1. You’re a project manager working on a software engineering project. The programmers have
started building the software, and the testers have started to create the test environment. Which
process group includes these activities?
A.	
B.	
C.	
D.	

Initiating
Planning
Executing
Closing

2. Which of the following is not a stakeholder?
A.	
B.	
C.	
D.	

The project manager who is responsible for building the project
A project team member who will work on the project
A customer who will use the final product
A competitor whose company will lose business because of the product

3. A project manager runs into a problem with her project’s contractors, and she isn’t sure
if they’re abiding by the terms of the contract. Which knowledge area is the BEST source of
processes to help her deal with this problem?
A.	
B.	
C.	
D.	

Cost Management
Risk Management
Procurement Management
Communications Management

4. You’re a project manager for a construction project. You’ve just finished creating a list of all of
the people who will be directly affected by the project. What process group are you in?
A.	
B.	
C.	
D.	

Initiating
Planning
Executing
Monitoring & Controlling

5. Which process group contains the Develop Project Charter process and the Identify
Stakeholders process?
A.	
B.	
C.	
D.	

Initiating
Executing
Monitoring and Controlling
Closing

you are here 4   81
Download at Boykma.Com
exam questions

Exam Questions
6. Which of the following is NOT a project?
A.	
B.	
C.	
D.	

Repairing a car
Building a highway overpass
Running an IT support department
Filming a motion picture

7. A project manager is running a software project that is supposed to be delivered in phases. She was
planning on dividing the resources into two separate teams to do the work for two phases at the same time,
but one of her senior developers suggested that she use an Agile methodology instead, and she agrees. Which
of the following BEST describes the relationship between her project’s phases?
A.	
B.	
C.	
D.	

Sequential relationship
Iterative relationship
Constrained relationship
Overlapping relationship

8. Which of the following is NOT true about overlapping phases?
A.	
B.	
C.	
D.	

Each phase is typically done by a separate team
There’s an increased risk of delays when a later phase can’t start until an earlier one ends
There’s an increased risk to the project due to potential for rework
Every phase must go through all five process groups

9. You’re the project manager for an industrial design project. Your team members report to you, and you’re
responsible for creating the budget, building the schedule, and assigning the tasks. When the project is
complete, you release the team so they can work on other projects for the company. What kind of organization
do you work in?
A.	
B.	
C.	
D.	

Functional
Weak matrix
Strong matrix
Projectized

10. You’re a project manager working in a weak matrix organization. Which of the following is NOT true?
A.	
B.	
C.	
D.	

Your team members report to functional managers
You are not in directly charge of resources
Functional managers make decisions that can affect your projects
You have sole responsibility for the success or failure of the project

82   Chapter 3
Download at Boykma.Com
Answers

the process framework

Exam Questions
1. Answer: C

The Executing process group is the one where the team does all the work. You’ll get a good feel for the
process groups pretty quickly!
2. Answer: D
One of the hardest things that a project manager has to do on a project is figure out who all the
stakeholders are. The project manager, the team, the sponsor (or client), the customers and people who
will use the software, the senior managers at the company—they’re all stakeholders. Competitors aren’t
stakeholders, because even though they’re affected by the project, they don’t actually have any direct
influence over it.
3. Answer: C
The Procurement Management knowledge area deals with contracts, contractors, buyers and sellers. If
you’ve got a question about a type of contract or how to deal with contract problems, you’re being asked
about a Procurement Management process.
4. Answer: A
People who will be directly affected by the project are stakeholders, and when you’re creating a list of
them you’re performing the Identify Stakeholders process. That’s one of the two processes in the Initiating
process group.
5. Answer: A
The first things that are created on a project are the charter (which you create in the Develop Project
Charter process) and the Stakeholder Register (which you create in the Identify Stakeholders process).
You do those things when you’re initiating the project.

you are here 4   83
Download at Boykma.Com
exam answers

Answers

Exam Questions
6. Answer: C

The work of an IT support department doesn’t have an end date—it’s not temporary. That’s why it’s
not a project. Now, if that support team had to work over the weekend to move the data center to a
new location, then that would be a project!

I see—so even when
something is a process and
not a project, there could
be projects related to it.

7. Answer: B
Agile development is a really good example of an iterative approach to project phases. In an Agile
project, the team will typically break down the project into phases, where they work on the current
phase while planning out the next one.

84   Chapter 3
Download at Boykma.Com
Answers

the process framework

Exam Questions
8. Answer: B

If there’s an increased risk of a project because one phase can’t start until another one ends, that means your project
phases aren’t overlapping. When you’ve got overlapping phases, that means that you typically have multiple teams
that start their phases independently of each other.
Also, take another look at answer C, because it’s an important point about overlapping phases. When your
phases have an overlapping relationship, there’s an increased risk of rework. This typically happens when one
team delivers the results of their project, but made assumptions about what another team is doing as part of their
phase. When that other team delivers their work, it turns out that the results that both teams produced aren’t quite
compatible with each other, and now both teams have to go back and rework their designs. This happens a lot
when your phases overlap, which is why overlapping phases have an increased risk of rework.

9. Answer: D
In a projectized organization, the project manager has the power to assign tasks, manage the budget, and release the
team.
10. Answer: D
In a weak matrix, project managers have very limited authority. They have to share a lot of responsibility with
functional managers, and those functional managers have a lot of leeway to make decisions about how the team
members are managed. In an organization like that, the project manager isn’t given a lot of responsibility.

likely to
That’s why you’re pediter
find a project ex
in a weak matrix.

you are here 4   85
Download at Boykma.Com

Mais conteúdo relacionado

Mais procurados

Mais procurados (20)

07 pmp cost management exam
07 pmp cost management exam07 pmp cost management exam
07 pmp cost management exam
 
1
11
1
 
04 pmp integration management exam
04 pmp integration management exam04 pmp integration management exam
04 pmp integration management exam
 
04 pmp integration management exam
04 pmp integration management exam04 pmp integration management exam
04 pmp integration management exam
 
06 pmp time management exam
06 pmp time  management exam06 pmp time  management exam
06 pmp time management exam
 
08 pmp quality management exam
08 pmp quality management exam08 pmp quality management exam
08 pmp quality management exam
 
11 pmp risk management exam
11 pmp risk management exam11 pmp risk management exam
11 pmp risk management exam
 
12 pmp procurement management exam
12 pmp procurement management exam12 pmp procurement management exam
12 pmp procurement management exam
 
05 pmp scope management exam
05 pmp scope management exam05 pmp scope management exam
05 pmp scope management exam
 
01 pmp introduct to project management exam
01 pmp introduct to project management exam01 pmp introduct to project management exam
01 pmp introduct to project management exam
 
Pmp exam q&a
Pmp exam q&aPmp exam q&a
Pmp exam q&a
 
13 pmp professional responsibility exam
13 pmp professional responsibility exam13 pmp professional responsibility exam
13 pmp professional responsibility exam
 
Pmp6
Pmp6Pmp6
Pmp6
 
150 PMP Questions
150 PMP Questions 150 PMP Questions
150 PMP Questions
 
Pmp Questions Complete
Pmp Questions CompletePmp Questions Complete
Pmp Questions Complete
 
Pmp test 02
Pmp test 02Pmp test 02
Pmp test 02
 
02 pmp project life cycle exam
02 pmp project life cycle exam02 pmp project life cycle exam
02 pmp project life cycle exam
 
Pmp sample questions
Pmp sample questionsPmp sample questions
Pmp sample questions
 
Pmi sp questions with answers
Pmi sp questions with answersPmi sp questions with answers
Pmi sp questions with answers
 
PMP Exam Sample Questions 4
PMP Exam Sample Questions 4PMP Exam Sample Questions 4
PMP Exam Sample Questions 4
 

Destaque

175 pmp sample_questions
175 pmp sample_questions175 pmp sample_questions
175 pmp sample_questionsNazakat Hussain
 
La nouvelle certification Portfolio Management Professional (PfMP)
La nouvelle certification Portfolio Management Professional (PfMP)La nouvelle certification Portfolio Management Professional (PfMP)
La nouvelle certification Portfolio Management Professional (PfMP)PMI-Montréal
 
Jamil Hassan, PMP lessons learned.
Jamil Hassan, PMP lessons learned.Jamil Hassan, PMP lessons learned.
Jamil Hassan, PMP lessons learned.Jamil Faraj , PMP
 
Le chef de projet et le business analyste
Le chef de projet et le business analysteLe chef de projet et le business analyste
Le chef de projet et le business analysteMarc Bonnemains
 
Présentation standards 2015 04-02
Présentation standards 2015 04-02Présentation standards 2015 04-02
Présentation standards 2015 04-02Dirdop
 
Pmp : management des parties prenantes
Pmp : management des parties prenantesPmp : management des parties prenantes
Pmp : management des parties prenantesHassan EL ALLOUSSI
 
Certification PMP - Retour d'Expérience en 12 points (Lessons Learned in French)
Certification PMP - Retour d'Expérience en 12 points (Lessons Learned in French)Certification PMP - Retour d'Expérience en 12 points (Lessons Learned in French)
Certification PMP - Retour d'Expérience en 12 points (Lessons Learned in French)Latyr Jean-Luc FAYE
 

Destaque (11)

175 pmp sample_questions
175 pmp sample_questions175 pmp sample_questions
175 pmp sample_questions
 
2
22
2
 
La nouvelle certification Portfolio Management Professional (PfMP)
La nouvelle certification Portfolio Management Professional (PfMP)La nouvelle certification Portfolio Management Professional (PfMP)
La nouvelle certification Portfolio Management Professional (PfMP)
 
Jamil Hassan, PMP lessons learned.
Jamil Hassan, PMP lessons learned.Jamil Hassan, PMP lessons learned.
Jamil Hassan, PMP lessons learned.
 
Le chef de projet et le business analyste
Le chef de projet et le business analysteLe chef de projet et le business analyste
Le chef de projet et le business analyste
 
Jamil faraj hassan CV
Jamil faraj hassan CVJamil faraj hassan CV
Jamil faraj hassan CV
 
Présentation standards 2015 04-02
Présentation standards 2015 04-02Présentation standards 2015 04-02
Présentation standards 2015 04-02
 
Pmp : management des parties prenantes
Pmp : management des parties prenantesPmp : management des parties prenantes
Pmp : management des parties prenantes
 
Certification PMP - Retour d'Expérience en 12 points (Lessons Learned in French)
Certification PMP - Retour d'Expérience en 12 points (Lessons Learned in French)Certification PMP - Retour d'Expérience en 12 points (Lessons Learned in French)
Certification PMP - Retour d'Expérience en 12 points (Lessons Learned in French)
 
Chap 2 Organization Strategy
Chap 2 Organization StrategyChap 2 Organization Strategy
Chap 2 Organization Strategy
 
Enactus ensem 01 dec13
Enactus ensem  01 dec13Enactus ensem  01 dec13
Enactus ensem 01 dec13
 

Semelhante a Pmp3

Chapter 2 Questionsand Answers1. There is a difference between t.docx
Chapter 2 Questionsand Answers1. There is a difference between t.docxChapter 2 Questionsand Answers1. There is a difference between t.docx
Chapter 2 Questionsand Answers1. There is a difference between t.docxwalterl4
 
Risk 2 simplelearn-exam1-ans
Risk 2 simplelearn-exam1-ansRisk 2 simplelearn-exam1-ans
Risk 2 simplelearn-exam1-ansMohamed Saeed
 
Project Management Professional (PMP) | Lesson 02 | Project Management Framework
Project Management Professional (PMP) | Lesson 02 | Project Management FrameworkProject Management Professional (PMP) | Lesson 02 | Project Management Framework
Project Management Professional (PMP) | Lesson 02 | Project Management FrameworkD10iT
 
2009 Top Ten Obstacles To Project Success
2009 Top Ten Obstacles To Project Success2009 Top Ten Obstacles To Project Success
2009 Top Ten Obstacles To Project SuccessLou Gasco
 
PMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdfPMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdfProject Cubicle
 
PMP Certification Training Course Part-64
PMP Certification Training Course Part-64PMP Certification Training Course Part-64
PMP Certification Training Course Part-64Skillogic Solutions
 
1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docxjackiewalcutt
 
questions-just-that.pdf.civil engineering
questions-just-that.pdf.civil engineeringquestions-just-that.pdf.civil engineering
questions-just-that.pdf.civil engineeringmocr84810
 
PMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfPMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfMoncefMakni1
 

Semelhante a Pmp3 (20)

PgMP
PgMP PgMP
PgMP
 
Chapter 2 Questionsand Answers1. There is a difference between t.docx
Chapter 2 Questionsand Answers1. There is a difference between t.docxChapter 2 Questionsand Answers1. There is a difference between t.docx
Chapter 2 Questionsand Answers1. There is a difference between t.docx
 
Risk 2 simplelearn-exam1-ans
Risk 2 simplelearn-exam1-ansRisk 2 simplelearn-exam1-ans
Risk 2 simplelearn-exam1-ans
 
PMP Exam Q & A
PMP Exam Q & APMP Exam Q & A
PMP Exam Q & A
 
Project Management Professional (PMP) | Lesson 02 | Project Management Framework
Project Management Professional (PMP) | Lesson 02 | Project Management FrameworkProject Management Professional (PMP) | Lesson 02 | Project Management Framework
Project Management Professional (PMP) | Lesson 02 | Project Management Framework
 
PMP Exam Sample Questions
PMP Exam Sample QuestionsPMP Exam Sample Questions
PMP Exam Sample Questions
 
Free PMP Exam Sample Question
Free PMP Exam Sample QuestionFree PMP Exam Sample Question
Free PMP Exam Sample Question
 
PMP® Sample Questions
PMP® Sample QuestionsPMP® Sample Questions
PMP® Sample Questions
 
PMP Sample Questions Set 3
PMP Sample Questions Set 3PMP Sample Questions Set 3
PMP Sample Questions Set 3
 
CAPM Study Session 2
CAPM Study Session 2CAPM Study Session 2
CAPM Study Session 2
 
Pmp test 03
Pmp test 03Pmp test 03
Pmp test 03
 
15 Free PMP Exam Questions
15 Free PMP Exam Questions15 Free PMP Exam Questions
15 Free PMP Exam Questions
 
2009 Top Ten Obstacles To Project Success
2009 Top Ten Obstacles To Project Success2009 Top Ten Obstacles To Project Success
2009 Top Ten Obstacles To Project Success
 
PMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdfPMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdf
 
PMP® Sample Questions 5
PMP® Sample Questions 5PMP® Sample Questions 5
PMP® Sample Questions 5
 
PMP Five Sample Questions - 3
PMP Five Sample Questions - 3PMP Five Sample Questions - 3
PMP Five Sample Questions - 3
 
PMP Certification Training Course Part-64
PMP Certification Training Course Part-64PMP Certification Training Course Part-64
PMP Certification Training Course Part-64
 
1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx
 
questions-just-that.pdf.civil engineering
questions-just-that.pdf.civil engineeringquestions-just-that.pdf.civil engineering
questions-just-that.pdf.civil engineering
 
PMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfPMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdf
 

Mais de Jamil Faraj , PMP

Mais de Jamil Faraj , PMP (8)

Corona-virus PMP study plan
Corona-virus PMP study planCorona-virus PMP study plan
Corona-virus PMP study plan
 
PMP Study Plan by Jamil Faraj, PMP
PMP Study Plan by Jamil Faraj, PMPPMP Study Plan by Jamil Faraj, PMP
PMP Study Plan by Jamil Faraj, PMP
 
Jamil Faraj CV 2020
Jamil Faraj CV 2020Jamil Faraj CV 2020
Jamil Faraj CV 2020
 
PMP ITTOs Quick Review
PMP ITTOs Quick Review PMP ITTOs Quick Review
PMP ITTOs Quick Review
 
Jamil pmp Certificate 2020
Jamil pmp Certificate 2020Jamil pmp Certificate 2020
Jamil pmp Certificate 2020
 
Jamil Faraj CV- English
Jamil Faraj CV- EnglishJamil Faraj CV- English
Jamil Faraj CV- English
 
Pmp Formula Pocket_Guide
Pmp Formula Pocket_GuidePmp Formula Pocket_Guide
Pmp Formula Pocket_Guide
 
دورة وظيفة العمر
دورة وظيفة العمردورة وظيفة العمر
دورة وظيفة العمر
 

Último

Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...Sapna Thakur
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfagholdier
 
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...PsychoTech Services
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxVishalSingh1417
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 
Disha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfDisha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfchloefrazer622
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...fonyou31
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhikauryashika82
 

Último (20)

Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
Advance Mobile Application Development class 07
Advance Mobile Application Development class 07Advance Mobile Application Development class 07
Advance Mobile Application Development class 07
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
Disha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfDisha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdf
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 

Pmp3

  • 1. the process framework Exam Questions 1. You’re a project manager working on a software engineering project. The programmers have started building the software, and the testers have started to create the test environment. Which process group includes these activities? A. B. C. D. Initiating Planning Executing Closing 2. Which of the following is not a stakeholder? A. B. C. D. The project manager who is responsible for building the project A project team member who will work on the project A customer who will use the final product A competitor whose company will lose business because of the product 3. A project manager runs into a problem with her project’s contractors, and she isn’t sure if they’re abiding by the terms of the contract. Which knowledge area is the BEST source of processes to help her deal with this problem? A. B. C. D. Cost Management Risk Management Procurement Management Communications Management 4. You’re a project manager for a construction project. You’ve just finished creating a list of all of the people who will be directly affected by the project. What process group are you in? A. B. C. D. Initiating Planning Executing Monitoring & Controlling 5. Which process group contains the Develop Project Charter process and the Identify Stakeholders process? A. B. C. D. Initiating Executing Monitoring and Controlling Closing you are here 4   81 Download at Boykma.Com
  • 2. exam questions Exam Questions 6. Which of the following is NOT a project? A. B. C. D. Repairing a car Building a highway overpass Running an IT support department Filming a motion picture 7. A project manager is running a software project that is supposed to be delivered in phases. She was planning on dividing the resources into two separate teams to do the work for two phases at the same time, but one of her senior developers suggested that she use an Agile methodology instead, and she agrees. Which of the following BEST describes the relationship between her project’s phases? A. B. C. D. Sequential relationship Iterative relationship Constrained relationship Overlapping relationship 8. Which of the following is NOT true about overlapping phases? A. B. C. D. Each phase is typically done by a separate team There’s an increased risk of delays when a later phase can’t start until an earlier one ends There’s an increased risk to the project due to potential for rework Every phase must go through all five process groups 9. You’re the project manager for an industrial design project. Your team members report to you, and you’re responsible for creating the budget, building the schedule, and assigning the tasks. When the project is complete, you release the team so they can work on other projects for the company. What kind of organization do you work in? A. B. C. D. Functional Weak matrix Strong matrix Projectized 10. You’re a project manager working in a weak matrix organization. Which of the following is NOT true? A. B. C. D. Your team members report to functional managers You are not in directly charge of resources Functional managers make decisions that can affect your projects You have sole responsibility for the success or failure of the project 82   Chapter 3 Download at Boykma.Com
  • 3. Answers the process framework Exam Questions 1. Answer: C The Executing process group is the one where the team does all the work. You’ll get a good feel for the process groups pretty quickly! 2. Answer: D One of the hardest things that a project manager has to do on a project is figure out who all the stakeholders are. The project manager, the team, the sponsor (or client), the customers and people who will use the software, the senior managers at the company—they’re all stakeholders. Competitors aren’t stakeholders, because even though they’re affected by the project, they don’t actually have any direct influence over it. 3. Answer: C The Procurement Management knowledge area deals with contracts, contractors, buyers and sellers. If you’ve got a question about a type of contract or how to deal with contract problems, you’re being asked about a Procurement Management process. 4. Answer: A People who will be directly affected by the project are stakeholders, and when you’re creating a list of them you’re performing the Identify Stakeholders process. That’s one of the two processes in the Initiating process group. 5. Answer: A The first things that are created on a project are the charter (which you create in the Develop Project Charter process) and the Stakeholder Register (which you create in the Identify Stakeholders process). You do those things when you’re initiating the project. you are here 4   83 Download at Boykma.Com
  • 4. exam answers Answers Exam Questions 6. Answer: C The work of an IT support department doesn’t have an end date—it’s not temporary. That’s why it’s not a project. Now, if that support team had to work over the weekend to move the data center to a new location, then that would be a project! I see—so even when something is a process and not a project, there could be projects related to it. 7. Answer: B Agile development is a really good example of an iterative approach to project phases. In an Agile project, the team will typically break down the project into phases, where they work on the current phase while planning out the next one. 84   Chapter 3 Download at Boykma.Com
  • 5. Answers the process framework Exam Questions 8. Answer: B If there’s an increased risk of a project because one phase can’t start until another one ends, that means your project phases aren’t overlapping. When you’ve got overlapping phases, that means that you typically have multiple teams that start their phases independently of each other. Also, take another look at answer C, because it’s an important point about overlapping phases. When your phases have an overlapping relationship, there’s an increased risk of rework. This typically happens when one team delivers the results of their project, but made assumptions about what another team is doing as part of their phase. When that other team delivers their work, it turns out that the results that both teams produced aren’t quite compatible with each other, and now both teams have to go back and rework their designs. This happens a lot when your phases overlap, which is why overlapping phases have an increased risk of rework. 9. Answer: D In a projectized organization, the project manager has the power to assign tasks, manage the budget, and release the team. 10. Answer: D In a weak matrix, project managers have very limited authority. They have to share a lot of responsibility with functional managers, and those functional managers have a lot of leeway to make decisions about how the team members are managed. In an organization like that, the project manager isn’t given a lot of responsibility. likely to That’s why you’re pediter find a project ex in a weak matrix. you are here 4   85 Download at Boykma.Com