Design & Development of a
           Schedule Management Plan

                     Session #PRJ10


Chris Carson, PMP, PSP, CCM
Alpha Corporation

                              “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                              ©2010 Permission is granted to PMI for PMI® Marketplace use only
Chris Carson, PSP, CCM, PMP
•   Corporate Director of Project Controls, Alpha Corporation
     – Developed and manages the PMO (Project Management Office) for Alpha Corporation
     – Responsible for standards, processes, and procedures for a team of schedulers, analysts,
         and project managers in multiple office locations, as well as analysis, work product, and
         testimony
     – Developed and manages the in-house project controls training program at Alpha
•   Certifications:
     – PSP (Planning & Scheduling Professional – AACEi)
     – CCM (Certified Construction Manager - CMAA)
     – PMP (Project Management Professional – PMI)
•   University: University of Virginia, Mechanical Engineering, 1968 - 1972
•   Professional Field: 38 years of experience in Construction Management Services specializing in
            Scheduling, Schedule Analysis, Estimating, Claims
•   Active in PMI (Project Management Institute) Scheduling Community of Practice
     – Vice President of Scheduling Excellence for CoS
     – Managing Director for SEI (Scheduling Excellence Initiative) writing Best Practices and
         Guidelines for Scheduling and Schedule Impact Analysis
     – Serving on team writing Best Practices for Scheduling for GAO
•   Active in CMAA (Construction Management Association of America)
     – Served on committee revising Time Management Chapter of CMAA’s CM Standards of
         Practice
•   Active in AACEi (Association for the Advancement of Cost Estimating International)
     – Member of P&S and CDR Committees
     – Author of Recommended Practices in Scheduling & Editor of Forensic Schedule Analysis RP
•   Active in Planning Planet
     – Chief Editor for US, writing Planner Users’ Guide, developing accreditations through a Guild
         for planners and
•   Award
     – “Significant Contributions to Scheduling Profession”, 2008 CoS Annual Conference


                                                                                                2     2
            2
Schedule Management Plan
 The PMBOK® Guide describes the Project
 Management Plan
   “Process of documenting actions necessary to define,
   prepare, integrate, coordinate all subsidiary plans”
     Knowledge Area – Integration
     Process Group – Planning
   Inputs
     “Outputs from many planning processes are integrated to
     create the Project Management Plan (PMP)”
     “Any baselines & subsidiary management plans that are
     output from other planning processes are inputs here”




                                    “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                                    ©2010Permission is granted to PMI for PMI® Marketplace use only                          3
Schedule Management Plan
 The PMBOK® Guide
   Does not describe or define the Schedule Management Plan
   Except to note the existence of subsidiary plans such as the
   “Schedule Management Plan”

 Described in the introduction to Chapter 6 as a
   “schedule management plan that selects a scheduling
   methodology, a scheduling tool, and sets the format and
   establishes criteria for developing and controlling the project
   schedule.”




                                  “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                                  ©2010Permission is granted to PMI for PMI® Marketplace use only                          4
Schedule Management Plan
 Purpose of the schedule management plan?
   Schedule Development meets the criteria for a “project” in itself
   The SMP provides a methodical approach for the schedule
   development
   Keeps the schedule development on track
   Prevents rework due to late understanding of needs
   Allows buy-in from end users prior to development
   Makes the schedule development session much more meaningful
   Documents the assumptions and intention of the schedule
      For reviewer and approver
      For future reference
      To facilitate changes in schedulers
      Place to capture Lessons Learned




                                        “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                                        ©2010Permission is granted to PMI for PMI® Marketplace use only                          5
Schedule Management Plan
 Scope of SMP vs. Schedule Development Processes
   Schedule Management Plan– Conceptualizing the
   schedule effort (designing the schedule)
     Planning
     Starting with the end in mind
     Providing concept of final product
     Creating organizational structure to fulfill the concept

   Development - Building the schedule
     Define activities
     Sequence activities - input logic
     Estimate activity resources
     Estimate activity durations
     Develop schedule
     Monitor and Control schedule




                                   “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                                   ©2010Permission is granted to PMI for PMI® Marketplace use only                          6
Schedule Management Plan
 Documentation & use of Schedule Management Plan
   Create a book or binder
   Use the highest level of checklist outline items as tabs
   Use the book as basis for SMP submittal
   documentation
   Keep the book current during project
   Use the book for handoff between schedulers
   Share a copy of the book with superintendent/PM
 Timing of the SMP
   Must be done prior to Schedule Development



                               “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                               ©2010Permission is granted to PMI for PMI® Marketplace use only                          7
Components of Schedule Management Plan

1.    Project Description
     1. Reference Documents Needed for the SMP
        1.    Contract
        2.    Project Drawings
        3.    Specifications
        4.    Scheduling Specification
        5.    Notice to Proceed or Release Letter
        6.    Any Owner produced master schedule
        7.    Liquidated Damages schedule
        8.    Area Designation Plan
        9.    Sequencing plan
        10.   Estimate & quantity surveys/bills of materials




                                        “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                                        ©2010Permission is granted to PMI for PMI® Marketplace use only                          8
Components of Schedule Management Plan

2.    Team Players
     1. Organizational Chart
     2. Who are Schedule Users?
        1.   Who has Input
        2.   Who Updates
        3.   Who Checks for Accuracy
        4.   Who Reviews
        5.   Who approves
     3. Identify Responsibility Assignment Matrix (RAM)




                                  “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                                  ©2010Permission is granted to PMI for PMI® Marketplace use only                          9
Components of Schedule Management Plan

   • RAM Example (based on PMBOK® RACI Chart)
      – Correlates tasks with roles and individuals




                               “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                               ©2010Permission is granted to PMI for PMI® Marketplace use only                          10
Components of Schedule Management Plan

3.    Software Identification
     1. Specific software required
        1. Required minimum and versions allowed
     2. Enterprise specific issues
        1.   Users identified
        2.   Schedules used for import or data source
        3.   Levels of access
        4.   Validation process
        5.   For master schedules, establish data dates




                                    “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                                    ©2010Permission is granted to PMI for PMI® Marketplace use only                          11
Components of Schedule Management Plan
4.    Work Product
     1.   What the Schedule can be used for (purpose)
     2.   Reports Generated from the Schedule
          1.   Who receives reports
          2.   List of reports
          3.   Samples of reports
     3.   Glossary/Lexicon of ambiguous terms (or cultural terms –
          is it programme or schedule?)
5.    Schedule Outline
     1.   Key Activities being tracked
     2.   Client Milestones
     3.   Long Lead Items
     4.   WBS Structure & cost accounts
     5.   Other Contracts on Project




                                      “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                                      ©2010Permission is granted to PMI for PMI® Marketplace use only                          12
Components of Schedule Management Plan
      • Reporting




                     “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                     ©2010Permission is granted to PMI for PMI® Marketplace use only                          13
Components of Schedule Management Plan
6.    Work Packages or Tenders
     1.   By Contract
     2.   As assigned by Client

7.    Level of Detail
     1.   Determine approach:
          1.   Bottom-up (starting with detailed activities)
          2.   Top-down (starting with summary schedule)
          3.   Both (prepare Top-down, then Bottom-up)
     2. Identify frequency of updates
     3. Establish smallest activity duration range



                                          “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                                          ©2010Permission is granted to PMI for PMI® Marketplace use only                          14
Components of Schedule Management Plan
8.    Codes Dictionary
     1. For tracking and monitoring work:
        1.   Work Phase
        2.   Structure
        3.   Area
        4.   Floor or Station
        5.   Location
     2. For Project Management:
        1.   Responsibility
        2.   Work Shifts
        3.   Costs
        4.   Resource
        5.   Specification
        6.   Change management




                                 “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                                 ©2010Permission is granted to PMI for PMI® Marketplace use only                          15
Components of Schedule Management Plan
9.    Calendars
     1.   Establish number needed
     2.   Define calendars and application
10. Costs & Resources
     1.   Estimate & correlation to cost loading
     2.   Bill of Quantities & use in resources
     3.   Resource Crew descriptions
     4.   Equipment descriptions
     5.   How actual production will be monitored
     6.   Earned Value Management System
11. Narrative Basis & Assumptions
     1.   Procedure Used to create the Schedule/Programme
     2.   Definitions/lexicon
     3.   Description of sequence of work per structure



                                      “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                                      ©2010Permission is granted to PMI for PMI® Marketplace use only                          16
Components of Schedule Management Plan

    • Narrative Basis




                        “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                        ©2010Permission is granted to PMI for PMI® Marketplace use only                          17
Components of Schedule Management Plan

12. Risks & Constructability
   1. Brainstorming of issues
      1.   Known problems (threats)
      2.   Predicted problems
      3.   Lessons Learned
      4.   Outside influences
      5.   Site condition concerns
      6.   Opportunities
   2. Develop Risk Management Plan
      1. Initial process during baseline schedule development
      2. Process for use during updates




                                 “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                                 ©2010Permission is granted to PMI for PMI® Marketplace use only                          18
Components of Schedule Management Plan
   • Risk Management
     Plan
     – Based on PMBOK®




                         “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                         ©2010Permission is granted to PMI for PMI® Marketplace use only                          19
Components of Schedule Management Plan

13. Weather planning
  1. Expected adverse weather
  2. Identify source or specification requirement
  3. Identify methodology
  4. Identify accounting method for actual weather




                             “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                             ©2010Permission is granted to PMI for PMI® Marketplace use only                          20
Components of Schedule Management Plan
14.    Time Contingencies
      1.   Amounts
      2.   Specific trade (from risk management plan)
      3.   Specific contractor contingency
      4.   How carried
      5.   Use historical data for reference
                            Time Performance Ratio

                     12.0
                     10.0
                      8.0
               TPR




                      6.0
                      4.0
                      2.0
                      0.0




                                ev s
                                          ry




                                           s
                                          ry




                                          nt
                                         ws




                              El cal
                                           e




                            / W ing




                                            l
                            Eq hes
                                         rk




                               ar ls
                              Si in




                                        ca
                                         g

                                       or
                                        et



                                        a

                                       nt
                                     on




                           Fu me
                                       m

                                    wo




                                      in
                                   do




                                    ni

                                    t ri
                                    et



                                    of




                                    at
                                    cr




                                  pe
                                  Ad




                                    s



                                 ish
                                 as




                                ha

                                ec
                                 te




                        oo Ro
                                 M




                                 ni

                                  p
                                on




                                 in



                               ui
                              Fi
                              M




                              rn



                             ec
                             El
                              C




                             C




                           M
                          rs
                      D




                                     Type of Work




                                           “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                                           ©2010Permission is granted to PMI for PMI® Marketplace use only                          21
Components of Schedule Management Plan

15. Establish Update process
   1.   Frequency
   2.   Data request and transmission
   3.   Validation
   4.   Process flowchart




                               “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                               ©2010Permission is granted to PMI for PMI® Marketplace use only                          22
Components of Schedule Management Plan

16. Change Management process
  1. Notification requirements
  2. Methodology allowed
  3. Process flowchart




                            “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                            ©2010Permission is granted to PMI for PMI® Marketplace use only                          23
Collect Admin                        Verify All
                 Progress Data                         Data

                                                                                                                                 No
Request for         Collect Field               Status              Update            Compare to               Critical Path
Update Data         Progress Data              Schedule            Schedule            Baseline                  Delay?


                                 Identify Contract                                                                    Yes
                                    Changes

                                                                                                             Identify Previous
                                                                                                                  Period
                                                                                                               Critical Path
                                                                                                                                            Publish
            Research                                                                                                                        Updated
                                        Quantify            Identify Causal         Identify Changes
          Documents For                                                                                                                     Schedule
                                         Delays             Delay Activities         To Critical Path
          Driving Delays


                                                                                        Is the
                Assess                  Any          Yes      Perform                  Owner            Yes
                                                                                                                                 Prepare
              Responsibility         Concurrent            Concurrent Delay          Responsible
                                                                                                                                 Recovery
               For Delays             Delays?                 Analysis                For Delay?
                                                                                                                                 Schedule

                                              No
                                                                                              No
                                                                                                                          Resolve
                                                              Is the                     Is a                           Subcontractor
                                    Verify Single            Owner             No    Subcontractor      No              Contributions
                                    Source Delay           Responsible               Responsible
                                    Responsibility          For Delay?                For Delay?
                                                                                                               Discuss Delay &
                                                                                                                Mitigation with
                                                                                               Yes
                                                                   Yes                                          Subcontractor
    Proposed Schedule Update
    With Change Management                                                                         Discuss Delay                   Prepare Delay
                                                                                                    & Mitigation                     Analysis
                                                                                                    With Owner                    & Change Order


                                                                                                                                            24         24
Components of Schedule Management Plan

17. Recovery process
  1. Identify what logic changes are
     acceptable without formal
     approval
  2. Identify what constitutes a
     Revision requiring approval
  3. Provide process description
     or flow chart




                            “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                            ©2010Permission is granted to PMI for PMI® Marketplace use only                          25
Components of Schedule Management Plan

18. Dispute resolution process
   1. Review program for claims avoidance
      1. Reinforce planning for claims avoidance
      2. Identify specific program for claims avoidance during
         schedule updates and change management
   2. Identify steps if change management process
      fails or stalls
   3. Follow specifications
   4. Provide time frames for stages in process
   5. Provide process description or flow chart


                                  “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                                  ©2010Permission is granted to PMI for PMI® Marketplace use only                          26
Schedule Management Plan

Conclusion
•   For success in guiding Schedule Development, the SMP
    should be a completely different process
•   SMP process done prior to Development
•   SMP Process and results documented
•   Documentation done in formal Schedule Management
    Plan Book
•   Becomes a part of the Organizational Process Assets,
    providing policy, procedures, and guidelines for the
    team




                               “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                               ©2010Permission is granted to PMI for PMI® Marketplace use only                          27
Schedule Management Plan
• Resources
   – See Lance Stephenson’s “Schedule Basis Memorandum”
     paper, also addresses schedule levels
   – See AACEi’s Total Cost Management
   – See PMBOK for Risk Management process
• Recommendations
   – Get involved with the SCoP SEI Project developing Best
     Practices and Guidelines for Scheduling
   – Get involved with AACEi and the Recommended Practices
     development
   – Get involved with CMAA in the Time Management development
   – Get involved with Planning Planet in the development of the
     Planners Users’ Guide




                                  “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                                  ©2010Permission is granted to PMI for PMI® Marketplace use only                          28
Contact Information

Chris Carson, PMP, PSP, CCM
Chris.carson@alphacorporation.com
757-342-5524 (US)
Linked-In Contact Information:
http://www.linkedin.com/in/chriswcarson
Session # PRJ10




                           “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                           ©2010Permission is granted to PMI for PMI® Marketplace use only

Mais conteúdo relacionado

Mais procurados

Schedule Review PMI
Schedule Review PMISchedule Review PMI
Schedule Review PMIChris Carson
 
10 Project Management Knowledge Areas
10 Project Management Knowledge Areas10 Project Management Knowledge Areas
10 Project Management Knowledge AreasElizabeth Harrin FAPM
 
Smart Goal Setting and Project Planning
Smart Goal Setting and Project PlanningSmart Goal Setting and Project Planning
Smart Goal Setting and Project PlanningOrangescrum
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueChris Carson
 
Project Prioritizing Model Powerpoint Presentation Slides
Project Prioritizing Model Powerpoint Presentation SlidesProject Prioritizing Model Powerpoint Presentation Slides
Project Prioritizing Model Powerpoint Presentation SlidesSlideTeam
 
PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principlestltiede
 
Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysisADITYA GHUMARE
 
Ms Project Workshop
Ms Project WorkshopMs Project Workshop
Ms Project WorkshopEder Alves
 
PMP Exam Prep_sample slides
PMP Exam Prep_sample slidesPMP Exam Prep_sample slides
PMP Exam Prep_sample slidesWilber Tuttleman
 
Project Management Office (PMO)
Project Management Office (PMO)Project Management Office (PMO)
Project Management Office (PMO)Anand Subramaniam
 
Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7Saad Merie
 
How to perform time impact analysis (TIA)
How to perform time impact analysis (TIA)How to perform time impact analysis (TIA)
How to perform time impact analysis (TIA)Amr Morsy
 
Project Management Foundations Course 101 - Project Management Concepts
Project Management Foundations Course 101 - Project Management ConceptsProject Management Foundations Course 101 - Project Management Concepts
Project Management Foundations Course 101 - Project Management ConceptsThink For A Change
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlM Maged Hegazy, LLM, MBA, CCP, P3O
 
Chap 9.5 Manage Team
Chap 9.5  Manage TeamChap 9.5  Manage Team
Chap 9.5 Manage TeamAnand Bobade
 

Mais procurados (20)

Schedule Review PMI
Schedule Review PMISchedule Review PMI
Schedule Review PMI
 
Forensic schedule analysis acesss
Forensic schedule analysis acesssForensic schedule analysis acesss
Forensic schedule analysis acesss
 
10 Project Management Knowledge Areas
10 Project Management Knowledge Areas10 Project Management Knowledge Areas
10 Project Management Knowledge Areas
 
Smart Goal Setting and Project Planning
Smart Goal Setting and Project PlanningSmart Goal Setting and Project Planning
Smart Goal Setting and Project Planning
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned Value
 
Project Prioritizing Model Powerpoint Presentation Slides
Project Prioritizing Model Powerpoint Presentation SlidesProject Prioritizing Model Powerpoint Presentation Slides
Project Prioritizing Model Powerpoint Presentation Slides
 
PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principles
 
Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysis
 
Ms Project Workshop
Ms Project WorkshopMs Project Workshop
Ms Project Workshop
 
PMP Exam Prep_sample slides
PMP Exam Prep_sample slidesPMP Exam Prep_sample slides
PMP Exam Prep_sample slides
 
Project Management Office (PMO)
Project Management Office (PMO)Project Management Office (PMO)
Project Management Office (PMO)
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
 
project management (10).pptx
project management (10).pptxproject management (10).pptx
project management (10).pptx
 
CCPM using ms project 2010 and prochain implementing ppm
CCPM using ms project 2010 and prochain implementing ppmCCPM using ms project 2010 and prochain implementing ppm
CCPM using ms project 2010 and prochain implementing ppm
 
Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7
 
How to perform time impact analysis (TIA)
How to perform time impact analysis (TIA)How to perform time impact analysis (TIA)
How to perform time impact analysis (TIA)
 
Project Management Foundations Course 101 - Project Management Concepts
Project Management Foundations Course 101 - Project Management ConceptsProject Management Foundations Course 101 - Project Management Concepts
Project Management Foundations Course 101 - Project Management Concepts
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project Control
 
Chap 9.5 Manage Team
Chap 9.5  Manage TeamChap 9.5  Manage Team
Chap 9.5 Manage Team
 
Pmbok6 to 7 transformation
Pmbok6 to 7 transformationPmbok6 to 7 transformation
Pmbok6 to 7 transformation
 

Destaque

Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueChris Carson
 
Mitigation of Risk in Dual Schedules
Mitigation of Risk in Dual SchedulesMitigation of Risk in Dual Schedules
Mitigation of Risk in Dual SchedulesChris Carson
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule DevelopmentChris Carson
 
Use Of Schedule Logs 2012 Pmi Scop Conference
Use Of Schedule Logs   2012 Pmi Scop ConferenceUse Of Schedule Logs   2012 Pmi Scop Conference
Use Of Schedule Logs 2012 Pmi Scop ConferenceChris Carson
 
Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIChris Carson
 
Baseline Schedules 1
Baseline Schedules 1Baseline Schedules 1
Baseline Schedules 1Chris Carson
 
Different types of glasses
Different types of glassesDifferent types of glasses
Different types of glassesKrishna Sahit
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time AnalysisFarhan Moosa
 
Sample project plan
Sample project planSample project plan
Sample project planmamoonnift
 
project on construction of house report.
project on construction of house report.project on construction of house report.
project on construction of house report.Hagi Sahib
 
Sample Business Plan Presentation
Sample Business Plan PresentationSample Business Plan Presentation
Sample Business Plan PresentationEnigma
 

Destaque (13)

Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned Value
 
Mitigation of Risk in Dual Schedules
Mitigation of Risk in Dual SchedulesMitigation of Risk in Dual Schedules
Mitigation of Risk in Dual Schedules
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule Development
 
Use Of Schedule Logs 2012 Pmi Scop Conference
Use Of Schedule Logs   2012 Pmi Scop ConferenceUse Of Schedule Logs   2012 Pmi Scop Conference
Use Of Schedule Logs 2012 Pmi Scop Conference
 
Schedule Updates
Schedule UpdatesSchedule Updates
Schedule Updates
 
Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEI
 
Baseline Schedules 1
Baseline Schedules 1Baseline Schedules 1
Baseline Schedules 1
 
06 project time management m
06 project time management m06 project time management m
06 project time management m
 
Different types of glasses
Different types of glassesDifferent types of glasses
Different types of glasses
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
 
Sample project plan
Sample project planSample project plan
Sample project plan
 
project on construction of house report.
project on construction of house report.project on construction of house report.
project on construction of house report.
 
Sample Business Plan Presentation
Sample Business Plan PresentationSample Business Plan Presentation
Sample Business Plan Presentation
 

Semelhante a Design & Development Of A Schedule Management Plan Presentation

Project management in pharmaceutical generic industry basics and standards
Project management in pharmaceutical generic industry basics and standardsProject management in pharmaceutical generic industry basics and standards
Project management in pharmaceutical generic industry basics and standardsJayesh Khatri
 
Schedule Design PMI
Schedule Design PMISchedule Design PMI
Schedule Design PMIChris Carson
 
Managing an ITIL SaaS implementation IT program
Managing an ITIL SaaS implementation IT programManaging an ITIL SaaS implementation IT program
Managing an ITIL SaaS implementation IT programGottfried Rudorfer
 
Macrosolutions Training: Planning and Monitoring Projects with Microsoft Proj...
Macrosolutions Training: Planning and Monitoring Projects with Microsoft Proj...Macrosolutions Training: Planning and Monitoring Projects with Microsoft Proj...
Macrosolutions Training: Planning and Monitoring Projects with Microsoft Proj...Macrosolutions SA
 
Pmp pmbok6 -2018 (1)
Pmp   pmbok6 -2018 (1)Pmp   pmbok6 -2018 (1)
Pmp pmbok6 -2018 (1)sai12234
 
Pmp pmbok6 -2018 (1)
Pmp   pmbok6 -2018 (1)Pmp   pmbok6 -2018 (1)
Pmp pmbok6 -2018 (1)sai12234
 
Implementation of the pmo proposal
Implementation of the pmo proposalImplementation of the pmo proposal
Implementation of the pmo proposalHugh Shults
 
PMI quick guide
PMI quick guide PMI quick guide
PMI quick guide Maven
 
Pmp training in kolkata
Pmp training in kolkataPmp training in kolkata
Pmp training in kolkataTejaspathiLV
 
Pmp pmbok6 -2018
Pmp   pmbok6 -2018Pmp   pmbok6 -2018
Pmp pmbok6 -2018sai12234
 
Pmp pmbok6 -2018
Pmp   pmbok6 -2018Pmp   pmbok6 -2018
Pmp pmbok6 -2018sai12234
 
pmp training
pmp trainingpmp training
pmp trainingsanfrrans
 
pmi agile certified practitioner course
pmi agile certified practitioner coursepmi agile certified practitioner course
pmi agile certified practitioner coursekrishna1132
 
PMP Certification Hyderabad
PMP Certification HyderabadPMP Certification Hyderabad
PMP Certification Hyderabadshivajbb
 
Pmp training bangalore
Pmp training bangalorePmp training bangalore
Pmp training bangaloreprathyusha1234
 
Pmp certification hyderabad
Pmp certification hyderabadPmp certification hyderabad
Pmp certification hyderabadprathyusha1234
 
pmi acp training bangalore
pmi acp training bangalorepmi acp training bangalore
pmi acp training bangaloredevipatnala1
 
Pmp pmbok6 -2018
Pmp   pmbok6 -2018Pmp   pmbok6 -2018
Pmp pmbok6 -2018sai12234
 

Semelhante a Design & Development Of A Schedule Management Plan Presentation (20)

2_Project Scope Management
2_Project Scope Management2_Project Scope Management
2_Project Scope Management
 
Project management in pharmaceutical generic industry basics and standards
Project management in pharmaceutical generic industry basics and standardsProject management in pharmaceutical generic industry basics and standards
Project management in pharmaceutical generic industry basics and standards
 
Schedule Design PMI
Schedule Design PMISchedule Design PMI
Schedule Design PMI
 
Managing an ITIL SaaS implementation IT program
Managing an ITIL SaaS implementation IT programManaging an ITIL SaaS implementation IT program
Managing an ITIL SaaS implementation IT program
 
Macrosolutions Training: Planning and Monitoring Projects with Microsoft Proj...
Macrosolutions Training: Planning and Monitoring Projects with Microsoft Proj...Macrosolutions Training: Planning and Monitoring Projects with Microsoft Proj...
Macrosolutions Training: Planning and Monitoring Projects with Microsoft Proj...
 
Pmp pmbok6 -2018 (1)
Pmp   pmbok6 -2018 (1)Pmp   pmbok6 -2018 (1)
Pmp pmbok6 -2018 (1)
 
Pmp pmbok6 -2018 (1)
Pmp   pmbok6 -2018 (1)Pmp   pmbok6 -2018 (1)
Pmp pmbok6 -2018 (1)
 
Implementation of the pmo proposal
Implementation of the pmo proposalImplementation of the pmo proposal
Implementation of the pmo proposal
 
PMI quick guide
PMI quick guide PMI quick guide
PMI quick guide
 
Pmp training in kolkata
Pmp training in kolkataPmp training in kolkata
Pmp training in kolkata
 
Pmp pmbok6 -2018
Pmp   pmbok6 -2018Pmp   pmbok6 -2018
Pmp pmbok6 -2018
 
PMP Certifiation
PMP CertifiationPMP Certifiation
PMP Certifiation
 
Pmp pmbok6 -2018
Pmp   pmbok6 -2018Pmp   pmbok6 -2018
Pmp pmbok6 -2018
 
pmp training
pmp trainingpmp training
pmp training
 
pmi agile certified practitioner course
pmi agile certified practitioner coursepmi agile certified practitioner course
pmi agile certified practitioner course
 
PMP Certification Hyderabad
PMP Certification HyderabadPMP Certification Hyderabad
PMP Certification Hyderabad
 
Pmp training bangalore
Pmp training bangalorePmp training bangalore
Pmp training bangalore
 
Pmp certification hyderabad
Pmp certification hyderabadPmp certification hyderabad
Pmp certification hyderabad
 
pmi acp training bangalore
pmi acp training bangalorepmi acp training bangalore
pmi acp training bangalore
 
Pmp pmbok6 -2018
Pmp   pmbok6 -2018Pmp   pmbok6 -2018
Pmp pmbok6 -2018
 

Mais de Chris Carson

Pmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation SchedulesPmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation SchedulesChris Carson
 
Types Of Industry Scheduling
Types Of Industry SchedulingTypes Of Industry Scheduling
Types Of Industry SchedulingChris Carson
 
Use Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis MethodUse Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis MethodChris Carson
 
Early Completion Schedules
Early Completion SchedulesEarly Completion Schedules
Early Completion SchedulesChris Carson
 
Can A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotCan A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotChris Carson
 
Schedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract AdminSchedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract AdminChris Carson
 
Presentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesPresentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesChris Carson
 
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...Chris Carson
 
Mitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel SchedulesMitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel SchedulesChris Carson
 
How To Structure A Successful Mediation
How To Structure A Successful MediationHow To Structure A Successful Mediation
How To Structure A Successful MediationChris Carson
 
2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule RevisionsChris Carson
 
Planning A Complex Project
Planning A Complex ProjectPlanning A Complex Project
Planning A Complex ProjectChris Carson
 
Innovative Program Delivery - Airport
Innovative Program Delivery - AirportInnovative Program Delivery - Airport
Innovative Program Delivery - AirportChris Carson
 
Planning For Adverse Weather
Planning For Adverse WeatherPlanning For Adverse Weather
Planning For Adverse WeatherChris Carson
 
Testimony Mistakes
Testimony MistakesTestimony Mistakes
Testimony MistakesChris Carson
 
Subcontractor Scheduling
Subcontractor SchedulingSubcontractor Scheduling
Subcontractor SchedulingChris Carson
 
DB Medical Pgm Mgmnt.
DB Medical Pgm Mgmnt.DB Medical Pgm Mgmnt.
DB Medical Pgm Mgmnt.Chris Carson
 
Baseline Schedules 2
Baseline Schedules 2Baseline Schedules 2
Baseline Schedules 2Chris Carson
 

Mais de Chris Carson (19)

Pmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation SchedulesPmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation Schedules
 
Types Of Industry Scheduling
Types Of Industry SchedulingTypes Of Industry Scheduling
Types Of Industry Scheduling
 
Use Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis MethodUse Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis Method
 
Early Completion Schedules
Early Completion SchedulesEarly Completion Schedules
Early Completion Schedules
 
Can A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotCan A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does Not
 
Schedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract AdminSchedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract Admin
 
Presentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesPresentation Classification Of Schedule Types
Presentation Classification Of Schedule Types
 
Claims Triage
Claims TriageClaims Triage
Claims Triage
 
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
 
Mitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel SchedulesMitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel Schedules
 
How To Structure A Successful Mediation
How To Structure A Successful MediationHow To Structure A Successful Mediation
How To Structure A Successful Mediation
 
2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions
 
Planning A Complex Project
Planning A Complex ProjectPlanning A Complex Project
Planning A Complex Project
 
Innovative Program Delivery - Airport
Innovative Program Delivery - AirportInnovative Program Delivery - Airport
Innovative Program Delivery - Airport
 
Planning For Adverse Weather
Planning For Adverse WeatherPlanning For Adverse Weather
Planning For Adverse Weather
 
Testimony Mistakes
Testimony MistakesTestimony Mistakes
Testimony Mistakes
 
Subcontractor Scheduling
Subcontractor SchedulingSubcontractor Scheduling
Subcontractor Scheduling
 
DB Medical Pgm Mgmnt.
DB Medical Pgm Mgmnt.DB Medical Pgm Mgmnt.
DB Medical Pgm Mgmnt.
 
Baseline Schedules 2
Baseline Schedules 2Baseline Schedules 2
Baseline Schedules 2
 

Design & Development Of A Schedule Management Plan Presentation

  • 1. Design & Development of a Schedule Management Plan Session #PRJ10 Chris Carson, PMP, PSP, CCM Alpha Corporation “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010 Permission is granted to PMI for PMI® Marketplace use only
  • 2. Chris Carson, PSP, CCM, PMP • Corporate Director of Project Controls, Alpha Corporation – Developed and manages the PMO (Project Management Office) for Alpha Corporation – Responsible for standards, processes, and procedures for a team of schedulers, analysts, and project managers in multiple office locations, as well as analysis, work product, and testimony – Developed and manages the in-house project controls training program at Alpha • Certifications: – PSP (Planning & Scheduling Professional – AACEi) – CCM (Certified Construction Manager - CMAA) – PMP (Project Management Professional – PMI) • University: University of Virginia, Mechanical Engineering, 1968 - 1972 • Professional Field: 38 years of experience in Construction Management Services specializing in Scheduling, Schedule Analysis, Estimating, Claims • Active in PMI (Project Management Institute) Scheduling Community of Practice – Vice President of Scheduling Excellence for CoS – Managing Director for SEI (Scheduling Excellence Initiative) writing Best Practices and Guidelines for Scheduling and Schedule Impact Analysis – Serving on team writing Best Practices for Scheduling for GAO • Active in CMAA (Construction Management Association of America) – Served on committee revising Time Management Chapter of CMAA’s CM Standards of Practice • Active in AACEi (Association for the Advancement of Cost Estimating International) – Member of P&S and CDR Committees – Author of Recommended Practices in Scheduling & Editor of Forensic Schedule Analysis RP • Active in Planning Planet – Chief Editor for US, writing Planner Users’ Guide, developing accreditations through a Guild for planners and • Award – “Significant Contributions to Scheduling Profession”, 2008 CoS Annual Conference 2 2 2
  • 3. Schedule Management Plan The PMBOK® Guide describes the Project Management Plan “Process of documenting actions necessary to define, prepare, integrate, coordinate all subsidiary plans” Knowledge Area – Integration Process Group – Planning Inputs “Outputs from many planning processes are integrated to create the Project Management Plan (PMP)” “Any baselines & subsidiary management plans that are output from other planning processes are inputs here” “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010Permission is granted to PMI for PMI® Marketplace use only 3
  • 4. Schedule Management Plan The PMBOK® Guide Does not describe or define the Schedule Management Plan Except to note the existence of subsidiary plans such as the “Schedule Management Plan” Described in the introduction to Chapter 6 as a “schedule management plan that selects a scheduling methodology, a scheduling tool, and sets the format and establishes criteria for developing and controlling the project schedule.” “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010Permission is granted to PMI for PMI® Marketplace use only 4
  • 5. Schedule Management Plan Purpose of the schedule management plan? Schedule Development meets the criteria for a “project” in itself The SMP provides a methodical approach for the schedule development Keeps the schedule development on track Prevents rework due to late understanding of needs Allows buy-in from end users prior to development Makes the schedule development session much more meaningful Documents the assumptions and intention of the schedule For reviewer and approver For future reference To facilitate changes in schedulers Place to capture Lessons Learned “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010Permission is granted to PMI for PMI® Marketplace use only 5
  • 6. Schedule Management Plan Scope of SMP vs. Schedule Development Processes Schedule Management Plan– Conceptualizing the schedule effort (designing the schedule) Planning Starting with the end in mind Providing concept of final product Creating organizational structure to fulfill the concept Development - Building the schedule Define activities Sequence activities - input logic Estimate activity resources Estimate activity durations Develop schedule Monitor and Control schedule “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010Permission is granted to PMI for PMI® Marketplace use only 6
  • 7. Schedule Management Plan Documentation & use of Schedule Management Plan Create a book or binder Use the highest level of checklist outline items as tabs Use the book as basis for SMP submittal documentation Keep the book current during project Use the book for handoff between schedulers Share a copy of the book with superintendent/PM Timing of the SMP Must be done prior to Schedule Development “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010Permission is granted to PMI for PMI® Marketplace use only 7
  • 8. Components of Schedule Management Plan 1. Project Description 1. Reference Documents Needed for the SMP 1. Contract 2. Project Drawings 3. Specifications 4. Scheduling Specification 5. Notice to Proceed or Release Letter 6. Any Owner produced master schedule 7. Liquidated Damages schedule 8. Area Designation Plan 9. Sequencing plan 10. Estimate & quantity surveys/bills of materials “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010Permission is granted to PMI for PMI® Marketplace use only 8
  • 9. Components of Schedule Management Plan 2. Team Players 1. Organizational Chart 2. Who are Schedule Users? 1. Who has Input 2. Who Updates 3. Who Checks for Accuracy 4. Who Reviews 5. Who approves 3. Identify Responsibility Assignment Matrix (RAM) “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010Permission is granted to PMI for PMI® Marketplace use only 9
  • 10. Components of Schedule Management Plan • RAM Example (based on PMBOK® RACI Chart) – Correlates tasks with roles and individuals “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010Permission is granted to PMI for PMI® Marketplace use only 10
  • 11. Components of Schedule Management Plan 3. Software Identification 1. Specific software required 1. Required minimum and versions allowed 2. Enterprise specific issues 1. Users identified 2. Schedules used for import or data source 3. Levels of access 4. Validation process 5. For master schedules, establish data dates “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010Permission is granted to PMI for PMI® Marketplace use only 11
  • 12. Components of Schedule Management Plan 4. Work Product 1. What the Schedule can be used for (purpose) 2. Reports Generated from the Schedule 1. Who receives reports 2. List of reports 3. Samples of reports 3. Glossary/Lexicon of ambiguous terms (or cultural terms – is it programme or schedule?) 5. Schedule Outline 1. Key Activities being tracked 2. Client Milestones 3. Long Lead Items 4. WBS Structure & cost accounts 5. Other Contracts on Project “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010Permission is granted to PMI for PMI® Marketplace use only 12
  • 13. Components of Schedule Management Plan • Reporting “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010Permission is granted to PMI for PMI® Marketplace use only 13
  • 14. Components of Schedule Management Plan 6. Work Packages or Tenders 1. By Contract 2. As assigned by Client 7. Level of Detail 1. Determine approach: 1. Bottom-up (starting with detailed activities) 2. Top-down (starting with summary schedule) 3. Both (prepare Top-down, then Bottom-up) 2. Identify frequency of updates 3. Establish smallest activity duration range “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010Permission is granted to PMI for PMI® Marketplace use only 14
  • 15. Components of Schedule Management Plan 8. Codes Dictionary 1. For tracking and monitoring work: 1. Work Phase 2. Structure 3. Area 4. Floor or Station 5. Location 2. For Project Management: 1. Responsibility 2. Work Shifts 3. Costs 4. Resource 5. Specification 6. Change management “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010Permission is granted to PMI for PMI® Marketplace use only 15
  • 16. Components of Schedule Management Plan 9. Calendars 1. Establish number needed 2. Define calendars and application 10. Costs & Resources 1. Estimate & correlation to cost loading 2. Bill of Quantities & use in resources 3. Resource Crew descriptions 4. Equipment descriptions 5. How actual production will be monitored 6. Earned Value Management System 11. Narrative Basis & Assumptions 1. Procedure Used to create the Schedule/Programme 2. Definitions/lexicon 3. Description of sequence of work per structure “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010Permission is granted to PMI for PMI® Marketplace use only 16
  • 17. Components of Schedule Management Plan • Narrative Basis “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010Permission is granted to PMI for PMI® Marketplace use only 17
  • 18. Components of Schedule Management Plan 12. Risks & Constructability 1. Brainstorming of issues 1. Known problems (threats) 2. Predicted problems 3. Lessons Learned 4. Outside influences 5. Site condition concerns 6. Opportunities 2. Develop Risk Management Plan 1. Initial process during baseline schedule development 2. Process for use during updates “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010Permission is granted to PMI for PMI® Marketplace use only 18
  • 19. Components of Schedule Management Plan • Risk Management Plan – Based on PMBOK® “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010Permission is granted to PMI for PMI® Marketplace use only 19
  • 20. Components of Schedule Management Plan 13. Weather planning 1. Expected adverse weather 2. Identify source or specification requirement 3. Identify methodology 4. Identify accounting method for actual weather “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010Permission is granted to PMI for PMI® Marketplace use only 20
  • 21. Components of Schedule Management Plan 14. Time Contingencies 1. Amounts 2. Specific trade (from risk management plan) 3. Specific contractor contingency 4. How carried 5. Use historical data for reference Time Performance Ratio 12.0 10.0 8.0 TPR 6.0 4.0 2.0 0.0 ev s ry s ry nt ws El cal e / W ing l Eq hes rk ar ls Si in ca g or et a nt on Fu me m wo in do ni t ri et of at cr pe Ad s ish as ha ec te oo Ro M ni p on in ui Fi M rn ec El C C M rs D Type of Work “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010Permission is granted to PMI for PMI® Marketplace use only 21
  • 22. Components of Schedule Management Plan 15. Establish Update process 1. Frequency 2. Data request and transmission 3. Validation 4. Process flowchart “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010Permission is granted to PMI for PMI® Marketplace use only 22
  • 23. Components of Schedule Management Plan 16. Change Management process 1. Notification requirements 2. Methodology allowed 3. Process flowchart “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010Permission is granted to PMI for PMI® Marketplace use only 23
  • 24. Collect Admin Verify All Progress Data Data No Request for Collect Field Status Update Compare to Critical Path Update Data Progress Data Schedule Schedule Baseline Delay? Identify Contract Yes Changes Identify Previous Period Critical Path Publish Research Updated Quantify Identify Causal Identify Changes Documents For Schedule Delays Delay Activities To Critical Path Driving Delays Is the Assess Any Yes Perform Owner Yes Prepare Responsibility Concurrent Concurrent Delay Responsible Recovery For Delays Delays? Analysis For Delay? Schedule No No Resolve Is the Is a Subcontractor Verify Single Owner No Subcontractor No Contributions Source Delay Responsible Responsible Responsibility For Delay? For Delay? Discuss Delay & Mitigation with Yes Yes Subcontractor Proposed Schedule Update With Change Management Discuss Delay Prepare Delay & Mitigation Analysis With Owner & Change Order 24 24
  • 25. Components of Schedule Management Plan 17. Recovery process 1. Identify what logic changes are acceptable without formal approval 2. Identify what constitutes a Revision requiring approval 3. Provide process description or flow chart “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010Permission is granted to PMI for PMI® Marketplace use only 25
  • 26. Components of Schedule Management Plan 18. Dispute resolution process 1. Review program for claims avoidance 1. Reinforce planning for claims avoidance 2. Identify specific program for claims avoidance during schedule updates and change management 2. Identify steps if change management process fails or stalls 3. Follow specifications 4. Provide time frames for stages in process 5. Provide process description or flow chart “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010Permission is granted to PMI for PMI® Marketplace use only 26
  • 27. Schedule Management Plan Conclusion • For success in guiding Schedule Development, the SMP should be a completely different process • SMP process done prior to Development • SMP Process and results documented • Documentation done in formal Schedule Management Plan Book • Becomes a part of the Organizational Process Assets, providing policy, procedures, and guidelines for the team “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010Permission is granted to PMI for PMI® Marketplace use only 27
  • 28. Schedule Management Plan • Resources – See Lance Stephenson’s “Schedule Basis Memorandum” paper, also addresses schedule levels – See AACEi’s Total Cost Management – See PMBOK for Risk Management process • Recommendations – Get involved with the SCoP SEI Project developing Best Practices and Guidelines for Scheduling – Get involved with AACEi and the Recommended Practices development – Get involved with CMAA in the Time Management development – Get involved with Planning Planet in the development of the Planners Users’ Guide “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010Permission is granted to PMI for PMI® Marketplace use only 28
  • 29. Contact Information Chris Carson, PMP, PSP, CCM Chris.carson@alphacorporation.com 757-342-5524 (US) Linked-In Contact Information: http://www.linkedin.com/in/chriswcarson Session # PRJ10 “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010Permission is granted to PMI for PMI® Marketplace use only