Earned Value Analysis
By Er. NikhilRaj
BAC BUDGETED AT COMPLETION PV PLANNED VALUE EV
EARNED VALUE
SV SCHEDULE VARIANCE CV COST VARIANCE SPI SCHEDULE
PERFORMANCE INDEX
CPI COST PERFORMANCE INDEX EAC ESTIMATE AT COMPLETION ETC
ESTIMATE TO COMPLETION
VAC VARIANCE AT
COMPLETION
1/21/2016
1all rights reserved to www.tutomaash.com | any queries can be mailed to tutomaash@gmail.com
Performance measuring system | Forecasting system
Contents
• What is earned value?
• Why earned value?
• EVM practiced industries
• Application example
• Application of same example in primavera p6
• Generation of financial s-curve
1/21/2016
2
Definition
Earned value management (EVM) is a methodology that combines scope,
schedule, and resource measurements to assess project performance and
progress.
It is a commonly used method of performance measurement for projects.
It integrates the scope baseline with the cost baseline, along with the
schedule baseline, to form the performance baseline, which helps the
project management team assess and measure project performance and
progress
- PMBOK 5th Edition Pg.217
1/21/2016
3
Why EVM?
Quantify and measure program/contract performance,
Provide an early warning system for deviation from a baseline,
Mitigate risks associated with cost and schedule overruns,
Provide a means to forecast final cost and schedule outcomes
1/21/2016
4
EVM practiced industries
Department of Defense (DoD)
The Federal government
Construction
IT sector
Commercial sector
R&D
Aerospace
1/21/2016
5
Example
2 weeks into the project
Ms Ann completed 35MILES
Also spent $15500
“Calculate the
Performance”
Imagine Ms Ann is the project manager of 100 miles road work
She must finish the project in 5 weeks
She can spent $10000/week
PLANNED
ACTUAL
2W
4W
3W
2W
1W
5W
1/21/2016
6
PLANNED VS ACTUAL
TOTAL PROJECT BUDGET=$50000
PLAN
(TIME)
W1
W2
W3
W4
W5
PLAN
(COST)
$10000
$20000
PV
$30000
$40000
$50000
BAC
PLAN
(%COMPLETE)
20%
20MILES
40%
40 MILES
60%
60 MILES
80%
80 MILES
100%
100 MILES
ACTUAL
(TIME)
W1
W2
W3
W4
W5
ACTUAL
(COST)
$15500
AC
ACTUAL
(%COMPLETE)
35%
35 MILES
1/21/2016
7
NAME DEFINITION EQUATION
VALUE
2nd week
INTERPRETATION
BAC | BUDGETED AT
COMPLETION
The value of total planned work, the project cost baseline $50000
PV | PLANNED VALUE
COST
The value of the work planned to be completed to a point in
time, usually the data date, or project completion $20000
EV | EARNED VALUE
COST
The planned value of all the work completed (earned) to a
point in time, usually the data date, without reference to actual
costs
$17500
AC | ACTUAL COST The actual cost of all the work completed to a point in time,
usually the data date $15500
CV | COST VARIANCE
The difference between the value of work completed to a point
in time, usually the data date, and the actual costs to the same
point in time
CV = EV –
AC $2000
Positive = Under planned cost
Neutral = On planned cost
Negative = Over planned cost
SV | SCHEDULE
VARIANCE
The difference between the work completed to a point in time,
and the work planned to be completed to the same point in
time.
SV = EV –
PV -$2500
Positive = Ahead of Schedule
Neutral = On schedule
Negative = Behind Schedule
CPI | COST
PERFORMANCE INDEX
A measure of the cost efficiency of budgeted resources
expressed as the ratio of earned value to actual cost. CPI = EV/AC 1.129
>1.0 = Under planned cost
Exactly 1.0 = On planned cost
<1.0 = Over planned cost
SPI | SCHEDULE
PERFORMANCE INDEX
A measure of schedule efficiency expressed as the ratio of
earned value to planned value
SPI = EV/PV 0.875
>1.0 = Ahead of schedule
Exactly 1.0 = On schedule
<1.0 = Behind schedule
VALUESCALCULATED
USINGEQUATION
VALUES
FROM
ACTUAL
VALUES
FROM
PLAN
1/21/2016
8
Project forecast
2WBAC= $50000 (Planned budget)
EAC= $44287 (Forecasted Budget calculated Based On 2nd week actual values)
ETC= EAC-AC
=$28786 (money to finish project)AC= $15500
1/21/2016
9
NAME DEFINITION EQUATION
VALUE
2nd week
EAC | ESTIMATE AT
COMPLETION
If the CPI is expected to be the same for the remainder of the
project, EAC can be calculated using EAC = BAC/CPI $44286.979
If future work will be accomplished at the planned rate, use: EAC = AC + BAC – EV $48000
If the initial plan is no longer valid, use: EAC = AC + Bottom-up ETC
If both the CPI and SPI influence the remaining work, use EAC = AC + [(BAC – EV)/(CPI x SPI)] $48398.899
ETC | ESTIMATE TO
COMPLETION
Assuming work is proceeding on plan, the cost of completing the
remaining authorized work can be calculated using:
ETC = EAC – AC $28786
Reestimate the remaining work from the bottom up ETC = Reestimate
VAC | VARIANCE AT
COMPLETION
The estimated difference in cost at the completion of the project.
Positive = Under planned cost
Neutral = On planned cost
Negative = Over planned cost
VAC = BAC – EAC $5713.021
1/21/2016
10
FORECASTEDVALUES
See Mix
in Action!
https://mix.office.com/watch/1otxpj7hz6kbx
(Copy the link and paste into your browser.
Or, when in a slide show, click the photo.)
1/21/2016
11
Get the add-in
Office Mix
Learn more at http://aka.ms/officemix
1/21/2016

Mais conteúdo relacionado

Mais procurados

Earned value management for Beginners
Earned value management for Beginners Earned value management for Beginners
Earned value management for Beginners
Shenin Hassan
 
EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...
Fahad Ali
 
Program evaluation review technique (pert)
Program evaluation review technique (pert)Program evaluation review technique (pert)
Program evaluation review technique (pert)
tomeh
 

Mais procurados (20)

Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Earned value management for Beginners
Earned value management for Beginners Earned value management for Beginners
Earned value management for Beginners
 
Resource allocation and smoothing
Resource allocation and smoothingResource allocation and smoothing
Resource allocation and smoothing
 
Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management
 
Project cost & control
Project cost & controlProject cost & control
Project cost & control
 
Work Breakdown Structure
Work Breakdown StructureWork Breakdown Structure
Work Breakdown Structure
 
Primavera - Tutorial
Primavera - TutorialPrimavera - Tutorial
Primavera - Tutorial
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 
EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Primavera training 02- Creating a new project
Primavera training  02- Creating a new projectPrimavera training  02- Creating a new project
Primavera training 02- Creating a new project
 
Schedule Updates
Schedule UpdatesSchedule Updates
Schedule Updates
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
A simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionA simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in action
 
Program evaluation review technique (pert)
Program evaluation review technique (pert)Program evaluation review technique (pert)
Program evaluation review technique (pert)
 
07 project cost management
07 project cost management07 project cost management
07 project cost management
 
Ms project training ppt
Ms project training pptMs project training ppt
Ms project training ppt
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
 

Destaque

Earned Value Analysis - EVA
Earned Value Analysis - EVAEarned Value Analysis - EVA
Earned Value Analysis - EVA
Ahmed Bamasdoos
 
Performance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value AnalysisPerformance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value Analysis
Deborah Obasogie
 
Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares
Vivek Prakash
 
Primavera P6 R8.3,8.4, R15 HD Training videos + Support For Working Professio...
Primavera P6 R8.3,8.4, R15 HD Training videos + Support For Working Professio...Primavera P6 R8.3,8.4, R15 HD Training videos + Support For Working Professio...
Primavera P6 R8.3,8.4, R15 HD Training videos + Support For Working Professio...
Nikhil Raj
 
Human aspect of project management
Human aspect of project managementHuman aspect of project management
Human aspect of project management
Kinshook Chaturvedi
 

Destaque (20)

Earned Value Analysis - EVA
Earned Value Analysis - EVAEarned Value Analysis - EVA
Earned Value Analysis - EVA
 
Earned Value Analysis - Basic Concepts
Earned Value Analysis  - Basic ConceptsEarned Value Analysis  - Basic Concepts
Earned Value Analysis - Basic Concepts
 
Agile and earned value management
Agile and earned value management  Agile and earned value management
Agile and earned value management
 
Performance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value AnalysisPerformance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value Analysis
 
Earned Value Analysis in the Control of Projects
Earned Value Analysis in the Control of ProjectsEarned Value Analysis in the Control of Projects
Earned Value Analysis in the Control of Projects
 
Earned value analysis - presentation
Earned value analysis  -  presentationEarned value analysis  -  presentation
Earned value analysis - presentation
 
S-Curve Presentation- 20130529
S-Curve Presentation- 20130529S-Curve Presentation- 20130529
S-Curve Presentation- 20130529
 
Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares
 
Calendar in Primavera P6 R15.2
Calendar in Primavera P6 R15.2Calendar in Primavera P6 R15.2
Calendar in Primavera P6 R15.2
 
Primavera P6 R8.3,8.4, R15 HD Training videos + Support For Working Professio...
Primavera P6 R8.3,8.4, R15 HD Training videos + Support For Working Professio...Primavera P6 R8.3,8.4, R15 HD Training videos + Support For Working Professio...
Primavera P6 R8.3,8.4, R15 HD Training videos + Support For Working Professio...
 
Résistance des matériaux
Résistance des  matériaux Résistance des  matériaux
Résistance des matériaux
 
Enterprise Project Structure (EPS)
Enterprise Project Structure (EPS)Enterprise Project Structure (EPS)
Enterprise Project Structure (EPS)
 
Activity Types and Relationships in Primavera p6
Activity Types and Relationships in Primavera p6 Activity Types and Relationships in Primavera p6
Activity Types and Relationships in Primavera p6
 
Robot 2010 patie3
Robot 2010 patie3Robot 2010 patie3
Robot 2010 patie3
 
Robot 2010 patie2
Robot 2010 patie2Robot 2010 patie2
Robot 2010 patie2
 
Critical path method (CPM)
Critical path method (CPM)Critical path method (CPM)
Critical path method (CPM)
 
Robot 2010 patie4
Robot 2010 patie4Robot 2010 patie4
Robot 2010 patie4
 
organizational breakdown structure (OBS)
organizational breakdown structure (OBS)organizational breakdown structure (OBS)
organizational breakdown structure (OBS)
 
Formation Robo2010 patie1
Formation Robo2010 patie1Formation Robo2010 patie1
Formation Robo2010 patie1
 
Human aspect of project management
Human aspect of project managementHuman aspect of project management
Human aspect of project management
 

Semelhante a Earned value analysis

Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
Serdar Temiz
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
sagarlesley
 

Semelhante a Earned value analysis (20)

5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
 
Project Management EVM & SCBA
Project Management EVM & SCBAProject Management EVM & SCBA
Project Management EVM & SCBA
 
PMP COST FORMULAE
PMP COST FORMULAEPMP COST FORMULAE
PMP COST FORMULAE
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
Project Cost Management - PMP preparation course
Project Cost Management - PMP preparation courseProject Cost Management - PMP preparation course
Project Cost Management - PMP preparation course
 
EVA - Metrics.ppt
EVA - Metrics.pptEVA - Metrics.ppt
EVA - Metrics.ppt
 
Cost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdfCost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdf
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Basics of EVM.pdf
Basics of  EVM.pdfBasics of  EVM.pdf
Basics of EVM.pdf
 
PM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfPM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdf
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
 
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value Management
 
Evm.calculations.Summary sheet
Evm.calculations.Summary sheetEvm.calculations.Summary sheet
Evm.calculations.Summary sheet
 
Project Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge AreaProject Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge Area
 
COST MANAGEMENT REPORT
COST MANAGEMENT REPORT COST MANAGEMENT REPORT
COST MANAGEMENT REPORT
 
An introduction to project accounting
An introduction to project accountingAn introduction to project accounting
An introduction to project accounting
 
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptcost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.ppt
 
Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part One
 

Último

1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
AldoGarca30
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
Epec Engineered Technologies
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
MayuraD1
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
mphochane1998
 

Último (20)

1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Moment Distribution Method For Btech Civil
Moment Distribution Method For Btech CivilMoment Distribution Method For Btech Civil
Moment Distribution Method For Btech Civil
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 

Earned value analysis

  • 1. Earned Value Analysis By Er. NikhilRaj BAC BUDGETED AT COMPLETION PV PLANNED VALUE EV EARNED VALUE SV SCHEDULE VARIANCE CV COST VARIANCE SPI SCHEDULE PERFORMANCE INDEX CPI COST PERFORMANCE INDEX EAC ESTIMATE AT COMPLETION ETC ESTIMATE TO COMPLETION VAC VARIANCE AT COMPLETION 1/21/2016 1all rights reserved to www.tutomaash.com | any queries can be mailed to tutomaash@gmail.com Performance measuring system | Forecasting system
  • 2. Contents • What is earned value? • Why earned value? • EVM practiced industries • Application example • Application of same example in primavera p6 • Generation of financial s-curve 1/21/2016 2
  • 3. Definition Earned value management (EVM) is a methodology that combines scope, schedule, and resource measurements to assess project performance and progress. It is a commonly used method of performance measurement for projects. It integrates the scope baseline with the cost baseline, along with the schedule baseline, to form the performance baseline, which helps the project management team assess and measure project performance and progress - PMBOK 5th Edition Pg.217 1/21/2016 3
  • 4. Why EVM? Quantify and measure program/contract performance, Provide an early warning system for deviation from a baseline, Mitigate risks associated with cost and schedule overruns, Provide a means to forecast final cost and schedule outcomes 1/21/2016 4
  • 5. EVM practiced industries Department of Defense (DoD) The Federal government Construction IT sector Commercial sector R&D Aerospace 1/21/2016 5
  • 6. Example 2 weeks into the project Ms Ann completed 35MILES Also spent $15500 “Calculate the Performance” Imagine Ms Ann is the project manager of 100 miles road work She must finish the project in 5 weeks She can spent $10000/week PLANNED ACTUAL 2W 4W 3W 2W 1W 5W 1/21/2016 6
  • 7. PLANNED VS ACTUAL TOTAL PROJECT BUDGET=$50000 PLAN (TIME) W1 W2 W3 W4 W5 PLAN (COST) $10000 $20000 PV $30000 $40000 $50000 BAC PLAN (%COMPLETE) 20% 20MILES 40% 40 MILES 60% 60 MILES 80% 80 MILES 100% 100 MILES ACTUAL (TIME) W1 W2 W3 W4 W5 ACTUAL (COST) $15500 AC ACTUAL (%COMPLETE) 35% 35 MILES 1/21/2016 7
  • 8. NAME DEFINITION EQUATION VALUE 2nd week INTERPRETATION BAC | BUDGETED AT COMPLETION The value of total planned work, the project cost baseline $50000 PV | PLANNED VALUE COST The value of the work planned to be completed to a point in time, usually the data date, or project completion $20000 EV | EARNED VALUE COST The planned value of all the work completed (earned) to a point in time, usually the data date, without reference to actual costs $17500 AC | ACTUAL COST The actual cost of all the work completed to a point in time, usually the data date $15500 CV | COST VARIANCE The difference between the value of work completed to a point in time, usually the data date, and the actual costs to the same point in time CV = EV – AC $2000 Positive = Under planned cost Neutral = On planned cost Negative = Over planned cost SV | SCHEDULE VARIANCE The difference between the work completed to a point in time, and the work planned to be completed to the same point in time. SV = EV – PV -$2500 Positive = Ahead of Schedule Neutral = On schedule Negative = Behind Schedule CPI | COST PERFORMANCE INDEX A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost. CPI = EV/AC 1.129 >1.0 = Under planned cost Exactly 1.0 = On planned cost <1.0 = Over planned cost SPI | SCHEDULE PERFORMANCE INDEX A measure of schedule efficiency expressed as the ratio of earned value to planned value SPI = EV/PV 0.875 >1.0 = Ahead of schedule Exactly 1.0 = On schedule <1.0 = Behind schedule VALUESCALCULATED USINGEQUATION VALUES FROM ACTUAL VALUES FROM PLAN 1/21/2016 8
  • 9. Project forecast 2WBAC= $50000 (Planned budget) EAC= $44287 (Forecasted Budget calculated Based On 2nd week actual values) ETC= EAC-AC =$28786 (money to finish project)AC= $15500 1/21/2016 9
  • 10. NAME DEFINITION EQUATION VALUE 2nd week EAC | ESTIMATE AT COMPLETION If the CPI is expected to be the same for the remainder of the project, EAC can be calculated using EAC = BAC/CPI $44286.979 If future work will be accomplished at the planned rate, use: EAC = AC + BAC – EV $48000 If the initial plan is no longer valid, use: EAC = AC + Bottom-up ETC If both the CPI and SPI influence the remaining work, use EAC = AC + [(BAC – EV)/(CPI x SPI)] $48398.899 ETC | ESTIMATE TO COMPLETION Assuming work is proceeding on plan, the cost of completing the remaining authorized work can be calculated using: ETC = EAC – AC $28786 Reestimate the remaining work from the bottom up ETC = Reestimate VAC | VARIANCE AT COMPLETION The estimated difference in cost at the completion of the project. Positive = Under planned cost Neutral = On planned cost Negative = Over planned cost VAC = BAC – EAC $5713.021 1/21/2016 10 FORECASTEDVALUES