1. OIL & GAS INDUSTRY HAS PLAYED A CRUCIAL ROLE IN THE
INDONESIA ECONOMIC DEVELOPMENT.
2. BY THE END OF 2012, THE INDUSTRY IS ACCOUNTED 1/4 OF
COUNTRIES GDP, (GREW 3-6 % ANNUAL RATE) 30 % OF
GOVERNMENT REVENUES (US$ 30-35 BILLION), AND ½ OF
MERCHANDIZED EXPORTS
3. INDONESIA IS RANKED HIGH IN THE SOUTH EAST ASIA REGION
FOR OIL AND GAS INVESTMENT AND 9TH MAJOR DESTINATION
FOR FOREIGN DIRECT INVESTMENT BECAUSE :
PROMISING PROSPECT (OIL : 7,408 MMSTB & GAS : 151 TCF)
INCREASING NEW PETROLEUM BLOCK (350 BLOCKS IN
OPERATION)
PROVIDING LARGE BENEFIT THROUGH PRODUCTION SHARING
CONTRACT SYSTEM
PROMOTING FAVORABLE INVESTMENT INCENTIVES
PRO MOTING EQUAL OPPORTUNITY FOR ANY PETROLEUM
INVESTMENT
INVESTMENT PROSPECTIVITY
3
4692
1576
596
402
49
66
7
20
OIL & CONDENSATE (IN THOUSAND
MSTB)
P1 P2 P3 TOTAL
3.741 1.939 1.728 7.408
*) P1+P2+P3 Status as of 1 Januari 2012
Opportunities
Indonesia’s Oil and Condensate Reserves *)
INDONESIA OIL & CONDENSATE RESERVES
4
2.57
9.28
2.98
50.27
24.14
NATUNA
7.08
NORTH SUMATRA
15.21
16.03
CENTRAL SUMATRA
ACEH (NAD)
SOUTH SUMATRA
WEST JAVA
5.26
EAST JAVA
EAST BORNEO
CELEBES
MOLUCCAS
PAPUA
(Advance Resources Interational, Inc., 2003 processed)
PROVEN = 103.35 TSCF
POTENTIAL = 47.35 TSCF
TOTAL = 150.70 TSCF
CBM RESOURCES = 453.30 TCFGAS RESERVES
(As of January 1st 2012)
Total CBM Basin = 11
(Advance Resources International, Inc., 2003)
Contract Signed up to 2012 : 54
CBM PSCs
SHALE GAS POTENTIAL
1.23
16.65
The Government is
currently doing prelimi nary
study & collecting data
about Shale Gas potential in
Indonesia
INDONESIA GAS RESOURCES & RESERVES
With the sharply increase of fuel demand and energy security the GOI needs to find
more proven resources & maintain stable existing oil & gas production. THEREFORE,
THE GOI IS INVITE NEW INVESTOR TO DEVELOP ABUNDANT PETROLEUM
INVESTMENT PERFORMANCE
First Break, Vol.25, Oct.,2007
Low
cost
FINDING & DEVELOPMENT COSTS PER BOE
INDONESIA HAS LOW PRODUCTION COST
3.00
3.50
4.00
4.50
5.00
5.50
6.00
6.50
7.00
2002 2003 2004 2005 2006 2007
US$perBOE
Production Cost
USA
Worldwide
Indonesia
Source: Performance Profiles of Major Energy Producers 2006, Energy Information Agency (EIA)
INDONESIA HAS LOW PRODUCTION COST
NET INCOME PER BOE
$0.00
$3.00
$6.00
$9.00
$12.00
$15.00
$18.00
2002 2003 2004 2005 2006
1. Worldwide 2. United States 3. Canada 4. Europe
5. Africa & Middle East 6. Asia-Pacific 7. South & Central America 8. Russia & Caspian
$/boe
2
4
6
8
First Break, Vol.25, Oct.,2007
.
PRODUCTION SHARING CONTRACT SYSTEM. OIL
PROJECT : 85% (GOI) & 15 (PSC) AND GAS : 70 %
GOVERNMENT OF INDONESIA
SIDE
• Fulfilling energy demand
• Finding more resources
and transfer it proven
reserves
• Maintaining production
output
• Optimizing Cost of
Petroleum Operations
• National/ Local
Capability and Capacity
enhancement
• Maintaining Macroecono
mic growth
• Securing of Energy
Supply
• Optimized GOI Take
INVESTORS SIDE
• Rights to Monetize
• Stability of Contract/
Contract sanctity
• Enforceable
International
Arbitration
• Competitive PSC
fiscal regime
• Legal Certainty
• Accessing to Blocks
• Optimizing Portfolio
MUTUAL BENEFIT ON THE BUSINESS
CONTRACTOR has technical competence and professional skills
necessary to carry out the Petroleum Operations .
CONTRACTOR shall be responsible to SKKMIGAS for the
execution of such operations in accordance with the provisions
of the PSC
CONTRACTOR shall carry the risk of Operating Costs required
in carrying out operations and shall therefore have an economic
interest in the development of the Petroleum deposits in the
Contract Area.
SKKMIGAS shall have and be responsible for the management
of the operations contemplated hereunder.
CONTRACTOR will recover all Operating Costs out of the sales
proceeds or disposition of the required quantity of Crude Oil
equal in value to such Operating Costs. Operating Costs means
expenditures made and obligations incurred in carrying out
SEGERA!
DIRECTORATE OF OIL AND GAS
10 % OF
INDONESIA
PARTICIPATION
JOINT
STUDY
TENDER
FOR
NEW BLOCK
APPROVAL
OF
PLAN OF
DEVELOPMENT
MONITORING
FIRM
COMMITMENT
SIGNING
OF
PSC CONTRACT
PROJECT
DEVELOPMENT
PRODUCTION
OIL
85 : 15
GAS
70 : 30
PLAN OF
DEVELOPMENT
PROCESS
COST RECOVERY : SUNK
COST, CAPITAL AND OPERATION COST
BY PSC
SKKMIGAS
MINISTRY OF EMR
EXPLOITATION
BASIC : AFE AND WP&B
ANDALUSIA BUMI ENERGI
Western part
• 20 prospects and 40 leads in Mesozoic; 3 leads in Palezoic.
• Average Geological Chance Factors 23% (Moderately Risk)
• Total Risked Resources 0.39 BBO + 5.7 TCF.
Eastern part
DEEP WATER (>200M) IN THE EASTERN PART
14PRIVATE AND CONFIDENTIAL
182
9 2 3
91
36
108
93
55 59
88
0
50
100
150
200
MBOEPD
2013 2014 2015 2016 2017 2018 2019
Sumpal
Ruby
Peciko
7C
Peciko
7B
SisiNubi
2B
Madura BD
ANDE-
ANDE
LUMUT
Banyu Urip
Kepodang
Bukit Tua
JANGKRI
K
Senoro
IDD -
Bangka
IDD –
Gehem
Hub
Masel
a
Tanggu
h
Train 3
Ga
s
oIL
IDD –
Gendalo
Hub
MDA-
MBH
Major future oil &gas projects will be dominated by gas prospect in offshore
areas
ANDALUSIA INTEREST
HEAVY OIL
PROJECT
ANDE-ANDE LUMUT SITE
CONTRACT DURATION
12 DECE 2004- 11 DEC 2034
(30 YEARS). PROVED
RESERVE 43 MMBO
• POD has been approved on November
30, 2011
• The Oil with approximately 25.000 to
(potential figures) 40.000 BOPD to be
produced from wellhead platform which is
to be bridge linked to FPSO for further
storage & offloading
• 6 initial development well will be drilled
using a jack up rig
• First Production stream is expected on Q-3
2015 (delay from planned 2014 )APPROVED EXPENDITURE 2013 IS US$ 29 MILLION
SALDO UNRECOVERED COST US$ 89 MILLION
TOTAL PROJECT INVESTMENT : 1,521 BILLION
Low Cost & Low Impact
Supply ATK, Toileteries,
Cattering, Cleaning Service, Antar jemput Pegawai
Penyewaan Kendaran, Rumah Dinas, Gudang
Perbaikan Jalan, Penimbunan Tanah
Supply Tenaga Kerja (Security,
 Bila diperlukan kerjasama dengan BPD untuk pendanaan
Low Cost High Impact
AMDAL, UKL/ UPL
Jasa Inspeksi NDT
 Kerjasama dengan Universitas, Perusahaan untuk
Knowledge & Skill Development
 Kerjasana dengan BPD untuk pendanaan
OVERALL SCHEME OF THE PROJECT
S
T
O
R
A
G
E
A
N
D
O
F
F
L
O
A
D
I
N
G
F
P
S
O
C
E
N
T
R
A
L
P
R
O
C
E
S
S
I
N
OVERALL PROJECT SCHEME
19PRIVATE AND CONFIDENTIAL
N
O
CRITERIA DESCRIPTION
1 FIELD ANDE ANDE LUMUT
2 PSC AWE (AUSTRALIAN)
3 BLOCK AREAS NORTHWEST NATUNA
4 POD APPROAVL 30/11/2011
5 ONSTREAM
TARGET(POD)
2014-2015
6 ONSTREAM (FORECAST) Q1 - 2015
REALIZATION OF EXPENDITURE VS POD VALUE
SUNK
COST
(MM
US$)
INVEST
MENT
(MM US$)
OPEX+AS
R
(MM
US$)
TOTAL
NILAI POD
(MM US$)
EXPENDITUR
RREALIZATIO
N
(MM US$)
PERSENTASE REALISASI EXP.
TERHADAP TOTAL NILAI POD
49.50 599.80 871.90
1,521.2
0
89 5.85 %
MAIN ISSUES
o PRODUCTION TARGET IS DELAYED
FROM 2014 TO Q-3 2015 DUE FARM
OUT PROCESS FROM GENTING OIL TO
AWE.
o PROCUREMENT ISSUES SHOULD BE
DEVELOPED BY FEED COMBINED
APPROACH.
o FPSO LEASED MUST BE INDONESIAN
FLAG BASED ON LAW NO 17/2008
REGARDING SHIPPING
o 10 % FARM OUT SHOULD BE
TRANSFRRED TO LOCAL
ENTERPRENEURSHIP AUTHORITIES
SCOPE OF ACTIVITY
PLAN OF DEVELOPMENT REALIZATION
Drilling : 43 wells
Production Facilities
o 1 Wellhead Platform construction
o FPSO aframax types
BASIC OF DEESIGN HAS BEEN
COMPLETED. FEED WELL HEAD
PLATFOM AND COMBINED FEED +
LEASED FPSO IS BEING TENDERED.
TARGET OF PRODUCTION BASED ON
POD)
NO PARAMETER DESCRIPTION
1 CUMULATIVE
PRODUCTION
Oil : 43.5 MMbbl
2 INITIAL
PRODEUCTION
RATE
Oil : 5 Mbopd
3 PEAK OF
PRODUCTION
Oil : 25 Mbopd
4 PRODUCTION
DURATION
10 YEARS
CURRENT PROJECT STATUS
20
• JV Eni 55% and GSZ 45%
 Discovery wells: Jangkrik-1 - Mar 2009
Jangkrik NE-1 - Jul 2011
 Location: Kutei Basin, 70 Km
offshore East Kalimantan
450 m W.D.
• Jangkrik field POD I approved in Nov
2011
• Jangkrik NE POD II submitted in Oct
18, 2012
• Production Plan : q2 2015– 300 mmscfd
Jangkrik NE
Bontang LNG
OVERVIEW JANGKRIK PROJECT
21PRIVATE AND CONFIDENTIAL
NO CRITERIA DESCRIPTION
1 FIELD JANGKRIK
2 PSC ENI MUARA BAKAU
3 BLOCK AREAS MUARA BAKAU
4 APOPROVAL POD 30/12/2011
5 ONSTREAM TARGET 2015
6 ONSTREAM (FORECAST) Q3 - 2015
REALISASI EXPENDITURE VS NILAI POD
SUNK
COST
(MM
US$)
INVESTME
NT
(MM US$)
OPEX+AS
R
(MM US$)
TOTAL POD
VALUE (MM
US$)
REALISATION
N
EXPENDITUR
E
(MM US$)
PERCENTAGE OF
REALIZATION TO POD
VALUE
235.10 2.14 0.78 238.02 513.16 215.60%
Main issues
Sharing facility (gas &
kondensat) with the east
kalimantan pipe line
system operating by Total
E&P Indonesie
SCOPE OF ACTIVITY
PLAN OF DEVELOPMENT REALIZATION
Drilling :
o Re-entry 3 eksisting wells
o 4 development well
Production Facilities :
o FPU development 300 MMscfd in
capacities
o Gas & Kondensat pipeline
o Onshore Receiving Facilities
o constructionBasic Engineering
100% completed
o PQ tender approved 25 Mei
2012
TARGET OF PRODUCTION (POD)
NO PARAMETER DESCRIPTION
1 CUMULATIVE
OF
PRODUCTION
Gas : 913 BSCF
Kond : 738 Mbbl
2 INITIASL
PRODUCTION
Gas : 288 Bscf
Kond : 488 bcpd
3 PEAK
PRODUCTION
Gas : 288 MMscfd
Kond : 488 bcpd
4 DURATION OF
PRODUCTION
14 YEARS
CURRENT PROJECT STATUS
• JANGKRIK TIE-IN SCOPE OF WORK
Tie-ins :
 Tie-in 1a gas line : 24” JKK to 42” PCK-BDK at km 7
 Tie-in 1b condensate line : 6” JKK to 12” HDL-PCK
Liquid line at km 7
 Tie-in 2 gas line : 20” new gas line to 20” HDL-NLM
at km 21.65
3 new lines :
 24” Onshore Jangkrik Gas Line : Landfall to km 7
 6” Onshore Jangkrik Condensate Line : Landfall to
km 7
 20” New Gas Line : Onshore receiving facility ORF
(200m from km7) to km 21.65
Jangkrik development under PSC Muara Bakau, consist of Jangkrik-
1 and Jangkrik North East
Location : Kutei Basin, 70 km offshore East Kalimantan, 450 m
WD
Capacity 450 MMscfd
Jangkrik field POD approved in November 2011
Basic Engineering completed in May 2012
Jangkrik NE POD II approval January 2013
FEED-EPCI 1 and 2 (FPU and Export Pipelines) bid plans
approved by BPMIGAS on July 2012. EPC 3 (SPS) bid plan
approved by BPMIGAS and under tender process
Project FID targeted by 4Q 2013
First Gas 2016 (subject to FPU Delivery) at the earliest
Tie in 1a/b
Tie-in 2
22
PIPELINE TIE IN PROGRAM
MINISTRY
OF FINANCE
STATE
REVENUE
OPPORTUNITY
JOINT STUDY
NEW BLOCK
FARM OUT/FARM IN
PSC ACQUISITION
UPST
REAM
THE PETROLEUM BUSINESS IN INDONESIA TODAY IS VERY DYNAMIC.
MANY BUSINESS OPPORTUNITIES ARE OPEN FOR INVESTMENT.
MINISTRY OF
ENERGY & MR
DIRECTORATE GENERAL
OIL AND GAS
DOWNSTREAM
-PIPELINE FEE
-- REFINERYSERVICES COMPANY
RELATED BUSINESS OPPORTUNITIES
SKKMIGAS AND PERTAMINA
COORDINATION
RELATED BUSINESS OPPORTUNITY
LIFTING TANKER
OVERALL PROJECT SCHEME
JOINT STUDY
INVESTOR TO DO THE STUDY AND DEVELOP IDENTIFIED HYDROCARBON
SITE WITHIN STUDY AREAS
NEW PETROLEUM BLOCK
INVESTOR PARTICIPATION THROUGH TENDER PROCESS (TWICE A YEAR)
FARM OUT/FARM IN
INVESTOR JOINT WITH LOCAL AUTHORITY TO GET 10 % INDONESIA
PARTICIPATION OR INVESTOR JOINT TO PSC FOR PARTICIPATION ANY
FARM OUT OFFERING
PSC ACQUISITION
INVESTOR TO BUY 100 % PSC SHARE (IT CAN BE INDIVIDU OR JOINT
VENTURE WITH OTHER INVESTOR)
VESSEL TANKER
INVESTOR JOINT WITH PERTAMINA TO BUILD NEW VESSEL TANKER OR
VIA PARTNERSHIP MODEL
SERVICE COMPANY
INVESTOR ESTABLISH SERVICE COMPANY IN INDONESIA FOR
EXPLORATION OR EXPLOITATION SCOPE

Mais conteúdo relacionado

Mais procurados

MARKET RESEARCH INTO THE NIGERIAN GAS
MARKET RESEARCH INTO THE NIGERIAN GASMARKET RESEARCH INTO THE NIGERIAN GAS
MARKET RESEARCH INTO THE NIGERIAN GAS
Muhammad A. Yar'Adua
 
Unx presentation nov 16 2010 (web)
Unx presentation nov 16 2010 (web)Unx presentation nov 16 2010 (web)
Unx presentation nov 16 2010 (web)
Kelsey Anderson
 
Issues-in-Implementing-the-Nigerian-Gas-Master-Plan (1)
Issues-in-Implementing-the-Nigerian-Gas-Master-Plan (1)Issues-in-Implementing-the-Nigerian-Gas-Master-Plan (1)
Issues-in-Implementing-the-Nigerian-Gas-Master-Plan (1)
Donald ofoegbu
 
New base energy news issue 877 dated 21 june 2016
New base energy news issue  877 dated 21  june 2016New base energy news issue  877 dated 21  june 2016
New base energy news issue 877 dated 21 june 2016
Khaled Al Awadi
 
Mitigating Disparity between Domestic Price and LNG price
Mitigating Disparity  between Domestic Price and LNG priceMitigating Disparity  between Domestic Price and LNG price
Mitigating Disparity between Domestic Price and LNG price
Andika Mahardika
 
Unx presentation nov 8 2010
Unx presentation nov 8 2010Unx presentation nov 8 2010
Unx presentation nov 8 2010
unxenergy
 
GAS UTILIZATION, CHALLENGES, PROSPECT AND THE WAY FORWARD
GAS UTILIZATION, CHALLENGES, PROSPECT AND THE WAY FORWARDGAS UTILIZATION, CHALLENGES, PROSPECT AND THE WAY FORWARD
GAS UTILIZATION, CHALLENGES, PROSPECT AND THE WAY FORWARD
ISRAEL ONYIJE
 

Mais procurados (20)

MARKET RESEARCH INTO THE NIGERIAN GAS
MARKET RESEARCH INTO THE NIGERIAN GASMARKET RESEARCH INTO THE NIGERIAN GAS
MARKET RESEARCH INTO THE NIGERIAN GAS
 
Unx presentation nov 16 2010 (web)
Unx presentation nov 16 2010 (web)Unx presentation nov 16 2010 (web)
Unx presentation nov 16 2010 (web)
 
New base 19 november 2021 energy news issue 1470 by khaled al awadi
New base  19 november  2021 energy news issue   1470  by khaled al awadiNew base  19 november  2021 energy news issue   1470  by khaled al awadi
New base 19 november 2021 energy news issue 1470 by khaled al awadi
 
Turkish E&P Sector & New Petroleum Law
Turkish E&P Sector & New Petroleum LawTurkish E&P Sector & New Petroleum Law
Turkish E&P Sector & New Petroleum Law
 
Salah wahbi's presentation slides from the 2010 World National Oil Companies ...
Salah wahbi's presentation slides from the 2010 World National Oil Companies ...Salah wahbi's presentation slides from the 2010 World National Oil Companies ...
Salah wahbi's presentation slides from the 2010 World National Oil Companies ...
 
Sami f al rushaid's presentation slides from the 2010 World National Oil Comp...
Sami f al rushaid's presentation slides from the 2010 World National Oil Comp...Sami f al rushaid's presentation slides from the 2010 World National Oil Comp...
Sami f al rushaid's presentation slides from the 2010 World National Oil Comp...
 
Dr seong hoon kim's presentation slides from the 2010 World National Oil Comp...
Dr seong hoon kim's presentation slides from the 2010 World National Oil Comp...Dr seong hoon kim's presentation slides from the 2010 World National Oil Comp...
Dr seong hoon kim's presentation slides from the 2010 World National Oil Comp...
 
Issues-in-Implementing-the-Nigerian-Gas-Master-Plan (1)
Issues-in-Implementing-the-Nigerian-Gas-Master-Plan (1)Issues-in-Implementing-the-Nigerian-Gas-Master-Plan (1)
Issues-in-Implementing-the-Nigerian-Gas-Master-Plan (1)
 
New base energy news issue 877 dated 21 june 2016
New base energy news issue  877 dated 21  june 2016New base energy news issue  877 dated 21  june 2016
New base energy news issue 877 dated 21 june 2016
 
New base energy news issue 923 dated 06 september 2016
New base energy news issue  923 dated 06 september 2016New base energy news issue  923 dated 06 september 2016
New base energy news issue 923 dated 06 september 2016
 
Mitigating Disparity between Domestic Price and LNG price
Mitigating Disparity  between Domestic Price and LNG priceMitigating Disparity  between Domestic Price and LNG price
Mitigating Disparity between Domestic Price and LNG price
 
Lyes boudiaf 4
Lyes boudiaf 4Lyes boudiaf 4
Lyes boudiaf 4
 
10 Things That May Affect the Future of Subsea Production
10 Things That May Affect the Future of Subsea Production10 Things That May Affect the Future of Subsea Production
10 Things That May Affect the Future of Subsea Production
 
Lng outlook and market webinar sept 2020
Lng outlook and market   webinar sept 2020Lng outlook and market   webinar sept 2020
Lng outlook and market webinar sept 2020
 
Unx presentation nov 8 2010
Unx presentation nov 8 2010Unx presentation nov 8 2010
Unx presentation nov 8 2010
 
SVCE Initiation of Coverage
SVCE Initiation of CoverageSVCE Initiation of Coverage
SVCE Initiation of Coverage
 
Microsoft word new base 997 special 07 february 2017 energy news
Microsoft word   new base 997 special 07 february 2017 energy newsMicrosoft word   new base 997 special 07 february 2017 energy news
Microsoft word new base 997 special 07 february 2017 energy news
 
New base 11 september 2017 energy news issue 1070 by khaled al awadi
New base 11 september 2017 energy news issue   1070  by khaled al awadiNew base 11 september 2017 energy news issue   1070  by khaled al awadi
New base 11 september 2017 energy news issue 1070 by khaled al awadi
 
GAS UTILIZATION, CHALLENGES, PROSPECT AND THE WAY FORWARD
GAS UTILIZATION, CHALLENGES, PROSPECT AND THE WAY FORWARDGAS UTILIZATION, CHALLENGES, PROSPECT AND THE WAY FORWARD
GAS UTILIZATION, CHALLENGES, PROSPECT AND THE WAY FORWARD
 
TWCOG
TWCOGTWCOG
TWCOG
 

Destaque

4. Exclusividade 2.0 - Diego Simon - VivaReal - Distrito Federal - Brasília
4. Exclusividade 2.0 - Diego Simon - VivaReal - Distrito Federal - Brasília4. Exclusividade 2.0 - Diego Simon - VivaReal - Distrito Federal - Brasília
4. Exclusividade 2.0 - Diego Simon - VivaReal - Distrito Federal - Brasília
Guru do Corretor
 
Guthrie Munion - Profile (2015)
Guthrie Munion - Profile (2015)Guthrie Munion - Profile (2015)
Guthrie Munion - Profile (2015)
Guthrie Munion
 
Apresentação futelazer 2013 5
Apresentação futelazer 2013 5Apresentação futelazer 2013 5
Apresentação futelazer 2013 5
Rose Paola
 
1 o que realmente importa
1   o que realmente importa1   o que realmente importa
1 o que realmente importa
Edmila Coelho
 
NPM.2011-12.AnnualReport
NPM.2011-12.AnnualReportNPM.2011-12.AnnualReport
NPM.2011-12.AnnualReport
Rishi Moudgil
 
Cloudera case study_experian
Cloudera case study_experianCloudera case study_experian
Cloudera case study_experian
John Murimi
 

Destaque (20)

Andro4dream powerpoint
Andro4dream powerpointAndro4dream powerpoint
Andro4dream powerpoint
 
4. Exclusividade 2.0 - Diego Simon - VivaReal - Distrito Federal - Brasília
4. Exclusividade 2.0 - Diego Simon - VivaReal - Distrito Federal - Brasília4. Exclusividade 2.0 - Diego Simon - VivaReal - Distrito Federal - Brasília
4. Exclusividade 2.0 - Diego Simon - VivaReal - Distrito Federal - Brasília
 
How To Write Compelling Subject Lines
How To Write Compelling Subject LinesHow To Write Compelling Subject Lines
How To Write Compelling Subject Lines
 
4.Mercado Imobiliário na Internet - Exclusividade 2 - Diego Simon - VivaReal ...
4.Mercado Imobiliário na Internet - Exclusividade 2 - Diego Simon - VivaReal ...4.Mercado Imobiliário na Internet - Exclusividade 2 - Diego Simon - VivaReal ...
4.Mercado Imobiliário na Internet - Exclusividade 2 - Diego Simon - VivaReal ...
 
Presentation1
Presentation1Presentation1
Presentation1
 
MRI Presentation
MRI PresentationMRI Presentation
MRI Presentation
 
Incentivo fiscal icms_apresentacao7
Incentivo fiscal icms_apresentacao7Incentivo fiscal icms_apresentacao7
Incentivo fiscal icms_apresentacao7
 
Guthrie Munion - Profile (2015)
Guthrie Munion - Profile (2015)Guthrie Munion - Profile (2015)
Guthrie Munion - Profile (2015)
 
Apresentação futelazer 2013 5
Apresentação futelazer 2013 5Apresentação futelazer 2013 5
Apresentação futelazer 2013 5
 
Smart income
Smart incomeSmart income
Smart income
 
1 o que realmente importa
1   o que realmente importa1   o que realmente importa
1 o que realmente importa
 
NPM.2011-12.AnnualReport
NPM.2011-12.AnnualReportNPM.2011-12.AnnualReport
NPM.2011-12.AnnualReport
 
uMobi: Concept presentation
uMobi: Concept presentationuMobi: Concept presentation
uMobi: Concept presentation
 
Question 6 Media Eval
Question 6 Media EvalQuestion 6 Media Eval
Question 6 Media Eval
 
Cloudera case study_experian
Cloudera case study_experianCloudera case study_experian
Cloudera case study_experian
 
3sixty email design by tammi st. angelo
3sixty email design by tammi st. angelo3sixty email design by tammi st. angelo
3sixty email design by tammi st. angelo
 
Paper Aeroplane Pitch
Paper Aeroplane PitchPaper Aeroplane Pitch
Paper Aeroplane Pitch
 
Muzik juara
Muzik juaraMuzik juara
Muzik juara
 
Design for Your Subscribers
Design for Your SubscribersDesign for Your Subscribers
Design for Your Subscribers
 
Re-engagement Strategies Author Todd Wilson
Re-engagement Strategies Author Todd Wilson  Re-engagement Strategies Author Todd Wilson
Re-engagement Strategies Author Todd Wilson
 

Semelhante a Andalusia Bumi Energi

OFASA_EVALUATION OF FLARED GAS UTILIZATION FOR ENHANCED OIL
OFASA_EVALUATION OF FLARED GAS UTILIZATION FOR ENHANCED OILOFASA_EVALUATION OF FLARED GAS UTILIZATION FOR ENHANCED OIL
OFASA_EVALUATION OF FLARED GAS UTILIZATION FOR ENHANCED OIL
Ofasa Abunumah
 
Ministry of Petroleum Resources
Ministry of Petroleum Resources Ministry of Petroleum Resources
Ministry of Petroleum Resources
Nigeria Centenary
 
Post Recession Offshore - Oil & Gas Industry
Post Recession Offshore - Oil & Gas IndustryPost Recession Offshore - Oil & Gas Industry
Post Recession Offshore - Oil & Gas Industry
Aftab Hasan
 

Semelhante a Andalusia Bumi Energi (20)

Presentasi rudy radjab
Presentasi rudy radjabPresentasi rudy radjab
Presentasi rudy radjab
 
Gas Arabia Summit: Unconventional Gas Developments in the Gulf
Gas Arabia Summit: Unconventional Gas Developments in the GulfGas Arabia Summit: Unconventional Gas Developments in the Gulf
Gas Arabia Summit: Unconventional Gas Developments in the Gulf
 
Aussei black-gold-market-overview
Aussei black-gold-market-overviewAussei black-gold-market-overview
Aussei black-gold-market-overview
 
Aussei black-gold-market-overview
Aussei black-gold-market-overviewAussei black-gold-market-overview
Aussei black-gold-market-overview
 
OFASA_EVALUATION OF FLARED GAS UTILIZATION FOR ENHANCED OIL
OFASA_EVALUATION OF FLARED GAS UTILIZATION FOR ENHANCED OILOFASA_EVALUATION OF FLARED GAS UTILIZATION FOR ENHANCED OIL
OFASA_EVALUATION OF FLARED GAS UTILIZATION FOR ENHANCED OIL
 
Ministry of Petroleum Resources
Ministry of Petroleum ResourcesMinistry of Petroleum Resources
Ministry of Petroleum Resources
 
Ministry of Petroleum Resources
Ministry of Petroleum Resources Ministry of Petroleum Resources
Ministry of Petroleum Resources
 
#MP2013 Presentation of the Minister of Petroleum Resources
#MP2013 Presentation of the Minister of Petroleum Resources#MP2013 Presentation of the Minister of Petroleum Resources
#MP2013 Presentation of the Minister of Petroleum Resources
 
Cabot Oil & Gas Presentation - March 21, 2016
Cabot Oil & Gas Presentation - March 21, 2016Cabot Oil & Gas Presentation - March 21, 2016
Cabot Oil & Gas Presentation - March 21, 2016
 
Sunoco Logistics Analyst Day Presentation - Nov 2014 in Dallas, TX
Sunoco Logistics Analyst Day Presentation - Nov 2014 in Dallas, TXSunoco Logistics Analyst Day Presentation - Nov 2014 in Dallas, TX
Sunoco Logistics Analyst Day Presentation - Nov 2014 in Dallas, TX
 
Q2.pdf
Q2.pdfQ2.pdf
Q2.pdf
 
India's Energy Sector - How to increase Oil Supply
India's Energy Sector - How to increase Oil Supply India's Energy Sector - How to increase Oil Supply
India's Energy Sector - How to increase Oil Supply
 
30.10.2012 Sharyn Gol - A New Dawn, Batmunkh Batkhuu
30.10.2012 Sharyn Gol - A New Dawn, Batmunkh Batkhuu30.10.2012 Sharyn Gol - A New Dawn, Batmunkh Batkhuu
30.10.2012 Sharyn Gol - A New Dawn, Batmunkh Batkhuu
 
Cabot oil and gas jp morgan presentation - june 2016
Cabot oil and gas   jp morgan presentation - june 2016Cabot oil and gas   jp morgan presentation - june 2016
Cabot oil and gas jp morgan presentation - june 2016
 
Platts oilgram news sep 17 2014 pag 5 colombian pipelines attacks
Platts oilgram news sep 17 2014 pag 5 colombian pipelines attacksPlatts oilgram news sep 17 2014 pag 5 colombian pipelines attacks
Platts oilgram news sep 17 2014 pag 5 colombian pipelines attacks
 
Mol Group_Investor Presentations, Reports November 2014
Mol Group_Investor Presentations, Reports November 2014Mol Group_Investor Presentations, Reports November 2014
Mol Group_Investor Presentations, Reports November 2014
 
Oil and gas_2006
Oil and gas_2006Oil and gas_2006
Oil and gas_2006
 
2014 investor seminar asx
2014 investor seminar asx2014 investor seminar asx
2014 investor seminar asx
 
The revival and transformation of Europe’s largest onshore oilfield; the Pato...
The revival and transformation of Europe’s largest onshore oilfield; the Pato...The revival and transformation of Europe’s largest onshore oilfield; the Pato...
The revival and transformation of Europe’s largest onshore oilfield; the Pato...
 
Post Recession Offshore - Oil & Gas Industry
Post Recession Offshore - Oil & Gas IndustryPost Recession Offshore - Oil & Gas Industry
Post Recession Offshore - Oil & Gas Industry
 

Andalusia Bumi Energi

  • 1.
  • 2. 1. OIL & GAS INDUSTRY HAS PLAYED A CRUCIAL ROLE IN THE INDONESIA ECONOMIC DEVELOPMENT. 2. BY THE END OF 2012, THE INDUSTRY IS ACCOUNTED 1/4 OF COUNTRIES GDP, (GREW 3-6 % ANNUAL RATE) 30 % OF GOVERNMENT REVENUES (US$ 30-35 BILLION), AND ½ OF MERCHANDIZED EXPORTS 3. INDONESIA IS RANKED HIGH IN THE SOUTH EAST ASIA REGION FOR OIL AND GAS INVESTMENT AND 9TH MAJOR DESTINATION FOR FOREIGN DIRECT INVESTMENT BECAUSE : PROMISING PROSPECT (OIL : 7,408 MMSTB & GAS : 151 TCF) INCREASING NEW PETROLEUM BLOCK (350 BLOCKS IN OPERATION) PROVIDING LARGE BENEFIT THROUGH PRODUCTION SHARING CONTRACT SYSTEM PROMOTING FAVORABLE INVESTMENT INCENTIVES PRO MOTING EQUAL OPPORTUNITY FOR ANY PETROLEUM INVESTMENT INVESTMENT PROSPECTIVITY
  • 3. 3 4692 1576 596 402 49 66 7 20 OIL & CONDENSATE (IN THOUSAND MSTB) P1 P2 P3 TOTAL 3.741 1.939 1.728 7.408 *) P1+P2+P3 Status as of 1 Januari 2012 Opportunities Indonesia’s Oil and Condensate Reserves *) INDONESIA OIL & CONDENSATE RESERVES
  • 4. 4 2.57 9.28 2.98 50.27 24.14 NATUNA 7.08 NORTH SUMATRA 15.21 16.03 CENTRAL SUMATRA ACEH (NAD) SOUTH SUMATRA WEST JAVA 5.26 EAST JAVA EAST BORNEO CELEBES MOLUCCAS PAPUA (Advance Resources Interational, Inc., 2003 processed) PROVEN = 103.35 TSCF POTENTIAL = 47.35 TSCF TOTAL = 150.70 TSCF CBM RESOURCES = 453.30 TCFGAS RESERVES (As of January 1st 2012) Total CBM Basin = 11 (Advance Resources International, Inc., 2003) Contract Signed up to 2012 : 54 CBM PSCs SHALE GAS POTENTIAL 1.23 16.65 The Government is currently doing prelimi nary study & collecting data about Shale Gas potential in Indonesia INDONESIA GAS RESOURCES & RESERVES
  • 5. With the sharply increase of fuel demand and energy security the GOI needs to find more proven resources & maintain stable existing oil & gas production. THEREFORE, THE GOI IS INVITE NEW INVESTOR TO DEVELOP ABUNDANT PETROLEUM INVESTMENT PERFORMANCE
  • 6. First Break, Vol.25, Oct.,2007 Low cost FINDING & DEVELOPMENT COSTS PER BOE
  • 7. INDONESIA HAS LOW PRODUCTION COST 3.00 3.50 4.00 4.50 5.00 5.50 6.00 6.50 7.00 2002 2003 2004 2005 2006 2007 US$perBOE Production Cost USA Worldwide Indonesia Source: Performance Profiles of Major Energy Producers 2006, Energy Information Agency (EIA) INDONESIA HAS LOW PRODUCTION COST
  • 8. NET INCOME PER BOE $0.00 $3.00 $6.00 $9.00 $12.00 $15.00 $18.00 2002 2003 2004 2005 2006 1. Worldwide 2. United States 3. Canada 4. Europe 5. Africa & Middle East 6. Asia-Pacific 7. South & Central America 8. Russia & Caspian $/boe 2 4 6 8 First Break, Vol.25, Oct.,2007 .
  • 9. PRODUCTION SHARING CONTRACT SYSTEM. OIL PROJECT : 85% (GOI) & 15 (PSC) AND GAS : 70 % GOVERNMENT OF INDONESIA SIDE • Fulfilling energy demand • Finding more resources and transfer it proven reserves • Maintaining production output • Optimizing Cost of Petroleum Operations • National/ Local Capability and Capacity enhancement • Maintaining Macroecono mic growth • Securing of Energy Supply • Optimized GOI Take INVESTORS SIDE • Rights to Monetize • Stability of Contract/ Contract sanctity • Enforceable International Arbitration • Competitive PSC fiscal regime • Legal Certainty • Accessing to Blocks • Optimizing Portfolio MUTUAL BENEFIT ON THE BUSINESS
  • 10. CONTRACTOR has technical competence and professional skills necessary to carry out the Petroleum Operations . CONTRACTOR shall be responsible to SKKMIGAS for the execution of such operations in accordance with the provisions of the PSC CONTRACTOR shall carry the risk of Operating Costs required in carrying out operations and shall therefore have an economic interest in the development of the Petroleum deposits in the Contract Area. SKKMIGAS shall have and be responsible for the management of the operations contemplated hereunder. CONTRACTOR will recover all Operating Costs out of the sales proceeds or disposition of the required quantity of Crude Oil equal in value to such Operating Costs. Operating Costs means expenditures made and obligations incurred in carrying out
  • 11. SEGERA! DIRECTORATE OF OIL AND GAS 10 % OF INDONESIA PARTICIPATION JOINT STUDY TENDER FOR NEW BLOCK APPROVAL OF PLAN OF DEVELOPMENT MONITORING FIRM COMMITMENT SIGNING OF PSC CONTRACT PROJECT DEVELOPMENT PRODUCTION OIL 85 : 15 GAS 70 : 30 PLAN OF DEVELOPMENT PROCESS COST RECOVERY : SUNK COST, CAPITAL AND OPERATION COST BY PSC SKKMIGAS MINISTRY OF EMR EXPLOITATION BASIC : AFE AND WP&B ANDALUSIA BUMI ENERGI
  • 12.
  • 13. Western part • 20 prospects and 40 leads in Mesozoic; 3 leads in Palezoic. • Average Geological Chance Factors 23% (Moderately Risk) • Total Risked Resources 0.39 BBO + 5.7 TCF. Eastern part DEEP WATER (>200M) IN THE EASTERN PART
  • 14. 14PRIVATE AND CONFIDENTIAL 182 9 2 3 91 36 108 93 55 59 88 0 50 100 150 200 MBOEPD 2013 2014 2015 2016 2017 2018 2019 Sumpal Ruby Peciko 7C Peciko 7B SisiNubi 2B Madura BD ANDE- ANDE LUMUT Banyu Urip Kepodang Bukit Tua JANGKRI K Senoro IDD - Bangka IDD – Gehem Hub Masel a Tanggu h Train 3 Ga s oIL IDD – Gendalo Hub MDA- MBH Major future oil &gas projects will be dominated by gas prospect in offshore areas ANDALUSIA INTEREST
  • 15.
  • 16. HEAVY OIL PROJECT ANDE-ANDE LUMUT SITE CONTRACT DURATION 12 DECE 2004- 11 DEC 2034 (30 YEARS). PROVED RESERVE 43 MMBO
  • 17. • POD has been approved on November 30, 2011 • The Oil with approximately 25.000 to (potential figures) 40.000 BOPD to be produced from wellhead platform which is to be bridge linked to FPSO for further storage & offloading • 6 initial development well will be drilled using a jack up rig • First Production stream is expected on Q-3 2015 (delay from planned 2014 )APPROVED EXPENDITURE 2013 IS US$ 29 MILLION SALDO UNRECOVERED COST US$ 89 MILLION TOTAL PROJECT INVESTMENT : 1,521 BILLION
  • 18. Low Cost & Low Impact Supply ATK, Toileteries, Cattering, Cleaning Service, Antar jemput Pegawai Penyewaan Kendaran, Rumah Dinas, Gudang Perbaikan Jalan, Penimbunan Tanah Supply Tenaga Kerja (Security,  Bila diperlukan kerjasama dengan BPD untuk pendanaan Low Cost High Impact AMDAL, UKL/ UPL Jasa Inspeksi NDT  Kerjasama dengan Universitas, Perusahaan untuk Knowledge & Skill Development  Kerjasana dengan BPD untuk pendanaan OVERALL SCHEME OF THE PROJECT S T O R A G E A N D O F F L O A D I N G F P S O C E N T R A L P R O C E S S I N OVERALL PROJECT SCHEME
  • 19. 19PRIVATE AND CONFIDENTIAL N O CRITERIA DESCRIPTION 1 FIELD ANDE ANDE LUMUT 2 PSC AWE (AUSTRALIAN) 3 BLOCK AREAS NORTHWEST NATUNA 4 POD APPROAVL 30/11/2011 5 ONSTREAM TARGET(POD) 2014-2015 6 ONSTREAM (FORECAST) Q1 - 2015 REALIZATION OF EXPENDITURE VS POD VALUE SUNK COST (MM US$) INVEST MENT (MM US$) OPEX+AS R (MM US$) TOTAL NILAI POD (MM US$) EXPENDITUR RREALIZATIO N (MM US$) PERSENTASE REALISASI EXP. TERHADAP TOTAL NILAI POD 49.50 599.80 871.90 1,521.2 0 89 5.85 % MAIN ISSUES o PRODUCTION TARGET IS DELAYED FROM 2014 TO Q-3 2015 DUE FARM OUT PROCESS FROM GENTING OIL TO AWE. o PROCUREMENT ISSUES SHOULD BE DEVELOPED BY FEED COMBINED APPROACH. o FPSO LEASED MUST BE INDONESIAN FLAG BASED ON LAW NO 17/2008 REGARDING SHIPPING o 10 % FARM OUT SHOULD BE TRANSFRRED TO LOCAL ENTERPRENEURSHIP AUTHORITIES SCOPE OF ACTIVITY PLAN OF DEVELOPMENT REALIZATION Drilling : 43 wells Production Facilities o 1 Wellhead Platform construction o FPSO aframax types BASIC OF DEESIGN HAS BEEN COMPLETED. FEED WELL HEAD PLATFOM AND COMBINED FEED + LEASED FPSO IS BEING TENDERED. TARGET OF PRODUCTION BASED ON POD) NO PARAMETER DESCRIPTION 1 CUMULATIVE PRODUCTION Oil : 43.5 MMbbl 2 INITIAL PRODEUCTION RATE Oil : 5 Mbopd 3 PEAK OF PRODUCTION Oil : 25 Mbopd 4 PRODUCTION DURATION 10 YEARS CURRENT PROJECT STATUS
  • 20. 20 • JV Eni 55% and GSZ 45%  Discovery wells: Jangkrik-1 - Mar 2009 Jangkrik NE-1 - Jul 2011  Location: Kutei Basin, 70 Km offshore East Kalimantan 450 m W.D. • Jangkrik field POD I approved in Nov 2011 • Jangkrik NE POD II submitted in Oct 18, 2012 • Production Plan : q2 2015– 300 mmscfd Jangkrik NE Bontang LNG OVERVIEW JANGKRIK PROJECT
  • 21. 21PRIVATE AND CONFIDENTIAL NO CRITERIA DESCRIPTION 1 FIELD JANGKRIK 2 PSC ENI MUARA BAKAU 3 BLOCK AREAS MUARA BAKAU 4 APOPROVAL POD 30/12/2011 5 ONSTREAM TARGET 2015 6 ONSTREAM (FORECAST) Q3 - 2015 REALISASI EXPENDITURE VS NILAI POD SUNK COST (MM US$) INVESTME NT (MM US$) OPEX+AS R (MM US$) TOTAL POD VALUE (MM US$) REALISATION N EXPENDITUR E (MM US$) PERCENTAGE OF REALIZATION TO POD VALUE 235.10 2.14 0.78 238.02 513.16 215.60% Main issues Sharing facility (gas & kondensat) with the east kalimantan pipe line system operating by Total E&P Indonesie SCOPE OF ACTIVITY PLAN OF DEVELOPMENT REALIZATION Drilling : o Re-entry 3 eksisting wells o 4 development well Production Facilities : o FPU development 300 MMscfd in capacities o Gas & Kondensat pipeline o Onshore Receiving Facilities o constructionBasic Engineering 100% completed o PQ tender approved 25 Mei 2012 TARGET OF PRODUCTION (POD) NO PARAMETER DESCRIPTION 1 CUMULATIVE OF PRODUCTION Gas : 913 BSCF Kond : 738 Mbbl 2 INITIASL PRODUCTION Gas : 288 Bscf Kond : 488 bcpd 3 PEAK PRODUCTION Gas : 288 MMscfd Kond : 488 bcpd 4 DURATION OF PRODUCTION 14 YEARS CURRENT PROJECT STATUS
  • 22. • JANGKRIK TIE-IN SCOPE OF WORK Tie-ins :  Tie-in 1a gas line : 24” JKK to 42” PCK-BDK at km 7  Tie-in 1b condensate line : 6” JKK to 12” HDL-PCK Liquid line at km 7  Tie-in 2 gas line : 20” new gas line to 20” HDL-NLM at km 21.65 3 new lines :  24” Onshore Jangkrik Gas Line : Landfall to km 7  6” Onshore Jangkrik Condensate Line : Landfall to km 7  20” New Gas Line : Onshore receiving facility ORF (200m from km7) to km 21.65 Jangkrik development under PSC Muara Bakau, consist of Jangkrik- 1 and Jangkrik North East Location : Kutei Basin, 70 km offshore East Kalimantan, 450 m WD Capacity 450 MMscfd Jangkrik field POD approved in November 2011 Basic Engineering completed in May 2012 Jangkrik NE POD II approval January 2013 FEED-EPCI 1 and 2 (FPU and Export Pipelines) bid plans approved by BPMIGAS on July 2012. EPC 3 (SPS) bid plan approved by BPMIGAS and under tender process Project FID targeted by 4Q 2013 First Gas 2016 (subject to FPU Delivery) at the earliest Tie in 1a/b Tie-in 2 22 PIPELINE TIE IN PROGRAM
  • 23. MINISTRY OF FINANCE STATE REVENUE OPPORTUNITY JOINT STUDY NEW BLOCK FARM OUT/FARM IN PSC ACQUISITION UPST REAM THE PETROLEUM BUSINESS IN INDONESIA TODAY IS VERY DYNAMIC. MANY BUSINESS OPPORTUNITIES ARE OPEN FOR INVESTMENT. MINISTRY OF ENERGY & MR DIRECTORATE GENERAL OIL AND GAS DOWNSTREAM -PIPELINE FEE -- REFINERYSERVICES COMPANY RELATED BUSINESS OPPORTUNITIES SKKMIGAS AND PERTAMINA COORDINATION RELATED BUSINESS OPPORTUNITY LIFTING TANKER
  • 24. OVERALL PROJECT SCHEME JOINT STUDY INVESTOR TO DO THE STUDY AND DEVELOP IDENTIFIED HYDROCARBON SITE WITHIN STUDY AREAS NEW PETROLEUM BLOCK INVESTOR PARTICIPATION THROUGH TENDER PROCESS (TWICE A YEAR) FARM OUT/FARM IN INVESTOR JOINT WITH LOCAL AUTHORITY TO GET 10 % INDONESIA PARTICIPATION OR INVESTOR JOINT TO PSC FOR PARTICIPATION ANY FARM OUT OFFERING PSC ACQUISITION INVESTOR TO BUY 100 % PSC SHARE (IT CAN BE INDIVIDU OR JOINT VENTURE WITH OTHER INVESTOR) VESSEL TANKER INVESTOR JOINT WITH PERTAMINA TO BUILD NEW VESSEL TANKER OR VIA PARTNERSHIP MODEL SERVICE COMPANY INVESTOR ESTABLISH SERVICE COMPANY IN INDONESIA FOR EXPLORATION OR EXPLOITATION SCOPE