UNIT I – RAILWAY PLANNING AND DESIGN
1. Mention some advantages of railways.
   The various advantages of railways may be as follows:
       a) It aids in the mass migration of people.
       b) Trade development has increased ten folds after the growth of railways.
       c) Land values have increased due to increased industrial growth.
       d) Speedy distribution of finished product is achieved through railways.

2. What is meant by zonal railways?
   The entire railway station has been divided into nine zonal railways having different territorial
   jurisdictions which are responsible for all management and planning of works.

3. What is COFMOW and what are its responsibilities?
   The Central Organization for Modernization of Workshop (COFMOW) is a specialized agency to
   implement the various workshop modernization programs of Indian Railways. They are
   responsible for the modernization of these workshops with the assistance of World Bank.

4. What do you mean by TACV or MAGLEV?
   All advances in the development of railways have been to achieve the speed of Airways and
   safety of railways at its best. This objective could be achieved by the usage of Track Air Cushion
   Vehicles (TACV) or Magnetic Levitation Vehicles (MAGLEV) on purpose made special Railway
   tracks using special locomotives and coaches to achieve a maximum speed of 250 km/hr.

5. What do you understand by the term “Buckling of rails”?
   The railway track gets out of the original position due to the buckling if the expansion of rails is
   prevented during hot weather. Such an action is known as “buckling of rails”.

6. What do you understand by the term “Ballast”?
   Ballast is the granular material packed under and around the sleeper to transfer loads from
   sleeper to ballast. It helps in providing elasticity to the truck.

7. What are the different types of gauges?
   The different types of gauges are as follows:

        a)   Broad Gauge (B.G.) – 1.67 mtrs.
        b)   Meter Gauge (M.G.) – 1.00 mtrs.
        c)   Narrow Gauge (N.G.) – 0.762 mtrs.
        d)   Light Gauge or Freeder Track Gauge –0.610 mtrs.

8. Enumerate the various factors that govern the selection of various types of gauges.
   There are numerous factors that are dependant in the selection of different gauges. However,
   few of them are mentioned below:
       a) Cost of Construction
       b) Volume and nature of traffic
       c) Development of the areas
       d) Physical features of the country
e) Speed of movement

9. What are the advantages of “Coning of wheels”?
   The various advantages of coning of wheels are:
       a) To reduce the wear and tear of the wheel flanges and rails due to rubbing action of
           flanges with the inside faces of the rail head.
       b) To provide a possibility of lateral movement of axil to the wheels.
       c) To restrict the wheels from slipping.

10. Define “Track modulus”.
    Track modulus is an index for stiffness of track. It is defined as load per unit length of the rail
    required to produce a unit depression in the track.

11. List down the various causes of “Track stresses”.
    Stresses in the railway track are produced due to many causes as listed below:
         a) Wheel loads
         b) Dynamic effect of wheel loads
         c) Hammer blow
         d) Horizontal thrust

12. What do you understand by the term “Grade compensation”?
    The reduction in the grading provided at an intersection of curve and gradiant is known as grade
    compensation on curves.

13. What is a “Sleeper”?
    A sleeper is a member laid transversely under the rails which are meant to support the rails over
    them and transfer the load from rails to ballast.

14. What are the functions of a “sleeper”?
    Sleepers perform the following functions:
        a) To distribute the load from the rails to the index area of ballast underlying it or to the
            girders in case of bridges.
        b) They add to the lateral and longitudinal stability of the permanent track to support the
            rails at a proper level in straight tracks and at proper super elevation on curves.
        c) To hold the rails to correct gauge.
        d) To act as an elastic medium in between the ballast and rails to absorb the vibrations of
            moving loads.

15. What are the different types of sleepers?
    Sleepers are classified into the following categories:
       i.   Wooden sleepers
      ii.   Metal sleepers
a) Cast Iron Sleepers
            b) Steel sleepers

     iii.   Concrete Sleepers
            a) Reinforced Concrete sleepers
            b) Pre-stressed Concrete Sleepers

16. What do you understand by the term “Fish Plates” and what are its uses?
    Fish plates are used in rail joints to maintain the continuity of rails and to permit any expansion
    or contraction of the rail due to thermal variations. They maintain the correct alignment of the
    line both horizontally and vertically.

17. What are the different types of “Ballast”?
    The different materials that are used vary from broken stone to sometimes earth. A few
    commonly used types of ballast are the following:
       a) Broken stone
       b) Gravel or shingles
       c) Ashes or cinders
       d) Moorum
       e) Blast furnace slag
       f) Kankar

18. What are the objectives of “Reconnaissance Survey”?
    The objectives of Reconnaissance Survey are as follows:
        a) To decide maximum grading and curvature for proposed alignment
        b) To locate various control points for getting an idea from where the alignment should
           pass and where the alignment should not.
        c) To have an idea about possible alternative alignments
        d) To prepare rough estimates for different proposed alignment to know most economical,
           efficient and safe alignment.

19. What are the instruments used in preliminary survey?
    The various instruments used in preliminary survey are:
        a) Theodolite - for traversing
        b) Tacheometer – for plotting main features
        c) Dumpy level – for drawing the longitudinal cross-sections
        d) Plain Table – for plotting interior details
        e) Prismatic Compass – for magnetic bearings of routes and main points.



20. What do you mean by “Transitional Curve”?
Transitional curve is defined as a curve of parabolic nature which is introduced between a
    straight and circular curve to provide an easy change from tangent to the radius selected for a
    particular curve.




                              UNIT II
      RAILWAY TRACK CONSTRUCTION, MAINTENANCE AND OPERATION

1. What is the necessity of points and crossings?
   The knowledge of points and crossings are important in the following ways:
       a) Points and crossings provide flexibility of movement by connecting one line to another.
       b) They help in imposing restrictions over turn outs which necessarily retard the
           movements.
       c) In regard of safety aspects, points and crossings are weak kinks or points in the track
           which are susceptible to derailments.

2. List down the different types of crossings.
   Crossings may be classified as below:
        a) V-Crossing
        b) Diamond Crossing
        c) Square Crossing
        d) Spring Crossing
        e) Ramped Crossing

3. What are the component parts of crossing?
     a) Chairs at crossing toe and heel
     b) Wing Rails
     c) Check Rails
     d) Pointed Splice Rails
     e) Vee Piece

4. List down the characteristics of Crossing.
        a) The assembly of crossing has to be rigid to stand against severe vibrations.
        b) The vear on parts of wing rails opposite the nose and also of nose itself must be
           protected.



5. What is flange way depth?
Flange way depth is the vertical distance between the top surface of the stock rail to the top
    surface of the heel-block used between the stock rail and check rail.

6. List down the necessities of points and crossings?
        a) Points and crossings provide flexibility of movement by connecting one line to another.
        b) They also help for imposing restrictions over turnouts which necessarily retard the
           movements.

7. List down the different types of track junctions.
   The important track junctions commonly employed are:
        a) Symmetrical split
        b) Tandem
        c) Diamond Crossing
        d) Single Slip and Double Slip
        e) Scissor Cross over
        f) Ladder tracks

8. Define Platform.
   Raised level surface from where either passengers board and alight from trains or loading and
   unloading of goods is done is commonly known as platform. They are of two types, namely,
   passenger platforms and goods platforms.

9. What do you understand by the term Stations yards?
   Yard is defined as a system of tracks laid usually on a level within defined limits for receiving,
   storing, sorting, making up new trains and dispatch of vehicles.

10. Classify the types of yards.
        a) Passenger Bogie yards
        b) Goods yards
        c) Marshalling yards
        d) Locomotive yards

11. What are the objectives of signaling?
    The various objectives of providing and operating signals are as below:
        a) To ensure safety between two or more trains which cross of approach each other’s
            path.
        b) To provide facilities for maximum utitlity of the tracks.
        c) To guide the trains movements during maintenance and rpair of tracks.
        d) To safeguard the trains at converging junctions and give directional indications at
            diverging junctions.

12. What are the types of signals based on the various categories?
i.    Operating characteristics
                a) Fog or audible signals
                b) Visual indication signals
      ii.   Functional characteristics
                a) Shunting signals
                b) Warner signals
                c) Semaphore type signals
     iii.   Locational characteristics
                a) Quoter signals (reception)
                b) Advanced Starter (departure)
     iv.    Special characteristics
                a) Point indicators
                b) Modified lower quadrant semaphore signals

13. What are the various sources of moisture in a railway track?
    The various sources of moisture affecting a railway track are:
        a) Surface water due to rain, dew or snow.
        b) Hydroscopic water or Held water.
        c) Seepage water
        d) Moisture by capillary action in sub grade

14. What are the requirements of a track drainage system?
      a) The track alignment should be made to rest on pervious naturally drained soils.
      b) The highest level of water table should be much below the level of sub grade.
      c) Sub surface water should be efficiently drained off by the sub surface drainage system.
      d) The surface water from adjoining land could be prevented from entering the track
           formation.

15. What are the advantages of good maintenance of railway track?
    The life of both track and rolling stock increases by proper maintenance. A well maintained track
    imparts smooth quality riding surface for vehicles which results in comfort to passengers and
    safety to goods.

16. What is meant by “Packing”?
    Packing is the method of forcing stone ballast below the sleepers by ramming with a beater cum
    pick-axe.

17. Define “Loops”.
    When a branch line terminates from a previously terminated main line, it is called loop. They are
    of three types: Split turnout, Trailing turnout, Straight and loop.

18. Enumerate the necessities of “Curves”.
a) To bypass natural or artificial obstacles
        b) To provide easier gradiants by diversions from the straight route.

19. What are the three methods by which safe speed can be calculated?
      a) Martin’s formula
      b) Super elevation formula
      c) Cant formula

20. What do you understand by the term “Ruling gradiant”?
    Ruling gradiant is defined as the gradiant which determines maximum load that the engine can
    haul on the section.


                                      UNIT III
                           AIRPORT PLANNING AND DESIGN

1. What are the advantages of Air transport?
   The advantages of air transport are:
       a) It reduces travel time considerably.
       b) It aims in the comfortable travel of passengers from point to point.

2. What are the limitations of Air transport?
   The limitations of air transport are:
       a) They are quite expensive
       b) They cause considerable amount of environmental damage

3. What do you mean by “Air Traffic Potential”?
   Air traffic potential refers to the maximum amount on aircrafts that the specified air space can
   hold within its boundaries.

4. What do you understand by “Wind Rose Diagram”?
   Wind Rose Diagram refers to the descriptive illustrative realization of the directional attitude of
   wind flow with respect to the geographical position at a specified time frame.

5. What do you understand by the term “Minimum Separation Distance”?
   Minimum Separation distance refers to the least distance that is to be maintained by two
   successive aircrafts during their taxing along the apron or along the taxi way.




6. What do you understand by the term “Design Speed”?
Design speed is the speed estimated by the planning and design engineers for a specified airport
    runway based on the type of airports and the aircrafts landing and taking off from them.

7. Define “Airport Zoning”.
   Airport zoning is the process of dividing the whole airport into several zones as clear zone,
   approach zone, buffer zone, turning zone for easy navigation and control and administration
   activities including maintenance.

8. Define “Approach Zone”.
   Approach Zone is defined as the specific zone in the airport which provides indication to the
   pilot of the approach of the landing strip.

9. What do you understand by the term “Airport Drainage”?
   Airport Drainage is the process of keeping the runway dry and accessible for aircrafts for the
   safe landing and takeoff of aircrafts to and from the airports.

10. What is meant by “clearance over highways and railways”?
    The minimum distance to be maintained vertically above the closest railway and highway zones
    to eradicate disturbance that maybe caused by the jet explosion during the flight of an aircraft is
    called its clearance over highways and railways.


        Unit IV – AIRPORT LAYOUTS, VISUAL AIDS AND AIR TRAFFIC
                               CONTROL

1. What are the objectives of master plan according to FAA?
   The objectives according to FAA are:
   a) To provide an effective graphical presentation of the ultimate development of the airport
   b) To describe various concepts and alternatives which were considered in the establishment of
   the proposed plan.
   c) To present the backup of information and data which were essential to the development of the
   master plan.
   d) To establish a schedule of priorities and phasing for the various improvements proposed in the
   plan.

2. What does the term ‘ Terminal area” mean?
   The terminal area refers to the portion of an airport other than the landing area. It serves as the
   focal point for activities on the airport which includes terminal and operational buildings, vehicle
   parking area and aircraft service hangars.

3. List out the purpose of a building area in an airport.
    The purpose for building area are:
    a) To provide shelter and space for surface activities.
b) To accommodate the basic facilities as toilet, telephone and medical services.
  c) To establish space for cargo handling and processing.
  d) To provide an enquiry counter to reach to the needs of passengers.

4. Enumerate the requirements of site selection or the factors affecting site selection.
  The suitability of site selection for terminal building is processed in accordance to the following:
  a) Sufficient area for roadways
  b) Central location with respect to runway
  c) Proximity and ease of installation of utilities
  d) Convenient access to the main highway.

5. List out the factors upon which the size of an apron is decided.
  The paved area for parking of aircrafts, loading and unloading of passengers and cargo is an
  apron and its size is dependent on:
  a) Aircraft parking systems
  b) Size of the loading are required for a type of aircraft or the gate position.
  c) Number of gate positions

6. What are the different types of aircraft parking systems?
  Aircrafts are grouped adjacent to terminal buildings in various patters as mentioned below:
  a) Frontal system
  b) Open apron system
  c) Finger system
  d) Satellite system

7. What do you mean by Blast Fences?
  Blast fences are used to deflect and dissipate the energy of high velocity jet exhaust so as to
  protect the passengers from the discomfort caused by the heat.

8. Classify the various types of runway markingbased on their utility.
  The various markings are divided as follows:
  a) Runway marking
  Taxiway marking
  Runway and taxiway shoulder marking
  d) Apron marking
  e) Wind direction indicator
  f) Landing direction indicator

9. What are different types of airport lighting available?
  a) Boundary lighting
  b) Code beacon
  c) Rotating beacon
  d) Apron and hangar lighting
  e) Approach lighting
  f) Threshold lighting
10. Why is threshold lighting so important in respect to landing?
   The identification of runway threshold lighting has an important bearing on the pilot’s decision
   whether to land or not. Thereby the area near the runway threshold is given special lighting
   considerations.

11. Bring out the need of air traffic control.
    The Air traffic Control (ATC) is primarily established to ensure a safe, economic and convenient
    movement of the aircraft flight from one airport to another during the actions of takeoff till
    landing at the desired port.

12. How is the wind indicator helpful in air traffic?
    The wind indicator is a wind cone placed at the center of the segmented circle (airport) marker
    which aids the pilot in locating the airport and the direction of wind.


13. What is a hangar and what is the main function of the same?
    Hangar is an enclosure for servicing, overhauling and performing repairs of the aircrafts located
    within the vicinity of a building area. These are usually constructed of steel frames and covered
    with galvanized iron sheets.

14. State the requirements of selecting a hangar site.
    The requirements of suitable hangar site are:
    a) The site should be such that there is a convenient road access to it from the site to the aprons
    and terminal building.
    b) Favorable topography providing good natural drainage.
    c) Reasonable proximity to the loading apron.
    d) Sufficient area to provide car parking facilities for working personnel.

15. What are the typical airport layouts that are practiced nowadays?
    The following are the basic airport layouts :
    a) Two intersecting Runway layout
    b) Non-intersecting runways layout
    c) Three intersecting runways layout
    d) Tangential runway layout

16. Enumerate the basic characteristics that a good airfield should possess.
    a) Sufficient terminal building facilities
    b) Lowest possible cost of construction
    c) Landing, taxiing and taking off a independent operations without interference.
    d) Excellent control tower visibility,

17. Write down the design considerations applied to taxiway lighting.
    The design considerations that applies to taxiway lighting are mentioned below:
    a) Crossing of taxiway and the runway should be clearly identified.
    b) Effective and simple presentation of guidance elements to permit rapid aircraft movement
    between runway and apron should be preferred.
    c) There should be adequate guidance along the taxiway.
d) Taxiway should be clearly identified so that they cannot be confused with the runways.

18. Define runway capacity and feature the factors affecting them.
    Runway capacity is the ability of a runway system to accommodate aircraft landings and take-
    offs. The factors affecting them are:
    a) Air traffic control
    b) Characteristics of demand
    c) Environmental factors
    d) Layout and design of the runway system

19. List out the points to be remembered for an efficient airport vehicular circulation and parking
system.
    a) Ease of passenger loading and unloading at the terminal building
    b) One way traffic wherever possible
    c) A minimum of driveway intersection
    d) Adequate driveway width to permit overtaking
    e) Sufficient and clearly defined parking and circulation routes.

20. Mention the various parking configurations of Aircrafts.
    The various parking configurations that are used in the present days are as follows:
    a) Nose-in
    b) Angle nose-in
    c) Nose-out
    d) Angle Nose-out
    e) Parallel


                           UNIT V
      HARBOUR ENGINEERING AND OTHER MODES OF TRANSPORT

1. Define 12arbor.
   Harbour is a sheltered area of sea where facilities for loading and unloading of cargo and
   passengers are provided.

2. Classify the different types of harbors.
       a) Natural harbor
       b) Semi-natural harbor
       c) Artificial harbor

3. What are the constituents of harbor?
     a) Entrance channel
     b) Approach channel
     c) Birthing Basin
     d) Breakwater
4. What are the requirements of a good port?
     a) It should be a place of defence and for resisting the sea borne invasion.
     b) It should command extensive and valuable trade
     c) The hinterland should be fertile with a good density of population.
     d) It should provide maximum facilities to all visiting ships.

5. What do you understand by the term “Breakwater”?
   Breakwaters are structures constructed to enclose the harbors to protect them from the effect
   of wind generated waves by reflecting and dissipating their force or energy.

6. What are the types of breakwaters?
     a) Vertical wall breakwater
     b) Heap breakwater
     c) Mound with super structure

7. Define dock.
   Docks are defined as enclosed areas for berthing the ships to keep them afloat at uniform level
   to facilitate loading and unloading of cargo.

8. What are the types of docks?
     a) Wet docks – used for berthing of vessels to facilitate loading and unloading of
          passengers and cargoes.
     b) Dry or repair docks – are used for repair of ships

9. What is a cable?
   A cable is a floating buoy consisting of a pendant which consists of a link chain (open) fitted with
   a swivel in the upper half.

10. What is apron?
    Apron is an open space used to expedite the unloading and loading of cargoes in vessels
    immediately in front of the berth.

11. What are warehouses?
    At times the port users need storage facilities for much longer periods than that provided by
    transit sheds. This has brought to the construction of storage facilities known as storage go
    downs or warehouses.

12. List out the types of dredging devices.
         a) Dipper dredger
         b) Grapple dredger
         c) Continuous bucket elevator or ladder dredger
13. What are locks and provide their components?
    Locks are a device used to connect a dock with the sea or river at different levels. The
    components of these are:
    a) Steel lock gates
    b) Granite sills
    c) Culverts
    d) Heavy masonry retaining walls
    e) Heavy plumbing plant

14. What are wharves?
    The platforms or loading places in the form of walls built near shores to berth are known as
    wharves. In other words they may be defined as a wall erected along a shore or bank to berth
    vessels for loading and unloading cargo.

15. What do you understand by the term ‘Dolphin’?
    A structure constructed at the entrance of a locked basin or alongside a pier or wharf to absorb
    the impact force of the vessel or to provide mooring facility is termed as dolphin due to their
    form of a cluster of spaced piles.

16. Site the difference between transit sheds and apron.
    Transit sheds are a temporary storage facility for goods in transit from vessel to consignee or
    vice-versa. Apron is an open space left immediately in front of the berth for utilization in the
    installation of mechanical devices as cranes.

17. What are the requirements of a signal?
    The basic requirements of a marine signal are:
    a) It should be positively recognizable and should not vary in character.
    b) It should be simple to identify and should make its meaning clear at a glance.
    c) It should permit time for easy response.
    d) It should be clearly visible from a long distance.

18. List out the purpose of construction of shore protection works.
    Shore protection works are usually provided to protect exposed beach line.However the
    following purposes are also intended:
    a) To stabilize the existing beach.
    b) To restore the eroded beach.
    c) To create and stabilize the artificial beaches.
    d) To protect an exposed beach line.

19. Mention the various shore protection works.
    The following shore protection works are usually adopted:
    a) Sea walls, Bulk heads and revetments
b) Protective beaches
    c) Sand dunes
    d) Groynes
    e) Off shore break waters

20. What are moorings?
    These are devices which are provided where anchorage water is limited. It is absolutely
    necessary to have some moorings n all harbours for vessels to discharge its passengers and
    cargo to barges for taking the same right upto coast.



                                                 6 MARKS

                       UNIT I – RAILWAY PLANNING AND DESIGN

1. Write a short note on the engineering surveys for track alignment.
   Railway project consists four different surveys – Traffic survey – Reconnaissance survey –
   Preliminary survey – Detailed survey – objects of each of them – factors to be considered

2. Define a permanent way and site the various requirements of an ideal permanent way.
   Definition of permanent way – requirements of an ideal permanent way ( any 6) – the typical
   cross section of the permanent way on embankment to be drawn.

3. What are the different gauge types used by the Indian Railways and write down the selection of
gauge factors.
   Definition of gauge – different types of gauge with their specific dimensions ( BG, MG, NG, LG) –
   factors affecting the selection of a particular gauge ( any 4 )

4. The wheels are coned to keep it in the central position. Comment on the statement.
   Definition of coning – advantage of coning – theory of coning – include a figure to depict the
   process.

5. What is meant by creep? Discuss on the theories propounded to explain probable effects of
creep.
   The longitudinal movement of rails with respect to sleepers in track – theories of creep ( Wave
   theory, Percussion theory and Drag Theory) – (any 4) effects of creep

6. What are the function of sleepers and the requirements of a good one?
   Sleepers are members laid transverse to rails on which rails are supported to transfer loads to the
   ballast – function of sleepers ( any 6) – requirements ( Any 6)

7. Shed some light on the functions and requirements of a good ballast.
    Ballast – granular material packed below and around sleepers to transmit load from sleepers to
    formation to allow drainage of track – function of ballast (Any 4) – requirements of ballast (Any 4)
8. Write a short note on the types of ballast.
   Ballast materials used – explain in brief any 6 of the following – Broken stones – Gravel , River
   Pebbles or Shingle – Ashes or Cinders – Sand – Moorum – Kankar – Brick Ballast – Blast Furnace
   Slag – Selected Earth

9. What are formations and enumerate the various function of subgrade or formation.
   Subgrade is the naturally occurring soil which is prepared to receive the ballast and other railway
   structures for the track – Formation is a prepares surface for the purpose of laying track –
   Function of sub grade or formation ( Any 4 )

10. Define the terms : (i) Super-elevation (ii) Negative super elevation (iii) Cant deficiency
     The raised elevation of the outer rail with respect to the inner rail – The variation of the
     elevation of the branch line to the main line –the difference between actual cant provided to
     the equilibrium cant ( all the definitions to be elaborately explained with suitable values to be
     offered wherever seemed necessary)

11. What are curves? Shed some light on the necessity and the effects of the curvature.
    The curvature provided at certain geographical conditions to enable a smooth transfer of trains
    – necessities to be furnished with the factors( any 4) - effects ( lateral bending of rails due to
    rigid wheel base , extra vertical load on the inner or outer rail based on the superelevation and
    speed of vehicle)

12. Write a short note on the widening of gauge on curves.
    Provision to avoid the striking of outer wheel against outer rail and the inner wheel to the inner
    is called widening of gauge. – lateral play may lead to derailment – extra gauge width formula
    and explain the terms.

UNIT II – RAILWAY TRACK CONSTRUCTION, MAINTENANCE AND OPERATION
1. Define points and crossings with their necessity to be adopted.
   These are used to direct trains to different routes either parallel or diverging to make way for
   movement from one route to another but also helps in marshaling and shunting work at station
   yards – necessity of points and crossings ( Any 4 )

2. Write a short note on the various types of crossings.
   Crossings are classified on two categories - Basis of shape of crossing – basis of assembly of
   crossing – briefly explain about all with suitable sketches wherever necessary.

3. What are track junctions and briefly mention the various types of track junctions?
   Track junctions are combinations of points and crossings with curves and straights to transfer the
trains from one track to another or to enable trains to cross over other tracks – mention the types of
track junctions ( Any 5 ) with suitable sketches.

4. Describe the factors that influence the selection of site for a railway station. How the railway
stations are classified?
   Factors affecting the site selection (explain any 4 from following Acquisition of land , Proximity to
town or village, Nature of land area, Approach roads to station site, station site alignment, Site
drainage, Station amenities, type of station and yard, role of authorities) – operational classification
– functional classification

5. Explain briefly about the tractive resistances.
The resistance to movement of trains on the track is known as resistance or track resistance – four
categories ( Train resistance , Resistance due to profile, resistances due to starting and acceleration,
wind resistance).

                       UNIT III – AIRPORT PLANNING AND DESIGN
1. Point out the important parts of an aero plane and discuss it in brief.
   With the help of a figure explaining the component parts of an aeroplane – Engine –Flaps –
Fuselage – Propeller – Three controls – Tricycle undercarriage – Wings

2. What are the factors that influence the selection of a location for an airport?
   Necessary data regarding the airport is collected from previous surveys conducted – factors on
which site selection is performed ( Any 8) – explain any 6 of them in detail.

3. What are zoning laws and briefly put your understanding of the same?
   Definition of zoning laws ( Height zoning , land-use zoning) – factors – legal interests – Nature of
ordinance – zoning map

4. What is meant by basic runway length and the three cases associated with them?
    Assumptions in runway length ( Any 4) – Three cases ( Normal landing, Normal Take off, Stepping
in emergency) – explain briefly each case with suitable sketches.

5. What are the corrections to basic runway length?
   Corrections are applied to get the actual length of runway – following corrections are considered
– correction for elevation – correction for gradient – correction for temperature – Airport reference
temperature formula – explain the three briefly with sufficient examples.

    UNIT IV – AIRPORT LAYOUTS, VISUAL AIDS AND AIR TRAFFIC CONTROL
1. Discuss briefly on the design objectives and space requirements in an airport.
   Design objectives – classified into four categories ( airline objectives – airport management
objectives – community objectives – Passengers’ objectives ) – space requirements as per FAA – all
the points to be discussed in brief with suitable examples wherever possible.

2. The type of aircraft parking is very crucial in the planning of an airport. Substantiate the
statement with suitable patterns of aircraft parking.
   The types of aircraft parking – five categories – nose in – nose out – angle nose in – angle nose
out – parallel (explain the types of parking configurations with neat sketches).

3. Explain on the systems of aircraft parking practiced these days in the airports of the world.
   Based on the horizontal terminal concept – various groupings of aircraft can be parked adjacent
to the terminal building – known as parking systems – frontal or linear system – open-apron or
transporter system –pier or finger system – satellite system – explain all with neat sketches
4. List out the aims of airport drainage and the function of airport drainage.
    Adequate drainage required – any 4 points on the aims – any 2 functions of drainage – any 5
special characteristics of airport drainage.

5. Write a short note on the various airport markings.
   Airport markings – guide pilots to the runways – marked with lines and numbers – to recognize
various airport elements – six groups – apron marking – landing direction indicator – runway
marking – shoulder marking – taxiway marking – wind direction indicator.

    UNIT V – HARBOUR ENGINEERING AND OTHER MODES OF TRANSPORT
1. What is a breakwater and explain in brief the various types of breakwaters?
   Protective barrier to enclose harbours to keep the waters undisturbed by the effect of heavy and
strong seas – types – Heap or mound breakwater – mound with superstructure or composite
breakwater – Upright wall breakwater – special breakwater – explain them briefly with their main
constituents and advantage over one another.

2. Pen down the major facilities to be available at a port.
   Facilities to be categorized into two groups – facilities to be provided at land – facilities
connected with basin water ( Entrance facilities, Loading unloading platforms, Turning facilities,
Repairing facilities)

3. What are the advantages and disadvantages of enclosed wet docks?
   Advantages ( uniform water level to be maintained – prevents rubbing of sides of ships against
quays – prevents the constant attention to alternating mooring – effect of storms in outer sea
doesn’t affect the dock) – disadvantages – costly arrangement – locks and lock gates to be provided
– more time for entry and exit of ships.

4. What are the various types of dredging devices available in modern marine engineering?
   Dipper dredge – Grapple dredge – ladder dredge – suction dredge – explain them in brief with
their working principles.

5. What are the moorings? Mention the accessories of fixed and floating types of moorings.
   Moorings are provided at regions where water is insufficient for anchorage – accessories – fixed –
mooring part – bollard – capstan – floating type – buoys – cables – anchors

                                              10 MARKS
                       UNIT I – RAILWAY PLANNING AND DESIGN
1. Railways are the significant and potential means of transporting men and materials over long
distances. Shed some light on the axiom.
   Advantage of railways – political – social – economic – Techno-economical – various types of
trains in India – its influence in the masses of India – modern trends in Indian railways(GIS, GPS,
Remote Sensing).
2. Discuss the various factors concerning the selection of rails. Mention the major defects seen in
rails.
    A rail is designated by its weight per unit length – factors – speed of train – gauge of track – axle
load and nature of traffic - type of rails – spacing of sleepers – maximum permissible wear on top or
rails – corrugated rails – hogged rails – kinks in rails – buckling of rails – damaged rails.

3. Explain in detail the various types of rail joints with neat sketches.
   Rail joints are necessary to hold together the adjoining ends of the rails in the correct position,
both in horizontal and vertical planes – Supported rail joints – Suspended rail joints – Bridge joint –
Base joint – Welded rail joints – Staggered or broken joint – Square or even joint – compromise joint
– Insulated joint – expansion joint- explain each of these with suitable sketches wherever necessary

4. Explain in detail the effects , measurement and prevention of creep.
   Effects of creep – sleepers move out of position – stresses exerted on fish plates and bolts to
cause breaking – points and crossings distorted – difficulty to re-align or fix the removed track –
kinks at joints – forging of ballast – Measurement of creep – creep indicator – diagram – chisel mark
– IR practice – intervals of 3 months – not more than 150mm – prevention of creep – pulling back
the rails – provision of anchors – use steel sleepers.

5. a)Explain the factors that the speed of train isdependent upon. Derive the equations to determine
the safe speeds of trains in the presence and absence of transition curves.
                                                                   M.G. track, the average speed of
different trains is 50 kph and allowable cant deficiency is half that of maximum cant deficiency.
Speed of trains – strength of rails – power of locomotive – safe speed dependent – gauge of track –
radius of curve – distance of resultant of weight of vehicle – amount of superelevation provided –
presence or absence of transition curve.
Martin’s formula – super elevation – length of transition curve – problem –
 i) for MG track 0.8V2 = 9.3 cm
                   R
ii) Max e = 1/10 of gauge = 10cm

iii) Max theoretical cant = Max cant + cant deficiency = 5.1cm
iv) Max speed = 52 kph.

UNIT II – RAILWAY TRACK CONSTRUCTION, MAINTENANCE AND OPERATION
1. What are crossings? What are the characteristics of crossings and various types of crossings?
   Crossings – device through which two flange ways allow the wheels of the flanges to move during
an intersection – requirements- assembly to be rigid – wear or parts of wing rails, opposite nose and
the nose must be protected - crossing body should be long and rigid – nose of crossing should have
some thickness – explain any 2 from both the classifications with neat sketches – Based on shape –
acute angle – obtuse angle – square crossing – based on assembly – spring or movable wing –
ramped crossing

2. Explain in detail the classification and various typed of signals.
   Operating characteristics – detonating – hand signals – fixed signals – functional characteristics –
semaphore type signals – warner signals – shunting signals – colored light signals – locational
characteristics – reception signals – quoter signals – home signals – departure signals – starter –
advance starter – special characteristics – repeater signals – routing signals – calling on signals –
point indicators – modified lower quadrant semaphore signals – miscellaneous signals.
3. Define interlocking and explain the principle of interlocking. Describe the various mechanical
devices used for interlocking.
   Interlocking – technique to ensure that the signal is taken to OFF for route which the signal
controls, is properly set – interlocking principles ( 4 points ) – mechanical devices – Detectors –
stretcher bar – lock plunger – lock bar – tappet locking – slotting of signals – connecting devices such
as rods – cranks – temperature compensators.

4. What is the necessity of relaying a track? Describe the standard method of relaying the track in
India. Discuss the various considerations to be made for replacing a track.
   Necessity – track materials are worn-out – heavier track replacement due to increased traffic –
old materials to be serviced and to be replaced by new materials for mail line – standard method of
relaying track – preliminary work – actual relaying of track – consolidation of relayed track and
removal of released materials – Considerations – traffic to be least affected - length of track to be
easily completed within working hours of a day – rails , sleepers and ballast to be replaces
simultaneously to be economical – super elevation and alignment to be checked on curves –at
points and crossing the set of them are arranged on an elevated platform

5. Explain in detail the tractive resistances. What is hauling capacity? Find out the hauling capacity of
a locomotive with 3 pairs of driving wheels and an axle load of 20 tons. Use 0.2 as coefficient of
frictions.
    Track resistances – train resistances – resistances dependent of speed – resistance independent
of speed – atmospheric resistances – resistance due to track profile – resistance due to gradients –
resistance due to curves – Resistance de to starting and accelerating – Wind resistances – hauling
capacity – product of coeffie=cient of friction and weight on driving wheels – problem – H.C. = coeff
0f friction x weight on driving wheels = 12000kg – hauling capacity should exceed the tractive power
in excess.

                       UNIT III – AIRPORT PLANNING AND DESIGN
1. Explain in detail the airport site selection process and the survey conducted for the same.
   Survey – Traffic survey – approach zone survey – drainage survey – meteorological survey –
natural resources survey – soil survey – topographical survey – any 5 from them – availability of land
for expansion – availability of utilities – development of surrounding areas – economy of
construction – ground accessibility – presence of other airports – regional plan – soil characteristics
– surrounding obstruction – topography – use of airport – any 5 of them .

2. Explain about the zoning laws. Shed some light on clear and turning zones. Mention the
particulars in regional planning.
    Zoning laws – height zoning – land use zoning – legal interests – nature of ordinance – zoning
map – clear zone – innermost portion of approach zone – provided at ends of runways – sketch up
the clear zone – turning zone – area of airport other than the runway – intended for turning
operations of the aircraft – sketch up the turning zone – regional planning – advantages – ( Any 4 ) –
air traffic – existing airports – population – topographical features.
3. Mention the preliminary information required for runway orientation. Describe the procedure
adopted to construct the wind rose.
   Preliminary info – maps of area - records of direction – head wind – during landing – during take-
off – wind rose – cross wind component – Wind coverage – chart representation of wind graphically
– wind rose diagram.

4. Enumerate the factors on which the location of the exit taxiways depends. Why are holding
aprons provided and pen down the points to be taken care during its planning?
   Location of exit taxiways – air traffic control – exit speed – location of runways – number of exits
– pilot variability – topographical features – types of aircraft – weather conditions – holding aprons –
for checking the engine operation prior to take off – points to be noted – configuration – entry of
runway – facility of bypass – holding bays – location – peak demands.

5. What are the principles that govern the design of the exit taxiway connecting runway and parallel
taxiway? Also mention the geometric standards for taxiway.
   Principles – angle of turn – compound curve – exit speed – length L1 and L2 – occupancy time –
shape of taxiway – stopping distance – explain the points in detail – geometric standards – eight
elements – length of taxiway – longitudinal gradient – rate of change of longitudinal gradient – sight
distance – transverse gradient – turning radius – width of safety area – width of taxiway

    UNIT IV – AIRPORT LAYOUTS, VISUAL AIDS AND AIR TRAFFIC CONTROL
1. What are the design objectives of terminal building? Explain the two concepts of planning a
terminal building. Suggest the reasonable requirements for terminal building having peak hour
traffic of 100 passengers.
   Objectives – Airline objectives – airport management objectives – community objectives –
passengers’ objectives – two concepts - Centralized system – Decentralized system – explain with
neat sketches –reasonable requirements to be noted in area needs for 100 passengers peak hour or
in percentage of area occupied by each service.

2. Sketch up the following:
    a) Parallel parking
    b) Open-apron system
    c) Satellite system
    d) Nose hangar
    e) Plan of grouped T-hangars

3. Explain the methods adopted to grant protection from the jet blast.
   Protection from jet blasts – inconvenience to passengers boarding aircraft – airport personnel –
damage to airport equipment – effects to components of airports – holding aprons – taxiways –
runway ends – terminal area – methods – blast fences – erosion control – explain with sketches.

4. Discuss some of the broad principles to be observed with respect to passenger flow in the design
of layout of terminal building.
    Principles – arrival gates – departure gates – baggage delivery – information – movement – to be
explained in view of passenger – an explanation of passenger activities may also be mentioned.
5. Explain in detail the factors affecting the type and intensity of airport lighting. Also mention the
elements of airport lighting.
   Airport lighting – factors – airport classification – amount of traffic – availability of power –
nature of aircraft using the airport – type of night operations planned – type of landing surfaces
provided – weather condition – nine elements – airport beacon – approach lighting – apron and
hangar lighting – boundary lighting – lighting of landing direction indicator – lighting of wind
direction indicator – runway lighting – taxiway lighting – threshold lighting – explain all in brief.

    UNIT V – HARBOUR ENGINEERING AND OTHER MODES OF TRANSPORT
1. How is the classification of harbor done on this basis of location? What are the factors considered
for the design of a harbor.
     Layout of harbor – greatly influenced by location – classification – canal harbor – Lake Harbor –
river or estuary harbor – sea or ocean harbor – factors – site selection – shape of harbor – harbor
depth – marine surveys – hydrographic surveys – topographic surveys – harbor planning.

2. What is a breakwater? How is its alignment decided? Describe design information and
considerations. Mention the forces that act on a breakwater.
    Breakwater – protective barrier constructed to enclose harbors and to keep the harbor waters
undisturbed by strong seas – alignment – straight converging arms – intersection angle should not
exceed 60 degrees – design information – character of coast – coat and availability of materials –
direction and force of winds – nature of foundation – height, force and intensity of waves –
considerations – design to be based on the extreme phenomena – material in foundation should not
scour – forces – hydrostatic force – external force – solvent action of sea water – sea insects .

3. Critically comment on jetties. Describe the several standard types of quay walls and their
construction.
    Jetties – structures in the form of piled projections – built form shore to deep water – comment
on the forces acting – traffic on them – designed standards for the same – natural condition and
constituents –types of quay walls - solid quay walls – dwarf quay walls – timber lattice work – timber
crib quay walls – rubble mound quay walls – explain them with neat sketches

4. Describe the various types of harbor signals. What is a lighthouse and how is it constructed? What
are the basic requirements of a marine signal?
     Types of signals – three categories – light signals ( Light ships, beacons, Buoys) – fog signals
(ordinary bells struck by hand, ordinary bells operated by mechanism, submarine bells struck by
mechanism, whistles or sirens blown by compressed air or stream) – audible signals – Light house –
lofty structure – built from masonry or concrete – constructional practice – requirements –visibility
from long distance – positively recognizable – simple for identification – permit time for easy
response.

5. What are the essential differences between a transit shed and warehouse as regards:
    a) their use
    b) their construction?
             Transit shed – one or two storeys – handling and distribution – incoming and outgoing
cargo requiring protection – sorting of cargo to different consignees – free period to remove
consignment – compensation to be paid for detention –construction requirement – doors to be
provided for ready and rapid opening – construction to be light and fire-resistance – ample lightings
with long skylights – should have modern firefighting arrangements – warehouses – permanent
structures – provided on shore or directly behind transit sheds for longer storage periods – storage
godowns

Mais conteúdo relacionado

Mais procurados

Rail gauges & rail sections Railway Engineering
Rail gauges & rail sections  Railway EngineeringRail gauges & rail sections  Railway Engineering
Rail gauges & rail sections Railway EngineeringLatif Hyder Wadho
 
ALIGNMENT OF RAILWAY LINE |ALIGNMENT OF RAILWAY TRACK |RAILWAY ENGINEERING
ALIGNMENT OF RAILWAY LINE |ALIGNMENT OF RAILWAY TRACK |RAILWAY ENGINEERINGALIGNMENT OF RAILWAY LINE |ALIGNMENT OF RAILWAY TRACK |RAILWAY ENGINEERING
ALIGNMENT OF RAILWAY LINE |ALIGNMENT OF RAILWAY TRACK |RAILWAY ENGINEERINGEduHUBOnline
 
Railway Engineering Introduction
Railway Engineering IntroductionRailway Engineering Introduction
Railway Engineering IntroductionT.Naga Anusha
 
Rail Gauges and Rail standards [Useful for Civil Engineering Students IECT SPPU]
Rail Gauges and Rail standards [Useful for Civil Engineering Students IECT SPPU]Rail Gauges and Rail standards [Useful for Civil Engineering Students IECT SPPU]
Rail Gauges and Rail standards [Useful for Civil Engineering Students IECT SPPU]Tushar Sonawane
 
Railway engineering-jdge@railway.gov.bd
Railway engineering-jdge@railway.gov.bdRailway engineering-jdge@railway.gov.bd
Railway engineering-jdge@railway.gov.bdMd. Sultan Ali
 
Introduction to railway engineering (T.E 2)
Introduction to railway engineering (T.E 2)Introduction to railway engineering (T.E 2)
Introduction to railway engineering (T.E 2)sharda university
 
Civil engineering in indian railways spce
Civil engineering in indian railways spceCivil engineering in indian railways spce
Civil engineering in indian railways spceirkportal
 
Railway engineering By T.Ravi Prakash/Kongu Engineering College
Railway engineering By T.Ravi Prakash/Kongu Engineering CollegeRailway engineering By T.Ravi Prakash/Kongu Engineering College
Railway engineering By T.Ravi Prakash/Kongu Engineering Collegeravicivil
 
Engineering surveys and construction of new lines
Engineering surveys and construction of new linesEngineering surveys and construction of new lines
Engineering surveys and construction of new linesNasir Uddin
 
Railway engineering
Railway engineeringRailway engineering
Railway engineeringjmaghade99
 
Chapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway trackChapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway trackKHUSHBU SHAH
 
Rails, Types, Joints, Creep, Failure of Rails and Welding of Rails
Rails, Types, Joints, Creep, Failure of Rails and Welding of RailsRails, Types, Joints, Creep, Failure of Rails and Welding of Rails
Rails, Types, Joints, Creep, Failure of Rails and Welding of Railssrinivas2036
 
Presentation on indian railway
Presentation on indian railwayPresentation on indian railway
Presentation on indian railwayKhusro_khan
 
Introduction to Railway Engineering
Introduction to Railway EngineeringIntroduction to Railway Engineering
Introduction to Railway EngineeringDavinderpal Singh
 
Construction of a New Railway Track
Construction of a New  Railway TrackConstruction of a New  Railway Track
Construction of a New Railway TrackArbaz Kazi
 
Planning principles of Railways Engineering
Planning principles of Railways EngineeringPlanning principles of Railways Engineering
Planning principles of Railways EngineeringLatif Hyder Wadho
 

Mais procurados (20)

Railway Track Maintenance
Railway Track  MaintenanceRailway Track  Maintenance
Railway Track Maintenance
 
Railway engineering part1
Railway engineering part1Railway engineering part1
Railway engineering part1
 
Rail gauges & rail sections Railway Engineering
Rail gauges & rail sections  Railway EngineeringRail gauges & rail sections  Railway Engineering
Rail gauges & rail sections Railway Engineering
 
ALIGNMENT OF RAILWAY LINE |ALIGNMENT OF RAILWAY TRACK |RAILWAY ENGINEERING
ALIGNMENT OF RAILWAY LINE |ALIGNMENT OF RAILWAY TRACK |RAILWAY ENGINEERINGALIGNMENT OF RAILWAY LINE |ALIGNMENT OF RAILWAY TRACK |RAILWAY ENGINEERING
ALIGNMENT OF RAILWAY LINE |ALIGNMENT OF RAILWAY TRACK |RAILWAY ENGINEERING
 
Railway Engineering Introduction
Railway Engineering IntroductionRailway Engineering Introduction
Railway Engineering Introduction
 
Rail Gauges and Rail standards [Useful for Civil Engineering Students IECT SPPU]
Rail Gauges and Rail standards [Useful for Civil Engineering Students IECT SPPU]Rail Gauges and Rail standards [Useful for Civil Engineering Students IECT SPPU]
Rail Gauges and Rail standards [Useful for Civil Engineering Students IECT SPPU]
 
Railway engineering-jdge@railway.gov.bd
Railway engineering-jdge@railway.gov.bdRailway engineering-jdge@railway.gov.bd
Railway engineering-jdge@railway.gov.bd
 
Introduction to railway engineering (T.E 2)
Introduction to railway engineering (T.E 2)Introduction to railway engineering (T.E 2)
Introduction to railway engineering (T.E 2)
 
Civil engineering in indian railways spce
Civil engineering in indian railways spceCivil engineering in indian railways spce
Civil engineering in indian railways spce
 
Railway engineering By T.Ravi Prakash/Kongu Engineering College
Railway engineering By T.Ravi Prakash/Kongu Engineering CollegeRailway engineering By T.Ravi Prakash/Kongu Engineering College
Railway engineering By T.Ravi Prakash/Kongu Engineering College
 
Engineering surveys and construction of new lines
Engineering surveys and construction of new linesEngineering surveys and construction of new lines
Engineering surveys and construction of new lines
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
 
Railway engineering part2
Railway engineering part2Railway engineering part2
Railway engineering part2
 
Chapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway trackChapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway track
 
Rails, Types, Joints, Creep, Failure of Rails and Welding of Rails
Rails, Types, Joints, Creep, Failure of Rails and Welding of RailsRails, Types, Joints, Creep, Failure of Rails and Welding of Rails
Rails, Types, Joints, Creep, Failure of Rails and Welding of Rails
 
Railway Gauge
Railway GaugeRailway Gauge
Railway Gauge
 
Presentation on indian railway
Presentation on indian railwayPresentation on indian railway
Presentation on indian railway
 
Introduction to Railway Engineering
Introduction to Railway EngineeringIntroduction to Railway Engineering
Introduction to Railway Engineering
 
Construction of a New Railway Track
Construction of a New  Railway TrackConstruction of a New  Railway Track
Construction of a New Railway Track
 
Planning principles of Railways Engineering
Planning principles of Railways EngineeringPlanning principles of Railways Engineering
Planning principles of Railways Engineering
 

Destaque

harbour and dock engineering ppt 01 introduction
harbour and dock engineering ppt 01 introductionharbour and dock engineering ppt 01 introduction
harbour and dock engineering ppt 01 introductionHasna Hassan
 
Port and Harbor Engineering
Port and Harbor EngineeringPort and Harbor Engineering
Port and Harbor EngineeringJerome Jaime
 
Horbour & Dock Engineerin
Horbour & Dock EngineerinHorbour & Dock Engineerin
Horbour & Dock Engineerinjamalkhan619
 
Classification of port and harbour ppt.pptx
Classification of port and harbour ppt.pptxClassification of port and harbour ppt.pptx
Classification of port and harbour ppt.pptxJAYA LAKSHMI ATHRAM
 
Airport planning and Design
Airport planning and DesignAirport planning and Design
Airport planning and Designsrinivas2036
 
Automatic railway level crossing gate & slurry management.
Automatic railway level crossing gate & slurry management.Automatic railway level crossing gate & slurry management.
Automatic railway level crossing gate & slurry management.Evans Belly
 
download-fullpapers-phe771413a53full
download-fullpapers-phe771413a53fulldownload-fullpapers-phe771413a53full
download-fullpapers-phe771413a53fullFaruk Alrosyidi
 
Careers in transportation engineering
Careers in transportation engineeringCareers in transportation engineering
Careers in transportation engineeringentranzz123
 
17418 transportation engineering
17418   transportation engineering17418   transportation engineering
17418 transportation engineeringsoni_nits
 
Transportation engineering
Transportation engineeringTransportation engineering
Transportation engineeringJagadeesh Kumar
 
International journal of Transportation Engineering and Traffic System vol 2 ...
International journal of Transportation Engineering and Traffic System vol 2 ...International journal of Transportation Engineering and Traffic System vol 2 ...
International journal of Transportation Engineering and Traffic System vol 2 ...JournalsPub www.journalspub.com
 
Airport Planning and Design
Airport Planning and DesignAirport Planning and Design
Airport Planning and DesignMohsen, S Ab
 
Airport master plan
Airport master planAirport master plan
Airport master planAravind Raj
 

Destaque (20)

harbour and dock engineering ppt 01 introduction
harbour and dock engineering ppt 01 introductionharbour and dock engineering ppt 01 introduction
harbour and dock engineering ppt 01 introduction
 
Port and Harbor Engineering
Port and Harbor EngineeringPort and Harbor Engineering
Port and Harbor Engineering
 
Horbour & Dock Engineerin
Horbour & Dock EngineerinHorbour & Dock Engineerin
Horbour & Dock Engineerin
 
Classification of port and harbour ppt.pptx
Classification of port and harbour ppt.pptxClassification of port and harbour ppt.pptx
Classification of port and harbour ppt.pptx
 
Airports presentation
Airports presentationAirports presentation
Airports presentation
 
Airport planning and Design
Airport planning and DesignAirport planning and Design
Airport planning and Design
 
Airport Layout
Airport LayoutAirport Layout
Airport Layout
 
Automatic railway level crossing gate & slurry management.
Automatic railway level crossing gate & slurry management.Automatic railway level crossing gate & slurry management.
Automatic railway level crossing gate & slurry management.
 
download-fullpapers-phe771413a53full
download-fullpapers-phe771413a53fulldownload-fullpapers-phe771413a53full
download-fullpapers-phe771413a53full
 
Careers in transportation engineering
Careers in transportation engineeringCareers in transportation engineering
Careers in transportation engineering
 
17418 transportation engineering
17418   transportation engineering17418   transportation engineering
17418 transportation engineering
 
Transportation engineering
Transportation engineeringTransportation engineering
Transportation engineering
 
International journal of Transportation Engineering and Traffic System vol 2 ...
International journal of Transportation Engineering and Traffic System vol 2 ...International journal of Transportation Engineering and Traffic System vol 2 ...
International journal of Transportation Engineering and Traffic System vol 2 ...
 
Fhwa
FhwaFhwa
Fhwa
 
Airport Planning and Design
Airport Planning and DesignAirport Planning and Design
Airport Planning and Design
 
Bandra worli sealink
Bandra worli sealinkBandra worli sealink
Bandra worli sealink
 
Airport master plan
Airport master planAirport master plan
Airport master plan
 
Guru membina ilmu, menyempurnakan akhlak
Guru membina ilmu, menyempurnakan akhlakGuru membina ilmu, menyempurnakan akhlak
Guru membina ilmu, menyempurnakan akhlak
 
HOWRAH BRIDGE(ESTD-1943)
HOWRAH BRIDGE(ESTD-1943)HOWRAH BRIDGE(ESTD-1943)
HOWRAH BRIDGE(ESTD-1943)
 
Navigation aids
Navigation aidsNavigation aids
Navigation aids
 

Semelhante a CV213 (S5) Transportation Engineering

unit-5-bridge-engg-components-classification-data-collection-site-selection-e...
unit-5-bridge-engg-components-classification-data-collection-site-selection-e...unit-5-bridge-engg-components-classification-data-collection-site-selection-e...
unit-5-bridge-engg-components-classification-data-collection-site-selection-e...SalmanRabbani5
 
ME6601 design of transmission systems - important 2 marks
ME6601 design of transmission systems - important 2 marksME6601 design of transmission systems - important 2 marks
ME6601 design of transmission systems - important 2 marksMohan2405
 
Parametric Study on Curved Bridges Subjected to Seismic Loading
Parametric Study on Curved Bridges Subjected to Seismic LoadingParametric Study on Curved Bridges Subjected to Seismic Loading
Parametric Study on Curved Bridges Subjected to Seismic LoadingIRJET Journal
 
Introduction to Railway Engineering design and construction
Introduction to Railway Engineering  design and constructionIntroduction to Railway Engineering  design and construction
Introduction to Railway Engineering design and constructionVICTOR A. KIPLAGAT
 
259107634-Indian-Railway-Engineering-Practice.pdf
259107634-Indian-Railway-Engineering-Practice.pdf259107634-Indian-Railway-Engineering-Practice.pdf
259107634-Indian-Railway-Engineering-Practice.pdfRaj Bakhtani
 
DESIGN OF T BEAM BRIDGE PROCEDURE
DESIGN OF T BEAM BRIDGE PROCEDUREDESIGN OF T BEAM BRIDGE PROCEDURE
DESIGN OF T BEAM BRIDGE PROCEDUREbabji syed
 
TRANSPORTATION ENGINEERING railway track gauge
TRANSPORTATION ENGINEERING railway track gaugeTRANSPORTATION ENGINEERING railway track gauge
TRANSPORTATION ENGINEERING railway track gaugeJangid Devendra
 
Chapter 5 Introduction to railway
Chapter 5 Introduction to railwayChapter 5 Introduction to railway
Chapter 5 Introduction to railwayKHUSHBU SHAH
 
Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Ankit Singh
 
railway and bridge engineering.pdf
railway and bridge engineering.pdfrailway and bridge engineering.pdf
railway and bridge engineering.pdfRESHMAFEGADE
 
railway and bridge engineering.pdf
railway and bridge engineering.pdfrailway and bridge engineering.pdf
railway and bridge engineering.pdfRESHMAFEGADE
 
Analysis and Design of Power Transmission Lines Steel Towers.docx
Analysis and Design of Power Transmission Lines Steel Towers.docxAnalysis and Design of Power Transmission Lines Steel Towers.docx
Analysis and Design of Power Transmission Lines Steel Towers.docxAdnan Lazem
 
Transportation engineering 2
Transportation engineering   2Transportation engineering   2
Transportation engineering 2R VIJAYAKUMAR
 
IRJET- Comparative Study of Effect of Varying Span Length on Major Elemen...
IRJET-  	  Comparative Study of Effect of Varying Span Length on Major Elemen...IRJET-  	  Comparative Study of Effect of Varying Span Length on Major Elemen...
IRJET- Comparative Study of Effect of Varying Span Length on Major Elemen...IRJET Journal
 
IRJET- Analysis and Design of Segmental Box Girder Bridge
IRJET- Analysis and Design of Segmental Box Girder BridgeIRJET- Analysis and Design of Segmental Box Girder Bridge
IRJET- Analysis and Design of Segmental Box Girder BridgeIRJET Journal
 
lecturenote_1888016911chapter-3 track.pdf
lecturenote_1888016911chapter-3 track.pdflecturenote_1888016911chapter-3 track.pdf
lecturenote_1888016911chapter-3 track.pdfssuser75acc8
 
4.engineering surveys
4.engineering surveys4.engineering surveys
4.engineering surveysMani Vel
 

Semelhante a CV213 (S5) Transportation Engineering (20)

unit-5-bridge-engg-components-classification-data-collection-site-selection-e...
unit-5-bridge-engg-components-classification-data-collection-site-selection-e...unit-5-bridge-engg-components-classification-data-collection-site-selection-e...
unit-5-bridge-engg-components-classification-data-collection-site-selection-e...
 
ME6601 design of transmission systems - important 2 marks
ME6601 design of transmission systems - important 2 marksME6601 design of transmission systems - important 2 marks
ME6601 design of transmission systems - important 2 marks
 
Parametric Study on Curved Bridges Subjected to Seismic Loading
Parametric Study on Curved Bridges Subjected to Seismic LoadingParametric Study on Curved Bridges Subjected to Seismic Loading
Parametric Study on Curved Bridges Subjected to Seismic Loading
 
Me 61
Me 61Me 61
Me 61
 
Introduction to Railway Engineering design and construction
Introduction to Railway Engineering  design and constructionIntroduction to Railway Engineering  design and construction
Introduction to Railway Engineering design and construction
 
259107634-Indian-Railway-Engineering-Practice.pdf
259107634-Indian-Railway-Engineering-Practice.pdf259107634-Indian-Railway-Engineering-Practice.pdf
259107634-Indian-Railway-Engineering-Practice.pdf
 
DESIGN OF T BEAM BRIDGE PROCEDURE
DESIGN OF T BEAM BRIDGE PROCEDUREDESIGN OF T BEAM BRIDGE PROCEDURE
DESIGN OF T BEAM BRIDGE PROCEDURE
 
TRANSPORTATION ENGINEERING railway track gauge
TRANSPORTATION ENGINEERING railway track gaugeTRANSPORTATION ENGINEERING railway track gauge
TRANSPORTATION ENGINEERING railway track gauge
 
Metro Work
Metro WorkMetro Work
Metro Work
 
Chapter 5 Introduction to railway
Chapter 5 Introduction to railwayChapter 5 Introduction to railway
Chapter 5 Introduction to railway
 
Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)
 
Unit 5
Unit 5Unit 5
Unit 5
 
railway and bridge engineering.pdf
railway and bridge engineering.pdfrailway and bridge engineering.pdf
railway and bridge engineering.pdf
 
railway and bridge engineering.pdf
railway and bridge engineering.pdfrailway and bridge engineering.pdf
railway and bridge engineering.pdf
 
Analysis and Design of Power Transmission Lines Steel Towers.docx
Analysis and Design of Power Transmission Lines Steel Towers.docxAnalysis and Design of Power Transmission Lines Steel Towers.docx
Analysis and Design of Power Transmission Lines Steel Towers.docx
 
Transportation engineering 2
Transportation engineering   2Transportation engineering   2
Transportation engineering 2
 
IRJET- Comparative Study of Effect of Varying Span Length on Major Elemen...
IRJET-  	  Comparative Study of Effect of Varying Span Length on Major Elemen...IRJET-  	  Comparative Study of Effect of Varying Span Length on Major Elemen...
IRJET- Comparative Study of Effect of Varying Span Length on Major Elemen...
 
IRJET- Analysis and Design of Segmental Box Girder Bridge
IRJET- Analysis and Design of Segmental Box Girder BridgeIRJET- Analysis and Design of Segmental Box Girder Bridge
IRJET- Analysis and Design of Segmental Box Girder Bridge
 
lecturenote_1888016911chapter-3 track.pdf
lecturenote_1888016911chapter-3 track.pdflecturenote_1888016911chapter-3 track.pdf
lecturenote_1888016911chapter-3 track.pdf
 
4.engineering surveys
4.engineering surveys4.engineering surveys
4.engineering surveys
 

Último

Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Mark Reed
 
FILIPINO PSYCHology sikolohiyang pilipino
FILIPINO PSYCHology sikolohiyang pilipinoFILIPINO PSYCHology sikolohiyang pilipino
FILIPINO PSYCHology sikolohiyang pilipinojohnmickonozaleda
 
How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17Celine George
 
Karra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxKarra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxAshokKarra1
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatYousafMalik24
 
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Celine George
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designMIPLM
 
ACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfSpandanaRallapalli
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxAnupkumar Sharma
 
Concurrency Control in Database Management system
Concurrency Control in Database Management systemConcurrency Control in Database Management system
Concurrency Control in Database Management systemChristalin Nelson
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPCeline George
 
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptxAUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptxiammrhaywood
 
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfAMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfphamnguyenenglishnb
 
Culture Uniformity or Diversity IN SOCIOLOGY.pptx
Culture Uniformity or Diversity IN SOCIOLOGY.pptxCulture Uniformity or Diversity IN SOCIOLOGY.pptx
Culture Uniformity or Diversity IN SOCIOLOGY.pptxPoojaSen20
 
4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptxmary850239
 
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYKayeClaireEstoconing
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONHumphrey A Beña
 
Choosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for ParentsChoosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for Parentsnavabharathschool99
 

Último (20)

Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)
 
FILIPINO PSYCHology sikolohiyang pilipino
FILIPINO PSYCHology sikolohiyang pilipinoFILIPINO PSYCHology sikolohiyang pilipino
FILIPINO PSYCHology sikolohiyang pilipino
 
How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17
 
Karra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxKarra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptx
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice great
 
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-design
 
ACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdf
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
 
Concurrency Control in Database Management system
Concurrency Control in Database Management systemConcurrency Control in Database Management system
Concurrency Control in Database Management system
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERP
 
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptxAUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
 
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfAMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
 
Culture Uniformity or Diversity IN SOCIOLOGY.pptx
Culture Uniformity or Diversity IN SOCIOLOGY.pptxCulture Uniformity or Diversity IN SOCIOLOGY.pptx
Culture Uniformity or Diversity IN SOCIOLOGY.pptx
 
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptxYOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
 
4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx
 
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
 
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptxLEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
 
Choosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for ParentsChoosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for Parents
 

CV213 (S5) Transportation Engineering

  • 1. NOORUL ISLAM UNIVERSITY, KUMARACOIL DEPARTMENT OF CIVIL ENGINEERING CV 213 – TRANSPORTATION ENGINEERING II RAILWAY ENGINEERING , DOCKS AND HARBOUR ENGINEERING AND AIRPORT ENGINEERING QUESTION BANK 2010-2011 Prepared by: TanzeelHabeebulla S5 ,CIVIL NIU Sumitted by: Jean Molly Simon Asst. Professor Civil, NIU
  • 2. UNIT I – RAILWAY PLANNING AND DESIGN 1. Mention some advantages of railways. The various advantages of railways may be as follows: a) It aids in the mass migration of people. b) Trade development has increased ten folds after the growth of railways. c) Land values have increased due to increased industrial growth. d) Speedy distribution of finished product is achieved through railways. 2. What is meant by zonal railways? The entire railway station has been divided into nine zonal railways having different territorial jurisdictions which are responsible for all management and planning of works. 3. What is COFMOW and what are its responsibilities? The Central Organization for Modernization of Workshop (COFMOW) is a specialized agency to implement the various workshop modernization programs of Indian Railways. They are responsible for the modernization of these workshops with the assistance of World Bank. 4. What do you mean by TACV or MAGLEV? All advances in the development of railways have been to achieve the speed of Airways and safety of railways at its best. This objective could be achieved by the usage of Track Air Cushion Vehicles (TACV) or Magnetic Levitation Vehicles (MAGLEV) on purpose made special Railway tracks using special locomotives and coaches to achieve a maximum speed of 250 km/hr. 5. What do you understand by the term “Buckling of rails”? The railway track gets out of the original position due to the buckling if the expansion of rails is prevented during hot weather. Such an action is known as “buckling of rails”. 6. What do you understand by the term “Ballast”? Ballast is the granular material packed under and around the sleeper to transfer loads from sleeper to ballast. It helps in providing elasticity to the truck. 7. What are the different types of gauges? The different types of gauges are as follows: a) Broad Gauge (B.G.) – 1.67 mtrs. b) Meter Gauge (M.G.) – 1.00 mtrs. c) Narrow Gauge (N.G.) – 0.762 mtrs. d) Light Gauge or Freeder Track Gauge –0.610 mtrs. 8. Enumerate the various factors that govern the selection of various types of gauges. There are numerous factors that are dependant in the selection of different gauges. However, few of them are mentioned below: a) Cost of Construction b) Volume and nature of traffic c) Development of the areas d) Physical features of the country
  • 3. e) Speed of movement 9. What are the advantages of “Coning of wheels”? The various advantages of coning of wheels are: a) To reduce the wear and tear of the wheel flanges and rails due to rubbing action of flanges with the inside faces of the rail head. b) To provide a possibility of lateral movement of axil to the wheels. c) To restrict the wheels from slipping. 10. Define “Track modulus”. Track modulus is an index for stiffness of track. It is defined as load per unit length of the rail required to produce a unit depression in the track. 11. List down the various causes of “Track stresses”. Stresses in the railway track are produced due to many causes as listed below: a) Wheel loads b) Dynamic effect of wheel loads c) Hammer blow d) Horizontal thrust 12. What do you understand by the term “Grade compensation”? The reduction in the grading provided at an intersection of curve and gradiant is known as grade compensation on curves. 13. What is a “Sleeper”? A sleeper is a member laid transversely under the rails which are meant to support the rails over them and transfer the load from rails to ballast. 14. What are the functions of a “sleeper”? Sleepers perform the following functions: a) To distribute the load from the rails to the index area of ballast underlying it or to the girders in case of bridges. b) They add to the lateral and longitudinal stability of the permanent track to support the rails at a proper level in straight tracks and at proper super elevation on curves. c) To hold the rails to correct gauge. d) To act as an elastic medium in between the ballast and rails to absorb the vibrations of moving loads. 15. What are the different types of sleepers? Sleepers are classified into the following categories: i. Wooden sleepers ii. Metal sleepers
  • 4. a) Cast Iron Sleepers b) Steel sleepers iii. Concrete Sleepers a) Reinforced Concrete sleepers b) Pre-stressed Concrete Sleepers 16. What do you understand by the term “Fish Plates” and what are its uses? Fish plates are used in rail joints to maintain the continuity of rails and to permit any expansion or contraction of the rail due to thermal variations. They maintain the correct alignment of the line both horizontally and vertically. 17. What are the different types of “Ballast”? The different materials that are used vary from broken stone to sometimes earth. A few commonly used types of ballast are the following: a) Broken stone b) Gravel or shingles c) Ashes or cinders d) Moorum e) Blast furnace slag f) Kankar 18. What are the objectives of “Reconnaissance Survey”? The objectives of Reconnaissance Survey are as follows: a) To decide maximum grading and curvature for proposed alignment b) To locate various control points for getting an idea from where the alignment should pass and where the alignment should not. c) To have an idea about possible alternative alignments d) To prepare rough estimates for different proposed alignment to know most economical, efficient and safe alignment. 19. What are the instruments used in preliminary survey? The various instruments used in preliminary survey are: a) Theodolite - for traversing b) Tacheometer – for plotting main features c) Dumpy level – for drawing the longitudinal cross-sections d) Plain Table – for plotting interior details e) Prismatic Compass – for magnetic bearings of routes and main points. 20. What do you mean by “Transitional Curve”?
  • 5. Transitional curve is defined as a curve of parabolic nature which is introduced between a straight and circular curve to provide an easy change from tangent to the radius selected for a particular curve. UNIT II RAILWAY TRACK CONSTRUCTION, MAINTENANCE AND OPERATION 1. What is the necessity of points and crossings? The knowledge of points and crossings are important in the following ways: a) Points and crossings provide flexibility of movement by connecting one line to another. b) They help in imposing restrictions over turn outs which necessarily retard the movements. c) In regard of safety aspects, points and crossings are weak kinks or points in the track which are susceptible to derailments. 2. List down the different types of crossings. Crossings may be classified as below: a) V-Crossing b) Diamond Crossing c) Square Crossing d) Spring Crossing e) Ramped Crossing 3. What are the component parts of crossing? a) Chairs at crossing toe and heel b) Wing Rails c) Check Rails d) Pointed Splice Rails e) Vee Piece 4. List down the characteristics of Crossing. a) The assembly of crossing has to be rigid to stand against severe vibrations. b) The vear on parts of wing rails opposite the nose and also of nose itself must be protected. 5. What is flange way depth?
  • 6. Flange way depth is the vertical distance between the top surface of the stock rail to the top surface of the heel-block used between the stock rail and check rail. 6. List down the necessities of points and crossings? a) Points and crossings provide flexibility of movement by connecting one line to another. b) They also help for imposing restrictions over turnouts which necessarily retard the movements. 7. List down the different types of track junctions. The important track junctions commonly employed are: a) Symmetrical split b) Tandem c) Diamond Crossing d) Single Slip and Double Slip e) Scissor Cross over f) Ladder tracks 8. Define Platform. Raised level surface from where either passengers board and alight from trains or loading and unloading of goods is done is commonly known as platform. They are of two types, namely, passenger platforms and goods platforms. 9. What do you understand by the term Stations yards? Yard is defined as a system of tracks laid usually on a level within defined limits for receiving, storing, sorting, making up new trains and dispatch of vehicles. 10. Classify the types of yards. a) Passenger Bogie yards b) Goods yards c) Marshalling yards d) Locomotive yards 11. What are the objectives of signaling? The various objectives of providing and operating signals are as below: a) To ensure safety between two or more trains which cross of approach each other’s path. b) To provide facilities for maximum utitlity of the tracks. c) To guide the trains movements during maintenance and rpair of tracks. d) To safeguard the trains at converging junctions and give directional indications at diverging junctions. 12. What are the types of signals based on the various categories?
  • 7. i. Operating characteristics a) Fog or audible signals b) Visual indication signals ii. Functional characteristics a) Shunting signals b) Warner signals c) Semaphore type signals iii. Locational characteristics a) Quoter signals (reception) b) Advanced Starter (departure) iv. Special characteristics a) Point indicators b) Modified lower quadrant semaphore signals 13. What are the various sources of moisture in a railway track? The various sources of moisture affecting a railway track are: a) Surface water due to rain, dew or snow. b) Hydroscopic water or Held water. c) Seepage water d) Moisture by capillary action in sub grade 14. What are the requirements of a track drainage system? a) The track alignment should be made to rest on pervious naturally drained soils. b) The highest level of water table should be much below the level of sub grade. c) Sub surface water should be efficiently drained off by the sub surface drainage system. d) The surface water from adjoining land could be prevented from entering the track formation. 15. What are the advantages of good maintenance of railway track? The life of both track and rolling stock increases by proper maintenance. A well maintained track imparts smooth quality riding surface for vehicles which results in comfort to passengers and safety to goods. 16. What is meant by “Packing”? Packing is the method of forcing stone ballast below the sleepers by ramming with a beater cum pick-axe. 17. Define “Loops”. When a branch line terminates from a previously terminated main line, it is called loop. They are of three types: Split turnout, Trailing turnout, Straight and loop. 18. Enumerate the necessities of “Curves”.
  • 8. a) To bypass natural or artificial obstacles b) To provide easier gradiants by diversions from the straight route. 19. What are the three methods by which safe speed can be calculated? a) Martin’s formula b) Super elevation formula c) Cant formula 20. What do you understand by the term “Ruling gradiant”? Ruling gradiant is defined as the gradiant which determines maximum load that the engine can haul on the section. UNIT III AIRPORT PLANNING AND DESIGN 1. What are the advantages of Air transport? The advantages of air transport are: a) It reduces travel time considerably. b) It aims in the comfortable travel of passengers from point to point. 2. What are the limitations of Air transport? The limitations of air transport are: a) They are quite expensive b) They cause considerable amount of environmental damage 3. What do you mean by “Air Traffic Potential”? Air traffic potential refers to the maximum amount on aircrafts that the specified air space can hold within its boundaries. 4. What do you understand by “Wind Rose Diagram”? Wind Rose Diagram refers to the descriptive illustrative realization of the directional attitude of wind flow with respect to the geographical position at a specified time frame. 5. What do you understand by the term “Minimum Separation Distance”? Minimum Separation distance refers to the least distance that is to be maintained by two successive aircrafts during their taxing along the apron or along the taxi way. 6. What do you understand by the term “Design Speed”?
  • 9. Design speed is the speed estimated by the planning and design engineers for a specified airport runway based on the type of airports and the aircrafts landing and taking off from them. 7. Define “Airport Zoning”. Airport zoning is the process of dividing the whole airport into several zones as clear zone, approach zone, buffer zone, turning zone for easy navigation and control and administration activities including maintenance. 8. Define “Approach Zone”. Approach Zone is defined as the specific zone in the airport which provides indication to the pilot of the approach of the landing strip. 9. What do you understand by the term “Airport Drainage”? Airport Drainage is the process of keeping the runway dry and accessible for aircrafts for the safe landing and takeoff of aircrafts to and from the airports. 10. What is meant by “clearance over highways and railways”? The minimum distance to be maintained vertically above the closest railway and highway zones to eradicate disturbance that maybe caused by the jet explosion during the flight of an aircraft is called its clearance over highways and railways. Unit IV – AIRPORT LAYOUTS, VISUAL AIDS AND AIR TRAFFIC CONTROL 1. What are the objectives of master plan according to FAA? The objectives according to FAA are: a) To provide an effective graphical presentation of the ultimate development of the airport b) To describe various concepts and alternatives which were considered in the establishment of the proposed plan. c) To present the backup of information and data which were essential to the development of the master plan. d) To establish a schedule of priorities and phasing for the various improvements proposed in the plan. 2. What does the term ‘ Terminal area” mean? The terminal area refers to the portion of an airport other than the landing area. It serves as the focal point for activities on the airport which includes terminal and operational buildings, vehicle parking area and aircraft service hangars. 3. List out the purpose of a building area in an airport. The purpose for building area are: a) To provide shelter and space for surface activities.
  • 10. b) To accommodate the basic facilities as toilet, telephone and medical services. c) To establish space for cargo handling and processing. d) To provide an enquiry counter to reach to the needs of passengers. 4. Enumerate the requirements of site selection or the factors affecting site selection. The suitability of site selection for terminal building is processed in accordance to the following: a) Sufficient area for roadways b) Central location with respect to runway c) Proximity and ease of installation of utilities d) Convenient access to the main highway. 5. List out the factors upon which the size of an apron is decided. The paved area for parking of aircrafts, loading and unloading of passengers and cargo is an apron and its size is dependent on: a) Aircraft parking systems b) Size of the loading are required for a type of aircraft or the gate position. c) Number of gate positions 6. What are the different types of aircraft parking systems? Aircrafts are grouped adjacent to terminal buildings in various patters as mentioned below: a) Frontal system b) Open apron system c) Finger system d) Satellite system 7. What do you mean by Blast Fences? Blast fences are used to deflect and dissipate the energy of high velocity jet exhaust so as to protect the passengers from the discomfort caused by the heat. 8. Classify the various types of runway markingbased on their utility. The various markings are divided as follows: a) Runway marking Taxiway marking Runway and taxiway shoulder marking d) Apron marking e) Wind direction indicator f) Landing direction indicator 9. What are different types of airport lighting available? a) Boundary lighting b) Code beacon c) Rotating beacon d) Apron and hangar lighting e) Approach lighting f) Threshold lighting
  • 11. 10. Why is threshold lighting so important in respect to landing? The identification of runway threshold lighting has an important bearing on the pilot’s decision whether to land or not. Thereby the area near the runway threshold is given special lighting considerations. 11. Bring out the need of air traffic control. The Air traffic Control (ATC) is primarily established to ensure a safe, economic and convenient movement of the aircraft flight from one airport to another during the actions of takeoff till landing at the desired port. 12. How is the wind indicator helpful in air traffic? The wind indicator is a wind cone placed at the center of the segmented circle (airport) marker which aids the pilot in locating the airport and the direction of wind. 13. What is a hangar and what is the main function of the same? Hangar is an enclosure for servicing, overhauling and performing repairs of the aircrafts located within the vicinity of a building area. These are usually constructed of steel frames and covered with galvanized iron sheets. 14. State the requirements of selecting a hangar site. The requirements of suitable hangar site are: a) The site should be such that there is a convenient road access to it from the site to the aprons and terminal building. b) Favorable topography providing good natural drainage. c) Reasonable proximity to the loading apron. d) Sufficient area to provide car parking facilities for working personnel. 15. What are the typical airport layouts that are practiced nowadays? The following are the basic airport layouts : a) Two intersecting Runway layout b) Non-intersecting runways layout c) Three intersecting runways layout d) Tangential runway layout 16. Enumerate the basic characteristics that a good airfield should possess. a) Sufficient terminal building facilities b) Lowest possible cost of construction c) Landing, taxiing and taking off a independent operations without interference. d) Excellent control tower visibility, 17. Write down the design considerations applied to taxiway lighting. The design considerations that applies to taxiway lighting are mentioned below: a) Crossing of taxiway and the runway should be clearly identified. b) Effective and simple presentation of guidance elements to permit rapid aircraft movement between runway and apron should be preferred. c) There should be adequate guidance along the taxiway.
  • 12. d) Taxiway should be clearly identified so that they cannot be confused with the runways. 18. Define runway capacity and feature the factors affecting them. Runway capacity is the ability of a runway system to accommodate aircraft landings and take- offs. The factors affecting them are: a) Air traffic control b) Characteristics of demand c) Environmental factors d) Layout and design of the runway system 19. List out the points to be remembered for an efficient airport vehicular circulation and parking system. a) Ease of passenger loading and unloading at the terminal building b) One way traffic wherever possible c) A minimum of driveway intersection d) Adequate driveway width to permit overtaking e) Sufficient and clearly defined parking and circulation routes. 20. Mention the various parking configurations of Aircrafts. The various parking configurations that are used in the present days are as follows: a) Nose-in b) Angle nose-in c) Nose-out d) Angle Nose-out e) Parallel UNIT V HARBOUR ENGINEERING AND OTHER MODES OF TRANSPORT 1. Define 12arbor. Harbour is a sheltered area of sea where facilities for loading and unloading of cargo and passengers are provided. 2. Classify the different types of harbors. a) Natural harbor b) Semi-natural harbor c) Artificial harbor 3. What are the constituents of harbor? a) Entrance channel b) Approach channel c) Birthing Basin d) Breakwater
  • 13. 4. What are the requirements of a good port? a) It should be a place of defence and for resisting the sea borne invasion. b) It should command extensive and valuable trade c) The hinterland should be fertile with a good density of population. d) It should provide maximum facilities to all visiting ships. 5. What do you understand by the term “Breakwater”? Breakwaters are structures constructed to enclose the harbors to protect them from the effect of wind generated waves by reflecting and dissipating their force or energy. 6. What are the types of breakwaters? a) Vertical wall breakwater b) Heap breakwater c) Mound with super structure 7. Define dock. Docks are defined as enclosed areas for berthing the ships to keep them afloat at uniform level to facilitate loading and unloading of cargo. 8. What are the types of docks? a) Wet docks – used for berthing of vessels to facilitate loading and unloading of passengers and cargoes. b) Dry or repair docks – are used for repair of ships 9. What is a cable? A cable is a floating buoy consisting of a pendant which consists of a link chain (open) fitted with a swivel in the upper half. 10. What is apron? Apron is an open space used to expedite the unloading and loading of cargoes in vessels immediately in front of the berth. 11. What are warehouses? At times the port users need storage facilities for much longer periods than that provided by transit sheds. This has brought to the construction of storage facilities known as storage go downs or warehouses. 12. List out the types of dredging devices. a) Dipper dredger b) Grapple dredger c) Continuous bucket elevator or ladder dredger
  • 14. 13. What are locks and provide their components? Locks are a device used to connect a dock with the sea or river at different levels. The components of these are: a) Steel lock gates b) Granite sills c) Culverts d) Heavy masonry retaining walls e) Heavy plumbing plant 14. What are wharves? The platforms or loading places in the form of walls built near shores to berth are known as wharves. In other words they may be defined as a wall erected along a shore or bank to berth vessels for loading and unloading cargo. 15. What do you understand by the term ‘Dolphin’? A structure constructed at the entrance of a locked basin or alongside a pier or wharf to absorb the impact force of the vessel or to provide mooring facility is termed as dolphin due to their form of a cluster of spaced piles. 16. Site the difference between transit sheds and apron. Transit sheds are a temporary storage facility for goods in transit from vessel to consignee or vice-versa. Apron is an open space left immediately in front of the berth for utilization in the installation of mechanical devices as cranes. 17. What are the requirements of a signal? The basic requirements of a marine signal are: a) It should be positively recognizable and should not vary in character. b) It should be simple to identify and should make its meaning clear at a glance. c) It should permit time for easy response. d) It should be clearly visible from a long distance. 18. List out the purpose of construction of shore protection works. Shore protection works are usually provided to protect exposed beach line.However the following purposes are also intended: a) To stabilize the existing beach. b) To restore the eroded beach. c) To create and stabilize the artificial beaches. d) To protect an exposed beach line. 19. Mention the various shore protection works. The following shore protection works are usually adopted: a) Sea walls, Bulk heads and revetments
  • 15. b) Protective beaches c) Sand dunes d) Groynes e) Off shore break waters 20. What are moorings? These are devices which are provided where anchorage water is limited. It is absolutely necessary to have some moorings n all harbours for vessels to discharge its passengers and cargo to barges for taking the same right upto coast. 6 MARKS UNIT I – RAILWAY PLANNING AND DESIGN 1. Write a short note on the engineering surveys for track alignment. Railway project consists four different surveys – Traffic survey – Reconnaissance survey – Preliminary survey – Detailed survey – objects of each of them – factors to be considered 2. Define a permanent way and site the various requirements of an ideal permanent way. Definition of permanent way – requirements of an ideal permanent way ( any 6) – the typical cross section of the permanent way on embankment to be drawn. 3. What are the different gauge types used by the Indian Railways and write down the selection of gauge factors. Definition of gauge – different types of gauge with their specific dimensions ( BG, MG, NG, LG) – factors affecting the selection of a particular gauge ( any 4 ) 4. The wheels are coned to keep it in the central position. Comment on the statement. Definition of coning – advantage of coning – theory of coning – include a figure to depict the process. 5. What is meant by creep? Discuss on the theories propounded to explain probable effects of creep. The longitudinal movement of rails with respect to sleepers in track – theories of creep ( Wave theory, Percussion theory and Drag Theory) – (any 4) effects of creep 6. What are the function of sleepers and the requirements of a good one? Sleepers are members laid transverse to rails on which rails are supported to transfer loads to the ballast – function of sleepers ( any 6) – requirements ( Any 6) 7. Shed some light on the functions and requirements of a good ballast. Ballast – granular material packed below and around sleepers to transmit load from sleepers to formation to allow drainage of track – function of ballast (Any 4) – requirements of ballast (Any 4)
  • 16. 8. Write a short note on the types of ballast. Ballast materials used – explain in brief any 6 of the following – Broken stones – Gravel , River Pebbles or Shingle – Ashes or Cinders – Sand – Moorum – Kankar – Brick Ballast – Blast Furnace Slag – Selected Earth 9. What are formations and enumerate the various function of subgrade or formation. Subgrade is the naturally occurring soil which is prepared to receive the ballast and other railway structures for the track – Formation is a prepares surface for the purpose of laying track – Function of sub grade or formation ( Any 4 ) 10. Define the terms : (i) Super-elevation (ii) Negative super elevation (iii) Cant deficiency The raised elevation of the outer rail with respect to the inner rail – The variation of the elevation of the branch line to the main line –the difference between actual cant provided to the equilibrium cant ( all the definitions to be elaborately explained with suitable values to be offered wherever seemed necessary) 11. What are curves? Shed some light on the necessity and the effects of the curvature. The curvature provided at certain geographical conditions to enable a smooth transfer of trains – necessities to be furnished with the factors( any 4) - effects ( lateral bending of rails due to rigid wheel base , extra vertical load on the inner or outer rail based on the superelevation and speed of vehicle) 12. Write a short note on the widening of gauge on curves. Provision to avoid the striking of outer wheel against outer rail and the inner wheel to the inner is called widening of gauge. – lateral play may lead to derailment – extra gauge width formula and explain the terms. UNIT II – RAILWAY TRACK CONSTRUCTION, MAINTENANCE AND OPERATION 1. Define points and crossings with their necessity to be adopted. These are used to direct trains to different routes either parallel or diverging to make way for movement from one route to another but also helps in marshaling and shunting work at station yards – necessity of points and crossings ( Any 4 ) 2. Write a short note on the various types of crossings. Crossings are classified on two categories - Basis of shape of crossing – basis of assembly of crossing – briefly explain about all with suitable sketches wherever necessary. 3. What are track junctions and briefly mention the various types of track junctions? Track junctions are combinations of points and crossings with curves and straights to transfer the trains from one track to another or to enable trains to cross over other tracks – mention the types of track junctions ( Any 5 ) with suitable sketches. 4. Describe the factors that influence the selection of site for a railway station. How the railway stations are classified? Factors affecting the site selection (explain any 4 from following Acquisition of land , Proximity to town or village, Nature of land area, Approach roads to station site, station site alignment, Site
  • 17. drainage, Station amenities, type of station and yard, role of authorities) – operational classification – functional classification 5. Explain briefly about the tractive resistances. The resistance to movement of trains on the track is known as resistance or track resistance – four categories ( Train resistance , Resistance due to profile, resistances due to starting and acceleration, wind resistance). UNIT III – AIRPORT PLANNING AND DESIGN 1. Point out the important parts of an aero plane and discuss it in brief. With the help of a figure explaining the component parts of an aeroplane – Engine –Flaps – Fuselage – Propeller – Three controls – Tricycle undercarriage – Wings 2. What are the factors that influence the selection of a location for an airport? Necessary data regarding the airport is collected from previous surveys conducted – factors on which site selection is performed ( Any 8) – explain any 6 of them in detail. 3. What are zoning laws and briefly put your understanding of the same? Definition of zoning laws ( Height zoning , land-use zoning) – factors – legal interests – Nature of ordinance – zoning map 4. What is meant by basic runway length and the three cases associated with them? Assumptions in runway length ( Any 4) – Three cases ( Normal landing, Normal Take off, Stepping in emergency) – explain briefly each case with suitable sketches. 5. What are the corrections to basic runway length? Corrections are applied to get the actual length of runway – following corrections are considered – correction for elevation – correction for gradient – correction for temperature – Airport reference temperature formula – explain the three briefly with sufficient examples. UNIT IV – AIRPORT LAYOUTS, VISUAL AIDS AND AIR TRAFFIC CONTROL 1. Discuss briefly on the design objectives and space requirements in an airport. Design objectives – classified into four categories ( airline objectives – airport management objectives – community objectives – Passengers’ objectives ) – space requirements as per FAA – all the points to be discussed in brief with suitable examples wherever possible. 2. The type of aircraft parking is very crucial in the planning of an airport. Substantiate the statement with suitable patterns of aircraft parking. The types of aircraft parking – five categories – nose in – nose out – angle nose in – angle nose out – parallel (explain the types of parking configurations with neat sketches). 3. Explain on the systems of aircraft parking practiced these days in the airports of the world. Based on the horizontal terminal concept – various groupings of aircraft can be parked adjacent to the terminal building – known as parking systems – frontal or linear system – open-apron or transporter system –pier or finger system – satellite system – explain all with neat sketches
  • 18. 4. List out the aims of airport drainage and the function of airport drainage. Adequate drainage required – any 4 points on the aims – any 2 functions of drainage – any 5 special characteristics of airport drainage. 5. Write a short note on the various airport markings. Airport markings – guide pilots to the runways – marked with lines and numbers – to recognize various airport elements – six groups – apron marking – landing direction indicator – runway marking – shoulder marking – taxiway marking – wind direction indicator. UNIT V – HARBOUR ENGINEERING AND OTHER MODES OF TRANSPORT 1. What is a breakwater and explain in brief the various types of breakwaters? Protective barrier to enclose harbours to keep the waters undisturbed by the effect of heavy and strong seas – types – Heap or mound breakwater – mound with superstructure or composite breakwater – Upright wall breakwater – special breakwater – explain them briefly with their main constituents and advantage over one another. 2. Pen down the major facilities to be available at a port. Facilities to be categorized into two groups – facilities to be provided at land – facilities connected with basin water ( Entrance facilities, Loading unloading platforms, Turning facilities, Repairing facilities) 3. What are the advantages and disadvantages of enclosed wet docks? Advantages ( uniform water level to be maintained – prevents rubbing of sides of ships against quays – prevents the constant attention to alternating mooring – effect of storms in outer sea doesn’t affect the dock) – disadvantages – costly arrangement – locks and lock gates to be provided – more time for entry and exit of ships. 4. What are the various types of dredging devices available in modern marine engineering? Dipper dredge – Grapple dredge – ladder dredge – suction dredge – explain them in brief with their working principles. 5. What are the moorings? Mention the accessories of fixed and floating types of moorings. Moorings are provided at regions where water is insufficient for anchorage – accessories – fixed – mooring part – bollard – capstan – floating type – buoys – cables – anchors 10 MARKS UNIT I – RAILWAY PLANNING AND DESIGN 1. Railways are the significant and potential means of transporting men and materials over long distances. Shed some light on the axiom. Advantage of railways – political – social – economic – Techno-economical – various types of trains in India – its influence in the masses of India – modern trends in Indian railways(GIS, GPS, Remote Sensing).
  • 19. 2. Discuss the various factors concerning the selection of rails. Mention the major defects seen in rails. A rail is designated by its weight per unit length – factors – speed of train – gauge of track – axle load and nature of traffic - type of rails – spacing of sleepers – maximum permissible wear on top or rails – corrugated rails – hogged rails – kinks in rails – buckling of rails – damaged rails. 3. Explain in detail the various types of rail joints with neat sketches. Rail joints are necessary to hold together the adjoining ends of the rails in the correct position, both in horizontal and vertical planes – Supported rail joints – Suspended rail joints – Bridge joint – Base joint – Welded rail joints – Staggered or broken joint – Square or even joint – compromise joint – Insulated joint – expansion joint- explain each of these with suitable sketches wherever necessary 4. Explain in detail the effects , measurement and prevention of creep. Effects of creep – sleepers move out of position – stresses exerted on fish plates and bolts to cause breaking – points and crossings distorted – difficulty to re-align or fix the removed track – kinks at joints – forging of ballast – Measurement of creep – creep indicator – diagram – chisel mark – IR practice – intervals of 3 months – not more than 150mm – prevention of creep – pulling back the rails – provision of anchors – use steel sleepers. 5. a)Explain the factors that the speed of train isdependent upon. Derive the equations to determine the safe speeds of trains in the presence and absence of transition curves. M.G. track, the average speed of different trains is 50 kph and allowable cant deficiency is half that of maximum cant deficiency. Speed of trains – strength of rails – power of locomotive – safe speed dependent – gauge of track – radius of curve – distance of resultant of weight of vehicle – amount of superelevation provided – presence or absence of transition curve. Martin’s formula – super elevation – length of transition curve – problem – i) for MG track 0.8V2 = 9.3 cm R ii) Max e = 1/10 of gauge = 10cm iii) Max theoretical cant = Max cant + cant deficiency = 5.1cm iv) Max speed = 52 kph. UNIT II – RAILWAY TRACK CONSTRUCTION, MAINTENANCE AND OPERATION 1. What are crossings? What are the characteristics of crossings and various types of crossings? Crossings – device through which two flange ways allow the wheels of the flanges to move during an intersection – requirements- assembly to be rigid – wear or parts of wing rails, opposite nose and the nose must be protected - crossing body should be long and rigid – nose of crossing should have some thickness – explain any 2 from both the classifications with neat sketches – Based on shape – acute angle – obtuse angle – square crossing – based on assembly – spring or movable wing – ramped crossing 2. Explain in detail the classification and various typed of signals. Operating characteristics – detonating – hand signals – fixed signals – functional characteristics – semaphore type signals – warner signals – shunting signals – colored light signals – locational
  • 20. characteristics – reception signals – quoter signals – home signals – departure signals – starter – advance starter – special characteristics – repeater signals – routing signals – calling on signals – point indicators – modified lower quadrant semaphore signals – miscellaneous signals. 3. Define interlocking and explain the principle of interlocking. Describe the various mechanical devices used for interlocking. Interlocking – technique to ensure that the signal is taken to OFF for route which the signal controls, is properly set – interlocking principles ( 4 points ) – mechanical devices – Detectors – stretcher bar – lock plunger – lock bar – tappet locking – slotting of signals – connecting devices such as rods – cranks – temperature compensators. 4. What is the necessity of relaying a track? Describe the standard method of relaying the track in India. Discuss the various considerations to be made for replacing a track. Necessity – track materials are worn-out – heavier track replacement due to increased traffic – old materials to be serviced and to be replaced by new materials for mail line – standard method of relaying track – preliminary work – actual relaying of track – consolidation of relayed track and removal of released materials – Considerations – traffic to be least affected - length of track to be easily completed within working hours of a day – rails , sleepers and ballast to be replaces simultaneously to be economical – super elevation and alignment to be checked on curves –at points and crossing the set of them are arranged on an elevated platform 5. Explain in detail the tractive resistances. What is hauling capacity? Find out the hauling capacity of a locomotive with 3 pairs of driving wheels and an axle load of 20 tons. Use 0.2 as coefficient of frictions. Track resistances – train resistances – resistances dependent of speed – resistance independent of speed – atmospheric resistances – resistance due to track profile – resistance due to gradients – resistance due to curves – Resistance de to starting and accelerating – Wind resistances – hauling capacity – product of coeffie=cient of friction and weight on driving wheels – problem – H.C. = coeff 0f friction x weight on driving wheels = 12000kg – hauling capacity should exceed the tractive power in excess. UNIT III – AIRPORT PLANNING AND DESIGN 1. Explain in detail the airport site selection process and the survey conducted for the same. Survey – Traffic survey – approach zone survey – drainage survey – meteorological survey – natural resources survey – soil survey – topographical survey – any 5 from them – availability of land for expansion – availability of utilities – development of surrounding areas – economy of construction – ground accessibility – presence of other airports – regional plan – soil characteristics – surrounding obstruction – topography – use of airport – any 5 of them . 2. Explain about the zoning laws. Shed some light on clear and turning zones. Mention the particulars in regional planning. Zoning laws – height zoning – land use zoning – legal interests – nature of ordinance – zoning map – clear zone – innermost portion of approach zone – provided at ends of runways – sketch up the clear zone – turning zone – area of airport other than the runway – intended for turning operations of the aircraft – sketch up the turning zone – regional planning – advantages – ( Any 4 ) – air traffic – existing airports – population – topographical features.
  • 21. 3. Mention the preliminary information required for runway orientation. Describe the procedure adopted to construct the wind rose. Preliminary info – maps of area - records of direction – head wind – during landing – during take- off – wind rose – cross wind component – Wind coverage – chart representation of wind graphically – wind rose diagram. 4. Enumerate the factors on which the location of the exit taxiways depends. Why are holding aprons provided and pen down the points to be taken care during its planning? Location of exit taxiways – air traffic control – exit speed – location of runways – number of exits – pilot variability – topographical features – types of aircraft – weather conditions – holding aprons – for checking the engine operation prior to take off – points to be noted – configuration – entry of runway – facility of bypass – holding bays – location – peak demands. 5. What are the principles that govern the design of the exit taxiway connecting runway and parallel taxiway? Also mention the geometric standards for taxiway. Principles – angle of turn – compound curve – exit speed – length L1 and L2 – occupancy time – shape of taxiway – stopping distance – explain the points in detail – geometric standards – eight elements – length of taxiway – longitudinal gradient – rate of change of longitudinal gradient – sight distance – transverse gradient – turning radius – width of safety area – width of taxiway UNIT IV – AIRPORT LAYOUTS, VISUAL AIDS AND AIR TRAFFIC CONTROL 1. What are the design objectives of terminal building? Explain the two concepts of planning a terminal building. Suggest the reasonable requirements for terminal building having peak hour traffic of 100 passengers. Objectives – Airline objectives – airport management objectives – community objectives – passengers’ objectives – two concepts - Centralized system – Decentralized system – explain with neat sketches –reasonable requirements to be noted in area needs for 100 passengers peak hour or in percentage of area occupied by each service. 2. Sketch up the following: a) Parallel parking b) Open-apron system c) Satellite system d) Nose hangar e) Plan of grouped T-hangars 3. Explain the methods adopted to grant protection from the jet blast. Protection from jet blasts – inconvenience to passengers boarding aircraft – airport personnel – damage to airport equipment – effects to components of airports – holding aprons – taxiways – runway ends – terminal area – methods – blast fences – erosion control – explain with sketches. 4. Discuss some of the broad principles to be observed with respect to passenger flow in the design of layout of terminal building. Principles – arrival gates – departure gates – baggage delivery – information – movement – to be explained in view of passenger – an explanation of passenger activities may also be mentioned.
  • 22. 5. Explain in detail the factors affecting the type and intensity of airport lighting. Also mention the elements of airport lighting. Airport lighting – factors – airport classification – amount of traffic – availability of power – nature of aircraft using the airport – type of night operations planned – type of landing surfaces provided – weather condition – nine elements – airport beacon – approach lighting – apron and hangar lighting – boundary lighting – lighting of landing direction indicator – lighting of wind direction indicator – runway lighting – taxiway lighting – threshold lighting – explain all in brief. UNIT V – HARBOUR ENGINEERING AND OTHER MODES OF TRANSPORT 1. How is the classification of harbor done on this basis of location? What are the factors considered for the design of a harbor. Layout of harbor – greatly influenced by location – classification – canal harbor – Lake Harbor – river or estuary harbor – sea or ocean harbor – factors – site selection – shape of harbor – harbor depth – marine surveys – hydrographic surveys – topographic surveys – harbor planning. 2. What is a breakwater? How is its alignment decided? Describe design information and considerations. Mention the forces that act on a breakwater. Breakwater – protective barrier constructed to enclose harbors and to keep the harbor waters undisturbed by strong seas – alignment – straight converging arms – intersection angle should not exceed 60 degrees – design information – character of coast – coat and availability of materials – direction and force of winds – nature of foundation – height, force and intensity of waves – considerations – design to be based on the extreme phenomena – material in foundation should not scour – forces – hydrostatic force – external force – solvent action of sea water – sea insects . 3. Critically comment on jetties. Describe the several standard types of quay walls and their construction. Jetties – structures in the form of piled projections – built form shore to deep water – comment on the forces acting – traffic on them – designed standards for the same – natural condition and constituents –types of quay walls - solid quay walls – dwarf quay walls – timber lattice work – timber crib quay walls – rubble mound quay walls – explain them with neat sketches 4. Describe the various types of harbor signals. What is a lighthouse and how is it constructed? What are the basic requirements of a marine signal? Types of signals – three categories – light signals ( Light ships, beacons, Buoys) – fog signals (ordinary bells struck by hand, ordinary bells operated by mechanism, submarine bells struck by mechanism, whistles or sirens blown by compressed air or stream) – audible signals – Light house – lofty structure – built from masonry or concrete – constructional practice – requirements –visibility from long distance – positively recognizable – simple for identification – permit time for easy response. 5. What are the essential differences between a transit shed and warehouse as regards: a) their use b) their construction? Transit shed – one or two storeys – handling and distribution – incoming and outgoing cargo requiring protection – sorting of cargo to different consignees – free period to remove consignment – compensation to be paid for detention –construction requirement – doors to be
  • 23. provided for ready and rapid opening – construction to be light and fire-resistance – ample lightings with long skylights – should have modern firefighting arrangements – warehouses – permanent structures – provided on shore or directly behind transit sheds for longer storage periods – storage godowns