SlideShare uma empresa Scribd logo
1 de 6
Baixar para ler offline
Issue 4, May 2006Contract 423 - PIE to Ubi Road 2
the The Kallang/Paya Lebar Expressway (KPE) project is
Singapore’s most complex expressway project to date.
With 9 kilometres of underground tunnels to construct,
engineers have had to face challenges ranging from
deep marine clay valleys, a network of underground
utilities, tunnel construction under the operational
east-west MRT line, tunnel construction under the
Geylang River and under the Pelton Canal.
KPE Contract 423 scope of works covers the design,
construction and completion of a 2.96 km vehicular
tunnel from PIE to Ubi Road 2. A major part of the
works is located under the Pelton Canal.
ForContract423,thetunnelworksatthePeltonCanal
has offered the greatest challenge to the project
team. The Pelton Canal’s width is between 19 and 27
metres. The KPE tunnels when completed (including
the north bound and south bound carriageways)
measure 34 metres across. How do you construct
a sub-terrain expressway tunnel under a canal,
constrained on both sides by residential buildings,
the closest of which is only 4 metres away from the
excavation edge?
Figure 1 Figure 2
Figure 5 Figure 6
Bored piling works next to Blk 125 Aljunied Road
Figure 3 Figure 4
Figure 7 Figure 8
To solve this problem, a half-box tunnel construction method was adopted for building the
tunnel. To illustrate how we accomplished this task, let us focus on the Aljunied area. As
part of the preparation work for the diversion of Pelton Canal, diaphragm walls (concrete
retaining walls) are installed at the extremity of the future KPE north bound tunnel adjacent
to Blk 125 Aljunied Road (see figure 1). Centre sheet piles were then driven into the ground
to form part of the temporary works that are necessary to support the diverted canal.
A temporary canal with equivalent capacity of the Pelton Canal was constructed infront of
Blk 125 Aljunied Road. The water from the original Pelton Canal was diverted into the new
temporary canal (see figure 2). This frees up space for the installation of the diaphragm
walls in front of Blk 122 Paya Lebar Way (see figure 3). To further minimize soil movement
and ensure the robustness of the temporary works, transverse walls and centre diaphragm
walls were installed deeper than the KPE tunnel formation level (see figure 4).The transverse
walls, installed at 7m intervals, formed a rigid support structure to the diaphragm walls
along the whole excavation length. This was followed by bored pile installation to support
the tunnel box and excavation for the south bound half of the tunnel (see figures 5 & 6).
Figure 9 Figure 10
Figure 11 Figure 12
In March 2006, we completed the construction of the
KPE south bound tunnel in front of Blk 122 Paya Lebar
Way (see figure 7). We have now embarked on the
construction of the KPE north bound tunnel. The works
that are currently in progress or coming up include
the temporary diversion of the canal on top of the
completed tunnel in front of Blk 122 Paya Lebar Way
(see figure 8), the installation of bored piles, complete
installationofthenorthbounddiaphragmwallsandthe
removal of the diverted Pelton Canal structure adjacent
to Blk 125 Aljunied Road (see figure 9).
The removal of the canal involves the break out of the
temporary Pelton Canal structure adjacent to Blk 125
Aljunied Road. This will be carried out in May 2006.
We are mindful that during the works, there will be
an increase in construction noise, dust and vibration.
We shall carry out noise and dust mitigating measures
such as erection of noise barriers, installation of noise
monitoring equipment to measure noise level and
frequent wetting of the area so as to reduce dust. Noisy
breaking out works will be stopped by 7pm daily from
Mondays to Saturdays, and will not be carried out on
Sundays. Once the diverted canal has been removed,
the north bound tunnel will be excavated and
constructed (see figures 10 & 11). Once all the tunnels
are completed, the Pelton Canal will be reconstructed
back to its original position (see figure 12).
For the area between the Pan-Island
Expressway to Aljunied Road, excavation
and strut installation works are in full swing.
Tunnel construction works are expected to
be completed by early 2007, after which,
the re-instatement of the Pelton Canal and
Ajunied Road Bridge will be carried out.
The construction of the KPE tunnels
between Aljunied Road and Merpati Road
area are making good progress. The KPE
The basic structure of KPE Ventilation Building ‘D’ located at the junction of
Upper Paya Lebar Road and Airport Road has been completed
south bound tunnel structures, in front of
Blk 122 Paya Lebar Way were completed in
March 2006. Works are now in progress for
the construction of the north bound tunnel.
The tunnels in the Mattar Road area (from
Block 79/79A to just after the MacPherson
Community Club) have been completed
and construction of the new Pelton Canal is
now in progress.This canal will be reinstated
over the completed tunnels in this area in
May 2006.
ProgressUpdate
If you have feedback or
suggestions, please contact:
Mr Michael Yap,
Deputy Manager,
Community Relations,
Land Transport Authority
mobile: 9831 4546
tel: 6396 1600
email: michael_yap@lta.gov.sg
or
Mr Mohd. Zulkafli,
Public Relations Manager of
Samsung Corporation
mobile: 9635 5674
FEEDBACK
Land Transport Authority
No. 1 Hampshire Road, Singapore 219428
Customer Service Line: 1800 225 5582
Fax: 6396 1148
Website: www.lta.gov.sg
For the tunnel between Merpati Road and Paya Lebar Road area,
the KPE south bound half-box tunnels on the Balam Estate side has
been completed. Excavation and tunnel construction works for the
KPE north bound half-box on the Jalan Chengkek side is currently in
progress. The tunnel works in this area are expected to be complete
by early 2007 and the Pelton Canal will be reinstated to its original
alignment by the end of 2007.
Between Paya Lebar Road and Ubi Road 2, tunnel construction
works are substantially complete. Reinstatement of Airport Road to
its original alignment will begin from June 2006 onwards. The basic
structure ofVentilation Building‘D’at the corner of Paya Lebar Road/
Airport Road junction has been completed. Architectural as well as
Electrical and Mechanical (E&M) fit out works are now in progress.
ProgressUpdate
We would like to
thank all the residents
for their patience
and understanding
throughout the
construction of KPE.

Mais conteúdo relacionado

Mais procurados

Brentcliffe - Victoria Park Construction Liaison Committee - September 2017
Brentcliffe - Victoria Park Construction Liaison Committee - September 2017Brentcliffe - Victoria Park Construction Liaison Committee - September 2017
Brentcliffe - Victoria Park Construction Liaison Committee - September 2017
Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - January 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - January 2018Pharmacy to Kennedy Construction Liaison Committee Meeting - January 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - January 2018
Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - September 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - September 2017Pharmacy to Kennedy Construction Liaison Committee Meeting - September 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - September 2017
Crosstown TO
 
Central Open House (Chaplin Station to Leaside Station) - spring 2018
Central Open House (Chaplin Station to Leaside Station) - spring 2018Central Open House (Chaplin Station to Leaside Station) - spring 2018
Central Open House (Chaplin Station to Leaside Station) - spring 2018
Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
Crosstown TO
 
Project - Solomon Spur Rail
Project - Solomon Spur RailProject - Solomon Spur Rail
Project - Solomon Spur Rail
Damian Brandon
 
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Crosstown TO
 
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - October 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - October 2017Brentcliffe-Victoria Park Construction Liaison Committee Meeting - October 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - October 2017
Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - February 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - February 2018Pharmacy to Kennedy Construction Liaison Committee Meeting - February 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - February 2018
Crosstown TO
 
Leaside & Laird Stations Construction Liaison Committee - October 2017
Leaside & Laird Stations Construction Liaison Committee - October 2017Leaside & Laird Stations Construction Liaison Committee - October 2017
Leaside & Laird Stations Construction Liaison Committee - October 2017
Crosstown TO
 
Central East Open House Spring 2019
Central East Open House Spring 2019Central East Open House Spring 2019
Central East Open House Spring 2019
Crosstown TO
 
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting - March 2018
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting -  March 2018 Brentcliffe - Vctoria Park Construction Liaison Committee Meeting -  March 2018
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting - March 2018
Crosstown TO
 
Leaside open house sep 2014 slides
Leaside open house sep 2014   slidesLeaside open house sep 2014   slides
Leaside open house sep 2014 slides
Crosstown TO
 
Caledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open HouseCaledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open House
Crosstown TO
 
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017Eglinton & Mount Pleasant Construction Liaison Committee - November 2017
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017
Crosstown TO
 

Mais procurados (20)

Brentcliffe - Victoria Park Construction Liaison Committee - September 2017
Brentcliffe - Victoria Park Construction Liaison Committee - September 2017Brentcliffe - Victoria Park Construction Liaison Committee - September 2017
Brentcliffe - Victoria Park Construction Liaison Committee - September 2017
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - January 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - January 2018Pharmacy to Kennedy Construction Liaison Committee Meeting - January 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - January 2018
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - September 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - September 2017Pharmacy to Kennedy Construction Liaison Committee Meeting - September 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - September 2017
 
Central Open House (Chaplin Station to Leaside Station) - spring 2018
Central Open House (Chaplin Station to Leaside Station) - spring 2018Central Open House (Chaplin Station to Leaside Station) - spring 2018
Central Open House (Chaplin Station to Leaside Station) - spring 2018
 
Station Design Update Meeting: East Open House
Station Design Update Meeting: East Open HouseStation Design Update Meeting: East Open House
Station Design Update Meeting: East Open House
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
 
Project - Solomon Spur Rail
Project - Solomon Spur RailProject - Solomon Spur Rail
Project - Solomon Spur Rail
 
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
 
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - October 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - October 2017Brentcliffe-Victoria Park Construction Liaison Committee Meeting - October 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - October 2017
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - February 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - February 2018Pharmacy to Kennedy Construction Liaison Committee Meeting - February 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - February 2018
 
Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November  Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November
 
Leaside & Laird Stations Construction Liaison Committee - October 2017
Leaside & Laird Stations Construction Liaison Committee - October 2017Leaside & Laird Stations Construction Liaison Committee - October 2017
Leaside & Laird Stations Construction Liaison Committee - October 2017
 
Central East Open House Spring 2019
Central East Open House Spring 2019Central East Open House Spring 2019
Central East Open House Spring 2019
 
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting - March 2018
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting -  March 2018 Brentcliffe - Vctoria Park Construction Liaison Committee Meeting -  March 2018
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting - March 2018
 
West Open House - Progress Update Sept 2014
West Open House - Progress Update Sept 2014West Open House - Progress Update Sept 2014
West Open House - Progress Update Sept 2014
 
Leaside open house sep 2014 slides
Leaside open house sep 2014   slidesLeaside open house sep 2014   slides
Leaside open house sep 2014 slides
 
Pharmacy kennedy clc meeting -january 29 2019
Pharmacy kennedy clc meeting -january 29 2019Pharmacy kennedy clc meeting -january 29 2019
Pharmacy kennedy clc meeting -january 29 2019
 
Caledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open HouseCaledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open House
 
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017Eglinton & Mount Pleasant Construction Liaison Committee - November 2017
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017
 

Destaque

Article guarantee May 2014
Article guarantee May 2014Article guarantee May 2014
Article guarantee May 2014
Shuchi Ray
 
Folha 325 mãozinha quase milagrosa na colheita do café
Folha 325   mãozinha quase milagrosa na colheita do caféFolha 325   mãozinha quase milagrosa na colheita do café
Folha 325 mãozinha quase milagrosa na colheita do café
Thiago Tavares
 
KDMiller_presentationFinal
KDMiller_presentationFinalKDMiller_presentationFinal
KDMiller_presentationFinal
Kyle Miller
 
McClure FedRAMP for FedScoop
McClure FedRAMP for FedScoopMcClure FedRAMP for FedScoop
McClure FedRAMP for FedScoop
Sherry Jones
 

Destaque (17)

Sugenya's article3 (1)
Sugenya's article3 (1)Sugenya's article3 (1)
Sugenya's article3 (1)
 
Manual do Pré-Amplificador FOCUSRITE Octopre MKII
Manual do Pré-Amplificador FOCUSRITE Octopre MKIIManual do Pré-Amplificador FOCUSRITE Octopre MKII
Manual do Pré-Amplificador FOCUSRITE Octopre MKII
 
Rolas en El Mañanero.
Rolas en El Mañanero.Rolas en El Mañanero.
Rolas en El Mañanero.
 
Rolas en El Mañanero.
Rolas en El Mañanero.Rolas en El Mañanero.
Rolas en El Mañanero.
 
WORKFORCE RE-STRUCTURING & RE-ALIGNMENT
WORKFORCE RE-STRUCTURING & RE-ALIGNMENTWORKFORCE RE-STRUCTURING & RE-ALIGNMENT
WORKFORCE RE-STRUCTURING & RE-ALIGNMENT
 
календарь 2016 последние правки 28-10
календарь 2016 последние правки 28-10календарь 2016 последние правки 28-10
календарь 2016 последние правки 28-10
 
Article guarantee May 2014
Article guarantee May 2014Article guarantee May 2014
Article guarantee May 2014
 
Folha 325 mãozinha quase milagrosa na colheita do café
Folha 325   mãozinha quase milagrosa na colheita do caféFolha 325   mãozinha quase milagrosa na colheita do café
Folha 325 mãozinha quase milagrosa na colheita do café
 
Erica Haines Welcome video
Erica Haines Welcome videoErica Haines Welcome video
Erica Haines Welcome video
 
Manual de estudio
Manual de estudioManual de estudio
Manual de estudio
 
KDMiller_presentationFinal
KDMiller_presentationFinalKDMiller_presentationFinal
KDMiller_presentationFinal
 
Cuadro comparativo-apartir-de-la-redaccion-de-objetivos-propsitos-y-competencias
Cuadro comparativo-apartir-de-la-redaccion-de-objetivos-propsitos-y-competenciasCuadro comparativo-apartir-de-la-redaccion-de-objetivos-propsitos-y-competencias
Cuadro comparativo-apartir-de-la-redaccion-de-objetivos-propsitos-y-competencias
 
Trends in Public Agricultural R&D Investment and Staffing in Pakistan
Trends in Public Agricultural R&D  Investment and Staffing in PakistanTrends in Public Agricultural R&D  Investment and Staffing in Pakistan
Trends in Public Agricultural R&D Investment and Staffing in Pakistan
 
Power Grid Cybersecurity
Power Grid CybersecurityPower Grid Cybersecurity
Power Grid Cybersecurity
 
Webinar | HIL-based Wide-area Monitoring, Protection and Control R&D and Testing
Webinar | HIL-based Wide-area Monitoring, Protection and Control R&D and TestingWebinar | HIL-based Wide-area Monitoring, Protection and Control R&D and Testing
Webinar | HIL-based Wide-area Monitoring, Protection and Control R&D and Testing
 
Joan vinyoli (1914 1984)
Joan vinyoli (1914 1984) Joan vinyoli (1914 1984)
Joan vinyoli (1914 1984)
 
McClure FedRAMP for FedScoop
McClure FedRAMP for FedScoopMcClure FedRAMP for FedScoop
McClure FedRAMP for FedScoop
 

Semelhante a Think Outside The Box

GLASS, Ian (Mar15)
GLASS, Ian (Mar15)GLASS, Ian (Mar15)
GLASS, Ian (Mar15)
ian glass
 
PIS Uyo - Ring Road Phases I
PIS Uyo - Ring Road Phases IPIS Uyo - Ring Road Phases I
PIS Uyo - Ring Road Phases I
Sven Maedler
 
Practical Work Report - Fletcher
Practical Work Report - FletcherPractical Work Report - Fletcher
Practical Work Report - Fletcher
Jade Keswick
 
Article for Africon FACET
Article for Africon FACETArticle for Africon FACET
Article for Africon FACET
Christo Beukes
 
UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15
ADAM DUKE
 
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Crosstown TO
 
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
Crosstown TO
 
PIS Uyo - Ikot Ekpene Road Phase I
PIS Uyo - Ikot Ekpene Road Phase IPIS Uyo - Ikot Ekpene Road Phase I
PIS Uyo - Ikot Ekpene Road Phase I
Sven Maedler
 
Western Works Construction Liaison Committee Meeting - January 2018
Western Works Construction Liaison Committee Meeting - January 2018Western Works Construction Liaison Committee Meeting - January 2018
Western Works Construction Liaison Committee Meeting - January 2018
Crosstown TO
 

Semelhante a Think Outside The Box (20)

GLASS, Ian (Mar15)
GLASS, Ian (Mar15)GLASS, Ian (Mar15)
GLASS, Ian (Mar15)
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
PIS Uyo - Ring Road Phases I
PIS Uyo - Ring Road Phases IPIS Uyo - Ring Road Phases I
PIS Uyo - Ring Road Phases I
 
Quay failure in barcelona harbour
Quay failure in barcelona harbourQuay failure in barcelona harbour
Quay failure in barcelona harbour
 
Practical Work Report - Fletcher
Practical Work Report - FletcherPractical Work Report - Fletcher
Practical Work Report - Fletcher
 
1 sethi
1 sethi1 sethi
1 sethi
 
Article for Africon FACET
Article for Africon FACETArticle for Africon FACET
Article for Africon FACET
 
UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15
 
Project report
Project reportProject report
Project report
 
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
 
laos-tj-2016
laos-tj-2016laos-tj-2016
laos-tj-2016
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
 
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
 
PIS Uyo - Ikot Ekpene Road Phase I
PIS Uyo - Ikot Ekpene Road Phase IPIS Uyo - Ikot Ekpene Road Phase I
PIS Uyo - Ikot Ekpene Road Phase I
 
report draft
report draftreport draft
report draft
 
Tunnel Construction info.pdf
Tunnel Construction info.pdfTunnel Construction info.pdf
Tunnel Construction info.pdf
 
Grouting
Grouting Grouting
Grouting
 
Western Works Construction Liaison Committee Meeting - January 2018
Western Works Construction Liaison Committee Meeting - January 2018Western Works Construction Liaison Committee Meeting - January 2018
Western Works Construction Liaison Committee Meeting - January 2018
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
 

Mais de Singapore Power Ltd

Closer: Circle Line Tunnel Breakthrough
Closer: Circle Line Tunnel BreakthroughCloser: Circle Line Tunnel Breakthrough
Closer: Circle Line Tunnel Breakthrough
Singapore Power Ltd
 
Sights & Sound Of A Community Carnival
Sights & Sound Of A Community CarnivalSights & Sound Of A Community Carnival
Sights & Sound Of A Community Carnival
Singapore Power Ltd
 

Mais de Singapore Power Ltd (16)

Fire In The Belly! SG Trains Trainspotters!
Fire In The Belly! SG Trains Trainspotters!Fire In The Belly! SG Trains Trainspotters!
Fire In The Belly! SG Trains Trainspotters!
 
War On Dengue
War On DengueWar On Dengue
War On Dengue
 
Playing to a full house
Playing to a full housePlaying to a full house
Playing to a full house
 
How To Encourage Pedestrians To Use A New Underpass?
How To Encourage Pedestrians To Use A New Underpass?How To Encourage Pedestrians To Use A New Underpass?
How To Encourage Pedestrians To Use A New Underpass?
 
Are We The Most Sheltered People
Are We The Most Sheltered PeopleAre We The Most Sheltered People
Are We The Most Sheltered People
 
"Shared Vision" - Briefing for PA held on 19 may 2010
"Shared Vision" - Briefing for PA held on 19 may 2010"Shared Vision" - Briefing for PA held on 19 may 2010
"Shared Vision" - Briefing for PA held on 19 may 2010
 
Public Relation is not a "Wayang Show"
Public Relation is not a "Wayang Show"Public Relation is not a "Wayang Show"
Public Relation is not a "Wayang Show"
 
7 steps to building a stronger corporate brand
7 steps to building a stronger corporate brand7 steps to building a stronger corporate brand
7 steps to building a stronger corporate brand
 
7 steps to building a stronger corporate brand
7 steps to building a stronger corporate brand7 steps to building a stronger corporate brand
7 steps to building a stronger corporate brand
 
Customer satisfaction survey analysis of results
Customer satisfaction survey analysis of resultsCustomer satisfaction survey analysis of results
Customer satisfaction survey analysis of results
 
Closer: Circle Line Tunnel Breakthrough
Closer: Circle Line Tunnel BreakthroughCloser: Circle Line Tunnel Breakthrough
Closer: Circle Line Tunnel Breakthrough
 
Off The Beaten Track
Off The Beaten TrackOff The Beaten Track
Off The Beaten Track
 
Sights & Sound Of A Community Carnival
Sights & Sound Of A Community CarnivalSights & Sound Of A Community Carnival
Sights & Sound Of A Community Carnival
 
At The Heart Of The Community
At The Heart Of The CommunityAt The Heart Of The Community
At The Heart Of The Community
 
A Public Communication Story
A Public Communication StoryA Public Communication Story
A Public Communication Story
 
We Keep Shoppers Moving
We Keep Shoppers MovingWe Keep Shoppers Moving
We Keep Shoppers Moving
 

Último

Último (20)

(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7
(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7
(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7
 
PPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORS
PPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORSPPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORS
PPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORS
 
VIP Model Call Girls Lohegaon ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Lohegaon ( Pune ) Call ON 8005736733 Starting From 5K to...VIP Model Call Girls Lohegaon ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Lohegaon ( Pune ) Call ON 8005736733 Starting From 5K to...
 
Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
 
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
 
Top Rated Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
Top Rated  Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...Top Rated  Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
Top Rated Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
 
Booking open Available Pune Call Girls Shukrawar Peth 6297143586 Call Hot In...
Booking open Available Pune Call Girls Shukrawar Peth  6297143586 Call Hot In...Booking open Available Pune Call Girls Shukrawar Peth  6297143586 Call Hot In...
Booking open Available Pune Call Girls Shukrawar Peth 6297143586 Call Hot In...
 
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
 
A Press for the Planet: Journalism in the face of the Environmental Crisis
A Press for the Planet: Journalism in the face of the Environmental CrisisA Press for the Planet: Journalism in the face of the Environmental Crisis
A Press for the Planet: Journalism in the face of the Environmental Crisis
 
Sustainability by Design: Assessment Tool for Just Energy Transition Plans
Sustainability by Design: Assessment Tool for Just Energy Transition PlansSustainability by Design: Assessment Tool for Just Energy Transition Plans
Sustainability by Design: Assessment Tool for Just Energy Transition Plans
 
Postal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptxPostal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptx
 
Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024
 
Election 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfElection 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdf
 
2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos Webinar2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos Webinar
 
best call girls in Pune - 450+ Call Girl Cash Payment 8005736733 Neha Thakur
best call girls in Pune - 450+ Call Girl Cash Payment 8005736733 Neha Thakurbest call girls in Pune - 450+ Call Girl Cash Payment 8005736733 Neha Thakur
best call girls in Pune - 450+ Call Girl Cash Payment 8005736733 Neha Thakur
 
Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)
 
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlAntisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
 
2024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 302024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 30
 
Akurdi ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
Akurdi ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...Akurdi ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...
Akurdi ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
 
Call Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance Booking
 

Think Outside The Box

  • 1. Issue 4, May 2006Contract 423 - PIE to Ubi Road 2 the The Kallang/Paya Lebar Expressway (KPE) project is Singapore’s most complex expressway project to date. With 9 kilometres of underground tunnels to construct, engineers have had to face challenges ranging from deep marine clay valleys, a network of underground utilities, tunnel construction under the operational east-west MRT line, tunnel construction under the Geylang River and under the Pelton Canal.
  • 2. KPE Contract 423 scope of works covers the design, construction and completion of a 2.96 km vehicular tunnel from PIE to Ubi Road 2. A major part of the works is located under the Pelton Canal. ForContract423,thetunnelworksatthePeltonCanal has offered the greatest challenge to the project team. The Pelton Canal’s width is between 19 and 27 metres. The KPE tunnels when completed (including the north bound and south bound carriageways) measure 34 metres across. How do you construct a sub-terrain expressway tunnel under a canal, constrained on both sides by residential buildings, the closest of which is only 4 metres away from the excavation edge? Figure 1 Figure 2 Figure 5 Figure 6 Bored piling works next to Blk 125 Aljunied Road
  • 3. Figure 3 Figure 4 Figure 7 Figure 8 To solve this problem, a half-box tunnel construction method was adopted for building the tunnel. To illustrate how we accomplished this task, let us focus on the Aljunied area. As part of the preparation work for the diversion of Pelton Canal, diaphragm walls (concrete retaining walls) are installed at the extremity of the future KPE north bound tunnel adjacent to Blk 125 Aljunied Road (see figure 1). Centre sheet piles were then driven into the ground to form part of the temporary works that are necessary to support the diverted canal. A temporary canal with equivalent capacity of the Pelton Canal was constructed infront of Blk 125 Aljunied Road. The water from the original Pelton Canal was diverted into the new temporary canal (see figure 2). This frees up space for the installation of the diaphragm walls in front of Blk 122 Paya Lebar Way (see figure 3). To further minimize soil movement and ensure the robustness of the temporary works, transverse walls and centre diaphragm walls were installed deeper than the KPE tunnel formation level (see figure 4).The transverse walls, installed at 7m intervals, formed a rigid support structure to the diaphragm walls along the whole excavation length. This was followed by bored pile installation to support the tunnel box and excavation for the south bound half of the tunnel (see figures 5 & 6).
  • 4. Figure 9 Figure 10 Figure 11 Figure 12 In March 2006, we completed the construction of the KPE south bound tunnel in front of Blk 122 Paya Lebar Way (see figure 7). We have now embarked on the construction of the KPE north bound tunnel. The works that are currently in progress or coming up include the temporary diversion of the canal on top of the completed tunnel in front of Blk 122 Paya Lebar Way (see figure 8), the installation of bored piles, complete installationofthenorthbounddiaphragmwallsandthe removal of the diverted Pelton Canal structure adjacent to Blk 125 Aljunied Road (see figure 9). The removal of the canal involves the break out of the temporary Pelton Canal structure adjacent to Blk 125 Aljunied Road. This will be carried out in May 2006. We are mindful that during the works, there will be an increase in construction noise, dust and vibration. We shall carry out noise and dust mitigating measures such as erection of noise barriers, installation of noise monitoring equipment to measure noise level and frequent wetting of the area so as to reduce dust. Noisy breaking out works will be stopped by 7pm daily from Mondays to Saturdays, and will not be carried out on Sundays. Once the diverted canal has been removed, the north bound tunnel will be excavated and constructed (see figures 10 & 11). Once all the tunnels are completed, the Pelton Canal will be reconstructed back to its original position (see figure 12).
  • 5. For the area between the Pan-Island Expressway to Aljunied Road, excavation and strut installation works are in full swing. Tunnel construction works are expected to be completed by early 2007, after which, the re-instatement of the Pelton Canal and Ajunied Road Bridge will be carried out. The construction of the KPE tunnels between Aljunied Road and Merpati Road area are making good progress. The KPE The basic structure of KPE Ventilation Building ‘D’ located at the junction of Upper Paya Lebar Road and Airport Road has been completed south bound tunnel structures, in front of Blk 122 Paya Lebar Way were completed in March 2006. Works are now in progress for the construction of the north bound tunnel. The tunnels in the Mattar Road area (from Block 79/79A to just after the MacPherson Community Club) have been completed and construction of the new Pelton Canal is now in progress.This canal will be reinstated over the completed tunnels in this area in May 2006. ProgressUpdate
  • 6. If you have feedback or suggestions, please contact: Mr Michael Yap, Deputy Manager, Community Relations, Land Transport Authority mobile: 9831 4546 tel: 6396 1600 email: michael_yap@lta.gov.sg or Mr Mohd. Zulkafli, Public Relations Manager of Samsung Corporation mobile: 9635 5674 FEEDBACK Land Transport Authority No. 1 Hampshire Road, Singapore 219428 Customer Service Line: 1800 225 5582 Fax: 6396 1148 Website: www.lta.gov.sg For the tunnel between Merpati Road and Paya Lebar Road area, the KPE south bound half-box tunnels on the Balam Estate side has been completed. Excavation and tunnel construction works for the KPE north bound half-box on the Jalan Chengkek side is currently in progress. The tunnel works in this area are expected to be complete by early 2007 and the Pelton Canal will be reinstated to its original alignment by the end of 2007. Between Paya Lebar Road and Ubi Road 2, tunnel construction works are substantially complete. Reinstatement of Airport Road to its original alignment will begin from June 2006 onwards. The basic structure ofVentilation Building‘D’at the corner of Paya Lebar Road/ Airport Road junction has been completed. Architectural as well as Electrical and Mechanical (E&M) fit out works are now in progress. ProgressUpdate We would like to thank all the residents for their patience and understanding throughout the construction of KPE.