SlideShare uma empresa Scribd logo
1 de 59
Prepared by Julian Kalac, P.Eng
Lean Six Sigma Master Black Belt
1
2
4
Shipped on time and customer happy
We Made $$$$
ProductionMaterial
Ship order
CUSTOMER
• No Wasted Time
• No Wasted Money
• No Wasted Resources
• No Wasted Material
? ?
99%
Customer Quality
The truth
5
The Hidden Factory
$5000-material
scrap costs
$35,000 REPRINTS
cost
Lost order
Wrong order shipped
ProductionMaterial
Ship order CUSTOMER
Hidden Factory
6
INSANITY --“Doing the
same thing over and
over again and expecting
different results”
Albert Einstein
7
8
 “Lean” is a Japanese methodology that
focuses on producing high quality products
FASTER, better and at lowest cost.
 Lean is about reducing NVA steps and waste
(scrap, rework,) focusing on the Value Add
work what the customer is paying for
 Lean is NOT ELIMINATING JOBS!
 The goal is that “you don’t work harder, but
rather smarter”
9
| | 10
 Customers demand shorter lead times,
improved quality & reduced prices
 Increase through-put and quality and reduce
time wasted and frustration by working on
non-value add activities.
 Gain new business
 Identification and systemic elimination of non-
value add costs and re-alignment of resources
to deliver value to the customer faster, better, &
more consistently
 Lean in Manufacturing:
◦ Focus: Eliminate waste, non-value add steps,
process constraints and bottle necks that cause
problems in work throughput
◦ Approach: Intuitive and broad - “inch-deep, mile
wide”
11
Leading to Leading toEliminate
Waste
Reduced
Cycle Times
Increased
Capacity
12
 Lean Manufacturing = SPEED
 focusses on reducing waste/Non-Value
Add activity and “Speeding” up the
Process cycle Times.
 Six Sigma = QUALITY 3.4 PPM
 focusses on reducing defects and process
variation
 Six Sigma “Quality”+ Lean “Speed" =
 PERFORMANCE
Value Added
Typically 95% of all lead time is non-value added
1. Overproduction
2. Waiting
3. Transportation
4. Non-Value Added Processing
5. Excess Inventory/Material
6. Defects
7. Excess Motion
8. Underutilized People
Non-Value Added
5%
| | 14
Lack of cross-functional training
Over relying on a select few while others
are Inadequately trained
 Operators are unable to rotate and help
each other out to balance the work-
load
High overtime, increased pressure stress
1
1
1
 Cycle Time is dictated by the slowest (bottleneck)
operation in the cell.
40
min
20
min
25
min
15
min
30
min
1
54
3
2
•What operation controls the cycle?
•How can you relieve the bottleneck?
Bottleneck Management:
•Maintain buffer in front of bottleneck
– (never starve the bottleneck !)
•Improve bottleneck operation
•Cross train on bottleneck
– Creates a visual work place
– Continuous Improvement
– Cell Support
– Balance activities / operations
20
Pull Systems
Production scheduling method used to link downstream
activities to upstream activities
Work begins based upon a demand signal (kanban) from
a downstream customer, either internal or external
Avoids overproduction, work backlog, and disconnects
within a process
Nothing is produced until the downstream customer
signals a need
 KANBAN
◦ A signal to produce
◦ Signal can be an empty square, bin, shelf, cart, or
kanban card
◦ Kanban qty is safety stock used while new order is
delivered
◦ Kanban qty is calculated based on usage, lead time,
delivery time
◦ Can be setup manually or automated
◦ Can extend through electronic notification to
suppliers using automatic messaging and triggers
2
 SETUP TIME
◦ Starts when last piece of previous job is
complete; ends when first good piece of next job
is complete
 INTERNAL SET-UP: While machine is shut-down
Goal is to reduce Internal setup time, less= better
 EXTERNAL SET-UP: While machine is working
◦ Goal is to transfer internal setup activities and
increase external setup time, more= better
Poke yoke = Error Proofing
 Eliminate/minimize chance for human error
to avoid mistakes
◦ Prevention Poke Yoke
 Stops the process before failures occur
 Does not allow defects to pass through the process
 High-Level Process Map
 Suppliers, Departments,
Customers
 Mid-Level Process Map
 Specific Area ex Production
 Detail-Level Process Map
 Specific process/operation
 (most commonly used)
Stop
Start
Stop
Start
Start
Stop
Stop
26
VA/NVA Ratio= 46%
DPU = ____
RTYield = _____
SCORE CARD:
I’m going to
have coffee
Fill c.
maker
with
water
Scoop
Coffee
into
c. maker
Get &
place
Filter in
c. maker
Drink
coffee
Is
taste
OK
Brew
coffee
Pour c.
into cup
Add
cream &
sugar
Water Supply
Process
Shopping
Process
Electricity
Supply
Process
Eating
Equipment
Supply
Process
Tasting
Process
Housekeeping Processes
Transactional&
SupportProcesses
ProcessData
&Information
NVA = Non-value Added Time
VA = Value Added Time
VA Time
NVA Time
Temp of Water= ___
Quality of Water= ___
Pressure of Water= ___
Amount of Coffee= ___
Quality of Coffee= ___
Type of Coffee= ___
Defective Coffee= ___
60 sec 30 sec 60 sec 360 sec 10 sec 60 sec
10 sec 10 sec 5 sec 600 sec 30 sec
SCOR (Supply Chain Operations Reference)
Model:
Structured around Five CORE Process Types
SCOR Model
Customer’s
Customer
Supplier’s
Supplier
Supplier
Internal or
External
Customer
Internal or
External
Your Company
Plan
Make DeliverSource Make /
Repair
DeliverMakeSourceDeliver SourceDeliverSource
Return Return Return
Return Return Return Return Return
Plan Plan
Provides Framework for your Transformation / Improvement Projects.
• Defining the boundaries / scope of the supply chain .
• Evaluate the supply chain’s strengths and weaknesses.
• Industry benchmarks, standardized terms, metrics,
Enables a total enterprise view of a supply chain
2
Product/ServiceValueStream
Processes Processes Process
Start
Process
Finish
Process
Steps
Processes Processes
Organization Customers End-use
Customers
Suppliers
Sub-
Suppliers
Process
Steps
TransactionalProcessSteps
Return Return
Plan
Make DeliverSource Make/Repai
r
DeliverMakeSourceDeliver SourceDeliverSource
Return Return Return Return Return Return
SCOR Supply Chain Model
29
Customer
Batch
WIP 1
Test
failures
Batch
WIP 2
Production
Defects
detected
Customer
Defects
Late
Orders
QC
I
Rework
Test
Rejects
QC
I2REWORK1
Sub-Assy
Riveting
Shipping
Supplier
Sub-Assy2
WIP2
Final-Assy
Test 2
Hurry Need
To ship!!!
NVA = 38%
Cost = 32%
DLV+Scrap
VA= 62%
30
15 coils/shift 8 20 26 39 31 10 20
4
13
19
20 8 40 20 20 20
20 20 20 20
Start Loop coils
180 deg
twist & prep
Skin Electric
Press
Coil form
Model
check
M/C tapePre-tape
Final Tape
Apply
Mylar
Micalast
Load
Micalastic
Impregnation
Final
Press &
Cure
Remove
Mylar
Final
gauge
ECP
Tape
ECP
oven
cure
Strand &
Final testPack &
Ship
Stop
Rotation schedule:
Based on the cycle times above every 2Hrs, Rotate Final Taping operators
with operators from “Skinning”, Electric Pressing. Coil forming & Model-
checking.
This will increase productivity from 28 Coils/Day to 40 Coils/Day and
ensure max exposure to F/T not more then 2hrs/day.
Needed: Cross-functional training and ~ 1 week
learning curve to achieve 85% operator efficiency
3
 Increased Coil Productivity by 30% from 28 to 40
Coils/day = $420K/Year
 Increased direct labour utilization by 26%
=$240K/Year
 Reduced in-process scrap from 20% to under 4%
 OEE improvement of 24% (from 62% to 84%)
 Flexible work Cells & cross functionally trained
workers able to help manage bottleneck efficiently
 MOL order on Final Tape exposure complied with
 Total Operational Savings = $ 800K
3
 The Five Principles of “Lean Thinking”
1. Define Customer demand TAKT TIME)
2. Map out the Current process (value stream)
identify Value and Non Value Add steps
3. Get the product to “flow” faster by
eliminating NVA steps and bottlenecks
4. Eliminate WIP, implement continuous flow
5. Implement POKE YOKE systems to error
proof to improvements
33
34
Lost managemant
time cost
Maintenance
cost
Lost opportunity
Lost assets cost
Rerun cost
Lost
business,
goodwill cost
Lost
credibility
cost
Prevention cost
appraisal cost
Project
rework cost
Litigation
SS Titanic
Management
Waste Costs:
Costs driven by problems and process steps that add no value
to products & services delivered to customers
Appraisal Costs:
Costs incurred to determine the degree
of conformance to customer needs
Prevention Costs:
Costs incurred to keep failure and
appraisal costs to a minimum
Failure Costs:
Costs directly incurred
due to defects internal
to the system or after
delivery to the
customer
THE PROCESS
PROCESS
OUTPUTS
CONTROLLED
VARIABLES
CUSTOMER
PROCESS
INPUTS
UNCONTROLLED
NOISE
VARIABLES
Process Variables
3
σ Methodology that Focuses on Reducing
Process Variation, using data-driven,
measurement-based, statistical methods
to Solve problems, improve performance
σ Focus: Surgical “inch-wide, mile-deep”
investigation and resolution
σ Approach:
σ Data driven solves problems at the
system and root cause level
σ Implement robust control plans for
sustained improvements
What is “Six Sigma”?
An Analytical Methodology that Focuses on Reducing Process Variation
1
)( 2




n
xxi


Sigma =  = Deviation
( Square root of variance )
-7
-6
-5
-4
-3
-2
-1
0
1
2
3
4
5
6
7
Axis graduated in Sigma
68.27 %
95.45 %
99.73 %
99.9937 %
99.999943 %
99.9999998 %
result: 317300 ppm outside
(deviation)
45500 ppm
2700 ppm
63 ppm
0.57 ppm
0.002 ppm
between + / - 1
between + / - 2
between + / - 3
between + / - 4
between + / - 5
between + / - 6
 =
38
•Identify customer
metrics
•Select performances
standards
•Select objectives
•Map the process
•Validate measurement
System (MSA)
•RESULT: Process maps
and good quality data
collected by listening to
the process
•Identify sources of variation & failure points
•Redefine and Re-prioritize
•Establish process capability
•Identify improvement opportunities
•RESULT: The critical sources of variation
identified root causes determined
•Monitor processes to prevent
recurrence of variation, defects
and non-value work
•Maintain performance levels
•find more creative ways to
improve
•fix root causes
•Find/Implement Preventive Fixes
•Deploy changes organization
•RESULT: Performance is more
predictable ; culture changing
•Plan and apply Improve Tools to fix
problems and reduce variation
•Implement improvement opportunities
•RESULT: Improve tools applied, changes
implemented and performance
improvement in place
DMAIC Improvement Model
A Road Map for guiding Improvement Projects
•Identify customer problems
•Identify performances standards
•Identify improvement objectives
•Link problem to the key performance metrics
•Find the right problems
•RESULT: Problem Statement & Project Charter
Define
Measure
AnalyzeImprove
Control
Results
Define
Measure
AnalyzeImprove
Control
Results
39
Define
Measure
AnalyzeImprove
Control
Results
Define
Measure
AnalyzeImprove
Control
Results
Applied Learning
Theory Practice
Coached Projects
 Training typically
occurs over a 4-6
month period using a
Learn  Apply;
Learn Apply; …
format.
 Projects that solve
real performance
problems in your
organization are part
of the certification
and learning process
Recognize:
•Find problems
•Link to organization's needs
•Form teams, define resources
•Understand program req’ts
Deploy:
•Validate improved
performance that
stays in place
•Spread
improvements
across the
enterprise
•Harvest the
performance
improvements
•Change the
culture
To understand where you want to be,
you need to know how to get there.v
Map the Process
Measure the Process
Identify the variables - ‘x’
Understand the Problem -
’Y’ = function of variables -’x’
Y=f(x)
4
2) Clearly Define your Problem and the Impact
Example:
Too many mistakes in purchase request specifications are causing rework
rates of 34%, high costs and late deliveries (less than 50% on time) to our
customers
1) Find
• Customer Issues
• Performance
Reviews
• Meetings
• New Projects
• Failures, Re-work
• Projects
• Continuous
improvement
activities
• Champions
• Stakeholders
• Employees
• SCOR Maps
• Research
• Brainstorm
• Wait until the crisis
hits you
• Value Stream
Maps
3) Clearly State the Initial Scope for your project
(Set targets and timelines!)
Example:
This first phase of this project – by 3Q 2004 - will identify problems and root
causes in the purchase request process, increase first pass yield rates to
95%, reduce the cost of poor quality by 50% and increase on-time
deliveries to our customers to greater than 90%
4) Link improvement targets to customer needs and
organizational objectives
5) Project Plan – Charter, Resources, Milestones
4
3
Process Flow
for Measure Phase
Data
Storage
and
Archiving
Foundations for Wisdom and good decision
making start with Good Data
What data do we need?
Can we use “old” historical data?
Is old data (still) usable?
How was it collected?
Wisdom
Knowledge
Data
Information
Wisdom
Knowledge
Data
Information
Wisdom
Knowledge
Data
Information
Data Selection
Data Integrity Analysis
Data Collection
Measurement System Analysis
Process Mapping
Is your error in the process or in the way you measure it?
Could it be that you actually are “good” but the error in the measurement
system shows that you are not “good”?
Overall Variation
Occurrence-to-
Occurrence ( or Piece-
to-Piece) Variation
Measurement System Variation
Repeatability:
Variation due to gage
or measurement tool
Reproducibility:
Variation due to people or
operators who are measuring
2
Total = 2
Part-Part + 2
R&R
Accurate but not precise - On
average, the shots are in the center of
the target but there is a lot of
variability
Precise but not accurate -
The average is not on the center,
but the variability is small
Source: iSixSigma
46
Organize & Understand your data
Statistical Analysis
Determine significant factors
Sort, Collate, Investigate your data
Wisdom
Knowledge
Data
Information
Wisdom
Knowledge
Data
Information
Wisdom
Knowledge
Data
Information
We know we must change X to create a change in Y…
But how do we know which Xs to change
and how to change them ?
4
Y =f (x1, x2, …)
process output key process input factors
affecting process output
function of
48
P value< 0.5--Significant
Statistical Analysis
0.0250.0200.0150.0100.0050.000
7
6
5
4
3
2
1
0
New Machine
Frequency
0.0250.0200.0150.0100.0050.000
30
20
10
0
Machine 6 mths
Frequency
 Is the factor really important?
 Do we understand the impact for
the factor?
 Has our improvement made an
impact
 What is the true impact?
Hypothesis Testing
Regression Analysis
55453525155
60
50
40
30
20
10
0
X
Y
R-Sq = 86.0 %
Y = 2.19469 + 0.918549X
95% PI
Regression
Regression Plot
Apply statistics to validate actions & improvements
P value< 0.5--Significant
The minimum
sample size
required to provide
exactly 5% overlap
(risk). In order to
distinguish the
Delta.
Note: If you are
working with Non-
normal Data,
multiply your
calculated sample
size by 1.1
50
40 50 60 7040 50 60 70
40 60 7050
Population
P value< 0.5--Significant
51
PROBLEM
FINDING
FACT
FINDING
PROBLEM
DEFINITION
IDEA
FINDING
EVAL. &
SELECT
PLAN
ACCEPT
-ANCE
ACTION
1
2
3
4
6
7
8
5
Select
Tool
Analyze Data & Information Apply tools & Make Changes
Six
Sigma
Projects
5S PM/TPM TQM
Rapid Improve-
ment Event
Integrated
Process
Team (IPT)
Establish Baselines/Metrics
Other CI
Tools
Kanban DFSS
ApplytheTool
(1)
(2)
(3)Implement / Deploy Fixes
(0) Identify failure points, bottlenecks and improvement
opportunities from Define-Measure-Analyze Phases
PM = Preventive Maintenance
TPM = Total Productive Maintenance
CI = Continuous Improvement
DFSS = Design for Six Sigma
TQM = Total Quality Management
Maintaining and Improving Control:
 Managing Change
 Quality Management Systems
 What’s Left? What’s Next?
52
Control Tools:
• POKA YOKE
• Control Charts
• Statistical Process Control (SPC)
Document
Procedures and
Best Practices
Create Visual
Controls and
“Dashboards”
Update
Deployment Plan
Complete
Control
FMEA
Update and Deploy
Communication Plan
Execute
Deployment Plan
Document Other
Opportunities
Prepare and
Implement
Control Plan
Report out, Hand-
off and Closure
Prepare and
Implement Training
Plan
Process Flow Diagram for Control Phase:
53
Key Process
Input Variable
Key Process
Output Variable
Process
Specification
(LSL, USL,
Target)
Capability (Cp,
Cpk, DPMO) and
date
Measurement
Technique
Sample Size
Sample
Frequency
Control Element Contigency Remedial Audit
Phone Call
LSL - NA
TGT- 10 sec
USL - 30 secs
Cpk=.85
05 Dec 03
Call Center
Manager
Dashboard 30 1/2 hourly
CCM to adjust
seated agents
CCM to reprioritize
worload to meet
specification
Daily report to be
examined by
Supervisor N
New Customer
LSL - NA
TGT- 15 min
USL - 30 min
Cpk=. 48
05 Dec 03
New Acct Dept
Visual Display 100 Weekly
Nacct Mgr to
monitor and adjust
new Acct Reps
Nacct Mgr to
reprioritize
Monthly report to
NAM regional
manager Y
New Accounts 0 Field defects
DPMO = 66289
05 Dec 03
New Acct Dept
Visual Display 100 Weekly
Nacct Mgr to
monitor and adjust
new Acct Reps
Nacct Mgr to use
Pareto Analysis to
determine defect
category
Monthly report to
NAM regional
manager Y
Lead Time
LSL - NA
TGT- 5 Days
USL - 10 Days
Cpk = 1.43
05 Dec 03
Operations
Dashboard 30 Daily Ops Mgr Review
Identify trend root
cause
Director Review
Weekly N
Customer
Expedite Expedite Order 0 Expedited
DPMO = 24721
05 Dec 03
Operations
Dashboard 25 Weekly Ops Mgr Review
Identify trend root
cause
Director Review
Monthly Y
Key Process Input Variable
Key Process Output Variable
Process Specification or Target Output Value
Current Performance Value
Sample Size
Sample Frequency
Control Element
Contingency Plans
Remedial Plans
Is the
Performance
Audited
DPMO / Control Chart
20000
25000
30000
35000
40000
45000
50000
55000
60000
65000
70000
75000
80000
85000
90000
95000
100000
2/5/2001
2/19/2001
3/5/2001
3/19/2001
4/2/2001
4/16/2001
4/30/2001
5/14/2001
5/28/2001
6/11/2001
6/25/2001
7/9/2001
7/23/2001
8/6/2001
8/20/2001
9/3/2001
9/17/2001
10/1/2001
10/15/2001
10/29/2001
11/12/2001
11/26/2001
12/10/2001
12/24/2001
DPMO
Baseline
DPMO
UCL
LCL
Mean
Goal
Process
Change
REGIONAL
CONTROL
BEGINS
PAST BKLOG PAST BKLOG P-DUE PAST
UNITS DUE PM DUE LUBE SVC DUE
REGION ASSIGN PM DAYS LUBE DAYS GOAL SVC
NETWORK 2327 1 0 107 4 93 77
CENTRAL 151 0 0 8 4.8 6 8
F.B.U. 74 0 0 0 0 3 2
MIDWEST 178 2 1 9 4.6 7 3
NORTHEAST 312 0 0 33 9.7 12 18
SOUTHERN 389 0 0 43 10.1 16 36
WESTERN 259 0 0 19 6.7 10 11
TOTAL 3689 3 0 219 5.4 150 155
OFFLINE 203 4 1.8 37 16.8 1 4
NEW ACCOUNT EXCEPTION SUMMARY 12/08/2003
Item
No. Problem/Opportunity Benefit
Person(s)
Responsible
Due
Date
%
Complete Comments
1
2
3
4
5
6
7
8
Kaizen Event Newspaper
Team: Kaizen Event:
Kaizen Newspaper
The Control Plan
explains how the
Dashboard
Works and what
to do if
performance
goes out of
controlImprovement Actions and Activities
Updated: __/__/__ By:________
5
DPMO / Control Chart
20000
25000
30000
35000
40000
45000
50000
55000
60000
65000
70000
75000
80000
85000
90000
95000
100000
2/5/2
0012/19/20013/5/2
0013/19/20014/2/2
0014/16/20014/30/20015/14/20015/28/20016/11/20016/25/20017/9/2
0017/23/20018/6/2
0018/20/20019/3/2
0019/17/200110/1/2001
10/15
/2001
10/29
/2001
11/12
/2001
11/26
/2001
12/10
/2001
12/24
/2001
DPMO
Baseline
DPMO
UCL
LCL
Mean
Goal
Process
Change
REGIONAL
CONTROL
BEGINS
5
Control Limits
-7
-6
-5
-4
-3
-2
-1
0
1
2
3
4
5
6
7
DPMO / Control Chart
20000
25000
30000
35000
40000
45000
50000
55000
60000
65000
70000
75000
80000
85000
90000
95000
100000
2/5/2
0012/19/20013/5/2
0013/19/20014/2/2
0014/16/20014/30/20015/14/20015/28/20016/11/20016/25/20017/9/2
0017/23/20018/6/2
0018/20/20019/3/2
0019/17/200110/1/2001
10/15
/2001
10/29
/2001
11/12
/2001
11/26
/2001
12/10
/2001
12/24
/2001
DPMO
Baseline
DPMO
UCL
LCL
Mean
Goal
Process
Change
REGIONAL
CONTROL
BEGINS
Lean Manufacturing
 Value Stream Mapping
 Line Balancing
 Continuous Flow
 PULL system
 KANBAN
 Set Up reduction
(SMED)
 Poke Yoke/Error
Proofing
 5S
Six Sigma
 DMAIC, SIPOC process
 Gage R&R
 FMEA
Hypothesis Testing
Regression
 Statistical Analysis
 Process Capability Cp, Cpk
 Roll Throughput Yield
 Design of Experiments
 Control Charts
57
“Lean” focuses on:
The systematic elimination of waste
and re-alignment of resources to
deliver value to the customer faster,
better, & more consistently
Supply Chain Management:
Mapping your processes
through the entire business
enterprise with standard elements
“Six Sigma” focuses on:
Use of analytical and methodical fact based
problem solving methods
Drastically reduce variation then control and
manage whatever variation is left over
Increase predictability, accuracy and precision
Product and Services
Cash/Funding
Information
Customer’s
Customer
Supplier’s
Supplier
SupplierSupplier CustomerCustomerYour Company
PlanPlan
Make DeliverSourceSource Make /
Repair
DeliverMakeSourceDeliver SourceDeliverDeliverSource
ReturnReturn ReturnReturn ReturnReturn
ReturnReturn ReturnReturn ReturnReturn ReturnReturn ReturnReturn
PlanPlan PlanPlan
LSL USLẊ
Theory of
Constraints:
Find & eliminate
the bottle necks
Business
Process Re-
engineering:
Start over
VA Time
NVA Time
FLOW
Numbers, words, quantities,
values stored sitting in piles or
queues waiting for future use
Charts, summaries, spread
sheets, etc. that organize the
data
Presentations, plans and tools
that explain and communicate
the information
Processes, organizations and
team using the information to
improve, manage, build
systems and develop cultures
Push the data “up” to become Wise
Always
loop
back to
check
the data
Wisdom
Knowledge
Data
Information
Where are you
looking from?
The WISDOM TOWER: Changing Perspectives

Mais conteúdo relacionado

Mais procurados

Lean Production
Lean ProductionLean Production
Lean Productiontutor2u
 
Lean Manufacturing : Concept & Overview nkchawla@gmail.com
Lean Manufacturing : Concept & Overview nkchawla@gmail.comLean Manufacturing : Concept & Overview nkchawla@gmail.com
Lean Manufacturing : Concept & Overview nkchawla@gmail.comNareshChawla
 
History of Lean manufacturing & TPS 14 Principal
History of Lean manufacturing & TPS 14 PrincipalHistory of Lean manufacturing & TPS 14 Principal
History of Lean manufacturing & TPS 14 PrincipalSumon Kumar Kundu
 
Process improvement
Process improvementProcess improvement
Process improvementaolrac
 
Lean Manufacturing Tools
Lean Manufacturing ToolsLean Manufacturing Tools
Lean Manufacturing ToolsJagriti Prasad
 
Bottleneck Analysis Theory Of Constraints (TOC)
Bottleneck Analysis Theory Of Constraints (TOC)Bottleneck Analysis Theory Of Constraints (TOC)
Bottleneck Analysis Theory Of Constraints (TOC)Self-employed
 
Introduction to lean manufacturing
Introduction to lean manufacturingIntroduction to lean manufacturing
Introduction to lean manufacturingleangeekcanada
 
Lean Inventory
Lean Inventory Lean Inventory
Lean Inventory Tom Craig
 
Value stream mapping - Future State
Value stream mapping - Future StateValue stream mapping - Future State
Value stream mapping - Future Statekrishnaheda
 
Kaizen ~ Continuous Process Improvement (Cpi)
Kaizen ~  Continuous Process Improvement (Cpi)Kaizen ~  Continuous Process Improvement (Cpi)
Kaizen ~ Continuous Process Improvement (Cpi)Anand Subramaniam
 

Mais procurados (20)

13. value stream mapping
13. value stream mapping13. value stream mapping
13. value stream mapping
 
Jit And Lean
Jit And LeanJit And Lean
Jit And Lean
 
Lean Production
Lean ProductionLean Production
Lean Production
 
Lean operations presentation
Lean operations   presentationLean operations   presentation
Lean operations presentation
 
Toyota production system
Toyota production systemToyota production system
Toyota production system
 
Lean Manufacturing : Concept & Overview nkchawla@gmail.com
Lean Manufacturing : Concept & Overview nkchawla@gmail.comLean Manufacturing : Concept & Overview nkchawla@gmail.com
Lean Manufacturing : Concept & Overview nkchawla@gmail.com
 
Spaghetti Diagrams
Spaghetti DiagramsSpaghetti Diagrams
Spaghetti Diagrams
 
Lean management
Lean management Lean management
Lean management
 
History of Lean manufacturing & TPS 14 Principal
History of Lean manufacturing & TPS 14 PrincipalHistory of Lean manufacturing & TPS 14 Principal
History of Lean manufacturing & TPS 14 Principal
 
Process improvement
Process improvementProcess improvement
Process improvement
 
Lean manufacturing
Lean manufacturingLean manufacturing
Lean manufacturing
 
Lean Manufacturing Tools
Lean Manufacturing ToolsLean Manufacturing Tools
Lean Manufacturing Tools
 
Bottleneck Analysis Theory Of Constraints (TOC)
Bottleneck Analysis Theory Of Constraints (TOC)Bottleneck Analysis Theory Of Constraints (TOC)
Bottleneck Analysis Theory Of Constraints (TOC)
 
8 Wastes
8 Wastes8 Wastes
8 Wastes
 
Manufacturing wastes
Manufacturing wastesManufacturing wastes
Manufacturing wastes
 
Introduction to lean manufacturing
Introduction to lean manufacturingIntroduction to lean manufacturing
Introduction to lean manufacturing
 
Lean Inventory
Lean Inventory Lean Inventory
Lean Inventory
 
Lean Process Improvement Techniques
Lean Process Improvement TechniquesLean Process Improvement Techniques
Lean Process Improvement Techniques
 
Value stream mapping - Future State
Value stream mapping - Future StateValue stream mapping - Future State
Value stream mapping - Future State
 
Kaizen ~ Continuous Process Improvement (Cpi)
Kaizen ~  Continuous Process Improvement (Cpi)Kaizen ~  Continuous Process Improvement (Cpi)
Kaizen ~ Continuous Process Improvement (Cpi)
 

Semelhante a Lean Supply Chain Management--by JULIAN KALAC

LEAN SPEED vs SIX SIGMA QUALITY by JULIAN KALAC
LEAN SPEED vs SIX SIGMA QUALITY by JULIAN KALAC LEAN SPEED vs SIX SIGMA QUALITY by JULIAN KALAC
LEAN SPEED vs SIX SIGMA QUALITY by JULIAN KALAC Julian Kalac P.Eng
 
Lean Six Sigma overview Julian Kalac
Lean  Six Sigma overview Julian KalacLean  Six Sigma overview Julian Kalac
Lean Six Sigma overview Julian KalacJulian Kalac P.Eng
 
37022309 lean-simple-solutions
37022309 lean-simple-solutions37022309 lean-simple-solutions
37022309 lean-simple-solutionssashi prabhu
 
lean-simple-solutions
 lean-simple-solutions lean-simple-solutions
lean-simple-solutionssashi prabhu
 
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORSLEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORSJulian Kalac P.Eng
 
Lean Bski Essentials
Lean Bski EssentialsLean Bski Essentials
Lean Bski Essentialsbstawski
 
Finding the ROI in Your Quality System
Finding the ROI in Your Quality SystemFinding the ROI in Your Quality System
Finding the ROI in Your Quality SystemNorthwest Analytics
 
Lean six sigma 3d
Lean six sigma 3dLean six sigma 3d
Lean six sigma 3dVarmahk
 
QUALMAN QUIZ # 1 Reviewer
QUALMAN QUIZ # 1 ReviewerQUALMAN QUIZ # 1 Reviewer
QUALMAN QUIZ # 1 ReviewerSamantha Abalos
 
Six Sigma- Define & Measure_Sudhanshu.pdf
Six Sigma- Define & Measure_Sudhanshu.pdfSix Sigma- Define & Measure_Sudhanshu.pdf
Six Sigma- Define & Measure_Sudhanshu.pdfSudhanshuMittal20
 
Introduction of Flow Management in Manufacturing - ADDVALUE - Nilesh Arora
Introduction of Flow Management in Manufacturing - ADDVALUE - Nilesh AroraIntroduction of Flow Management in Manufacturing - ADDVALUE - Nilesh Arora
Introduction of Flow Management in Manufacturing - ADDVALUE - Nilesh AroraADD VALUE CONSULTING Inc
 
Understanding and concept Lean cheat sheet.pdf
Understanding and concept Lean cheat sheet.pdfUnderstanding and concept Lean cheat sheet.pdf
Understanding and concept Lean cheat sheet.pdfpriyaagrawalpefn20
 
Lean Process and Production
Lean Process and ProductionLean Process and Production
Lean Process and Productionravina10008
 
Project six sigma
Project  six sigmaProject  six sigma
Project six sigmaUrooj Iqbal
 
Lean presentation ppt
Lean presentation pptLean presentation ppt
Lean presentation pptbwu.nl
 
Optimizing Sterile Processing Workflow
Optimizing Sterile Processing WorkflowOptimizing Sterile Processing Workflow
Optimizing Sterile Processing Workflowdpjphx
 

Semelhante a Lean Supply Chain Management--by JULIAN KALAC (20)

LEAN SPEED vs SIX SIGMA QUALITY by JULIAN KALAC
LEAN SPEED vs SIX SIGMA QUALITY by JULIAN KALAC LEAN SPEED vs SIX SIGMA QUALITY by JULIAN KALAC
LEAN SPEED vs SIX SIGMA QUALITY by JULIAN KALAC
 
Lean vs six sigma -jk
Lean vs six sigma  -jkLean vs six sigma  -jk
Lean vs six sigma -jk
 
Lean Six Sigma overview Julian Kalac
Lean  Six Sigma overview Julian KalacLean  Six Sigma overview Julian Kalac
Lean Six Sigma overview Julian Kalac
 
37022309 lean-simple-solutions
37022309 lean-simple-solutions37022309 lean-simple-solutions
37022309 lean-simple-solutions
 
lean-simple-solutions
 lean-simple-solutions lean-simple-solutions
lean-simple-solutions
 
Kaizen
KaizenKaizen
Kaizen
 
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORSLEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
 
Cost reduction beyond price
Cost reduction beyond priceCost reduction beyond price
Cost reduction beyond price
 
Lean Bski Essentials
Lean Bski EssentialsLean Bski Essentials
Lean Bski Essentials
 
Finding the ROI in Your Quality System
Finding the ROI in Your Quality SystemFinding the ROI in Your Quality System
Finding the ROI in Your Quality System
 
Lean six sigma 3d
Lean six sigma 3dLean six sigma 3d
Lean six sigma 3d
 
QUALMAN QUIZ # 1 Reviewer
QUALMAN QUIZ # 1 ReviewerQUALMAN QUIZ # 1 Reviewer
QUALMAN QUIZ # 1 Reviewer
 
Six Sigma- Define & Measure_Sudhanshu.pdf
Six Sigma- Define & Measure_Sudhanshu.pdfSix Sigma- Define & Measure_Sudhanshu.pdf
Six Sigma- Define & Measure_Sudhanshu.pdf
 
Introduction of Flow Management in Manufacturing - ADDVALUE - Nilesh Arora
Introduction of Flow Management in Manufacturing - ADDVALUE - Nilesh AroraIntroduction of Flow Management in Manufacturing - ADDVALUE - Nilesh Arora
Introduction of Flow Management in Manufacturing - ADDVALUE - Nilesh Arora
 
Understanding and concept Lean cheat sheet.pdf
Understanding and concept Lean cheat sheet.pdfUnderstanding and concept Lean cheat sheet.pdf
Understanding and concept Lean cheat sheet.pdf
 
Lean Process and Production
Lean Process and ProductionLean Process and Production
Lean Process and Production
 
Project six sigma
Project  six sigmaProject  six sigma
Project six sigma
 
Lean presentation ppt
Lean presentation pptLean presentation ppt
Lean presentation ppt
 
Optimizing Sterile Processing Workflow
Optimizing Sterile Processing WorkflowOptimizing Sterile Processing Workflow
Optimizing Sterile Processing Workflow
 
Lean principles taster
Lean principles tasterLean principles taster
Lean principles taster
 

Mais de Julian Kalac P.Eng

VOLVO EATS RACK LEAN TRANSFORMATION by Julian Kalac, P.Eng
VOLVO EATS RACK LEAN TRANSFORMATION  by Julian Kalac, P.EngVOLVO EATS RACK LEAN TRANSFORMATION  by Julian Kalac, P.Eng
VOLVO EATS RACK LEAN TRANSFORMATION by Julian Kalac, P.EngJulian Kalac P.Eng
 
Batch & Queue vs Lean Continuous Flow
Batch & Queue vs Lean Continuous FlowBatch & Queue vs Lean Continuous Flow
Batch & Queue vs Lean Continuous FlowJulian Kalac P.Eng
 
Design for Six Sigma in Automotive
Design for Six Sigma in Automotive Design for Six Sigma in Automotive
Design for Six Sigma in Automotive Julian Kalac P.Eng
 
1000 Ton Transfer Press Risk Assessment
1000 Ton Transfer Press Risk Assessment 1000 Ton Transfer Press Risk Assessment
1000 Ton Transfer Press Risk Assessment Julian Kalac P.Eng
 
PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS
PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS
PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS Julian Kalac P.Eng
 
1000 TON TRANSFER PRESS SAFE WORK PROCEDURE ;DIE SETUP/CHANGEOVER
1000 TON TRANSFER PRESS SAFE WORK PROCEDURE ;DIE SETUP/CHANGEOVER1000 TON TRANSFER PRESS SAFE WORK PROCEDURE ;DIE SETUP/CHANGEOVER
1000 TON TRANSFER PRESS SAFE WORK PROCEDURE ;DIE SETUP/CHANGEOVERJulian Kalac P.Eng
 
Live wire testing lock out tag out safe work procedure
Live wire testing lock out tag out safe work procedureLive wire testing lock out tag out safe work procedure
Live wire testing lock out tag out safe work procedureJulian Kalac P.Eng
 
Julian Kalac lean 6 sigma project list--2018
 Julian Kalac lean 6 sigma  project list--2018 Julian Kalac lean 6 sigma  project list--2018
Julian Kalac lean 6 sigma project list--2018Julian Kalac P.Eng
 
Machine Safeguarding with Lock Out Tag Out
Machine Safeguarding with Lock Out Tag OutMachine Safeguarding with Lock Out Tag Out
Machine Safeguarding with Lock Out Tag OutJulian Kalac P.Eng
 
Custom Lean Eyelet machine SOP with 5 min changeover
Custom Lean Eyelet machine SOP with 5 min changeoverCustom Lean Eyelet machine SOP with 5 min changeover
Custom Lean Eyelet machine SOP with 5 min changeoverJulian Kalac P.Eng
 
FCI AUTOMOTIVE 2005 FORD MINIVAN ABS-VSC LAUNCH
FCI AUTOMOTIVE 2005 FORD MINIVAN ABS-VSC LAUNCHFCI AUTOMOTIVE 2005 FORD MINIVAN ABS-VSC LAUNCH
FCI AUTOMOTIVE 2005 FORD MINIVAN ABS-VSC LAUNCHJulian Kalac P.Eng
 
DESIGN FMEA TRAINING FOR LITENS AUTOMOTIVE
DESIGN FMEA TRAINING FOR LITENS AUTOMOTIVE DESIGN FMEA TRAINING FOR LITENS AUTOMOTIVE
DESIGN FMEA TRAINING FOR LITENS AUTOMOTIVE Julian Kalac P.Eng
 
DFMEA DUE DILIGENCE TRAINING FOR LITENS AUTOMOTIVE
DFMEA DUE DILIGENCE TRAINING FOR LITENS AUTOMOTIVE DFMEA DUE DILIGENCE TRAINING FOR LITENS AUTOMOTIVE
DFMEA DUE DILIGENCE TRAINING FOR LITENS AUTOMOTIVE Julian Kalac P.Eng
 
Process Capability shift over time
Process Capability shift over timeProcess Capability shift over time
Process Capability shift over timeJulian Kalac P.Eng
 
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS Julian Kalac P.Eng
 
LEAN Setup Reduction (SMED) training for welding by JULIAN KALAC
LEAN Setup Reduction (SMED) training for welding by JULIAN KALACLEAN Setup Reduction (SMED) training for welding by JULIAN KALAC
LEAN Setup Reduction (SMED) training for welding by JULIAN KALACJulian Kalac P.Eng
 
Continuous improvement by Julian Kalac
Continuous improvement  by Julian KalacContinuous improvement  by Julian Kalac
Continuous improvement by Julian KalacJulian Kalac P.Eng
 
The hidden factory by JULIAN KALAC
The hidden factory by JULIAN KALACThe hidden factory by JULIAN KALAC
The hidden factory by JULIAN KALACJulian Kalac P.Eng
 

Mais de Julian Kalac P.Eng (20)

VOLVO EATS RACK LEAN TRANSFORMATION by Julian Kalac, P.Eng
VOLVO EATS RACK LEAN TRANSFORMATION  by Julian Kalac, P.EngVOLVO EATS RACK LEAN TRANSFORMATION  by Julian Kalac, P.Eng
VOLVO EATS RACK LEAN TRANSFORMATION by Julian Kalac, P.Eng
 
Batch & Queue vs Lean Continuous Flow
Batch & Queue vs Lean Continuous FlowBatch & Queue vs Lean Continuous Flow
Batch & Queue vs Lean Continuous Flow
 
Design for Six Sigma in Automotive
Design for Six Sigma in Automotive Design for Six Sigma in Automotive
Design for Six Sigma in Automotive
 
1000 Ton Transfer Press Risk Assessment
1000 Ton Transfer Press Risk Assessment 1000 Ton Transfer Press Risk Assessment
1000 Ton Transfer Press Risk Assessment
 
PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS
PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS
PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS
 
1000 TON TRANSFER PRESS SAFE WORK PROCEDURE ;DIE SETUP/CHANGEOVER
1000 TON TRANSFER PRESS SAFE WORK PROCEDURE ;DIE SETUP/CHANGEOVER1000 TON TRANSFER PRESS SAFE WORK PROCEDURE ;DIE SETUP/CHANGEOVER
1000 TON TRANSFER PRESS SAFE WORK PROCEDURE ;DIE SETUP/CHANGEOVER
 
Live wire testing lock out tag out safe work procedure
Live wire testing lock out tag out safe work procedureLive wire testing lock out tag out safe work procedure
Live wire testing lock out tag out safe work procedure
 
Julian Kalac lean 6 sigma project list--2018
 Julian Kalac lean 6 sigma  project list--2018 Julian Kalac lean 6 sigma  project list--2018
Julian Kalac lean 6 sigma project list--2018
 
Machine Safeguarding with Lock Out Tag Out
Machine Safeguarding with Lock Out Tag OutMachine Safeguarding with Lock Out Tag Out
Machine Safeguarding with Lock Out Tag Out
 
Custom Lean Eyelet machine SOP with 5 min changeover
Custom Lean Eyelet machine SOP with 5 min changeoverCustom Lean Eyelet machine SOP with 5 min changeover
Custom Lean Eyelet machine SOP with 5 min changeover
 
MWV CONTROL VS SPEC
MWV CONTROL VS SPECMWV CONTROL VS SPEC
MWV CONTROL VS SPEC
 
FCI AUTOMOTIVE 2005 FORD MINIVAN ABS-VSC LAUNCH
FCI AUTOMOTIVE 2005 FORD MINIVAN ABS-VSC LAUNCHFCI AUTOMOTIVE 2005 FORD MINIVAN ABS-VSC LAUNCH
FCI AUTOMOTIVE 2005 FORD MINIVAN ABS-VSC LAUNCH
 
DESIGN FMEA TRAINING FOR LITENS AUTOMOTIVE
DESIGN FMEA TRAINING FOR LITENS AUTOMOTIVE DESIGN FMEA TRAINING FOR LITENS AUTOMOTIVE
DESIGN FMEA TRAINING FOR LITENS AUTOMOTIVE
 
DFMEA DUE DILIGENCE TRAINING FOR LITENS AUTOMOTIVE
DFMEA DUE DILIGENCE TRAINING FOR LITENS AUTOMOTIVE DFMEA DUE DILIGENCE TRAINING FOR LITENS AUTOMOTIVE
DFMEA DUE DILIGENCE TRAINING FOR LITENS AUTOMOTIVE
 
Process Capability shift over time
Process Capability shift over timeProcess Capability shift over time
Process Capability shift over time
 
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS
 
LEAN Setup Reduction (SMED) training for welding by JULIAN KALAC
LEAN Setup Reduction (SMED) training for welding by JULIAN KALACLEAN Setup Reduction (SMED) training for welding by JULIAN KALAC
LEAN Setup Reduction (SMED) training for welding by JULIAN KALAC
 
Continuous improvement by Julian Kalac
Continuous improvement  by Julian KalacContinuous improvement  by Julian Kalac
Continuous improvement by Julian Kalac
 
The hidden factory by JULIAN KALAC
The hidden factory by JULIAN KALACThe hidden factory by JULIAN KALAC
The hidden factory by JULIAN KALAC
 
LOTO LIVE WIRE CS
LOTO LIVE WIRE CSLOTO LIVE WIRE CS
LOTO LIVE WIRE CS
 

Último

Future Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionFuture Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionMintel Group
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxMarkAnthonyAurellano
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesKeppelCorporation
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Kirill Klimov
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfJos Voskuil
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607dollysharma2066
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCRashishs7044
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Seta Wicaksana
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchirictsugar
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Pereraictsugar
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024christinemoorman
 
Call Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any TimeCall Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any Timedelhimodelshub1
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailAriel592675
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdfKhaled Al Awadi
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?Olivia Kresic
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy Verified Accounts
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africaictsugar
 

Último (20)

Future Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionFuture Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted Version
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation Slides
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdf
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchir
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Perera
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024
 
Call Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any TimeCall Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any Time
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detail
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail Accounts
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africa
 

Lean Supply Chain Management--by JULIAN KALAC

  • 1. Prepared by Julian Kalac, P.Eng Lean Six Sigma Master Black Belt 1
  • 2. 2
  • 3.
  • 4. 4 Shipped on time and customer happy We Made $$$$ ProductionMaterial Ship order CUSTOMER • No Wasted Time • No Wasted Money • No Wasted Resources • No Wasted Material ? ? 99% Customer Quality
  • 5. The truth 5 The Hidden Factory $5000-material scrap costs $35,000 REPRINTS cost Lost order Wrong order shipped ProductionMaterial Ship order CUSTOMER Hidden Factory
  • 6. 6 INSANITY --“Doing the same thing over and over again and expecting different results” Albert Einstein
  • 7. 7
  • 8. 8
  • 9.  “Lean” is a Japanese methodology that focuses on producing high quality products FASTER, better and at lowest cost.  Lean is about reducing NVA steps and waste (scrap, rework,) focusing on the Value Add work what the customer is paying for  Lean is NOT ELIMINATING JOBS!  The goal is that “you don’t work harder, but rather smarter” 9
  • 10. | | 10  Customers demand shorter lead times, improved quality & reduced prices  Increase through-put and quality and reduce time wasted and frustration by working on non-value add activities.  Gain new business
  • 11.  Identification and systemic elimination of non- value add costs and re-alignment of resources to deliver value to the customer faster, better, & more consistently  Lean in Manufacturing: ◦ Focus: Eliminate waste, non-value add steps, process constraints and bottle necks that cause problems in work throughput ◦ Approach: Intuitive and broad - “inch-deep, mile wide” 11 Leading to Leading toEliminate Waste Reduced Cycle Times Increased Capacity
  • 12. 12  Lean Manufacturing = SPEED  focusses on reducing waste/Non-Value Add activity and “Speeding” up the Process cycle Times.  Six Sigma = QUALITY 3.4 PPM  focusses on reducing defects and process variation  Six Sigma “Quality”+ Lean “Speed" =  PERFORMANCE
  • 13. Value Added Typically 95% of all lead time is non-value added 1. Overproduction 2. Waiting 3. Transportation 4. Non-Value Added Processing 5. Excess Inventory/Material 6. Defects 7. Excess Motion 8. Underutilized People Non-Value Added 5%
  • 14. | | 14 Lack of cross-functional training Over relying on a select few while others are Inadequately trained  Operators are unable to rotate and help each other out to balance the work- load High overtime, increased pressure stress
  • 15. 1
  • 16. 1
  • 17.
  • 18. 1
  • 19.  Cycle Time is dictated by the slowest (bottleneck) operation in the cell. 40 min 20 min 25 min 15 min 30 min 1 54 3 2 •What operation controls the cycle? •How can you relieve the bottleneck?
  • 20. Bottleneck Management: •Maintain buffer in front of bottleneck – (never starve the bottleneck !) •Improve bottleneck operation •Cross train on bottleneck – Creates a visual work place – Continuous Improvement – Cell Support – Balance activities / operations 20
  • 21. Pull Systems Production scheduling method used to link downstream activities to upstream activities Work begins based upon a demand signal (kanban) from a downstream customer, either internal or external Avoids overproduction, work backlog, and disconnects within a process Nothing is produced until the downstream customer signals a need
  • 22.  KANBAN ◦ A signal to produce ◦ Signal can be an empty square, bin, shelf, cart, or kanban card ◦ Kanban qty is safety stock used while new order is delivered ◦ Kanban qty is calculated based on usage, lead time, delivery time ◦ Can be setup manually or automated ◦ Can extend through electronic notification to suppliers using automatic messaging and triggers
  • 23. 2
  • 24.  SETUP TIME ◦ Starts when last piece of previous job is complete; ends when first good piece of next job is complete  INTERNAL SET-UP: While machine is shut-down Goal is to reduce Internal setup time, less= better  EXTERNAL SET-UP: While machine is working ◦ Goal is to transfer internal setup activities and increase external setup time, more= better
  • 25. Poke yoke = Error Proofing  Eliminate/minimize chance for human error to avoid mistakes ◦ Prevention Poke Yoke  Stops the process before failures occur  Does not allow defects to pass through the process
  • 26.  High-Level Process Map  Suppliers, Departments, Customers  Mid-Level Process Map  Specific Area ex Production  Detail-Level Process Map  Specific process/operation  (most commonly used) Stop Start Stop Start Start Stop Stop 26
  • 27. VA/NVA Ratio= 46% DPU = ____ RTYield = _____ SCORE CARD: I’m going to have coffee Fill c. maker with water Scoop Coffee into c. maker Get & place Filter in c. maker Drink coffee Is taste OK Brew coffee Pour c. into cup Add cream & sugar Water Supply Process Shopping Process Electricity Supply Process Eating Equipment Supply Process Tasting Process Housekeeping Processes Transactional& SupportProcesses ProcessData &Information NVA = Non-value Added Time VA = Value Added Time VA Time NVA Time Temp of Water= ___ Quality of Water= ___ Pressure of Water= ___ Amount of Coffee= ___ Quality of Coffee= ___ Type of Coffee= ___ Defective Coffee= ___ 60 sec 30 sec 60 sec 360 sec 10 sec 60 sec 10 sec 10 sec 5 sec 600 sec 30 sec
  • 28. SCOR (Supply Chain Operations Reference) Model: Structured around Five CORE Process Types SCOR Model Customer’s Customer Supplier’s Supplier Supplier Internal or External Customer Internal or External Your Company Plan Make DeliverSource Make / Repair DeliverMakeSourceDeliver SourceDeliverSource Return Return Return Return Return Return Return Return Plan Plan Provides Framework for your Transformation / Improvement Projects. • Defining the boundaries / scope of the supply chain . • Evaluate the supply chain’s strengths and weaknesses. • Industry benchmarks, standardized terms, metrics, Enables a total enterprise view of a supply chain 2
  • 29. Product/ServiceValueStream Processes Processes Process Start Process Finish Process Steps Processes Processes Organization Customers End-use Customers Suppliers Sub- Suppliers Process Steps TransactionalProcessSteps Return Return Plan Make DeliverSource Make/Repai r DeliverMakeSourceDeliver SourceDeliverSource Return Return Return Return Return Return SCOR Supply Chain Model 29
  • 31. 15 coils/shift 8 20 26 39 31 10 20 4 13 19 20 8 40 20 20 20 20 20 20 20 Start Loop coils 180 deg twist & prep Skin Electric Press Coil form Model check M/C tapePre-tape Final Tape Apply Mylar Micalast Load Micalastic Impregnation Final Press & Cure Remove Mylar Final gauge ECP Tape ECP oven cure Strand & Final testPack & Ship Stop Rotation schedule: Based on the cycle times above every 2Hrs, Rotate Final Taping operators with operators from “Skinning”, Electric Pressing. Coil forming & Model- checking. This will increase productivity from 28 Coils/Day to 40 Coils/Day and ensure max exposure to F/T not more then 2hrs/day. Needed: Cross-functional training and ~ 1 week learning curve to achieve 85% operator efficiency 3
  • 32.  Increased Coil Productivity by 30% from 28 to 40 Coils/day = $420K/Year  Increased direct labour utilization by 26% =$240K/Year  Reduced in-process scrap from 20% to under 4%  OEE improvement of 24% (from 62% to 84%)  Flexible work Cells & cross functionally trained workers able to help manage bottleneck efficiently  MOL order on Final Tape exposure complied with  Total Operational Savings = $ 800K 3
  • 33.  The Five Principles of “Lean Thinking” 1. Define Customer demand TAKT TIME) 2. Map out the Current process (value stream) identify Value and Non Value Add steps 3. Get the product to “flow” faster by eliminating NVA steps and bottlenecks 4. Eliminate WIP, implement continuous flow 5. Implement POKE YOKE systems to error proof to improvements 33
  • 34. 34 Lost managemant time cost Maintenance cost Lost opportunity Lost assets cost Rerun cost Lost business, goodwill cost Lost credibility cost Prevention cost appraisal cost Project rework cost Litigation SS Titanic Management Waste Costs: Costs driven by problems and process steps that add no value to products & services delivered to customers Appraisal Costs: Costs incurred to determine the degree of conformance to customer needs Prevention Costs: Costs incurred to keep failure and appraisal costs to a minimum Failure Costs: Costs directly incurred due to defects internal to the system or after delivery to the customer
  • 36. 3 σ Methodology that Focuses on Reducing Process Variation, using data-driven, measurement-based, statistical methods to Solve problems, improve performance σ Focus: Surgical “inch-wide, mile-deep” investigation and resolution σ Approach: σ Data driven solves problems at the system and root cause level σ Implement robust control plans for sustained improvements What is “Six Sigma”? An Analytical Methodology that Focuses on Reducing Process Variation
  • 37. 1 )( 2     n xxi   Sigma =  = Deviation ( Square root of variance ) -7 -6 -5 -4 -3 -2 -1 0 1 2 3 4 5 6 7 Axis graduated in Sigma 68.27 % 95.45 % 99.73 % 99.9937 % 99.999943 % 99.9999998 % result: 317300 ppm outside (deviation) 45500 ppm 2700 ppm 63 ppm 0.57 ppm 0.002 ppm between + / - 1 between + / - 2 between + / - 3 between + / - 4 between + / - 5 between + / - 6  =
  • 38. 38 •Identify customer metrics •Select performances standards •Select objectives •Map the process •Validate measurement System (MSA) •RESULT: Process maps and good quality data collected by listening to the process •Identify sources of variation & failure points •Redefine and Re-prioritize •Establish process capability •Identify improvement opportunities •RESULT: The critical sources of variation identified root causes determined •Monitor processes to prevent recurrence of variation, defects and non-value work •Maintain performance levels •find more creative ways to improve •fix root causes •Find/Implement Preventive Fixes •Deploy changes organization •RESULT: Performance is more predictable ; culture changing •Plan and apply Improve Tools to fix problems and reduce variation •Implement improvement opportunities •RESULT: Improve tools applied, changes implemented and performance improvement in place DMAIC Improvement Model A Road Map for guiding Improvement Projects •Identify customer problems •Identify performances standards •Identify improvement objectives •Link problem to the key performance metrics •Find the right problems •RESULT: Problem Statement & Project Charter Define Measure AnalyzeImprove Control Results Define Measure AnalyzeImprove Control Results
  • 39. 39 Define Measure AnalyzeImprove Control Results Define Measure AnalyzeImprove Control Results Applied Learning Theory Practice Coached Projects  Training typically occurs over a 4-6 month period using a Learn  Apply; Learn Apply; … format.  Projects that solve real performance problems in your organization are part of the certification and learning process Recognize: •Find problems •Link to organization's needs •Form teams, define resources •Understand program req’ts Deploy: •Validate improved performance that stays in place •Spread improvements across the enterprise •Harvest the performance improvements •Change the culture
  • 40.
  • 41. To understand where you want to be, you need to know how to get there.v Map the Process Measure the Process Identify the variables - ‘x’ Understand the Problem - ’Y’ = function of variables -’x’ Y=f(x)
  • 42. 4 2) Clearly Define your Problem and the Impact Example: Too many mistakes in purchase request specifications are causing rework rates of 34%, high costs and late deliveries (less than 50% on time) to our customers 1) Find • Customer Issues • Performance Reviews • Meetings • New Projects • Failures, Re-work • Projects • Continuous improvement activities • Champions • Stakeholders • Employees • SCOR Maps • Research • Brainstorm • Wait until the crisis hits you • Value Stream Maps 3) Clearly State the Initial Scope for your project (Set targets and timelines!) Example: This first phase of this project – by 3Q 2004 - will identify problems and root causes in the purchase request process, increase first pass yield rates to 95%, reduce the cost of poor quality by 50% and increase on-time deliveries to our customers to greater than 90% 4) Link improvement targets to customer needs and organizational objectives 5) Project Plan – Charter, Resources, Milestones
  • 43. 4 3 Process Flow for Measure Phase Data Storage and Archiving Foundations for Wisdom and good decision making start with Good Data What data do we need? Can we use “old” historical data? Is old data (still) usable? How was it collected? Wisdom Knowledge Data Information Wisdom Knowledge Data Information Wisdom Knowledge Data Information Data Selection Data Integrity Analysis Data Collection Measurement System Analysis Process Mapping
  • 44. Is your error in the process or in the way you measure it? Could it be that you actually are “good” but the error in the measurement system shows that you are not “good”? Overall Variation Occurrence-to- Occurrence ( or Piece- to-Piece) Variation Measurement System Variation Repeatability: Variation due to gage or measurement tool Reproducibility: Variation due to people or operators who are measuring 2 Total = 2 Part-Part + 2 R&R
  • 45. Accurate but not precise - On average, the shots are in the center of the target but there is a lot of variability Precise but not accurate - The average is not on the center, but the variability is small Source: iSixSigma
  • 46. 46 Organize & Understand your data Statistical Analysis Determine significant factors Sort, Collate, Investigate your data Wisdom Knowledge Data Information Wisdom Knowledge Data Information Wisdom Knowledge Data Information
  • 47. We know we must change X to create a change in Y… But how do we know which Xs to change and how to change them ? 4 Y =f (x1, x2, …) process output key process input factors affecting process output function of
  • 49. Statistical Analysis 0.0250.0200.0150.0100.0050.000 7 6 5 4 3 2 1 0 New Machine Frequency 0.0250.0200.0150.0100.0050.000 30 20 10 0 Machine 6 mths Frequency  Is the factor really important?  Do we understand the impact for the factor?  Has our improvement made an impact  What is the true impact? Hypothesis Testing Regression Analysis 55453525155 60 50 40 30 20 10 0 X Y R-Sq = 86.0 % Y = 2.19469 + 0.918549X 95% PI Regression Regression Plot Apply statistics to validate actions & improvements P value< 0.5--Significant
  • 50. The minimum sample size required to provide exactly 5% overlap (risk). In order to distinguish the Delta. Note: If you are working with Non- normal Data, multiply your calculated sample size by 1.1 50 40 50 60 7040 50 60 70 40 60 7050 Population P value< 0.5--Significant
  • 51. 51 PROBLEM FINDING FACT FINDING PROBLEM DEFINITION IDEA FINDING EVAL. & SELECT PLAN ACCEPT -ANCE ACTION 1 2 3 4 6 7 8 5 Select Tool Analyze Data & Information Apply tools & Make Changes Six Sigma Projects 5S PM/TPM TQM Rapid Improve- ment Event Integrated Process Team (IPT) Establish Baselines/Metrics Other CI Tools Kanban DFSS ApplytheTool (1) (2) (3)Implement / Deploy Fixes (0) Identify failure points, bottlenecks and improvement opportunities from Define-Measure-Analyze Phases PM = Preventive Maintenance TPM = Total Productive Maintenance CI = Continuous Improvement DFSS = Design for Six Sigma TQM = Total Quality Management
  • 52. Maintaining and Improving Control:  Managing Change  Quality Management Systems  What’s Left? What’s Next? 52 Control Tools: • POKA YOKE • Control Charts • Statistical Process Control (SPC) Document Procedures and Best Practices Create Visual Controls and “Dashboards” Update Deployment Plan Complete Control FMEA Update and Deploy Communication Plan Execute Deployment Plan Document Other Opportunities Prepare and Implement Control Plan Report out, Hand- off and Closure Prepare and Implement Training Plan Process Flow Diagram for Control Phase:
  • 53. 53 Key Process Input Variable Key Process Output Variable Process Specification (LSL, USL, Target) Capability (Cp, Cpk, DPMO) and date Measurement Technique Sample Size Sample Frequency Control Element Contigency Remedial Audit Phone Call LSL - NA TGT- 10 sec USL - 30 secs Cpk=.85 05 Dec 03 Call Center Manager Dashboard 30 1/2 hourly CCM to adjust seated agents CCM to reprioritize worload to meet specification Daily report to be examined by Supervisor N New Customer LSL - NA TGT- 15 min USL - 30 min Cpk=. 48 05 Dec 03 New Acct Dept Visual Display 100 Weekly Nacct Mgr to monitor and adjust new Acct Reps Nacct Mgr to reprioritize Monthly report to NAM regional manager Y New Accounts 0 Field defects DPMO = 66289 05 Dec 03 New Acct Dept Visual Display 100 Weekly Nacct Mgr to monitor and adjust new Acct Reps Nacct Mgr to use Pareto Analysis to determine defect category Monthly report to NAM regional manager Y Lead Time LSL - NA TGT- 5 Days USL - 10 Days Cpk = 1.43 05 Dec 03 Operations Dashboard 30 Daily Ops Mgr Review Identify trend root cause Director Review Weekly N Customer Expedite Expedite Order 0 Expedited DPMO = 24721 05 Dec 03 Operations Dashboard 25 Weekly Ops Mgr Review Identify trend root cause Director Review Monthly Y Key Process Input Variable Key Process Output Variable Process Specification or Target Output Value Current Performance Value Sample Size Sample Frequency Control Element Contingency Plans Remedial Plans Is the Performance Audited
  • 54. DPMO / Control Chart 20000 25000 30000 35000 40000 45000 50000 55000 60000 65000 70000 75000 80000 85000 90000 95000 100000 2/5/2001 2/19/2001 3/5/2001 3/19/2001 4/2/2001 4/16/2001 4/30/2001 5/14/2001 5/28/2001 6/11/2001 6/25/2001 7/9/2001 7/23/2001 8/6/2001 8/20/2001 9/3/2001 9/17/2001 10/1/2001 10/15/2001 10/29/2001 11/12/2001 11/26/2001 12/10/2001 12/24/2001 DPMO Baseline DPMO UCL LCL Mean Goal Process Change REGIONAL CONTROL BEGINS PAST BKLOG PAST BKLOG P-DUE PAST UNITS DUE PM DUE LUBE SVC DUE REGION ASSIGN PM DAYS LUBE DAYS GOAL SVC NETWORK 2327 1 0 107 4 93 77 CENTRAL 151 0 0 8 4.8 6 8 F.B.U. 74 0 0 0 0 3 2 MIDWEST 178 2 1 9 4.6 7 3 NORTHEAST 312 0 0 33 9.7 12 18 SOUTHERN 389 0 0 43 10.1 16 36 WESTERN 259 0 0 19 6.7 10 11 TOTAL 3689 3 0 219 5.4 150 155 OFFLINE 203 4 1.8 37 16.8 1 4 NEW ACCOUNT EXCEPTION SUMMARY 12/08/2003 Item No. Problem/Opportunity Benefit Person(s) Responsible Due Date % Complete Comments 1 2 3 4 5 6 7 8 Kaizen Event Newspaper Team: Kaizen Event: Kaizen Newspaper The Control Plan explains how the Dashboard Works and what to do if performance goes out of controlImprovement Actions and Activities Updated: __/__/__ By:________
  • 55. 5 DPMO / Control Chart 20000 25000 30000 35000 40000 45000 50000 55000 60000 65000 70000 75000 80000 85000 90000 95000 100000 2/5/2 0012/19/20013/5/2 0013/19/20014/2/2 0014/16/20014/30/20015/14/20015/28/20016/11/20016/25/20017/9/2 0017/23/20018/6/2 0018/20/20019/3/2 0019/17/200110/1/2001 10/15 /2001 10/29 /2001 11/12 /2001 11/26 /2001 12/10 /2001 12/24 /2001 DPMO Baseline DPMO UCL LCL Mean Goal Process Change REGIONAL CONTROL BEGINS
  • 56. 5 Control Limits -7 -6 -5 -4 -3 -2 -1 0 1 2 3 4 5 6 7 DPMO / Control Chart 20000 25000 30000 35000 40000 45000 50000 55000 60000 65000 70000 75000 80000 85000 90000 95000 100000 2/5/2 0012/19/20013/5/2 0013/19/20014/2/2 0014/16/20014/30/20015/14/20015/28/20016/11/20016/25/20017/9/2 0017/23/20018/6/2 0018/20/20019/3/2 0019/17/200110/1/2001 10/15 /2001 10/29 /2001 11/12 /2001 11/26 /2001 12/10 /2001 12/24 /2001 DPMO Baseline DPMO UCL LCL Mean Goal Process Change REGIONAL CONTROL BEGINS
  • 57. Lean Manufacturing  Value Stream Mapping  Line Balancing  Continuous Flow  PULL system  KANBAN  Set Up reduction (SMED)  Poke Yoke/Error Proofing  5S Six Sigma  DMAIC, SIPOC process  Gage R&R  FMEA Hypothesis Testing Regression  Statistical Analysis  Process Capability Cp, Cpk  Roll Throughput Yield  Design of Experiments  Control Charts 57
  • 58. “Lean” focuses on: The systematic elimination of waste and re-alignment of resources to deliver value to the customer faster, better, & more consistently Supply Chain Management: Mapping your processes through the entire business enterprise with standard elements “Six Sigma” focuses on: Use of analytical and methodical fact based problem solving methods Drastically reduce variation then control and manage whatever variation is left over Increase predictability, accuracy and precision Product and Services Cash/Funding Information Customer’s Customer Supplier’s Supplier SupplierSupplier CustomerCustomerYour Company PlanPlan Make DeliverSourceSource Make / Repair DeliverMakeSourceDeliver SourceDeliverDeliverSource ReturnReturn ReturnReturn ReturnReturn ReturnReturn ReturnReturn ReturnReturn ReturnReturn ReturnReturn PlanPlan PlanPlan LSL USLẊ Theory of Constraints: Find & eliminate the bottle necks Business Process Re- engineering: Start over VA Time NVA Time FLOW
  • 59. Numbers, words, quantities, values stored sitting in piles or queues waiting for future use Charts, summaries, spread sheets, etc. that organize the data Presentations, plans and tools that explain and communicate the information Processes, organizations and team using the information to improve, manage, build systems and develop cultures Push the data “up” to become Wise Always loop back to check the data Wisdom Knowledge Data Information Where are you looking from? The WISDOM TOWER: Changing Perspectives