Topics Covered:

(I)Land acquisition process for National Highways
(II)Land acquisition for container terminal at Cochin port
(III)Land evacuation, R&R lessons from the DIA (pg160-
164)
Differences between LAA, 1894 & NHA, 1956
Land Acquisition Act, 1894                                   National Highway Act, 1956
•   Covers land acquisition for dams, industries ,           •    Covers land acquisition only for national
    hospitals, educational institutions, housings,                highways.
    commercial buildings, airports, railways, state
    highways.

•   Land acquisition handled by District Collector,          •    Land acquisition handled by a competent
    his staff of land record keepers and surveyors.               authority appointed by NHA.

•   Collector must acquire land within 2 yrs, else           •    No time limit for land acquisition.
    the proceeding collapses.

                                                             •    No Urgency clause.
•   Under urgency clause govt can acquire land
    within 15 days of notification

•   Solatium amount paid besides compensation.               •    No such provision.


•   No ex-gratia grant under R&R Benefits in                 •    An ex-gratia grant of minimum 20000 allowed
    addition to compensation allowed.                             besides compensation allowed.
                                       Presented By : Tusar & Sudhanshu (PGPIM-
                                                    4th Batch AIIM)
Reasons for delays Land Projects
 Delays related to Land Acquisition
• Administration- Delay in appointment of competent authority
• Weak existing capacity, awareness and knowledge levels amongst planners and
   executors
• Frequent transfers of planners and executors
• Inter-departmental works demand time
• Valuation process is time consuming
• Preparation of poor plans result in resettlement of claims
• Duplication of procedures

Delays related to Clearances
• Obtaining Forest, environmental and wildlife clearances are highly time consuming



                             Presented By : Tusar & Sudhanshu (PGPIM-
                                          4th Batch AIIM)
Issues in Forest Clearances
•   Required only for that stretch passing through the forest
•   Preceded by Environmental Clearance
•   Granted in 2 stages- In-principle approval stage  final stage
•   Additional and sometimes unreasonable and difficult conditions are imposed by
    state forest departments besides conditions imposed by MoEF


             Issues in Wildlife Clearances
•   Required only for that stretch which disrupts the wildlife
•   Preceded by Environmental Clearance
•   Involves many stages and many departments like CEC, SC, NBW, SWAB etc
•   Takes almost 2-3 years in getting final approvals
•   Two stage clearance for surveying the area and final clearance create uncertainty
•   Environmental and other clearances need to be taken up at DPR preparation stage

                              Presented By : Tusar & Sudhanshu (PGPIM-
                                           4th Batch AIIM)
Issues in Environmental Clearance
• MoEF adopting procedures notified under EIA Notification,2006
• Environmental Clearance required for :
  (i) New NHs of more than 30 kms
  (ii) NHs of more than 30 kms and widening of more than 20 kms
• For each project MOEF drafts a separate TOR
• Based on TOR proponent authorities prepare complete EIA
• EIA to be then examined by the Govt.
• Time period for the process is 9 to 12 months
• Projects having Right of Way of 60 mts , standard norm, to be exempted from the
    clearance




                             Presented By : Tusar & Sudhanshu (PGPIM-
                                          4th Batch AIIM)
Way Forward
• Educate public and revenue officers on their duties and responsibilities, add extra
  staff to mobilize high volume works

• Maintaining updated and accessible revenue records

• To update records in villages coming under project, prior to start of the acquisition
  process

• Increase outsourcing of critical works

• MoEF should consider issue of uniform and reasonable policy guidelines by State
  Governments


                               Presented By : Tusar & Sudhanshu (PGPIM-
                                            4th Batch AIIM)
ICTT                                   - Strategic location on the main east-west global
                                                      shipping lines
                                                      - Offering draft of about 16 m, Cochin is a premier
Development of International Container                gateway to southern India
Transshipment Terminal in Vallarpadam island,         - Cochin offers an alternative to Sri Lanka and
Kerala                                                Singapore for containers being transshipped for the
                                                      Indian market.



  1991        DPR was prepared
  1992        Bids were invited for establishment of terminal with private participation
  1998        Project report updated. Planned a state of art terminal with annual
               handling cap of 3M TEU
  Jan 2005    License agreement between Cochin Port Trust and M/s India Gateway
              Terminal Pvt Ltd (BOT)
  Nov 2006    Environmental clearance status for ICTT and SEZ status to the project
              area
  Nov 2007    Contract awarded – Phase 1 development of terminal (600m berth) - $150M
  Dec 2007    Construction work started


  Terms of agreement between CPT & IGT
  Supporting infrastructure facility for rail connectivity to(PGPIM-
                                   Presented By : Tusar & Sudhanshu
                                                                    the project area at Vallarpadam
  will be arranged by CPT                       4th Batch AIIM)
- Unwillingness of people to give
                                                               up their land led to agitation
                                                               - People’s council formed
                                  Govt. starts                 -Indefinite hunger strike and relay
Govt. of Kerala                   registration of              sathyagraha
publishes                         land under                   - People were dissatisfied with
notification for                  DLPC scheme.                 Govt. R&R package (4 – 6 cents of
Phase 1 L/A                                                    land) and filed writ petitions at
                                                               High court
                                                               - High Court directs monetary
                                                               compensation for extra 0.5 cents
                                                               of land



                   10 Oct 07                               15 Jul 08                         11 Feb11

  9 Apr 07                         1 Jan 08




                     Govt. of
                      Kerala
                    publishes                                                            ICTT commissioned
                                                       All land owners
                   notification                                                      successfully with a capacity
                                                     accept High court’s
                   for Phase 2                                                        to handle 1 million TEUs
                                                    order & surrendered
                       L/A                                                                     annually
                                                           their land
                                    Presented By : Tusar & Sudhanshu (PGPIM-
                                                 4th Batch AIIM)
Lessons learnt
• Acquiring a small size of land (4.3 ha) affected as many as 261 families
• Forced eviction led govt. to consider R&R package (NRRP-2007 makes R&R
  mandatory only for those projects that involve displacement of more than
  400 families)
• Major feature of R&R package – land for land and offering land to close
  proximity to where the displaced used to live




                          Presented By : Tusar & Sudhanshu (PGPIM-
                                       4th Batch AIIM)
LER&R-Lessons From DIAL

• DIAL is a joint venture consortium comprising the GMR Group
  (50.1%), AAI (26 %), Fraport AG and Eraman Malaysia (10
  %each), and IDF (3.9 %)
                                                   Land identified for development
                                                   faces issues on three key reasons:
                                                        •Environment concerns
                                                        •Social well being concerns
                                                        •Benefit sharing concerns




                    Presented By : Tusar & Sudhanshu (PGPIM-
                                 4th Batch AIIM)
 147 cases challenging the land acquisition and the
  compensation provided by AAI were pending in the Delhi High
  court
 Many families had sold the allotted land (Rangpuri village) &
  continued to stay at their native village
 Native sold their land to outsiders (Commercial)
 Outsider filed petition seeking alternate land
 Encroachment on about 30 acres of land housing 1952 families
 Inability of families to produce revenue records resulted in less
  allotment against their eligibility
 Agitation and protest surrounding land acquisition


                     Presented By : Tusar & Sudhanshu (PGPIM-
                                  4th Batch AIIM)
   Formed a strategic nine member team (land management department)
   Team was familiar with the local culture and vernacular language
   Petition to transfer all cases under one judge
   Requested MoCA to form Apex and working committee to oversee the progress
    of land evacuation
   Apex committee – Chief Sec. GNCTD, GMR Grp, D. Collector
   Working committee– DDA,DJB,DTL,GMR chaired by D. Collector
   LMD met representative of village and political leaders, bureaucrats and
    highlighted the fact and importance of project
   Team build a rapport and gain information on actual status
   DIAL offered to pay each family the rent for 6 month
   Resettlement of J&J 29k /squatter family




                         Presented By : Tusar & Sudhanshu (PGPIM-
                                      4th Batch AIIM)
 DIAL roped in GMR social Arm (CSR) to
  provide basic facilities to the affected
  people
 Provision for R& R package was well
  utilized by providing assistance on
  transportation and labor.
 Made R&R a pleasant experience for
  the affected people and earn their
  goodwill
 Lack of clarity in contracts regarding
  responsibility of land evacuation ,DIAL
  took upon itself.




                         Presented By : Tusar & Sudhanshu (PGPIM-
                                      4th Batch AIIM)
Thank You


Presented By : Tusar & Sudhanshu (PGPIM-4th Batch AIIM)

Mais conteúdo relacionado

Mais procurados

Delhi Mumbai Industrial Corridor
Delhi Mumbai Industrial CorridorDelhi Mumbai Industrial Corridor
Delhi Mumbai Industrial Corridor
Vishal Dedhia
 
STUDY ON BOT PROJECT WITH A CASE STUDY OF DELHI GURGAON EXPRESSWAY
STUDY ON BOT PROJECT WITH A CASE STUDY OF DELHI GURGAON EXPRESSWAYSTUDY ON BOT PROJECT WITH A CASE STUDY OF DELHI GURGAON EXPRESSWAY
STUDY ON BOT PROJECT WITH A CASE STUDY OF DELHI GURGAON EXPRESSWAY
Shabaz Khan
 

Mais procurados (20)

Ahmedabad metro rail project (amrc) deepen
Ahmedabad metro rail project (amrc)   deepenAhmedabad metro rail project (amrc)   deepen
Ahmedabad metro rail project (amrc) deepen
 
Arbitration Of Construction Disputes
Arbitration Of Construction DisputesArbitration Of Construction Disputes
Arbitration Of Construction Disputes
 
Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)
 
Delhi Mumbai Industrial Corridor
Delhi Mumbai Industrial CorridorDelhi Mumbai Industrial Corridor
Delhi Mumbai Industrial Corridor
 
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORTROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
 
Cross section of road and sight distance
Cross section of road and sight distanceCross section of road and sight distance
Cross section of road and sight distance
 
Real Estate (Development & Regulation) Act, 2016
Real Estate (Development & Regulation) Act, 2016Real Estate (Development & Regulation) Act, 2016
Real Estate (Development & Regulation) Act, 2016
 
1. New Land Acquisition Act Process Flow
1. New Land Acquisition Act Process Flow1. New Land Acquisition Act Process Flow
1. New Land Acquisition Act Process Flow
 
Land acquisition for NH under the NH act, 1956
Land acquisition for NH under the NH act, 1956Land acquisition for NH under the NH act, 1956
Land acquisition for NH under the NH act, 1956
 
Land Acquisition Flow Chart
Land Acquisition Flow ChartLand Acquisition Flow Chart
Land Acquisition Flow Chart
 
LARR act 2013
LARR act 2013LARR act 2013
LARR act 2013
 
Land Acquisition Act 1894
Land Acquisition Act 1894Land Acquisition Act 1894
Land Acquisition Act 1894
 
Casting yard
Casting yardCasting yard
Casting yard
 
Ahmedabad Metro Project
Ahmedabad Metro ProjectAhmedabad Metro Project
Ahmedabad Metro Project
 
Land acquisition procedure in Gujarat State
Land acquisition procedure in Gujarat StateLand acquisition procedure in Gujarat State
Land acquisition procedure in Gujarat State
 
Construction of residential building summer training ppt
 Construction of residential building summer training ppt Construction of residential building summer training ppt
Construction of residential building summer training ppt
 
STUDY ON BOT PROJECT WITH A CASE STUDY OF DELHI GURGAON EXPRESSWAY
STUDY ON BOT PROJECT WITH A CASE STUDY OF DELHI GURGAON EXPRESSWAYSTUDY ON BOT PROJECT WITH A CASE STUDY OF DELHI GURGAON EXPRESSWAY
STUDY ON BOT PROJECT WITH A CASE STUDY OF DELHI GURGAON EXPRESSWAY
 
FINAL REPORT
FINAL REPORTFINAL REPORT
FINAL REPORT
 
Construction equipments
Construction equipmentsConstruction equipments
Construction equipments
 
Indian Land acquisition for public purpose - The Right to Fair Compensation a...
Indian Land acquisition for public purpose - The Right to Fair Compensation a...Indian Land acquisition for public purpose - The Right to Fair Compensation a...
Indian Land acquisition for public purpose - The Right to Fair Compensation a...
 

Destaque

Rttfc in larr_2013_2
Rttfc in larr_2013_2Rttfc in larr_2013_2
Rttfc in larr_2013_2
PSPCL
 
Land acquisition kelly dhru
Land acquisition kelly dhruLand acquisition kelly dhru
Land acquisition kelly dhru
Bishal Tiwari
 
Land Acquisition in India Final
Land Acquisition in India FinalLand Acquisition in India Final
Land Acquisition in India Final
Nilesh Singh
 
Rehabilitation & Resettlement policy
Rehabilitation & Resettlement policyRehabilitation & Resettlement policy
Rehabilitation & Resettlement policy
Prastut Maurya
 
Vu assignment marketing waqas
Vu assignment marketing waqasVu assignment marketing waqas
Vu assignment marketing waqas
Kokab Manzoor
 

Destaque (20)

Land acquisition
Land acquisitionLand acquisition
Land acquisition
 
Land acquisition act
Land acquisition actLand acquisition act
Land acquisition act
 
land acquisition
land acquisitionland acquisition
land acquisition
 
Land acquisition (1)
Land acquisition (1)Land acquisition (1)
Land acquisition (1)
 
LAND ACQUISITION ACT-1894
LAND ACQUISITION  ACT-1894LAND ACQUISITION  ACT-1894
LAND ACQUISITION ACT-1894
 
Streamlining Approval Procedure for Real Estate Projects (SAPREP) - 19 sept '14
Streamlining Approval Procedure for Real Estate Projects (SAPREP) -  19 sept '14Streamlining Approval Procedure for Real Estate Projects (SAPREP) -  19 sept '14
Streamlining Approval Procedure for Real Estate Projects (SAPREP) - 19 sept '14
 
Tata motor case (Singur)
Tata motor case (Singur)Tata motor case (Singur)
Tata motor case (Singur)
 
Day2: Mr. Rk sinha dgh presentation ippai goa
Day2: Mr. Rk sinha dgh presentation ippai goaDay2: Mr. Rk sinha dgh presentation ippai goa
Day2: Mr. Rk sinha dgh presentation ippai goa
 
Outline of land_acquisition_law_in_india_e-_naveen_kumar_shelar-_advocate
Outline of land_acquisition_law_in_india_e-_naveen_kumar_shelar-_advocateOutline of land_acquisition_law_in_india_e-_naveen_kumar_shelar-_advocate
Outline of land_acquisition_law_in_india_e-_naveen_kumar_shelar-_advocate
 
Rttfc in larr_2013_2
Rttfc in larr_2013_2Rttfc in larr_2013_2
Rttfc in larr_2013_2
 
Project Land Acquisition in India
Project   Land Acquisition in IndiaProject   Land Acquisition in India
Project Land Acquisition in India
 
Land acquisition kelly dhru
Land acquisition kelly dhruLand acquisition kelly dhru
Land acquisition kelly dhru
 
Land Acquisition in India Final
Land Acquisition in India FinalLand Acquisition in India Final
Land Acquisition in India Final
 
Land acquisition bill in india 2015
Land acquisition bill in india 2015Land acquisition bill in india 2015
Land acquisition bill in india 2015
 
Roads Sectore Report - December 2016
Roads Sectore Report - December 2016Roads Sectore Report - December 2016
Roads Sectore Report - December 2016
 
Exploring Alternatives to Land Acquisition
Exploring Alternatives to Land AcquisitionExploring Alternatives to Land Acquisition
Exploring Alternatives to Land Acquisition
 
Land acquisition in India
Land acquisition in IndiaLand acquisition in India
Land acquisition in India
 
Land acquisition act 2
Land acquisition act 2Land acquisition act 2
Land acquisition act 2
 
Rehabilitation & Resettlement policy
Rehabilitation & Resettlement policyRehabilitation & Resettlement policy
Rehabilitation & Resettlement policy
 
Vu assignment marketing waqas
Vu assignment marketing waqasVu assignment marketing waqas
Vu assignment marketing waqas
 

Semelhante a LAND ACQUISITION BY NHAI

Applicant guide-mining-activities-conservation-land
Applicant guide-mining-activities-conservation-landApplicant guide-mining-activities-conservation-land
Applicant guide-mining-activities-conservation-land
Kalyan Ram
 
PMO Mining Assets (as of 22 Sep 2020).pptx
PMO Mining Assets (as of 22 Sep 2020).pptxPMO Mining Assets (as of 22 Sep 2020).pptx
PMO Mining Assets (as of 22 Sep 2020).pptx
SherinaVT
 

Semelhante a LAND ACQUISITION BY NHAI (20)

Applicant guide-mining-activities-conservation-land
Applicant guide-mining-activities-conservation-landApplicant guide-mining-activities-conservation-land
Applicant guide-mining-activities-conservation-land
 
Ultra mega power projects
Ultra mega power projectsUltra mega power projects
Ultra mega power projects
 
THE PHILIPPINE MINING INDUSTRY - LEGAL AND ENVIRONMENTAL FRAMEWORK
THE PHILIPPINE MINING INDUSTRY - LEGAL AND ENVIRONMENTAL FRAMEWORKTHE PHILIPPINE MINING INDUSTRY - LEGAL AND ENVIRONMENTAL FRAMEWORK
THE PHILIPPINE MINING INDUSTRY - LEGAL AND ENVIRONMENTAL FRAMEWORK
 
Nationally Significant Infrastructure Projects and IPC
Nationally Significant Infrastructure Projects and IPCNationally Significant Infrastructure Projects and IPC
Nationally Significant Infrastructure Projects and IPC
 
Student Assignment Agrarian Law - Lecturer Ricco Survival Yubaidi (10).pdf
Student Assignment Agrarian Law - Lecturer Ricco Survival Yubaidi (10).pdfStudent Assignment Agrarian Law - Lecturer Ricco Survival Yubaidi (10).pdf
Student Assignment Agrarian Law - Lecturer Ricco Survival Yubaidi (10).pdf
 
4.Land Acquisition ppt.pptx
4.Land Acquisition ppt.pptx4.Land Acquisition ppt.pptx
4.Land Acquisition ppt.pptx
 
PMO Mining Assets (as of 22 Sep 2020).pptx
PMO Mining Assets (as of 22 Sep 2020).pptxPMO Mining Assets (as of 22 Sep 2020).pptx
PMO Mining Assets (as of 22 Sep 2020).pptx
 
Energy Laws and Policies Presentation.pptx
Energy Laws and Policies Presentation.pptxEnergy Laws and Policies Presentation.pptx
Energy Laws and Policies Presentation.pptx
 
Presentation on Implementation of Coastal Regulation Zone Notification dtd.19...
Presentation on Implementation of Coastal Regulation Zone Notification dtd.19...Presentation on Implementation of Coastal Regulation Zone Notification dtd.19...
Presentation on Implementation of Coastal Regulation Zone Notification dtd.19...
 
Tiamson introduction to land titling
Tiamson  introduction to land titlingTiamson  introduction to land titling
Tiamson introduction to land titling
 
Final project cjm46
Final project cjm46Final project cjm46
Final project cjm46
 
Chan sophal s2 policy dialogue agriculture investment
Chan sophal s2 policy dialogue agriculture investmentChan sophal s2 policy dialogue agriculture investment
Chan sophal s2 policy dialogue agriculture investment
 
DPI - large-scale solar site selection crown land options
DPI - large-scale solar site selection crown land optionsDPI - large-scale solar site selection crown land options
DPI - large-scale solar site selection crown land options
 
Benjamin Asante, Snr. Procurement Officer at GNPC - The jubilee field a world...
Benjamin Asante, Snr. Procurement Officer at GNPC - The jubilee field a world...Benjamin Asante, Snr. Procurement Officer at GNPC - The jubilee field a world...
Benjamin Asante, Snr. Procurement Officer at GNPC - The jubilee field a world...
 
Thar coal hurdle&solution
Thar coal hurdle&solutionThar coal hurdle&solution
Thar coal hurdle&solution
 
Utilizing our Natural Resources in the Environmental Way
Utilizing our Natural Resources in the Environmental WayUtilizing our Natural Resources in the Environmental Way
Utilizing our Natural Resources in the Environmental Way
 
agarian reform policies.pdf
agarian reform policies.pdfagarian reform policies.pdf
agarian reform policies.pdf
 
Environment Clearance Procedure-India
Environment Clearance Procedure-IndiaEnvironment Clearance Procedure-India
Environment Clearance Procedure-India
 
Mining - Breaking the Stigma
Mining - Breaking the StigmaMining - Breaking the Stigma
Mining - Breaking the Stigma
 
tarbela-dam-project.pptx
tarbela-dam-project.pptxtarbela-dam-project.pptx
tarbela-dam-project.pptx
 

LAND ACQUISITION BY NHAI

  • 1. Topics Covered: (I)Land acquisition process for National Highways (II)Land acquisition for container terminal at Cochin port (III)Land evacuation, R&R lessons from the DIA (pg160- 164)
  • 2. Differences between LAA, 1894 & NHA, 1956 Land Acquisition Act, 1894 National Highway Act, 1956 • Covers land acquisition for dams, industries , • Covers land acquisition only for national hospitals, educational institutions, housings, highways. commercial buildings, airports, railways, state highways. • Land acquisition handled by District Collector, • Land acquisition handled by a competent his staff of land record keepers and surveyors. authority appointed by NHA. • Collector must acquire land within 2 yrs, else • No time limit for land acquisition. the proceeding collapses. • No Urgency clause. • Under urgency clause govt can acquire land within 15 days of notification • Solatium amount paid besides compensation. • No such provision. • No ex-gratia grant under R&R Benefits in • An ex-gratia grant of minimum 20000 allowed addition to compensation allowed. besides compensation allowed. Presented By : Tusar & Sudhanshu (PGPIM- 4th Batch AIIM)
  • 3. Reasons for delays Land Projects Delays related to Land Acquisition • Administration- Delay in appointment of competent authority • Weak existing capacity, awareness and knowledge levels amongst planners and executors • Frequent transfers of planners and executors • Inter-departmental works demand time • Valuation process is time consuming • Preparation of poor plans result in resettlement of claims • Duplication of procedures Delays related to Clearances • Obtaining Forest, environmental and wildlife clearances are highly time consuming Presented By : Tusar & Sudhanshu (PGPIM- 4th Batch AIIM)
  • 4. Issues in Forest Clearances • Required only for that stretch passing through the forest • Preceded by Environmental Clearance • Granted in 2 stages- In-principle approval stage  final stage • Additional and sometimes unreasonable and difficult conditions are imposed by state forest departments besides conditions imposed by MoEF Issues in Wildlife Clearances • Required only for that stretch which disrupts the wildlife • Preceded by Environmental Clearance • Involves many stages and many departments like CEC, SC, NBW, SWAB etc • Takes almost 2-3 years in getting final approvals • Two stage clearance for surveying the area and final clearance create uncertainty • Environmental and other clearances need to be taken up at DPR preparation stage Presented By : Tusar & Sudhanshu (PGPIM- 4th Batch AIIM)
  • 5. Issues in Environmental Clearance • MoEF adopting procedures notified under EIA Notification,2006 • Environmental Clearance required for : (i) New NHs of more than 30 kms (ii) NHs of more than 30 kms and widening of more than 20 kms • For each project MOEF drafts a separate TOR • Based on TOR proponent authorities prepare complete EIA • EIA to be then examined by the Govt. • Time period for the process is 9 to 12 months • Projects having Right of Way of 60 mts , standard norm, to be exempted from the clearance Presented By : Tusar & Sudhanshu (PGPIM- 4th Batch AIIM)
  • 6. Way Forward • Educate public and revenue officers on their duties and responsibilities, add extra staff to mobilize high volume works • Maintaining updated and accessible revenue records • To update records in villages coming under project, prior to start of the acquisition process • Increase outsourcing of critical works • MoEF should consider issue of uniform and reasonable policy guidelines by State Governments Presented By : Tusar & Sudhanshu (PGPIM- 4th Batch AIIM)
  • 7. ICTT - Strategic location on the main east-west global shipping lines - Offering draft of about 16 m, Cochin is a premier Development of International Container gateway to southern India Transshipment Terminal in Vallarpadam island, - Cochin offers an alternative to Sri Lanka and Kerala Singapore for containers being transshipped for the Indian market. 1991 DPR was prepared 1992 Bids were invited for establishment of terminal with private participation 1998 Project report updated. Planned a state of art terminal with annual handling cap of 3M TEU Jan 2005 License agreement between Cochin Port Trust and M/s India Gateway Terminal Pvt Ltd (BOT) Nov 2006 Environmental clearance status for ICTT and SEZ status to the project area Nov 2007 Contract awarded – Phase 1 development of terminal (600m berth) - $150M Dec 2007 Construction work started Terms of agreement between CPT & IGT Supporting infrastructure facility for rail connectivity to(PGPIM- Presented By : Tusar & Sudhanshu the project area at Vallarpadam will be arranged by CPT 4th Batch AIIM)
  • 8. - Unwillingness of people to give up their land led to agitation - People’s council formed Govt. starts -Indefinite hunger strike and relay Govt. of Kerala registration of sathyagraha publishes land under - People were dissatisfied with notification for DLPC scheme. Govt. R&R package (4 – 6 cents of Phase 1 L/A land) and filed writ petitions at High court - High Court directs monetary compensation for extra 0.5 cents of land 10 Oct 07 15 Jul 08 11 Feb11 9 Apr 07 1 Jan 08 Govt. of Kerala publishes ICTT commissioned All land owners notification successfully with a capacity accept High court’s for Phase 2 to handle 1 million TEUs order & surrendered L/A annually their land Presented By : Tusar & Sudhanshu (PGPIM- 4th Batch AIIM)
  • 9. Lessons learnt • Acquiring a small size of land (4.3 ha) affected as many as 261 families • Forced eviction led govt. to consider R&R package (NRRP-2007 makes R&R mandatory only for those projects that involve displacement of more than 400 families) • Major feature of R&R package – land for land and offering land to close proximity to where the displaced used to live Presented By : Tusar & Sudhanshu (PGPIM- 4th Batch AIIM)
  • 10. LER&R-Lessons From DIAL • DIAL is a joint venture consortium comprising the GMR Group (50.1%), AAI (26 %), Fraport AG and Eraman Malaysia (10 %each), and IDF (3.9 %) Land identified for development faces issues on three key reasons: •Environment concerns •Social well being concerns •Benefit sharing concerns Presented By : Tusar & Sudhanshu (PGPIM- 4th Batch AIIM)
  • 11.  147 cases challenging the land acquisition and the compensation provided by AAI were pending in the Delhi High court  Many families had sold the allotted land (Rangpuri village) & continued to stay at their native village  Native sold their land to outsiders (Commercial)  Outsider filed petition seeking alternate land  Encroachment on about 30 acres of land housing 1952 families  Inability of families to produce revenue records resulted in less allotment against their eligibility  Agitation and protest surrounding land acquisition Presented By : Tusar & Sudhanshu (PGPIM- 4th Batch AIIM)
  • 12. Formed a strategic nine member team (land management department)  Team was familiar with the local culture and vernacular language  Petition to transfer all cases under one judge  Requested MoCA to form Apex and working committee to oversee the progress of land evacuation  Apex committee – Chief Sec. GNCTD, GMR Grp, D. Collector  Working committee– DDA,DJB,DTL,GMR chaired by D. Collector  LMD met representative of village and political leaders, bureaucrats and highlighted the fact and importance of project  Team build a rapport and gain information on actual status  DIAL offered to pay each family the rent for 6 month  Resettlement of J&J 29k /squatter family Presented By : Tusar & Sudhanshu (PGPIM- 4th Batch AIIM)
  • 13.  DIAL roped in GMR social Arm (CSR) to provide basic facilities to the affected people  Provision for R& R package was well utilized by providing assistance on transportation and labor.  Made R&R a pleasant experience for the affected people and earn their goodwill  Lack of clarity in contracts regarding responsibility of land evacuation ,DIAL took upon itself. Presented By : Tusar & Sudhanshu (PGPIM- 4th Batch AIIM)