October 19th, 2012                                                                         ECONOMICS
Parichart Suttiprasit
Electricity Generating Authority of Thailand (EGAT)
CEPSI 2012                                                                                 PERFORMANCE


                                                                                           EFFECTIVE
                                                                                           ASSET
                                                                                           MANAGEMENT




                                          Leading the way to Operational Excellence 2011
Introduction




               2
Leading the way to Operational Excellence 2011   3
Fuel Cost
(THB kWh)
                                                              Replacement
                                                              Energy Gain
                                               Merit Order
             Must Run

                                 Must
                                 Take             Marginal
                                                   Plant




                        Electricity Demand

                                        Coal        Natural
                                                     Gas       Oil


    A   B C D E F G H I         J K L M N O P Q R S T U V W
                                 Power Plants
                                                                     4
Duration      Correct
 Extend?        Seal !

                            OEM
                          Supervisor

 EGAT



How much are
 we losing?


               Leading the way to Operational Excellence 2011   5
Outlines
  Planned
 Outage: off-
    grid
Operation: on-
    grid
 Conclusion
Scheduling
Executing
Function Test
                Leading the way to Operational Excellence 2011
Scheduling   Unit:
             Baht /day




                8
Unit:
Scheduling               Baht /day

                    Year 2012
        AA-C20        11.18

 Mar    April    May     June
 8.18   11.18    11.85   6.75
                                     9
Unit:
Scheduling                                    Baht /day

                             Year 2012
       AA-C20                  11.18




                Leading the way to Operational Excellence 2011   10
Performance                                        Planning
                       Decrease of Efficiency
Heat Rate (kJ/kWh)




                     10300 -                         10285.72

                     10250 -
                                10216.37
                     10200 -
                                                       Current
                         19    199 199 200 200 200 2008
                         95    6   9    1     3
                                   Operation Time (year) 2010
                                                    6
         Assumption: Heat rate has been constantly increased since 1995.
         Source: EGAT production efficiency division, 2006
Decision Making
          Before Outage
          “If main turbine do not overhaul (not remove rotor)”
                                                                  Availability Payment
                                   +   Revenues                    Executing
                                                         Energy Payment
                                             Critical Path Management
                                                                          Replacement
                EP
                EP
           Entire Asset
                                                              Fuel Cost - Energy Cost
                                                                           $3.3 M USD
                                   -      Cost
                                                                          Performance
                                                            O&M Cost +         Lost
                                   - Capital                  Maintenance $2.3 M USD
                                                              -
                                     Charge                           Cost
Reference:                                                         $0.5 M USD
Parichart, S. (2008) Outage optimization of steam turbine and auxiliaries.                     12
Proceedings of 17th Conference of the Electric Power Supply Industry (CEPSI 2008), October. Macao.
Unit:
  Executing                          Baht /day

                            Year 2012
              AA-C20          11.18
     Mar       April    May          June
Duration
     8.18      11.18    11.85        6.75
Extend?
          Critical Path Management               13
Scheduling
Executing
Function Test
                Leading the way to Operational Excellence 2011
Economic Profit (EP) Driver Tree
Strategic Improvement Plan (SIP)


                  Leading the way to Operational Excellence 2011   15
EP Driver Tree &
      SIPs
         EE-C2
         CWPs, CT efficiency Increase
         AA-T1-4
         Fuel Optimize
         BB-C3
         Exhaust Gas Temp. Increase

         Station Service Reduction :
         AA-T2-4, BB-C3-4
         Adjust Fan Blade Angle
         CC-T1-10
         Pump Speed Reduce
         DD-H1-5
         Mini Hydro Turbine Install




                                        14
Strategic Improvement Plans
Year 2012 Forecasted economic profit (rE

              Fuel
            Reduction




Economic          kWh
                increment
  Profit


               PPA
                                   15
358.4
                                                             WN-C3 TIAC system
                                                             BPK-T2-4, BPK-C3-4 MM-T4-                 0.6
                                                             13 Station Service
                                                                                                       2.3
                                                             SNR-1-5 Mini. Hydro TB
                                                                                                     0.71


            Economic                                 kWh
                                                  increment
              Profit                                 408                   45.3 *

                                                                           Outside CAH



                                                PPA                                                   16
Remark: *estimate only generation from Hydro Power Plants according to Internal Power Purchase Agreement
399 *                               SB-C2 CWPs, CT                        4.4
 WN-C3 TIAC system
 BPK-T2-4, BPK-C3-4 MM-T4-      N/A                                BPK-T1-4
                                                Fuel               •Min. Gen.,                          59.4 *
 13 Station Service
 SNR-1-5 Mini. Hydro TB         1.7 *         Reduction
                                                                   •Fuel Optimize (Mixed Fire)
                                                                                                        3.26
                                                                   BPK-C3
                                 0.5                               Exhaust Gas Temp. Increase
                                                                                                        4.0
                                               534


           Economic                                                                        61.9 *

             Profit                                                                        SB-C3
                                                                                        Online Filter
                                                                                          Change


                                 This economic profit is one part of the whole
                                 Fuel Gain of Generation deputy.
Remark:

                                                 PPA
* present the fuel savings from both individual Power Plants and
  Replacement Energy Gain of all power plants                                                           17
Strategic Improvement Plans
Year 2012 Forecasted economic profit (rE

                Fuel
              Reduction

                534


Economic              kWh
                  increment
  Profit              408


           Total Economic Profit = 942 M THB
                 PPA
                                               18
Conclusion

1. Dividing 2 groups: PO and Operation
Key functions are changed depending on duration
                                               Replacement Energy
2. PO duration ;                                    Gain/Loss
Key function : Scheduling->Executing->Function Test

3.Operation duration; Key function is Efficiency & Productivity

     Critical Equipment                        EP driver tree and SIPs
         Series Type                                 are applied

                                   Leading the way to Operational Excellence 2011   19
• Parichart Suttiprasit
• parichart.su@egat.co.th
• Electricity Generating Authority of Thailand
  (EGAT)


                           Leading the way to Operational Excellence 2011

Mais conteúdo relacionado

Mais procurados

1 q08 earnings call presentation
1 q08 earnings call presentation1 q08 earnings call presentation
1 q08 earnings call presentationAES Tietê
 
20110921 opower english_combined
20110921 opower english_combined20110921 opower english_combined
20110921 opower english_combinedcleantechventures
 
Ng Exec Pres. Master (4)
Ng Exec Pres. Master (4)Ng Exec Pres. Master (4)
Ng Exec Pres. Master (4)franciefinn
 
20110928 harasoftware english
20110928 harasoftware english20110928 harasoftware english
20110928 harasoftware englishcleantechventures
 
Grid Connections And PPAs: Tim Foster, Smartest Energy
Grid Connections And PPAs: Tim Foster, Smartest EnergyGrid Connections And PPAs: Tim Foster, Smartest Energy
Grid Connections And PPAs: Tim Foster, Smartest EnergySonia Large
 
Building Energy Rating & Disclosure: A Catalyst for Efficiency
Building Energy Rating & Disclosure: A Catalyst for EfficiencyBuilding Energy Rating & Disclosure: A Catalyst for Efficiency
Building Energy Rating & Disclosure: A Catalyst for EfficiencyCliff Majersik
 
2009 12 08 Nuclear Power International Ed Kee Slides & Notes
2009 12 08 Nuclear Power International   Ed Kee Slides & Notes2009 12 08 Nuclear Power International   Ed Kee Slides & Notes
2009 12 08 Nuclear Power International Ed Kee Slides & NotesEdward Kee
 
public serviceenterprise group MerrillLynch
public serviceenterprise group MerrillLynchpublic serviceenterprise group MerrillLynch
public serviceenterprise group MerrillLynchfinance20
 
Energy Management
Energy ManagementEnergy Management
Energy Managementjbcinvest
 
120208 Property Forum Presentation
120208 Property Forum Presentation120208 Property Forum Presentation
120208 Property Forum PresentationRachaelEdge
 
Presentation of the Annual Results 2009
Presentation of the Annual Results 2009Presentation of the Annual Results 2009
Presentation of the Annual Results 2009COLEXON Energy AG
 
public serviceenterprise group Deutsche
public serviceenterprise group  Deutschepublic serviceenterprise group  Deutsche
public serviceenterprise group Deutschefinance20
 

Mais procurados (17)

1 q08 earnings call presentation
1 q08 earnings call presentation1 q08 earnings call presentation
1 q08 earnings call presentation
 
Annual report
Annual reportAnnual report
Annual report
 
20110921 opower english_combined
20110921 opower english_combined20110921 opower english_combined
20110921 opower english_combined
 
Ng Exec Pres. Master (4)
Ng Exec Pres. Master (4)Ng Exec Pres. Master (4)
Ng Exec Pres. Master (4)
 
20110928 harasoftware english
20110928 harasoftware english20110928 harasoftware english
20110928 harasoftware english
 
Grid Connections And PPAs: Tim Foster, Smartest Energy
Grid Connections And PPAs: Tim Foster, Smartest EnergyGrid Connections And PPAs: Tim Foster, Smartest Energy
Grid Connections And PPAs: Tim Foster, Smartest Energy
 
Building Energy Rating & Disclosure: A Catalyst for Efficiency
Building Energy Rating & Disclosure: A Catalyst for EfficiencyBuilding Energy Rating & Disclosure: A Catalyst for Efficiency
Building Energy Rating & Disclosure: A Catalyst for Efficiency
 
EATON Corporation
EATON CorporationEATON Corporation
EATON Corporation
 
FSM Energy Policy-Summary
FSM Energy Policy-SummaryFSM Energy Policy-Summary
FSM Energy Policy-Summary
 
Ppa Overview Tioga Energy 2009 04 13 2 Ppa 1
Ppa Overview Tioga Energy 2009 04 13 2 Ppa 1Ppa Overview Tioga Energy 2009 04 13 2 Ppa 1
Ppa Overview Tioga Energy 2009 04 13 2 Ppa 1
 
Pirelli Industrial Plan Financials
Pirelli Industrial Plan FinancialsPirelli Industrial Plan Financials
Pirelli Industrial Plan Financials
 
2009 12 08 Nuclear Power International Ed Kee Slides & Notes
2009 12 08 Nuclear Power International   Ed Kee Slides & Notes2009 12 08 Nuclear Power International   Ed Kee Slides & Notes
2009 12 08 Nuclear Power International Ed Kee Slides & Notes
 
public serviceenterprise group MerrillLynch
public serviceenterprise group MerrillLynchpublic serviceenterprise group MerrillLynch
public serviceenterprise group MerrillLynch
 
Energy Management
Energy ManagementEnergy Management
Energy Management
 
120208 Property Forum Presentation
120208 Property Forum Presentation120208 Property Forum Presentation
120208 Property Forum Presentation
 
Presentation of the Annual Results 2009
Presentation of the Annual Results 2009Presentation of the Annual Results 2009
Presentation of the Annual Results 2009
 
public serviceenterprise group Deutsche
public serviceenterprise group  Deutschepublic serviceenterprise group  Deutsche
public serviceenterprise group Deutsche
 

Destaque

Economic selection of type of genration and types of equipment used in power...
 Economic selection of type of genration and types of equipment used in power... Economic selection of type of genration and types of equipment used in power...
Economic selection of type of genration and types of equipment used in power...Madhusudan Sharma
 
Conference ANIMP & ECI Oct 2012 korean companies strategies for overseas cons...
Conference ANIMP & ECI Oct 2012 korean companies strategies for overseas cons...Conference ANIMP & ECI Oct 2012 korean companies strategies for overseas cons...
Conference ANIMP & ECI Oct 2012 korean companies strategies for overseas cons...Antonio Coladarce
 
Thomas Koziarski Consulting brief presentation 2016
Thomas Koziarski Consulting brief presentation 2016Thomas Koziarski Consulting brief presentation 2016
Thomas Koziarski Consulting brief presentation 2016Thomas Frank.
 
Assessment of Risks in International EPC Projects Reference Current Global Ec...
Assessment of Risks in International EPC Projects Reference Current Global Ec...Assessment of Risks in International EPC Projects Reference Current Global Ec...
Assessment of Risks in International EPC Projects Reference Current Global Ec...HIMADRI BANERJI
 
Managing the Construction Lien Process: A Primer on the Lien Act and Recurrin...
Managing the Construction Lien Process: A Primer on the Lien Act and Recurrin...Managing the Construction Lien Process: A Primer on the Lien Act and Recurrin...
Managing the Construction Lien Process: A Primer on the Lien Act and Recurrin...Bodman PLC
 
Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Tahir B Mirza
 
Episode 28 : Project Management Contract
Episode 28 : Project Management ContractEpisode 28 : Project Management Contract
Episode 28 : Project Management ContractSAJJAD KHUDHUR ABBAS
 
Session-02 17-09-2011
Session-02 17-09-2011Session-02 17-09-2011
Session-02 17-09-2011Tahir B Mirza
 
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Antonio Coladarce
 
Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)Roland_Nikles
 
Project Execution & Control Checklist
Project Execution & Control ChecklistProject Execution & Control Checklist
Project Execution & Control ChecklistAnand Subramaniam
 
"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"Abhishek Shah
 
Oil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanOil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanDavid H Moloney
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closuresrinivas2036
 
Construction claims management + project documentation seminar
Construction claims management + project documentation seminarConstruction claims management + project documentation seminar
Construction claims management + project documentation seminarKegler Brown Hill + Ritter
 
7 Steps Project Execution Process
7 Steps Project Execution Process7 Steps Project Execution Process
7 Steps Project Execution ProcessC K Vishwakarma
 
TYPES OF HYDRO POWER PLANTS
TYPES OF HYDRO POWER PLANTSTYPES OF HYDRO POWER PLANTS
TYPES OF HYDRO POWER PLANTSRAJ BAIRWA
 
How to Make Awesome SlideShares: Tips & Tricks
How to Make Awesome SlideShares: Tips & TricksHow to Make Awesome SlideShares: Tips & Tricks
How to Make Awesome SlideShares: Tips & TricksSlideShare
 
Getting Started With SlideShare
Getting Started With SlideShareGetting Started With SlideShare
Getting Started With SlideShareSlideShare
 

Destaque (20)

Economic selection of type of genration and types of equipment used in power...
 Economic selection of type of genration and types of equipment used in power... Economic selection of type of genration and types of equipment used in power...
Economic selection of type of genration and types of equipment used in power...
 
Conference ANIMP & ECI Oct 2012 korean companies strategies for overseas cons...
Conference ANIMP & ECI Oct 2012 korean companies strategies for overseas cons...Conference ANIMP & ECI Oct 2012 korean companies strategies for overseas cons...
Conference ANIMP & ECI Oct 2012 korean companies strategies for overseas cons...
 
Thomas Koziarski Consulting brief presentation 2016
Thomas Koziarski Consulting brief presentation 2016Thomas Koziarski Consulting brief presentation 2016
Thomas Koziarski Consulting brief presentation 2016
 
claims management framework
 claims management framework claims management framework
claims management framework
 
Assessment of Risks in International EPC Projects Reference Current Global Ec...
Assessment of Risks in International EPC Projects Reference Current Global Ec...Assessment of Risks in International EPC Projects Reference Current Global Ec...
Assessment of Risks in International EPC Projects Reference Current Global Ec...
 
Managing the Construction Lien Process: A Primer on the Lien Act and Recurrin...
Managing the Construction Lien Process: A Primer on the Lien Act and Recurrin...Managing the Construction Lien Process: A Primer on the Lien Act and Recurrin...
Managing the Construction Lien Process: A Primer on the Lien Act and Recurrin...
 
Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)
 
Episode 28 : Project Management Contract
Episode 28 : Project Management ContractEpisode 28 : Project Management Contract
Episode 28 : Project Management Contract
 
Session-02 17-09-2011
Session-02 17-09-2011Session-02 17-09-2011
Session-02 17-09-2011
 
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
 
Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)
 
Project Execution & Control Checklist
Project Execution & Control ChecklistProject Execution & Control Checklist
Project Execution & Control Checklist
 
"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"
 
Oil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanOil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution Plan
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 
Construction claims management + project documentation seminar
Construction claims management + project documentation seminarConstruction claims management + project documentation seminar
Construction claims management + project documentation seminar
 
7 Steps Project Execution Process
7 Steps Project Execution Process7 Steps Project Execution Process
7 Steps Project Execution Process
 
TYPES OF HYDRO POWER PLANTS
TYPES OF HYDRO POWER PLANTSTYPES OF HYDRO POWER PLANTS
TYPES OF HYDRO POWER PLANTS
 
How to Make Awesome SlideShares: Tips & Tricks
How to Make Awesome SlideShares: Tips & TricksHow to Make Awesome SlideShares: Tips & Tricks
How to Make Awesome SlideShares: Tips & Tricks
 
Getting Started With SlideShare
Getting Started With SlideShareGetting Started With SlideShare
Getting Started With SlideShare
 

Semelhante a How Economic Value Management can be Applied to Power Plant Management

EAM ASE Breakfast Seminar NSW - April 2008
EAM ASE Breakfast Seminar NSW - April 2008EAM ASE Breakfast Seminar NSW - April 2008
EAM ASE Breakfast Seminar NSW - April 2008jmortensen
 
energy future holindings 040108_Conf_Call_Deck_FINAL
energy future holindings 040108_Conf_Call_Deck_FINALenergy future holindings 040108_Conf_Call_Deck_FINAL
energy future holindings 040108_Conf_Call_Deck_FINALfinance29
 
energy future holindings 040108_Conf_Call_Deck_FINAL
energy future holindings 040108_Conf_Call_Deck_FINALenergy future holindings 040108_Conf_Call_Deck_FINAL
energy future holindings 040108_Conf_Call_Deck_FINALfinance29
 
4 q07 and 2007 earnings call presentation
4 q07 and 2007 earnings call presentation4 q07 and 2007 earnings call presentation
4 q07 and 2007 earnings call presentationAES Tietê
 
4Q08 and 2008 Earnings Results
4Q08 and 2008 Earnings Results4Q08 and 2008 Earnings Results
4Q08 and 2008 Earnings ResultsAES Tietê
 
03/30/2009 - 4Q08 and 2008 Earnings Results
03/30/2009  	-   	4Q08 and 2008 Earnings Results03/30/2009  	-   	4Q08 and 2008 Earnings Results
03/30/2009 - 4Q08 and 2008 Earnings ResultsAES Tietê
 
4 q08 and 2008 earnings results
4 q08 and 2008 earnings results4 q08 and 2008 earnings results
4 q08 and 2008 earnings resultsAES Tietê
 
Energy Conservation For Liu
Energy Conservation For LiuEnergy Conservation For Liu
Energy Conservation For Liurolewis1
 
Duurzaam The Electrification Of The Vehicle Driveline, Han Automotive
Duurzaam   The Electrification Of The Vehicle Driveline, Han AutomotiveDuurzaam   The Electrification Of The Vehicle Driveline, Han Automotive
Duurzaam The Electrification Of The Vehicle Driveline, Han AutomotiveHans Mestrum videofilm expert
 
2 q08 earnings call presentation
2 q08 earnings call presentation2 q08 earnings call presentation
2 q08 earnings call presentationAES Tietê
 
EnVogue July'14 Edition #EnergyEfficiency #EETPL #India
EnVogue July'14 Edition #EnergyEfficiency #EETPL #IndiaEnVogue July'14 Edition #EnergyEfficiency #EETPL #India
EnVogue July'14 Edition #EnergyEfficiency #EETPL #IndiaUmesh Bhutoria
 
Mercedes-Benz "E-Mobility - The Way into the Future"
Mercedes-Benz "E-Mobility - The Way into the Future"Mercedes-Benz "E-Mobility - The Way into the Future"
Mercedes-Benz "E-Mobility - The Way into the Future"accessio
 
Green Key Performance Indicators for Healthcare
Green Key Performance Indicators for HealthcareGreen Key Performance Indicators for Healthcare
Green Key Performance Indicators for HealthcareGraham Takata
 
ENVOGUE - Energy Trending!
ENVOGUE - Energy Trending!ENVOGUE - Energy Trending!
ENVOGUE - Energy Trending!Umesh Bhutoria
 
A 5 auction results
A 5 auction resultsA 5 auction results
A 5 auction resultsMPX_RI
 
Power LifeMax* - Solutions for B/E Gas Turbine Fleet
Power LifeMax* - Solutions forB/E Gas Turbine FleetPower LifeMax* - Solutions forB/E Gas Turbine Fleet
Power LifeMax* - Solutions for B/E Gas Turbine FleetGE_India
 

Semelhante a How Economic Value Management can be Applied to Power Plant Management (20)

Resd technologies-epri
Resd technologies-epriResd technologies-epri
Resd technologies-epri
 
GCCSI Financial Model Case Study
GCCSI Financial Model Case StudyGCCSI Financial Model Case Study
GCCSI Financial Model Case Study
 
EAM ASE Breakfast Seminar NSW - April 2008
EAM ASE Breakfast Seminar NSW - April 2008EAM ASE Breakfast Seminar NSW - April 2008
EAM ASE Breakfast Seminar NSW - April 2008
 
energy future holindings 040108_Conf_Call_Deck_FINAL
energy future holindings 040108_Conf_Call_Deck_FINALenergy future holindings 040108_Conf_Call_Deck_FINAL
energy future holindings 040108_Conf_Call_Deck_FINAL
 
energy future holindings 040108_Conf_Call_Deck_FINAL
energy future holindings 040108_Conf_Call_Deck_FINALenergy future holindings 040108_Conf_Call_Deck_FINAL
energy future holindings 040108_Conf_Call_Deck_FINAL
 
4 q07 and 2007 earnings call presentation
4 q07 and 2007 earnings call presentation4 q07 and 2007 earnings call presentation
4 q07 and 2007 earnings call presentation
 
4Q08 and 2008 Earnings Results
4Q08 and 2008 Earnings Results4Q08 and 2008 Earnings Results
4Q08 and 2008 Earnings Results
 
03/30/2009 - 4Q08 and 2008 Earnings Results
03/30/2009  	-   	4Q08 and 2008 Earnings Results03/30/2009  	-   	4Q08 and 2008 Earnings Results
03/30/2009 - 4Q08 and 2008 Earnings Results
 
4 q08 and 2008 earnings results
4 q08 and 2008 earnings results4 q08 and 2008 earnings results
4 q08 and 2008 earnings results
 
Energy Conservation For Liu
Energy Conservation For LiuEnergy Conservation For Liu
Energy Conservation For Liu
 
Duurzaam The Electrification Of The Vehicle Driveline, Han Automotive
Duurzaam   The Electrification Of The Vehicle Driveline, Han AutomotiveDuurzaam   The Electrification Of The Vehicle Driveline, Han Automotive
Duurzaam The Electrification Of The Vehicle Driveline, Han Automotive
 
2 q08 earnings call presentation
2 q08 earnings call presentation2 q08 earnings call presentation
2 q08 earnings call presentation
 
EnVogue July'14 Edition #EnergyEfficiency #EETPL #India
EnVogue July'14 Edition #EnergyEfficiency #EETPL #IndiaEnVogue July'14 Edition #EnergyEfficiency #EETPL #India
EnVogue July'14 Edition #EnergyEfficiency #EETPL #India
 
Mercedes-Benz "E-Mobility - The Way into the Future"
Mercedes-Benz "E-Mobility - The Way into the Future"Mercedes-Benz "E-Mobility - The Way into the Future"
Mercedes-Benz "E-Mobility - The Way into the Future"
 
Boma 2011 presentation
Boma 2011 presentationBoma 2011 presentation
Boma 2011 presentation
 
Green Key Performance Indicators for Healthcare
Green Key Performance Indicators for HealthcareGreen Key Performance Indicators for Healthcare
Green Key Performance Indicators for Healthcare
 
ENVOGUE - Energy Trending!
ENVOGUE - Energy Trending!ENVOGUE - Energy Trending!
ENVOGUE - Energy Trending!
 
A 5 auction results
A 5 auction resultsA 5 auction results
A 5 auction results
 
BHEL CCDP audit
BHEL CCDP auditBHEL CCDP audit
BHEL CCDP audit
 
Power LifeMax* - Solutions for B/E Gas Turbine Fleet
Power LifeMax* - Solutions forB/E Gas Turbine FleetPower LifeMax* - Solutions forB/E Gas Turbine Fleet
Power LifeMax* - Solutions for B/E Gas Turbine Fleet
 

Mais de Par Sut

SOCIAL CROWDFUNDING: a case study of EGAT invention making a positive impact...
SOCIAL CROWDFUNDING:  a case study of EGAT invention making a positive impact...SOCIAL CROWDFUNDING:  a case study of EGAT invention making a positive impact...
SOCIAL CROWDFUNDING: a case study of EGAT invention making a positive impact...Par Sut
 
MMSMC-KOTRA20210825submit.pdf
MMSMC-KOTRA20210825submit.pdfMMSMC-KOTRA20210825submit.pdf
MMSMC-KOTRA20210825submit.pdfPar Sut
 
ทิศทางพลังงานของประเทศไทย
ทิศทางพลังงานของประเทศไทยทิศทางพลังงานของประเทศไทย
ทิศทางพลังงานของประเทศไทยPar Sut
 
ThaiPBS-EnergyThai-GreenhouseGasMitigation from @EnergyTH
 ThaiPBS-EnergyThai-GreenhouseGasMitigation  from @EnergyTH  ThaiPBS-EnergyThai-GreenhouseGasMitigation  from @EnergyTH
ThaiPBS-EnergyThai-GreenhouseGasMitigation from @EnergyTH Par Sut
 
ThaiPBS-EnergyThai-GreenhouseGasMitigation
ThaiPBS-EnergyThai-GreenhouseGasMitigationThaiPBS-EnergyThai-GreenhouseGasMitigation
ThaiPBS-EnergyThai-GreenhouseGasMitigationPar Sut
 
CEPSI2008 parichart
CEPSI2008 parichartCEPSI2008 parichart
CEPSI2008 parichartPar Sut
 
สถานการณ์โรงไฟฟ้าในประเทศไทย
สถานการณ์โรงไฟฟ้าในประเทศไทยสถานการณ์โรงไฟฟ้าในประเทศไทย
สถานการณ์โรงไฟฟ้าในประเทศไทยPar Sut
 

Mais de Par Sut (7)

SOCIAL CROWDFUNDING: a case study of EGAT invention making a positive impact...
SOCIAL CROWDFUNDING:  a case study of EGAT invention making a positive impact...SOCIAL CROWDFUNDING:  a case study of EGAT invention making a positive impact...
SOCIAL CROWDFUNDING: a case study of EGAT invention making a positive impact...
 
MMSMC-KOTRA20210825submit.pdf
MMSMC-KOTRA20210825submit.pdfMMSMC-KOTRA20210825submit.pdf
MMSMC-KOTRA20210825submit.pdf
 
ทิศทางพลังงานของประเทศไทย
ทิศทางพลังงานของประเทศไทยทิศทางพลังงานของประเทศไทย
ทิศทางพลังงานของประเทศไทย
 
ThaiPBS-EnergyThai-GreenhouseGasMitigation from @EnergyTH
 ThaiPBS-EnergyThai-GreenhouseGasMitigation  from @EnergyTH  ThaiPBS-EnergyThai-GreenhouseGasMitigation  from @EnergyTH
ThaiPBS-EnergyThai-GreenhouseGasMitigation from @EnergyTH
 
ThaiPBS-EnergyThai-GreenhouseGasMitigation
ThaiPBS-EnergyThai-GreenhouseGasMitigationThaiPBS-EnergyThai-GreenhouseGasMitigation
ThaiPBS-EnergyThai-GreenhouseGasMitigation
 
CEPSI2008 parichart
CEPSI2008 parichartCEPSI2008 parichart
CEPSI2008 parichart
 
สถานการณ์โรงไฟฟ้าในประเทศไทย
สถานการณ์โรงไฟฟ้าในประเทศไทยสถานการณ์โรงไฟฟ้าในประเทศไทย
สถานการณ์โรงไฟฟ้าในประเทศไทย
 

Último

How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityEric T. Tung
 
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165meghakumariji156
 
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGBerhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGpr788182
 
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...pujan9679
 
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGParadip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGpr788182
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptxnandhinijagan9867
 
Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingNauman Safdar
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...daisycvs
 
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All TimeCall 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Timegargpaaro
 
Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024Marel
 
New 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck TemplateNew 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck TemplateCannaBusinessPlans
 
JAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR ESCORTS
JAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR  ESCORTSJAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR  ESCORTS
JAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR ESCORTSkajalroy875762
 
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur DubaiUAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubaijaehdlyzca
 
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizharallensay1
 
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAIGetting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAITim Wilson
 
Arti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfArti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfwill854175
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxCynthia Clay
 
PHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPanhandleOilandGas
 

Último (20)

How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
 
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGBerhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
 
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGParadip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptx
 
Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All TimeCall 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
 
WheelTug Short Pitch Deck 2024 | Byond Insights
WheelTug Short Pitch Deck 2024 | Byond InsightsWheelTug Short Pitch Deck 2024 | Byond Insights
WheelTug Short Pitch Deck 2024 | Byond Insights
 
Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024
 
New 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck TemplateNew 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck Template
 
JAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR ESCORTS
JAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR  ESCORTSJAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR  ESCORTS
JAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR ESCORTS
 
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur DubaiUAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
 
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
 
HomeRoots Pitch Deck | Investor Insights | April 2024
HomeRoots Pitch Deck | Investor Insights | April 2024HomeRoots Pitch Deck | Investor Insights | April 2024
HomeRoots Pitch Deck | Investor Insights | April 2024
 
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAIGetting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
 
Arti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfArti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdf
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
PHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation Final
 

How Economic Value Management can be Applied to Power Plant Management

  • 1. October 19th, 2012 ECONOMICS Parichart Suttiprasit Electricity Generating Authority of Thailand (EGAT) CEPSI 2012 PERFORMANCE EFFECTIVE ASSET MANAGEMENT Leading the way to Operational Excellence 2011
  • 3. Leading the way to Operational Excellence 2011 3
  • 4. Fuel Cost (THB kWh) Replacement Energy Gain Merit Order Must Run Must Take Marginal Plant Electricity Demand Coal Natural Gas Oil A B C D E F G H I J K L M N O P Q R S T U V W Power Plants 4
  • 5. Duration Correct Extend? Seal ! OEM Supervisor EGAT How much are we losing? Leading the way to Operational Excellence 2011 5
  • 6. Outlines Planned Outage: off- grid Operation: on- grid Conclusion
  • 7. Scheduling Executing Function Test Leading the way to Operational Excellence 2011
  • 8. Scheduling Unit: Baht /day 8
  • 9. Unit: Scheduling Baht /day Year 2012 AA-C20 11.18 Mar April May June 8.18 11.18 11.85 6.75 9
  • 10. Unit: Scheduling Baht /day Year 2012 AA-C20 11.18 Leading the way to Operational Excellence 2011 10
  • 11. Performance Planning  Decrease of Efficiency Heat Rate (kJ/kWh) 10300 - 10285.72 10250 - 10216.37 10200 - Current 19 199 199 200 200 200 2008 95 6 9 1 3 Operation Time (year) 2010 6 Assumption: Heat rate has been constantly increased since 1995. Source: EGAT production efficiency division, 2006
  • 12. Decision Making Before Outage “If main turbine do not overhaul (not remove rotor)” Availability Payment + Revenues Executing Energy Payment Critical Path Management Replacement EP EP Entire Asset Fuel Cost - Energy Cost $3.3 M USD - Cost Performance O&M Cost + Lost - Capital Maintenance $2.3 M USD - Charge Cost Reference: $0.5 M USD Parichart, S. (2008) Outage optimization of steam turbine and auxiliaries. 12 Proceedings of 17th Conference of the Electric Power Supply Industry (CEPSI 2008), October. Macao.
  • 13. Unit: Executing Baht /day Year 2012 AA-C20 11.18 Mar April May June Duration 8.18 11.18 11.85 6.75 Extend? Critical Path Management 13
  • 14. Scheduling Executing Function Test Leading the way to Operational Excellence 2011
  • 15. Economic Profit (EP) Driver Tree Strategic Improvement Plan (SIP) Leading the way to Operational Excellence 2011 15
  • 16. EP Driver Tree & SIPs EE-C2 CWPs, CT efficiency Increase AA-T1-4 Fuel Optimize BB-C3 Exhaust Gas Temp. Increase Station Service Reduction : AA-T2-4, BB-C3-4 Adjust Fan Blade Angle CC-T1-10 Pump Speed Reduce DD-H1-5 Mini Hydro Turbine Install 14
  • 17. Strategic Improvement Plans Year 2012 Forecasted economic profit (rE Fuel Reduction Economic kWh increment Profit PPA 15
  • 18. 358.4 WN-C3 TIAC system BPK-T2-4, BPK-C3-4 MM-T4- 0.6 13 Station Service 2.3 SNR-1-5 Mini. Hydro TB 0.71 Economic kWh increment Profit 408 45.3 * Outside CAH PPA 16 Remark: *estimate only generation from Hydro Power Plants according to Internal Power Purchase Agreement
  • 19. 399 * SB-C2 CWPs, CT 4.4 WN-C3 TIAC system BPK-T2-4, BPK-C3-4 MM-T4- N/A BPK-T1-4 Fuel •Min. Gen., 59.4 * 13 Station Service SNR-1-5 Mini. Hydro TB 1.7 * Reduction •Fuel Optimize (Mixed Fire) 3.26 BPK-C3 0.5 Exhaust Gas Temp. Increase 4.0 534 Economic 61.9 * Profit SB-C3 Online Filter Change This economic profit is one part of the whole Fuel Gain of Generation deputy. Remark: PPA * present the fuel savings from both individual Power Plants and Replacement Energy Gain of all power plants 17
  • 20. Strategic Improvement Plans Year 2012 Forecasted economic profit (rE Fuel Reduction 534 Economic kWh increment Profit 408 Total Economic Profit = 942 M THB PPA 18
  • 21. Conclusion 1. Dividing 2 groups: PO and Operation Key functions are changed depending on duration Replacement Energy 2. PO duration ; Gain/Loss Key function : Scheduling->Executing->Function Test 3.Operation duration; Key function is Efficiency & Productivity Critical Equipment EP driver tree and SIPs Series Type are applied Leading the way to Operational Excellence 2011 19
  • 22. • Parichart Suttiprasit • parichart.su@egat.co.th • Electricity Generating Authority of Thailand (EGAT) Leading the way to Operational Excellence 2011

Notas do Editor

  1. “เพิ่มผลผลิต” ดูในกรอบของการเพิ่มSpinning reserve  เพิ่มความมั่นคงของระบบ แต่ยังไม่ได้มองไปถึงว่าส่วนที่เพิ่มนั้นจะถึงปลายทาง ขายจริงได้หรือไม่ ขายได้ต้องเดินโรงนั้น ช่วงความต้องการเพิ่ม อาจเรียกเดินโรงไฟฟ้า IPPแต่เพื่อให้มองเห็นตัวเลขการเพิ่มมูลค่า จึงคำนวณแบบคาดการณ์ โดย 2.56 Baht/kWh (ของจริงคือ…..)c