The following information is for X Company for 2014: 1. What was the 2014 master (static) budget for total costs? 2. What was the 2014 flexible budget for total costs ? Solution So total master budget = 104760 +181700 = 286460 Total flexible budget cost = 158166+177237 = 335403 .