Basic Steps of Mine design and Scheduling
Geological Model
Data from the exploration boreholes is captured and using a modelling software the
ore body is modelled to represent the ore body solid having different grades.
Based on the Geo-tech
recommendation the pit is
designed with the defined bench
parameters (heights and slopes,
haulage) to maximise the ore
recovery.
Pit designing
Ore Body
Block modelling and Reserves estimation
Strips–Forevery50m
Blocks – For every 50m
The whole pit is divided into Strips and Blocks with the defined dimensions (Example: 50m
Strips x 50m Blocks) vertically and with the Bench heights in a horizontal plane, this forms a
block model.
Bench-1
Bench-2
Bench-3
Bench-4
Bench-5
Bench-6
Ore Body
Block modelling and Reserves estimation
The waste and ore reserves including the quality parameters are calculated for each
individual block. Which can be reported in the desired format. The volumes and spatial data
representing the roof and floor of each block also are exported into a CSV file for importing
into a scheduling software.
Dump Designing & Reserves
Bench-7
Bench-6
Bench-4
Bench-3
Bench-2
Bench-1
The similar designing, blocks generation and reserving is done for both external and internal
dumps. The volumes of each block along with the roof and floor polygons are exported into
a CSV file from the design software to import back to scheduling software.
Scheduling Softwares
There are different scheduling softwares available in the market. The predominant software
for scheduling are XPAC and Deswik and the latest one is SPRY.
Scheduling Setup
This presentation details the general scheduling methodology (which is similar in XPAC)
Major Steps:
• Importing the reserves and Spatial data
• Validation and Aggregation
• Calendar creation
• Process Definition – Productive and Non productive
• Equipment Definition and defining scheduling quantities
• Roster restrictions
• Creating the dependency rules
• Pre-scheduling
• Defining the input path for each equipment
• Running the Schedule
• Generation of the Output reports, Stage Plans, Gant Charts, etc.
Scheduling – Importing and Aggregation
The Reserve blocks including the
spatial data are imported into the
scheduling software. Validation of the
data done and assign the default
values for the parameters which have
invalid data. Aggregation of the seams
and waste layers is done by defining
the minimum thickness for each of
them.
Before Aggregation After Aggregation
Waste Waste
Seam-1A
Seam-1B
Waste
Waste
Waste
Seam-1
Seam-2A
Seam-2B
Seam-3 Seam-3
Scheduling - Calendar
Define the Calendar either Daily, Monthly or Yearly based on the
requirement. Define the start date for each period.
It is possible to define the equipment KPIs for each period in the
Calendar and can be used for scheduling.
WEEK 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53
MON 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26
TUES 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27
WED 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28
THURS 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29
FRI 26 2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30
SAT 27 3 10 17 24 1 8 15 22 29 5 12 19 26 3 10 17 24 31
SUN 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25
PUBLIC HOLIDAYS KEY REPORTING DATES
New Year's Day 3 Jan Internal Site MPR / MOP Inputs Sign-Off
Australia Day 26 Jan Agree ROM Schedule with HOO and fwd to ICC
Good Friday 22 Apr Agree ICC Schedule with HOO & GM
Easter Saturday 23 Apr SLT MOP Review and MOP finalised
Easter Monday (QLD) 26 Apr Month end close
Anzac Day 25 Apr Actuals due, site replications
Labour Day (QLD) 2 May (Survey Physicals and Financials)
Queen's Birthday 13 Jun AAMC MPR's
Royal Queensland Show (Brisbane only) 17 Aug AAMC QPR's
Labour Day (NSW) 3 Oct London MPR & QPR's, Plan Reviews
Christmas Day 26 Dec
Boxing Day 27 Dec Budget Financials Complete in CoalMIS
QLD SCHOOL HOLIDAYS 16th Apr - 25th Apr
25th Jun - 10th Jul CoalMIS 1st Review of 2011 (6+6) & 2012-2014 Plan 6 Jul
17th Sep - 2nd Oct CoalMIS Finalise 2011 (7+5) & 2012-2014 Plan 16 Aug
10th Dec - 22rd Jan CoalMIS Update 2011 (8+4) & 2012-2014 Plan 2 Sep
NSW SCHOOL HOLIDAYS 9th Apr - 25th Apr
2nd Jul - 17th Jul London Plan Reviews 21 Sep & 9 Nov
24th Sep - 9th Oct
21st Dec - 26th Jan
(5 weeks) (4 weeks) (5 weeks) (4.9 weeks)
SEPTEMBER OCTOBER NOVEMBER DECEMBER
2011 Reporting Calendar
(As at 23 August 2011 - Updated for Monthly MOPs from September)
Scheduling - Processes
Define the Processes which can be
-Productive like
- Topsoil removal
- Drilling and Blasting
- Waste Mining
- Ore Mining
- Non Productive like
- Relocation
- Maintenance
- Wait on other process
- Wet Weather
- Un Scheduled...
Scheduling – Equipment
Define the equipment and assign the Process for each of them and
assign the scheduled quantity field. KPIs (Rate, Availability and
Utilisation) can be assigned for each equipment or can be referred to
the Calendar for each period, if it is varying.
More than once process can be assigned to an equipment or a
particular process can be done using a particular equipment.
Equipments typically
- Draglines
- Rope/ Electric Shovels
- Diggers or Excavators
- Drills
- Dozers
- Loaders
Scheduling – Roster restrictions & Dependencies
Define the roster restrictions like certain equipment work in certain
periods, or 5 day working only, or any other working roster or certain
equipment can not start until certain time.
Dependency rules are set. This is basically defining the order of mining
that is the lower block cant be mined until the blocks on the top of that
is mined out. It can be once process dependent on other like drill and
blast is done only when top soil removal is finished. Inpit dumping is
only possible when mining is finished and the defined minimum area is
available for dumping. All these can be defined under dependency rule.
Scheduling – Preschedule
If it is a new mine then there is no preschedule, but if you are working
on an existing mine with some mined out areas then the blocks which
fall in the mined out area need to be defined as mined out, this process
is called prescheduling. This will allow the alignment of the short term
and medium term scheduling if it is done separately.
Actual Preschedule Forecast
Scheduling – Input path for Equipment
Define the path for each of the equipment – this is basically assigning
the blocks to each equipment in a sequential order which satisfies the
dependency conditions.
The input path is modified after running the schedule and based on the
results produced. Example, if one process is waiting on other process
then the path is changed so as to fully utilise the equipment and make
sure all the equipments are working in the available time after all the
delays are removed from the calendar time.
Scheduling – Run and Reports generation
Schedule is run at end. Every time the reserve data or path of the
equipment changes, it is re run to produce the scheduled quantities for
the periods defined in the Calendar.
Then the reports are generated based on the requirement, Gant charts
are produced based on the equipment, pit or any other condition.
Stage plans can be produced in various formats for each period of the
Calendar.
Scheduling – Destination Scheduling & Haulage
Destination quantity field is assigned for each of the scheduling equipment and
Destination path is defined for filling the dumps based on the priority.
Haulage – is also a big thing to discuss, but in a nut shell it is the path from
Source to Destination and cycle times are worked out based on the road
conditions and truck parameters giving the truck numbers for each haulage path.
Thanks

Mais conteúdo relacionado

Mais procurados

Open pit mining
Open pit miningOpen pit mining
Open pit mining
gereltuya
 

Mais procurados (20)

Mine planning
Mine planning Mine planning
Mine planning
 
2 surface mine planning
2 surface mine planning2 surface mine planning
2 surface mine planning
 
Drilling and blasting
Drilling and blastingDrilling and blasting
Drilling and blasting
 
Open pit mining
Open pit miningOpen pit mining
Open pit mining
 
Topic 7-mining methods-part iii -surface mining- placer mining
Topic 7-mining methods-part iii -surface mining- placer miningTopic 7-mining methods-part iii -surface mining- placer mining
Topic 7-mining methods-part iii -surface mining- placer mining
 
Open pit mining
Open pit miningOpen pit mining
Open pit mining
 
Surface mining planning and design of open pit mining
Surface mining planning and design of open pit miningSurface mining planning and design of open pit mining
Surface mining planning and design of open pit mining
 
Sampling techniques for mineral deposit
Sampling techniques for mineral depositSampling techniques for mineral deposit
Sampling techniques for mineral deposit
 
Caving Underground Mining Methods (longwall, Sublevel caving, & Block caving)
Caving Underground Mining Methods (longwall, Sublevel caving, &  Block caving)Caving Underground Mining Methods (longwall, Sublevel caving, &  Block caving)
Caving Underground Mining Methods (longwall, Sublevel caving, & Block caving)
 
BENCH & ROAD STANDARS IN OPENCAST MINES.pptx
BENCH & ROAD STANDARS IN OPENCAST MINES.pptxBENCH & ROAD STANDARS IN OPENCAST MINES.pptx
BENCH & ROAD STANDARS IN OPENCAST MINES.pptx
 
Topic 5: Mining Methods-Part I-Surface mining
Topic 5: Mining Methods-Part I-Surface mining Topic 5: Mining Methods-Part I-Surface mining
Topic 5: Mining Methods-Part I-Surface mining
 
Blast hole drill
Blast hole drillBlast hole drill
Blast hole drill
 
Blasting
BlastingBlasting
Blasting
 
Drilling in Surface Mine.pdf
Drilling in Surface Mine.pdfDrilling in Surface Mine.pdf
Drilling in Surface Mine.pdf
 
Blasting and rock fragmentation
Blasting and rock fragmentationBlasting and rock fragmentation
Blasting and rock fragmentation
 
TYPES OF VENTILATION SYSTEMS IN MINES - CENTRAL BOUNDARY U W Z
TYPES OF VENTILATION SYSTEMS IN MINES - CENTRAL BOUNDARY U W ZTYPES OF VENTILATION SYSTEMS IN MINES - CENTRAL BOUNDARY U W Z
TYPES OF VENTILATION SYSTEMS IN MINES - CENTRAL BOUNDARY U W Z
 
Mine waste dump
Mine waste dumpMine waste dump
Mine waste dump
 
Mine planning feasibility report
Mine planning feasibility reportMine planning feasibility report
Mine planning feasibility report
 
Rock blasting for mining
Rock blasting  for miningRock blasting  for mining
Rock blasting for mining
 
Mine Opening and Development
Mine Opening and DevelopmentMine Opening and Development
Mine Opening and Development
 

Semelhante a Mine scheduling process

IRS Sep2016 Vonline
IRS Sep2016 VonlineIRS Sep2016 Vonline
IRS Sep2016 Vonline
Mahdi Athari
 
13 lecture project management
13 lecture project management13 lecture project management
13 lecture project management
Ahmad Basim Hamza
 
Functions of production planning and control
Functions of production planning and controlFunctions of production planning and control
Functions of production planning and control
Vignesh Jayakumar
 
Functions of production planning and control 2
Functions of production planning and control 2Functions of production planning and control 2
Functions of production planning and control 2
Vignesh Jayakumar
 
Pert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertPert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gert
Raj J Das
 

Semelhante a Mine scheduling process (20)

EWSO
EWSOEWSO
EWSO
 
C03.05-Scheduling.key.pdf
C03.05-Scheduling.key.pdfC03.05-Scheduling.key.pdf
C03.05-Scheduling.key.pdf
 
IRS Sep2016 Vonline
IRS Sep2016 VonlineIRS Sep2016 Vonline
IRS Sep2016 Vonline
 
PM-Problems.pptx
PM-Problems.pptxPM-Problems.pptx
PM-Problems.pptx
 
State of Hawaii Digital Leveling Project
State of Hawaii Digital Leveling ProjectState of Hawaii Digital Leveling Project
State of Hawaii Digital Leveling Project
 
The construction programme - assurance and controls
The construction programme - assurance and controlsThe construction programme - assurance and controls
The construction programme - assurance and controls
 
13 lecture project management
13 lecture project management13 lecture project management
13 lecture project management
 
Functions of production planning and control
Functions of production planning and controlFunctions of production planning and control
Functions of production planning and control
 
Functions of production planning and control 2
Functions of production planning and control 2Functions of production planning and control 2
Functions of production planning and control 2
 
production scheduling
production schedulingproduction scheduling
production scheduling
 
Ianson
IansonIanson
Ianson
 
Topic 5 Production Sequencing and Scheduling.ppt
Topic 5 Production Sequencing and Scheduling.pptTopic 5 Production Sequencing and Scheduling.ppt
Topic 5 Production Sequencing and Scheduling.ppt
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
 
Lecture 5- Monitoring and Controlling Projects.ppt
Lecture 5- Monitoring and Controlling Projects.pptLecture 5- Monitoring and Controlling Projects.ppt
Lecture 5- Monitoring and Controlling Projects.ppt
 
Program Management 2.0: Schedule Prediction Accuracy
Program Management 2.0: Schedule Prediction AccuracyProgram Management 2.0: Schedule Prediction Accuracy
Program Management 2.0: Schedule Prediction Accuracy
 
WELL CONSTRUCTION DIGITAL SOLUTION FOR AUTOMATION & OPTIMIZATION
WELL CONSTRUCTION DIGITAL SOLUTION FOR AUTOMATION & OPTIMIZATIONWELL CONSTRUCTION DIGITAL SOLUTION FOR AUTOMATION & OPTIMIZATION
WELL CONSTRUCTION DIGITAL SOLUTION FOR AUTOMATION & OPTIMIZATION
 
5.Production Scheduling and Sequencing.pptx
5.Production Scheduling and Sequencing.pptx5.Production Scheduling and Sequencing.pptx
5.Production Scheduling and Sequencing.pptx
 
50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only
 
Pert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertPert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gert
 
ABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning Slides
 

Mais de VR M

Energy - India (11th Plan)
Energy - India (11th Plan)Energy - India (11th Plan)
Energy - India (11th Plan)
VR M
 
Methods of extraction in Opencast mine
Methods of extraction in Opencast mineMethods of extraction in Opencast mine
Methods of extraction in Opencast mine
VR M
 
Vulcan tutorial 01
Vulcan tutorial 01Vulcan tutorial 01
Vulcan tutorial 01
VR M
 
Project Management (PMP Material)
Project Management (PMP Material)Project Management (PMP Material)
Project Management (PMP Material)
VR M
 
Openpit Design Fundas
Openpit Design FundasOpenpit Design Fundas
Openpit Design Fundas
VR M
 
Bolter miner @ Russia
Bolter miner @ RussiaBolter miner @ Russia
Bolter miner @ Russia
VR M
 
Longwall AFC changing - innovation
Longwall AFC changing - innovationLongwall AFC changing - innovation
Longwall AFC changing - innovation
VR M
 
Statutory clearances required to start a greenfield captive opencast coal mine
Statutory clearances required to start a greenfield captive opencast coal mineStatutory clearances required to start a greenfield captive opencast coal mine
Statutory clearances required to start a greenfield captive opencast coal mine
VR M
 
Top ten in world
Top ten in worldTop ten in world
Top ten in world
VR M
 
Highwall Mining Technology
Highwall Mining TechnologyHighwall Mining Technology
Highwall Mining Technology
VR M
 
Legal flow schemes for a greenfield mining project
Legal flow schemes for a greenfield mining projectLegal flow schemes for a greenfield mining project
Legal flow schemes for a greenfield mining project
VR M
 
Mine communication sysetms
Mine communication sysetmsMine communication sysetms
Mine communication sysetms
VR M
 
Mine Tech Seminar '10 - Gist of Papers
Mine Tech Seminar '10 - Gist of PapersMine Tech Seminar '10 - Gist of Papers
Mine Tech Seminar '10 - Gist of Papers
VR M
 
Reduction of risk from roof and side fall in Indian coal mines
Reduction of risk from roof and side fall in Indian coal minesReduction of risk from roof and side fall in Indian coal mines
Reduction of risk from roof and side fall in Indian coal mines
VR M
 
goaves effect on subsidence
goaves effect on subsidencegoaves effect on subsidence
goaves effect on subsidence
VR M
 
Longwall - The road ahead
Longwall - The road aheadLongwall - The road ahead
Longwall - The road ahead
VR M
 
Design of Longwall for 2 seam of Ramagundam
Design of Longwall for 2 seam of RamagundamDesign of Longwall for 2 seam of Ramagundam
Design of Longwall for 2 seam of Ramagundam
VR M
 
Longwall exp india-expectations
Longwall exp india-expectationsLongwall exp india-expectations
Longwall exp india-expectations
VR M
 
Future Longwalls in India
Future Longwalls in IndiaFuture Longwalls in India
Future Longwalls in India
VR M
 

Mais de VR M (20)

Dragline Planning
Dragline PlanningDragline Planning
Dragline Planning
 
Energy - India (11th Plan)
Energy - India (11th Plan)Energy - India (11th Plan)
Energy - India (11th Plan)
 
Methods of extraction in Opencast mine
Methods of extraction in Opencast mineMethods of extraction in Opencast mine
Methods of extraction in Opencast mine
 
Vulcan tutorial 01
Vulcan tutorial 01Vulcan tutorial 01
Vulcan tutorial 01
 
Project Management (PMP Material)
Project Management (PMP Material)Project Management (PMP Material)
Project Management (PMP Material)
 
Openpit Design Fundas
Openpit Design FundasOpenpit Design Fundas
Openpit Design Fundas
 
Bolter miner @ Russia
Bolter miner @ RussiaBolter miner @ Russia
Bolter miner @ Russia
 
Longwall AFC changing - innovation
Longwall AFC changing - innovationLongwall AFC changing - innovation
Longwall AFC changing - innovation
 
Statutory clearances required to start a greenfield captive opencast coal mine
Statutory clearances required to start a greenfield captive opencast coal mineStatutory clearances required to start a greenfield captive opencast coal mine
Statutory clearances required to start a greenfield captive opencast coal mine
 
Top ten in world
Top ten in worldTop ten in world
Top ten in world
 
Highwall Mining Technology
Highwall Mining TechnologyHighwall Mining Technology
Highwall Mining Technology
 
Legal flow schemes for a greenfield mining project
Legal flow schemes for a greenfield mining projectLegal flow schemes for a greenfield mining project
Legal flow schemes for a greenfield mining project
 
Mine communication sysetms
Mine communication sysetmsMine communication sysetms
Mine communication sysetms
 
Mine Tech Seminar '10 - Gist of Papers
Mine Tech Seminar '10 - Gist of PapersMine Tech Seminar '10 - Gist of Papers
Mine Tech Seminar '10 - Gist of Papers
 
Reduction of risk from roof and side fall in Indian coal mines
Reduction of risk from roof and side fall in Indian coal minesReduction of risk from roof and side fall in Indian coal mines
Reduction of risk from roof and side fall in Indian coal mines
 
goaves effect on subsidence
goaves effect on subsidencegoaves effect on subsidence
goaves effect on subsidence
 
Longwall - The road ahead
Longwall - The road aheadLongwall - The road ahead
Longwall - The road ahead
 
Design of Longwall for 2 seam of Ramagundam
Design of Longwall for 2 seam of RamagundamDesign of Longwall for 2 seam of Ramagundam
Design of Longwall for 2 seam of Ramagundam
 
Longwall exp india-expectations
Longwall exp india-expectationsLongwall exp india-expectations
Longwall exp india-expectations
 
Future Longwalls in India
Future Longwalls in IndiaFuture Longwalls in India
Future Longwalls in India
 

Último

Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
MsecMca
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
Epec Engineered Technologies
 

Último (20)

Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdf
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 

Mine scheduling process

  • 1.
  • 2. Basic Steps of Mine design and Scheduling
  • 3. Geological Model Data from the exploration boreholes is captured and using a modelling software the ore body is modelled to represent the ore body solid having different grades.
  • 4. Based on the Geo-tech recommendation the pit is designed with the defined bench parameters (heights and slopes, haulage) to maximise the ore recovery. Pit designing Ore Body
  • 5. Block modelling and Reserves estimation Strips–Forevery50m Blocks – For every 50m The whole pit is divided into Strips and Blocks with the defined dimensions (Example: 50m Strips x 50m Blocks) vertically and with the Bench heights in a horizontal plane, this forms a block model. Bench-1 Bench-2 Bench-3 Bench-4 Bench-5 Bench-6 Ore Body
  • 6. Block modelling and Reserves estimation The waste and ore reserves including the quality parameters are calculated for each individual block. Which can be reported in the desired format. The volumes and spatial data representing the roof and floor of each block also are exported into a CSV file for importing into a scheduling software.
  • 7. Dump Designing & Reserves Bench-7 Bench-6 Bench-4 Bench-3 Bench-2 Bench-1 The similar designing, blocks generation and reserving is done for both external and internal dumps. The volumes of each block along with the roof and floor polygons are exported into a CSV file from the design software to import back to scheduling software.
  • 8. Scheduling Softwares There are different scheduling softwares available in the market. The predominant software for scheduling are XPAC and Deswik and the latest one is SPRY.
  • 9. Scheduling Setup This presentation details the general scheduling methodology (which is similar in XPAC) Major Steps: • Importing the reserves and Spatial data • Validation and Aggregation • Calendar creation • Process Definition – Productive and Non productive • Equipment Definition and defining scheduling quantities • Roster restrictions • Creating the dependency rules • Pre-scheduling • Defining the input path for each equipment • Running the Schedule • Generation of the Output reports, Stage Plans, Gant Charts, etc.
  • 10. Scheduling – Importing and Aggregation The Reserve blocks including the spatial data are imported into the scheduling software. Validation of the data done and assign the default values for the parameters which have invalid data. Aggregation of the seams and waste layers is done by defining the minimum thickness for each of them. Before Aggregation After Aggregation Waste Waste Seam-1A Seam-1B Waste Waste Waste Seam-1 Seam-2A Seam-2B Seam-3 Seam-3
  • 11. Scheduling - Calendar Define the Calendar either Daily, Monthly or Yearly based on the requirement. Define the start date for each period. It is possible to define the equipment KPIs for each period in the Calendar and can be used for scheduling. WEEK 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 MON 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 TUES 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 WED 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 THURS 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29 FRI 26 2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 SAT 27 3 10 17 24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 SUN 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 PUBLIC HOLIDAYS KEY REPORTING DATES New Year's Day 3 Jan Internal Site MPR / MOP Inputs Sign-Off Australia Day 26 Jan Agree ROM Schedule with HOO and fwd to ICC Good Friday 22 Apr Agree ICC Schedule with HOO & GM Easter Saturday 23 Apr SLT MOP Review and MOP finalised Easter Monday (QLD) 26 Apr Month end close Anzac Day 25 Apr Actuals due, site replications Labour Day (QLD) 2 May (Survey Physicals and Financials) Queen's Birthday 13 Jun AAMC MPR's Royal Queensland Show (Brisbane only) 17 Aug AAMC QPR's Labour Day (NSW) 3 Oct London MPR & QPR's, Plan Reviews Christmas Day 26 Dec Boxing Day 27 Dec Budget Financials Complete in CoalMIS QLD SCHOOL HOLIDAYS 16th Apr - 25th Apr 25th Jun - 10th Jul CoalMIS 1st Review of 2011 (6+6) & 2012-2014 Plan 6 Jul 17th Sep - 2nd Oct CoalMIS Finalise 2011 (7+5) & 2012-2014 Plan 16 Aug 10th Dec - 22rd Jan CoalMIS Update 2011 (8+4) & 2012-2014 Plan 2 Sep NSW SCHOOL HOLIDAYS 9th Apr - 25th Apr 2nd Jul - 17th Jul London Plan Reviews 21 Sep & 9 Nov 24th Sep - 9th Oct 21st Dec - 26th Jan (5 weeks) (4 weeks) (5 weeks) (4.9 weeks) SEPTEMBER OCTOBER NOVEMBER DECEMBER 2011 Reporting Calendar (As at 23 August 2011 - Updated for Monthly MOPs from September)
  • 12. Scheduling - Processes Define the Processes which can be -Productive like - Topsoil removal - Drilling and Blasting - Waste Mining - Ore Mining - Non Productive like - Relocation - Maintenance - Wait on other process - Wet Weather - Un Scheduled...
  • 13. Scheduling – Equipment Define the equipment and assign the Process for each of them and assign the scheduled quantity field. KPIs (Rate, Availability and Utilisation) can be assigned for each equipment or can be referred to the Calendar for each period, if it is varying. More than once process can be assigned to an equipment or a particular process can be done using a particular equipment. Equipments typically - Draglines - Rope/ Electric Shovels - Diggers or Excavators - Drills - Dozers - Loaders
  • 14. Scheduling – Roster restrictions & Dependencies Define the roster restrictions like certain equipment work in certain periods, or 5 day working only, or any other working roster or certain equipment can not start until certain time. Dependency rules are set. This is basically defining the order of mining that is the lower block cant be mined until the blocks on the top of that is mined out. It can be once process dependent on other like drill and blast is done only when top soil removal is finished. Inpit dumping is only possible when mining is finished and the defined minimum area is available for dumping. All these can be defined under dependency rule.
  • 15. Scheduling – Preschedule If it is a new mine then there is no preschedule, but if you are working on an existing mine with some mined out areas then the blocks which fall in the mined out area need to be defined as mined out, this process is called prescheduling. This will allow the alignment of the short term and medium term scheduling if it is done separately. Actual Preschedule Forecast
  • 16. Scheduling – Input path for Equipment Define the path for each of the equipment – this is basically assigning the blocks to each equipment in a sequential order which satisfies the dependency conditions. The input path is modified after running the schedule and based on the results produced. Example, if one process is waiting on other process then the path is changed so as to fully utilise the equipment and make sure all the equipments are working in the available time after all the delays are removed from the calendar time.
  • 17. Scheduling – Run and Reports generation Schedule is run at end. Every time the reserve data or path of the equipment changes, it is re run to produce the scheduled quantities for the periods defined in the Calendar. Then the reports are generated based on the requirement, Gant charts are produced based on the equipment, pit or any other condition. Stage plans can be produced in various formats for each period of the Calendar.
  • 18. Scheduling – Destination Scheduling & Haulage Destination quantity field is assigned for each of the scheduling equipment and Destination path is defined for filling the dumps based on the priority. Haulage – is also a big thing to discuss, but in a nut shell it is the path from Source to Destination and cycle times are worked out based on the road conditions and truck parameters giving the truck numbers for each haulage path.