectmanagement
Criticalchainprojectmanagementkaton808
 
chapter 6.ppt
chapter 6.pptchapter 6.ppt
chapter 6.pptDejeneDay
 
Mba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management aMba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management aRai University
 
Pert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertPert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertRaj J Das
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTsalsa moyara
 
Time cost trade off
Time cost trade offTime cost trade off
Time cost trade offzollatrix
 
Reducing Project Duration_Jagat Prasad Upadhyay.pptx
Reducing Project Duration_Jagat Prasad Upadhyay.pptxReducing Project Duration_Jagat Prasad Upadhyay.pptx
Reducing Project Duration_Jagat Prasad Upadhyay.pptxJagat Upadhyay
 
Allocating Resources To The Project
Allocating Resources To The ProjectAllocating Resources To The Project
Allocating Resources To The ProjectJeff Brooks
 
06 project time management
06  project time management06  project time management
06 project time managementAla Ibrahim
 

Semelhante a crashing of project (20)

Resource-Allocation.ppt
Resource-Allocation.pptResource-Allocation.ppt
Resource-Allocation.ppt
 
ch09s.ppt
ch09s.pptch09s.ppt
ch09s.ppt
 
Software Project Scheduling Diagrams
Software Project Scheduling DiagramsSoftware Project Scheduling Diagrams
Software Project Scheduling Diagrams
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
 
Criticalchainprojectmanagement
CriticalchainprojectmanagementCriticalchainprojectmanagement
Criticalchainprojectmanagement
 
chapter 6.ppt
chapter 6.pptchapter 6.ppt
chapter 6.ppt
 
Mba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management aMba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management a
 
Pert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertPert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gert
 
Chapter 07
Chapter 07Chapter 07
Chapter 07
 
Project time management
Project time managementProject time management
Project time management
 
EpM
EpMEpM
EpM
 
Ch09 (1).pptx
Ch09 (1).pptxCh09 (1).pptx
Ch09 (1).pptx
 
Project management techniques
Project management techniquesProject management techniques
Project management techniques
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENT
 
Time cost trade off
Time cost trade offTime cost trade off
Time cost trade off
 
Reducing Project Duration_Jagat Prasad Upadhyay.pptx
Reducing Project Duration_Jagat Prasad Upadhyay.pptxReducing Project Duration_Jagat Prasad Upadhyay.pptx
Reducing Project Duration_Jagat Prasad Upadhyay.pptx
 
pm--basic.pptx
pm--basic.pptxpm--basic.pptx
pm--basic.pptx
 
Allocating Resources To The Project
Allocating Resources To The ProjectAllocating Resources To The Project
Allocating Resources To The Project
 
06 project time management
06  project time management06  project time management
06 project time management
 
Unit IV-Project Management
Unit IV-Project ManagementUnit IV-Project Management
Unit IV-Project Management
 

Mais de Mir Zafarullah

Introduction to Irrigation System of Pakistan
Introduction to Irrigation System of PakistanIntroduction to Irrigation System of Pakistan
Introduction to Irrigation System of PakistanMir Zafarullah
 
Transition curve and Superelevation
Transition curve and SuperelevationTransition curve and Superelevation
Transition curve and SuperelevationMir Zafarullah
 
Obstaclesinchaining 170811123641
Obstaclesinchaining 170811123641Obstaclesinchaining 170811123641
Obstaclesinchaining 170811123641Mir Zafarullah
 
Errorsandmistakesinchaining 170810071200
Errorsandmistakesinchaining 170810071200Errorsandmistakesinchaining 170810071200
Errorsandmistakesinchaining 170810071200Mir Zafarullah
 
Types of flow in open channel
Types of flow in open channelTypes of flow in open channel
Types of flow in open channelMir Zafarullah
 
Types of beam & types of supports
Types of beam & types of supportsTypes of beam & types of supports
Types of beam & types of supportsMir Zafarullah
 
Hydrographics surveying
Hydrographics surveyingHydrographics surveying
Hydrographics surveyingMir Zafarullah
 
Levelling, terms related to levelling, methods of levelling
Levelling, terms related to levelling, methods of levellingLevelling, terms related to levelling, methods of levelling
Levelling, terms related to levelling, methods of levellingMir Zafarullah
 
Water pollution and source
Water pollution and sourceWater pollution and source
Water pollution and sourceMir Zafarullah
 
Self purification of river water
Self purification of river waterSelf purification of river water
Self purification of river waterMir Zafarullah
 
Water sampling , procedure, purpose , techniques and equipments
Water sampling , procedure, purpose , techniques and equipmentsWater sampling , procedure, purpose , techniques and equipments
Water sampling , procedure, purpose , techniques and equipmentsMir Zafarullah
 
Environmental Pollution and its causess
Environmental Pollution and its causessEnvironmental Pollution and its causess
Environmental Pollution and its causessMir Zafarullah
 
Water Filtration by sand filtration
Water Filtration by sand filtrationWater Filtration by sand filtration
Water Filtration by sand filtrationMir Zafarullah
 
coagulation and flocculation
coagulation and flocculation coagulation and flocculation
coagulation and flocculation Mir Zafarullah
 
sedimentation and its types
sedimentation and its typessedimentation and its types
sedimentation and its typesMir Zafarullah
 
Water purification and methods
Water purification and methodsWater purification and methods
Water purification and methodsMir Zafarullah
 

Mais de Mir Zafarullah (20)

Introduction to Irrigation System of Pakistan
Introduction to Irrigation System of PakistanIntroduction to Irrigation System of Pakistan
Introduction to Irrigation System of Pakistan
 
Transition curve and Superelevation
Transition curve and SuperelevationTransition curve and Superelevation
Transition curve and Superelevation
 
Ranging 170811123447
Ranging 170811123447Ranging 170811123447
Ranging 170811123447
 
Obstaclesinchaining 170811123641
Obstaclesinchaining 170811123641Obstaclesinchaining 170811123641
Obstaclesinchaining 170811123641
 
Errorsandmistakesinchaining 170810071200
Errorsandmistakesinchaining 170810071200Errorsandmistakesinchaining 170810071200
Errorsandmistakesinchaining 170810071200
 
Friction factor
Friction factorFriction factor
Friction factor
 
Types of flow in open channel
Types of flow in open channelTypes of flow in open channel
Types of flow in open channel
 
Types of beam & types of supports
Types of beam & types of supportsTypes of beam & types of supports
Types of beam & types of supports
 
Hydrographics surveying
Hydrographics surveyingHydrographics surveying
Hydrographics surveying
 
Levelling, terms related to levelling, methods of levelling
Levelling, terms related to levelling, methods of levellingLevelling, terms related to levelling, methods of levelling
Levelling, terms related to levelling, methods of levelling
 
Water pollution and source
Water pollution and sourceWater pollution and source
Water pollution and source
 
Self purification of river water
Self purification of river waterSelf purification of river water
Self purification of river water
 
Water sampling , procedure, purpose , techniques and equipments
Water sampling , procedure, purpose , techniques and equipmentsWater sampling , procedure, purpose , techniques and equipments
Water sampling , procedure, purpose , techniques and equipments
 
Reverse osmosis
Reverse osmosisReverse osmosis
Reverse osmosis
 
Environmental Pollution and its causess
Environmental Pollution and its causessEnvironmental Pollution and its causess
Environmental Pollution and its causess
 
Hard and soft water
Hard and soft water Hard and soft water
Hard and soft water
 
Water Filtration by sand filtration
Water Filtration by sand filtrationWater Filtration by sand filtration
Water Filtration by sand filtration
 
coagulation and flocculation
coagulation and flocculation coagulation and flocculation
coagulation and flocculation
 
sedimentation and its types
sedimentation and its typessedimentation and its types
sedimentation and its types
 
Water purification and methods
Water purification and methodsWater purification and methods
Water purification and methods
 

Último

Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 

Último (20)

Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 

crashing of project

  • 2. Project crashingProject crashing • It is common in project management that additional resources are used to either speed up some activities to get the project back on schedule or to reduce the project completion time. • Crashing an activity refers to the speeding up or shortening of the duration of an activity by using additional resources. These include overtime, hiring temporary staff, renting more efficient equipment, and other measures.
  • 3. Project crashingProject crashing • Project crashing refers to the process of shortening the duration of the project by crashing the duration of a number of activities. • Since it generally results in an increase of the overall project costs, the challenge faced by the project manager is to identify the activities to crash and the duration reduction for each activity such that as the project crashing is done in the least expensive manner possible.
  • 4. Project crashingProject crashing • The normal time refers to the estimated activity duration used with CPM or PERT in the computation of earliest (latest) start or finish times. • The normal cost refers to the activity cost under the normal activity time. •
  • 5. Project crashingProject crashing • The crash time refers to the shortest possible time to complete an activity with additional resources. • The crashing cost refers to the activity cost under the crashing activity time. This relationship is assumed to be linear. Hence, for each activity a crash cost per period (e.g.,per week) can be derived as follows: • crash cost per period = (Crash cost - Normal Cost)/ (Normal time - Crash time)
  • 6. Project crashingProject crashing • the cost to crash per period assumes that the relationship between adding more money to the activity and reducing the time is linear. Spend half of the money, and get half the time reduction, spend _ of the money and get _ time reduction. This is not always true in practice, but works alright for a rough planning technique
  • 7. THE GENERAL RELATIONSHIP OF TIMETHE GENERAL RELATIONSHIP OF TIME AND COSTAND COST • Crashing costs increase as project durationCrashing costs increase as project duration decreases.decreases. • Indirect costs increase as productionIndirect costs increase as production duration increases.duration increases. • Reduce project length as long as crashingReduce project length as long as crashing costs are less than indirect costs.costs are less than indirect costs.
  • 9. Conti….Conti…. • The objective of crashing was to reduce theThe objective of crashing was to reduce the scheduled completion time to reap thescheduled completion time to reap the results of the projects sooner.results of the projects sooner. • However, there may be other reasons forHowever, there may be other reasons for reducing project time.reducing project time. • There also may be direct financial penaltiesThere also may be direct financial penalties for not completing a project on time.for not completing a project on time.
  • 10. What criteria should it be based onWhat criteria should it be based on when deciding to crashing criticalwhen deciding to crashing critical times?times? The critical path is 1-2-3, the completion time =11The critical path is 1-2-3, the completion time =11 How? Path: 1-2-3 = 5+6=11 weeksHow? Path: 1-2-3 = 5+6=11 weeks Path: 1-3 = 5 weeksPath: 1-3 = 5 weeks Now, how many days can we “crash” it?Now, how many days can we “crash” it? 1 3 25 (1) 6(3)
  • 11. Conti…Conti… • The maximum time that can be crashed for:The maximum time that can be crashed for: Path 1-2-3 = 1 + 3 = 4Path 1-2-3 = 1 + 3 = 4 Path 1-3 = 0Path 1-3 = 0 • ShouldShould we use up all these 4 weeks?we use up all these 4 weeks? 1 3 25 (1) 6(3) 5(0)
  • 12. • If we used all 4 days, then path 1-2-3 has (5-1) + (6-3) = 7 completion weeks Now, we need to check if the completion time for path 1-3 has lesser than 7 weeks (why?) Now, path 1-3 has (5-0) = 5 weeks Since path 1-3 still shorter than 7 weeks, we used up all 4 crashed weeks • Question: What if path 1-3 has, say 8 weeks completion time? 1 3 2 5 (1) 6(3) 5(0) 4(0) 3(0)
  • 13. • Now, we cannot use all 4 days (Why?) Because path 1-2-3 will not be critical path anymore path 1-3 would now has longest hour to finish • Rule: When a path is a critical path, it will not stay as a critical path • So, we can only reduce the path 1-2-3 completion time to the same time • as path 1-3. (HOW?) 1 3 25 (1) 6(3) 8(0)
  • 14. • We can only reduce total time for path 1-2-3 =We can only reduce total time for path 1-2-3 = path 1-path 1-33,, that is 8 weeksthat is 8 weeks If the cost for path 1-2 and path 2-3 is the sameIf the cost for path 1-2 and path 2-3 is the same thenthen We can random pick them to crash so that itsWe can random pick them to crash so that its completioncompletion Time is 8 weeksTime is 8 weeks 1 3 25 (1) 6(3) 8(0)
  • 15. 1 3 25 (1)5 (1) 6(3)6(3) 8(0)8(0) 1 2 3 5 (1)5 (1) 6(3)6(3) 8(0)8(0) OR 4(0)4(0) 4(1)4(1) 3(0)3(0)