Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Measure A Status Report, 2010
1. Measure A – Building our Future!
San Ramon Valley Unified School District
Modernization and Reconstruction Status Report
February 2010
2. Measure A – a community investment!
Thanks to voter-approved school facilities bonds passed in 1998 (Measure D) and 2002
(Measure A), the San Ramon Valley Unified School District continues to move forward
with major modernization projects, promoting safe, healthy and highly functional
facilities for our children to learn!
Measure A, a $260 million bond, is allowing the district to reduce overcrowding
(particularly at our high schools), upgrade and replace outdated electrical and HVAC
systems, upgrade and renovate classrooms that are 25 years old, add science and
technology labs and replace temporary portable classrooms with permanent buildings.
The designs of these facilities are functional, cost-effective, and of high-quality
construction making the buildings easier to maintain and reducing future maintenance
costs. In addition, the district has been able to secure more than $60 million in state
matching funds, giving taxpayers a higher return on their investment.
For more information about Measure A and school facilities, contact the SRVUSD
Facilities Department at 925-552-5986 or visit www.srvusd.net
3. Measure A Oversight Committee
State law requires that Measure A, a Proposition 39 Facilities Bond, has a citizens' oversight committee that
conducts independent financial and performance audits to ensure funds are spent specifically on school
improvements. The Measure A Facilities Oversight and Advisory Committee was appointed by the Board of
Education in January 2003. The Committee, commonly referred to as the "FOAC," meets monthly and is
charged with the following:
• Provide oversight of Measure A expenditures in order to assure bond proceeds are utilized to complete the
Measure A projects.
• Inform the public about the expenditure of bond proceeds, including the submission of an annual report to
the Board of Education.
• Provide design and cost recommendations to the Board at the conceptual design and construction document
phases of projects consistent with the intent of Measure A.
• Provide recommendations on priorities for remaining Measure A projects.
• Provide input and recommendations on future facilities needs of schools and district.
• Provide recommendations on specific related issues as requested by the Board of Education.
Through this committee, the community as a whole is able to participate in the process of reviewing school
facilities and planning for the future. The committee began its work in February 2005. Regular meetings are held
once a month on Tuesday evenings. The FOAC is an official Board oversight committee; as such, committee
meetings are open to the public and subject to all provisions of the Brown Act. For more information about the
oversight committee, contact the Facilities Department at 925-552-5986.
For more information about Measure A and school facilities, contact the SRVUSD
Facilities Department at 925-552-5986 or visit www.srvusd.net
4. We’ve come a long way!
Measure A Project Status
Project Complete In Construction Bidding Pending Preparing In Design Master Plan
Award State Approval Construction
Documents
Neil Armstrong Elementary X
Walt Disney Elementary X
Montair Elementary X
John Baldwin Elementary X
Bollinger Canyon Elementary X
Greenbrook Elementary X
Green Valley Elementary X
Rancho Romero Elementary X
Tassajara Hills Elementary
!Science Classroom X
!Traffic signal modifications X
Twin Creeks Elementary
!MPR X
Vista Grande Elementary
!New MPR X
!Modernization X
Charlotte Wood Middle
!HVAC only X
!Science Classroom X
Diablo Vista Middle
!Library X
!Gymnasium X
!Science Conversion X
!Classroom Conversion X
!Four new classrooms X
Iron Horse Middle
!Science Conversion X
Los Cerros Middle
!Kitchen X
Pine Valley Middle X
Stone Valley Middle X
Dougherty Valley X
For more information about Measure A and school facilities, contact the SRVUSD
Facilities Department at 925-552-5986 or visit www.srvusd.net
5. Measure A Project Status (p2)
Project Complete In Bidding Pending Preparing In Design Master Plan
Construction Award State Construction
Approval Documents
California High
!Classroom/Library X
!Elective Building X
!Gym mod & Sports Med X
!Theater and Event Center X
!New Career Tech building X
!Auxiliary gym X
!Renovate parking lot X
!New turf field X
!Add Storage at Pool X
Monte Vista High
!New 18 Classroom building X
!Commons X
!Science Conversion X
!Culinary/Morgue X
!Career Tech X
!Child Care X
!Sports Med building X
!Pool shade structure X
!New turf field X
!Renovate bleachers X
San Ramon Valley High
!New ommons/Library bld. X
!Music Building X
!Classroom Building/Aux. Gym X
!Career Tech/Quad/Main Gym X
!New turf field X
!Gym replacement/Sports Med X
!Renovate bleachers X
!Stadium restrooms X
!Gymnasium X
!Replace stadium lights X
Venture High School X
Service Center
Technology Upgrades X X
Future Measure A school construction projects include: Alamo Elementary, Country Club Elementary, Golden View Elementary, Montevideo Elementary,
Sycamore Valley Elementary, Los Cerros Middle, Del Amigo
For more information about Measure A and school facilities, contact the SRVUSD
Facilities Department at 925-552-5986 or visit www.srvusd.net
6. For more information about Measure A and school facilities, contact the SRVUSD
Facilities Department at 925-552-5986 or visit www.srvusd.net
7. Neil Armstrong Elementary School
2849 Calais Drive, San Ramon
Project: Modernization
Start Date: September 2003
Completion Date: April 2005
Modernization at Neil Armstrong began in the fall of
2003 and was completed for the 2005-2006 school
year. The project included a total school renovation
with the addition of a new computer lab with 34
stations, a science lab, and a self-contained
library. Armstrong looks like a brand new school
thanks to the generosity of this community and the
new modernization of this building project.
8. John Baldwin Elementary School
41 Brookside Drive, Danville
Project: New School Construction
Construction Start Date: June 2005
Completion Date: August 2006
After careful analysis, a staff and Measure A Citizen’s
Oversight Committee recommendation was approved
by the Board of Education to entirely re-construct John
Baldwin Elementary School, which included
kindergarten classrooms, K-5 classrooms, office, and
library. With the exception of the newer multipurpose
building, the school was demolished and rebuilt to a
much more functional design.
9. Bollinger Canyon Elementary School
2300 Talavera Drive, San Ramon
Project: New School Construction
Start Date: June 2005
Completion Date: August 2006
Similar to John Baldwin Elementary, a staff and Measure
A Citizen’s Oversight Committee recommendation was
approved by the Board of Education to entirely re-
construct Bollinger Canyon Elementary School, which
included kindergarten classrooms, K-5 classrooms,
office, and library. With the exception of the newer
multipurpose building, the school was demolished and
rebuilt to a much more functional design.
10. Walt Disney Elementary School
3250 Pine Valley Road, San Ramon
Project: Modernization
Start Date: July 2003
Completion Date: February 2005
Walt Disney’s campus-wide modernization included:
Renovation of the school library and all classrooms,
new HVAC units throughout the campus, structural
upgrades, new carpet and linoleum, restroom upgrades,
and two new computer labs.
11. Green Valley Elementary School
1001 Diablo Road, Danville
Project: Modernization
Start Date: December 2006
Completion Date: Spring 2008
Construction at Green Valley Elementary School was
completed in the late Spring of 2008. Two
new classroom wings were added replacing old
portable classrooms. The computer classroom was
modernized and the existing multipurpose room was
enlarged and modified. The newly
constructed administration building includes two
resource rooms, a speech, and a psychology room.
12. Greenbrook Elementary School
1475 Harlan Drive, Danville
Project: New School Construction
Start Date: June 2005
Completion Date: August 2006
Similar to John Baldwin and Bollinger Canyon,
Greenbrook Elementary was approved for demolition
and complete reconstruction, which included
kindergarten classrooms, K-5 classrooms, office, and
library. With the exception of the newer multipurpose
building, the school was demolished and rebuilt to a
much more functional design.
13. Montair Elementary School
300 Quinterra Lane, Danville
Project: Modernization
Start Date: July 2003
Completion Date: March 2005
Montair’s modernization involved a campus-wide
renovation including construction of permanent
classrooms to replace temporary portable classrooms.
Other improvements included: New metal roofs on
every building, new HVAC units throughout the
campus, structural upgrades, new concrete walkways,
and new electrical, lighting, data and plumbing systems
throughout.
14. Rancho Romero Elementary School
180 Hemme Avenue, Alamo
Project: Modernization - New Kindergarten
Building/Computer Lab/Admin Bldg. Construction
Start Date: September 2007
Completion Date: April 2008
The new kindergarten building includes two
classrooms, teachers’ work room, staff, student and
kindergarten bathrooms. The new playground and
building are joined by new covered walkways which
were installed throughout the campus. The data
network and all utilities were placed underground,
allowing for the completion of new metal roofs campus
wide. The project also included new landscaping and
irrigation, and administration building.
15. Tassajara Hills Elementary School
4675 Camino Tassajara, Danville
Project: New Computer Classroom Building
Construction Start Date: June 2006
Completion Date: December 2006
Construction of the new computer classroom building
at Tassajara Hills Elementary School was completed in
the fall of 2006. Prior to this, there were no computer
classrooms at Tassajara Hills. The computer classroom
was built to the District’s standard including new
computers, projector, screen and furniture.
16. Twin Creeks Elementary School
785 Marsh Drive, San Ramon
Project: New Multi-Use Building/Master Plan
Start Date: Design 2008, Construction 2009
Estimated Completion Date: Spring 2010
A new multipurpose building is currently under
construction at Twin Creeks. The building includes a full
basketball court, elevated stage, kitchen and state-of-
the art audio and video projection equipment.
Twin Creeks has also been master planned for a future
bond to include a new kindergarten building, standard
classrooms, and redesign of the existing multipurpose
and library buildings.
17. Vista Grande Elementary School
667 Diablo Road, Danville
Project: Modernization
Start Date: July 2005
Completion Date: April 2007
The modernization of Vista Grande included a new
multipurpose building, upgraded underground utilities,
classroom improvements (including lighting and HVAC),
new library and computer lab, installation of Voice-over-
internet-protocol telephones throughout the campus,
and upgraded clock and speaker system. The
administration area was demolished and rebuilt with a
new teacher lounge and outdoor patio area.
18. For more information about Measure A and school facilities, contact the SRVUSD
Facilities Department at 925-552-5986 or visit www.srvusd.net
19. Charlotte Wood Middle School
600 El Capitan, Danville
Project: Modernization, HVAC/Science Classroom
Start Date: July 2005
Completion Date: April 2007
Project included a science classroom and HVAC
upgrade.
20. Diablo Vista Middle School
4100 Camino Tassajara, Danville
Project: New Gymnasium/Play Fields and Library/
Media Center
Start Date: June 2004
Completion Date: August 2007
Completion of the construction at Diablo Vista Middle
School included a new 10,500 square foot gymnasium,
synthetic turf field and track, playfields and school
parking lot. The new library/media center was
completed Spring 2005. The building includes new
library, computer lab, conference room, counselor
offices, and a special education classroom.
21. Pine Valley Middle School
3000 Pine Valley Road, San Ramon
Project: New School Construction
Start Date: December 2006
Completion Date: August 2008
Construction at Pine Valley Middle School consisted
of a total modernization of the existing campus
including new campus infrastructure with a new
classroom building, new electrical and data. In the
15,432 sq. ft. of new construction, the new buildings
contain all classrooms, a library, two computer labs, two
art rooms, and boys' and girls' locker rooms. There
are also new covered walkways throughout the
campus.
22. For more information about Measure A and school facilities, contact the SRVUSD
Facilities Department at 925-552-5986 or visit www.srvusd.net
23. California High School
9870 Broadmoor Ave., San Ramon
Project: Modernization
Start Date: January 2005
Completion Date: Fall 2010
The massive modernization at California High School
includes the following completed projects:
• New 3-story, 63-classroom building is in its second
year of use.
• New 8311 sq. ft. library in its second year of use.
• New, open quad area of approximately 67,000 square
feet provides a gathering place for students.
• New 3,700 sq. ft. career technology building.
• New 3,577 sq. ft. counseling building.
• New two-story fine and applied arts building.
24. California High School – Phase 3
9870 Broadmoor Ave., San Ramon
Project: Modernization Phase 3
Estimated Completion Date: Fall 2010
• Phase 3 of the CHS Modernization Project includes
construction of a new gymnasium building/events
center, partial demolition and remodeling of the
existing theater building, construction of a new portion
of the theater building, and fire alarm and clock/
speaker system upgrades on campus.
25. Monte Vista High School
3131 Stone Valley Road, Alamo
Project: Modernization
Start Date: November 2005
Completion Date: August 2007
Many of the upgrades to Monte Vista High School were
completed under the previous school construction
bond. Measure A modernization construction consisted
of an addition to the existing commons area, a new
two-story classroom building with 18 standard
classrooms, a science and culinary classroom, a new
career tech. building with a clean and dirty lab, and all
associated utility work, hardscape and landscaping.
A total of more than 41,000 square feet of construction.
26. San Ramon Valley High School
501 Danville Blvd., Danville
Project: Modernization
Start Date: May 2005
Estimated Completion Date: August 2010
The major modernization of San Ramon Valley High
School includes the following completed projects:
• New two-story, 28,354 sq. ft. Commons and Library
building. The Commons consists of a central kitchen
with indoor and outdoor serving, video production
classrooms, restrooms, and storage rooms. The Library
consists of a work room, conference rooms, teachers’
lounge, staff restrooms, and computer lab.
• New 8.000 sq. ft addition to the existing Performing
Arts building consisting of state-of-the-art instrumental
and vocal classrooms, practice rooms, and storage.
• New two-story 28,804 sq. ft. classroom building
consisting of 15 standard classrooms, 2 computer labs,
and computer workroom.
• New 22,685 sq. ft. Auxiliary Gymnasium building
which consists of an 8,100 sq. ft. gymnasium, girls’
locker room and showers, girls’ team room, staff office,
training room, aerobics/wrestling room, dance room,
fitness/weight room, meeting room, boys and girls
restrooms, and four storage rooms.
27. San Ramon Valley HS – in construction...
501 Danville Blvd., Danville
Project: New Gymnasium/Career Technology
Estimated Completion Date: August 2010
Demolition of the main gymnasium started in June
2008 and was completed in the Fall of 2008.
• Demolition of the old auxiliary gymnasium was
completed in June 2009, ready for the construction of
the new main gymnasium.
• A new main gymnasium is currently under
construction.
• A new career technology building and new parking
area are currently under construction.
28. Venture School
10540 Albion Road, San Ramon
Project: New School Construction
Start Date: January 2006
Completion Date: August 2007
Venture Independent Study School’s new facility
opened on the southeast corner of the Dougherty
Valley High School property. The new 11,200 square
foot facility includes two classrooms, administration
offices with conference room, art/science room,
computer lab and student study/media center room.
29. Thanks to our community!
The local school facilities projects included in the
Measure A School Construction Bond have become
a major source of community pride! These schools
are safer, more functional and more conducive to
environments that support the extremely high level
of academic excellence to which the San Ramon
Valley community has become accustomed.
We thank the voters of our community for
supporting public education and for understanding
that quality school facilities are a sound investment
in our future!
For more information about Measure A and school facilities, contact the SRVUSD
Facilities Department at 925-552-5986 or visit www.srvusd.net