SlideShare uma empresa Scribd logo
1 de 19
Baixar para ler offline
Planning & Iron Triangle
Project Management Plan
3Project Management Plan
The Project Management Plan (PMP) is a formal, approved document used to manage project execution. The PMP
documents the actions necessary to define, prepare, integrate and coordinate the various planning activities. The
PMP defines how the project is executed, monitored and controlled, and closed. It is progressively elaborated by
updates throughout the course of the project. The PMP is also a communication vehicle for ensuring key stakeholders
share an understanding of the project. The PMP is NOT a project schedule. A project schedule lists planned dates for
performing tasks and activities to meet milestones identified in the project plan.
4Project Management Plan TOC
Critical Path Method
6Develop Schedule
To develop your project schedule, you'll need to do three things first...
• Define Activity
• Sequence Activity
• Estimate Activity Durations
1. Define Activity
The first step to developing your schedule is to define the specific activities that need to be performed in order to
complete the project.
2. Sequence Activity
Once your activity list is ready, the next step is to determine the order each of the activities needs to be completed in.
3. Estimate Activity Durations
The third step is to estimate how long each activity will take to complete. This needs to take into account the type,
amount, and availability of people, material, equipment and supplies that are needed to perform each activity.
7Activity Dependency
8Critical Path Method
Critical path schedules...
• Help you identify the activities that must be completed on time in order to complete the whole project on time.
• Show you which activitys can be delayed and for how long without impacting the overall project schedule.
• Calculate the minimum amount of time it will take to complete the project.
• Tell you the earliest and latest dates each activity can start on in order to maintain the schedule.
The CPM has four key elements...
• Critical Path Analysis
• Float Determination
• Early Start & Early Finish Calculation
• Late Start & Late Finish Calculation
9Activity Dependency
10Activity Dependency
Critical path schedules...
• Help you identify the activities that must be completed on time in order to
complete the whole project on time.
• Show you which activities can be delayed and for how long without impacting the
overall project schedule.
• Calculate the minimum amount of time it will take to complete the project.
• Tell you the earliest and latest dates each activity can start on in order to maintain
the schedule.
The CPM has four key elements...
• Critical Path Analysis
• Float Determination
• Early Start & Early Finish Calculation
• Late Start & Late Finish Calculation
11Critical Path Method
12Float
13Early Start & Early Finish Calculation
The Critical Path Method includes a technique called the Forward Pass which is used to determine the earliest date an activity can
start and the earliest date it can finish. These dates are valid as long as all prior activities in that path started on their earliest start
date and didn't slip.
Starting with the critical path, the Early Start (ES) of the first activity is one. The Early Finish (EF) of an activity is its ES plus its
duration minus one. Using our earlier example, Activity 2 is the first activity on the critical path: ES = 1, EF = 1 + 5 -1 = 5.
You then move to the next activity in the path, in this case Activity 3. Its ES is the previous activity's EF + 1. Activity 3
ES = 5 + 1 = 6. Its EF is calculated the same as before: EF = 6 + 7 - 1 = 12.
If an activity has more than one predecessor, to calculate its ES you will use the activity with the latest EF.
14Late Start & Late Finish Calculation
The Backward Pass is a Critical Path Method techique you can use to determine the latest date an activity can start and the latest
date it can finish before it delays the project.
You'll start once again with the critical path, but this time you'l begin from the last activity in the path. The Late Finish (LF) for the
last activity in every path is the same as the last activity's EF in the critical path. The Late Start (LS) is the LF - duration + 1.
In our example, Activity 4 is the last activity on the critical path. Its LF is the same as its EF, which is 14. To calculate the LS, subtract
its duration from its LF and add one. LS = 14 - 2 + 1 = 13.
You then move on to the next activity in the path. Its LF is determined by subtracting one from the previous activity's LS. In our
example, the next Activity in the critical path is Activity 3. Its LF is equal to Activity 4 LS - 1. Activity 3 LF = 13 -1 = 12. It's LS is
calculated the same as before by subtracting its duration from the LF and adding one. Activity 3 LS = 12 - 7 + 1 = 6.
You will continue in this manner moving along each path filling in LF and LS for activities that don't have it already filled in.
Earn Value Metrics
16Earn Value Metrics
Earned Value measures performance against a plan at a given point in time.
Term Full Name Meaning
PV Planned Value Estimated value of the work planned to be done
EV Earned Value Estimated value of the work actually accomplished
AC Actual Costs Actual Costs Incurred
BAC Budget At Completion Amount budgeted for total project
EAC Estimate At Completion Currently expected total for project
ETC Estimate To Complete How much More to finish
VAC Variance At Completion How much over/under we expect to be
17Formula
Earned Value Formula
Name Formula Meaning
Cost Variance CV=EV-AC -ve=over budget, +ve=under budget
Schedule Variance SV=EV-PV -ve=behind schedule, +ve=ahead schedule
AC Actual Costs Actual Costs Incurred
Cost Performance
Index (CPI)
CPI=EV/AC We are getting _ cents out of every $ spent
Schedule Performance
Index
SPI=EV/PV We are progressing at _% of the rate originally planned
Estimate At
Completion
EAC=BAC/CPI As of now, how much do we expect the total project to cost
Estimate To Complete ETC=EAC-AC How much more to finish
Variance At
Completion
BAC-EAC How much over/under we expect to be
18Example
Let’s imagine our project is to build a wall around a garden. Assuming 4 equal sides, a budget of $200 per side and
a schedule of 1 side per day. We should be finished in 4 days for a total of $800. If, after Day 3, our progress is as
follows:
19Calculation
Name Formula Day 3 Value
PV - Planned Value Estimated value of the work planned to be done
Should have done 3 x $200 = $600 or
Percentage Complete 75%
SV=EV-PV Estimated value of the work actually accomplished
Actually done 2.5 sides $200+$200+$100 = $500 or
Actual Percentage Complete 62.5%
AC - Actual Costs Actual Costs Incurred $200+$220+$140=$560
Cost Performance Index Over / Under Budget factor CPI = EV / AC $500 / $560 = 0.89
Schedule Performance Index Ahead / Behind Schedule factor SPI = EV / PV
$500 / $600 = 0.83 0r
62.5%/75%% = 0.83
BAC - Budget At Completion Amount budgeted for total project $800
EAC - Estimate At Completion ETC=EAC-AC Currently expected total for project EAC=BAC / CPI
ETC - Estimate To Complete How much more to finish? ETC = EAC - AC $899 - $560 = $339
VAC - Variance At Completion
How much over/under we expect to be VAC = BAC –
EAC
$800 - $899 = -$99

Mais conteúdo relacionado

Mais procurados

How Project Network Diagram's Can Help You Become A Better Project Manager
How Project Network Diagram's Can Help You Become A Better Project ManagerHow Project Network Diagram's Can Help You Become A Better Project Manager
How Project Network Diagram's Can Help You Become A Better Project ManagerPraveen Malik, PMP
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)chandkec
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path AnalysisDavid Zaki
 
The Critical Path Method
The Critical Path MethodThe Critical Path Method
The Critical Path MethodNicola2903
 
Critical path method
Critical path methodCritical path method
Critical path methodDhruv Shah
 
Using The Earned Value Method To Calculate Project Delays In Terms Of Time
Using The Earned Value Method To Calculate Project Delays In Terms Of TimeUsing The Earned Value Method To Calculate Project Delays In Terms Of Time
Using The Earned Value Method To Calculate Project Delays In Terms Of TimeAhmed Elsayed
 
Free float and total float - PMP/CAPM from PMI
Free float and total float - PMP/CAPM from PMIFree float and total float - PMP/CAPM from PMI
Free float and total float - PMP/CAPM from PMIMudassir Iqbal
 
Unit.6. network analysis with cpm and pert
Unit.6. network analysis with cpm and pertUnit.6. network analysis with cpm and pert
Unit.6. network analysis with cpm and pertDagnaygebawGoshme
 
Ms Project 2007(advanced)
Ms Project 2007(advanced)Ms Project 2007(advanced)
Ms Project 2007(advanced)Dinesh Singh
 
CPM - Critical Path Method
CPM - Critical Path MethodCPM - Critical Path Method
CPM - Critical Path MethodParth Desani
 
Critical path method & pert
Critical path method & pertCritical path method & pert
Critical path method & pertBhim Upadhyaya
 
Cm ch4 scheduling
Cm ch4 schedulingCm ch4 scheduling
Cm ch4 schedulingAhmed Gamal
 

Mais procurados (20)

How Project Network Diagram's Can Help You Become A Better Project Manager
How Project Network Diagram's Can Help You Become A Better Project ManagerHow Project Network Diagram's Can Help You Become A Better Project Manager
How Project Network Diagram's Can Help You Become A Better Project Manager
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path Analysis
 
Project Management Techniques
Project Management TechniquesProject Management Techniques
Project Management Techniques
 
Critical path method
Critical path methodCritical path method
Critical path method
 
The Critical Path Method
The Critical Path MethodThe Critical Path Method
The Critical Path Method
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Per tand project crashing
Per tand project crashingPer tand project crashing
Per tand project crashing
 
Using The Earned Value Method To Calculate Project Delays In Terms Of Time
Using The Earned Value Method To Calculate Project Delays In Terms Of TimeUsing The Earned Value Method To Calculate Project Delays In Terms Of Time
Using The Earned Value Method To Calculate Project Delays In Terms Of Time
 
Ppsi pertemuan-3
Ppsi pertemuan-3Ppsi pertemuan-3
Ppsi pertemuan-3
 
CPM NETWORK
CPM NETWORKCPM NETWORK
CPM NETWORK
 
Free float and total float - PMP/CAPM from PMI
Free float and total float - PMP/CAPM from PMIFree float and total float - PMP/CAPM from PMI
Free float and total float - PMP/CAPM from PMI
 
06 pert cpm
06 pert cpm06 pert cpm
06 pert cpm
 
Unit.6. network analysis with cpm and pert
Unit.6. network analysis with cpm and pertUnit.6. network analysis with cpm and pert
Unit.6. network analysis with cpm and pert
 
Ms Project 2007(advanced)
Ms Project 2007(advanced)Ms Project 2007(advanced)
Ms Project 2007(advanced)
 
CPM - Critical Path Method
CPM - Critical Path MethodCPM - Critical Path Method
CPM - Critical Path Method
 
Critical path method & pert
Critical path method & pertCritical path method & pert
Critical path method & pert
 
Network Techniques
Network TechniquesNetwork Techniques
Network Techniques
 
Cm ch4 scheduling
Cm ch4 schedulingCm ch4 scheduling
Cm ch4 scheduling
 
Chapt 6 slides
Chapt 6 slidesChapt 6 slides
Chapt 6 slides
 

Destaque

Proteccion juridica software
Proteccion juridica softwareProteccion juridica software
Proteccion juridica softwareHenry Marca
 
Tendências de bilhetagem eletrônica: Casos de uso Cartões Dupla função
Tendências de bilhetagem eletrônica: Casos de uso Cartões Dupla funçãoTendências de bilhetagem eletrônica: Casos de uso Cartões Dupla função
Tendências de bilhetagem eletrônica: Casos de uso Cartões Dupla funçãoAndre Dantas
 
Taller#6 walter rojas hurtado 8°c
Taller#6 walter rojas hurtado 8°cTaller#6 walter rojas hurtado 8°c
Taller#6 walter rojas hurtado 8°cwalter rojas hurtado
 
Acta semanal de desempeño (1)
Acta semanal de desempeño (1)Acta semanal de desempeño (1)
Acta semanal de desempeño (1)Yeferson Valencia
 
Integrative Design for Health A systematic approach to promoting health, well...
Integrative Design for Health A systematic approach to promoting health, well...Integrative Design for Health A systematic approach to promoting health, well...
Integrative Design for Health A systematic approach to promoting health, well...smcmahonusgbc
 
Cambios técnicos computadoras-Laptop
Cambios técnicos computadoras-LaptopCambios técnicos computadoras-Laptop
Cambios técnicos computadoras-LaptopHuGo Carpio
 
Profil exécutif de DFx TECH
Profil exécutif de DFx TECHProfil exécutif de DFx TECH
Profil exécutif de DFx TECHMartin Paré
 
Relatório curso de reprocessamento de endoscópios digestivos e acessórios
Relatório curso de reprocessamento de endoscópios digestivos e acessóriosRelatório curso de reprocessamento de endoscópios digestivos e acessórios
Relatório curso de reprocessamento de endoscópios digestivos e acessóriosNoémia Leite
 
Sectores económicos
Sectores económicosSectores económicos
Sectores económicosdianba26
 

Destaque (12)

Proteccion juridica software
Proteccion juridica softwareProteccion juridica software
Proteccion juridica software
 
Tendências de bilhetagem eletrônica: Casos de uso Cartões Dupla função
Tendências de bilhetagem eletrônica: Casos de uso Cartões Dupla funçãoTendências de bilhetagem eletrônica: Casos de uso Cartões Dupla função
Tendências de bilhetagem eletrônica: Casos de uso Cartões Dupla função
 
Factores de riesgo
Factores de riesgoFactores de riesgo
Factores de riesgo
 
Taller#6 walter rojas hurtado 8°c
Taller#6 walter rojas hurtado 8°cTaller#6 walter rojas hurtado 8°c
Taller#6 walter rojas hurtado 8°c
 
Taller#7 walter rojas hurtado
Taller#7 walter rojas hurtadoTaller#7 walter rojas hurtado
Taller#7 walter rojas hurtado
 
La netiqueta 8c
La netiqueta  8cLa netiqueta  8c
La netiqueta 8c
 
Acta semanal de desempeño (1)
Acta semanal de desempeño (1)Acta semanal de desempeño (1)
Acta semanal de desempeño (1)
 
Integrative Design for Health A systematic approach to promoting health, well...
Integrative Design for Health A systematic approach to promoting health, well...Integrative Design for Health A systematic approach to promoting health, well...
Integrative Design for Health A systematic approach to promoting health, well...
 
Cambios técnicos computadoras-Laptop
Cambios técnicos computadoras-LaptopCambios técnicos computadoras-Laptop
Cambios técnicos computadoras-Laptop
 
Profil exécutif de DFx TECH
Profil exécutif de DFx TECHProfil exécutif de DFx TECH
Profil exécutif de DFx TECH
 
Relatório curso de reprocessamento de endoscópios digestivos e acessórios
Relatório curso de reprocessamento de endoscópios digestivos e acessóriosRelatório curso de reprocessamento de endoscópios digestivos e acessórios
Relatório curso de reprocessamento de endoscópios digestivos e acessórios
 
Sectores económicos
Sectores económicosSectores económicos
Sectores económicos
 

Semelhante a Day 2 Revision

Critical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateCritical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateSHAZEBALIKHAN1
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)Debanjan15
 
Critical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docxCritical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docxannettsparrow
 
Pert cpm SIDDANNA M BALAPGOL
Pert cpm SIDDANNA M BALAPGOLPert cpm SIDDANNA M BALAPGOL
Pert cpm SIDDANNA M BALAPGOLSiddanna Balapgol
 
Critical path lecture by EDP.pptxbdhshsjjdj
Critical path lecture by EDP.pptxbdhshsjjdjCritical path lecture by EDP.pptxbdhshsjjdj
Critical path lecture by EDP.pptxbdhshsjjdjlicpn03
 
SPM presentation extra material-Lect 9and 10.pptx
SPM presentation extra material-Lect 9and 10.pptxSPM presentation extra material-Lect 9and 10.pptx
SPM presentation extra material-Lect 9and 10.pptxMuhammadAbubakar114879
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Akaresh Jose Kaviyil JY
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1adeelmunir158
 
Syam critical path cpa
Syam critical path cpaSyam critical path cpa
Syam critical path cpasyamputra
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentationNithin Dev
 
ABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesYousef Abugosh, PMP, MA
 
Pb602 operation management chapter 7
Pb602  operation management chapter 7Pb602  operation management chapter 7
Pb602 operation management chapter 7Akihisa Akimoto
 
PMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docxPMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docxstilliegeorgiana
 

Semelhante a Day 2 Revision (20)

Day 1 - Revision
Day 1 - RevisionDay 1 - Revision
Day 1 - Revision
 
Critical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateCritical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel Template
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
 
cpmpertmy (1)
cpmpertmy (1)cpmpertmy (1)
cpmpertmy (1)
 
Critical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docxCritical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docx
 
Pert cpm SIDDANNA M BALAPGOL
Pert cpm SIDDANNA M BALAPGOLPert cpm SIDDANNA M BALAPGOL
Pert cpm SIDDANNA M BALAPGOL
 
Critical path lecture by EDP.pptxbdhshsjjdj
Critical path lecture by EDP.pptxbdhshsjjdjCritical path lecture by EDP.pptxbdhshsjjdj
Critical path lecture by EDP.pptxbdhshsjjdj
 
SPM presentation extra material-Lect 9and 10.pptx
SPM presentation extra material-Lect 9and 10.pptxSPM presentation extra material-Lect 9and 10.pptx
SPM presentation extra material-Lect 9and 10.pptx
 
PM-Problems.pptx
PM-Problems.pptxPM-Problems.pptx
PM-Problems.pptx
 
Cpm pert
Cpm pertCpm pert
Cpm pert
 
PERT-Overview1.pdf
PERT-Overview1.pdfPERT-Overview1.pdf
PERT-Overview1.pdf
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )
 
Project Management.pptx
Project Management.pptxProject Management.pptx
Project Management.pptx
 
Pmp time chapter 6
Pmp time chapter 6Pmp time chapter 6
Pmp time chapter 6
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1
 
Syam critical path cpa
Syam critical path cpaSyam critical path cpa
Syam critical path cpa
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentation
 
ABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning Slides
 
Pb602 operation management chapter 7
Pb602  operation management chapter 7Pb602  operation management chapter 7
Pb602 operation management chapter 7
 
PMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docxPMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docx
 

Mais de Joyce Wong

Day 00000 - Bootcamp Roadmap for PowerPM
Day 00000 - Bootcamp Roadmap for PowerPMDay 00000 - Bootcamp Roadmap for PowerPM
Day 00000 - Bootcamp Roadmap for PowerPMJoyce Wong
 
Day 4 Group effectiveness
Day 4   Group effectivenessDay 4   Group effectiveness
Day 4 Group effectivenessJoyce Wong
 
Day 2 - Revision
Day 2 - RevisionDay 2 - Revision
Day 2 - RevisionJoyce Wong
 
Day 0 Introduction to PM
Day 0   Introduction to PMDay 0   Introduction to PM
Day 0 Introduction to PMJoyce Wong
 
Day 1 revision
Day 1  revisionDay 1  revision
Day 1 revisionJoyce Wong
 
Day 0 Introduction to PM
Day 0   Introduction to PMDay 0   Introduction to PM
Day 0 Introduction to PMJoyce Wong
 

Mais de Joyce Wong (6)

Day 00000 - Bootcamp Roadmap for PowerPM
Day 00000 - Bootcamp Roadmap for PowerPMDay 00000 - Bootcamp Roadmap for PowerPM
Day 00000 - Bootcamp Roadmap for PowerPM
 
Day 4 Group effectiveness
Day 4   Group effectivenessDay 4   Group effectiveness
Day 4 Group effectiveness
 
Day 2 - Revision
Day 2 - RevisionDay 2 - Revision
Day 2 - Revision
 
Day 0 Introduction to PM
Day 0   Introduction to PMDay 0   Introduction to PM
Day 0 Introduction to PM
 
Day 1 revision
Day 1  revisionDay 1  revision
Day 1 revision
 
Day 0 Introduction to PM
Day 0   Introduction to PMDay 0   Introduction to PM
Day 0 Introduction to PM
 

Último

2k Shots ≽ 9205541914 ≼ Call Girls In Palam (Delhi)
2k Shots ≽ 9205541914 ≼ Call Girls In Palam (Delhi)2k Shots ≽ 9205541914 ≼ Call Girls In Palam (Delhi)
2k Shots ≽ 9205541914 ≼ Call Girls In Palam (Delhi)Delhi Call girls
 
$ Love Spells^ 💎 (310) 882-6330 in West Virginia, WV | Psychic Reading Best B...
$ Love Spells^ 💎 (310) 882-6330 in West Virginia, WV | Psychic Reading Best B...$ Love Spells^ 💎 (310) 882-6330 in West Virginia, WV | Psychic Reading Best B...
$ Love Spells^ 💎 (310) 882-6330 in West Virginia, WV | Psychic Reading Best B...PsychicRuben LoveSpells
 
Top Rated Pune Call Girls Tingre Nagar ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Tingre Nagar ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Tingre Nagar ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Tingre Nagar ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Pokemon Go... Unraveling the Conspiracy Theory
Pokemon Go... Unraveling the Conspiracy TheoryPokemon Go... Unraveling the Conspiracy Theory
Pokemon Go... Unraveling the Conspiracy Theorydrae5
 
The Selfspace Journal Preview by Mindbrush
The Selfspace Journal Preview by MindbrushThe Selfspace Journal Preview by Mindbrush
The Selfspace Journal Preview by MindbrushShivain97
 
2k Shots ≽ 9205541914 ≼ Call Girls In Dashrath Puri (Delhi)
2k Shots ≽ 9205541914 ≼ Call Girls In Dashrath Puri (Delhi)2k Shots ≽ 9205541914 ≼ Call Girls In Dashrath Puri (Delhi)
2k Shots ≽ 9205541914 ≼ Call Girls In Dashrath Puri (Delhi)Delhi Call girls
 
LC_YouSaidYes_NewBelieverBookletDone.pdf
LC_YouSaidYes_NewBelieverBookletDone.pdfLC_YouSaidYes_NewBelieverBookletDone.pdf
LC_YouSaidYes_NewBelieverBookletDone.pdfpastor83
 
9892124323, Call Girls in mumbai, Vashi Call Girls , Kurla Call girls
9892124323, Call Girls in mumbai, Vashi Call Girls , Kurla Call girls9892124323, Call Girls in mumbai, Vashi Call Girls , Kurla Call girls
9892124323, Call Girls in mumbai, Vashi Call Girls , Kurla Call girlsPooja Nehwal
 
2k Shots ≽ 9205541914 ≼ Call Girls In Mukherjee Nagar (Delhi)
2k Shots ≽ 9205541914 ≼ Call Girls In Mukherjee Nagar (Delhi)2k Shots ≽ 9205541914 ≼ Call Girls In Mukherjee Nagar (Delhi)
2k Shots ≽ 9205541914 ≼ Call Girls In Mukherjee Nagar (Delhi)Delhi Call girls
 
CALL ON ➥8923113531 🔝Call Girls Mahanagar Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Mahanagar Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Mahanagar Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Mahanagar Lucknow best sexual serviceanilsa9823
 
CALL ON ➥8923113531 🔝Call Girls Jankipuram Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Jankipuram Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Jankipuram Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Jankipuram Lucknow best sexual serviceanilsa9823
 
Introducing to billionaire brain wave.pdf
Introducing to billionaire brain wave.pdfIntroducing to billionaire brain wave.pdf
Introducing to billionaire brain wave.pdfnoumannajam04
 
Lilac Illustrated Social Psychology Presentation.pptx
Lilac Illustrated Social Psychology Presentation.pptxLilac Illustrated Social Psychology Presentation.pptx
Lilac Illustrated Social Psychology Presentation.pptxABMWeaklings
 
CALL ON ➥8923113531 🔝Call Girls Rajajipuram Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Rajajipuram Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Rajajipuram Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Rajajipuram Lucknow best sexual serviceanilsa9823
 
8377087607 Full Enjoy @24/7-CLEAN-Call Girls In Chhatarpur,
8377087607 Full Enjoy @24/7-CLEAN-Call Girls In Chhatarpur,8377087607 Full Enjoy @24/7-CLEAN-Call Girls In Chhatarpur,
8377087607 Full Enjoy @24/7-CLEAN-Call Girls In Chhatarpur,dollysharma2066
 
CALL ON ➥8923113531 🔝Call Girls Adil Nagar Lucknow best Female service
CALL ON ➥8923113531 🔝Call Girls Adil Nagar Lucknow best Female serviceCALL ON ➥8923113531 🔝Call Girls Adil Nagar Lucknow best Female service
CALL ON ➥8923113531 🔝Call Girls Adil Nagar Lucknow best Female serviceanilsa9823
 
Lucknow 💋 High Class Call Girls Lucknow 10k @ I'm VIP Independent Escorts Gir...
Lucknow 💋 High Class Call Girls Lucknow 10k @ I'm VIP Independent Escorts Gir...Lucknow 💋 High Class Call Girls Lucknow 10k @ I'm VIP Independent Escorts Gir...
Lucknow 💋 High Class Call Girls Lucknow 10k @ I'm VIP Independent Escorts Gir...anilsa9823
 
CALL ON ➥8923113531 🔝Call Girls Aliganj Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Aliganj Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Aliganj Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Aliganj Lucknow best sexual serviceanilsa9823
 

Último (20)

2k Shots ≽ 9205541914 ≼ Call Girls In Palam (Delhi)
2k Shots ≽ 9205541914 ≼ Call Girls In Palam (Delhi)2k Shots ≽ 9205541914 ≼ Call Girls In Palam (Delhi)
2k Shots ≽ 9205541914 ≼ Call Girls In Palam (Delhi)
 
$ Love Spells^ 💎 (310) 882-6330 in West Virginia, WV | Psychic Reading Best B...
$ Love Spells^ 💎 (310) 882-6330 in West Virginia, WV | Psychic Reading Best B...$ Love Spells^ 💎 (310) 882-6330 in West Virginia, WV | Psychic Reading Best B...
$ Love Spells^ 💎 (310) 882-6330 in West Virginia, WV | Psychic Reading Best B...
 
Top Rated Pune Call Girls Tingre Nagar ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Tingre Nagar ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Tingre Nagar ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Tingre Nagar ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Pokemon Go... Unraveling the Conspiracy Theory
Pokemon Go... Unraveling the Conspiracy TheoryPokemon Go... Unraveling the Conspiracy Theory
Pokemon Go... Unraveling the Conspiracy Theory
 
The Selfspace Journal Preview by Mindbrush
The Selfspace Journal Preview by MindbrushThe Selfspace Journal Preview by Mindbrush
The Selfspace Journal Preview by Mindbrush
 
2k Shots ≽ 9205541914 ≼ Call Girls In Dashrath Puri (Delhi)
2k Shots ≽ 9205541914 ≼ Call Girls In Dashrath Puri (Delhi)2k Shots ≽ 9205541914 ≼ Call Girls In Dashrath Puri (Delhi)
2k Shots ≽ 9205541914 ≼ Call Girls In Dashrath Puri (Delhi)
 
(Aarini) Russian Call Girls Surat Call Now 8250077686 Surat Escorts 24x7
(Aarini) Russian Call Girls Surat Call Now 8250077686 Surat Escorts 24x7(Aarini) Russian Call Girls Surat Call Now 8250077686 Surat Escorts 24x7
(Aarini) Russian Call Girls Surat Call Now 8250077686 Surat Escorts 24x7
 
(Anamika) VIP Call Girls Navi Mumbai Call Now 8250077686 Navi Mumbai Escorts ...
(Anamika) VIP Call Girls Navi Mumbai Call Now 8250077686 Navi Mumbai Escorts ...(Anamika) VIP Call Girls Navi Mumbai Call Now 8250077686 Navi Mumbai Escorts ...
(Anamika) VIP Call Girls Navi Mumbai Call Now 8250077686 Navi Mumbai Escorts ...
 
LC_YouSaidYes_NewBelieverBookletDone.pdf
LC_YouSaidYes_NewBelieverBookletDone.pdfLC_YouSaidYes_NewBelieverBookletDone.pdf
LC_YouSaidYes_NewBelieverBookletDone.pdf
 
9892124323, Call Girls in mumbai, Vashi Call Girls , Kurla Call girls
9892124323, Call Girls in mumbai, Vashi Call Girls , Kurla Call girls9892124323, Call Girls in mumbai, Vashi Call Girls , Kurla Call girls
9892124323, Call Girls in mumbai, Vashi Call Girls , Kurla Call girls
 
2k Shots ≽ 9205541914 ≼ Call Girls In Mukherjee Nagar (Delhi)
2k Shots ≽ 9205541914 ≼ Call Girls In Mukherjee Nagar (Delhi)2k Shots ≽ 9205541914 ≼ Call Girls In Mukherjee Nagar (Delhi)
2k Shots ≽ 9205541914 ≼ Call Girls In Mukherjee Nagar (Delhi)
 
CALL ON ➥8923113531 🔝Call Girls Mahanagar Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Mahanagar Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Mahanagar Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Mahanagar Lucknow best sexual service
 
CALL ON ➥8923113531 🔝Call Girls Jankipuram Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Jankipuram Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Jankipuram Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Jankipuram Lucknow best sexual service
 
Introducing to billionaire brain wave.pdf
Introducing to billionaire brain wave.pdfIntroducing to billionaire brain wave.pdf
Introducing to billionaire brain wave.pdf
 
Lilac Illustrated Social Psychology Presentation.pptx
Lilac Illustrated Social Psychology Presentation.pptxLilac Illustrated Social Psychology Presentation.pptx
Lilac Illustrated Social Psychology Presentation.pptx
 
CALL ON ➥8923113531 🔝Call Girls Rajajipuram Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Rajajipuram Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Rajajipuram Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Rajajipuram Lucknow best sexual service
 
8377087607 Full Enjoy @24/7-CLEAN-Call Girls In Chhatarpur,
8377087607 Full Enjoy @24/7-CLEAN-Call Girls In Chhatarpur,8377087607 Full Enjoy @24/7-CLEAN-Call Girls In Chhatarpur,
8377087607 Full Enjoy @24/7-CLEAN-Call Girls In Chhatarpur,
 
CALL ON ➥8923113531 🔝Call Girls Adil Nagar Lucknow best Female service
CALL ON ➥8923113531 🔝Call Girls Adil Nagar Lucknow best Female serviceCALL ON ➥8923113531 🔝Call Girls Adil Nagar Lucknow best Female service
CALL ON ➥8923113531 🔝Call Girls Adil Nagar Lucknow best Female service
 
Lucknow 💋 High Class Call Girls Lucknow 10k @ I'm VIP Independent Escorts Gir...
Lucknow 💋 High Class Call Girls Lucknow 10k @ I'm VIP Independent Escorts Gir...Lucknow 💋 High Class Call Girls Lucknow 10k @ I'm VIP Independent Escorts Gir...
Lucknow 💋 High Class Call Girls Lucknow 10k @ I'm VIP Independent Escorts Gir...
 
CALL ON ➥8923113531 🔝Call Girls Aliganj Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Aliganj Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Aliganj Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Aliganj Lucknow best sexual service
 

Day 2 Revision

  • 1. Planning & Iron Triangle
  • 3. 3Project Management Plan The Project Management Plan (PMP) is a formal, approved document used to manage project execution. The PMP documents the actions necessary to define, prepare, integrate and coordinate the various planning activities. The PMP defines how the project is executed, monitored and controlled, and closed. It is progressively elaborated by updates throughout the course of the project. The PMP is also a communication vehicle for ensuring key stakeholders share an understanding of the project. The PMP is NOT a project schedule. A project schedule lists planned dates for performing tasks and activities to meet milestones identified in the project plan.
  • 6. 6Develop Schedule To develop your project schedule, you'll need to do three things first... • Define Activity • Sequence Activity • Estimate Activity Durations 1. Define Activity The first step to developing your schedule is to define the specific activities that need to be performed in order to complete the project. 2. Sequence Activity Once your activity list is ready, the next step is to determine the order each of the activities needs to be completed in. 3. Estimate Activity Durations The third step is to estimate how long each activity will take to complete. This needs to take into account the type, amount, and availability of people, material, equipment and supplies that are needed to perform each activity.
  • 8. 8Critical Path Method Critical path schedules... • Help you identify the activities that must be completed on time in order to complete the whole project on time. • Show you which activitys can be delayed and for how long without impacting the overall project schedule. • Calculate the minimum amount of time it will take to complete the project. • Tell you the earliest and latest dates each activity can start on in order to maintain the schedule. The CPM has four key elements... • Critical Path Analysis • Float Determination • Early Start & Early Finish Calculation • Late Start & Late Finish Calculation
  • 10. 10Activity Dependency Critical path schedules... • Help you identify the activities that must be completed on time in order to complete the whole project on time. • Show you which activities can be delayed and for how long without impacting the overall project schedule. • Calculate the minimum amount of time it will take to complete the project. • Tell you the earliest and latest dates each activity can start on in order to maintain the schedule. The CPM has four key elements... • Critical Path Analysis • Float Determination • Early Start & Early Finish Calculation • Late Start & Late Finish Calculation
  • 13. 13Early Start & Early Finish Calculation The Critical Path Method includes a technique called the Forward Pass which is used to determine the earliest date an activity can start and the earliest date it can finish. These dates are valid as long as all prior activities in that path started on their earliest start date and didn't slip. Starting with the critical path, the Early Start (ES) of the first activity is one. The Early Finish (EF) of an activity is its ES plus its duration minus one. Using our earlier example, Activity 2 is the first activity on the critical path: ES = 1, EF = 1 + 5 -1 = 5. You then move to the next activity in the path, in this case Activity 3. Its ES is the previous activity's EF + 1. Activity 3 ES = 5 + 1 = 6. Its EF is calculated the same as before: EF = 6 + 7 - 1 = 12. If an activity has more than one predecessor, to calculate its ES you will use the activity with the latest EF.
  • 14. 14Late Start & Late Finish Calculation The Backward Pass is a Critical Path Method techique you can use to determine the latest date an activity can start and the latest date it can finish before it delays the project. You'll start once again with the critical path, but this time you'l begin from the last activity in the path. The Late Finish (LF) for the last activity in every path is the same as the last activity's EF in the critical path. The Late Start (LS) is the LF - duration + 1. In our example, Activity 4 is the last activity on the critical path. Its LF is the same as its EF, which is 14. To calculate the LS, subtract its duration from its LF and add one. LS = 14 - 2 + 1 = 13. You then move on to the next activity in the path. Its LF is determined by subtracting one from the previous activity's LS. In our example, the next Activity in the critical path is Activity 3. Its LF is equal to Activity 4 LS - 1. Activity 3 LF = 13 -1 = 12. It's LS is calculated the same as before by subtracting its duration from the LF and adding one. Activity 3 LS = 12 - 7 + 1 = 6. You will continue in this manner moving along each path filling in LF and LS for activities that don't have it already filled in.
  • 16. 16Earn Value Metrics Earned Value measures performance against a plan at a given point in time. Term Full Name Meaning PV Planned Value Estimated value of the work planned to be done EV Earned Value Estimated value of the work actually accomplished AC Actual Costs Actual Costs Incurred BAC Budget At Completion Amount budgeted for total project EAC Estimate At Completion Currently expected total for project ETC Estimate To Complete How much More to finish VAC Variance At Completion How much over/under we expect to be
  • 17. 17Formula Earned Value Formula Name Formula Meaning Cost Variance CV=EV-AC -ve=over budget, +ve=under budget Schedule Variance SV=EV-PV -ve=behind schedule, +ve=ahead schedule AC Actual Costs Actual Costs Incurred Cost Performance Index (CPI) CPI=EV/AC We are getting _ cents out of every $ spent Schedule Performance Index SPI=EV/PV We are progressing at _% of the rate originally planned Estimate At Completion EAC=BAC/CPI As of now, how much do we expect the total project to cost Estimate To Complete ETC=EAC-AC How much more to finish Variance At Completion BAC-EAC How much over/under we expect to be
  • 18. 18Example Let’s imagine our project is to build a wall around a garden. Assuming 4 equal sides, a budget of $200 per side and a schedule of 1 side per day. We should be finished in 4 days for a total of $800. If, after Day 3, our progress is as follows:
  • 19. 19Calculation Name Formula Day 3 Value PV - Planned Value Estimated value of the work planned to be done Should have done 3 x $200 = $600 or Percentage Complete 75% SV=EV-PV Estimated value of the work actually accomplished Actually done 2.5 sides $200+$200+$100 = $500 or Actual Percentage Complete 62.5% AC - Actual Costs Actual Costs Incurred $200+$220+$140=$560 Cost Performance Index Over / Under Budget factor CPI = EV / AC $500 / $560 = 0.89 Schedule Performance Index Ahead / Behind Schedule factor SPI = EV / PV $500 / $600 = 0.83 0r 62.5%/75%% = 0.83 BAC - Budget At Completion Amount budgeted for total project $800 EAC - Estimate At Completion ETC=EAC-AC Currently expected total for project EAC=BAC / CPI ETC - Estimate To Complete How much more to finish? ETC = EAC - AC $899 - $560 = $339 VAC - Variance At Completion How much over/under we expect to be VAC = BAC – EAC $800 - $899 = -$99