1. Integration management
2. Scope management
3. Time management
4. Cost management
5. Quality management
6. Human resources management
7. Communications management
8. Risk management
9. Procurement management
10. Stakeholder management
Project Management Knowledge Areas
PMI PMBOK 5th edition
• Coordination and balancing of all project activities
• Responsibility: project manager
• Less detailed than other knowledge areas
• Very important segment of the PMP examination
Project Integration Management
1. Develop Project Charter
2. Develop Project Management Plan
3. Direct and Manage Project Work
4. Monitor and Control Project Work
5. Perform Integrated Change Control
6. Close Project or Phase
Project Integration Management Processes:
Develop Project Charter
Inputs
• Project statement of work
• Business case
• Agreements
• Enterprise environmental
factors
• Organizational process assets
Tools and Techniques
• Expert judgment
• Facilitation techniques
Outputs
• Project charter
Develop Project
Charter
Develop Project
Management
Plan
Direct and
Manage Project
Work
Monitor and
Control Project
Work
Perform
Integrated
Change Control
Close Project or
Phase
Develop Project Charter: Data Flow
Develop Project
charter
Develop Project
management
plan
Collect
Requirements
Define Scope
Plan Schedule
Management
Plan Cost
Management
Plan Risk
Management
Identify
stakeholders
Plan Scope
Management
Project Initiator /
Sponsor
Enterprise /
Organization
Project Integration Management
• Project charter
• Agreements
• Business case
• Project SoW
• OPA
• EEF
Approved Project charter Start Project!
Develop Project Management Plan
Inputs
• Project charter
• Outputs from other
processes
• Enterprise environmental
factors
• Organizational process assets
Tools and Techniques
• Expert judgment
• Facilitation techniques
Outputs
• Project management plan
Develop Project
Charter
Develop Project
Management
Plan
Direct and
Manage Project
Work
Monitor and
Control Project
Work
Perform
Integrated
Change Control
Close Project or
Phase
Develop Project Management Plan: Data Flow
Develop Project
Management
Plan
Develop
Project
charter
Plan Scope
Management
Outputs from
Other Processes
Enterprise /
Organization
Project Integration Management
• Project charter• OPA
• EEF
Control scope
Plan Schedule
Management
Control
Schedule
Plan Cost
Management
Control Costs
Plan Quality
Management
Plan HR
Management
Plan Comm’s
Management
Control
Communic.
Plan Risk
Management
Control Risks
Plan Procur.
Management
Control
Procurements
Close
Procurements
Plan Stahek.
Management
Ctrl. Stakeh.
Engagement
Direct and
manage
project work
Monitor and
control
project work
• Project management plan
• Communications management plan
• Cost management plan
• Human resource plan
• Procurement management plan
• Process improvement plan
• Quality management plan
• Requirements management plan
• Risk management plan
• Schedule management plan
• Scope management plan
• Stakeholder management plan
• Cost baseline
• Schedule baseline
• Scope baseline
• Project management plan updates
Perform
Integrated
Change Ctrl
Close Project
or Phase
Direct and Manage Project Work
Inputs
• Project management plan
• Approved change requests
• Enterprise environmental
factors
• Organizational process assets
Tools and Techniques
• Expert judgment
• Project management
information system
• Meetings
Outputs
• Deliverables
• Work performance data
• Change requests
• Project management plan
updates
• Project documents updates
Develop Project
Charter
Develop Project
Management
Plan
Direct and
Manage Project
Work
Monitor and
Control Project
Work
Perform
Integrated
Change Control
Close Project or
Phase
Direct and Manage Project Work: Data Flow
Direct and
Manage
Project Work
Perform
Integr. Chg.
Control
Enterprise /
Organization
Project Integration Management
• Approved
change requests
• OPA
• EEF
Validate Scope
Control Scope
Control Schedule
Control Costs
Control
Communications
Control Risks
Control
Procurements
Control Stakeh.
Engagement
Control Quality
Develop
Project
Mgmt Plan
• Project mgmt
plan updates
Project Documents
• Project
management plan
• Change requests
• Project documents
updates
• Deliverables
• Work performance data
Monitor and Control Project Work
Inputs
• Project management plan
• Schedule forecasts
• Cost forecasts
• Validated changes
• Work performance
information
• Enterprise environmental
factors
• Organizational process assets
Tools and Techniques
• Expert judgment
• Analytical techniques
• Project management
information system
• Meetings
Outputs
• Change requests
• Work performance reports
• Project management plan
updates
• Project documents updates
Develop Project
Charter
Develop Project
Management
Plan
Direct and
Manage Project
Work
Monitor and
Control Project
Work
Perform
Integrated
Change Control
Close Project or
Phase
• Work performance
information
Monitor and Control Project Work: Data Flow
Monitor and
Control Project
Work
Perform
Integr. Chg.
Control
Enterprise /
Organization
Project Integration Management
• Change requests
• Work performance reports
• OPA
• EEF
Manage Project
Team
Manage
Communications
Control Risks
Control
Procurements
Develop
Project
Mgmt Plan
• Project mgmt
plan updates
Project Documents
• Project
management plan
• Project documents
updates
Validate Scope
Control Scope
Control
Communications
Control Risks
Control
Procurements
Control Stakeh.
Engagement
Control Schedule
Control Costs
Control Quality
• Schedule forecasts
• Cost forecasts
• Validated changes
• Work performance reports
Perform Integrated Change Conrol
Inputs
• Project management plan
• Work performance reports
• Change requests
• Enterprise environmental
factors
• Organizational process assets
Tools and Techniques
• Expert judgment
• Meetings
• Change control tools
Outputs
• Approved change requests
• Change log
• Project management plan
updates
• Project documents updates
Develop Project
Charter
Develop Project
Management
Plan
Direct and
Manage Project
Work
Monitor and
Control Project
Work
Perform
Integrated
Change Control
Close Project or
Phase
Perform Integrated Change Control: Data Flow
Perform
Integrated
Change Control
Monitor and
Control
Project Work
Validate
Scope
Enterprise /
Organization Project Integration Management
• OPA
• EEF
Control scope
Control
Schedule
Control Costs
Perform Qual.
Assurance
Control
Quality
Manage
Project Team
Control
Communic.
Control Risks
Plan Procur.
Management
Conduct
Procurements
Ctrl. Stakeh.
Engagement
Develop
Project
Manag. Plan
Direct and
Manage
Project Work
• Project
management plan
Mng. Stakeh.
Engagement
Control
Procurements
Control
Quality
Control
Procurements
Mng. Stakeh.
Engagement
Project
Documents
• Project management
plan updates
• Change requests
• Work performance
reports
• Change requests
• Project documents
updates
• Change log
• Approved change
requests
• Change requests
Close Project or Phase
Inputs
• Project management plan
• Accepted deliverables
• Organizational process assets
Tools and Techniques
• Expert judgment
• Analytical techniques
• Meetings
Outputs
• Final product, service or
result transition
• Organizational process assets
updates
Develop Project
Charter
Develop Project
Management
Plan
Direct and
Manage Project
Work
Monitor and
Control Project
Work
Perform
Integrated
Change Control
Close Project or
Phase
Close Project or Phase: Data Flow
Close Project or
Phase
Develop Project
management
plan
Validate Scope
Customer
Enterprise /
Organization
Project Integration Management
• Project
management plan
• Accepted
deliverables
• OPA
• OPA updates
• Final product, service
or result transition
• The Project charter is:
A. Developed before the project statement of work, and after the project
management plan.
B. Developed after the project statement of work and before the project
management plan
C. Developed before the contract and after the project management plan
D. Developed before the project and before the project management plan
Sample question #1
• The Project charter is:
A. Developed before the project statement of work, and after the project
management plan.
B. Developed after the project statement of work and before the project
management plan
C. Developed before the contract and after the project management plan
D. Developed before the project and before the project management plan
Sample question #1
• A project is plagued by changes to the project charter. Who has the
primary responsibility to decide if these changes are necessary?
A. The project manager
B. The project team
C. The sponsor
D. The stakeholders
Sample question #2
• A project is plagued by changes to the project charter. Who has the
primary responsibility to decide if these changes are necessary?
A. The project manager
B. The project team
C. The sponsor
D. The stakeholders
Sample question #2
• During project executing, the project manager determines that a
change is needed to material purchased for the project. The project
manager calls a meeting of the team to plan how to make the change.
This is an example of:
A. Management by objectives
B. Lack of a change management plan
C. Good team relations
D. Lack of a clear work breakdown structure
Sample question #3
• During project executing, the project manager determines that a
change is needed to material purchased for the project. The project
manager calls a meeting of the team to plan how to make the change.
This is an example of:
A. Management by objectives
B. Lack of a change management plan
C. Good team relations
D. Lack of a clear work breakdown structure
Sample question #3
• When it comes to changes, the project manager's attention is BEST
given to:
A. Making changes
B. Tracking and recording changes
C. Informing the sponsor of changes
D. Preventing unnecessary changes
Sample question #4
• When it comes to changes, the project manager's attention is BEST
given to:
A. Making changes
B. Tracking and recording changes
C. Informing the sponsor of changes
D. Preventing unnecessary changes
Sample question #4
• Project management plan updates are NOT an output of:
A. Perform Integrated Change Control
B. Develop Project Plan
C. Direct and Manage Project Execution
D. Close Project or Phase
Sample question #5
• Project management plan updates are NOT an output of:
A. Perform Integrated Change Control
B. Develop Project Plan
C. Direct and Manage Project Execution
D. Close Project or Phase
Sample question #5
• An output of the Close Project or Phase process is the creation of:
A. Project archives
B. A project charter
C. A project management plan
D. A risk analysis plan
Sample question #6
• An output of the Close Project or Phase process is the creation of:
A. Project archives
B. A project charter
C. A project management plan
D. A risk analysis plan
Sample question #6
• If you are creating a single document to guide project execution,
monitoring and control and closure, you are creating:
A. The execution plan
B. The project management plan
C. The integration plan
D. The project framework
Sample question #7
• If you are creating a single document to guide project execution,
monitoring and control and closure, you are creating:
A. The execution plan
B. The project management plan
C. The integration plan
D. The project framework
Sample question #7
• A project management plan should be realistic in order to be used to
manage the project. Which of the following is the BEST method to achieve a
realistic project management plan?
A. Sponsor creates the project management plan based on input from the project
manager
B. Functional manager creates the project management plan based on input from
the project manager
C. Project manager creates the project management plan based on input from
senior management
D. Project manager creates the project management plan based on input from the
team
Sample question #8
• A project management plan should be realistic in order to be used to
manage the project. Which of the following is the BEST method to achieve a
realistic project management plan?
A. Sponsor creates the project management plan based on input from the project
manager
B. Functional manager creates the project management plan based on input from
the project manager
C. Project manager creates the project management plan based on input from
senior management
D. Project manager creates the project management plan based on input from the
team
Sample question #8
• A defect in the product was brought to the project manager's
attention and now the project team is engaged in repairing it. Which
project management process would be the most applicable to this?
A. Perform Integrated Change Control
B. Monitor and Control Project Work
C. Direct and Manage Project Execution
D. Close Project or Phase
Sample question #9
• A defect in the product was brought to the project manager's
attention and now the project team is engaged in repairing it. Which
project management process would be the most applicable to this?
A. Perform Integrated Change Control
B. Monitor and Control Project Work
C. Direct and Manage Project Execution
D. Close Project or Phase
Sample question #9
• Which of the following BEST describes the project manager's role as
an integrator?
A. Help team members become familiar with the project
B. Put all the pieces of a project into a cohesive whole
C. Put all the pieces of a project into a program
D. Get all team members together into a cohesive whole
Sample question #10
• Which of the following BEST describes the project manager's role as
an integrator?
A. Help team members become familiar with the project
B. Put all the pieces of a project into a cohesive whole
C. Put all the pieces of a project into a program
D. Get all team members together into a cohesive whole
Sample question #10
• Theory vs Reality
• Studying resources
• Preparation for the testing day
• The test itself: stress, time & energy management
Tips & Tricks
Vladimir VUJOVIĆ, PMP E-mail: vladimir.vujovic@gmail.com
SAP Project Manager
Delhaize Serbia
Sources used:
PMBOK Guide, 5th Edition
Rita Mulcahy’s PMP Exam Prep, 8th Edition
Good Luck!

Mais conteúdo relacionado

Mais procurados

Project Procurement Management - PMP preparation course
Project Procurement Management - PMP preparation courseProject Procurement Management - PMP preparation course
Project Procurement Management - PMP preparation courseVladimir Vujovic
 
PMP Chap 12 - Project Procurement Management Details - Part2
PMP   Chap 12 - Project Procurement Management Details - Part2PMP   Chap 12 - Project Procurement Management Details - Part2
PMP Chap 12 - Project Procurement Management Details - Part2Anand Bobade
 
Project integration management
Project integration managementProject integration management
Project integration managementSaad Al Jabri
 
Practical Project Management - full course
Practical Project Management - full coursePractical Project Management - full course
Practical Project Management - full courseMarten Schoonman
 
PMO View Interactive Dashboard
PMO View Interactive DashboardPMO View Interactive Dashboard
PMO View Interactive DashboardMatt Angerer
 
Chap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project workChap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project workAnand Bobade
 
PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1Anand Bobade
 
Project integration management
Project  integration managementProject  integration management
Project integration managementdeep sharma
 
Chap 12.3 Control Procurement
Chap 12.3 Control ProcurementChap 12.3 Control Procurement
Chap 12.3 Control ProcurementAnand Bobade
 
Project integration management
Project integration managementProject integration management
Project integration managementPrabudh Dhingra
 
Project Integration Management
Project Integration ManagementProject Integration Management
Project Integration Managementpankajsh10
 
Project Management Fundamentals | Project Management Simplified | PMP® Traini...
Project Management Fundamentals | Project Management Simplified | PMP® Traini...Project Management Fundamentals | Project Management Simplified | PMP® Traini...
Project Management Fundamentals | Project Management Simplified | PMP® Traini...Edureka!
 
PMP Knowledge Areas - PMBOK 6 (PMI) INFOGRAPHIC
PMP Knowledge Areas  - PMBOK 6  (PMI)   INFOGRAPHICPMP Knowledge Areas  - PMBOK 6  (PMI)   INFOGRAPHIC
PMP Knowledge Areas - PMBOK 6 (PMI) INFOGRAPHICJonathan Donado
 
Project Management Framework - PMBOK 5
Project Management Framework - PMBOK 5Project Management Framework - PMBOK 5
Project Management Framework - PMBOK 5pankajsh10
 
Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7Saad Merie
 
PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...
PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...
PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...Edureka!
 

Mais procurados (20)

Project Procurement Management - PMP preparation course
Project Procurement Management - PMP preparation courseProject Procurement Management - PMP preparation course
Project Procurement Management - PMP preparation course
 
PMP Chap 12 - Project Procurement Management Details - Part2
PMP   Chap 12 - Project Procurement Management Details - Part2PMP   Chap 12 - Project Procurement Management Details - Part2
PMP Chap 12 - Project Procurement Management Details - Part2
 
Project integration management
Project integration managementProject integration management
Project integration management
 
Practical Project Management - full course
Practical Project Management - full coursePractical Project Management - full course
Practical Project Management - full course
 
PMO View Interactive Dashboard
PMO View Interactive DashboardPMO View Interactive Dashboard
PMO View Interactive Dashboard
 
Chap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project workChap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project work
 
2_Project Scope Management
2_Project Scope Management2_Project Scope Management
2_Project Scope Management
 
Project management
Project managementProject management
Project management
 
PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1
 
Project integration management
Project  integration managementProject  integration management
Project integration management
 
041006-Program Management PMI NB - PMI Logo
041006-Program Management PMI NB - PMI Logo041006-Program Management PMI NB - PMI Logo
041006-Program Management PMI NB - PMI Logo
 
Chap 12.3 Control Procurement
Chap 12.3 Control ProcurementChap 12.3 Control Procurement
Chap 12.3 Control Procurement
 
Project integration management
Project integration managementProject integration management
Project integration management
 
Project Integration Management
Project Integration ManagementProject Integration Management
Project Integration Management
 
Project Management Fundamentals | Project Management Simplified | PMP® Traini...
Project Management Fundamentals | Project Management Simplified | PMP® Traini...Project Management Fundamentals | Project Management Simplified | PMP® Traini...
Project Management Fundamentals | Project Management Simplified | PMP® Traini...
 
PMP Knowledge Areas - PMBOK 6 (PMI) INFOGRAPHIC
PMP Knowledge Areas  - PMBOK 6  (PMI)   INFOGRAPHICPMP Knowledge Areas  - PMBOK 6  (PMI)   INFOGRAPHIC
PMP Knowledge Areas - PMBOK 6 (PMI) INFOGRAPHIC
 
Project Management Framework - PMBOK 5
Project Management Framework - PMBOK 5Project Management Framework - PMBOK 5
Project Management Framework - PMBOK 5
 
Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7
 
PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...
PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...
PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...
 
Pmbok 5 ed diagram
Pmbok 5 ed diagramPmbok 5 ed diagram
Pmbok 5 ed diagram
 

Destaque

PMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT Summary
PMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT SummaryPMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT Summary
PMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT SummaryYudha Pratama, PMP
 
PMP Exam Prep - Communications Management
PMP Exam Prep - Communications ManagementPMP Exam Prep - Communications Management
PMP Exam Prep - Communications Managementtkrikau
 
5.communication management
5.communication management5.communication management
5.communication managementPanos Fitsilis
 
Pmbok 4th edition chapter 4 - Project Integration Management
Pmbok 4th edition   chapter 4 - Project Integration Management Pmbok 4th edition   chapter 4 - Project Integration Management
Pmbok 4th edition chapter 4 - Project Integration Management Ahmad Maharma, PMP,RMP
 
Project Management Framework automation for Project and Portfolio Management ...
Project Management Framework automation for Project and Portfolio Management ...Project Management Framework automation for Project and Portfolio Management ...
Project Management Framework automation for Project and Portfolio Management ...PMILebanonChapter
 
Webinar como lograr ser pmp
Webinar como lograr ser pmpWebinar como lograr ser pmp
Webinar como lograr ser pmpitService ®
 
PMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration ManagementPMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration ManagementMohamed Loey
 
Day 3-6 - Final Revision (HR)
Day 3-6 - Final Revision (HR)Day 3-6 - Final Revision (HR)
Day 3-6 - Final Revision (HR)Jeffrey Cheah
 
Day 3-7 - Final Revision (Communications)
Day 3-7 - Final Revision (Communications)Day 3-7 - Final Revision (Communications)
Day 3-7 - Final Revision (Communications)Jeffrey Cheah
 
ISSUE & WIKI based Integration of Project Management
ISSUE & WIKI based Integration of Project ManagementISSUE & WIKI based Integration of Project Management
ISSUE & WIKI based Integration of Project ManagementPeter Kim
 
Day 3-4 - Final Revision (Cost)
Day 3-4 - Final Revision (Cost)Day 3-4 - Final Revision (Cost)
Day 3-4 - Final Revision (Cost)Jeffrey Cheah
 
Tuckman's group development (Storming)
Tuckman's group development (Storming)Tuckman's group development (Storming)
Tuckman's group development (Storming)Jeffrey Cheah
 
Day 1 - 3PM Revision
Day 1 - 3PM RevisionDay 1 - 3PM Revision
Day 1 - 3PM RevisionJeffrey Cheah
 
Day 3-10 - Final Revision (Stakeholder)
Day 3-10 - Final Revision (Stakeholder)Day 3-10 - Final Revision (Stakeholder)
Day 3-10 - Final Revision (Stakeholder)Jeffrey Cheah
 

Destaque (20)

PMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT Summary
PMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT SummaryPMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT Summary
PMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT Summary
 
PMP Exam Prep - Communications Management
PMP Exam Prep - Communications ManagementPMP Exam Prep - Communications Management
PMP Exam Prep - Communications Management
 
PMP_Project Time Management
PMP_Project Time ManagementPMP_Project Time Management
PMP_Project Time Management
 
3.time management
3.time management3.time management
3.time management
 
Pmp quality management
Pmp quality managementPmp quality management
Pmp quality management
 
5.communication management
5.communication management5.communication management
5.communication management
 
Pmbok 4th edition chapter 4 - Project Integration Management
Pmbok 4th edition   chapter 4 - Project Integration Management Pmbok 4th edition   chapter 4 - Project Integration Management
Pmbok 4th edition chapter 4 - Project Integration Management
 
Project Management Framework automation for Project and Portfolio Management ...
Project Management Framework automation for Project and Portfolio Management ...Project Management Framework automation for Project and Portfolio Management ...
Project Management Framework automation for Project and Portfolio Management ...
 
Webinar como lograr ser pmp
Webinar como lograr ser pmpWebinar como lograr ser pmp
Webinar como lograr ser pmp
 
PMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration ManagementPMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration Management
 
Day 3-6 - Final Revision (HR)
Day 3-6 - Final Revision (HR)Day 3-6 - Final Revision (HR)
Day 3-6 - Final Revision (HR)
 
Time Masterclass
Time MasterclassTime Masterclass
Time Masterclass
 
Day 3-7 - Final Revision (Communications)
Day 3-7 - Final Revision (Communications)Day 3-7 - Final Revision (Communications)
Day 3-7 - Final Revision (Communications)
 
ISSUE & WIKI based Integration of Project Management
ISSUE & WIKI based Integration of Project ManagementISSUE & WIKI based Integration of Project Management
ISSUE & WIKI based Integration of Project Management
 
Day 3-4 - Final Revision (Cost)
Day 3-4 - Final Revision (Cost)Day 3-4 - Final Revision (Cost)
Day 3-4 - Final Revision (Cost)
 
Quality Masterclass
Quality MasterclassQuality Masterclass
Quality Masterclass
 
Tuckman's group development (Storming)
Tuckman's group development (Storming)Tuckman's group development (Storming)
Tuckman's group development (Storming)
 
Day 2 - Revision
Day 2 - RevisionDay 2 - Revision
Day 2 - Revision
 
Day 1 - 3PM Revision
Day 1 - 3PM RevisionDay 1 - 3PM Revision
Day 1 - 3PM Revision
 
Day 3-10 - Final Revision (Stakeholder)
Day 3-10 - Final Revision (Stakeholder)Day 3-10 - Final Revision (Stakeholder)
Day 3-10 - Final Revision (Stakeholder)
 

Semelhante a Project Integration Management - PMP Preparation

pmicertificationpreparationintegrationmanagementvvujovic20170307-170308083758...
pmicertificationpreparationintegrationmanagementvvujovic20170307-170308083758...pmicertificationpreparationintegrationmanagementvvujovic20170307-170308083758...
pmicertificationpreparationintegrationmanagementvvujovic20170307-170308083758...RaheelMuhammad5
 
Project_Integration_Managemen.pptx
Project_Integration_Managemen.pptxProject_Integration_Managemen.pptx
Project_Integration_Managemen.pptxIvarsLinde1
 
Undestand PMBok 5th, Section 4
Undestand PMBok 5th, Section 4Undestand PMBok 5th, Section 4
Undestand PMBok 5th, Section 4Amr Miqdadi
 
Pmp training sigmora
Pmp training sigmoraPmp training sigmora
Pmp training sigmorabgadicha
 
CAPM Exam preparation - series 1
CAPM Exam preparation - series 1CAPM Exam preparation - series 1
CAPM Exam preparation - series 1Toe Myint Naing
 
122 Part 1 - GuideFigure 4-15. Close Project or Phase Dat.docx
122 Part 1 - GuideFigure 4-15. Close Project or Phase Dat.docx122 Part 1 - GuideFigure 4-15. Close Project or Phase Dat.docx
122 Part 1 - GuideFigure 4-15. Close Project or Phase Dat.docxRAJU852744
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project ManagementRasan Samarasinghe
 
07. Project Integration Management
07. Project Integration Management07. Project Integration Management
07. Project Integration ManagementBhuWan Khadka
 
Kick-Off Meeting Template for Project Management
Kick-Off Meeting Template for Project ManagementKick-Off Meeting Template for Project Management
Kick-Off Meeting Template for Project Managementzjcin
 
Fundamentals of Project Management
Fundamentals of Project Management Fundamentals of Project Management
Fundamentals of Project Management Yesica Adicondro
 
04 projectintegrationmanagement
04 projectintegrationmanagement04 projectintegrationmanagement
04 projectintegrationmanagementDhamo daran
 
Fundamentalsof PM.pptx
Fundamentalsof PM.pptxFundamentalsof PM.pptx
Fundamentalsof PM.pptxagathamarlinee
 
2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptx2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptxProfDrAnbalaganChinn
 
PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principlestltiede
 

Semelhante a Project Integration Management - PMP Preparation (20)

pmicertificationpreparationintegrationmanagementvvujovic20170307-170308083758...
pmicertificationpreparationintegrationmanagementvvujovic20170307-170308083758...pmicertificationpreparationintegrationmanagementvvujovic20170307-170308083758...
pmicertificationpreparationintegrationmanagementvvujovic20170307-170308083758...
 
Project_Integration_Managemen.pptx
Project_Integration_Managemen.pptxProject_Integration_Managemen.pptx
Project_Integration_Managemen.pptx
 
Undestand PMBok 5th, Section 4
Undestand PMBok 5th, Section 4Undestand PMBok 5th, Section 4
Undestand PMBok 5th, Section 4
 
Pmp training sigmora
Pmp training sigmoraPmp training sigmora
Pmp training sigmora
 
Lecture 2.pptx
Lecture 2.pptxLecture 2.pptx
Lecture 2.pptx
 
CAPM Exam preparation - series 1
CAPM Exam preparation - series 1CAPM Exam preparation - series 1
CAPM Exam preparation - series 1
 
04 project integration management
04 project integration management04 project integration management
04 project integration management
 
PMP Prep Handout_Integration
PMP Prep Handout_IntegrationPMP Prep Handout_Integration
PMP Prep Handout_Integration
 
122 Part 1 - GuideFigure 4-15. Close Project or Phase Dat.docx
122 Part 1 - GuideFigure 4-15. Close Project or Phase Dat.docx122 Part 1 - GuideFigure 4-15. Close Project or Phase Dat.docx
122 Part 1 - GuideFigure 4-15. Close Project or Phase Dat.docx
 
Session 22 4th edition PMP
Session 22 4th edition PMPSession 22 4th edition PMP
Session 22 4th edition PMP
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project Management
 
07. Project Integration Management
07. Project Integration Management07. Project Integration Management
07. Project Integration Management
 
05 project scope management
05 project scope management05 project scope management
05 project scope management
 
Kick-Off Meeting Template for Project Management
Kick-Off Meeting Template for Project ManagementKick-Off Meeting Template for Project Management
Kick-Off Meeting Template for Project Management
 
Fundamentals of Project Management
Fundamentals of Project Management Fundamentals of Project Management
Fundamentals of Project Management
 
04 projectintegrationmanagement
04 projectintegrationmanagement04 projectintegrationmanagement
04 projectintegrationmanagement
 
Fundamentalsof PM.pptx
Fundamentalsof PM.pptxFundamentalsof PM.pptx
Fundamentalsof PM.pptx
 
05 project scope management
05 project scope management05 project scope management
05 project scope management
 
2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptx2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptx
 
PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principles
 

Último

Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentationuneakwhite
 
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)Adnet Communications
 
Over the Top (OTT) Market Size & Growth Outlook 2024-2030
Over the Top (OTT) Market Size & Growth Outlook 2024-2030Over the Top (OTT) Market Size & Growth Outlook 2024-2030
Over the Top (OTT) Market Size & Growth Outlook 2024-2030tarushabhavsar
 
Arti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfArti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfwill854175
 
Falcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon investment
 
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...Falcon Invoice Discounting
 
Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingNauman Safdar
 
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 MonthsSEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 MonthsIndeedSEO
 
TVB_The Vietnam Believer Newsletter_May 6th, 2024_ENVol. 006.pdf
TVB_The Vietnam Believer Newsletter_May 6th, 2024_ENVol. 006.pdfTVB_The Vietnam Believer Newsletter_May 6th, 2024_ENVol. 006.pdf
TVB_The Vietnam Believer Newsletter_May 6th, 2024_ENVol. 006.pdfbelieveminhh
 
Structuring and Writing DRL Mckinsey (1).pdf
Structuring and Writing DRL Mckinsey (1).pdfStructuring and Writing DRL Mckinsey (1).pdf
Structuring and Writing DRL Mckinsey (1).pdflaloo_007
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityEric T. Tung
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1kcpayne
 
Falcon Invoice Discounting: Aviate Your Cash Flow Challenges
Falcon Invoice Discounting: Aviate Your Cash Flow ChallengesFalcon Invoice Discounting: Aviate Your Cash Flow Challenges
Falcon Invoice Discounting: Aviate Your Cash Flow Challengeshemanthkumar470700
 
Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon investment
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfAdmir Softic
 
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...ssuserf63bd7
 
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...meghakumariji156
 
Rice Manufacturers in India | Shree Krishna Exports
Rice Manufacturers in India | Shree Krishna ExportsRice Manufacturers in India | Shree Krishna Exports
Rice Manufacturers in India | Shree Krishna ExportsShree Krishna Exports
 
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All TimeCall 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Timegargpaaro
 

Último (20)

Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentation
 
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
 
Over the Top (OTT) Market Size & Growth Outlook 2024-2030
Over the Top (OTT) Market Size & Growth Outlook 2024-2030Over the Top (OTT) Market Size & Growth Outlook 2024-2030
Over the Top (OTT) Market Size & Growth Outlook 2024-2030
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
Arti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfArti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdf
 
Falcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business Growth
 
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
 
Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
 
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 MonthsSEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
 
TVB_The Vietnam Believer Newsletter_May 6th, 2024_ENVol. 006.pdf
TVB_The Vietnam Believer Newsletter_May 6th, 2024_ENVol. 006.pdfTVB_The Vietnam Believer Newsletter_May 6th, 2024_ENVol. 006.pdf
TVB_The Vietnam Believer Newsletter_May 6th, 2024_ENVol. 006.pdf
 
Structuring and Writing DRL Mckinsey (1).pdf
Structuring and Writing DRL Mckinsey (1).pdfStructuring and Writing DRL Mckinsey (1).pdf
Structuring and Writing DRL Mckinsey (1).pdf
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1
 
Falcon Invoice Discounting: Aviate Your Cash Flow Challenges
Falcon Invoice Discounting: Aviate Your Cash Flow ChallengesFalcon Invoice Discounting: Aviate Your Cash Flow Challenges
Falcon Invoice Discounting: Aviate Your Cash Flow Challenges
 
Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business Potential
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
 
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
 
Rice Manufacturers in India | Shree Krishna Exports
Rice Manufacturers in India | Shree Krishna ExportsRice Manufacturers in India | Shree Krishna Exports
Rice Manufacturers in India | Shree Krishna Exports
 
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All TimeCall 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
 

Project Integration Management - PMP Preparation

  • 1. Presented by: Vladimir Vujović, PMP PMI Certification Preparation: PMP / CAPM - Project Integration Management - Project Management Institute, Inc. All rights reserved.
  • 2. • Presenter • Participants: profile, background, expectations • Session: structure, approach and benefits Introduction to the session
  • 3. 1. Integration management 2. Scope management 3. Time management 4. Cost management 5. Quality management 6. Human resources management 7. Communications management 8. Risk management 9. Procurement management 10. Stakeholder management Project Management Knowledge Areas PMI PMBOK 5th edition
  • 4. • Coordination and balancing of all project activities • Responsibility: project manager • Less detailed than other knowledge areas • Very important segment of the PMP examination Project Integration Management
  • 5. 1. Develop Project Charter 2. Develop Project Management Plan 3. Direct and Manage Project Work 4. Monitor and Control Project Work 5. Perform Integrated Change Control 6. Close Project or Phase Project Integration Management Processes:
  • 6. Develop Project Charter Inputs • Project statement of work • Business case • Agreements • Enterprise environmental factors • Organizational process assets Tools and Techniques • Expert judgment • Facilitation techniques Outputs • Project charter Develop Project Charter Develop Project Management Plan Direct and Manage Project Work Monitor and Control Project Work Perform Integrated Change Control Close Project or Phase
  • 7. Develop Project Charter: Data Flow Develop Project charter Develop Project management plan Collect Requirements Define Scope Plan Schedule Management Plan Cost Management Plan Risk Management Identify stakeholders Plan Scope Management Project Initiator / Sponsor Enterprise / Organization Project Integration Management • Project charter • Agreements • Business case • Project SoW • OPA • EEF Approved Project charter Start Project!
  • 8. Develop Project Management Plan Inputs • Project charter • Outputs from other processes • Enterprise environmental factors • Organizational process assets Tools and Techniques • Expert judgment • Facilitation techniques Outputs • Project management plan Develop Project Charter Develop Project Management Plan Direct and Manage Project Work Monitor and Control Project Work Perform Integrated Change Control Close Project or Phase
  • 9. Develop Project Management Plan: Data Flow Develop Project Management Plan Develop Project charter Plan Scope Management Outputs from Other Processes Enterprise / Organization Project Integration Management • Project charter• OPA • EEF Control scope Plan Schedule Management Control Schedule Plan Cost Management Control Costs Plan Quality Management Plan HR Management Plan Comm’s Management Control Communic. Plan Risk Management Control Risks Plan Procur. Management Control Procurements Close Procurements Plan Stahek. Management Ctrl. Stakeh. Engagement Direct and manage project work Monitor and control project work • Project management plan • Communications management plan • Cost management plan • Human resource plan • Procurement management plan • Process improvement plan • Quality management plan • Requirements management plan • Risk management plan • Schedule management plan • Scope management plan • Stakeholder management plan • Cost baseline • Schedule baseline • Scope baseline • Project management plan updates Perform Integrated Change Ctrl Close Project or Phase
  • 10. Direct and Manage Project Work Inputs • Project management plan • Approved change requests • Enterprise environmental factors • Organizational process assets Tools and Techniques • Expert judgment • Project management information system • Meetings Outputs • Deliverables • Work performance data • Change requests • Project management plan updates • Project documents updates Develop Project Charter Develop Project Management Plan Direct and Manage Project Work Monitor and Control Project Work Perform Integrated Change Control Close Project or Phase
  • 11. Direct and Manage Project Work: Data Flow Direct and Manage Project Work Perform Integr. Chg. Control Enterprise / Organization Project Integration Management • Approved change requests • OPA • EEF Validate Scope Control Scope Control Schedule Control Costs Control Communications Control Risks Control Procurements Control Stakeh. Engagement Control Quality Develop Project Mgmt Plan • Project mgmt plan updates Project Documents • Project management plan • Change requests • Project documents updates • Deliverables • Work performance data
  • 12. Monitor and Control Project Work Inputs • Project management plan • Schedule forecasts • Cost forecasts • Validated changes • Work performance information • Enterprise environmental factors • Organizational process assets Tools and Techniques • Expert judgment • Analytical techniques • Project management information system • Meetings Outputs • Change requests • Work performance reports • Project management plan updates • Project documents updates Develop Project Charter Develop Project Management Plan Direct and Manage Project Work Monitor and Control Project Work Perform Integrated Change Control Close Project or Phase
  • 13. • Work performance information Monitor and Control Project Work: Data Flow Monitor and Control Project Work Perform Integr. Chg. Control Enterprise / Organization Project Integration Management • Change requests • Work performance reports • OPA • EEF Manage Project Team Manage Communications Control Risks Control Procurements Develop Project Mgmt Plan • Project mgmt plan updates Project Documents • Project management plan • Project documents updates Validate Scope Control Scope Control Communications Control Risks Control Procurements Control Stakeh. Engagement Control Schedule Control Costs Control Quality • Schedule forecasts • Cost forecasts • Validated changes • Work performance reports
  • 14. Perform Integrated Change Conrol Inputs • Project management plan • Work performance reports • Change requests • Enterprise environmental factors • Organizational process assets Tools and Techniques • Expert judgment • Meetings • Change control tools Outputs • Approved change requests • Change log • Project management plan updates • Project documents updates Develop Project Charter Develop Project Management Plan Direct and Manage Project Work Monitor and Control Project Work Perform Integrated Change Control Close Project or Phase
  • 15. Perform Integrated Change Control: Data Flow Perform Integrated Change Control Monitor and Control Project Work Validate Scope Enterprise / Organization Project Integration Management • OPA • EEF Control scope Control Schedule Control Costs Perform Qual. Assurance Control Quality Manage Project Team Control Communic. Control Risks Plan Procur. Management Conduct Procurements Ctrl. Stakeh. Engagement Develop Project Manag. Plan Direct and Manage Project Work • Project management plan Mng. Stakeh. Engagement Control Procurements Control Quality Control Procurements Mng. Stakeh. Engagement Project Documents • Project management plan updates • Change requests • Work performance reports • Change requests • Project documents updates • Change log • Approved change requests • Change requests
  • 16. Close Project or Phase Inputs • Project management plan • Accepted deliverables • Organizational process assets Tools and Techniques • Expert judgment • Analytical techniques • Meetings Outputs • Final product, service or result transition • Organizational process assets updates Develop Project Charter Develop Project Management Plan Direct and Manage Project Work Monitor and Control Project Work Perform Integrated Change Control Close Project or Phase
  • 17. Close Project or Phase: Data Flow Close Project or Phase Develop Project management plan Validate Scope Customer Enterprise / Organization Project Integration Management • Project management plan • Accepted deliverables • OPA • OPA updates • Final product, service or result transition
  • 18. • The Project charter is: A. Developed before the project statement of work, and after the project management plan. B. Developed after the project statement of work and before the project management plan C. Developed before the contract and after the project management plan D. Developed before the project and before the project management plan Sample question #1
  • 19. • The Project charter is: A. Developed before the project statement of work, and after the project management plan. B. Developed after the project statement of work and before the project management plan C. Developed before the contract and after the project management plan D. Developed before the project and before the project management plan Sample question #1
  • 20. • A project is plagued by changes to the project charter. Who has the primary responsibility to decide if these changes are necessary? A. The project manager B. The project team C. The sponsor D. The stakeholders Sample question #2
  • 21. • A project is plagued by changes to the project charter. Who has the primary responsibility to decide if these changes are necessary? A. The project manager B. The project team C. The sponsor D. The stakeholders Sample question #2
  • 22. • During project executing, the project manager determines that a change is needed to material purchased for the project. The project manager calls a meeting of the team to plan how to make the change. This is an example of: A. Management by objectives B. Lack of a change management plan C. Good team relations D. Lack of a clear work breakdown structure Sample question #3
  • 23. • During project executing, the project manager determines that a change is needed to material purchased for the project. The project manager calls a meeting of the team to plan how to make the change. This is an example of: A. Management by objectives B. Lack of a change management plan C. Good team relations D. Lack of a clear work breakdown structure Sample question #3
  • 24. • When it comes to changes, the project manager's attention is BEST given to: A. Making changes B. Tracking and recording changes C. Informing the sponsor of changes D. Preventing unnecessary changes Sample question #4
  • 25. • When it comes to changes, the project manager's attention is BEST given to: A. Making changes B. Tracking and recording changes C. Informing the sponsor of changes D. Preventing unnecessary changes Sample question #4
  • 26. • Project management plan updates are NOT an output of: A. Perform Integrated Change Control B. Develop Project Plan C. Direct and Manage Project Execution D. Close Project or Phase Sample question #5
  • 27. • Project management plan updates are NOT an output of: A. Perform Integrated Change Control B. Develop Project Plan C. Direct and Manage Project Execution D. Close Project or Phase Sample question #5
  • 28. • An output of the Close Project or Phase process is the creation of: A. Project archives B. A project charter C. A project management plan D. A risk analysis plan Sample question #6
  • 29. • An output of the Close Project or Phase process is the creation of: A. Project archives B. A project charter C. A project management plan D. A risk analysis plan Sample question #6
  • 30. • If you are creating a single document to guide project execution, monitoring and control and closure, you are creating: A. The execution plan B. The project management plan C. The integration plan D. The project framework Sample question #7
  • 31. • If you are creating a single document to guide project execution, monitoring and control and closure, you are creating: A. The execution plan B. The project management plan C. The integration plan D. The project framework Sample question #7
  • 32. • A project management plan should be realistic in order to be used to manage the project. Which of the following is the BEST method to achieve a realistic project management plan? A. Sponsor creates the project management plan based on input from the project manager B. Functional manager creates the project management plan based on input from the project manager C. Project manager creates the project management plan based on input from senior management D. Project manager creates the project management plan based on input from the team Sample question #8
  • 33. • A project management plan should be realistic in order to be used to manage the project. Which of the following is the BEST method to achieve a realistic project management plan? A. Sponsor creates the project management plan based on input from the project manager B. Functional manager creates the project management plan based on input from the project manager C. Project manager creates the project management plan based on input from senior management D. Project manager creates the project management plan based on input from the team Sample question #8
  • 34. • A defect in the product was brought to the project manager's attention and now the project team is engaged in repairing it. Which project management process would be the most applicable to this? A. Perform Integrated Change Control B. Monitor and Control Project Work C. Direct and Manage Project Execution D. Close Project or Phase Sample question #9
  • 35. • A defect in the product was brought to the project manager's attention and now the project team is engaged in repairing it. Which project management process would be the most applicable to this? A. Perform Integrated Change Control B. Monitor and Control Project Work C. Direct and Manage Project Execution D. Close Project or Phase Sample question #9
  • 36. • Which of the following BEST describes the project manager's role as an integrator? A. Help team members become familiar with the project B. Put all the pieces of a project into a cohesive whole C. Put all the pieces of a project into a program D. Get all team members together into a cohesive whole Sample question #10
  • 37. • Which of the following BEST describes the project manager's role as an integrator? A. Help team members become familiar with the project B. Put all the pieces of a project into a cohesive whole C. Put all the pieces of a project into a program D. Get all team members together into a cohesive whole Sample question #10
  • 38. • Theory vs Reality • Studying resources • Preparation for the testing day • The test itself: stress, time & energy management Tips & Tricks
  • 39. Vladimir VUJOVIĆ, PMP E-mail: vladimir.vujovic@gmail.com SAP Project Manager Delhaize Serbia Sources used: PMBOK Guide, 5th Edition Rita Mulcahy’s PMP Exam Prep, 8th Edition Good Luck!

Notas do Editor

  1. How presentation will benefit audience: Adult learners are more interested in a subject if they know how or why it is important to them. Presenter’s level of expertise in the subject: Briefly state your credentials in this area, or explain why participants should listen to you.
  2. Lesson descriptions should be brief.
  3. Example objectives At the end of this lesson, you will be able to: Save files to the team Web server. Move files to different locations on the team Web server. Share files on the team Web server.