SlideShare uma empresa Scribd logo
1 de 21
PMP Exam
Preparation
Eng. Shamil Habet; MSc; PMP; JPE
Based on PMBOK 6th
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 1
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
Initiating a Project
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 2
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
PROJECT SELECTION METHODS
1- Numeric Methods
 Benefit Measurement Model (also called Comparative approach)
 PresentValue (PV) (PV = FV / (1+r)^n), (Select the project with highest PV)
 Net PresentValue (NPV), (Select the project with highest NPV)
 Return On Investment (ROI), (Select the project with highest ROI)
 Internal Rate of Return (IRR), (Select the project with highest IRR)
 Pay-Back Period (PBP), (Select the project with lowest PBP)
 Benefit-Cost Ratio, (Select the project with highest BCR; BCR>1 Good; BCR<1 Bad)
 Cost-Benefit Ratio, (Select the project with lowest CBR; CBR>1 Bad; CBR<1 Good)
 Mathematical Models (also called Constrained Optimization)
Use linear, dynamic, non-linear, multi-objective programming to solve problem.
2- Non Numeric Method
 Sacred cow: Senior Management wants it; it may often turn out well; many visionary
projects start here
 Murder Board: Also known as a "scrub-down", is a committee of questioners set up to
critically review a proposal and/or help someone prepare for a difficult oral examination.
 Operating Necessity: The project is required to keep the system running
 Competitive Necessity: Project is necessary to sustain a competitive position
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 3
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
SCORING MODEL WEIGHTED CRITERIA
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 4
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
DEVELOP PROJECT CHARTER
Project Charter: A document issued by the project initiator or sponsor
(Some times Called Project Champion) that formally authorizes the existence of
a project and provides the project manager with the authority to apply
organizational resources to project activities. This process is performed
once or at predefined points in the project.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 5
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
The key benefits of developing Project Charter:
 Provides a direct link between the project and the strategic objectives of
the organization,
 Creates a formal record of the project
 Shows the organizational commitment to the project
DEVELOP PROJECT CHARTER
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 6
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
Business Case: The approved business case, or similar, is the business
document most commonly used to create the project charter. The business
case describes the necessary information from a business standpoint to
determine whether the expected outcomes of the project justify the required
investment. The business case is created as a result of one or more
of the following:
 Government regulations
 Strategic opportunity
 Organizational need
 Ecological impacts
 Competition
 Politics
DEVELOP PROJECT CHARTER (Inputs)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 7
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 Agreements are used to define initial intentions for a project.
Agreements may take the form of:
 Contracts, (used when a project is being performed for an external customer)
 Memorandums of understanding (MOUs),
 Service level agreements (SLA),
 Letters of agreement,
 Letters of intent, verbal agreements,
 E-mail, or other written agreements.
DEVELOP PROJECT CHARTER (Inputs)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 8
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 Expert Judgment is defined as judgment provided based upon expertise in an
application area, Knowledge Area, discipline, industry, etc., as appropriate for the
activity being performed. Such expertise may be provided by any group or
person with specialized education, knowledge, skill, experience, or training.
 Facilitation: The ability to effectively guide a group event to a successful
decision, solution, or conclusion. A facilitator ensures that there is effective
participation, that participants achieve a mutual understanding, that all
contributions are considered, that conclusions or results have full buy-in
according to the decision process established for the project, and that the
actions and agreements achieved are appropriately dealt with afterward.
 Data-GatheringTechniques: (To be Described Later)
 Meetings: For this process, meetings are held with key stakeholders to
identify the project objectives, success criteria, key deliverables, high-level
requirements, summary milestones, and other summary information.
DEVELOP PROJECT CHARTER (Tools & Techniques)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 9
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 Project Charter documents the high-level information on the project and
on the product, service, or result the project is intended to satisfy, such as:
 Project purpose;
 Measurable project objectives and related success criteria;
 High-level requirements;
 High-level project description, boundaries, and key deliverables;
 Overall project risk;
 Summary milestone schedule;
 Preapproved financial resources;
 Key stakeholder list;
 Project approval requirements (i.e., what constitutes project success, who
decides the project is successful, and who signs off on the project);
 Project exit criteria (i.e., what are the conditions to be met in order to
close or to cancel the project or phase);
 Assigned project manager, responsibility, and authority level;
 Name and authority of the sponsor or other person(s) authorizing the
project charter.
DEVELOP PROJECT CHARTER (Outputs)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 10
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 Assumption Log:
High-level strategic and operational assumptions and constraints are
normally identified in the business case before the project is initiated and will
flow into the project charter.
Important Notes:
- Lower-level activity and task assumptions are generated throughout
the project such as defining technical specifications, estimates, the
schedule, risks, etc.
- Assumption Log is used to record all assumptions and constraints
throughout the project life cycle.
DEVELOP PROJECT CHARTER (Outputs)
ID Category/
Impact
Assumption or
Constraint
Responsible
Party
Due Date Actions Status Comments
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 11
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
DEVELOP PROJECT CHARTER (Outputs)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 12
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
IDENTIFY STAKEHOLDERS
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 13
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
Identify Stakeholders is the process of identifying project stakeholders
regularly and analyzing and documenting relevant information regarding their
interests, involvement, interdependencies, influence, and potential impact on
project success.
The key benefit of this process is that it enables the project team to identify
the appropriate focus for engagement of each stakeholder or group of
stakeholders. This process is performed periodically throughout the
project as needed.
IDENTIFY STAKEHOLDERS
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 14
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 Meetings: Meetings are used to develop an understanding of significant
project stakeholders. They can take the form of facilitation workshops,
small group guided discussions, and virtual groups using electronics or
social media technologies to share ideas and analyze data.
 Data Analysis techniques that can be used for this process include but
are not limited to:
- Document Analysis: Assessing the available project documentation
and lessons learned from previous projects to identify stakeholders and
other supporting information.
- Stakeholder Analysis: results in a list of stakeholders and relevant
information such as their positions in the organization, roles on the
project, “stakes,” expectations, attitudes (their levels of support for the
project), and their interest in information about the project.
Stakeholders’ stakes can include but are not limited to a combination of:
IDENTIFY STAKEHOLDERS (Tools & Techniques)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 15
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 Interest: A person or group can be affected by a decision related to the
project or its outcomes.
 Rights (legal or moral rights): Legal rights, such as occupational health
and safety, may be defined in the legislation framework of a country.
Moral rights may involve concepts of protection of historical sites or
environmental sustainability.
 Ownership: A person or group has a legal title to an asset or a
property.
 Knowledge: Specialist knowledge, which can benefit the project
through more effective delivery of project objectives, organizational
outcomes, or knowledge of the power structures of the organization.
 Contribution: Provision of funds or other resources, including human
resources, or providing support for the project in more intangible ways,
such as advocacy in the form of promoting the objectives of the project
or acting as a buffer between the project and the power structures of
the organization and its politics.
IDENTIFY STAKEHOLDERS (Tools & Techniques)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 16
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 A Data Representation Technique: stakeholder mapping/ representation.
Stakeholder mapping and representation is a method of categorizing
stakeholders using various methods. Categorizing stakeholders assists the team
in building relationships with the identified project stakeholders. Common
methods include:
 Power/interest grid, power/influence grid, or impact/influence grid
 Stakeholder cube.
 Salience model.
IDENTIFY STAKEHOLDERS (Tools & Techniques)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 17
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 Directions of Influence:
- Upward (senior management of the performing organization or
customer organization, sponsor, and steering committee),
- Downward (the team or specialists contributing knowledge or skills in
a temporary capacity),
- Outward (stakeholder groups and their representatives outside the
project team, such as suppliers, government departments, the public,
end-users, and regulators),
- Sideward (the peers of the project manager, such as other project
managers or middle managers who are in competition for scarce
project resources or who collaborate with the project manager in
sharing resources or information).
 Prioritization: Prioritizing stakeholders may be necessary for projects
with a large number of stakeholders, where the membership of the
stakeholder community is changing frequently, or when the relationships
between stakeholders and the project team or within the stakeholder
community are complex.
IDENTIFY STAKEHOLDERS (Tools & Techniques)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 18
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
IDENTIFY STAKEHOLDERS (Outputs)
 Stakeholder Register
This document contains information about identified stakeholders that
includes but is not limited to:
 Identification Information: Name, organizational position, location
and contact details, and role on the project.
 Assessment Information: Major requirements, expectations,
potential for influencing project outcomes, and the phase of the project
life cycle where the stakeholder has the most influence or impact.
 Stakeholder Classification: impact/ influence/ power/ interest;
upward/ downward/ outward/ sideward; Internal/external, or any other
classification model chosen by the project manager.
 Change Request
As stakeholder identification continues throughout the project, new
stakeholders, or new information about stakeholders, may result in a change
request to the product, project management plan, or project documents.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 19
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
IDENTIFY STAKEHOLDERS (Outputs)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 20
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 21
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE

Mais conteúdo relacionado

Mais procurados

PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
Anand Bobade
 

Mais procurados (20)

PMP PMBOK 6th
PMP PMBOK 6thPMP PMBOK 6th
PMP PMBOK 6th
 
Chap 4.0 Project integration management Overview
Chap 4.0 Project integration management OverviewChap 4.0 Project integration management Overview
Chap 4.0 Project integration management Overview
 
PMP Chapter 3 of 6 Planning Process Group (24- Processes) (Based on PMBOK 6t...
PMP Chapter 3 of 6  Planning Process Group (24- Processes) (Based on PMBOK 6t...PMP Chapter 3 of 6  Planning Process Group (24- Processes) (Based on PMBOK 6t...
PMP Chapter 3 of 6 Planning Process Group (24- Processes) (Based on PMBOK 6t...
 
Setting up a pmo
Setting up a pmoSetting up a pmo
Setting up a pmo
 
Establishing an Effective PMO
Establishing an Effective PMOEstablishing an Effective PMO
Establishing an Effective PMO
 
Pmbok6 to 7 transformation
Pmbok6 to 7 transformationPmbok6 to 7 transformation
Pmbok6 to 7 transformation
 
Introduction to Project Management by Javid Hamdard
Introduction to Project Management by Javid HamdardIntroduction to Project Management by Javid Hamdard
Introduction to Project Management by Javid Hamdard
 
PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2
 
PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principles
 
PMP Chapter 5 of 6 M & C Process Group (12- Processes) (Based on PMBOK 6th e...
PMP Chapter 5 of 6  M & C Process Group (12- Processes) (Based on PMBOK 6th e...PMP Chapter 5 of 6  M & C Process Group (12- Processes) (Based on PMBOK 6th e...
PMP Chapter 5 of 6 M & C Process Group (12- Processes) (Based on PMBOK 6th e...
 
project management concepts
project management conceptsproject management concepts
project management concepts
 
Instructor Slides - PMP/CAPM PMBOK 6th Edition
Instructor Slides - PMP/CAPM PMBOK 6th EditionInstructor Slides - PMP/CAPM PMBOK 6th Edition
Instructor Slides - PMP/CAPM PMBOK 6th Edition
 
PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1
 
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
 
PMP Certification Presentation
PMP Certification PresentationPMP Certification Presentation
PMP Certification Presentation
 
PMP
PMPPMP
PMP
 
PMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project ManagementPMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project Management
 
PMP Exam Preparation - 200 Questions
PMP Exam Preparation - 200 QuestionsPMP Exam Preparation - 200 Questions
PMP Exam Preparation - 200 Questions
 
Project Management Concepts
Project Management ConceptsProject Management Concepts
Project Management Concepts
 
Fundamentals of project management
Fundamentals of project managementFundamentals of project management
Fundamentals of project management
 

Semelhante a PMP Chapter 2 of 6 Initiating Process Group (2- Processes) (Based on PMBOK 6th edition)

LavaCon Best Practices For Multiple Technical Projects V1R2
LavaCon Best Practices For Multiple Technical Projects V1R2LavaCon Best Practices For Multiple Technical Projects V1R2
LavaCon Best Practices For Multiple Technical Projects V1R2
Jose Figueroa
 
Project management unit 5(1)
Project management unit 5(1)Project management unit 5(1)
Project management unit 5(1)
Rintu Das
 
Project Management Overview
Project Management OverviewProject Management Overview
Project Management Overview
cford1973
 
2005.04.04.cpp.project.management.adb
2005.04.04.cpp.project.management.adb2005.04.04.cpp.project.management.adb
2005.04.04.cpp.project.management.adb
ngocjos
 

Semelhante a PMP Chapter 2 of 6 Initiating Process Group (2- Processes) (Based on PMBOK 6th edition) (20)

PMP Chapter 6 of 6 closing process group (1- Process) (Based on PMBOK 6th ed...
PMP Chapter 6 of 6  closing process group (1- Process) (Based on PMBOK 6th ed...PMP Chapter 6 of 6  closing process group (1- Process) (Based on PMBOK 6th ed...
PMP Chapter 6 of 6 closing process group (1- Process) (Based on PMBOK 6th ed...
 
Integration Management Presentation
Integration Management Presentation Integration Management Presentation
Integration Management Presentation
 
Chap 4.1- Develop Project Charter
Chap 4.1- Develop Project CharterChap 4.1- Develop Project Charter
Chap 4.1- Develop Project Charter
 
PMP TKS GUIDE: Closing Process Group; Tasks, Knowledge & Skills
PMP TKS GUIDE:  Closing Process Group; Tasks, Knowledge & SkillsPMP TKS GUIDE:  Closing Process Group; Tasks, Knowledge & Skills
PMP TKS GUIDE: Closing Process Group; Tasks, Knowledge & Skills
 
Guid to implement initiating and planning processes
Guid to implement initiating and planning processesGuid to implement initiating and planning processes
Guid to implement initiating and planning processes
 
PMP - Project Initiation Template for Professionals
PMP - Project Initiation Template for ProfessionalsPMP - Project Initiation Template for Professionals
PMP - Project Initiation Template for Professionals
 
LavaCon Best Practices For Multiple Technical Projects V1R2
LavaCon Best Practices For Multiple Technical Projects V1R2LavaCon Best Practices For Multiple Technical Projects V1R2
LavaCon Best Practices For Multiple Technical Projects V1R2
 
Project Management Professional PMI-PMP Based on PMBOK 6th Edition
Project Management Professional PMI-PMP Based on PMBOK 6th EditionProject Management Professional PMI-PMP Based on PMBOK 6th Edition
Project Management Professional PMI-PMP Based on PMBOK 6th Edition
 
Program management-steps
Program management-stepsProgram management-steps
Program management-steps
 
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...
 
Free PMP Notes based on PMBOK guide and covers latest PMP changes after 11 Ja...
Free PMP Notes based on PMBOK guide and covers latest PMP changes after 11 Ja...Free PMP Notes based on PMBOK guide and covers latest PMP changes after 11 Ja...
Free PMP Notes based on PMBOK guide and covers latest PMP changes after 11 Ja...
 
PMP integration review
PMP integration reviewPMP integration review
PMP integration review
 
Project management unit 5(1)
Project management unit 5(1)Project management unit 5(1)
Project management unit 5(1)
 
2_Project Scope Management
2_Project Scope Management2_Project Scope Management
2_Project Scope Management
 
Sure Hit PMP @ First Attempt - Chapter Wise Summary Notes & Q & A’s Integrat...
Sure Hit PMP @ First Attempt - Chapter Wise  Summary Notes & Q & A’s Integrat...Sure Hit PMP @ First Attempt - Chapter Wise  Summary Notes & Q & A’s Integrat...
Sure Hit PMP @ First Attempt - Chapter Wise Summary Notes & Q & A’s Integrat...
 
Project Management Overview
Project Management OverviewProject Management Overview
Project Management Overview
 
PMO and Tollgate Process
PMO and Tollgate Process PMO and Tollgate Process
PMO and Tollgate Process
 
Lec 01 - Introduction.pptx
Lec 01 - Introduction.pptxLec 01 - Introduction.pptx
Lec 01 - Introduction.pptx
 
C:\fakepath\ginger rey pmo office - advanced project managment part i.doc
C:\fakepath\ginger rey   pmo office - advanced project managment part i.docC:\fakepath\ginger rey   pmo office - advanced project managment part i.doc
C:\fakepath\ginger rey pmo office - advanced project managment part i.doc
 
2005.04.04.cpp.project.management.adb
2005.04.04.cpp.project.management.adb2005.04.04.cpp.project.management.adb
2005.04.04.cpp.project.management.adb
 

Último

Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
PECB
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
kauryashika82
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
ciinovamais
 

Último (20)

microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writing
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
General AI for Medical Educators April 2024
General AI for Medical Educators April 2024General AI for Medical Educators April 2024
General AI for Medical Educators April 2024
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
Disha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfDisha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdf
 
Advance Mobile Application Development class 07
Advance Mobile Application Development class 07Advance Mobile Application Development class 07
Advance Mobile Application Development class 07
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 

PMP Chapter 2 of 6 Initiating Process Group (2- Processes) (Based on PMBOK 6th edition)

  • 1. PMP Exam Preparation Eng. Shamil Habet; MSc; PMP; JPE Based on PMBOK 6th PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 1 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 2. Initiating a Project PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 2 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 3. PROJECT SELECTION METHODS 1- Numeric Methods  Benefit Measurement Model (also called Comparative approach)  PresentValue (PV) (PV = FV / (1+r)^n), (Select the project with highest PV)  Net PresentValue (NPV), (Select the project with highest NPV)  Return On Investment (ROI), (Select the project with highest ROI)  Internal Rate of Return (IRR), (Select the project with highest IRR)  Pay-Back Period (PBP), (Select the project with lowest PBP)  Benefit-Cost Ratio, (Select the project with highest BCR; BCR>1 Good; BCR<1 Bad)  Cost-Benefit Ratio, (Select the project with lowest CBR; CBR>1 Bad; CBR<1 Good)  Mathematical Models (also called Constrained Optimization) Use linear, dynamic, non-linear, multi-objective programming to solve problem. 2- Non Numeric Method  Sacred cow: Senior Management wants it; it may often turn out well; many visionary projects start here  Murder Board: Also known as a "scrub-down", is a committee of questioners set up to critically review a proposal and/or help someone prepare for a difficult oral examination.  Operating Necessity: The project is required to keep the system running  Competitive Necessity: Project is necessary to sustain a competitive position PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 3 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 4. SCORING MODEL WEIGHTED CRITERIA PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 4 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 5. DEVELOP PROJECT CHARTER Project Charter: A document issued by the project initiator or sponsor (Some times Called Project Champion) that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities. This process is performed once or at predefined points in the project. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 5 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 6. The key benefits of developing Project Charter:  Provides a direct link between the project and the strategic objectives of the organization,  Creates a formal record of the project  Shows the organizational commitment to the project DEVELOP PROJECT CHARTER PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 6 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 7. Business Case: The approved business case, or similar, is the business document most commonly used to create the project charter. The business case describes the necessary information from a business standpoint to determine whether the expected outcomes of the project justify the required investment. The business case is created as a result of one or more of the following:  Government regulations  Strategic opportunity  Organizational need  Ecological impacts  Competition  Politics DEVELOP PROJECT CHARTER (Inputs) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 7 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 8.  Agreements are used to define initial intentions for a project. Agreements may take the form of:  Contracts, (used when a project is being performed for an external customer)  Memorandums of understanding (MOUs),  Service level agreements (SLA),  Letters of agreement,  Letters of intent, verbal agreements,  E-mail, or other written agreements. DEVELOP PROJECT CHARTER (Inputs) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 8 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 9.  Expert Judgment is defined as judgment provided based upon expertise in an application area, Knowledge Area, discipline, industry, etc., as appropriate for the activity being performed. Such expertise may be provided by any group or person with specialized education, knowledge, skill, experience, or training.  Facilitation: The ability to effectively guide a group event to a successful decision, solution, or conclusion. A facilitator ensures that there is effective participation, that participants achieve a mutual understanding, that all contributions are considered, that conclusions or results have full buy-in according to the decision process established for the project, and that the actions and agreements achieved are appropriately dealt with afterward.  Data-GatheringTechniques: (To be Described Later)  Meetings: For this process, meetings are held with key stakeholders to identify the project objectives, success criteria, key deliverables, high-level requirements, summary milestones, and other summary information. DEVELOP PROJECT CHARTER (Tools & Techniques) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 9 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 10.  Project Charter documents the high-level information on the project and on the product, service, or result the project is intended to satisfy, such as:  Project purpose;  Measurable project objectives and related success criteria;  High-level requirements;  High-level project description, boundaries, and key deliverables;  Overall project risk;  Summary milestone schedule;  Preapproved financial resources;  Key stakeholder list;  Project approval requirements (i.e., what constitutes project success, who decides the project is successful, and who signs off on the project);  Project exit criteria (i.e., what are the conditions to be met in order to close or to cancel the project or phase);  Assigned project manager, responsibility, and authority level;  Name and authority of the sponsor or other person(s) authorizing the project charter. DEVELOP PROJECT CHARTER (Outputs) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 10 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 11.  Assumption Log: High-level strategic and operational assumptions and constraints are normally identified in the business case before the project is initiated and will flow into the project charter. Important Notes: - Lower-level activity and task assumptions are generated throughout the project such as defining technical specifications, estimates, the schedule, risks, etc. - Assumption Log is used to record all assumptions and constraints throughout the project life cycle. DEVELOP PROJECT CHARTER (Outputs) ID Category/ Impact Assumption or Constraint Responsible Party Due Date Actions Status Comments PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 11 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 12. DEVELOP PROJECT CHARTER (Outputs) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 12 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 13. IDENTIFY STAKEHOLDERS PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 13 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 14. Identify Stakeholders is the process of identifying project stakeholders regularly and analyzing and documenting relevant information regarding their interests, involvement, interdependencies, influence, and potential impact on project success. The key benefit of this process is that it enables the project team to identify the appropriate focus for engagement of each stakeholder or group of stakeholders. This process is performed periodically throughout the project as needed. IDENTIFY STAKEHOLDERS PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 14 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 15.  Meetings: Meetings are used to develop an understanding of significant project stakeholders. They can take the form of facilitation workshops, small group guided discussions, and virtual groups using electronics or social media technologies to share ideas and analyze data.  Data Analysis techniques that can be used for this process include but are not limited to: - Document Analysis: Assessing the available project documentation and lessons learned from previous projects to identify stakeholders and other supporting information. - Stakeholder Analysis: results in a list of stakeholders and relevant information such as their positions in the organization, roles on the project, “stakes,” expectations, attitudes (their levels of support for the project), and their interest in information about the project. Stakeholders’ stakes can include but are not limited to a combination of: IDENTIFY STAKEHOLDERS (Tools & Techniques) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 15 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 16.  Interest: A person or group can be affected by a decision related to the project or its outcomes.  Rights (legal or moral rights): Legal rights, such as occupational health and safety, may be defined in the legislation framework of a country. Moral rights may involve concepts of protection of historical sites or environmental sustainability.  Ownership: A person or group has a legal title to an asset or a property.  Knowledge: Specialist knowledge, which can benefit the project through more effective delivery of project objectives, organizational outcomes, or knowledge of the power structures of the organization.  Contribution: Provision of funds or other resources, including human resources, or providing support for the project in more intangible ways, such as advocacy in the form of promoting the objectives of the project or acting as a buffer between the project and the power structures of the organization and its politics. IDENTIFY STAKEHOLDERS (Tools & Techniques) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 16 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 17.  A Data Representation Technique: stakeholder mapping/ representation. Stakeholder mapping and representation is a method of categorizing stakeholders using various methods. Categorizing stakeholders assists the team in building relationships with the identified project stakeholders. Common methods include:  Power/interest grid, power/influence grid, or impact/influence grid  Stakeholder cube.  Salience model. IDENTIFY STAKEHOLDERS (Tools & Techniques) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 17 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 18.  Directions of Influence: - Upward (senior management of the performing organization or customer organization, sponsor, and steering committee), - Downward (the team or specialists contributing knowledge or skills in a temporary capacity), - Outward (stakeholder groups and their representatives outside the project team, such as suppliers, government departments, the public, end-users, and regulators), - Sideward (the peers of the project manager, such as other project managers or middle managers who are in competition for scarce project resources or who collaborate with the project manager in sharing resources or information).  Prioritization: Prioritizing stakeholders may be necessary for projects with a large number of stakeholders, where the membership of the stakeholder community is changing frequently, or when the relationships between stakeholders and the project team or within the stakeholder community are complex. IDENTIFY STAKEHOLDERS (Tools & Techniques) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 18 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 19. IDENTIFY STAKEHOLDERS (Outputs)  Stakeholder Register This document contains information about identified stakeholders that includes but is not limited to:  Identification Information: Name, organizational position, location and contact details, and role on the project.  Assessment Information: Major requirements, expectations, potential for influencing project outcomes, and the phase of the project life cycle where the stakeholder has the most influence or impact.  Stakeholder Classification: impact/ influence/ power/ interest; upward/ downward/ outward/ sideward; Internal/external, or any other classification model chosen by the project manager.  Change Request As stakeholder identification continues throughout the project, new stakeholders, or new information about stakeholders, may result in a change request to the product, project management plan, or project documents. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 19 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 20. IDENTIFY STAKEHOLDERS (Outputs) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 20 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 21. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 21 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE