SlideShare uma empresa Scribd logo
1 de 30
Draft 5 29 2012




    Process Safety Management

                  John Newquist
Overview

Trends
Top PSM Cited
 Issues
Outline of Standard

• Application            • Pre-Start up Safety
• Employee                 Review
  Participation          • Mechanical Integrity
• Process Safety         • Hot Work (Non-routine
  Information              Work Authorizations)
• Process Hazard         • Management of
  Analysis                 Change
• Operating Procedures   • Incident Investigation
• Employee Training      • Emergency Planning
• Contractors              and Response
                         • Compliance Audits
Trends
•   CHEM NEP
•   Ammonia
•   Sigcases
•   Repeat
    Violations
P&IDs
• 119(d)(3)(i)(B)
• Relief Valves not in P&ID
• P&ID indicated flame arrestors that did not
  exist.
• P&ID did not indicate correct piping
  connections to vessels. Incorrect
  diameters of piping.
• P&ID did not show LEL detectors and
  interlocks.
P&IDs
•   119(d)(3)(i)(B)
•   No design basis for relief valves on reactor
•   Valve tags were reversed, mislabeled
•   HF vent line was not marked
•   HF dump tank was not identified.
•   Three way valves were not identified
•   Equipment were transposed on the
    diagrams
Process Safety Information
• 119(d)(3)(i)(H)
PSI did not list:
• Cutout devices and Interlocks
• High and low level sensors
• Ammonia detectors
• High and low pressure devices
• Emergency Stop Buttons
• Electrical Classification of Equipment
RAGAGEP
•   119(d)(3)(ii)
•   U-1 Form missing for pressure vessel
•   Mechanical room for ammonia had no emergency ventilation
•   Electrical Classification of equipment missing
•   Venting Flanges not meet ANSI/ASME 31.3
•   No documentation that piping fit for service per API 570
•   Manual block valves were located down stream of automatic dump
    valves (Hydrogen Fluoride Industry Practice Institute or HFIPI)
•   HF tanks not sized 1.5x for anticipated deliveries. HFIPI
•   HF dump tank did not have capacity of largest HF tank. HFIPI
•   HF liquid flow velocity exceeded 5.9 feet/second
•   Eye wash and shower were not configured to sound in the control
    room. HFIPI
•   No valve capping kit for HF rail car unloading
•   High pressure vent lines were not labeled.
•   Relief valve discharge 3.5` above platform vs. 15 feet. (IIAR 2-2008)
PHA
•   119(e)(1)
•   No PHA on the Hydrogen Storage tank
•   PHA missing several elements
•   PHA did not address failure of ventilation
•   PHA did not address previous fires.
•   PHA did not previous piping failures.
•   PHA did not address previous failures of
    cooling systems
PHA
• 119(e)(3)(i) The hazards of the process;
• The hazard of power failure was not discussed in the
  PHA.
• The Hazard of natural gas draining to the surge drum too
  long.
• The hazard of releasing material in the neutralization pits
• The hazard of weight of hoses on pipe nipples was not
  addressed
• The Hazards of venting flanges was not addressed in the
  PHA.
• The hazard of forklift traffic was not addressed.
PHA
• 119(e)(3)(v)
• No analysis of facility siting issues related
  to formaldehyde dispersion
• Building siting and how affected by the
  ammonia process
• Ammonia system including piping,
  recirculator, chiller, receiver, and
  condensors were located to the roadway
  and subject to vehicle impact.
PHA
•   119(e)(3)(vi)
•   Human factor
•   Fatigue
•   No consider of opening block valves
    downstream of remote operated dump valve
•   Second and third shift training
•   People on vacation leave
•   Operational overload during emergencies
•   Operation interactions
PHA
• 119(e)(5)
• PHA items not resolved for years
• PHA did not address team finding and
  recommendations such as
• Installing back flow prevention when adding
  flammable liquids in a tank
• Automatic Pressure controls for Nitrogen
• Adding relief valves
• Facility siting for control rooms
• Reconfigurations of valves issue on PHA was
  not resolved.
Operating Procedures
• 119(f)(1)
• No written procedures for maintaining the ammonia
  systems
• No procedures for communicating issues during shift
  changes
• No procedures for upset condition or avoiding deviations
  beyond operating limits.
• Transferring chemicals from pit to pit
• Neutralization of chemicals
Operating Procedures
• 119(f)(1)(i)(E)
• No procedures for when discharge pressure, suction
  pressure, discharge temperature, lubrication oil
  pressure, and lubrication oil temperature exceed normal
  operating range
• No Specific steps to stop an emergency
• No identification of emergency upset conditions and
  procedures to take to resolve it.
• No procedure for emergency operations for transfer of
  chemicals out a Surge tank
• No clear procedures for emptying HF tanks with isolating
  nitrogen systems
Operating Procedures
• 119(f)(3)
• No certification of operating procedures
  annually.
Safe Work Practices
• 119(f)(4)
• No safe work procedures developed for
  contractors or maintenance employees
  working on PSM covered processes for
• Lockout
• Confined space
• Hot works
Mechanical Integrity
•   119(j)(2) No inspection procedures
•   Pressure Vessels
•   Piping, components, Hose adapters
•   Pump
•   Venting Flanges
•   Compressors and cutout switches
•   Relief Systems and change out schedule
•   Emergency Shutdown Systems
•   Valves requiring Carseals
•   No Procedures for torquing bolts
Mechanical Integrity
• 119(j)(4)(i) No inspection of
• Relief valves
• Pressure vessels (Oil pot, Accumulator,
  Receiver, and Transfer Drum)
• Ammonia Feed Pumps
• Venting flanges
• Pipe Nipples, Deadlegs, Inspection ports, hose
  adapters
• High Level alarms and emergency shutdown
  systems.
Mechanical Integrity
• 119(j)(4)(ii)
• No authorized API 570/574 piping inspector or piping
  inspections
• No API 510 pressure vessel inspector
• No corrosion rates established for pressure vessels
• Pump not maintained and lubricated per manufacturer’s
  recommendations
• Rupture Disk was not replaced per manufacturer’s
  recommendations
• No 100% Radiography or Ultrasonic testing on process
  pipe weld repair per ANSI B31.1
• No fitness for service for repairs per API 579 for tanks
  undergoing repair at head nozzles
Mechanical Integrity
•   119(j)(4)(iii)
•   No annual piping inspection
•   No API internal pressure vessel inspection
•   No inspection testing of the condensate vapor
    system for buildup that might clog the system.
•   No hydrostatic testing of HF tanks
•   No testing or exercising of HF vent valves/dump
    valves
•   Not testing compressor cutout switches
•   Blast Evaporators, heat exchangers not
    inspected
•   No pump inspections
Management of Change
• 119(L)(1)
• No implementation of procedures after
• Replacing manual valves with pneumatic actuated
  valves.
• Installing a LEL detector
• Disconnection of the Cooling water System
• Installing an alarm on the quench system
• Expanding Toulene tank system
• Leak at Relief Header Rupture disk
• Bolt torquing procedure change
• After making changes in the Ammonia system
• No MOC for condenser removed from process
Incident Investigation
• 119(m)(1)
• No incident investigation for
• Ice buildup and cracks in evaporator coils
• Prior incident of adding high temperature
  product to flammables
• Prior ammonia release.
• Prior corrosion in pipes
Compliance Audits
• 119(o)(1)
• No PSM evaluation audits were conducted
• No audits of Mechanical integrity,
  Management of Change, PHA, and
  Emergency Response.
Other Issues
•   Lockout
•   Emergency Response
•   Confined Space Rescue
•   Electrical Classification
•   Hot Works
•   Boiler Safety
Two Investigators
• In most of the cases that we investigate, we
  have found that most firms completely ignore the
  1910.119(j)(5) requirement, and don’t even
  consider doing an MOC for a temporary change
  that meets the requirements of 1910.119(l).
• We have two or three cases in our backlog of
  open cases that deal exactly with these issues.
  Guess the refinery NEP is having some impact.
More Comments
•   I fully agree on the MOC’s; they are called by the workers “Matter of
    Convenience” because they believe they are used to justify
    exceptions and deviations.
•   I would add a couple to your list; PSSR (Pre Start-up Safety
    Review) and organizational issues.
•   I just reviewed a couple of investigations where there was an
    unexpected shutdown on a portion of the unit and in a rush to get
    the unit back up (they did not fully understand why it had shutdown)
    and they ended up in a more serious situation.
•   Most companies only apply the PSSR part of the PSM standard to a
    cold start, and even the procedures are written for a cold start and
    do not work for hot restarts.
Summary
•   Identify the top risks in the facility
•   Look at corrosion monitoring on pipes and vessels,
•   Pump vibration leads to failures and fires.
•   Procedures related to boiler startup, hot works,
•   Evaluate hydrogen sulfide monitoring, hydrofluoric acid,
•   Address fatigue and control panel alarms during start
    ups,
•   Management of change is slipping.
•   Gasket torquing procedures should be reviewed as well
    as gasket compatibility for service,
•   Relief valve inspection and testing is a must.
•   Facility siting is ever present
312-353-5977               Facebook….john newquist




 johnanewquist@gmail.com         Twitter is johnanewquist




Newquist.john@dol.gov


                                    LinkedIn is john
                                    newquist
Further
 This was prepared as a collaborative effort several
  friends as a preliminary aid for anyone in the safety and
  health field.
 These are just some the issues. A comprehensive job
  hazard analysis should be conducted for any task where
  someone can get hurt.
 This is not an official OSHA publication. Those will be on
  the OSHA.gov website.
 If you see any errors my email is Newquist.john@dol.gov
 312-353-5977
 I want to thank Bryan H. Art D. Jim L. Clyde T. Mark K.
  and Janet S. for all their assistance in answering
  questions and providing insight to the many hazards in
  this sector.

Mais conteúdo relacionado

Mais procurados

Ai Ch E Overpressure Protection Training
Ai Ch E Overpressure Protection TrainingAi Ch E Overpressure Protection Training
Ai Ch E Overpressure Protection Training
ernestvictor
 
06 procedure of start up boiler ok
06 procedure of start up boiler ok06 procedure of start up boiler ok
06 procedure of start up boiler ok
Bunk Bonk
 
BP_Waterline Hydrostatic
BP_Waterline HydrostaticBP_Waterline Hydrostatic
BP_Waterline Hydrostatic
Scott Nunn
 
Hydrotest REPORT FOR 4'' 158m Line.
Hydrotest REPORT FOR 4'' 158m Line.Hydrotest REPORT FOR 4'' 158m Line.
Hydrotest REPORT FOR 4'' 158m Line.
Emeka Ngwobia
 

Mais procurados (20)

Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION
 
Eng handbook crosby pressure relief valve engineering handbook
Eng handbook crosby pressure relief valve engineering handbookEng handbook crosby pressure relief valve engineering handbook
Eng handbook crosby pressure relief valve engineering handbook
 
Ai Ch E Overpressure Protection Training
Ai Ch E Overpressure Protection TrainingAi Ch E Overpressure Protection Training
Ai Ch E Overpressure Protection Training
 
06 procedure of start up boiler ok
06 procedure of start up boiler ok06 procedure of start up boiler ok
06 procedure of start up boiler ok
 
Pipininspect
PipininspectPipininspect
Pipininspect
 
( Itp ag pipe) rapid p006 a scs qac itp 3200 0007
( Itp ag pipe) rapid p006 a scs qac itp 3200 0007( Itp ag pipe) rapid p006 a scs qac itp 3200 0007
( Itp ag pipe) rapid p006 a scs qac itp 3200 0007
 
Power Plant Boiler feed pump
Power Plant Boiler feed pump Power Plant Boiler feed pump
Power Plant Boiler feed pump
 
How to maintain ro
How to maintain roHow to maintain ro
How to maintain ro
 
Relief and blowdown in
Relief and blowdown           inRelief and blowdown           in
Relief and blowdown in
 
Offshore Drilling equipment Technical documentation
Offshore Drilling equipment Technical documentationOffshore Drilling equipment Technical documentation
Offshore Drilling equipment Technical documentation
 
BP_Waterline Hydrostatic
BP_Waterline HydrostaticBP_Waterline Hydrostatic
BP_Waterline Hydrostatic
 
API STD 521
API STD 521API STD 521
API STD 521
 
04 lewabrane manual_monitoring_performance
04 lewabrane manual_monitoring_performance04 lewabrane manual_monitoring_performance
04 lewabrane manual_monitoring_performance
 
Opportunity Assessment and Advanced Control
Opportunity Assessment and Advanced ControlOpportunity Assessment and Advanced Control
Opportunity Assessment and Advanced Control
 
Rtk katalog gb
Rtk katalog gbRtk katalog gb
Rtk katalog gb
 
Amended rule in_boiler_1160
Amended rule in_boiler_1160Amended rule in_boiler_1160
Amended rule in_boiler_1160
 
Solutions Manual for Process Control Modeling Design And Simulation 1st Editi...
Solutions Manual for Process Control Modeling Design And Simulation 1st Editi...Solutions Manual for Process Control Modeling Design And Simulation 1st Editi...
Solutions Manual for Process Control Modeling Design And Simulation 1st Editi...
 
NONG YAO PROJECT SUBSEA VALVE Rev 0
NONG YAO PROJECT SUBSEA VALVE Rev 0NONG YAO PROJECT SUBSEA VALVE Rev 0
NONG YAO PROJECT SUBSEA VALVE Rev 0
 
Hydrotest REPORT FOR 4'' 158m Line.
Hydrotest REPORT FOR 4'' 158m Line.Hydrotest REPORT FOR 4'' 158m Line.
Hydrotest REPORT FOR 4'' 158m Line.
 
Bfwp
BfwpBfwp
Bfwp
 

Semelhante a Psm vpppa reg v

Discussing osha 1910 106 nfpa 30 and recent fire incidents of 2015 2016
Discussing osha 1910 106 nfpa 30 and recent fire incidents of 2015 2016Discussing osha 1910 106 nfpa 30 and recent fire incidents of 2015 2016
Discussing osha 1910 106 nfpa 30 and recent fire incidents of 2015 2016
John Newquist
 
Safety-Moment-SIMOPS-gas-venting.pptx
Safety-Moment-SIMOPS-gas-venting.pptxSafety-Moment-SIMOPS-gas-venting.pptx
Safety-Moment-SIMOPS-gas-venting.pptx
MoHSEn Ahamdiani
 
20150709 - Americas Industrial Services
20150709 - Americas Industrial Services20150709 - Americas Industrial Services
20150709 - Americas Industrial Services
Maribel Renteria
 
Boiler safety 11 28 2011 abridged
Boiler safety 11 28 2011 abridgedBoiler safety 11 28 2011 abridged
Boiler safety 11 28 2011 abridged
vtsiri
 
Boiler safety 11 28 2011 abridged
Boiler safety 11 28 2011 abridgedBoiler safety 11 28 2011 abridged
Boiler safety 11 28 2011 abridged
Bryan Haywood
 
Safety Alert: The Human Component in a Mechanical System
Safety Alert: The Human Component in a Mechanical SystemSafety Alert: The Human Component in a Mechanical System
Safety Alert: The Human Component in a Mechanical System
FAA Safety Team Central Florida
 
Back To Basics GMPs[1]
Back To Basics GMPs[1]Back To Basics GMPs[1]
Back To Basics GMPs[1]
Bob Darius
 
Ankur Sood-Instrument engineer
Ankur Sood-Instrument engineerAnkur Sood-Instrument engineer
Ankur Sood-Instrument engineer
ankur sood
 
Ankur Sood-Instrument engineer
Ankur Sood-Instrument engineerAnkur Sood-Instrument engineer
Ankur Sood-Instrument engineer
ankur sood
 

Semelhante a Psm vpppa reg v (20)

Nfpa Process Safety Management and osha 6 8 2013
Nfpa Process Safety Management and osha 6 8 2013Nfpa Process Safety Management and osha 6 8 2013
Nfpa Process Safety Management and osha 6 8 2013
 
COMPL OF WORKS1
COMPL OF WORKS1COMPL OF WORKS1
COMPL OF WORKS1
 
Discussing osha 1910 106 nfpa 30 and recent fire incidents of 2015 2016
Discussing osha 1910 106 nfpa 30 and recent fire incidents of 2015 2016Discussing osha 1910 106 nfpa 30 and recent fire incidents of 2015 2016
Discussing osha 1910 106 nfpa 30 and recent fire incidents of 2015 2016
 
Safety-Moment-SIMOPS-gas-venting.pptx
Safety-Moment-SIMOPS-gas-venting.pptxSafety-Moment-SIMOPS-gas-venting.pptx
Safety-Moment-SIMOPS-gas-venting.pptx
 
Lessons learned solving pilot valve instability issues on LNG storage tanks
Lessons learned solving pilot valve instability issues on LNG storage tanksLessons learned solving pilot valve instability issues on LNG storage tanks
Lessons learned solving pilot valve instability issues on LNG storage tanks
 
Episode 34 : Project Execution Part (5)
Episode 34 :  Project Execution Part (5)Episode 34 :  Project Execution Part (5)
Episode 34 : Project Execution Part (5)
 
20150709 - Americas Industrial Services
20150709 - Americas Industrial Services20150709 - Americas Industrial Services
20150709 - Americas Industrial Services
 
Boiler safety 11 28 2011 abridged
Boiler safety 11 28 2011 abridgedBoiler safety 11 28 2011 abridged
Boiler safety 11 28 2011 abridged
 
Boiler safety 11 28 2011 abridged
Boiler safety 11 28 2011 abridgedBoiler safety 11 28 2011 abridged
Boiler safety 11 28 2011 abridged
 
Failure Analysis, benefits, logistics and limitations
Failure Analysis, benefits, logistics and limitationsFailure Analysis, benefits, logistics and limitations
Failure Analysis, benefits, logistics and limitations
 
Safety Alert: The Human Component in a Mechanical System
Safety Alert: The Human Component in a Mechanical SystemSafety Alert: The Human Component in a Mechanical System
Safety Alert: The Human Component in a Mechanical System
 
Back To Basics GMPs[1]
Back To Basics GMPs[1]Back To Basics GMPs[1]
Back To Basics GMPs[1]
 
Phillips66Talk.ppt
Phillips66Talk.pptPhillips66Talk.ppt
Phillips66Talk.ppt
 
TeamCapabilitiesBro
TeamCapabilitiesBroTeamCapabilitiesBro
TeamCapabilitiesBro
 
Piping hydrotest
Piping hydrotestPiping hydrotest
Piping hydrotest
 
Root Cause Failure Analysis Methods for Pump Failures
Root Cause Failure Analysis Methods for Pump FailuresRoot Cause Failure Analysis Methods for Pump Failures
Root Cause Failure Analysis Methods for Pump Failures
 
ACTTROM - talk by Roger Watson, University of Edinburgh, at the opening of th...
ACTTROM - talk by Roger Watson, University of Edinburgh, at the opening of th...ACTTROM - talk by Roger Watson, University of Edinburgh, at the opening of th...
ACTTROM - talk by Roger Watson, University of Edinburgh, at the opening of th...
 
Rbi presentation inventure technologies
Rbi presentation inventure technologiesRbi presentation inventure technologies
Rbi presentation inventure technologies
 
Ankur Sood-Instrument engineer
Ankur Sood-Instrument engineerAnkur Sood-Instrument engineer
Ankur Sood-Instrument engineer
 
Ankur Sood-Instrument engineer
Ankur Sood-Instrument engineerAnkur Sood-Instrument engineer
Ankur Sood-Instrument engineer
 

Mais de vtsiri

Gi2013 introduction to safety
Gi2013 introduction to safetyGi2013 introduction to safety
Gi2013 introduction to safety
vtsiri
 
1926 power transmission fall issues 2014
1926 power transmission fall issues 20141926 power transmission fall issues 2014
1926 power transmission fall issues 2014
vtsiri
 
Scaffold safety email
Scaffold safety emailScaffold safety email
Scaffold safety email
vtsiri
 
Welding Safety 2014
Welding Safety 2014Welding Safety 2014
Welding Safety 2014
vtsiri
 

Mais de vtsiri (20)

Combustible Dust 2015 nfpa 644
Combustible Dust 2015 nfpa 644Combustible Dust 2015 nfpa 644
Combustible Dust 2015 nfpa 644
 
Understanding Legionnaires’ Disease A Fact Sheet For Workers And Unions
Understanding Legionnaires’ Disease A Fact Sheet For Workers And UnionsUnderstanding Legionnaires’ Disease A Fact Sheet For Workers And Unions
Understanding Legionnaires’ Disease A Fact Sheet For Workers And Unions
 
Tree trimming update mi 2015
Tree trimming update mi 2015Tree trimming update mi 2015
Tree trimming update mi 2015
 
Gi forklift and mat handling 2015
Gi forklift and mat handling 2015Gi forklift and mat handling 2015
Gi forklift and mat handling 2015
 
Capacitive app note
Capacitive app noteCapacitive app note
Capacitive app note
 
Trenching 2014 year in review
Trenching 2014 year in reviewTrenching 2014 year in review
Trenching 2014 year in review
 
Industrial electrical safety
Industrial electrical safetyIndustrial electrical safety
Industrial electrical safety
 
2015 industrial hygiene & respiratory care
2015 industrial hygiene & respiratory care2015 industrial hygiene & respiratory care
2015 industrial hygiene & respiratory care
 
Fy2014 mfc construction_1.2015
Fy2014 mfc construction_1.2015Fy2014 mfc construction_1.2015
Fy2014 mfc construction_1.2015
 
Fy2014 mfc general industry 1.2015
Fy2014 mfc general industry 1.2015Fy2014 mfc general industry 1.2015
Fy2014 mfc general industry 1.2015
 
Construction issues for 2015
Construction issues for 2015Construction issues for 2015
Construction issues for 2015
 
OSHA record keeping update
OSHA record keeping  updateOSHA record keeping  update
OSHA record keeping update
 
Gi 2014 fire siosh
Gi 2014 fire sioshGi 2014 fire siosh
Gi 2014 fire siosh
 
General Industry 2014 ppe newsletter
General Industry 2014 ppe newsletterGeneral Industry 2014 ppe newsletter
General Industry 2014 ppe newsletter
 
OSHA regulations Fall protection
OSHA regulations Fall protection OSHA regulations Fall protection
OSHA regulations Fall protection
 
Gi2013 introduction to safety
Gi2013 introduction to safetyGi2013 introduction to safety
Gi2013 introduction to safety
 
1926 power transmission fall issues 2014
1926 power transmission fall issues 20141926 power transmission fall issues 2014
1926 power transmission fall issues 2014
 
Scaffold safety email
Scaffold safety emailScaffold safety email
Scaffold safety email
 
Welding Safety 2014
Welding Safety 2014Welding Safety 2014
Welding Safety 2014
 
Ladder safety
Ladder safetyLadder safety
Ladder safety
 

Último

The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
daisycvs
 

Último (20)

Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGParadip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
GUWAHATI 💋 Call Girl 9827461493 Call Girls in Escort service book now
GUWAHATI 💋 Call Girl 9827461493 Call Girls in  Escort service book nowGUWAHATI 💋 Call Girl 9827461493 Call Girls in  Escort service book now
GUWAHATI 💋 Call Girl 9827461493 Call Girls in Escort service book now
 
joint cost.pptx COST ACCOUNTING Sixteenth Edition ...
joint cost.pptx  COST ACCOUNTING  Sixteenth Edition                          ...joint cost.pptx  COST ACCOUNTING  Sixteenth Edition                          ...
joint cost.pptx COST ACCOUNTING Sixteenth Edition ...
 
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
 
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
 
Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business Potential
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
 
HomeRoots Pitch Deck | Investor Insights | April 2024
HomeRoots Pitch Deck | Investor Insights | April 2024HomeRoots Pitch Deck | Investor Insights | April 2024
HomeRoots Pitch Deck | Investor Insights | April 2024
 
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service AvailableNashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
 
Arti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfArti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdf
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investors
 
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAIGetting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
 
Pre Engineered Building Manufacturers Hyderabad.pptx
Pre Engineered  Building Manufacturers Hyderabad.pptxPre Engineered  Building Manufacturers Hyderabad.pptx
Pre Engineered Building Manufacturers Hyderabad.pptx
 
Falcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business Growth
 
Durg CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN durg ESCORTS
Durg CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN durg ESCORTSDurg CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN durg ESCORTS
Durg CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN durg ESCORTS
 
Berhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGBerhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 

Psm vpppa reg v

  • 1. Draft 5 29 2012 Process Safety Management John Newquist
  • 3. Outline of Standard • Application • Pre-Start up Safety • Employee Review Participation • Mechanical Integrity • Process Safety • Hot Work (Non-routine Information Work Authorizations) • Process Hazard • Management of Analysis Change • Operating Procedures • Incident Investigation • Employee Training • Emergency Planning • Contractors and Response • Compliance Audits
  • 4. Trends • CHEM NEP • Ammonia • Sigcases • Repeat Violations
  • 5. P&IDs • 119(d)(3)(i)(B) • Relief Valves not in P&ID • P&ID indicated flame arrestors that did not exist. • P&ID did not indicate correct piping connections to vessels. Incorrect diameters of piping. • P&ID did not show LEL detectors and interlocks.
  • 6. P&IDs • 119(d)(3)(i)(B) • No design basis for relief valves on reactor • Valve tags were reversed, mislabeled • HF vent line was not marked • HF dump tank was not identified. • Three way valves were not identified • Equipment were transposed on the diagrams
  • 7. Process Safety Information • 119(d)(3)(i)(H) PSI did not list: • Cutout devices and Interlocks • High and low level sensors • Ammonia detectors • High and low pressure devices • Emergency Stop Buttons • Electrical Classification of Equipment
  • 8. RAGAGEP • 119(d)(3)(ii) • U-1 Form missing for pressure vessel • Mechanical room for ammonia had no emergency ventilation • Electrical Classification of equipment missing • Venting Flanges not meet ANSI/ASME 31.3 • No documentation that piping fit for service per API 570 • Manual block valves were located down stream of automatic dump valves (Hydrogen Fluoride Industry Practice Institute or HFIPI) • HF tanks not sized 1.5x for anticipated deliveries. HFIPI • HF dump tank did not have capacity of largest HF tank. HFIPI • HF liquid flow velocity exceeded 5.9 feet/second • Eye wash and shower were not configured to sound in the control room. HFIPI • No valve capping kit for HF rail car unloading • High pressure vent lines were not labeled. • Relief valve discharge 3.5` above platform vs. 15 feet. (IIAR 2-2008)
  • 9. PHA • 119(e)(1) • No PHA on the Hydrogen Storage tank • PHA missing several elements • PHA did not address failure of ventilation • PHA did not address previous fires. • PHA did not previous piping failures. • PHA did not address previous failures of cooling systems
  • 10. PHA • 119(e)(3)(i) The hazards of the process; • The hazard of power failure was not discussed in the PHA. • The Hazard of natural gas draining to the surge drum too long. • The hazard of releasing material in the neutralization pits • The hazard of weight of hoses on pipe nipples was not addressed • The Hazards of venting flanges was not addressed in the PHA. • The hazard of forklift traffic was not addressed.
  • 11. PHA • 119(e)(3)(v) • No analysis of facility siting issues related to formaldehyde dispersion • Building siting and how affected by the ammonia process • Ammonia system including piping, recirculator, chiller, receiver, and condensors were located to the roadway and subject to vehicle impact.
  • 12. PHA • 119(e)(3)(vi) • Human factor • Fatigue • No consider of opening block valves downstream of remote operated dump valve • Second and third shift training • People on vacation leave • Operational overload during emergencies • Operation interactions
  • 13. PHA • 119(e)(5) • PHA items not resolved for years • PHA did not address team finding and recommendations such as • Installing back flow prevention when adding flammable liquids in a tank • Automatic Pressure controls for Nitrogen • Adding relief valves • Facility siting for control rooms • Reconfigurations of valves issue on PHA was not resolved.
  • 14. Operating Procedures • 119(f)(1) • No written procedures for maintaining the ammonia systems • No procedures for communicating issues during shift changes • No procedures for upset condition or avoiding deviations beyond operating limits. • Transferring chemicals from pit to pit • Neutralization of chemicals
  • 15. Operating Procedures • 119(f)(1)(i)(E) • No procedures for when discharge pressure, suction pressure, discharge temperature, lubrication oil pressure, and lubrication oil temperature exceed normal operating range • No Specific steps to stop an emergency • No identification of emergency upset conditions and procedures to take to resolve it. • No procedure for emergency operations for transfer of chemicals out a Surge tank • No clear procedures for emptying HF tanks with isolating nitrogen systems
  • 16. Operating Procedures • 119(f)(3) • No certification of operating procedures annually.
  • 17. Safe Work Practices • 119(f)(4) • No safe work procedures developed for contractors or maintenance employees working on PSM covered processes for • Lockout • Confined space • Hot works
  • 18. Mechanical Integrity • 119(j)(2) No inspection procedures • Pressure Vessels • Piping, components, Hose adapters • Pump • Venting Flanges • Compressors and cutout switches • Relief Systems and change out schedule • Emergency Shutdown Systems • Valves requiring Carseals • No Procedures for torquing bolts
  • 19. Mechanical Integrity • 119(j)(4)(i) No inspection of • Relief valves • Pressure vessels (Oil pot, Accumulator, Receiver, and Transfer Drum) • Ammonia Feed Pumps • Venting flanges • Pipe Nipples, Deadlegs, Inspection ports, hose adapters • High Level alarms and emergency shutdown systems.
  • 20. Mechanical Integrity • 119(j)(4)(ii) • No authorized API 570/574 piping inspector or piping inspections • No API 510 pressure vessel inspector • No corrosion rates established for pressure vessels • Pump not maintained and lubricated per manufacturer’s recommendations • Rupture Disk was not replaced per manufacturer’s recommendations • No 100% Radiography or Ultrasonic testing on process pipe weld repair per ANSI B31.1 • No fitness for service for repairs per API 579 for tanks undergoing repair at head nozzles
  • 21. Mechanical Integrity • 119(j)(4)(iii) • No annual piping inspection • No API internal pressure vessel inspection • No inspection testing of the condensate vapor system for buildup that might clog the system. • No hydrostatic testing of HF tanks • No testing or exercising of HF vent valves/dump valves • Not testing compressor cutout switches • Blast Evaporators, heat exchangers not inspected • No pump inspections
  • 22. Management of Change • 119(L)(1) • No implementation of procedures after • Replacing manual valves with pneumatic actuated valves. • Installing a LEL detector • Disconnection of the Cooling water System • Installing an alarm on the quench system • Expanding Toulene tank system • Leak at Relief Header Rupture disk • Bolt torquing procedure change • After making changes in the Ammonia system • No MOC for condenser removed from process
  • 23. Incident Investigation • 119(m)(1) • No incident investigation for • Ice buildup and cracks in evaporator coils • Prior incident of adding high temperature product to flammables • Prior ammonia release. • Prior corrosion in pipes
  • 24. Compliance Audits • 119(o)(1) • No PSM evaluation audits were conducted • No audits of Mechanical integrity, Management of Change, PHA, and Emergency Response.
  • 25. Other Issues • Lockout • Emergency Response • Confined Space Rescue • Electrical Classification • Hot Works • Boiler Safety
  • 26. Two Investigators • In most of the cases that we investigate, we have found that most firms completely ignore the 1910.119(j)(5) requirement, and don’t even consider doing an MOC for a temporary change that meets the requirements of 1910.119(l). • We have two or three cases in our backlog of open cases that deal exactly with these issues. Guess the refinery NEP is having some impact.
  • 27. More Comments • I fully agree on the MOC’s; they are called by the workers “Matter of Convenience” because they believe they are used to justify exceptions and deviations. • I would add a couple to your list; PSSR (Pre Start-up Safety Review) and organizational issues. • I just reviewed a couple of investigations where there was an unexpected shutdown on a portion of the unit and in a rush to get the unit back up (they did not fully understand why it had shutdown) and they ended up in a more serious situation. • Most companies only apply the PSSR part of the PSM standard to a cold start, and even the procedures are written for a cold start and do not work for hot restarts.
  • 28. Summary • Identify the top risks in the facility • Look at corrosion monitoring on pipes and vessels, • Pump vibration leads to failures and fires. • Procedures related to boiler startup, hot works, • Evaluate hydrogen sulfide monitoring, hydrofluoric acid, • Address fatigue and control panel alarms during start ups, • Management of change is slipping. • Gasket torquing procedures should be reviewed as well as gasket compatibility for service, • Relief valve inspection and testing is a must. • Facility siting is ever present
  • 29. 312-353-5977 Facebook….john newquist johnanewquist@gmail.com Twitter is johnanewquist Newquist.john@dol.gov LinkedIn is john newquist
  • 30. Further  This was prepared as a collaborative effort several friends as a preliminary aid for anyone in the safety and health field.  These are just some the issues. A comprehensive job hazard analysis should be conducted for any task where someone can get hurt.  This is not an official OSHA publication. Those will be on the OSHA.gov website.  If you see any errors my email is Newquist.john@dol.gov  312-353-5977  I want to thank Bryan H. Art D. Jim L. Clyde T. Mark K. and Janet S. for all their assistance in answering questions and providing insight to the many hazards in this sector.

Notas do Editor

  1. PSM is an elemental approach. These elements are (in order as they appear in the standard):
  2. 1910.119(d)(3)(i)(B) Piping and instrument diagrams (P&ID's); Cargill, Am Pack, Case farms, Loveland Products
  3. Akzo Morris, Honeywell,
  4. 1910.119(d)(3)(i)(H) Safety systems (e.g. interlocks, detection or suppression systems). Cargill, Bostik
  5. 1910.119(d)(3)(ii) The employer shall document that equipment complies with recognized and generally accepted good engineering practices. Cargill, Bostik, Exxon-mobil, Equistar, Honeywell, Pilgrims Pride, Midwest Biofuels, Niagara Coop, Sorrento Lactals
  6. 1910.119(e)(1) The employer shall perform an initial process hazard analysis (hazard evaluation) on processes covered by this standard. The process hazard analysis shall be appropriate to the complexity of the process and shall identify, evaluate, and control the hazards involved in the process. Employers shall determine and document the priority order for conducting process hazard analyses based on a rationale which includes such considerations as extent of the process hazards, number of potentially affected employees, age of the process, and operating history of the process. The process hazard analysis shall be conducted as soon as possible, but not later than the following schedule: Azko, am pack,
  7. 1910.119(e)(3)(i) The hazards of the process; Marathon 2007 OH, Exxon Mobil 2010m midwest biofuels,
  8. 1910.119(e)(3)(v) Facility siting Columbus chemical, case farms, Loveland Products, midwest biofuels.
  9. 1910.119(e)(3)(vi) Human factors; and Cal OSHA, Honeywell, Case Farm
  10. 1910.119(e)(5) The employer shall establish a system to promptly address the team's findings and recommendations; assure that the recommendations are resolved in a timely manner and that the resolution is documented; document what actions are to be taken; complete actions as soon as possible; develop a written schedule of when these actions are to be completed; communicate the actions to operating, maintenance and other employees whose work assignments are in the process and who may be affected by the recommendations or actions. Equistar, Honeywell many others
  11. Bostik, cargill, marathon, QG LLC, Midwest Biofuel, Niagara Coop, 1910.119(f)(1) The employer shall develop and implement written operating procedures that provide clear instructions for safely conducting activities involved in each covered process consistent with the process safety information and shall address at least the following elements.
  12. 1910.119(f)(1)(i)(E) Emergency Operations; Cargill, Marathon
  13. QG LLC, Columbus chemical and others 1910.119(f)(3) The operating procedures shall be reviewed as often as necessary to assure that they reflect current operating practice, including changes that result from changes in process chemicals, technology, and equipment, and changes to facilities. The employer shall certify annually that these operating procedures are current and accurate.
  14. Am pack, QG LLC, 1910.119(f)(4) The employer shall develop and implement safe work practices to provide for the control of hazards during operations such as lockout/tagout; confined space entry; opening process equipment or piping; and control over entrance into a facility by maintenance, contractor, laboratory, or other support personnel. These safe work practices shall apply to employees and contractor employees.
  15. Several and exxon mobil. QG LLC, Honeywell, Case Farm, Loveland products 1910.119(j)(2) Written procedures. The employer shall establish and implement written procedures to maintain the on-going integrity of process equipment.
  16. Also AKZO, Exxon-mobil, Honeywell, Niagrara COOP, 1910.119(j)(4)(i) Inspections and tests shall be performed on process equipment.
  17. Azko, ampack, 1910.119(j)(4)(ii) Inspection and testing procedures shall follow recognized and generally accepted good engineering practices.
  18. Cargill,azko, bostik, pilgrim pride, sorrento lactals IIAR Bulletin requires annual inspections. 1910.119(j)(4)(iii) The frequency of inspections and tests of process equipment shall be consistent with applicable manufacturers' recommendations and good engineering practices, and more frequently if determined to be necessary by prior operating experience.
  19. QG LLC and many others 1910.119(l)(1) The employer shall establish and implement written procedures to manage changes (except for "replacements in kind") to process chemicals, technology, equipment, and procedures; and, changes to facilities that affect a covered process.
  20. Cargill, bostik, Case farm, Midwest Biofuels, 1910.119(m)(1) The employer shall investigate each incident which resulted in, or could reasonably have resulted in a catastrophic release of highly hazardous chemical in the workplace.
  21. QG LLC, Columbus Chemical, Loveland Products and many others. 1910.119(o)(1) Employers shall certify that they have evaluated compliance with the provisions of this section at least every three years to verify that the procedures and practices developed under the standard are adequate and are being followed.