ENERGY
                           Indian Scenario (11th   Plan)




                                                           Venkat
A Gist from Planning Commission Report
Highlights of 11th Plan
• The envisaged growth
  rate of economy is 9%.

• India is 7th largest energy
  producer and 5th largest
  energy consumer in
  world.

• Estimated average peak
  shortage is 12% in 2006-
  07.
Projected Energy requirement, 2030
• The projected requirement of coal has been estimated
  assuming its calorie content to be 4000 kcal per kg and
  2865 kcal per kg for lignite.
Available Energy
              70%-HC
             Potential                     Resource
                                        70%-HC
                                       Potential




70%-HC                      70%-Coal




         6%-Coal
         10%-HC Potential
Coal Reserves of India (April 2009)
                                                  In Million Tonnes
 Formation           Proved        Indicated Inferred      Total
Gondwana
                       105,343        123,380         37,414        266,137
Coals
Tertiary Coals               477             90         506*            1,073
     Total             105,820        123,470       37,920*         267,210
* Includes 456 Mt of Inferred resources established through mapping in NE region.
Source – Ministry of Coal site.



                Energy Mix of India
Demand & Supply of Primary Energy
Energy Demand
Coal Demand & Supply Sector-wise
Company-wise coal production
       programme
Projected commercial Energy requirement
      for 2011-12 @ 9% growth rate
Growth rates of Domestic supply
Way Forward
• India is short of all energy resources. Need to expand resources
  through exploration, energy efficiency, renewables and R&D.
• Additional sources of energy like CBM must be fully exploited.
  Renewable energy sources contribution should be increased.
• More transparent policy framework that treats the different energy
  sources in similar manner.
• Institutions promoting energy conservation and improvement need
  to be strengthened.
• Subsidies and support need to be linked to outcome of renewable
  energy instead of capital investment.
• Development of robust energy R&D systems.
Energy Generation
                                                                  In MW

Capacity at      Type    Centre       State      Private       Total
the end of    Hydro      7,563.00   25,785.62    1,306.15     34,654.77
              Thermal   33,658.99   43,334.33    9,021.52     86,014.84
 10th Plan
              Nuclear    3,900.00           -            -     3,900.00
              Total     45,121.99   69,119.95   10,327.67    124,569.61#



                 Type    Centre       State      Private       Total
              Hydro      9,685.00    3,605.00    3,263.00     16,553.00
 Addition     Thermal   26,800.00   24,347.00    7,497.00     58,644.00
  during      Nuclear    3,380.00           -            -     3,380.00
 11th Plan    Total     39,865.00   27,952.00   10,760.00     78,577.00
Development of alternative Fuels
• CBM-Coal Bed Methane – 26 blocks already been offered in
  bidding.
• Gas Hydrates – National GH Programme started in 1997.
  Seismic surveys conducted in KG & Mahanadi basin.
  Potential areas are Kerala & Konkan basin.
• UCG-Underground Coal Gasification – ONGC & GAIL
  engaged for exploration.
• CTL-Coal To Liquid – Two blocks allocated to Tata & Jindal.
• Bio fuels – Planned for 5% increase of ethanol in Bio-diesel
  blended fuel.
• Oil Shale – Identified in Assam, Arunachal Pradesh &
  Nagaland estimated about 100 Billion barrels.
Thanks

Mais conteúdo relacionado

Mais procurados

Presentation To N P T I O Il & Gas Source Nov 03 1
Presentation To  N P T I  O Il &  Gas  Source  Nov 03 1Presentation To  N P T I  O Il &  Gas  Source  Nov 03 1
Presentation To N P T I O Il & Gas Source Nov 03 1
Jayanta Bora
 
LNG Penetration (1)
LNG Penetration (1)LNG Penetration (1)
LNG Penetration (1)
Paul Joy
 
Polygeneration and CCS India
Polygeneration and CCS IndiaPolygeneration and CCS India
Polygeneration and CCS India
RahulA
 
Coal synthesis gas a substitution of natural
Coal synthesis gas  a substitution of naturalCoal synthesis gas  a substitution of natural
Coal synthesis gas a substitution of natural
eeiej
 
Economics of promotions_of_r&d_of_carbon_capture
Economics of promotions_of_r&d_of_carbon_captureEconomics of promotions_of_r&d_of_carbon_capture
Economics of promotions_of_r&d_of_carbon_capture
Suresh Malluswamy
 
Power generation and demand in bangladesh
Power generation and demand in bangladeshPower generation and demand in bangladesh
Power generation and demand in bangladesh
Galib Ghani
 
WG Nuclear Energy Presentation
WG Nuclear Energy PresentationWG Nuclear Energy Presentation
WG Nuclear Energy Presentation
William Gaskell
 

Mais procurados (19)

Energy
EnergyEnergy
Energy
 
Presentation To N P T I O Il & Gas Source Nov 03 1
Presentation To  N P T I  O Il &  Gas  Source  Nov 03 1Presentation To  N P T I  O Il &  Gas  Source  Nov 03 1
Presentation To N P T I O Il & Gas Source Nov 03 1
 
LNG Penetration (1)
LNG Penetration (1)LNG Penetration (1)
LNG Penetration (1)
 
Polygeneration and CCS India
Polygeneration and CCS IndiaPolygeneration and CCS India
Polygeneration and CCS India
 
Coal synthesis gas a substitution of natural
Coal synthesis gas  a substitution of naturalCoal synthesis gas  a substitution of natural
Coal synthesis gas a substitution of natural
 
Bede Boyle & George Edwards - Coal Ventures Limited
Bede Boyle & George Edwards - Coal Ventures LimitedBede Boyle & George Edwards - Coal Ventures Limited
Bede Boyle & George Edwards - Coal Ventures Limited
 
Economics of promotions_of_r&d_of_carbon_capture
Economics of promotions_of_r&d_of_carbon_captureEconomics of promotions_of_r&d_of_carbon_capture
Economics of promotions_of_r&d_of_carbon_capture
 
11v3 ch10
11v3 ch1011v3 ch10
11v3 ch10
 
Wayne Calder – Department of Resources, Energy and Tourism – CCS and carbon p...
Wayne Calder – Department of Resources, Energy and Tourism – CCS and carbon p...Wayne Calder – Department of Resources, Energy and Tourism – CCS and carbon p...
Wayne Calder – Department of Resources, Energy and Tourism – CCS and carbon p...
 
Atlantic Council - Maryann Locke
Atlantic Council - Maryann LockeAtlantic Council - Maryann Locke
Atlantic Council - Maryann Locke
 
Ian Macfarlane - Queensland Resources Council
Ian Macfarlane - Queensland Resources CouncilIan Macfarlane - Queensland Resources Council
Ian Macfarlane - Queensland Resources Council
 
Energy modeling approach to the global energy-mineral nexus: Exploring metal ...
Energy modeling approach to the global energy-mineral nexus: Exploring metal ...Energy modeling approach to the global energy-mineral nexus: Exploring metal ...
Energy modeling approach to the global energy-mineral nexus: Exploring metal ...
 
Power generation and demand in bangladesh
Power generation and demand in bangladeshPower generation and demand in bangladesh
Power generation and demand in bangladesh
 
Heritage Resource Bank Apr09
Heritage Resource Bank Apr09Heritage Resource Bank Apr09
Heritage Resource Bank Apr09
 
Prospect of Coal Based IGCC to Meet the Clean Energy Challenge
Prospect of Coal Based IGCC to Meet the Clean Energy ChallengeProspect of Coal Based IGCC to Meet the Clean Energy Challenge
Prospect of Coal Based IGCC to Meet the Clean Energy Challenge
 
Energy crisis of Nepal and it's sustainable solutions
Energy crisis of Nepal and  it's sustainable solutions Energy crisis of Nepal and  it's sustainable solutions
Energy crisis of Nepal and it's sustainable solutions
 
Grangemouth CCS project, Stephen Kerr, Summit Power - UKCCSRC Strathclyde Bia...
Grangemouth CCS project, Stephen Kerr, Summit Power - UKCCSRC Strathclyde Bia...Grangemouth CCS project, Stephen Kerr, Summit Power - UKCCSRC Strathclyde Bia...
Grangemouth CCS project, Stephen Kerr, Summit Power - UKCCSRC Strathclyde Bia...
 
WG Nuclear Energy Presentation
WG Nuclear Energy PresentationWG Nuclear Energy Presentation
WG Nuclear Energy Presentation
 
Energy crisis of nepal and efficiency measures in industries
Energy crisis of nepal and efficiency measures in industriesEnergy crisis of nepal and efficiency measures in industries
Energy crisis of nepal and efficiency measures in industries
 

Semelhante a Energy - India (11th Plan)

Energy Sector Pakistan
Energy Sector PakistanEnergy Sector Pakistan
Energy Sector Pakistan
Ultraspectra
 
The SAARC Grid: Policy, Regulatory, Infra-structure, Contractual Issues in C...
The SAARC Grid:Policy, Regulatory, Infra-structure, Contractual Issues in C...The SAARC Grid:Policy, Regulatory, Infra-structure, Contractual Issues in C...
The SAARC Grid: Policy, Regulatory, Infra-structure, Contractual Issues in C...
IPPAI
 
APP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.ppt
APP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.pptAPP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.ppt
APP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.ppt
somnathmahapatra6
 
GC Advisors - RPO
GC Advisors - RPOGC Advisors - RPO
GC Advisors - RPO
GCAdvisors
 
SAARC Energy Ring - a Vision to Promote Energy Security in South Asia
SAARC Energy Ring - a Vision to Promote Energy Security in South AsiaSAARC Energy Ring - a Vision to Promote Energy Security in South Asia
SAARC Energy Ring - a Vision to Promote Energy Security in South Asia
IPPAI
 

Semelhante a Energy - India (11th Plan) (20)

Developing Solar Projects under REC Mechanism in India
Developing Solar Projects under REC Mechanism in IndiaDeveloping Solar Projects under REC Mechanism in India
Developing Solar Projects under REC Mechanism in India
 
Energy Sector Pakistan
Energy Sector PakistanEnergy Sector Pakistan
Energy Sector Pakistan
 
The SAARC Grid: Policy, Regulatory, Infra-structure, Contractual Issues in C...
The SAARC Grid:Policy, Regulatory, Infra-structure, Contractual Issues in C...The SAARC Grid:Policy, Regulatory, Infra-structure, Contractual Issues in C...
The SAARC Grid: Policy, Regulatory, Infra-structure, Contractual Issues in C...
 
Fuel and energy final
Fuel and energy finalFuel and energy final
Fuel and energy final
 
presentation vsv.ppt
presentation vsv.pptpresentation vsv.ppt
presentation vsv.ppt
 
APP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.ppt
APP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.pptAPP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.ppt
APP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.ppt
 
Power procurement strategy--Mr. rohit bajaj
Power procurement strategy--Mr. rohit bajaj  Power procurement strategy--Mr. rohit bajaj
Power procurement strategy--Mr. rohit bajaj
 
Power procurement strategy-- Mr. Rohit Bajaj
Power procurement strategy-- Mr. Rohit BajajPower procurement strategy-- Mr. Rohit Bajaj
Power procurement strategy-- Mr. Rohit Bajaj
 
Corporate Overview, Narendra Kumar Verma, ONGC
Corporate Overview, Narendra Kumar Verma, ONGCCorporate Overview, Narendra Kumar Verma, ONGC
Corporate Overview, Narendra Kumar Verma, ONGC
 
GC Advisors - RPO
GC Advisors - RPOGC Advisors - RPO
GC Advisors - RPO
 
ntpc annual presentation
ntpc annual presentationntpc annual presentation
ntpc annual presentation
 
Captive Power Plants
Captive Power PlantsCaptive Power Plants
Captive Power Plants
 
SAARC Energy Ring - a Vision to Promote Energy Security in South Asia
SAARC Energy Ring - a Vision to Promote Energy Security in South AsiaSAARC Energy Ring - a Vision to Promote Energy Security in South Asia
SAARC Energy Ring - a Vision to Promote Energy Security in South Asia
 
Energy Analysis of Nigeria
Energy Analysis of NigeriaEnergy Analysis of Nigeria
Energy Analysis of Nigeria
 
01 Green Power.ppt form uit rgpv very important topic
01 Green Power.ppt form uit rgpv very important topic01 Green Power.ppt form uit rgpv very important topic
01 Green Power.ppt form uit rgpv very important topic
 
Bhutan Country Presentation at ACEF 2014
Bhutan Country Presentation at ACEF 2014Bhutan Country Presentation at ACEF 2014
Bhutan Country Presentation at ACEF 2014
 
Ntpc kahalgaon training report
Ntpc kahalgaon training reportNtpc kahalgaon training report
Ntpc kahalgaon training report
 
Report ntpc auraiya
Report ntpc auraiyaReport ntpc auraiya
Report ntpc auraiya
 
LNG Penetration
LNG PenetrationLNG Penetration
LNG Penetration
 
Ee opportunities
Ee opportunities Ee opportunities
Ee opportunities
 

Mais de VR M

Methods of extraction in Opencast mine
Methods of extraction in Opencast mineMethods of extraction in Opencast mine
Methods of extraction in Opencast mine
VR M
 
Vulcan tutorial 01
Vulcan tutorial 01Vulcan tutorial 01
Vulcan tutorial 01
VR M
 
Project Management (PMP Material)
Project Management (PMP Material)Project Management (PMP Material)
Project Management (PMP Material)
VR M
 
Haul road design
Haul road designHaul road design
Haul road design
VR M
 
Openpit Design Fundas
Openpit Design FundasOpenpit Design Fundas
Openpit Design Fundas
VR M
 
Openpit fundamentals
Openpit fundamentalsOpenpit fundamentals
Openpit fundamentals
VR M
 
Bolter miner @ Russia
Bolter miner @ RussiaBolter miner @ Russia
Bolter miner @ Russia
VR M
 
Longwall AFC changing - innovation
Longwall AFC changing - innovationLongwall AFC changing - innovation
Longwall AFC changing - innovation
VR M
 
Statutory clearances required to start a greenfield captive opencast coal mine
Statutory clearances required to start a greenfield captive opencast coal mineStatutory clearances required to start a greenfield captive opencast coal mine
Statutory clearances required to start a greenfield captive opencast coal mine
VR M
 
Top ten in world
Top ten in worldTop ten in world
Top ten in world
VR M
 
Highwall Mining Technology
Highwall Mining TechnologyHighwall Mining Technology
Highwall Mining Technology
VR M
 
Legal flow schemes for a greenfield mining project
Legal flow schemes for a greenfield mining projectLegal flow schemes for a greenfield mining project
Legal flow schemes for a greenfield mining project
VR M
 
Mine communication sysetms
Mine communication sysetmsMine communication sysetms
Mine communication sysetms
VR M
 
Mine Tech Seminar '10 - Gist of Papers
Mine Tech Seminar '10 - Gist of PapersMine Tech Seminar '10 - Gist of Papers
Mine Tech Seminar '10 - Gist of Papers
VR M
 
Reduction of risk from roof and side fall in Indian coal mines
Reduction of risk from roof and side fall in Indian coal minesReduction of risk from roof and side fall in Indian coal mines
Reduction of risk from roof and side fall in Indian coal mines
VR M
 
goaves effect on subsidence
goaves effect on subsidencegoaves effect on subsidence
goaves effect on subsidence
VR M
 
Longwall - The road ahead
Longwall - The road aheadLongwall - The road ahead
Longwall - The road ahead
VR M
 

Mais de VR M (20)

Dragline Planning
Dragline PlanningDragline Planning
Dragline Planning
 
Spry Scheduling and Haulage model - Tutorial
Spry Scheduling and Haulage model - TutorialSpry Scheduling and Haulage model - Tutorial
Spry Scheduling and Haulage model - Tutorial
 
Mine scheduling process
Mine scheduling processMine scheduling process
Mine scheduling process
 
Methods of extraction in Opencast mine
Methods of extraction in Opencast mineMethods of extraction in Opencast mine
Methods of extraction in Opencast mine
 
Vulcan tutorial 01
Vulcan tutorial 01Vulcan tutorial 01
Vulcan tutorial 01
 
Project Management (PMP Material)
Project Management (PMP Material)Project Management (PMP Material)
Project Management (PMP Material)
 
Haul road design
Haul road designHaul road design
Haul road design
 
Openpit Design Fundas
Openpit Design FundasOpenpit Design Fundas
Openpit Design Fundas
 
Openpit fundamentals
Openpit fundamentalsOpenpit fundamentals
Openpit fundamentals
 
Bolter miner @ Russia
Bolter miner @ RussiaBolter miner @ Russia
Bolter miner @ Russia
 
Longwall AFC changing - innovation
Longwall AFC changing - innovationLongwall AFC changing - innovation
Longwall AFC changing - innovation
 
Statutory clearances required to start a greenfield captive opencast coal mine
Statutory clearances required to start a greenfield captive opencast coal mineStatutory clearances required to start a greenfield captive opencast coal mine
Statutory clearances required to start a greenfield captive opencast coal mine
 
Top ten in world
Top ten in worldTop ten in world
Top ten in world
 
Highwall Mining Technology
Highwall Mining TechnologyHighwall Mining Technology
Highwall Mining Technology
 
Legal flow schemes for a greenfield mining project
Legal flow schemes for a greenfield mining projectLegal flow schemes for a greenfield mining project
Legal flow schemes for a greenfield mining project
 
Mine communication sysetms
Mine communication sysetmsMine communication sysetms
Mine communication sysetms
 
Mine Tech Seminar '10 - Gist of Papers
Mine Tech Seminar '10 - Gist of PapersMine Tech Seminar '10 - Gist of Papers
Mine Tech Seminar '10 - Gist of Papers
 
Reduction of risk from roof and side fall in Indian coal mines
Reduction of risk from roof and side fall in Indian coal minesReduction of risk from roof and side fall in Indian coal mines
Reduction of risk from roof and side fall in Indian coal mines
 
goaves effect on subsidence
goaves effect on subsidencegoaves effect on subsidence
goaves effect on subsidence
 
Longwall - The road ahead
Longwall - The road aheadLongwall - The road ahead
Longwall - The road ahead
 

Último

Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
Joaquim Jorge
 

Último (20)

Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
 
Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024
 
Evaluating the top large language models.pdf
Evaluating the top large language models.pdfEvaluating the top large language models.pdf
Evaluating the top large language models.pdf
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
GenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdfGenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdf
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 
What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Script
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)
 

Energy - India (11th Plan)

  • 1. ENERGY Indian Scenario (11th Plan) Venkat A Gist from Planning Commission Report
  • 2. Highlights of 11th Plan • The envisaged growth rate of economy is 9%. • India is 7th largest energy producer and 5th largest energy consumer in world. • Estimated average peak shortage is 12% in 2006- 07.
  • 3. Projected Energy requirement, 2030 • The projected requirement of coal has been estimated assuming its calorie content to be 4000 kcal per kg and 2865 kcal per kg for lignite.
  • 4. Available Energy 70%-HC Potential Resource 70%-HC Potential 70%-HC 70%-Coal 6%-Coal 10%-HC Potential
  • 5. Coal Reserves of India (April 2009) In Million Tonnes Formation Proved Indicated Inferred Total Gondwana 105,343 123,380 37,414 266,137 Coals Tertiary Coals 477 90 506* 1,073 Total 105,820 123,470 37,920* 267,210 * Includes 456 Mt of Inferred resources established through mapping in NE region. Source – Ministry of Coal site. Energy Mix of India
  • 6. Demand & Supply of Primary Energy
  • 8. Coal Demand & Supply Sector-wise
  • 10. Projected commercial Energy requirement for 2011-12 @ 9% growth rate
  • 11. Growth rates of Domestic supply
  • 12. Way Forward • India is short of all energy resources. Need to expand resources through exploration, energy efficiency, renewables and R&D. • Additional sources of energy like CBM must be fully exploited. Renewable energy sources contribution should be increased. • More transparent policy framework that treats the different energy sources in similar manner. • Institutions promoting energy conservation and improvement need to be strengthened. • Subsidies and support need to be linked to outcome of renewable energy instead of capital investment. • Development of robust energy R&D systems.
  • 13. Energy Generation In MW Capacity at Type Centre State Private Total the end of Hydro 7,563.00 25,785.62 1,306.15 34,654.77 Thermal 33,658.99 43,334.33 9,021.52 86,014.84 10th Plan Nuclear 3,900.00 - - 3,900.00 Total 45,121.99 69,119.95 10,327.67 124,569.61# Type Centre State Private Total Hydro 9,685.00 3,605.00 3,263.00 16,553.00 Addition Thermal 26,800.00 24,347.00 7,497.00 58,644.00 during Nuclear 3,380.00 - - 3,380.00 11th Plan Total 39,865.00 27,952.00 10,760.00 78,577.00
  • 14. Development of alternative Fuels • CBM-Coal Bed Methane – 26 blocks already been offered in bidding. • Gas Hydrates – National GH Programme started in 1997. Seismic surveys conducted in KG & Mahanadi basin. Potential areas are Kerala & Konkan basin. • UCG-Underground Coal Gasification – ONGC & GAIL engaged for exploration. • CTL-Coal To Liquid – Two blocks allocated to Tata & Jindal. • Bio fuels – Planned for 5% increase of ethanol in Bio-diesel blended fuel. • Oil Shale – Identified in Assam, Arunachal Pradesh & Nagaland estimated about 100 Billion barrels.