FPSO’s & DNV




EOCBR 514 – Newbuildings and Conversions
Marcelo Spotorno
Rio de Janeiro, 16.07.2009
More than 140 years of managing risk
       Det Norske Veritas (DNV) was established in 1864 in Norway
       The main scope of work was to identify, assess and manage risk
        – initially for maritime insurance companies




© Det Norske Veritas AS. All rights reserved   28 September 2011         Slide 2
300 offices in 100 countries




                                               Head office           Local offices


© Det Norske Veritas AS. All rights reserved           28 September 2011             Slide 3
Our people – a vital resource
            People are the core of DNV            9000 employees      97 nationalities




© Det Norske Veritas AS. All rights reserved   28 September 2011                            Slide 4
FPSO – Market share

                   Vietnam
                     1%

                       Rina                      Unknown
         CCS           1%                          6%
         1%                                                                                                          ABS
                                                                                                                     35 %
             BV
             4%


              LR
             12 %




                                                                                                              DNV
                                                                                                              40 %
  Source:
  - Mobile Production systems of the World, 7th Edition, 2007/2008, Clarkson Research Services Limited
  - Floating Production Systems - assessment of the outlook for FPSO vessels, production semis, TLPs
  and Spars, November 2007, International Maritime Associates Inc.




© Det Norske Veritas AS. All rights reserved                                                    28 September 2011           Slide 5
Petrojarl I
       the world’s first FPSO built for harsh environment(1986)




© Det Norske Veritas AS. All rights reserved   28 September 2011   Slide 6
First FPSO GoM
       BW Yùum K’ak’Náab




© Det Norske Veritas AS. All rights reserved   28 September 2011   Slide 7
Cascade Chinook / First FPSO for US GoM
   Chinook Cascade
              First FPSO for US GoM




  © Det Norske Veritas AS. All rights reserved   28 September 2011   Slide 8
FPSOs/FSOs Newbuildings & Conversions

                                               BP Skarv-Idun                  Korea-Samsumg   Newbuilding

                                               BW Pioneer - Cascade/Chinook     Singapore     Conversion
                                               Nexus 01                       Korea-Samsumg   Newbuilding
                                               Nexus 02                       Korea-Samsumg   Newbuilding
                                               P-58 - Baleia Azul               Singapore     Conversion
                                               Sevan 300 No. 04               China-Hantong   Newbuilding
                                               Sevan 300 No. 05               China-Hantong   Newbuilding
                                               Ichtys FPSO                          -         Newbuilding
                                               FSO Rita                           Dubai       Conversion
                                               Dynamic Producer                 Singapore     Conversion
                                               Knock Dee FSO                      Dubai       Conversion
                                               Deep Producer                    Singapore     Conversion




© Det Norske Veritas AS. All rights reserved              28 September 2011                            Slide 9
”DNV classed units” around the world
                                                               North Sea:
                                                               FPSO: 18
                                               Canada:
                                               FPSO: 1

                                                                   North Africa:
                                                                   FPSO: 2
                                       Gulf of Mexico:
                                       FPSO: 2


                                                             West Africa:
                                                                                            Asia and Australia:
                                                             FPSO: 12
                                                                                            FPSO: 15


                                                   Brazil:
                                                   FPSO: 3




© Det Norske Veritas AS. All rights reserved                            28 September 2011                         Slide 10
FPSO’s – DNV fleet in Brazil
  SSP300 - Sevan Piranema


  Petrojarl Cidade de Rio das Ostras


  BW Cidade de São Vicente




© Det Norske Veritas AS. All rights reserved   28 September 2011   Slide 11
DNV Offshore Standards




© Det Norske Veritas AS. All rights reserved   28 September 2011   Slide 12
Benign Waters
       DNV OS-C-102 - Structural Design of Offshore Ships
            - World-wide operation
            - Benign waters - Environments at which the required to hull girder capacity
              calculated according to the LRFD method is less than the minimum section
              modulus according to the ‘Main Class Requirements’.




© Det Norske Veritas AS. All rights reserved   28 September 2011                           Slide 13
Benign Waters
       Alternative design procedures
            - Alternative 1 - Ship Rules - The hull scantlings are based on the “main class
              requirements”.No direct calculations of wave bending moments and shear
              forces are required.
            - Alternative 2 - LRFD method - The hull is designed according to the principles
              given in Ch.1. The midship section modulus may be less than the ”main class
              requirements”. When design Alternative 2, LRFD method, is applied, the
              minimum midship section modulus according to the ”main class requirements”
              may be reduced by maximum 25%.




© Det Norske Veritas AS. All rights reserved   28 September 2011                         Slide 14
P-58 - Nauticus Construction


Default


Innerstructure


Outershell


Thickness map


Material map


© Det Norske Veritas AS. All rights reserved   28 September 2011   Slide 15
Information – dimensions and steel grades
 You  get an over-view from colour
  display and printed numbers.
 Gives you access to the dimensions
  and steel grades of plates, stiffeners
  and girders
 Byclicking the structural parts you get
  more details




© Det Norske Veritas AS. All rights reserved   28 September 2011   Slide 16
Maintenance – Steel renewal / weight




                    Marking up all plates and/or
                    stiffeners within a 3D zone by               Plates and stiffeners can be marked
                    defining and extruding a polygon             up independently by using separate
                                                                 zones




© Det Norske Veritas AS. All rights reserved           28 September 2011                               Slide 17
Maintenance – Coating Area Calculations




                                                                               Marking up single structures for
                     Marking up all structures for
                                                                               partial coating: top, one side (gray on
                     complete or part of the compartment
                                                                               aft side means not coated)
© Det Norske Veritas AS. All rights reserved               28 September 2011                                         Slide 18
Maintenance – Docking specifications
       Planning and cost
        control prior/during a
        docking of a vessel.
       Specification or for
        verification purposes
        of the figures given
        by the ship repair
        yard.




© Det Norske Veritas AS. All rights reserved   28 September 2011   Slide 19
Maintenance – Emergency Repairs

                                                                    Facilitates
                                                                              the
                                                                    documentation of damage:
                                                                     - Location
                                                                     - Extent
                                                                     - Type of structure
                                                                    Noneed for long and
                                                                    complex descriptions.
                                                                    Enables  overview and
                                                                    control the expenses.




© Det Norske Veritas AS. All rights reserved   28 September 2011                             Slide 20
Monitoring - Coating Monitoring Tool
 The Nauticus Coating
 Monitoring Tool takes
 advantage of 3D technology to
 visualise the coating status
 and calculate re-coating areas.
 The tool also supports a
 structured recording of coating
 inspection results referring to
 pre-defined cells/bays of the
 ballast tanks. Finally, it assists
 you in preparing the re-coating
 specification and estimates the
 costs.
 When  tool is used one has
 stop to take a risk of
 unpredicted situations in
 respect to mintenance or
 failure.

 © Det Norske Veritas AS. All rights reserved   28 September 2011   Slide 21
Monitoring – UTM




                                This improves UTM measurement support improved
                                           Thickness process: shorter time,
                                 quality and communication, input to maintenance
                                The Nauticus UTM Tool improves planning, execution and
                                 strategy: of ultrasonic thicknesslower cost
                                 evaluation better control and measurements.




© Det Norske Veritas AS. All rights reserved          28 September 2011                  Slide 22
Management – Maintenance Strategy
                                 Set of UTM readings                                                 The curve shows tendency
                                 from previous years                                                 of steel diminution within
                                                                                                     the years and can be used
                                                                                                     for prognosis
                                                                                                                Trend Curve

                                                                                                    25%
                                                                                                              t dim




                                                                             Thickness Diminution
                                                                                                    20%       t sub
                                                                                                              t min
                                                                                                    15%

                                                                                                    10%

                                                                                                    5%

                                                                                                    0%
                                                                                                      1983   1988     1993 1998   2003   2008   2013
                                                                                                                          Years




                                               Coating Condition Status
© Det Norske Veritas AS. All rights reserved             28 September 2011                                                                         Slide 23
Training – Naming of Structure




© Det Norske Veritas AS. All rights reserved   28 September 2011   Slide 24
Training – Areas of Attention
                                                                             “Risk Based Inspection” with Focus on ”Critical Areas”




                                                                                                                             Inspection of upper hopper knuckle especially
                                                                                                                                       in way of trv. web frames




                                               Inspection of lower hopper knuckle especially
                                                         in way of trv. web frames




© Det Norske Veritas AS. All rights reserved                                                       28 September 2011                                                         Slide 25
© Det Norske Veritas AS. All rights reserved   28 September 2011   Slide 26

Mais conteúdo relacionado

Mais procurados

Oil Production Facilities
Oil Production FacilitiesOil Production Facilities
Oil Production FacilitiesInGu Lee
 
OFFSHORE PLATFORM_1.ppt (1).pdf
OFFSHORE PLATFORM_1.ppt (1).pdfOFFSHORE PLATFORM_1.ppt (1).pdf
OFFSHORE PLATFORM_1.ppt (1).pdfAisyah Asyikin
 
Basic whp presentation(1)
Basic whp presentation(1)Basic whp presentation(1)
Basic whp presentation(1)nguyen_uptorcem
 
FPSO Redeployment
FPSO RedeploymentFPSO Redeployment
FPSO RedeploymentDan Benson
 
Offshore oil and gas overview
Offshore oil and gas overviewOffshore oil and gas overview
Offshore oil and gas overviewminh nguyễn
 
Tank design - powerpoint slides
Tank design - powerpoint slidesTank design - powerpoint slides
Tank design - powerpoint slidesmoamen mohamed
 
ASME Section VIII Div 1. design training
ASME Section VIII Div 1.  design trainingASME Section VIII Div 1.  design training
ASME Section VIII Div 1. design trainingSam Jose
 
Distillation Trays as Mechanical Equipment (Advisian).pdf
Distillation Trays as Mechanical Equipment (Advisian).pdfDistillation Trays as Mechanical Equipment (Advisian).pdf
Distillation Trays as Mechanical Equipment (Advisian).pdfDWNLDUSRML
 
Metode Konstruksi Offshore Platform_2016_2_18.ppt
Metode Konstruksi Offshore Platform_2016_2_18.pptMetode Konstruksi Offshore Platform_2016_2_18.ppt
Metode Konstruksi Offshore Platform_2016_2_18.pptMFaridGeonova
 
Offshore structure design, Sigve Hamilton Aspelund
Offshore structure design, Sigve Hamilton AspelundOffshore structure design, Sigve Hamilton Aspelund
Offshore structure design, Sigve Hamilton AspelundSigve Hamilton Aspelund
 
C9 FPSO Layout and Turret 2004
C9 FPSO Layout and Turret 2004C9 FPSO Layout and Turret 2004
C9 FPSO Layout and Turret 2004David Seow
 
Oil & Gas Production and Surface Facilities
Oil & Gas Production and Surface FacilitiesOil & Gas Production and Surface Facilities
Oil & Gas Production and Surface FacilitiesMohamed Elnagar
 
List of API standards for rotating equipment
List of API standards for rotating equipmentList of API standards for rotating equipment
List of API standards for rotating equipmentravisriniv
 

Mais procurados (20)

Oil Production Facilities
Oil Production FacilitiesOil Production Facilities
Oil Production Facilities
 
OFFSHORE PLATFORM_1.ppt (1).pdf
OFFSHORE PLATFORM_1.ppt (1).pdfOFFSHORE PLATFORM_1.ppt (1).pdf
OFFSHORE PLATFORM_1.ppt (1).pdf
 
Basic whp presentation(1)
Basic whp presentation(1)Basic whp presentation(1)
Basic whp presentation(1)
 
Offshore packages
Offshore packagesOffshore packages
Offshore packages
 
Wellheads and Flow Lines.pdf
Wellheads and Flow Lines.pdfWellheads and Flow Lines.pdf
Wellheads and Flow Lines.pdf
 
212790628 fpso
212790628 fpso212790628 fpso
212790628 fpso
 
FPSO Redeployment
FPSO RedeploymentFPSO Redeployment
FPSO Redeployment
 
Offshore oil and gas overview
Offshore oil and gas overviewOffshore oil and gas overview
Offshore oil and gas overview
 
Structural Design of Drill Ships
Structural Design of Drill ShipsStructural Design of Drill Ships
Structural Design of Drill Ships
 
Tank design - powerpoint slides
Tank design - powerpoint slidesTank design - powerpoint slides
Tank design - powerpoint slides
 
Introduction to Offshore Oil and Gas Surface Facilities
Introduction to Offshore Oil and Gas Surface FacilitiesIntroduction to Offshore Oil and Gas Surface Facilities
Introduction to Offshore Oil and Gas Surface Facilities
 
Advanced Methods for ULS and FLS
Advanced Methods for ULS and FLSAdvanced Methods for ULS and FLS
Advanced Methods for ULS and FLS
 
ASME Section VIII Div 1. design training
ASME Section VIII Div 1.  design trainingASME Section VIII Div 1.  design training
ASME Section VIII Div 1. design training
 
Distillation Trays as Mechanical Equipment (Advisian).pdf
Distillation Trays as Mechanical Equipment (Advisian).pdfDistillation Trays as Mechanical Equipment (Advisian).pdf
Distillation Trays as Mechanical Equipment (Advisian).pdf
 
Metode Konstruksi Offshore Platform_2016_2_18.ppt
Metode Konstruksi Offshore Platform_2016_2_18.pptMetode Konstruksi Offshore Platform_2016_2_18.ppt
Metode Konstruksi Offshore Platform_2016_2_18.ppt
 
Offshore structure design, Sigve Hamilton Aspelund
Offshore structure design, Sigve Hamilton AspelundOffshore structure design, Sigve Hamilton Aspelund
Offshore structure design, Sigve Hamilton Aspelund
 
C9 FPSO Layout and Turret 2004
C9 FPSO Layout and Turret 2004C9 FPSO Layout and Turret 2004
C9 FPSO Layout and Turret 2004
 
Oil & Gas Production and Surface Facilities
Oil & Gas Production and Surface FacilitiesOil & Gas Production and Surface Facilities
Oil & Gas Production and Surface Facilities
 
List of API standards for rotating equipment
List of API standards for rotating equipmentList of API standards for rotating equipment
List of API standards for rotating equipment
 
Offshore platforms
Offshore platformsOffshore platforms
Offshore platforms
 

Semelhante a FPSO Requirements

FPSOs in 2011. Double dip or capacity crunch
FPSOs in 2011. Double dip or capacity crunchFPSOs in 2011. Double dip or capacity crunch
FPSOs in 2011. Double dip or capacity crunchIQPC
 
FPSOs in 2011: Double dip or capacity crunch?
FPSOs in 2011: Double dip or capacity crunch?FPSOs in 2011: Double dip or capacity crunch?
FPSOs in 2011: Double dip or capacity crunch?FPSO Network
 
Paul Goodfellow– Haynesville operations and operating principles
Paul Goodfellow– Haynesville operations and operating principlesPaul Goodfellow– Haynesville operations and operating principles
Paul Goodfellow– Haynesville operations and operating principlesShell plc
 
Osx project update eng_january
Osx project update eng_januaryOsx project update eng_january
Osx project update eng_januaryosxri
 
TOO Q4 2011: Teekay Offshore Partners Fourth Quarter 2011 Earnings Presentation
TOO Q4 2011: Teekay Offshore Partners Fourth Quarter 2011 Earnings Presentation TOO Q4 2011: Teekay Offshore Partners Fourth Quarter 2011 Earnings Presentation
TOO Q4 2011: Teekay Offshore Partners Fourth Quarter 2011 Earnings Presentation Altera Infrastructure
 
Osx project update ing_novembro_final
Osx project update ing_novembro_finalOsx project update ing_novembro_final
Osx project update ing_novembro_finalosxri
 
Osx project update english_november 2011
Osx project update english_november 2011Osx project update english_november 2011
Osx project update english_november 2011osxri
 
Snapmirror Design
Snapmirror DesignSnapmirror Design
Snapmirror DesignOkieUnix
 
Osx project update eng_ janeiro
Osx project update eng_ janeiroOsx project update eng_ janeiro
Osx project update eng_ janeiroosxri
 
Osx project update english_november
Osx project update english_novemberOsx project update english_november
Osx project update english_novemberosxri
 
Osx project update eng_ march
Osx project update eng_ marchOsx project update eng_ march
Osx project update eng_ marchosxri
 
PROJECT UPDATE
PROJECT UPDATE PROJECT UPDATE
PROJECT UPDATE osxri
 
Osx project update english_november
Osx project update english_novemberOsx project update english_november
Osx project update english_novemberosxri
 
Osx project update eng_ janeiro
Osx project update eng_ janeiroOsx project update eng_ janeiro
Osx project update eng_ janeiroosxri
 

Semelhante a FPSO Requirements (20)

download
downloaddownload
download
 
FPSOs in 2011. Double dip or capacity crunch
FPSOs in 2011. Double dip or capacity crunchFPSOs in 2011. Double dip or capacity crunch
FPSOs in 2011. Double dip or capacity crunch
 
FPSOs in 2011: Double dip or capacity crunch?
FPSOs in 2011: Double dip or capacity crunch?FPSOs in 2011: Double dip or capacity crunch?
FPSOs in 2011: Double dip or capacity crunch?
 
Paul Goodfellow– Haynesville operations and operating principles
Paul Goodfellow– Haynesville operations and operating principlesPaul Goodfellow– Haynesville operations and operating principles
Paul Goodfellow– Haynesville operations and operating principles
 
TOO NAPTP Conference 2012
TOO NAPTP Conference 2012TOO NAPTP Conference 2012
TOO NAPTP Conference 2012
 
TGP NAPTP Conference 2012
TGP NAPTP Conference 2012TGP NAPTP Conference 2012
TGP NAPTP Conference 2012
 
Osx project update eng_january
Osx project update eng_januaryOsx project update eng_january
Osx project update eng_january
 
Steve banks woodside browse ukti aog presentation
Steve banks   woodside browse ukti aog presentationSteve banks   woodside browse ukti aog presentation
Steve banks woodside browse ukti aog presentation
 
TOO Q4 2011: Teekay Offshore Partners Fourth Quarter 2011 Earnings Presentation
TOO Q4 2011: Teekay Offshore Partners Fourth Quarter 2011 Earnings Presentation TOO Q4 2011: Teekay Offshore Partners Fourth Quarter 2011 Earnings Presentation
TOO Q4 2011: Teekay Offshore Partners Fourth Quarter 2011 Earnings Presentation
 
Osx project update ing_novembro_final
Osx project update ing_novembro_finalOsx project update ing_novembro_final
Osx project update ing_novembro_final
 
Osx project update english_november 2011
Osx project update english_november 2011Osx project update english_november 2011
Osx project update english_november 2011
 
Snapmirror Design
Snapmirror DesignSnapmirror Design
Snapmirror Design
 
Osx project update eng_ janeiro
Osx project update eng_ janeiroOsx project update eng_ janeiro
Osx project update eng_ janeiro
 
Osx project update english_november
Osx project update english_novemberOsx project update english_november
Osx project update english_november
 
Osx project update eng_ march
Osx project update eng_ marchOsx project update eng_ march
Osx project update eng_ march
 
PROJECT UPDATE
PROJECT UPDATE PROJECT UPDATE
PROJECT UPDATE
 
Osx project update english_november
Osx project update english_novemberOsx project update english_november
Osx project update english_november
 
Osx project update eng_ janeiro
Osx project update eng_ janeiroOsx project update eng_ janeiro
Osx project update eng_ janeiro
 
API-Rp f110 2007-10
API-Rp f110 2007-10API-Rp f110 2007-10
API-Rp f110 2007-10
 
Brazilian Wave 4
Brazilian Wave 4Brazilian Wave 4
Brazilian Wave 4
 

Mais de João Henrique Volpini Mattos

SUC Brazil 2012 : Analysis of Equipment Foundations of a Laydeck Barge
SUC Brazil 2012 : Analysis of Equipment Foundations of a Laydeck BargeSUC Brazil 2012 : Analysis of Equipment Foundations of a Laydeck Barge
SUC Brazil 2012 : Analysis of Equipment Foundations of a Laydeck BargeJoão Henrique Volpini Mattos
 
SUC Brasil 2012 : Optimization of a Floating Platforms Mooring System Based o...
SUC Brasil 2012 : Optimization of a Floating Platforms Mooring System Based o...SUC Brasil 2012 : Optimization of a Floating Platforms Mooring System Based o...
SUC Brasil 2012 : Optimization of a Floating Platforms Mooring System Based o...João Henrique Volpini Mattos
 
SUC Brasil 2012 : Engineering Study for Barge Lifting Weight on Crane Barge O...
SUC Brasil 2012 : Engineering Study for Barge Lifting Weight on Crane Barge O...SUC Brasil 2012 : Engineering Study for Barge Lifting Weight on Crane Barge O...
SUC Brasil 2012 : Engineering Study for Barge Lifting Weight on Crane Barge O...João Henrique Volpini Mattos
 
SUC Brasil 2012 : Coupled Dynamic Analysis FPSO / Mooring / Risers
SUC Brasil 2012 : Coupled Dynamic Analysis FPSO / Mooring / RisersSUC Brasil 2012 : Coupled Dynamic Analysis FPSO / Mooring / Risers
SUC Brasil 2012 : Coupled Dynamic Analysis FPSO / Mooring / RisersJoão Henrique Volpini Mattos
 
SUC Brasil 2012 : Coupled Analysis of Hose Loadings in a Tandem Offloading Op...
SUC Brasil 2012 : Coupled Analysis of Hose Loadings in a Tandem Offloading Op...SUC Brasil 2012 : Coupled Analysis of Hose Loadings in a Tandem Offloading Op...
SUC Brasil 2012 : Coupled Analysis of Hose Loadings in a Tandem Offloading Op...João Henrique Volpini Mattos
 
SUC Brasil 2012 : Next Generation Hydrod and Recent Development in Hydrod
SUC Brasil 2012 : Next Generation Hydrod and Recent Development in HydrodSUC Brasil 2012 : Next Generation Hydrod and Recent Development in Hydrod
SUC Brasil 2012 : Next Generation Hydrod and Recent Development in HydrodJoão Henrique Volpini Mattos
 
Sesam : Ferramentas de Análise de Pipelines e Flowlines
Sesam : Ferramentas de Análise de Pipelines e FlowlinesSesam : Ferramentas de Análise de Pipelines e Flowlines
Sesam : Ferramentas de Análise de Pipelines e FlowlinesJoão Henrique Volpini Mattos
 

Mais de João Henrique Volpini Mattos (20)

Hydrostatics and stability
Hydrostatics and stabilityHydrostatics and stability
Hydrostatics and stability
 
SUC Brazil 2012 : Analysis of Equipment Foundations of a Laydeck Barge
SUC Brazil 2012 : Analysis of Equipment Foundations of a Laydeck BargeSUC Brazil 2012 : Analysis of Equipment Foundations of a Laydeck Barge
SUC Brazil 2012 : Analysis of Equipment Foundations of a Laydeck Barge
 
SUC Brasil 2012 : The New Sesam Manager
SUC Brasil 2012 : The New Sesam ManagerSUC Brasil 2012 : The New Sesam Manager
SUC Brasil 2012 : The New Sesam Manager
 
SUC Brasil 2012 : Sima for Marine Operations
SUC Brasil 2012 : Sima for Marine OperationsSUC Brasil 2012 : Sima for Marine Operations
SUC Brasil 2012 : Sima for Marine Operations
 
SUC Brasil 2012 : Sesam for Topsides
SUC Brasil 2012 : Sesam for TopsidesSUC Brasil 2012 : Sesam for Topsides
SUC Brasil 2012 : Sesam for Topsides
 
Suc Brasil 2012 : Sesam for SURF
Suc Brasil 2012 : Sesam for SURFSuc Brasil 2012 : Sesam for SURF
Suc Brasil 2012 : Sesam for SURF
 
SUC Brasil 2012 : Optimization of a Floating Platforms Mooring System Based o...
SUC Brasil 2012 : Optimization of a Floating Platforms Mooring System Based o...SUC Brasil 2012 : Optimization of a Floating Platforms Mooring System Based o...
SUC Brasil 2012 : Optimization of a Floating Platforms Mooring System Based o...
 
SUC Brasil 2012 : Importing Models to Sesam GeniE
SUC Brasil 2012 : Importing Models to Sesam GeniESUC Brasil 2012 : Importing Models to Sesam GeniE
SUC Brasil 2012 : Importing Models to Sesam GeniE
 
SUC Brasil 2012 : GeniE Recent Releases
SUC Brasil 2012 : GeniE Recent ReleasesSUC Brasil 2012 : GeniE Recent Releases
SUC Brasil 2012 : GeniE Recent Releases
 
SUC Brasil 2012 : Engineering Study for Barge Lifting Weight on Crane Barge O...
SUC Brasil 2012 : Engineering Study for Barge Lifting Weight on Crane Barge O...SUC Brasil 2012 : Engineering Study for Barge Lifting Weight on Crane Barge O...
SUC Brasil 2012 : Engineering Study for Barge Lifting Weight on Crane Barge O...
 
SUC Brasil 2012 : Coupled Dynamic Analysis FPSO / Mooring / Risers
SUC Brasil 2012 : Coupled Dynamic Analysis FPSO / Mooring / RisersSUC Brasil 2012 : Coupled Dynamic Analysis FPSO / Mooring / Risers
SUC Brasil 2012 : Coupled Dynamic Analysis FPSO / Mooring / Risers
 
SUC Brasil 2012 : Coupled Analysis of Hose Loadings in a Tandem Offloading Op...
SUC Brasil 2012 : Coupled Analysis of Hose Loadings in a Tandem Offloading Op...SUC Brasil 2012 : Coupled Analysis of Hose Loadings in a Tandem Offloading Op...
SUC Brasil 2012 : Coupled Analysis of Hose Loadings in a Tandem Offloading Op...
 
SUC Brasil 2012 : Next Generation Hydrod and Recent Development in Hydrod
SUC Brasil 2012 : Next Generation Hydrod and Recent Development in HydrodSUC Brasil 2012 : Next Generation Hydrod and Recent Development in Hydrod
SUC Brasil 2012 : Next Generation Hydrod and Recent Development in Hydrod
 
Apresentação Conjunta DNV-DNVS
Apresentação Conjunta DNV-DNVSApresentação Conjunta DNV-DNVS
Apresentação Conjunta DNV-DNVS
 
Shaft Alignment and Whirling Vibration
Shaft Alignment and Whirling VibrationShaft Alignment and Whirling Vibration
Shaft Alignment and Whirling Vibration
 
Shaft Lateral Analysis Overview
Shaft Lateral Analysis OverviewShaft Lateral Analysis Overview
Shaft Lateral Analysis Overview
 
Sesam : Ferramentas de Análise de Pipelines e Flowlines
Sesam : Ferramentas de Análise de Pipelines e FlowlinesSesam : Ferramentas de Análise de Pipelines e Flowlines
Sesam : Ferramentas de Análise de Pipelines e Flowlines
 
Umbilicals Design with UmbiliCAD and Helica
Umbilicals Design with UmbiliCAD and HelicaUmbilicals Design with UmbiliCAD and Helica
Umbilicals Design with UmbiliCAD and Helica
 
MIMOSA - Análise de Sistemas de Ancoragem
MIMOSA - Análise de Sistemas de AncoragemMIMOSA - Análise de Sistemas de Ancoragem
MIMOSA - Análise de Sistemas de Ancoragem
 
Apresentação Sesam Estruturas Fixas
Apresentação Sesam Estruturas FixasApresentação Sesam Estruturas Fixas
Apresentação Sesam Estruturas Fixas
 

Último

Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsMaria Levchenko
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure servicePooja Nehwal
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptxHampshireHUG
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationSafe Software
 
Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Paola De la Torre
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsMemoori
 
Key Features Of Token Development (1).pptx
Key  Features Of Token  Development (1).pptxKey  Features Of Token  Development (1).pptx
Key Features Of Token Development (1).pptxLBM Solutions
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...HostedbyConfluent
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024Scott Keck-Warren
 
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024BookNet Canada
 
Azure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAzure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAndikSusilo4
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024Rafal Los
 
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphSIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphNeo4j
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking MenDelhi Call girls
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticscarlostorres15106
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking MenDelhi Call girls
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationRadu Cotescu
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machinePadma Pradeep
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Allon Mureinik
 

Último (20)

Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial Buildings
 
Key Features Of Token Development (1).pptx
Key  Features Of Token  Development (1).pptxKey  Features Of Token  Development (1).pptx
Key Features Of Token Development (1).pptx
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024
 
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
 
Azure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAzure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & Application
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphSIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machine
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)
 

FPSO Requirements

  • 1. FPSO’s & DNV EOCBR 514 – Newbuildings and Conversions Marcelo Spotorno Rio de Janeiro, 16.07.2009
  • 2. More than 140 years of managing risk  Det Norske Veritas (DNV) was established in 1864 in Norway  The main scope of work was to identify, assess and manage risk – initially for maritime insurance companies © Det Norske Veritas AS. All rights reserved 28 September 2011 Slide 2
  • 3. 300 offices in 100 countries Head office Local offices © Det Norske Veritas AS. All rights reserved 28 September 2011 Slide 3
  • 4. Our people – a vital resource  People are the core of DNV  9000 employees  97 nationalities © Det Norske Veritas AS. All rights reserved 28 September 2011 Slide 4
  • 5. FPSO – Market share Vietnam 1% Rina Unknown CCS 1% 6% 1% ABS 35 % BV 4% LR 12 % DNV 40 % Source: - Mobile Production systems of the World, 7th Edition, 2007/2008, Clarkson Research Services Limited - Floating Production Systems - assessment of the outlook for FPSO vessels, production semis, TLPs and Spars, November 2007, International Maritime Associates Inc. © Det Norske Veritas AS. All rights reserved 28 September 2011 Slide 5
  • 6. Petrojarl I  the world’s first FPSO built for harsh environment(1986) © Det Norske Veritas AS. All rights reserved 28 September 2011 Slide 6
  • 7. First FPSO GoM  BW Yùum K’ak’Náab © Det Norske Veritas AS. All rights reserved 28 September 2011 Slide 7
  • 8. Cascade Chinook / First FPSO for US GoM Chinook Cascade  First FPSO for US GoM © Det Norske Veritas AS. All rights reserved 28 September 2011 Slide 8
  • 9. FPSOs/FSOs Newbuildings & Conversions BP Skarv-Idun Korea-Samsumg Newbuilding BW Pioneer - Cascade/Chinook Singapore Conversion Nexus 01 Korea-Samsumg Newbuilding Nexus 02 Korea-Samsumg Newbuilding P-58 - Baleia Azul Singapore Conversion Sevan 300 No. 04 China-Hantong Newbuilding Sevan 300 No. 05 China-Hantong Newbuilding Ichtys FPSO - Newbuilding FSO Rita Dubai Conversion Dynamic Producer Singapore Conversion Knock Dee FSO Dubai Conversion Deep Producer Singapore Conversion © Det Norske Veritas AS. All rights reserved 28 September 2011 Slide 9
  • 10. ”DNV classed units” around the world North Sea: FPSO: 18 Canada: FPSO: 1 North Africa: FPSO: 2 Gulf of Mexico: FPSO: 2 West Africa: Asia and Australia: FPSO: 12 FPSO: 15 Brazil: FPSO: 3 © Det Norske Veritas AS. All rights reserved 28 September 2011 Slide 10
  • 11. FPSO’s – DNV fleet in Brazil  SSP300 - Sevan Piranema  Petrojarl Cidade de Rio das Ostras  BW Cidade de São Vicente © Det Norske Veritas AS. All rights reserved 28 September 2011 Slide 11
  • 12. DNV Offshore Standards © Det Norske Veritas AS. All rights reserved 28 September 2011 Slide 12
  • 13. Benign Waters  DNV OS-C-102 - Structural Design of Offshore Ships - World-wide operation - Benign waters - Environments at which the required to hull girder capacity calculated according to the LRFD method is less than the minimum section modulus according to the ‘Main Class Requirements’. © Det Norske Veritas AS. All rights reserved 28 September 2011 Slide 13
  • 14. Benign Waters  Alternative design procedures - Alternative 1 - Ship Rules - The hull scantlings are based on the “main class requirements”.No direct calculations of wave bending moments and shear forces are required. - Alternative 2 - LRFD method - The hull is designed according to the principles given in Ch.1. The midship section modulus may be less than the ”main class requirements”. When design Alternative 2, LRFD method, is applied, the minimum midship section modulus according to the ”main class requirements” may be reduced by maximum 25%. © Det Norske Veritas AS. All rights reserved 28 September 2011 Slide 14
  • 15. P-58 - Nauticus Construction Default Innerstructure Outershell Thickness map Material map © Det Norske Veritas AS. All rights reserved 28 September 2011 Slide 15
  • 16. Information – dimensions and steel grades  You get an over-view from colour display and printed numbers.  Gives you access to the dimensions and steel grades of plates, stiffeners and girders  Byclicking the structural parts you get more details © Det Norske Veritas AS. All rights reserved 28 September 2011 Slide 16
  • 17. Maintenance – Steel renewal / weight Marking up all plates and/or stiffeners within a 3D zone by Plates and stiffeners can be marked defining and extruding a polygon up independently by using separate zones © Det Norske Veritas AS. All rights reserved 28 September 2011 Slide 17
  • 18. Maintenance – Coating Area Calculations Marking up single structures for Marking up all structures for partial coating: top, one side (gray on complete or part of the compartment aft side means not coated) © Det Norske Veritas AS. All rights reserved 28 September 2011 Slide 18
  • 19. Maintenance – Docking specifications  Planning and cost control prior/during a docking of a vessel.  Specification or for verification purposes of the figures given by the ship repair yard. © Det Norske Veritas AS. All rights reserved 28 September 2011 Slide 19
  • 20. Maintenance – Emergency Repairs  Facilitates the documentation of damage: - Location - Extent - Type of structure  Noneed for long and complex descriptions.  Enables overview and control the expenses. © Det Norske Veritas AS. All rights reserved 28 September 2011 Slide 20
  • 21. Monitoring - Coating Monitoring Tool  The Nauticus Coating Monitoring Tool takes advantage of 3D technology to visualise the coating status and calculate re-coating areas. The tool also supports a structured recording of coating inspection results referring to pre-defined cells/bays of the ballast tanks. Finally, it assists you in preparing the re-coating specification and estimates the costs.  When tool is used one has stop to take a risk of unpredicted situations in respect to mintenance or failure. © Det Norske Veritas AS. All rights reserved 28 September 2011 Slide 21
  • 22. Monitoring – UTM This improves UTM measurement support improved Thickness process: shorter time, quality and communication, input to maintenance The Nauticus UTM Tool improves planning, execution and strategy: of ultrasonic thicknesslower cost evaluation better control and measurements. © Det Norske Veritas AS. All rights reserved 28 September 2011 Slide 22
  • 23. Management – Maintenance Strategy Set of UTM readings The curve shows tendency from previous years of steel diminution within the years and can be used for prognosis Trend Curve 25% t dim Thickness Diminution 20% t sub t min 15% 10% 5% 0% 1983 1988 1993 1998 2003 2008 2013 Years Coating Condition Status © Det Norske Veritas AS. All rights reserved 28 September 2011 Slide 23
  • 24. Training – Naming of Structure © Det Norske Veritas AS. All rights reserved 28 September 2011 Slide 24
  • 25. Training – Areas of Attention “Risk Based Inspection” with Focus on ”Critical Areas” Inspection of upper hopper knuckle especially in way of trv. web frames Inspection of lower hopper knuckle especially in way of trv. web frames © Det Norske Veritas AS. All rights reserved 28 September 2011 Slide 25
  • 26. © Det Norske Veritas AS. All rights reserved 28 September 2011 Slide 26