time management
Exam Questions
1. You’re managing a project, when your client tells you that an external problem happened, and
now you have to meet an earlier deadline. Your supervisor heard that in a situation like this, you
can use schedule compression by either crashing or fast-tracking the schedule, but he’s not sure
which is which. What do you tell him?
Crashing the project adds risk, whileA.	 fast-tracking adds cost
When youB.	 crash a project, it always shortens the total duration of the project
Crashing the project adds cost, while fast-tracking adds riskC.	
When you fast-track a project, it always shortens the total duration of the projectD.	
2. Given this portion of the network diagram to the right, what’s the ES of activity F?
9A.	
10B.	
12C.	
13D.	
3. Given this portion of the network
diagram to the right, what’s the LF of activity F?
10A.	
11B.	
16C.	
17D.	
4. You are managing a software project. Your QA manager tells you that you need to plan to have
her team start their test planning activity so that it finishes just before testing begins. But other
than that, she says it can start as late in the project as necessary. What’s the relationship between
the test planning activity and the testing activity?
Start-to-Start (SS)A.	
Start-to-finish (SF)B.	
Finish-to-Start (FS)C.	
Finish-to-Finish (FF)D.	
5. You’re managing an industrial design project. You’ve come up with the complete activity list,
created network diagrams, assigned resources to each activity, and estimated their durations.
What’s the next thing that you do?
Use Rolling Wave Planning to compensate for the fact that you don’t have complete informationA.	
Create the scheduleB.	
Consult the project scope statement and performC.	 Sequence Activities
Use fast-tracking to reduce the total durationD.	
D
ES = 7 EF = 9
LS = 3 LF = 4
G
ES = 17 EF = 26
LS = 17 LF = 26
H
ES = 17 EF = 19
LS = 11 LF = 13
E
ES = 10 EF = 12
LS = 3 LF = 4
F
...
...
...
...
Download at Boykma.Com
312   Chapter 6
6. Which of the following is NOT an input to Develop Schedule?
Activity listA.	
Project schedule network diagramsB.	
Resource calendarsC.	
Schedule baselineD.	
7. Three members of your project team want to pad their estimates because they believe there are certain
risks that might materialize. What is the BEST way to handle this situation?
Estimate the activities honestly, and then use aA.	 contingency reserve to cover any unexpected costs
Allow more time for the work by adding aB.	 buffer to every activity in the schedule
Tell the team members not to worry about it, and if the schedule is wrong it’s okay for the project to be lateC.	
Crash the scheduleD.	
8. Which of the following tools is used for adding buffers to a schedule?
Three-point estimatesA.	
B.	 Critical chain method
Expert judgmentC.	
Critical path analysisD.	
9. What is the critical path in the activity list to the right?
Start-A-B-C-FinishA.	
Start-A-D-E-F-FinishB.	
Start-G-H-I-J-FinishC.	
Start-A-B-J-FinishD.	
10. What is the float for activity F in the activity list to the right?
0A.	
7B.	
8C.	
10D.	
11. You’re managing an interior decoration project, when you find out that you need to get it done earlier than
originally planned. You decide to fast-track the project. This means:
Starting the project sooner and working overtimeA.	
Assigning more people to the tasks at a greater total cost, especially for activities on the critical pathB.	
Starting activities earlier and overlapping them more, which will cost more and could add risksC.	
Shortening the durations of the activities and asking people to work overtime to accommodate that.D.	
Name Predecessor Duration
Start — —
A Start 6
B A 4
C B 8
D A 1
E D 1
F E 2
G Start 3
H G 3
I H 2
J B, I 3
Finish F, J, C —
exam questions
Exam Questions
Download at Boykma.Com
you are here 4   313
time management
12. Slack is a synonym for:
FloatA.	
LagB.	
BufferC.	
ReserveD.	
13. You’re managing a construction project. You’ve decomposed work packages into activities, and
your client needs a duration estimate for each activity that you come up with. Which of the following
will you use for this?
Milestone listA.	
Activity listB.	
Critical path analysisC.	
Project schedule network diagramD.	
14. What’s the correct order of the Time Management planning processes?
A.	 Sequence Activities, Define Activities, Estimate Activity Resources, Estimate Activity Durations,
Develop Schedule
Define Activities, Sequence Activities, Develop Schedule, Estimate Activity Resources, EstimateB.	
Activity Durations
Define Activities, Sequence Activities, Estimate Activity Resources, Estimate Activity Durations,C.	
Develop Schedule
D.	 Develop Schedule, Define Activities, Sequence Activities, Estimate Activity Resources, Estimate
Activity Durations
15. Which of the following is NOT a tool or technique used in Estimate Activity Durations?
SWAG EstimationA.	
Parametric EstimationB.	
Analogous EstimationC.	
Three-Point EstimationD.	
16. You’re managing a project to build a new project management information system. You work with
the team to come up with an estimate of 27 weeks. In the best case, this could be shortened by two
weeks because you can reuse a previous component. But there’s a risk that a vendor delay could cause
the project to be delayed by five weeks. Use PERT to calculate a three-point estimate for this project.
A.	 25.83 weeks
26 weeksB.	
27.5 weeksC.	
28.3 weeksD.	
Exam Questions
Download at Boykma.Com
314   Chapter 6
Exam Questions
17. Given the network diagram below, what’s the critical path?
Start-A-B-C-EndA.	
Start-A-D-G-EndB.	
Start-E-D-C-EndC.	
Start-E-F-G-EndD.	
18. For that same network diagram below, what’s the float for activity A?
0 weeksA.	
1 weekB.	
2 weeksC.	
4 weeksD.	
19. For that same network diagram below, what’s the float for activity E?
0 weeksA.	
1 weekB.	
2 weeksC.	
4 weeksD.	
exam questions
Start
End
A
B
D
C
E
G
4
3
6
2
8
1
F
1
Download at Boykma.Com
you are here 4   315
time management
Exam Questions
20. You’re managing a software project, when your customer informs you that a schedule change is
necessary. Which is the BEST thing to do?
Consult the schedule management planA.	
Notify the team and the sponsor that there’s going to be a schedule changeB.	
Influence the factors that cause changeC.	
Refuse to make the change because there’s already a schedule baselineD.	
21. Your company has previously run other projects similar to the one you’re currently managing. What is
the BEST way to use that information?
Check the organizational process assets for lessons learned and other information about the past projectsA.	
Use parametric estimation to estimate your project based on past projects’ performanceB.	
Start from scratch because you don’t want mistakes from past projects to influence youC.	
Reuse the project management plan from a past projectD.	
22. You’re planning the schedule for a highway construction project, but the final date you came up with
will run into the next budget year. The state comes up with capital from a reserve fund, and now you can
increase the budget for your resources. What’s the BEST way to compress the schedule?
Go back to your three-point estimates and use the most optimistic onesA.	
Use the extra budget to increase yourB.	 contingency reserve
Hire more experts to use expert judgment so your estimates are more accurateC.	
Crash the scheduleD.	
23. You’re managing a software project. You’ve created the schedule, and you need to figure out which
activities absolutely cannot slip. You’ve done critical path analysis, identifying the critical path and
calculating the early start and early finish for each activity. Which activities cannot slip without making the
project late?
The ones with the biggest difference between ES and LFA.	
The activities on the critical pathB.	
The activity with the mostC.	 lag
The last activity in the project, because it has no floatD.	
24. You’re managing a construction project. You’ve decomposed work packages into activities, and your
client needs a duration estimate for each activity that you came up with. Which of the following BEST
describes what you are doing?
Evaluating each activity to figure out how much effort it will takeA.	
Estimating the number of person-hours that will be required for each activityB.	
Understanding, in calendar time, how long each activity will takeC.	
Estimating how many people it will take to perform each activityD.	
Download at Boykma.Com
316   Chapter 6
Exam Questions
Answers
1. Answer: C
You’ll definitely get some questions that ask you about crashing and fast-tracking, and it’s important to know
the difference between them. When you crash the project, it means that you add resources to it, especially
to the critical path. There’s no real risk in doing that—in the worst-case scenario, the extra people just sit
around!—but it does cost more. Fast-tracking means adjusting the schedule so that activities overlap. The
same resources are doing the work, so it’s not going to cost more, but it’s definitely riskier, because now
you’ve eliminated buffers and possibly broken some dependencies! And remember that crashing or fast-
tracking won’t always work to make the project go faster!
2. Answer: D
Calculating the early start (ES) of an activity isn’t hard. All you need to do is look at the early finish (EF) of the
previous activity and add one. If there’s more than one predecessor, then you take the largest EF and add one.
In this case, the predecessors to activity F are D, with an EF of 9, and E, with an EF of 12. So the ES of F is
12 + 1 = 13.
3. Answer: A
It’s just as easy to calculate the late finish (LF). Look at the following activity, take its LS (late start), and
subtract one. If there’s more than one following activity, use the one with the lowest LS. So for activity F in the
question, the following activities are G, with an LS of 17, and H, with an LS of 11. So the LF of F is 11 - 1 = 10.
4. Answer: C
Don’t let the jargon fool you! You don’t need to know anything about software testing to answer this question.
When you have two activities, and the first activity has to be timed so that it finishes before the second one
starts, then you’ve got a Finish-to-Start relationship, or FS.
5. Answer: B
This is a Which-is-next question that describes a project that’s completed the Define Activities, Sequence
Activities, Estimate Activity Resources, and Estimate Activity Durations processes. The next process in Time
Management is Develop Schedule, which means that the next thing you do is create the schedule!
Did answer A trick you? No need for
rolling wave planning when you’ve got
enough info to define all the activities!
exam answers
Download at Boykma.Com
you are here 4   317
time management
Exam Questions
Answers
6. Answer: D
The schedule baseline is an output of the Develop Schedule process, not an input. You should definitely
know what goes into the schedule baseline: it’s a specific version of the schedule that you set aside and
use for comparison later on, when you want to know if the project is running late.
7. Answer: A
You always want to be honest with your estimates. Every project has unknowns and risks, and there’s no
way to estimate any activity exactly! Luckily, we have tools to deal with this. You can use reserve analysis,
a tool of Estimate Activity Durations, to come up with a contingency reserve that you can use to plan for
these risks.
8. Answer: B
Critical chain method is a technique that’s part of Develop Schedule that lets you figure out how to handle
the problems that come with having limited resources. You use it to shuffle both activities and resources
on your critical path. One important aspect of the critical chain method is that you can use it to add buffers
to the schedule to reduce the risk of certain activities.
9. Answer: A
When you draw out a network diagram for the activities in the table, you end up with four paths. And you
definitely should draw out the activity diagram for a question like this! You’re allowed to use scratch paper
on the exam, and this is one place where you should definitely do it. Of the four paths, only one has the
longest duration: Start‑A‑B‑C‑Finish, which has a duration of 6+ 4 + 8 = 18. That’s the critical path.
I get it—we can use the
schedule baseline the same way that we
use the scope baseline! We take a snapshot
of it and then save it, so we can compare the
project’s performance against it later!
Download at Boykma.Com
318   Chapter 6
10. Answer: C
Activity F is in the path Start-A-D-E-F-Finish. This path has a duration of 6 + 1 + 1 + 2 = 10. The float of
an activity is the longest time it can slip before it affects the critical path. In this case, activity F can slip by
8 without causing the path that it’s on to go beyond the critical path. But any more than that, and its path
becomes the new critical path!
11. Answer: C
This is the definition of fast-tracking, and you’re probably getting the hang of this one by now. You may get
a question like this, but you’ll almost certainly see fast-tracking as an incorrect answer to several questions!
12. Answer: A
Remember that when you see “slack,” it’s the same thing as float. Either term could appear on the exam!
13. Answer: B
This question is asking about the Estimate Activity Durations process. Take a look at the answers—there’s
only one answer that’s used in that process: you need to start with the activity list in order to do the
estimates for the activities! The other answers are things that are inputs, tools, or techniques for other
processes.
14. Answer: C
It’s not hard to remember the order in which the Time Management processes are performed. If you use
a little common sense, you can reason your way through a question like this. You need to define your
activities before you can sequence them, you need to know who’s going to be doing an activity before you
can estimate how long it’s going to take, and you need to do all of that before you can build a schedule!
15. Answer: A
You’ll have to know the different kinds of estimating techniques for the exam. You don’t necessarily have
to be good at doing them, but you should recognize which are which. Parametric estimating is when you
plug values into a formula, program, or spreadsheet and get an estimate. Analogous estimating uses
similar activities from past projects to calculate new estimates. Three-point estimating uses an optimistic,
pessimistic, and realistic estimate.
Exam Questions
Answers
Did you notice answer A? Don’t forget
that the float of any activity in the
critical path is zero!
When a question asks what you’d use for a process,it’s asking you to pick an input, tool, or techniquethat’s part of the process.
exam answers
Control Schedule isn’t included in the list of proceses
because if a schedule change happens, you’ll have to
go back and revisit the other Time Management
processes. So it doesn’t have a specific order!
Download at Boykma.Com
you are here 4   319
time management
Exam Questions
Answers
16. Answer: C
This question is asking you to apply the PERT three-point estimation formula: (Optimistic Time + 4 x Most Likely
Time + Pessimistic Time) ÷ 6. When a question gives you these values directly, it’s easy. But in this case, to
answer the question you had to figure out the values for the Optimistic Time and Pessimistic Time, which meant
that you needed to look at the assumptions that the team was making. The most likely time was given: 27 weeks.
The best case scenario would come in two weeks earlier, at 25 weeks, and the worst case would come in five
weeks late, at 32 weeks. So the estimate is (25 weeks + 4 x (27 weeks) + 32 weeks) ÷ 6 = 27.5 weeks.
17. Answer: C
The path Start-E-D-C-End has a duration of 8 + 2 + 4 = 14, which is the longest total duration in the entire network.
18. Answer: B
Activity A is on three different paths: Start-A-B-C-End (13), Start-A-D-C-End (12), and Start-A-D-G-End (9). To
calculate its float, you take the longest path’s length and subtract it from the lenth of the critical path: 14 - 13 = 1.
19. Answer: A
Since activity E is on the critical path, its float is zero, because the float of any activity on the critical path is zero.
20. Answer: A
The schedule management plan tells you how changes to the schedule are to be handled. Any time there’s a
change, the first thing you should do is consult the plan to see how it should be handled.
It looks like there will be a
bunch of questions on the
critical path method! It’s a
good thing I’ve got so much
practice with it.
Sometimes you’ll get a question about
applying a formula, but you’ll need
to read the text in the question to
figure out all of the variables
Can you think of how a question
might quiz you on this information
without actually asking you to look
at a network diagram?
Download at Boykma.Com
320   Chapter 6
21. Answer: A
The organizational process assets contain historical information about past projects. When you write up your
lessons learned, or create work performance information, you store it in your company’s organizational process
asset library! Also, did you notice that answer B was the wrong definition of parametric estimation?
22. Answer: D
Crashing the schedule is the form of schedule compression that increases cost. This is a difficult question
because all of the answers sound good, and one or two are a little misleading! Don’t fall into the trap of
choosing an answer because you recognize a valid tool or technique in it. Reserve analysis and three-point
estimates are very useful techniques, but they’re not the answer to this question.
23. Answer: B
The critical path is the path in the network diagram where any delay will cause a delay in the schedule. These
are the activities that cannot slip without making the project late!
24. Answer: C
This question was really about the definition of “duration,” and the key to answering it is to understand how
duration is different from effort. The correct answer talks about “calendar time,” which is what a duration is: it’s a
measurement (or estimate) of how long the activity will take in real life, taking into account the number of people
who will be doing the work, the availability of the people and other resources, everyone’s vacation time, time
taken away from the schedule because people are pulled off of the activity to work on higher priority activities,
and other real-world factors. That’s different from effort (which is often measured in person-hours), and it’s
different from resource estimating (which involves estimating how many people and what other resources will
be used for the activity).
Exam Questions
Answers
exam answers
Download at Boykma.Com

Mais conteúdo relacionado

Mais procurados (20)

05 pmp scope management exam
05 pmp scope management exam05 pmp scope management exam
05 pmp scope management exam
 
Exam1
Exam1Exam1
Exam1
 
11 pmp risk management exam
11 pmp risk management exam11 pmp risk management exam
11 pmp risk management exam
 
04 pmp integration management exam
04 pmp integration management exam04 pmp integration management exam
04 pmp integration management exam
 
1
11
1
 
Pmp5
Pmp5Pmp5
Pmp5
 
Pmp3
Pmp3Pmp3
Pmp3
 
Pmp6
Pmp6Pmp6
Pmp6
 
Pmp1
Pmp1Pmp1
Pmp1
 
01 pmp introduct to project management exam
01 pmp introduct to project management exam01 pmp introduct to project management exam
01 pmp introduct to project management exam
 
Pmp exam q&a
Pmp exam q&aPmp exam q&a
Pmp exam q&a
 
12 pmp procurement management exam
12 pmp procurement management exam12 pmp procurement management exam
12 pmp procurement management exam
 
150 PMP Questions
150 PMP Questions 150 PMP Questions
150 PMP Questions
 
02 pmp project life cycle exam
02 pmp project life cycle exam02 pmp project life cycle exam
02 pmp project life cycle exam
 
13 pmp professional responsibility exam
13 pmp professional responsibility exam13 pmp professional responsibility exam
13 pmp professional responsibility exam
 
Pmi sp questions with answers
Pmi sp questions with answersPmi sp questions with answers
Pmi sp questions with answers
 
Pmp test 02
Pmp test 02Pmp test 02
Pmp test 02
 
1440 pmp exam question bank
1440 pmp exam question bank1440 pmp exam question bank
1440 pmp exam question bank
 
Manajemen SDM Proyek
Manajemen SDM  ProyekManajemen SDM  Proyek
Manajemen SDM Proyek
 
Pmp test 04
Pmp test 04Pmp test 04
Pmp test 04
 

Destaque (10)

2
22
2
 
Jamil faraj hassan CV
Jamil faraj hassan CVJamil faraj hassan CV
Jamil faraj hassan CV
 
Scope part 1 day 1
Scope part 1 day 1 Scope part 1 day 1
Scope part 1 day 1
 
Jamil pmp Certificate 2020
Jamil pmp Certificate 2020Jamil pmp Certificate 2020
Jamil pmp Certificate 2020
 
Jamil Faraj CV- English
Jamil Faraj CV- EnglishJamil Faraj CV- English
Jamil Faraj CV- English
 
Jamil Hassan, PMP lessons learned.
Jamil Hassan, PMP lessons learned.Jamil Hassan, PMP lessons learned.
Jamil Hassan, PMP lessons learned.
 
Pmp Formula Pocket_Guide
Pmp Formula Pocket_GuidePmp Formula Pocket_Guide
Pmp Formula Pocket_Guide
 
Ch4 scheduling
Ch4 schedulingCh4 scheduling
Ch4 scheduling
 
Capm exam prep-questions_2010_ol
Capm exam prep-questions_2010_olCapm exam prep-questions_2010_ol
Capm exam prep-questions_2010_ol
 
Questions
QuestionsQuestions
Questions
 

Semelhante a 06 pmp time management exam

PMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docxPMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docxstilliegeorgiana
 
PertGanttchart
PertGanttchartPertGanttchart
PertGanttchartlearnt
 
PrintNetwork Diagrams and Resource UtilizationIntroduction B.docx
PrintNetwork Diagrams and Resource UtilizationIntroduction  B.docxPrintNetwork Diagrams and Resource UtilizationIntroduction  B.docx
PrintNetwork Diagrams and Resource UtilizationIntroduction B.docxChantellPantoja184
 
Critical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docxCritical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docxannettsparrow
 
PROJECT-ANALYSIS-TOOL-PPT.pptx
PROJECT-ANALYSIS-TOOL-PPT.pptxPROJECT-ANALYSIS-TOOL-PPT.pptx
PROJECT-ANALYSIS-TOOL-PPT.pptxPHOEBEANNEARTECHE1
 
1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docxjackiewalcutt
 
Chapter-5-Scheduling-and-Resource-Allocation.ppt
Chapter-5-Scheduling-and-Resource-Allocation.pptChapter-5-Scheduling-and-Resource-Allocation.ppt
Chapter-5-Scheduling-and-Resource-Allocation.pptTecnicoItca
 
L05 time management
L05 time managementL05 time management
L05 time managementAsa Chan
 
Resource-Allocation.ppt
Resource-Allocation.pptResource-Allocation.ppt
Resource-Allocation.pptTecnicoItca
 
Introduction to Project Management
Introduction to Project Management Introduction to Project Management
Introduction to Project Management Joshua Miranda
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)Debanjan15
 

Semelhante a 06 pmp time management exam (20)

PMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docxPMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docx
 
Session 5 gdas pmp study group presentation
Session 5   gdas pmp study group presentationSession 5   gdas pmp study group presentation
Session 5 gdas pmp study group presentation
 
CAPM Study Session 3
CAPM Study Session 3CAPM Study Session 3
CAPM Study Session 3
 
PertGanttchart
PertGanttchartPertGanttchart
PertGanttchart
 
PrintNetwork Diagrams and Resource UtilizationIntroduction B.docx
PrintNetwork Diagrams and Resource UtilizationIntroduction  B.docxPrintNetwork Diagrams and Resource UtilizationIntroduction  B.docx
PrintNetwork Diagrams and Resource UtilizationIntroduction B.docx
 
Self test engine PSP-PMI-SP
Self test engine PSP-PMI-SPSelf test engine PSP-PMI-SP
Self test engine PSP-PMI-SP
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
Pert Analysis
Pert AnalysisPert Analysis
Pert Analysis
 
Critical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docxCritical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docx
 
PROJECT-ANALYSIS-TOOL-PPT.pptx
PROJECT-ANALYSIS-TOOL-PPT.pptxPROJECT-ANALYSIS-TOOL-PPT.pptx
PROJECT-ANALYSIS-TOOL-PPT.pptx
 
1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx
 
Escaping the Waterfall: Reducing Risk with Agile Development with Scrum
Escaping the Waterfall: Reducing Risk with Agile Development with ScrumEscaping the Waterfall: Reducing Risk with Agile Development with Scrum
Escaping the Waterfall: Reducing Risk with Agile Development with Scrum
 
CAPM Exam Study Session 1
CAPM Exam Study Session 1CAPM Exam Study Session 1
CAPM Exam Study Session 1
 
Chapter-5-Scheduling-and-Resource-Allocation.ppt
Chapter-5-Scheduling-and-Resource-Allocation.pptChapter-5-Scheduling-and-Resource-Allocation.ppt
Chapter-5-Scheduling-and-Resource-Allocation.ppt
 
L05 time management
L05 time managementL05 time management
L05 time management
 
Resource-Allocation.ppt
Resource-Allocation.pptResource-Allocation.ppt
Resource-Allocation.ppt
 
Introduction to Project Management
Introduction to Project Management Introduction to Project Management
Introduction to Project Management
 
Introduction to schedule management
Introduction to schedule managementIntroduction to schedule management
Introduction to schedule management
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
 
Chap03
Chap03Chap03
Chap03
 

Último

How to refresh to be fit for the future world
How to refresh to be fit for the future worldHow to refresh to be fit for the future world
How to refresh to be fit for the future worldChris Skinner
 
Toyota Kata Coaching for Agile Teams & Transformations
Toyota Kata Coaching for Agile Teams & TransformationsToyota Kata Coaching for Agile Teams & Transformations
Toyota Kata Coaching for Agile Teams & TransformationsStefan Wolpers
 
LinkedIn Masterclass Techweek 2024 v4.1.pptx
LinkedIn Masterclass Techweek 2024 v4.1.pptxLinkedIn Masterclass Techweek 2024 v4.1.pptx
LinkedIn Masterclass Techweek 2024 v4.1.pptxSymbio Agency Ltd
 
Creative Ideas for Interactive Team Presentations
Creative Ideas for Interactive Team PresentationsCreative Ideas for Interactive Team Presentations
Creative Ideas for Interactive Team PresentationsSlidesAI
 
Global Internal Audit Standards 2024.pdf
Global Internal Audit Standards 2024.pdfGlobal Internal Audit Standards 2024.pdf
Global Internal Audit Standards 2024.pdfAmer Morgan
 
بروفايل شركة ميار الخليج للاستشارات الهندسية.pdf
بروفايل شركة ميار الخليج للاستشارات الهندسية.pdfبروفايل شركة ميار الخليج للاستشارات الهندسية.pdf
بروفايل شركة ميار الخليج للاستشارات الهندسية.pdfomnme1
 
zidauu _business communication.pptx /pdf
zidauu _business  communication.pptx /pdfzidauu _business  communication.pptx /pdf
zidauu _business communication.pptx /pdfzukhrafshabbir
 
1Q24_EN hyundai capital 1q performance
1Q24_EN   hyundai capital 1q performance1Q24_EN   hyundai capital 1q performance
1Q24_EN hyundai capital 1q performanceirhcs
 
8 Questions B2B Commercial Teams Can Ask To Help Product Discovery
8 Questions B2B Commercial Teams Can Ask To Help Product Discovery8 Questions B2B Commercial Teams Can Ask To Help Product Discovery
8 Questions B2B Commercial Teams Can Ask To Help Product DiscoveryDesmond Leo
 
Aptar Closures segment - Corporate Overview-India.pdf
Aptar Closures segment - Corporate Overview-India.pdfAptar Closures segment - Corporate Overview-India.pdf
Aptar Closures segment - Corporate Overview-India.pdfprchbhandari
 
HAL Financial Performance Analysis and Future Prospects
HAL Financial Performance Analysis and Future ProspectsHAL Financial Performance Analysis and Future Prospects
HAL Financial Performance Analysis and Future ProspectsRajesh Gupta
 
Powers and Functions of CPCB - The Water Act 1974.pdf
Powers and Functions of CPCB - The Water Act 1974.pdfPowers and Functions of CPCB - The Water Act 1974.pdf
Powers and Functions of CPCB - The Water Act 1974.pdflinciy03
 
What is paper chromatography, principal, procedure,types, diagram, advantages...
What is paper chromatography, principal, procedure,types, diagram, advantages...What is paper chromatography, principal, procedure,types, diagram, advantages...
What is paper chromatography, principal, procedure,types, diagram, advantages...srcw2322l101
 
stock price prediction using machine learning
stock price prediction using machine learningstock price prediction using machine learning
stock price prediction using machine learninggauravwankar27
 
Stages of Startup Funding - An Explainer
Stages of Startup Funding - An ExplainerStages of Startup Funding - An Explainer
Stages of Startup Funding - An ExplainerAlejandro Cremades
 
NewBase 17 May 2024 Energy News issue - 1725 by Khaled Al Awadi_compresse...
NewBase   17 May  2024  Energy News issue - 1725 by Khaled Al Awadi_compresse...NewBase   17 May  2024  Energy News issue - 1725 by Khaled Al Awadi_compresse...
NewBase 17 May 2024 Energy News issue - 1725 by Khaled Al Awadi_compresse...Khaled Al Awadi
 
Inside the Black Box of Venture Capital (VC)
Inside the Black Box of Venture Capital (VC)Inside the Black Box of Venture Capital (VC)
Inside the Black Box of Venture Capital (VC)Alejandro Cremades
 
Daftar Rumpun, Pohon, dan Cabang Ilmu (2024).pdf
Daftar Rumpun, Pohon, dan Cabang Ilmu (2024).pdfDaftar Rumpun, Pohon, dan Cabang Ilmu (2024).pdf
Daftar Rumpun, Pohon, dan Cabang Ilmu (2024).pdfAgusHalim9
 
Potato Flakes Manufacturing Plant Project Report.pdf
Potato Flakes Manufacturing Plant Project Report.pdfPotato Flakes Manufacturing Plant Project Report.pdf
Potato Flakes Manufacturing Plant Project Report.pdfhostl9518
 
TriStar Gold Corporate Presentation May 2024
TriStar Gold Corporate Presentation May 2024TriStar Gold Corporate Presentation May 2024
TriStar Gold Corporate Presentation May 2024Adnet Communications
 

Último (20)

How to refresh to be fit for the future world
How to refresh to be fit for the future worldHow to refresh to be fit for the future world
How to refresh to be fit for the future world
 
Toyota Kata Coaching for Agile Teams & Transformations
Toyota Kata Coaching for Agile Teams & TransformationsToyota Kata Coaching for Agile Teams & Transformations
Toyota Kata Coaching for Agile Teams & Transformations
 
LinkedIn Masterclass Techweek 2024 v4.1.pptx
LinkedIn Masterclass Techweek 2024 v4.1.pptxLinkedIn Masterclass Techweek 2024 v4.1.pptx
LinkedIn Masterclass Techweek 2024 v4.1.pptx
 
Creative Ideas for Interactive Team Presentations
Creative Ideas for Interactive Team PresentationsCreative Ideas for Interactive Team Presentations
Creative Ideas for Interactive Team Presentations
 
Global Internal Audit Standards 2024.pdf
Global Internal Audit Standards 2024.pdfGlobal Internal Audit Standards 2024.pdf
Global Internal Audit Standards 2024.pdf
 
بروفايل شركة ميار الخليج للاستشارات الهندسية.pdf
بروفايل شركة ميار الخليج للاستشارات الهندسية.pdfبروفايل شركة ميار الخليج للاستشارات الهندسية.pdf
بروفايل شركة ميار الخليج للاستشارات الهندسية.pdf
 
zidauu _business communication.pptx /pdf
zidauu _business  communication.pptx /pdfzidauu _business  communication.pptx /pdf
zidauu _business communication.pptx /pdf
 
1Q24_EN hyundai capital 1q performance
1Q24_EN   hyundai capital 1q performance1Q24_EN   hyundai capital 1q performance
1Q24_EN hyundai capital 1q performance
 
8 Questions B2B Commercial Teams Can Ask To Help Product Discovery
8 Questions B2B Commercial Teams Can Ask To Help Product Discovery8 Questions B2B Commercial Teams Can Ask To Help Product Discovery
8 Questions B2B Commercial Teams Can Ask To Help Product Discovery
 
Aptar Closures segment - Corporate Overview-India.pdf
Aptar Closures segment - Corporate Overview-India.pdfAptar Closures segment - Corporate Overview-India.pdf
Aptar Closures segment - Corporate Overview-India.pdf
 
HAL Financial Performance Analysis and Future Prospects
HAL Financial Performance Analysis and Future ProspectsHAL Financial Performance Analysis and Future Prospects
HAL Financial Performance Analysis and Future Prospects
 
Powers and Functions of CPCB - The Water Act 1974.pdf
Powers and Functions of CPCB - The Water Act 1974.pdfPowers and Functions of CPCB - The Water Act 1974.pdf
Powers and Functions of CPCB - The Water Act 1974.pdf
 
What is paper chromatography, principal, procedure,types, diagram, advantages...
What is paper chromatography, principal, procedure,types, diagram, advantages...What is paper chromatography, principal, procedure,types, diagram, advantages...
What is paper chromatography, principal, procedure,types, diagram, advantages...
 
stock price prediction using machine learning
stock price prediction using machine learningstock price prediction using machine learning
stock price prediction using machine learning
 
Stages of Startup Funding - An Explainer
Stages of Startup Funding - An ExplainerStages of Startup Funding - An Explainer
Stages of Startup Funding - An Explainer
 
NewBase 17 May 2024 Energy News issue - 1725 by Khaled Al Awadi_compresse...
NewBase   17 May  2024  Energy News issue - 1725 by Khaled Al Awadi_compresse...NewBase   17 May  2024  Energy News issue - 1725 by Khaled Al Awadi_compresse...
NewBase 17 May 2024 Energy News issue - 1725 by Khaled Al Awadi_compresse...
 
Inside the Black Box of Venture Capital (VC)
Inside the Black Box of Venture Capital (VC)Inside the Black Box of Venture Capital (VC)
Inside the Black Box of Venture Capital (VC)
 
Daftar Rumpun, Pohon, dan Cabang Ilmu (2024).pdf
Daftar Rumpun, Pohon, dan Cabang Ilmu (2024).pdfDaftar Rumpun, Pohon, dan Cabang Ilmu (2024).pdf
Daftar Rumpun, Pohon, dan Cabang Ilmu (2024).pdf
 
Potato Flakes Manufacturing Plant Project Report.pdf
Potato Flakes Manufacturing Plant Project Report.pdfPotato Flakes Manufacturing Plant Project Report.pdf
Potato Flakes Manufacturing Plant Project Report.pdf
 
TriStar Gold Corporate Presentation May 2024
TriStar Gold Corporate Presentation May 2024TriStar Gold Corporate Presentation May 2024
TriStar Gold Corporate Presentation May 2024
 

06 pmp time management exam

  • 1. you are here 4   311 time management Exam Questions 1. You’re managing a project, when your client tells you that an external problem happened, and now you have to meet an earlier deadline. Your supervisor heard that in a situation like this, you can use schedule compression by either crashing or fast-tracking the schedule, but he’s not sure which is which. What do you tell him? Crashing the project adds risk, whileA. fast-tracking adds cost When youB. crash a project, it always shortens the total duration of the project Crashing the project adds cost, while fast-tracking adds riskC. When you fast-track a project, it always shortens the total duration of the projectD. 2. Given this portion of the network diagram to the right, what’s the ES of activity F? 9A. 10B. 12C. 13D. 3. Given this portion of the network diagram to the right, what’s the LF of activity F? 10A. 11B. 16C. 17D. 4. You are managing a software project. Your QA manager tells you that you need to plan to have her team start their test planning activity so that it finishes just before testing begins. But other than that, she says it can start as late in the project as necessary. What’s the relationship between the test planning activity and the testing activity? Start-to-Start (SS)A. Start-to-finish (SF)B. Finish-to-Start (FS)C. Finish-to-Finish (FF)D. 5. You’re managing an industrial design project. You’ve come up with the complete activity list, created network diagrams, assigned resources to each activity, and estimated their durations. What’s the next thing that you do? Use Rolling Wave Planning to compensate for the fact that you don’t have complete informationA. Create the scheduleB. Consult the project scope statement and performC. Sequence Activities Use fast-tracking to reduce the total durationD. D ES = 7 EF = 9 LS = 3 LF = 4 G ES = 17 EF = 26 LS = 17 LF = 26 H ES = 17 EF = 19 LS = 11 LF = 13 E ES = 10 EF = 12 LS = 3 LF = 4 F ... ... ... ... Download at Boykma.Com
  • 2. 312   Chapter 6 6. Which of the following is NOT an input to Develop Schedule? Activity listA. Project schedule network diagramsB. Resource calendarsC. Schedule baselineD. 7. Three members of your project team want to pad their estimates because they believe there are certain risks that might materialize. What is the BEST way to handle this situation? Estimate the activities honestly, and then use aA. contingency reserve to cover any unexpected costs Allow more time for the work by adding aB. buffer to every activity in the schedule Tell the team members not to worry about it, and if the schedule is wrong it’s okay for the project to be lateC. Crash the scheduleD. 8. Which of the following tools is used for adding buffers to a schedule? Three-point estimatesA. B. Critical chain method Expert judgmentC. Critical path analysisD. 9. What is the critical path in the activity list to the right? Start-A-B-C-FinishA. Start-A-D-E-F-FinishB. Start-G-H-I-J-FinishC. Start-A-B-J-FinishD. 10. What is the float for activity F in the activity list to the right? 0A. 7B. 8C. 10D. 11. You’re managing an interior decoration project, when you find out that you need to get it done earlier than originally planned. You decide to fast-track the project. This means: Starting the project sooner and working overtimeA. Assigning more people to the tasks at a greater total cost, especially for activities on the critical pathB. Starting activities earlier and overlapping them more, which will cost more and could add risksC. Shortening the durations of the activities and asking people to work overtime to accommodate that.D. Name Predecessor Duration Start — — A Start 6 B A 4 C B 8 D A 1 E D 1 F E 2 G Start 3 H G 3 I H 2 J B, I 3 Finish F, J, C — exam questions Exam Questions Download at Boykma.Com
  • 3. you are here 4   313 time management 12. Slack is a synonym for: FloatA. LagB. BufferC. ReserveD. 13. You’re managing a construction project. You’ve decomposed work packages into activities, and your client needs a duration estimate for each activity that you come up with. Which of the following will you use for this? Milestone listA. Activity listB. Critical path analysisC. Project schedule network diagramD. 14. What’s the correct order of the Time Management planning processes? A. Sequence Activities, Define Activities, Estimate Activity Resources, Estimate Activity Durations, Develop Schedule Define Activities, Sequence Activities, Develop Schedule, Estimate Activity Resources, EstimateB. Activity Durations Define Activities, Sequence Activities, Estimate Activity Resources, Estimate Activity Durations,C. Develop Schedule D. Develop Schedule, Define Activities, Sequence Activities, Estimate Activity Resources, Estimate Activity Durations 15. Which of the following is NOT a tool or technique used in Estimate Activity Durations? SWAG EstimationA. Parametric EstimationB. Analogous EstimationC. Three-Point EstimationD. 16. You’re managing a project to build a new project management information system. You work with the team to come up with an estimate of 27 weeks. In the best case, this could be shortened by two weeks because you can reuse a previous component. But there’s a risk that a vendor delay could cause the project to be delayed by five weeks. Use PERT to calculate a three-point estimate for this project. A. 25.83 weeks 26 weeksB. 27.5 weeksC. 28.3 weeksD. Exam Questions Download at Boykma.Com
  • 4. 314   Chapter 6 Exam Questions 17. Given the network diagram below, what’s the critical path? Start-A-B-C-EndA. Start-A-D-G-EndB. Start-E-D-C-EndC. Start-E-F-G-EndD. 18. For that same network diagram below, what’s the float for activity A? 0 weeksA. 1 weekB. 2 weeksC. 4 weeksD. 19. For that same network diagram below, what’s the float for activity E? 0 weeksA. 1 weekB. 2 weeksC. 4 weeksD. exam questions Start End A B D C E G 4 3 6 2 8 1 F 1 Download at Boykma.Com
  • 5. you are here 4   315 time management Exam Questions 20. You’re managing a software project, when your customer informs you that a schedule change is necessary. Which is the BEST thing to do? Consult the schedule management planA. Notify the team and the sponsor that there’s going to be a schedule changeB. Influence the factors that cause changeC. Refuse to make the change because there’s already a schedule baselineD. 21. Your company has previously run other projects similar to the one you’re currently managing. What is the BEST way to use that information? Check the organizational process assets for lessons learned and other information about the past projectsA. Use parametric estimation to estimate your project based on past projects’ performanceB. Start from scratch because you don’t want mistakes from past projects to influence youC. Reuse the project management plan from a past projectD. 22. You’re planning the schedule for a highway construction project, but the final date you came up with will run into the next budget year. The state comes up with capital from a reserve fund, and now you can increase the budget for your resources. What’s the BEST way to compress the schedule? Go back to your three-point estimates and use the most optimistic onesA. Use the extra budget to increase yourB. contingency reserve Hire more experts to use expert judgment so your estimates are more accurateC. Crash the scheduleD. 23. You’re managing a software project. You’ve created the schedule, and you need to figure out which activities absolutely cannot slip. You’ve done critical path analysis, identifying the critical path and calculating the early start and early finish for each activity. Which activities cannot slip without making the project late? The ones with the biggest difference between ES and LFA. The activities on the critical pathB. The activity with the mostC. lag The last activity in the project, because it has no floatD. 24. You’re managing a construction project. You’ve decomposed work packages into activities, and your client needs a duration estimate for each activity that you came up with. Which of the following BEST describes what you are doing? Evaluating each activity to figure out how much effort it will takeA. Estimating the number of person-hours that will be required for each activityB. Understanding, in calendar time, how long each activity will takeC. Estimating how many people it will take to perform each activityD. Download at Boykma.Com
  • 6. 316   Chapter 6 Exam Questions Answers 1. Answer: C You’ll definitely get some questions that ask you about crashing and fast-tracking, and it’s important to know the difference between them. When you crash the project, it means that you add resources to it, especially to the critical path. There’s no real risk in doing that—in the worst-case scenario, the extra people just sit around!—but it does cost more. Fast-tracking means adjusting the schedule so that activities overlap. The same resources are doing the work, so it’s not going to cost more, but it’s definitely riskier, because now you’ve eliminated buffers and possibly broken some dependencies! And remember that crashing or fast- tracking won’t always work to make the project go faster! 2. Answer: D Calculating the early start (ES) of an activity isn’t hard. All you need to do is look at the early finish (EF) of the previous activity and add one. If there’s more than one predecessor, then you take the largest EF and add one. In this case, the predecessors to activity F are D, with an EF of 9, and E, with an EF of 12. So the ES of F is 12 + 1 = 13. 3. Answer: A It’s just as easy to calculate the late finish (LF). Look at the following activity, take its LS (late start), and subtract one. If there’s more than one following activity, use the one with the lowest LS. So for activity F in the question, the following activities are G, with an LS of 17, and H, with an LS of 11. So the LF of F is 11 - 1 = 10. 4. Answer: C Don’t let the jargon fool you! You don’t need to know anything about software testing to answer this question. When you have two activities, and the first activity has to be timed so that it finishes before the second one starts, then you’ve got a Finish-to-Start relationship, or FS. 5. Answer: B This is a Which-is-next question that describes a project that’s completed the Define Activities, Sequence Activities, Estimate Activity Resources, and Estimate Activity Durations processes. The next process in Time Management is Develop Schedule, which means that the next thing you do is create the schedule! Did answer A trick you? No need for rolling wave planning when you’ve got enough info to define all the activities! exam answers Download at Boykma.Com
  • 7. you are here 4   317 time management Exam Questions Answers 6. Answer: D The schedule baseline is an output of the Develop Schedule process, not an input. You should definitely know what goes into the schedule baseline: it’s a specific version of the schedule that you set aside and use for comparison later on, when you want to know if the project is running late. 7. Answer: A You always want to be honest with your estimates. Every project has unknowns and risks, and there’s no way to estimate any activity exactly! Luckily, we have tools to deal with this. You can use reserve analysis, a tool of Estimate Activity Durations, to come up with a contingency reserve that you can use to plan for these risks. 8. Answer: B Critical chain method is a technique that’s part of Develop Schedule that lets you figure out how to handle the problems that come with having limited resources. You use it to shuffle both activities and resources on your critical path. One important aspect of the critical chain method is that you can use it to add buffers to the schedule to reduce the risk of certain activities. 9. Answer: A When you draw out a network diagram for the activities in the table, you end up with four paths. And you definitely should draw out the activity diagram for a question like this! You’re allowed to use scratch paper on the exam, and this is one place where you should definitely do it. Of the four paths, only one has the longest duration: Start‑A‑B‑C‑Finish, which has a duration of 6+ 4 + 8 = 18. That’s the critical path. I get it—we can use the schedule baseline the same way that we use the scope baseline! We take a snapshot of it and then save it, so we can compare the project’s performance against it later! Download at Boykma.Com
  • 8. 318   Chapter 6 10. Answer: C Activity F is in the path Start-A-D-E-F-Finish. This path has a duration of 6 + 1 + 1 + 2 = 10. The float of an activity is the longest time it can slip before it affects the critical path. In this case, activity F can slip by 8 without causing the path that it’s on to go beyond the critical path. But any more than that, and its path becomes the new critical path! 11. Answer: C This is the definition of fast-tracking, and you’re probably getting the hang of this one by now. You may get a question like this, but you’ll almost certainly see fast-tracking as an incorrect answer to several questions! 12. Answer: A Remember that when you see “slack,” it’s the same thing as float. Either term could appear on the exam! 13. Answer: B This question is asking about the Estimate Activity Durations process. Take a look at the answers—there’s only one answer that’s used in that process: you need to start with the activity list in order to do the estimates for the activities! The other answers are things that are inputs, tools, or techniques for other processes. 14. Answer: C It’s not hard to remember the order in which the Time Management processes are performed. If you use a little common sense, you can reason your way through a question like this. You need to define your activities before you can sequence them, you need to know who’s going to be doing an activity before you can estimate how long it’s going to take, and you need to do all of that before you can build a schedule! 15. Answer: A You’ll have to know the different kinds of estimating techniques for the exam. You don’t necessarily have to be good at doing them, but you should recognize which are which. Parametric estimating is when you plug values into a formula, program, or spreadsheet and get an estimate. Analogous estimating uses similar activities from past projects to calculate new estimates. Three-point estimating uses an optimistic, pessimistic, and realistic estimate. Exam Questions Answers Did you notice answer A? Don’t forget that the float of any activity in the critical path is zero! When a question asks what you’d use for a process,it’s asking you to pick an input, tool, or techniquethat’s part of the process. exam answers Control Schedule isn’t included in the list of proceses because if a schedule change happens, you’ll have to go back and revisit the other Time Management processes. So it doesn’t have a specific order! Download at Boykma.Com
  • 9. you are here 4   319 time management Exam Questions Answers 16. Answer: C This question is asking you to apply the PERT three-point estimation formula: (Optimistic Time + 4 x Most Likely Time + Pessimistic Time) ÷ 6. When a question gives you these values directly, it’s easy. But in this case, to answer the question you had to figure out the values for the Optimistic Time and Pessimistic Time, which meant that you needed to look at the assumptions that the team was making. The most likely time was given: 27 weeks. The best case scenario would come in two weeks earlier, at 25 weeks, and the worst case would come in five weeks late, at 32 weeks. So the estimate is (25 weeks + 4 x (27 weeks) + 32 weeks) ÷ 6 = 27.5 weeks. 17. Answer: C The path Start-E-D-C-End has a duration of 8 + 2 + 4 = 14, which is the longest total duration in the entire network. 18. Answer: B Activity A is on three different paths: Start-A-B-C-End (13), Start-A-D-C-End (12), and Start-A-D-G-End (9). To calculate its float, you take the longest path’s length and subtract it from the lenth of the critical path: 14 - 13 = 1. 19. Answer: A Since activity E is on the critical path, its float is zero, because the float of any activity on the critical path is zero. 20. Answer: A The schedule management plan tells you how changes to the schedule are to be handled. Any time there’s a change, the first thing you should do is consult the plan to see how it should be handled. It looks like there will be a bunch of questions on the critical path method! It’s a good thing I’ve got so much practice with it. Sometimes you’ll get a question about applying a formula, but you’ll need to read the text in the question to figure out all of the variables Can you think of how a question might quiz you on this information without actually asking you to look at a network diagram? Download at Boykma.Com
  • 10. 320   Chapter 6 21. Answer: A The organizational process assets contain historical information about past projects. When you write up your lessons learned, or create work performance information, you store it in your company’s organizational process asset library! Also, did you notice that answer B was the wrong definition of parametric estimation? 22. Answer: D Crashing the schedule is the form of schedule compression that increases cost. This is a difficult question because all of the answers sound good, and one or two are a little misleading! Don’t fall into the trap of choosing an answer because you recognize a valid tool or technique in it. Reserve analysis and three-point estimates are very useful techniques, but they’re not the answer to this question. 23. Answer: B The critical path is the path in the network diagram where any delay will cause a delay in the schedule. These are the activities that cannot slip without making the project late! 24. Answer: C This question was really about the definition of “duration,” and the key to answering it is to understand how duration is different from effort. The correct answer talks about “calendar time,” which is what a duration is: it’s a measurement (or estimate) of how long the activity will take in real life, taking into account the number of people who will be doing the work, the availability of the people and other resources, everyone’s vacation time, time taken away from the schedule because people are pulled off of the activity to work on higher priority activities, and other real-world factors. That’s different from effort (which is often measured in person-hours), and it’s different from resource estimating (which involves estimating how many people and what other resources will be used for the activity). Exam Questions Answers exam answers Download at Boykma.Com