PRODUCTIVITY IMPROVEMENT THROUGH LEAN DEPLOYMENT &
WORK STUDY METHODS
Prathamesh P. Kulkarni1
, Sagar S. Kshire2
, Kailas V. Chandratre3
1, 2
Student (Final Year), 3
Associate Professor & Head of The Department, Department of Mechanical Engineering, GES’s
R.H.S. COE, Nashik, Maharashtra, India
Abstract
The objective of this paper is to present an overview on a new combined methodology for the efficient improvement in productivity
with the help of various Work Study Methods associated with Lean Manufacturing Principles & Tools. Lean manufacturing tools are
one of the most influential & most effective methodologies for eliminating wastes (MUDA), controlling quality, and improving overall
performance of any machine, system or process in any industry with the complete assurance of large annual profit margins. This
prescriptive paper proposes genuine solutions & concepts for implementing Work Study Methods and deploying associated lean
manufacturing tools in any enterprise or industry, covering the technical, engineering, and manufacturing aspects as well as the
business etiquette affairs. Lean Manufacturing together with Work Study Methods, being the most sophisticated & vast area of studies
has a huge scope for implementation & deployment of their very own concepts.
Keywords: 5S, Wastes (Muda), Time & Method Study, Setup Time Reduction (SUR), Standardized Work (SDW).
----------------------------------------------------------------------***------------------------------------------------------------------------
1. INTRODUCTION
Productivity has been generally defined as the ratio of an
extent of output to the unit of all of the resources used to
produce this output. Productivity usually deviates from
production. Production concerns with an increment in output
over a given span of time; productivity is concerned with the
ratio of output to an input. Putting in another way, improving
productivity has to do with how effectively people combine
different resources to manufacture parts and services others
dream to purchase. With the correct choices, improved
production, higher values and elevated incomes can be
accomplished for every hour worked. [1]
With rapid increase in demand of production, manufacturing
industries need to increase their potentials in production &
effectiveness to compete against their competitors. At the
same time, the production process has to be ready with the
ability to have abated costs with higher proficiency. Hence the
route to simplify the problem regarding the production is of
paramount importance. There are many ways i.e. Standardize
Work (SDW), Setup Reduction (SUR), Cycle Time
Reduction, Waste Elimination, etc. to solve the problems
concerning & governing productivity.
Considering the inclination towards a customer-focused
environment while facing fierce juxtapositions, majority of
manufacturers are implementing Work Study Methods along
with lean manufacturing tools to help eliminate wastes and
increase proficiencies rather than depending on conventional
processes and procedures [8]. According to many researchers,
using Lean Tools is the best way to improve productivity by
eliminating or reducing time consuming actions which
generally do not contribute in actual production. It is a way by
which one can reduce the cost of manufacturing & increase
productivity, which also increases annual profitability of the
industry. [2]
1.1 Role of Lean Tools in Improving Productivity
The basic definition of Lean Manufacturing can be stated as, a
perspective to manufacturing that searches for an opportunity
to reduce the operation time of processes, increase
maneuverability, and improve the corresponding attributes.
The primary concept behind Lean manufacturing is optimizing
customer significance while minimizing wastes, thereby
achieving manufacturing excellence through the creation of
more value with fewer or absolutely no capital investments.
[4]
Specific set of tools used in/for Lean Manufacturing, which
comprises together a complete methodology and which are
interdependent on each other forming a sophisticated yet
effective system are knows as Lean Tools. They play vital role
in any productivity improvement event as they have a very
high rate of success & also long lasting improved effect.
1.2 Role of Work Study in Improving Productivity
Work Study is the systematic methodology of carrying out
different yet related activities such as to improve the efficient
use of resources and to set up standards of performance &
quality for the activities to be carried out.
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
_______________________________________________________________________________________
Volume: 03 Issue: 02 | Feb-2014, Available @ http://www.ijret.org 430
In simple language, it may be defined as the analysis of a job
for the sheer purpose of finding the subsequent method of
doing it and also determining the required standard time to
perform it by the selected or given method. [9]
Work Study generally is classified in two areas: Method study
(Motion study) and Time study (Work measurement).
2. LEAN TOOLS
Lean tools have not been derived or proposed in one single
day. They have been derived from the research of many
people throughout the history. As they are why very complex
& interdependent on each other and one can find similarities
in one another.
Fig -1: Critical Lean Tools
Currently in practice, there are approximately 25 Lean Tools,
out of which, these five tools are considered to be the most
critical Lean Tools of all, as shown in above figure. [8]
2.1 Bottleneck Analysis
A point of concourse in a machine or system that arises when
work load gathers at a point in the system more hastily than
that specific point can hope to maintain them. The intricacies
fetched about by the bottleneck often make a queue and a
longer overall cycle time. By definition, a bottleneck is a
phenomenon where the competency of a complete system or
line is restricted or limited by a single or limited number of
components or resources & analysis of such event is called as
Bottleneck Analysis.
Hence, Bottleneck Analysis is nothing but the identification of
which part/machine of the manufacturing process/line limits
the overall output and focuses on improvement the
performance of that part/machine of the process/line. [5]
Bottleneck Analysis is usually done along with the Time
Study Method. The system on which the analysis is required to
be done is first selected. Then in the form of ‘Daily Analysis’,
‘Minute to Minute Analysis; or ‘Macro Second Study
Analysis’ the entire process is carried out along with the
guidance of Time Study Methods.
An example of Minute to Minute Bottleneck Analysis is as
shown in the figure below
Fig -2: Example of Bottleneck Analysis Sheet
2.2 Wastes (MUDA)
Anything in the manufacturing process that does not add value
to the product from the customer’s perspective is known as
Waste. In simple Language, It is nothing but any process for
which the customer does not pay the company.
There are 7 most Deadly Wastes in common –
Fig -3: Seven Deadly Wastes
1.24 To 1.26 2.00 407
1.26 To 1.30 4.00
1.30 To 1.45
1.45 To 1.50 10.00
1.50 To 3.09
3.09 To 3.30 21.00
Down Time: 175Total Time: 510.0 No. of change over
Run time = 335 minutes (Total time - Down time )
Operator Away from machine, m/c Stopped
263 no's produced
M/c Stopped, Shift Change
Tool Change
Operator Away from machine, m/c Stopped
Tea break
Down Time (Min) To
7.00 To 7.34 34.00
7.34 To 7.44 10.00
7.44 To 7.51 7.00
7.51 To 8.10 19.00
8.10 To 8.19 9.00
8.19 To 8.27
8.27 To 8.32 5.00
27 no's produced
Machine Stopped, Point problem
Single job produced, Lab testing for quality
Power Loss
Operator Absent, M/c stopped due to power loss
Machine Setting and Parameters Checking
Time (Min) Remark
Operator Absent
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
_______________________________________________________________________________________
Volume: 03 Issue: 02 | Feb-2014, Available @ http://www.ijret.org 431
1. Transportation - The unnecessary movements of
operator, products or components from one place to
another result in this waste. Unnecessary transport more
commonly occurs together with product damages, lost
parts and systems, which are related with movements. [3]
2. Inventory - Inventory is the quantity of materials in
stores, which are required to manufacture a job. When
they are not used, they take up valuable storage space,
may become useless, which cannot be used for more
important goods. [3]
3. Motion - This waste comprises of all unnecessary
movements occur when operator is moving around his
work area and as a result of this; his time & efforts are
wasted. All kinds of unnecessary motion may be caused
by improper working standard practices, un-optimized
process design or work space layout. [3]
4. Waiting - If operators, machine, system or materials of
the production process are delayed by any reason,
production time is wasted, the productivity is decreased &
the cost of production will be increased.
5. Over Processing - It can also mean manufacturing the
products of a larger quality than required. This can also be
result of not checking what the customers’ real
requirements are. [3]
6. Over Production - It arises when the manufacturer is
producing more products than the customer really asks
for. This is the worst kind of waste, as it generally creates
other kinds of wastes. It increases rework factor, material
storage, processing, holding & waiting, as well as
transportation & unnecessary motion. [3]
7. Defects (Rework, Scrap) - Rework is required when
products and components are defective or damaged.
Defects are caused by bad manufacturing processes
(caused by human or machine errors). In worst case
scenario the items have to be discarded.
In these 7 wastes, ‘Over Production’ & ‘Inventory’ are
observed to be very similar to one another & hence, in modern
Lean Methodology, ‘Inventory’ is often replaced by
‘Inspection’.
Also, one more waste is being added to these 7 deadly wastes
as this waste is also observed to be of great importance, and
that is ‘Unutilized Skill’.
2.3 5S
An established methodology procreating in Japan that, when
implemented, mitigates the waste of resources and work area
in spite of increment in manufacturing & operational
proficiency. The 5S elements when translated in English are
Sort, Set-in-Order, Shine, Standardize & Sustain and are
applied in various industries to achieve lean manufacturing &
to ultimately improve productivity. [5]
Idea of 5S can be explained by following 5 Steps -
 Sort: Completely Sort out & classify that which item is
required and/or not required in the work area.
 Set in Order: Arrange items in required order that are
important so that they are ready to find & easy to use.
 Shine: Clean the work area, tools, machine &
equipments on a continuous basis in order to identify
defects& maintain standards.
 Standardize: Ensure standard & uniform procedures
and methods throughout the operation to promote
changeover.
 Sustain: Stay to the regulations to maintain the
standard & continue to improve every day. [5][6]
2.4 Standardized Work (SDW)
Standardized work is a collection and implementation of the
best practices known to that point. It includes what is
mandatory to begin the procedure and the completed state of
the same. Standard Work is the sequential method for defining
the best practices and ensuring that every operator is strictly
following them to endow the value to the customers. Because
improvements in safety, quality, productivity & profitability
will arise from time to time & the standardized work is to be
updated via work instructions document, training, and
practice. These are the methodologies that improve quality,
safety, productivity & profitability.
Basically, standardized work consists of four elements:
 Takt time, which is the rate at which the products
must be manufactured in order to meet customer
demand on time.
 The accurate work sequence in which the operator
performs tasks within takt time.
 The corresponding inventory, including jobs in
machines, required to maintain the process operation
smoothly.
 The dexterity of the operator & the maneuverability
of the machine or system.
2.4.1 Steps Involved in Standardized Work
1. Identify and define the best system that bestows a quality
result, consistently.
2. Document the steps for performing the best practice, and
make it visual using combination of pictures and text.
3. Place it at each work station where this process is being
performed by the operator.
4. Train the operators to do the tasks as defined in the
Standard Operating Procedure.
Standardized work adds regimentation to the abidance, an
element that is frequently neglected but essential for lean to
take foundation.
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
_______________________________________________________________________________________
Volume: 03 Issue: 02 | Feb-2014, Available @ http://www.ijret.org 432
3. WORK STUDY METHODS
In order to understand the work study methods, we need to
understand the importance of method study and that of time
study. ‘Method study’ (sometimes also called Work Method
Design) is mostly used to improve the method of doing work.
When applied to existing products, method study aims to
allocate better methods of manufacturing the jobs that are safe,
effective, & economical, require mitigated human effort, and
need smaller make-ready time. The better method involves the
optimum use of best materials and appropriate manpower so
that work is performed in well-organized manner leading to
increased resource utilization, optimized quality and appeased
costs.
Fig -4: Work Study Methods
It can therefore be stated that through 'Method study' one can
have a systematic way of developing human resource
ascendancy, providing elevated machine and equipment use,
and making economical use of raw materials. ‘Time study’,
however, provides the standard required time, that is the time
needed by worker to complete a job by the standard method.
By the application of method study and time study together
with Lean Tools, any industry can thus achieve greater output
at less cost and of better quality, and hence can easily achieve
higher productivity. [9]
3.1 Method Study (Work Method Design)
Fig -5: Method Study Procedure
As seen earlier, Method study focuses to achieve the better
method of doing work, and for this reason method study is
sometimes called Work Method Design.
The following steps depict the procedure for creating a method
study.
1. Select (the work to be studied).
2. Record (all relevant information about that work).
3. Examine (the recorded information).
4. Develop (an improved way of doing things).
5. Install (the new method as standard practice)
6. Maintain (the new standard proactive).
3.2 Time Study (Work Measurement)
Work measurement refers to the estimation of standard time
for an activity that is the time specific for completing one job
by using the predicted method. Standard time can be defined
as the time utilized by an average experienced skillful operator
for the job with provisions for delays beyond the operator’s
control.
A work has to be measured for the following reasons:
 To identify and eliminate missing or ineffective time.
 To install standard times for performance & quality
measurement.
 To measure performance against original expectations.
 To set manufacturing & operating objectives.
Time study can be simply defined as a technique to estimate
the time to be allowed to a qualified and well-trained worker
working at a normal pace to complete a specified task by using
specified method.
Fig -6: Time Study Procedure
METHOD STUDY
Scrutinizing a Product &
searching more proficient
methods to carry it.
TIME STUDY
Deciding the time required to
perform a job & its associative
precautions.
WORK
STUDY
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
_______________________________________________________________________________________
Volume: 03 Issue: 02 | Feb-2014, Available @ http://www.ijret.org 433
4. SETUP TIME REDUCTION (SUR)
Setup is a set of activities to be prepared for the next part or
process, Whereas, Setup Time is the total elapsed time from
completion of the last good part from the previous setup to the
completion of the first good part from the new setup. Setup
Time Reduction or Change-over Time Reduction is defined as
the efficient reduction time to change from the last item of the
previous order to the first good item of the next order in order
to obtain increased productivity. [11]
Setup includes preparation, replacement, location and
adjustment activities. In setup reduction process, internal setup
activities require an inactive (shut down) process, meaning
that no jobs can be manufactured while the setup activity is
taking place & external setup activities may be done while the
machine is operational. By definition, all activities performed
while the machine is not producing parts are considered
internal activities. And, all the setup related activities that are
performed while the machine is producing good parts (either
the previous order or the new order) are considered external
activities. Incredible reductions in total setup time have been
realized simply by making internal activities external
activities. [10]
4.1 Need for Setup Time Reduction
Today’s manufacturing and business environments are
reaching a point that competition for survival and market share
is an obligation. Tracking the global economy will show that
being good is not sufficient, therefore every organization
really endeavor for transcendence if want to remain in the
competition.
Why Setup Reduction?
Simply -
“Equipment and the operator are occupied but
there is NO output”
Setup Time Reduction is one of the best methods to increase
efficiency of the overall plant and thereby improving the
profitability.
• Setup time reduction improves the equipment
availability, increasing the total capacity & results in:
– Better utilization of operator’s time.
– Better utilization of resources & capital cost.
– Reduced capital investment.
• Reduced setup time makes smaller batch sizes
possible, without the economic penalty, resulting in reduced:
– Overall lead times.
– Inventory & storage space needs.
– Reject rates.
Setup Reduction allows batch size reduction, which is critical
for continuous flow manufacturing & improves manufacturing
flexibility.
The following five-step approach to setup reduction may be
used to achieve efficient results –
Fig -7: Five Step Approach to SUR
5. SUMMARY
In summary, with the help of systematic study of all the
critical lean tools stated above along with efficient work study
methods, the required results of improving productivity can be
achieved in limited or very less resources in return.
In order to select target for the improvement, method study
can firstly be done to obtain accurate results about the system
which is crucial for defining the problem. After the
corresponding target has been selected, Bottleneck Analysis is
the best option to narrow down the area of problem. Once that
is done, advanced time study methods are to be implemented
to find out detailed problems present in the system.
Once the industry gets hold of the detailed problems, they can
be categorized in substantial groups in order to maintain their
integrity & so that, efficient solution on a particular problem
can easily be obtained. With Critical Lean tools stated above,
problems can be efficiently classified in corresponding area
and those tools can be applied one by one to get long lasting
results along with improved productivity as well as profit
margin.
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
_______________________________________________________________________________________
Volume: 03 Issue: 02 | Feb-2014, Available @ http://www.ijret.org 434
CONCLUSIONS
From the above paper & Studies, it can be concluded that,
Critical lean tools when effectively combined with Work
Study Methods, a unique leaner system can be formed which
will be the universal solution for any type of industry having
any sort of problem regarding the productivity. If implemented
in proper order, 100% positive results are assured.
REFERENCES
[1]. Diane Galarneau and Cécile Dumas, About productivity,
Spring 1993 (Vol. 5, No. 1) Article No. 5
[2]. W. Wiyaratn, and A. Watanapa, Improvement Plant
Layout Using Systematic Layout Planning (SLP) for Increased
Productivity, World Academy of Science, Engineering and
Technology, Volume - 48 (2010).
[3]. Khalil A. El-Namrouty, Mohammed S. AbuShaaban,
Seven wastes elimination targeted by lean manufacturing case
study “gaza strip manufacturing firms’’, International Journal
of Economics, Finance and Management Sciences (2013).
[4]. Ramunė Čiarnienė, Milita Vienažindienė, Lean
Manufacturing: Theory and Practice, Economics And
Management (2012).
[5]. Michal Leporis and Zdenka Králová, A Simulation
Approach To Production Line Bottleneck Analysis,
International Conference in CYBERNETICS AND
INFORMATICS, February (2010).
[6]. Derya Sevim Korkut, Nevzat Cakıcıer, E.Seda Erdinler,
Göksel Ulay, 5S activities and its application at a sample
company, African Journal of Biotechnology, ISSN 1684–5315
© 2009 Academic Journals Vol. 8 (8), 20 April, 2009.
[7]. Prof. S. B. Khedkar, Prof. R. D. Thakre, Prof. Y. V.
Mahantare, Mr. Ravi Gondne, Study of Implementing 5S
Techniques in Plastic Moulding, International Journal of
Modern Engineering Research(IJMER) Vol.2, Issue.5, Sep.-
Oct. 2012,ISSN: 2249-6645.
[8]. David Mann, Creating Lean Culture, Volume I. (Book).
[9]. Ralph M. Barnes, Motion and Time Study, 2nd edition,
1940.
[10]. Mr. Rahul.R.Joshi, Prof.G.R.Naik, Reduction in Setup
Time By SMED A Literature Review, International Journal of
Modern Engineering Research (IJMER) Vol.2, Issue.1, Jan-
Feb 2012.
[11]. Patel Chintan Kumar, Set up Reduction – A perfect way
for productivity improvement of computer numerical control
(CNC) set up in manufacturing company, Journal of
Mechanical Engineering Research, Vol. 5(8), November 2013.
BIOGRAPHIES
Prathamesh Pramod Kulkarni, Pursuing Final
Year in Bachelor of Mechanical Engineering
degree from GES’s R.H.S. C.O.E, Nashik,
under the affiliation of University of Pune,
Maharashtra, India.
Sagar Sunil Kshire, Pursuing Final Year in
Bachelor of Mechanical Engineering degree
from GES’s R.H.S. C.O.E, Nashik, under the
affiliation of University of Pune, Maharashtra,
India.
Prof. Kailas V. Chandratre, B.E. in Production
Engineering from K.K.W. College of
Engineering, Nashik. (University of Pune).
M.E. in Mechanical Engineering from
Walchand College of Engineering, Sangli.
(Shivaji University) Ph.D. (Pursuing) registered at University
of Pune.

Mais conteúdo relacionado

Mais procurados

IRJET- Productivity Improvement by Implementing Lean Manufacturing Tools ...
IRJET-  	  Productivity Improvement by Implementing Lean Manufacturing Tools ...IRJET-  	  Productivity Improvement by Implementing Lean Manufacturing Tools ...
IRJET- Productivity Improvement by Implementing Lean Manufacturing Tools ...IRJET Journal
 
MANUFACTURING LEAD TIME REDUCTION IN A SCAFFOLD MAKING INDUSTRY USING LEAN MA...
MANUFACTURING LEAD TIME REDUCTION IN A SCAFFOLD MAKING INDUSTRY USING LEAN MA...MANUFACTURING LEAD TIME REDUCTION IN A SCAFFOLD MAKING INDUSTRY USING LEAN MA...
MANUFACTURING LEAD TIME REDUCTION IN A SCAFFOLD MAKING INDUSTRY USING LEAN MA...IAEME Publication
 
A038301010
A038301010A038301010
A038301010theijes
 
Implementation of Single Minute Exchange of Die in Motor Manufacturing Unit
Implementation of Single Minute Exchange of Die in Motor Manufacturing UnitImplementation of Single Minute Exchange of Die in Motor Manufacturing Unit
Implementation of Single Minute Exchange of Die in Motor Manufacturing UnitIRJET Journal
 
PRODUCTION PROCESS ANALYSIS ON MANUFACTURING OF HYDRAULIC GEAR PUMP
PRODUCTION PROCESS ANALYSIS ON MANUFACTURING OF HYDRAULIC GEAR PUMPPRODUCTION PROCESS ANALYSIS ON MANUFACTURING OF HYDRAULIC GEAR PUMP
PRODUCTION PROCESS ANALYSIS ON MANUFACTURING OF HYDRAULIC GEAR PUMPmeijjournal
 
Report on JIT , for Projects and Seminars
Report on JIT , for Projects and SeminarsReport on JIT , for Projects and Seminars
Report on JIT , for Projects and Seminarsomkar jagtap
 
Operations management-bba calicut university notes
Operations management-bba calicut university notes Operations management-bba calicut university notes
Operations management-bba calicut university notes Akhilesh Krishnan
 
Kobetsu Kaizen Losses Analysis to Enhance the Overall Plant Effectiveness in ...
Kobetsu Kaizen Losses Analysis to Enhance the Overall Plant Effectiveness in ...Kobetsu Kaizen Losses Analysis to Enhance the Overall Plant Effectiveness in ...
Kobetsu Kaizen Losses Analysis to Enhance the Overall Plant Effectiveness in ...IRJET Journal
 
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...ijsrd.com
 
IRJET- Application of Work Study in Construction Project
IRJET-  	  Application of Work Study in Construction ProjectIRJET-  	  Application of Work Study in Construction Project
IRJET- Application of Work Study in Construction ProjectIRJET Journal
 
IRJET- Enhance the Capacity of Outer Tube Machining Cell
IRJET-  	  Enhance the Capacity of Outer Tube Machining CellIRJET-  	  Enhance the Capacity of Outer Tube Machining Cell
IRJET- Enhance the Capacity of Outer Tube Machining CellIRJET Journal
 
Introduction to Production and Operations Research
 Introduction to Production and Operations Research Introduction to Production and Operations Research
Introduction to Production and Operations ResearchDr. Jerry John
 
Productivity improvement at assembly station using work study techniques
Productivity improvement at assembly station using work study techniquesProductivity improvement at assembly station using work study techniques
Productivity improvement at assembly station using work study techniqueseSAT Publishing House
 
Jit ppt with case study
Jit ppt with case studyJit ppt with case study
Jit ppt with case studyomkar jagtap
 

Mais procurados (20)

IRJET- Productivity Improvement by Implementing Lean Manufacturing Tools ...
IRJET-  	  Productivity Improvement by Implementing Lean Manufacturing Tools ...IRJET-  	  Productivity Improvement by Implementing Lean Manufacturing Tools ...
IRJET- Productivity Improvement by Implementing Lean Manufacturing Tools ...
 
MANUFACTURING LEAD TIME REDUCTION IN A SCAFFOLD MAKING INDUSTRY USING LEAN MA...
MANUFACTURING LEAD TIME REDUCTION IN A SCAFFOLD MAKING INDUSTRY USING LEAN MA...MANUFACTURING LEAD TIME REDUCTION IN A SCAFFOLD MAKING INDUSTRY USING LEAN MA...
MANUFACTURING LEAD TIME REDUCTION IN A SCAFFOLD MAKING INDUSTRY USING LEAN MA...
 
A038301010
A038301010A038301010
A038301010
 
Wcm 2
Wcm 2Wcm 2
Wcm 2
 
Implementation of Single Minute Exchange of Die in Motor Manufacturing Unit
Implementation of Single Minute Exchange of Die in Motor Manufacturing UnitImplementation of Single Minute Exchange of Die in Motor Manufacturing Unit
Implementation of Single Minute Exchange of Die in Motor Manufacturing Unit
 
PRODUCTION PROCESS ANALYSIS ON MANUFACTURING OF HYDRAULIC GEAR PUMP
PRODUCTION PROCESS ANALYSIS ON MANUFACTURING OF HYDRAULIC GEAR PUMPPRODUCTION PROCESS ANALYSIS ON MANUFACTURING OF HYDRAULIC GEAR PUMP
PRODUCTION PROCESS ANALYSIS ON MANUFACTURING OF HYDRAULIC GEAR PUMP
 
Report on JIT , for Projects and Seminars
Report on JIT , for Projects and SeminarsReport on JIT , for Projects and Seminars
Report on JIT , for Projects and Seminars
 
Operations management-bba calicut university notes
Operations management-bba calicut university notes Operations management-bba calicut university notes
Operations management-bba calicut university notes
 
Kobetsu Kaizen Losses Analysis to Enhance the Overall Plant Effectiveness in ...
Kobetsu Kaizen Losses Analysis to Enhance the Overall Plant Effectiveness in ...Kobetsu Kaizen Losses Analysis to Enhance the Overall Plant Effectiveness in ...
Kobetsu Kaizen Losses Analysis to Enhance the Overall Plant Effectiveness in ...
 
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
 
H012535263
H012535263H012535263
H012535263
 
IRJET- Application of Work Study in Construction Project
IRJET-  	  Application of Work Study in Construction ProjectIRJET-  	  Application of Work Study in Construction Project
IRJET- Application of Work Study in Construction Project
 
IRJET- Enhance the Capacity of Outer Tube Machining Cell
IRJET-  	  Enhance the Capacity of Outer Tube Machining CellIRJET-  	  Enhance the Capacity of Outer Tube Machining Cell
IRJET- Enhance the Capacity of Outer Tube Machining Cell
 
Introduction to Production and Operations Research
 Introduction to Production and Operations Research Introduction to Production and Operations Research
Introduction to Production and Operations Research
 
Productivity improvement at assembly station using work study techniques
Productivity improvement at assembly station using work study techniquesProductivity improvement at assembly station using work study techniques
Productivity improvement at assembly station using work study techniques
 
Wcm 3
Wcm 3Wcm 3
Wcm 3
 
Wcm 5
Wcm 5Wcm 5
Wcm 5
 
Jit ppt with case study
Jit ppt with case studyJit ppt with case study
Jit ppt with case study
 
Just in Time
Just in Time Just in Time
Just in Time
 
Lean manufacturing english
Lean manufacturing   englishLean manufacturing   english
Lean manufacturing english
 

Destaque

Modern Software Productivity Measurement: The Pragmatic Guide
Modern Software Productivity Measurement: The Pragmatic GuideModern Software Productivity Measurement: The Pragmatic Guide
Modern Software Productivity Measurement: The Pragmatic GuideCAST
 
Case Study 3 Production Cost Perfect Comp Answer Sheet - new
Case Study 3 Production Cost Perfect Comp Answer Sheet - newCase Study 3 Production Cost Perfect Comp Answer Sheet - new
Case Study 3 Production Cost Perfect Comp Answer Sheet - newKayla Davenport
 
Productivity and Improvement in Productivity
Productivity and Improvement in ProductivityProductivity and Improvement in Productivity
Productivity and Improvement in ProductivityBinal Kapadia
 
The impact of colors
The impact of colorsThe impact of colors
The impact of colorsHassan Yahya
 
AMLA Project: Action plan Mizoram
AMLA Project: Action plan MizoramAMLA Project: Action plan Mizoram
AMLA Project: Action plan MizoramSanjay Talukdar
 
Case study- Implementing fully integrated solutions for the food industry
Case study- Implementing fully integrated solutions for the food industryCase study- Implementing fully integrated solutions for the food industry
Case study- Implementing fully integrated solutions for the food industryFedegari Group
 
Kanpur Confectioneries Case Analysis
Kanpur Confectioneries Case AnalysisKanpur Confectioneries Case Analysis
Kanpur Confectioneries Case AnalysisJayant Kushwaha
 
Plant Productivity Measurement, Analysis & Improvement: Business Case
Plant Productivity Measurement, Analysis & Improvement: Business CasePlant Productivity Measurement, Analysis & Improvement: Business Case
Plant Productivity Measurement, Analysis & Improvement: Business CaseMohammed Hamed Ahmed Soliman
 
WORK MEASUREMENT AND PRODUCTIVITY IMPROVEMENT, Authored by Dr. SUBHASH S NAIK...
WORK MEASUREMENT AND PRODUCTIVITY IMPROVEMENT, Authored by Dr. SUBHASH S NAIK...WORK MEASUREMENT AND PRODUCTIVITY IMPROVEMENT, Authored by Dr. SUBHASH S NAIK...
WORK MEASUREMENT AND PRODUCTIVITY IMPROVEMENT, Authored by Dr. SUBHASH S NAIK...Dr. Subhash Naik
 
Masters Thesis - Smart Cafeteria
Masters Thesis - Smart CafeteriaMasters Thesis - Smart Cafeteria
Masters Thesis - Smart CafeteriaRichard Philip
 
Work study method-and_time_study-final
Work study method-and_time_study-finalWork study method-and_time_study-final
Work study method-and_time_study-finalHareesh M
 
Effect of work study & time study on production and quality
 Effect of work study & time study on production and quality Effect of work study & time study on production and quality
Effect of work study & time study on production and qualityMd. Mazadul Hasan Shishir
 
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...Karina Islam
 
Effect of work study & time study on production and quality
Effect of work study & time study on production and qualityEffect of work study & time study on production and quality
Effect of work study & time study on production and qualityMd. Mazadul Hasan Shishir
 
Patanjali Business Strategies
Patanjali Business Strategies Patanjali Business Strategies
Patanjali Business Strategies Kuldeep Sharma
 

Destaque (20)

Modern Software Productivity Measurement: The Pragmatic Guide
Modern Software Productivity Measurement: The Pragmatic GuideModern Software Productivity Measurement: The Pragmatic Guide
Modern Software Productivity Measurement: The Pragmatic Guide
 
Case Study 3 Production Cost Perfect Comp Answer Sheet - new
Case Study 3 Production Cost Perfect Comp Answer Sheet - newCase Study 3 Production Cost Perfect Comp Answer Sheet - new
Case Study 3 Production Cost Perfect Comp Answer Sheet - new
 
Productivity and Improvement in Productivity
Productivity and Improvement in ProductivityProductivity and Improvement in Productivity
Productivity and Improvement in Productivity
 
The impact of colors
The impact of colorsThe impact of colors
The impact of colors
 
AMLA Project: Action plan Mizoram
AMLA Project: Action plan MizoramAMLA Project: Action plan Mizoram
AMLA Project: Action plan Mizoram
 
Case study- Implementing fully integrated solutions for the food industry
Case study- Implementing fully integrated solutions for the food industryCase study- Implementing fully integrated solutions for the food industry
Case study- Implementing fully integrated solutions for the food industry
 
Kanpur Confectioneries Case Analysis
Kanpur Confectioneries Case AnalysisKanpur Confectioneries Case Analysis
Kanpur Confectioneries Case Analysis
 
IE Training
IE Training IE Training
IE Training
 
Dabur
DaburDabur
Dabur
 
Methods Enigeering
Methods EnigeeringMethods Enigeering
Methods Enigeering
 
Plant Productivity Measurement, Analysis & Improvement: Business Case
Plant Productivity Measurement, Analysis & Improvement: Business CasePlant Productivity Measurement, Analysis & Improvement: Business Case
Plant Productivity Measurement, Analysis & Improvement: Business Case
 
The Toyota Way - Toyota dramatic business success
The Toyota Way - Toyota dramatic business successThe Toyota Way - Toyota dramatic business success
The Toyota Way - Toyota dramatic business success
 
WORK MEASUREMENT AND PRODUCTIVITY IMPROVEMENT, Authored by Dr. SUBHASH S NAIK...
WORK MEASUREMENT AND PRODUCTIVITY IMPROVEMENT, Authored by Dr. SUBHASH S NAIK...WORK MEASUREMENT AND PRODUCTIVITY IMPROVEMENT, Authored by Dr. SUBHASH S NAIK...
WORK MEASUREMENT AND PRODUCTIVITY IMPROVEMENT, Authored by Dr. SUBHASH S NAIK...
 
Masters Thesis - Smart Cafeteria
Masters Thesis - Smart CafeteriaMasters Thesis - Smart Cafeteria
Masters Thesis - Smart Cafeteria
 
Work study method-and_time_study-final
Work study method-and_time_study-finalWork study method-and_time_study-final
Work study method-and_time_study-final
 
Effect of work study & time study on production and quality
 Effect of work study & time study on production and quality Effect of work study & time study on production and quality
Effect of work study & time study on production and quality
 
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
 
Effect of work study & time study on production and quality
Effect of work study & time study on production and qualityEffect of work study & time study on production and quality
Effect of work study & time study on production and quality
 
Patanjali Business Strategies
Patanjali Business Strategies Patanjali Business Strategies
Patanjali Business Strategies
 
Dabur India- Case Study
Dabur India- Case StudyDabur India- Case Study
Dabur India- Case Study
 

Semelhante a Productivity improvement through lean deployment & work study methods

PRODUCTIVITY IMPROVEMENT USING LEAN TOOLS IN PUMP INDUSTRY
PRODUCTIVITY IMPROVEMENT USING LEAN TOOLS IN PUMP INDUSTRYPRODUCTIVITY IMPROVEMENT USING LEAN TOOLS IN PUMP INDUSTRY
PRODUCTIVITY IMPROVEMENT USING LEAN TOOLS IN PUMP INDUSTRYIRJET Journal
 
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump IndustryManufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump IndustryIRJET Journal
 
Facility Layout/Production Planning & Control(PPC)/ Method Study/ Capacity Pl...
Facility Layout/Production Planning & Control(PPC)/ Method Study/ Capacity Pl...Facility Layout/Production Planning & Control(PPC)/ Method Study/ Capacity Pl...
Facility Layout/Production Planning & Control(PPC)/ Method Study/ Capacity Pl...viveksangwan007
 
Malabar cements
Malabar cementsMalabar cements
Malabar cementssarathpkd
 
Productivity Improvement by Optimum Utilization of Plant Layout: A Case Study
Productivity Improvement by Optimum Utilization of Plant Layout: A Case StudyProductivity Improvement by Optimum Utilization of Plant Layout: A Case Study
Productivity Improvement by Optimum Utilization of Plant Layout: A Case StudyIRJET Journal
 
A case study on productivity improvement of wearing insert and cutting ring
A case study on productivity improvement of wearing insert and cutting ringA case study on productivity improvement of wearing insert and cutting ring
A case study on productivity improvement of wearing insert and cutting ringIJECSJournal
 
J0371055062
J0371055062J0371055062
J0371055062theijes
 
Achieving operational excellence by implementing an erp (enterprise resource ...
Achieving operational excellence by implementing an erp (enterprise resource ...Achieving operational excellence by implementing an erp (enterprise resource ...
Achieving operational excellence by implementing an erp (enterprise resource ...eSAT Publishing House
 
IRJET - Productivity Improvement by Time Study and Motion Study
IRJET - Productivity Improvement by Time Study and Motion StudyIRJET - Productivity Improvement by Time Study and Motion Study
IRJET - Productivity Improvement by Time Study and Motion StudyIRJET Journal
 
Production System optimization: Case Study of a Local Textile Company
Production System optimization: Case Study of a Local Textile CompanyProduction System optimization: Case Study of a Local Textile Company
Production System optimization: Case Study of a Local Textile Companyjournal ijrtem
 
KAIZEN: A Lean Manufacturing Technique
KAIZEN: A Lean Manufacturing TechniqueKAIZEN: A Lean Manufacturing Technique
KAIZEN: A Lean Manufacturing Techniquevivatechijri
 
Line Balancing and facility optimization of Machine Shop with Work Study and ...
Line Balancing and facility optimization of Machine Shop with Work Study and ...Line Balancing and facility optimization of Machine Shop with Work Study and ...
Line Balancing and facility optimization of Machine Shop with Work Study and ...IRJET Journal
 
8. chapter 7 work study (time and motion study)
8. chapter 7   work study (time and motion study)8. chapter 7   work study (time and motion study)
8. chapter 7 work study (time and motion study)sundar sivam
 
IRJET- Implementing Lean Manufacturing Principle in Fabrication Process- A...
IRJET- 	  Implementing Lean Manufacturing Principle in Fabrication Process- A...IRJET- 	  Implementing Lean Manufacturing Principle in Fabrication Process- A...
IRJET- Implementing Lean Manufacturing Principle in Fabrication Process- A...IRJET Journal
 
Industrial Engineering - Method Study
Industrial Engineering - Method StudyIndustrial Engineering - Method Study
Industrial Engineering - Method Studyjosy2108
 
INTRODUCTION TO PRODUCTION AND OPERATIONS MANAGEMENT - Unit 1 (BBA-Bangalore ...
INTRODUCTION TO PRODUCTION AND OPERATIONS MANAGEMENT - Unit 1 (BBA-Bangalore ...INTRODUCTION TO PRODUCTION AND OPERATIONS MANAGEMENT - Unit 1 (BBA-Bangalore ...
INTRODUCTION TO PRODUCTION AND OPERATIONS MANAGEMENT - Unit 1 (BBA-Bangalore ...Afsana salam
 

Semelhante a Productivity improvement through lean deployment & work study methods (20)

PRODUCTIVITY IMPROVEMENT USING LEAN TOOLS IN PUMP INDUSTRY
PRODUCTIVITY IMPROVEMENT USING LEAN TOOLS IN PUMP INDUSTRYPRODUCTIVITY IMPROVEMENT USING LEAN TOOLS IN PUMP INDUSTRY
PRODUCTIVITY IMPROVEMENT USING LEAN TOOLS IN PUMP INDUSTRY
 
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump IndustryManufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry
 
Lean System
Lean SystemLean System
Lean System
 
Facility Layout/Production Planning & Control(PPC)/ Method Study/ Capacity Pl...
Facility Layout/Production Planning & Control(PPC)/ Method Study/ Capacity Pl...Facility Layout/Production Planning & Control(PPC)/ Method Study/ Capacity Pl...
Facility Layout/Production Planning & Control(PPC)/ Method Study/ Capacity Pl...
 
Malabar cements
Malabar cementsMalabar cements
Malabar cements
 
Productivity Improvement by Optimum Utilization of Plant Layout: A Case Study
Productivity Improvement by Optimum Utilization of Plant Layout: A Case StudyProductivity Improvement by Optimum Utilization of Plant Layout: A Case Study
Productivity Improvement by Optimum Utilization of Plant Layout: A Case Study
 
A case study on productivity improvement of wearing insert and cutting ring
A case study on productivity improvement of wearing insert and cutting ringA case study on productivity improvement of wearing insert and cutting ring
A case study on productivity improvement of wearing insert and cutting ring
 
Work Study Part- I
Work Study Part- IWork Study Part- I
Work Study Part- I
 
J0371055062
J0371055062J0371055062
J0371055062
 
Achieving operational excellence by implementing an erp (enterprise resource ...
Achieving operational excellence by implementing an erp (enterprise resource ...Achieving operational excellence by implementing an erp (enterprise resource ...
Achieving operational excellence by implementing an erp (enterprise resource ...
 
IRJET - Productivity Improvement by Time Study and Motion Study
IRJET - Productivity Improvement by Time Study and Motion StudyIRJET - Productivity Improvement by Time Study and Motion Study
IRJET - Productivity Improvement by Time Study and Motion Study
 
Production System optimization: Case Study of a Local Textile Company
Production System optimization: Case Study of a Local Textile CompanyProduction System optimization: Case Study of a Local Textile Company
Production System optimization: Case Study of a Local Textile Company
 
KAIZEN: A Lean Manufacturing Technique
KAIZEN: A Lean Manufacturing TechniqueKAIZEN: A Lean Manufacturing Technique
KAIZEN: A Lean Manufacturing Technique
 
Line Balancing and facility optimization of Machine Shop with Work Study and ...
Line Balancing and facility optimization of Machine Shop with Work Study and ...Line Balancing and facility optimization of Machine Shop with Work Study and ...
Line Balancing and facility optimization of Machine Shop with Work Study and ...
 
8. chapter 7 work study (time and motion study)
8. chapter 7   work study (time and motion study)8. chapter 7   work study (time and motion study)
8. chapter 7 work study (time and motion study)
 
IRJET- Implementing Lean Manufacturing Principle in Fabrication Process- A...
IRJET- 	  Implementing Lean Manufacturing Principle in Fabrication Process- A...IRJET- 	  Implementing Lean Manufacturing Principle in Fabrication Process- A...
IRJET- Implementing Lean Manufacturing Principle in Fabrication Process- A...
 
Industrial Engineering - Method Study
Industrial Engineering - Method StudyIndustrial Engineering - Method Study
Industrial Engineering - Method Study
 
Pom unit 3
Pom unit 3Pom unit 3
Pom unit 3
 
INTRODUCTION TO PRODUCTION AND OPERATIONS MANAGEMENT - Unit 1 (BBA-Bangalore ...
INTRODUCTION TO PRODUCTION AND OPERATIONS MANAGEMENT - Unit 1 (BBA-Bangalore ...INTRODUCTION TO PRODUCTION AND OPERATIONS MANAGEMENT - Unit 1 (BBA-Bangalore ...
INTRODUCTION TO PRODUCTION AND OPERATIONS MANAGEMENT - Unit 1 (BBA-Bangalore ...
 
Group technolog1 assegment
Group technolog1 assegmentGroup technolog1 assegment
Group technolog1 assegment
 

Mais de eSAT Journals

Mechanical properties of hybrid fiber reinforced concrete for pavements
Mechanical properties of hybrid fiber reinforced concrete for pavementsMechanical properties of hybrid fiber reinforced concrete for pavements
Mechanical properties of hybrid fiber reinforced concrete for pavementseSAT Journals
 
Material management in construction – a case study
Material management in construction – a case studyMaterial management in construction – a case study
Material management in construction – a case studyeSAT Journals
 
Managing drought short term strategies in semi arid regions a case study
Managing drought    short term strategies in semi arid regions  a case studyManaging drought    short term strategies in semi arid regions  a case study
Managing drought short term strategies in semi arid regions a case studyeSAT Journals
 
Life cycle cost analysis of overlay for an urban road in bangalore
Life cycle cost analysis of overlay for an urban road in bangaloreLife cycle cost analysis of overlay for an urban road in bangalore
Life cycle cost analysis of overlay for an urban road in bangaloreeSAT Journals
 
Laboratory studies of dense bituminous mixes ii with reclaimed asphalt materials
Laboratory studies of dense bituminous mixes ii with reclaimed asphalt materialsLaboratory studies of dense bituminous mixes ii with reclaimed asphalt materials
Laboratory studies of dense bituminous mixes ii with reclaimed asphalt materialseSAT Journals
 
Laboratory investigation of expansive soil stabilized with natural inorganic ...
Laboratory investigation of expansive soil stabilized with natural inorganic ...Laboratory investigation of expansive soil stabilized with natural inorganic ...
Laboratory investigation of expansive soil stabilized with natural inorganic ...eSAT Journals
 
Influence of reinforcement on the behavior of hollow concrete block masonry p...
Influence of reinforcement on the behavior of hollow concrete block masonry p...Influence of reinforcement on the behavior of hollow concrete block masonry p...
Influence of reinforcement on the behavior of hollow concrete block masonry p...eSAT Journals
 
Influence of compaction energy on soil stabilized with chemical stabilizer
Influence of compaction energy on soil stabilized with chemical stabilizerInfluence of compaction energy on soil stabilized with chemical stabilizer
Influence of compaction energy on soil stabilized with chemical stabilizereSAT Journals
 
Geographical information system (gis) for water resources management
Geographical information system (gis) for water resources managementGeographical information system (gis) for water resources management
Geographical information system (gis) for water resources managementeSAT Journals
 
Forest type mapping of bidar forest division, karnataka using geoinformatics ...
Forest type mapping of bidar forest division, karnataka using geoinformatics ...Forest type mapping of bidar forest division, karnataka using geoinformatics ...
Forest type mapping of bidar forest division, karnataka using geoinformatics ...eSAT Journals
 
Factors influencing compressive strength of geopolymer concrete
Factors influencing compressive strength of geopolymer concreteFactors influencing compressive strength of geopolymer concrete
Factors influencing compressive strength of geopolymer concreteeSAT Journals
 
Experimental investigation on circular hollow steel columns in filled with li...
Experimental investigation on circular hollow steel columns in filled with li...Experimental investigation on circular hollow steel columns in filled with li...
Experimental investigation on circular hollow steel columns in filled with li...eSAT Journals
 
Experimental behavior of circular hsscfrc filled steel tubular columns under ...
Experimental behavior of circular hsscfrc filled steel tubular columns under ...Experimental behavior of circular hsscfrc filled steel tubular columns under ...
Experimental behavior of circular hsscfrc filled steel tubular columns under ...eSAT Journals
 
Evaluation of punching shear in flat slabs
Evaluation of punching shear in flat slabsEvaluation of punching shear in flat slabs
Evaluation of punching shear in flat slabseSAT Journals
 
Evaluation of performance of intake tower dam for recent earthquake in india
Evaluation of performance of intake tower dam for recent earthquake in indiaEvaluation of performance of intake tower dam for recent earthquake in india
Evaluation of performance of intake tower dam for recent earthquake in indiaeSAT Journals
 
Evaluation of operational efficiency of urban road network using travel time ...
Evaluation of operational efficiency of urban road network using travel time ...Evaluation of operational efficiency of urban road network using travel time ...
Evaluation of operational efficiency of urban road network using travel time ...eSAT Journals
 
Estimation of surface runoff in nallur amanikere watershed using scs cn method
Estimation of surface runoff in nallur amanikere watershed using scs cn methodEstimation of surface runoff in nallur amanikere watershed using scs cn method
Estimation of surface runoff in nallur amanikere watershed using scs cn methodeSAT Journals
 
Estimation of morphometric parameters and runoff using rs & gis techniques
Estimation of morphometric parameters and runoff using rs & gis techniquesEstimation of morphometric parameters and runoff using rs & gis techniques
Estimation of morphometric parameters and runoff using rs & gis techniqueseSAT Journals
 
Effect of variation of plastic hinge length on the results of non linear anal...
Effect of variation of plastic hinge length on the results of non linear anal...Effect of variation of plastic hinge length on the results of non linear anal...
Effect of variation of plastic hinge length on the results of non linear anal...eSAT Journals
 
Effect of use of recycled materials on indirect tensile strength of asphalt c...
Effect of use of recycled materials on indirect tensile strength of asphalt c...Effect of use of recycled materials on indirect tensile strength of asphalt c...
Effect of use of recycled materials on indirect tensile strength of asphalt c...eSAT Journals
 

Mais de eSAT Journals (20)

Mechanical properties of hybrid fiber reinforced concrete for pavements
Mechanical properties of hybrid fiber reinforced concrete for pavementsMechanical properties of hybrid fiber reinforced concrete for pavements
Mechanical properties of hybrid fiber reinforced concrete for pavements
 
Material management in construction – a case study
Material management in construction – a case studyMaterial management in construction – a case study
Material management in construction – a case study
 
Managing drought short term strategies in semi arid regions a case study
Managing drought    short term strategies in semi arid regions  a case studyManaging drought    short term strategies in semi arid regions  a case study
Managing drought short term strategies in semi arid regions a case study
 
Life cycle cost analysis of overlay for an urban road in bangalore
Life cycle cost analysis of overlay for an urban road in bangaloreLife cycle cost analysis of overlay for an urban road in bangalore
Life cycle cost analysis of overlay for an urban road in bangalore
 
Laboratory studies of dense bituminous mixes ii with reclaimed asphalt materials
Laboratory studies of dense bituminous mixes ii with reclaimed asphalt materialsLaboratory studies of dense bituminous mixes ii with reclaimed asphalt materials
Laboratory studies of dense bituminous mixes ii with reclaimed asphalt materials
 
Laboratory investigation of expansive soil stabilized with natural inorganic ...
Laboratory investigation of expansive soil stabilized with natural inorganic ...Laboratory investigation of expansive soil stabilized with natural inorganic ...
Laboratory investigation of expansive soil stabilized with natural inorganic ...
 
Influence of reinforcement on the behavior of hollow concrete block masonry p...
Influence of reinforcement on the behavior of hollow concrete block masonry p...Influence of reinforcement on the behavior of hollow concrete block masonry p...
Influence of reinforcement on the behavior of hollow concrete block masonry p...
 
Influence of compaction energy on soil stabilized with chemical stabilizer
Influence of compaction energy on soil stabilized with chemical stabilizerInfluence of compaction energy on soil stabilized with chemical stabilizer
Influence of compaction energy on soil stabilized with chemical stabilizer
 
Geographical information system (gis) for water resources management
Geographical information system (gis) for water resources managementGeographical information system (gis) for water resources management
Geographical information system (gis) for water resources management
 
Forest type mapping of bidar forest division, karnataka using geoinformatics ...
Forest type mapping of bidar forest division, karnataka using geoinformatics ...Forest type mapping of bidar forest division, karnataka using geoinformatics ...
Forest type mapping of bidar forest division, karnataka using geoinformatics ...
 
Factors influencing compressive strength of geopolymer concrete
Factors influencing compressive strength of geopolymer concreteFactors influencing compressive strength of geopolymer concrete
Factors influencing compressive strength of geopolymer concrete
 
Experimental investigation on circular hollow steel columns in filled with li...
Experimental investigation on circular hollow steel columns in filled with li...Experimental investigation on circular hollow steel columns in filled with li...
Experimental investigation on circular hollow steel columns in filled with li...
 
Experimental behavior of circular hsscfrc filled steel tubular columns under ...
Experimental behavior of circular hsscfrc filled steel tubular columns under ...Experimental behavior of circular hsscfrc filled steel tubular columns under ...
Experimental behavior of circular hsscfrc filled steel tubular columns under ...
 
Evaluation of punching shear in flat slabs
Evaluation of punching shear in flat slabsEvaluation of punching shear in flat slabs
Evaluation of punching shear in flat slabs
 
Evaluation of performance of intake tower dam for recent earthquake in india
Evaluation of performance of intake tower dam for recent earthquake in indiaEvaluation of performance of intake tower dam for recent earthquake in india
Evaluation of performance of intake tower dam for recent earthquake in india
 
Evaluation of operational efficiency of urban road network using travel time ...
Evaluation of operational efficiency of urban road network using travel time ...Evaluation of operational efficiency of urban road network using travel time ...
Evaluation of operational efficiency of urban road network using travel time ...
 
Estimation of surface runoff in nallur amanikere watershed using scs cn method
Estimation of surface runoff in nallur amanikere watershed using scs cn methodEstimation of surface runoff in nallur amanikere watershed using scs cn method
Estimation of surface runoff in nallur amanikere watershed using scs cn method
 
Estimation of morphometric parameters and runoff using rs & gis techniques
Estimation of morphometric parameters and runoff using rs & gis techniquesEstimation of morphometric parameters and runoff using rs & gis techniques
Estimation of morphometric parameters and runoff using rs & gis techniques
 
Effect of variation of plastic hinge length on the results of non linear anal...
Effect of variation of plastic hinge length on the results of non linear anal...Effect of variation of plastic hinge length on the results of non linear anal...
Effect of variation of plastic hinge length on the results of non linear anal...
 
Effect of use of recycled materials on indirect tensile strength of asphalt c...
Effect of use of recycled materials on indirect tensile strength of asphalt c...Effect of use of recycled materials on indirect tensile strength of asphalt c...
Effect of use of recycled materials on indirect tensile strength of asphalt c...
 

Último

DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationBhangaleSonal
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdfKamal Acharya
 
Wadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxWadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxNadaHaitham1
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdfKamal Acharya
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadhamedmustafa094
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdfKamal Acharya
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxchumtiyababu
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdfKamal Acharya
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARKOUSTAV SARKAR
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesMayuraD1
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxMuhammadAsimMuhammad6
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network DevicesChandrakantDivate1
 

Último (20)

DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
Wadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxWadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptx
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal load
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptx
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 

Productivity improvement through lean deployment & work study methods

  • 1. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _______________________________________________________________________________________ Volume: 03 Issue: 02 | Feb-2014, Available @ http://www.ijret.org 429 PRODUCTIVITY IMPROVEMENT THROUGH LEAN DEPLOYMENT & WORK STUDY METHODS Prathamesh P. Kulkarni1 , Sagar S. Kshire2 , Kailas V. Chandratre3 1, 2 Student (Final Year), 3 Associate Professor & Head of The Department, Department of Mechanical Engineering, GES’s R.H.S. COE, Nashik, Maharashtra, India Abstract The objective of this paper is to present an overview on a new combined methodology for the efficient improvement in productivity with the help of various Work Study Methods associated with Lean Manufacturing Principles & Tools. Lean manufacturing tools are one of the most influential & most effective methodologies for eliminating wastes (MUDA), controlling quality, and improving overall performance of any machine, system or process in any industry with the complete assurance of large annual profit margins. This prescriptive paper proposes genuine solutions & concepts for implementing Work Study Methods and deploying associated lean manufacturing tools in any enterprise or industry, covering the technical, engineering, and manufacturing aspects as well as the business etiquette affairs. Lean Manufacturing together with Work Study Methods, being the most sophisticated & vast area of studies has a huge scope for implementation & deployment of their very own concepts. Keywords: 5S, Wastes (Muda), Time & Method Study, Setup Time Reduction (SUR), Standardized Work (SDW). ----------------------------------------------------------------------***------------------------------------------------------------------------ 1. INTRODUCTION Productivity has been generally defined as the ratio of an extent of output to the unit of all of the resources used to produce this output. Productivity usually deviates from production. Production concerns with an increment in output over a given span of time; productivity is concerned with the ratio of output to an input. Putting in another way, improving productivity has to do with how effectively people combine different resources to manufacture parts and services others dream to purchase. With the correct choices, improved production, higher values and elevated incomes can be accomplished for every hour worked. [1] With rapid increase in demand of production, manufacturing industries need to increase their potentials in production & effectiveness to compete against their competitors. At the same time, the production process has to be ready with the ability to have abated costs with higher proficiency. Hence the route to simplify the problem regarding the production is of paramount importance. There are many ways i.e. Standardize Work (SDW), Setup Reduction (SUR), Cycle Time Reduction, Waste Elimination, etc. to solve the problems concerning & governing productivity. Considering the inclination towards a customer-focused environment while facing fierce juxtapositions, majority of manufacturers are implementing Work Study Methods along with lean manufacturing tools to help eliminate wastes and increase proficiencies rather than depending on conventional processes and procedures [8]. According to many researchers, using Lean Tools is the best way to improve productivity by eliminating or reducing time consuming actions which generally do not contribute in actual production. It is a way by which one can reduce the cost of manufacturing & increase productivity, which also increases annual profitability of the industry. [2] 1.1 Role of Lean Tools in Improving Productivity The basic definition of Lean Manufacturing can be stated as, a perspective to manufacturing that searches for an opportunity to reduce the operation time of processes, increase maneuverability, and improve the corresponding attributes. The primary concept behind Lean manufacturing is optimizing customer significance while minimizing wastes, thereby achieving manufacturing excellence through the creation of more value with fewer or absolutely no capital investments. [4] Specific set of tools used in/for Lean Manufacturing, which comprises together a complete methodology and which are interdependent on each other forming a sophisticated yet effective system are knows as Lean Tools. They play vital role in any productivity improvement event as they have a very high rate of success & also long lasting improved effect. 1.2 Role of Work Study in Improving Productivity Work Study is the systematic methodology of carrying out different yet related activities such as to improve the efficient use of resources and to set up standards of performance & quality for the activities to be carried out.
  • 2. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _______________________________________________________________________________________ Volume: 03 Issue: 02 | Feb-2014, Available @ http://www.ijret.org 430 In simple language, it may be defined as the analysis of a job for the sheer purpose of finding the subsequent method of doing it and also determining the required standard time to perform it by the selected or given method. [9] Work Study generally is classified in two areas: Method study (Motion study) and Time study (Work measurement). 2. LEAN TOOLS Lean tools have not been derived or proposed in one single day. They have been derived from the research of many people throughout the history. As they are why very complex & interdependent on each other and one can find similarities in one another. Fig -1: Critical Lean Tools Currently in practice, there are approximately 25 Lean Tools, out of which, these five tools are considered to be the most critical Lean Tools of all, as shown in above figure. [8] 2.1 Bottleneck Analysis A point of concourse in a machine or system that arises when work load gathers at a point in the system more hastily than that specific point can hope to maintain them. The intricacies fetched about by the bottleneck often make a queue and a longer overall cycle time. By definition, a bottleneck is a phenomenon where the competency of a complete system or line is restricted or limited by a single or limited number of components or resources & analysis of such event is called as Bottleneck Analysis. Hence, Bottleneck Analysis is nothing but the identification of which part/machine of the manufacturing process/line limits the overall output and focuses on improvement the performance of that part/machine of the process/line. [5] Bottleneck Analysis is usually done along with the Time Study Method. The system on which the analysis is required to be done is first selected. Then in the form of ‘Daily Analysis’, ‘Minute to Minute Analysis; or ‘Macro Second Study Analysis’ the entire process is carried out along with the guidance of Time Study Methods. An example of Minute to Minute Bottleneck Analysis is as shown in the figure below Fig -2: Example of Bottleneck Analysis Sheet 2.2 Wastes (MUDA) Anything in the manufacturing process that does not add value to the product from the customer’s perspective is known as Waste. In simple Language, It is nothing but any process for which the customer does not pay the company. There are 7 most Deadly Wastes in common – Fig -3: Seven Deadly Wastes 1.24 To 1.26 2.00 407 1.26 To 1.30 4.00 1.30 To 1.45 1.45 To 1.50 10.00 1.50 To 3.09 3.09 To 3.30 21.00 Down Time: 175Total Time: 510.0 No. of change over Run time = 335 minutes (Total time - Down time ) Operator Away from machine, m/c Stopped 263 no's produced M/c Stopped, Shift Change Tool Change Operator Away from machine, m/c Stopped Tea break Down Time (Min) To 7.00 To 7.34 34.00 7.34 To 7.44 10.00 7.44 To 7.51 7.00 7.51 To 8.10 19.00 8.10 To 8.19 9.00 8.19 To 8.27 8.27 To 8.32 5.00 27 no's produced Machine Stopped, Point problem Single job produced, Lab testing for quality Power Loss Operator Absent, M/c stopped due to power loss Machine Setting and Parameters Checking Time (Min) Remark Operator Absent
  • 3. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _______________________________________________________________________________________ Volume: 03 Issue: 02 | Feb-2014, Available @ http://www.ijret.org 431 1. Transportation - The unnecessary movements of operator, products or components from one place to another result in this waste. Unnecessary transport more commonly occurs together with product damages, lost parts and systems, which are related with movements. [3] 2. Inventory - Inventory is the quantity of materials in stores, which are required to manufacture a job. When they are not used, they take up valuable storage space, may become useless, which cannot be used for more important goods. [3] 3. Motion - This waste comprises of all unnecessary movements occur when operator is moving around his work area and as a result of this; his time & efforts are wasted. All kinds of unnecessary motion may be caused by improper working standard practices, un-optimized process design or work space layout. [3] 4. Waiting - If operators, machine, system or materials of the production process are delayed by any reason, production time is wasted, the productivity is decreased & the cost of production will be increased. 5. Over Processing - It can also mean manufacturing the products of a larger quality than required. This can also be result of not checking what the customers’ real requirements are. [3] 6. Over Production - It arises when the manufacturer is producing more products than the customer really asks for. This is the worst kind of waste, as it generally creates other kinds of wastes. It increases rework factor, material storage, processing, holding & waiting, as well as transportation & unnecessary motion. [3] 7. Defects (Rework, Scrap) - Rework is required when products and components are defective or damaged. Defects are caused by bad manufacturing processes (caused by human or machine errors). In worst case scenario the items have to be discarded. In these 7 wastes, ‘Over Production’ & ‘Inventory’ are observed to be very similar to one another & hence, in modern Lean Methodology, ‘Inventory’ is often replaced by ‘Inspection’. Also, one more waste is being added to these 7 deadly wastes as this waste is also observed to be of great importance, and that is ‘Unutilized Skill’. 2.3 5S An established methodology procreating in Japan that, when implemented, mitigates the waste of resources and work area in spite of increment in manufacturing & operational proficiency. The 5S elements when translated in English are Sort, Set-in-Order, Shine, Standardize & Sustain and are applied in various industries to achieve lean manufacturing & to ultimately improve productivity. [5] Idea of 5S can be explained by following 5 Steps -  Sort: Completely Sort out & classify that which item is required and/or not required in the work area.  Set in Order: Arrange items in required order that are important so that they are ready to find & easy to use.  Shine: Clean the work area, tools, machine & equipments on a continuous basis in order to identify defects& maintain standards.  Standardize: Ensure standard & uniform procedures and methods throughout the operation to promote changeover.  Sustain: Stay to the regulations to maintain the standard & continue to improve every day. [5][6] 2.4 Standardized Work (SDW) Standardized work is a collection and implementation of the best practices known to that point. It includes what is mandatory to begin the procedure and the completed state of the same. Standard Work is the sequential method for defining the best practices and ensuring that every operator is strictly following them to endow the value to the customers. Because improvements in safety, quality, productivity & profitability will arise from time to time & the standardized work is to be updated via work instructions document, training, and practice. These are the methodologies that improve quality, safety, productivity & profitability. Basically, standardized work consists of four elements:  Takt time, which is the rate at which the products must be manufactured in order to meet customer demand on time.  The accurate work sequence in which the operator performs tasks within takt time.  The corresponding inventory, including jobs in machines, required to maintain the process operation smoothly.  The dexterity of the operator & the maneuverability of the machine or system. 2.4.1 Steps Involved in Standardized Work 1. Identify and define the best system that bestows a quality result, consistently. 2. Document the steps for performing the best practice, and make it visual using combination of pictures and text. 3. Place it at each work station where this process is being performed by the operator. 4. Train the operators to do the tasks as defined in the Standard Operating Procedure. Standardized work adds regimentation to the abidance, an element that is frequently neglected but essential for lean to take foundation.
  • 4. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _______________________________________________________________________________________ Volume: 03 Issue: 02 | Feb-2014, Available @ http://www.ijret.org 432 3. WORK STUDY METHODS In order to understand the work study methods, we need to understand the importance of method study and that of time study. ‘Method study’ (sometimes also called Work Method Design) is mostly used to improve the method of doing work. When applied to existing products, method study aims to allocate better methods of manufacturing the jobs that are safe, effective, & economical, require mitigated human effort, and need smaller make-ready time. The better method involves the optimum use of best materials and appropriate manpower so that work is performed in well-organized manner leading to increased resource utilization, optimized quality and appeased costs. Fig -4: Work Study Methods It can therefore be stated that through 'Method study' one can have a systematic way of developing human resource ascendancy, providing elevated machine and equipment use, and making economical use of raw materials. ‘Time study’, however, provides the standard required time, that is the time needed by worker to complete a job by the standard method. By the application of method study and time study together with Lean Tools, any industry can thus achieve greater output at less cost and of better quality, and hence can easily achieve higher productivity. [9] 3.1 Method Study (Work Method Design) Fig -5: Method Study Procedure As seen earlier, Method study focuses to achieve the better method of doing work, and for this reason method study is sometimes called Work Method Design. The following steps depict the procedure for creating a method study. 1. Select (the work to be studied). 2. Record (all relevant information about that work). 3. Examine (the recorded information). 4. Develop (an improved way of doing things). 5. Install (the new method as standard practice) 6. Maintain (the new standard proactive). 3.2 Time Study (Work Measurement) Work measurement refers to the estimation of standard time for an activity that is the time specific for completing one job by using the predicted method. Standard time can be defined as the time utilized by an average experienced skillful operator for the job with provisions for delays beyond the operator’s control. A work has to be measured for the following reasons:  To identify and eliminate missing or ineffective time.  To install standard times for performance & quality measurement.  To measure performance against original expectations.  To set manufacturing & operating objectives. Time study can be simply defined as a technique to estimate the time to be allowed to a qualified and well-trained worker working at a normal pace to complete a specified task by using specified method. Fig -6: Time Study Procedure METHOD STUDY Scrutinizing a Product & searching more proficient methods to carry it. TIME STUDY Deciding the time required to perform a job & its associative precautions. WORK STUDY
  • 5. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _______________________________________________________________________________________ Volume: 03 Issue: 02 | Feb-2014, Available @ http://www.ijret.org 433 4. SETUP TIME REDUCTION (SUR) Setup is a set of activities to be prepared for the next part or process, Whereas, Setup Time is the total elapsed time from completion of the last good part from the previous setup to the completion of the first good part from the new setup. Setup Time Reduction or Change-over Time Reduction is defined as the efficient reduction time to change from the last item of the previous order to the first good item of the next order in order to obtain increased productivity. [11] Setup includes preparation, replacement, location and adjustment activities. In setup reduction process, internal setup activities require an inactive (shut down) process, meaning that no jobs can be manufactured while the setup activity is taking place & external setup activities may be done while the machine is operational. By definition, all activities performed while the machine is not producing parts are considered internal activities. And, all the setup related activities that are performed while the machine is producing good parts (either the previous order or the new order) are considered external activities. Incredible reductions in total setup time have been realized simply by making internal activities external activities. [10] 4.1 Need for Setup Time Reduction Today’s manufacturing and business environments are reaching a point that competition for survival and market share is an obligation. Tracking the global economy will show that being good is not sufficient, therefore every organization really endeavor for transcendence if want to remain in the competition. Why Setup Reduction? Simply - “Equipment and the operator are occupied but there is NO output” Setup Time Reduction is one of the best methods to increase efficiency of the overall plant and thereby improving the profitability. • Setup time reduction improves the equipment availability, increasing the total capacity & results in: – Better utilization of operator’s time. – Better utilization of resources & capital cost. – Reduced capital investment. • Reduced setup time makes smaller batch sizes possible, without the economic penalty, resulting in reduced: – Overall lead times. – Inventory & storage space needs. – Reject rates. Setup Reduction allows batch size reduction, which is critical for continuous flow manufacturing & improves manufacturing flexibility. The following five-step approach to setup reduction may be used to achieve efficient results – Fig -7: Five Step Approach to SUR 5. SUMMARY In summary, with the help of systematic study of all the critical lean tools stated above along with efficient work study methods, the required results of improving productivity can be achieved in limited or very less resources in return. In order to select target for the improvement, method study can firstly be done to obtain accurate results about the system which is crucial for defining the problem. After the corresponding target has been selected, Bottleneck Analysis is the best option to narrow down the area of problem. Once that is done, advanced time study methods are to be implemented to find out detailed problems present in the system. Once the industry gets hold of the detailed problems, they can be categorized in substantial groups in order to maintain their integrity & so that, efficient solution on a particular problem can easily be obtained. With Critical Lean tools stated above, problems can be efficiently classified in corresponding area and those tools can be applied one by one to get long lasting results along with improved productivity as well as profit margin.
  • 6. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _______________________________________________________________________________________ Volume: 03 Issue: 02 | Feb-2014, Available @ http://www.ijret.org 434 CONCLUSIONS From the above paper & Studies, it can be concluded that, Critical lean tools when effectively combined with Work Study Methods, a unique leaner system can be formed which will be the universal solution for any type of industry having any sort of problem regarding the productivity. If implemented in proper order, 100% positive results are assured. REFERENCES [1]. Diane Galarneau and Cécile Dumas, About productivity, Spring 1993 (Vol. 5, No. 1) Article No. 5 [2]. W. Wiyaratn, and A. Watanapa, Improvement Plant Layout Using Systematic Layout Planning (SLP) for Increased Productivity, World Academy of Science, Engineering and Technology, Volume - 48 (2010). [3]. Khalil A. El-Namrouty, Mohammed S. AbuShaaban, Seven wastes elimination targeted by lean manufacturing case study “gaza strip manufacturing firms’’, International Journal of Economics, Finance and Management Sciences (2013). [4]. Ramunė Čiarnienė, Milita Vienažindienė, Lean Manufacturing: Theory and Practice, Economics And Management (2012). [5]. Michal Leporis and Zdenka Králová, A Simulation Approach To Production Line Bottleneck Analysis, International Conference in CYBERNETICS AND INFORMATICS, February (2010). [6]. Derya Sevim Korkut, Nevzat Cakıcıer, E.Seda Erdinler, Göksel Ulay, 5S activities and its application at a sample company, African Journal of Biotechnology, ISSN 1684–5315 © 2009 Academic Journals Vol. 8 (8), 20 April, 2009. [7]. Prof. S. B. Khedkar, Prof. R. D. Thakre, Prof. Y. V. Mahantare, Mr. Ravi Gondne, Study of Implementing 5S Techniques in Plastic Moulding, International Journal of Modern Engineering Research(IJMER) Vol.2, Issue.5, Sep.- Oct. 2012,ISSN: 2249-6645. [8]. David Mann, Creating Lean Culture, Volume I. (Book). [9]. Ralph M. Barnes, Motion and Time Study, 2nd edition, 1940. [10]. Mr. Rahul.R.Joshi, Prof.G.R.Naik, Reduction in Setup Time By SMED A Literature Review, International Journal of Modern Engineering Research (IJMER) Vol.2, Issue.1, Jan- Feb 2012. [11]. Patel Chintan Kumar, Set up Reduction – A perfect way for productivity improvement of computer numerical control (CNC) set up in manufacturing company, Journal of Mechanical Engineering Research, Vol. 5(8), November 2013. BIOGRAPHIES Prathamesh Pramod Kulkarni, Pursuing Final Year in Bachelor of Mechanical Engineering degree from GES’s R.H.S. C.O.E, Nashik, under the affiliation of University of Pune, Maharashtra, India. Sagar Sunil Kshire, Pursuing Final Year in Bachelor of Mechanical Engineering degree from GES’s R.H.S. C.O.E, Nashik, under the affiliation of University of Pune, Maharashtra, India. Prof. Kailas V. Chandratre, B.E. in Production Engineering from K.K.W. College of Engineering, Nashik. (University of Pune). M.E. in Mechanical Engineering from Walchand College of Engineering, Sangli. (Shivaji University) Ph.D. (Pursuing) registered at University of Pune.