The document provides an overview of procurement management as it relates to the PMP exam. It discusses the four primary processes involved in project procurement management: plan procurements, conduct procurements, administer procurements, and close procurements. For each process, it outlines the typical inputs, tools and techniques, and outputs involved. The document aims to explain the key concepts and components of procurement management to help study for the relevant questions on the PMP exam.
3. What is Procurement Management?
Includes the processes required to acquire
goods or services from outside the project
team.
It also includes Contract Management and
Change Control Processes.
Emak International Academy 3
4. Project Procurement Management
Plan Procurements
Plan Procurements Administer Procurements
Administer Procurements
Conduct Procurements Close Procurements
Emak International Academy 4
5. 1. PLAN PROCUREMENTS
INPUTS TOOLS & TECHNIQUES
1. Scope Baseline
2. Requirements Documentation 1. Make or Buy Analysis
3. Teaming Agreements 2. Expert Judgment
4. Risk Register 3. Contract Types
5. Risk Related Contract Decisions
6. Activity Resource Requirements
7. Project Schedule
8. Activity Cost Estimates
9. Cost Performance Baseline
10. Enterprise Environmental Factors
11. Organizational Process Assets
OUTPUTS
1. Procurement Management Plan
2. Procurement SOW
3. Make or Buy Decisions
4. Procurement Documents
5. Selection Criteria
Emak International Academy 5
6. Change Requests
6. 1. PLAN PROCUREMENTS - Inputs
Identifies products or services that can be
acquired from outside the project organization Vs
needs that can be accomplished by the project
team.
Involves consideration of potential sellers.
Can influence project schedule, resource
estimating and make or buy decisions.
Includes reviewing the risks involved and type of
contract to be used.
Emak International Academy 6
7. 1. PLAN PROCUREMENTS - Inputs
1. Scope Baseline
2. Requirements Documentation
Project Requirements
Legal and Contractual Requirements; health,
safety, warrantees, insurance, IPR, terms and
conditions, KPIs, SLAs…etc.
3. Teaming Agreements (Contractual Agreements)
Emak International Academy 7
8. 1. PLAN PROCUREMENTS - Inputs
4. Risk Register
5. Risk Related Contract Decisions
6. Activity Resource Requirements (People,
equipment or location)
7. Project Schedule
8. Activity Cost Estimates (Internal Cost
Estimates for activities being procured)
9. Cost Performance Baseline (Planned Budget)
Emak International Academy 8
9. 1. PLAN PROCUREMENTS - Inputs
10. Enterprise Environmental Factors:
Market place conditions: (Products and
services available in the market, from whom
and under what terms and conditions.)
Suppliers and typical terms and conditions?
11. Organizational Process Assets:
Procurement related policies and guidelines.
Centralized or Decentralized?
Emak International Academy 9
10. 1. PLAN PROCUREMENTS – Tools &
Techniques
1. Make or Buy Analysis:
Determine whether a product or service
needs to be procured or can be produced
by the project team.
Purchase or make - Purchase or
renting/leasing
Reasons to Buy:
Capacity and Capability
Exploit Opportunity
Shift risk (cost, time, or scope)
Reasons to Make:
Idle resources
Want to control
Confidential information Academy
Emak International 10
11. 1. PLAN PROCUREMENTS – Tools
& Techniques
2. Expert Judgment
3. Contract types
The primary aim of considering which contract
type is most suitable for the procurement
situation is to distribute the risk between
buyer and seller.
The three major types of contracts are:
Fixed-Price
Cost-Reimbursable
Time and Material
Emak International Academy 11
12. 1. PLAN PROCUREMENTS –
Tools & Techniques
A. Fixed Price:
FFP
- Well defined scope/ product.
- Fixed total Price. FPIF
- Risk is on the seller.
FP-EPA
B. Cost Reimbursable
CPFF
Contract:
- Scope and Product aren’t CPIF
exactly defined.
- Price is open based on the CPAF
final costs the product will incur.
- Risk is on the buyer.
Emak International Academy 12
13. 1. PLAN PROCUREMENTS – Tools &
Techniques
C. Time and Material:
- Cost is charged to identified tasks of an on
going activity, ex. research.
- Scope per unit is defined.
- Risk is on the buyer. (seller has no incentive to
control costs)
Emak International Academy 13
14. 1. PLAN PROCUREMENTS –Outputs
1. Procurement Management Plan: It includes;
Procurement Processes
Risk Management
Standardized Procurement Documents
Types of contracts used
Responsibilities
Pre-qualified sellers
Scheduled dates for deliverables
Managing multiple providers
Emak International Academy 14
15. 1. PLAN PROCUREMENTS –Outputs
2.Procurement Statement of Work: includes
Specifications, quality levels, quantity desired
and other requirements.
Describes the procurement item in sufficient
detail to allow sellers to determine if they are
capable of providing the item.
3. Make or Buy Decisions: documented
decisions.
4. Change Requests
Emak International Academy 15
16. 1. PLAN PROCUREMENTS – Outputs
5. Procurement Documents: are used to solicit
proposals, quotes, and bids from sellers
Bid / Tender / Quotation (IRB – RFT –
RFQ)
• Selection is mainly based on price.
Proposal
• Selection will be based on price and other
factors; as technical capability, technical
approach…etc.
Terminology may vary by industry.
Emak International Academy 16
17. 1. PLAN PROCUREMENTS –Outputs
6. Source Selection Criteria:
The project team must be prepared to compare
the proposals received in an unbiased manner
based on identified and documented selection
criteria to rate or score proposals.
Includes:
Past performance
Understanding of need
Overall or life cycle cost
References
Technical capability and approach
Risk
Management approach
Financial stability and capacity
Emak International Academy 17
18. Q: With a clear scope of work a seller completes work
as specified, but the buyer is not pleased with the
results. The contract is considered to be:
a. Null and void
b. Incomplete
c. Complete
d. Waived
C. Complete
Emak International Academy 18
19. Q. In a fixed price contract, the fee or profit is:
a. Unknown
b. Part of the negotiation involved in paying every invoice
c. Applied as a line item in every invoice
d. Determined at the end of the project
a. unknown
Emak International Academy 19
20. 2. CONDUCT PROCUREMENTS
INPUTS TOOLS & TECHNIQUES
1. Bidder Conferences
1. Project Management Plan
2. Proposal Evaluation Techniques
2. Procurement Documents
3. Independent Estimates
3. Source Selection Criteria
4. Expert Judgment
4. Qualified Seller List
5. Advertising
5. Seller Proposals
6. Internet Search
6. Project Documents
7. Procurement Negotiations
7. Make or Buy Decisions
8. Teaming Agreements
9. Organizational Process Assets
OUTPUTS
1. Selected Sellers
2. Procurement Contract Award
3. Resource Calendars
4. Change Requests
5. Project Management Plan Updates
6. Project Documents Updates Emak International Academy 20
21. 2. CONDUCT PROCUREMENTS
Obtain sellers’ responses, select sellers and
award contracts.
Emak International Academy 21
22. 2. CONDUCT PROCUREMENTS - Inputs
1. Project Management Plan
2. Procurement Documents
3. Source Selection Criteria
4. Qualified Seller List (Approved Bidders List and
new pre-qualified sellers)
5. Seller Proposals (obtained from sellers)
6. Project Documents (Scope, Schedule, Cost, Risk)
7. Make or Buy Decisions
8. Teaming Agreements
9. Organizational Process Assets (Past Experience,
Bidders List)
Emak International Academy 22
23. 2. CONDUCT PROCUREMENTS –
Tools & Techniques
1. Bidder Conferences
Are also known as contractor, vendor, or pre-
bid conferences.
The purpose of these conferences is to clarify
any of the information not clearly stated in
the RFP.
Creates a clear and common understanding
of the procurement.
Proposals received will be more clearly
aligned with project requirements, due to the
fact that bidder conferences make the
requirements clear.
Emak International Academy 23
24. 2. CONDUCT PROCUREMENTS –
Tools & Techniques
2. Proposal Evaluation Techniques (agreed by
Evaluation Committee)
3. Independent Estimates (serves as a
benchmark and help uncover SOW deficiencies
and ambiguities misunderstanding of Scope)
4. Expert Judgment
5. Advertising
- Is a tool that may be used to increase the
number of potential sellers contacted via
Newspapers, Professional journals or Websites
Emak International Academy 24
25. 2. CONDUCT PROCUREMENTS –
Tools & Techniques
6. Internet Search
7. Procurement Negotiations (Team)
Negotiations can cover the following
areas:
Responsibilities and authorities
Applicable terms and law
Scope, technical and business management
approaches
Contract financing (Payment Schedule)
Price
Emak International Academy 25
26. 2. CONDUCT PROCUREMENTS –
Outputs
1. Selected Sellers
2. Procurement contract Award
A mutually binding agreement that obligates the seller to
provide the specified product and obligates the buyer to
pay for it.
Major components:
SOW Schedule Roles and responsibilities
Pricing Payment Acceptance criteria
Warranty product support Incentives
Penalties Insurance Performance bonds
Change requests Termination mechanisms
Emak International Academy 26
27. 2. CONDUCT PROCUREMENTS Outputs
3. Resource Calendars
4. Change Requests
5. Project Management Plan Updates (Scope,
Cost, Schedule, Procurement Management
Plan…etc.)
6. Project Document Updates (SOW and
Requirements Documentation)
Emak International Academy 27
28. Q: Bidder Conferences are part of :
a. Plan Procurements
b. Conduct Procurements
c. Administer Procurements
d. Conduct Purchasing
Answer B
Emak International Academy 28
29. Q. The project team is arguing about whether they
should complete a work package themselves or
outsource the work. What part of the procurement
process are they in:
a. Contract administration
b. Plan Procurements
c. Conduct Procurements
d. Select sellers
Answer B
Emak International Academy 29
30. 3. ADMINISTER PROCUREMENTS
INPUTS TOOLS & TECHNIQUES
1. Procurement Documents 1. Contract Change Control System
2. Project Management Plan 2. Procurement Performance Reviews
3. Contract 3. Inspections and Audits
4. Performance Reports 4. Performance Reporting
5. Approved Change Requests 5. Payment Systems
6. Work Performance Information 6. Claims Administration
7. Records Management System
OUTPUTS
1. Procurement Documentation
2. Organizational Process Assets Updates
3. Change Requests
4. Project Management Plan Updates
Emak International Academy 30
31. 3. ADMINISTER PROCUREMENTS
Manage procurements relationships,
monitor contract performance and make
changes and corrections as needed.
Emak International Academy 31
32. 3. ADMINISTER PROCUREMENTS -Inputs
1. Procurement Documents
2. Project Management Plan
3. Contract
4. Performance Reports
Technical documentation and other
deliverables information developed by the
seller.
Seller Performance Reports.
Emak International Academy 32
33. 3. ADMINISTER PROCUREMENTS -
Inputs
5. Approved Change Request.
6. Work Performance Information: Includes;
The extent to which quality standards are
being met.
Indicates which deliverables have been
completed.
Identifies which costs have been incurred.
Seller invoices: submitted from time to time
to request payment for work performed.
Emak International Academy 33
34. 3. ADMINISTER PROCUREMENTS –
Tools and Techniques
1. Contract Change Control System
Defines the process by which the contract
may be modified.
It includes the paperwork, tracking systems,
dispute resolution procedures, and approval
levels necessary for authorizing changes.
Should be integrated with the integrated
change control system.
2. Procurement Performance
Review; A structured review on the
sellers’ progress to deliver as per planned
scope – quality – schedule – quality, etc..
Emak International Academy 34
35. 3. ADMINISTER PROCUREMENTS –
Tools and Techniques
3. Inspections and Audits; required by the buyer
and supported by the seller to identify any
weaknesses in the seller’s work performance or
deliverables.
4. Performance Reporting: Provides information to
management about how effectively the seller is
achieving the contractual objectives.
5. Payment System: Handled by the accounts
payable department of the performing organization.
Must include reviews and approvals of seller invoices
by the project team prior to issuing a payment to a
seller.
Emak International Academy 35
36. 3. ADMINISTER PROCUREMENTS –
Tools and Techniques
6. Claims Administration: (disputes or appeals)
Where buyer and seller cannot agree on
compensation for the change, or that a change has
even occurred.
Should be documented and managed in accordance
with the terms of the contract.
Might involve arbitration or litigation.
7. Record Management System:
A set of processes and automation tools
consolidated into the project Management
Information System to manage contract
documentation and records.
To maintain an index of contract records, and
correspondences for archiving and future use.
Emak International Academy 36
37. 3. ADMINISTER PROCUREMENTS –
Outputs
1. Procurement Documentation: A complete
set of indexed records regarding the contract.
Includes;
Schedules
Approved and unapproved change requests
Technical documentation
Work performance information
Performance reports
Financial docs (invoices ad payment records)
2. Change Requests
Emak International Academy 37
38. 3. ADMINISTER PROCUREMENTS –
Outputs
3. Updated Organizational Process Assets:
including
Correspondence: communication between buyer
and seller.
Payment Schedules and requests; if the project
is using an external payment system.
Seller performance Evaluation documentation:
performed by the buyer to document seller’s
ability to continue to perform work on the
project or to be allowed to work on future
projects.
Basis for early termination
Can be included in qualified seller lists in the
organization.
4.Updated Project Management Plan
Emak International Academy 38
39. Q. All of the following statements about change control are
incorrect EXCEPT:
a. A fixed price contract will minimize the need for change
control.
b. Changes seldom provide real benefits to the project
c. Contracts should include procedures to accommodate
changes.
d. More detailed specifications eliminate the causes of
changes.
Answer C
Emak International Academy 39
40. 4. CLOSE PROCUREMENTS
INPUTS TOOLS & TECHNIQUES
1. Procurement Documentation 1. Procurement Audits
2. Project Management Plan 2. Negotiated Settlements
3. Records Management System
OUTPUTS
1. Closed Procurement
2. Organizational Process Assets Updates
Emak International Academy 40
41. 4. CLOSE PROCUREMENTS
The process of completing each project procurement.
Involves verification that all of the procurement work
was completed and accepted. (Product Verification)
Emak International Academy 41
42. 4. CLOSE PROCUREMENTS - Inputs
1. Project Management Plan
2. Procurement Documentation
The contract.
Supporting schedules
Requested and approved changes
Technical documentation
Performance reports
Financial reports
Emak International Academy 42
43. 4. CLOSE PROCUREMENTS – Tools
and Techniques
1. Procurement Audits:
A structured review of the procurement
process from Plan Procurements to Administer
Procurements.
The objective is to identify the successes and
failures that warrant recognition.
2. Negotiated Settlements
3. Records Management System.
Emak International Academy 43
44. 4. CLOSE PROCUREMENTS – outputs
1. Closed Procurements: Formal written notice
that the contract has been completed.
2. Updated Organizational Process Assets:
Contract File:
A complete set of indexed contract documentation.
Deliverable Acceptance:
A formal written notice from the buyer that the
contract has been accepted.
Requirements should be defined in the contract.
Lessons Learned documentation
Emak International Academy 44