SlideShare uma empresa Scribd logo
1 de 14
Baixar para ler offline
 
SCHOOL OF ARCHITECTURE, BUILD AND DESIGN
BACHELOR OF QUANTITY SURVEYING (HONOURS)
PROFESSIONAL PRACTICE 2 (QSB 60904)
Coursework 2
NAME STUDENT ID
Hing Pui Kei 0325961
Le Jia Nian 0319957
Lim Ting Le 0320028
Ng Huoy Miin 0319097
Sylvester Tang Kiok Heng 0325152
Wong Qin Kai 0320024
Charanjeev Gunputh 0323942
TABLE OF CONTENT
DESCRIPTION PAGE
1.0 Question 1
2.0 Question 2
3.0 Question 3
4.0 Question 4
4.1 Question 4 (a)
4.2 Question 4 (b)
4.3 Question 4 (c)
4.4 Question 4 (d)
Question 1.
You are required to prepare a report to your director, explaining briefly the adjustments of the
essential elements in your preparation of this project’s final account. (15 marks)
According to the clause 30.11 in the PAM Contract 2006 (with quantities), the work
adjustment made to the contract sum must be shown in the final account. The final account
shall be conclusive and deemed agreed by the parties otherwise any outstanding items to be
resolved separately among the employer and the contractor. In this project final account, the
following essential element will be:
1.Variation works
-Under clause 11.1, works being executed will be defined as variation works. Next, the rules
of valuation will be based on clause 11.6(a) to 11.6(d) if it is an additional works. Whereas,
the rules of valuation will be based on clause 11.6(e) if it is an omission works, stating that
the contract rates and price will be used for omission.
2.Remeasurement of provisional quantities
-A need in re-measured of the provisional quantities under clause 30.10 says that
documents shall contain details of quantities. Architect must re-measured items in the
contract bills which are provisional quantities based on the actual quantities executed. Based
on clause 11.6(f), the rates and prices in the schedule of rates shall determine their
valuations.
3.Omission of prime cost and provisional sum
-Final account shall show the omission of all prime cost sums and the related profits
provided by the contractor in the contract document stated in clause 30.11(c). Moreover,
some items which are allowed in the provisional sum will not be added back into the final
account, example the contingency sum. Hence, the omission of the prime cost and
provisional sum is for the amount that will need to be re-measured based on the tender
price.
4. Adding back of NSC and NS final account
-Under the clause 30.11(c), the final account of the NSC for the prime cost sum and
provisional sum should be added back to the final account as the figure in the contract sum
may not be the actual sum incurred.
5.Adjustment of profit and attendance
-The contractor will be given profit and attendance with the basics of NSC and NS final
account according to the clause 30.11(c). If the provisional sums item is executed by the
contractor themself, profit and attendance will not be given.
6.Adjustment of provisional sum based on actual expended and omitted if not
expended
-Provisional will be adjusted based on actual expended and will be omitted if not expended
stated in the clause 30.11(d). Whereas for some provisional sum that is executed by the
NSC, the contractor will be given profit and attendance.
7.Additional expenses claims
-Clause 11.7 stated that any additional expenses caused by the variation that the contractor
will not be paid under any provisions in clause 11.6 can be claimed.
8.Loss and expense claims
-According to the clause 24.1, claim can be made by contractor for matters referred in clause
24.3. Moreover, contractor must have actually incurred a loss and expense. Based on clause
24.4, any amount of loss and expense shall be added to the contract sum. Final account has
to include the loss and expenses incurred by the contractor.
Question 2.
The tender drawings shows that the apartment has an entrance porch on the layout but no
details were provided sufficiently for measurement of quantities. The Quantity Surveyor then
had suggested that these items be listed as Provisional Sum. However you have forgot about this
item and did not include it in your tender document. The contract was awarded without it. Your
director would also like to know the significance and contractual implications of this
omission.(10 marks)
Being omitted from the tender document, the entrance porch is not within the Contractor’s obligation
under the contract. Under Clause 12.2, this issue of omission can be corrected by the Architect or
Consultant without voiding the contract itself which is a benefit for the Employer.
The Architect can issue an AI ordering a Variation under Clause 11.1(a) which refers to the entrance
porch being an additional provisional sum to the contract. The employer is protected by the Clause
11.2 which states that no Variations issued by the Architect shall vitiate the contract.
Being a provisional sum which has been added later, a new contract sum which takes the entrance
porch into account will be calculated. Being a provisional sum, it implies that the exact cost of the
works could not be calculated at the start due to lack of information. The cost of works will be
included in the Interim Certificate.
In the interim certificate, the works related with the entrance porch will be measured and placed under
variations, and will be valued according to clause 11.6(b) which uses rates and prices in the Contract
Document. Part of the cost will be retained as retention sum for the Defect Liability Period.
Throughout the projects, cost of the entrance porch will be included in the Interim Certificates until all
the related works are completed.
There will be an increase in contract sum compared to the original one, but the sum stated as
provisional sum is generally an overestimate of the cost of the related works.
Question 3.
In accordance with clause 30.10 of the contract, the contractor duly submitted his Final
Accounts within 6 months after the issuance of the Certificate of Practical Completion. You are
then required to assess this application and prepare the Final Account for the apartment project
based of the following valuations and adjustments made to the Contract Sum: (35 marks)
Project: ​Apartment project
Employer:
Contractor:
STATEMENT OF FINAL ACCOUNT
1.0 Original Contract Sum 71,800,000.00
2.0 ​Less​: P.C & Provisional Sums
(9,600,000.00)
​Total Builder’s Works
62,200,000.00
3.0 ​Add​: Variation works (V.O. Nos 1-4)
Total Additions 1,200,000.00
Total Omissions 586,000.00
Nett Additions ​ 614,000.00 ​614,000.00
​62,814,000.00
4.0 ​Add​: NSC’s final account
4.1 Lift Services 1,700,000.00
4.2 Air Conditioning Services 2,000,000.00
4.3 Electrical Services 2,700,000.00
4.4 Entrance Porch 1,250,000.00
​ 7,650,000.00 7,650,000.00
4.5 Profit and Attendance
a. Profit @ 2% of RM7,650,000.00 153,000.00
b. Attendance @ lump sum 151,000.00
​ 304,000.00 304,000.00
5.0 Contractual Claims:
5.1 Loss and Expenses 10,000.00
​ 10,000.00 10,000.00
FINAL CONTRACT VALUE
SUMMARY OF ORIGINAL CONTRACT SUM
Item Description Omission (RM) Addition
(RM)
Nett Addition/
Omission (RM)
1
2
3
4
Preliminaries
Building Works
Local Infrastructure Works
P.C. and Provisional Sums
5,250,000.00
50,450,000.00
6,500,000.00
9,600,000.00
-
-
-
-
5,250,000.00
50,450,000.00
6,500,000.00
9,600,000.00
TOTAL CARRIED TO
STATEMENT OF FINAL ACCOUNT
71,800,000.00 71,800,000.00
SUMMARY OF VARIATION WORKS
Variation
item
Description Omission
(RM)
Addition
(RM)
Nett Addition/
Omission (RM)
VO/1
VO/2
VO/3
VO/4
Changes of entrance lobby from
floor tiles to granite floor
New guard house
Changes from concrete block
drains to precast concrete culverts
Omission of hand railing to yard
300,000.00
-
200,000.00
86,000.00
500,000.00
300,000.00
400,000.00
-
200,000.00
300,000.00
200,000.00
(86,000.00)
TOTAL CARRIED TO
STATEMENT OF FINAL ACCOUNT
586,000.00 1,200,000.00 614,000.00
SUMMARY OF NSC FINAL ACCOUNTS
Variation
item
Description Omission (RM) Addition (RM) Nett Addition/
Omission (RM)
NSC/1
NSC/2
NSC/3
NSC/4
Lift Services
Profit @ 2%
Attendance as item
Air Conditioning Services
Profit @ 2%
Attendance as item
Electrical Services
Profit @ 2%
Attendance as item
Provisional
Profit @ 2%
Attendance as item
1,500,000.00
30,000.00
30,000.00
2,200,000.00
44,000.00
44,000.00
2,600,000.00
52,000.00
52,000.00
1,700,000.00
34,000.00
30,000.00
2,000,000.00
40,000.00
44,000.00
2,700,000.00
54,000.00
52,000.00
1,250,000.00
25,000.00
25,000.00
204,000.00
(204,000.00)
102,000.00
1,3000,000.00
TOTAL CARRIED TO
STATEMENT OF FINAL ACCOUNT
6,552,000.00 7,954,000.00 13,102,000.00
Total NSC Final Account 6,300,000.00 7,650,000.00
Total Profit 126,000.00 153,000.00
Total Attendance 126,000.00 151,000.00
SUMMARY OF LOSS AND EXPENSES
Variation
Item
Description Omision
(RM)
Addition
(RM)
Nett addition/
Omission(RM)
1. Additional expenses for
insurance premium
10,000.00 10,000.00
TOTAL CARRIED TO
STATEMENT OF FINAL ACCOUNT
10,000.00 10,000.00
Question 4.
On a different project, you were asked to explain the basis on how the following variations may
be finalised and priced during the Final Account stage:
(a) The Contractor had priced RM 160,000.00 for the Contractor All Risk Insurance policy in
the Preliminaries Bills. The Contractor failed to purchase this insurance when the works
commence. The Employer, then, bought and paid for the said insurance for RM 180,000.00 on
behalf of the Contractor. (10 marks)
Under Clause 20.A.1 in PAM Contract 2006 (With Quantities), It stated the insurance of new
buildings and works with contractor’s risks. Clause 20.A.1 provides the contractor’s All Risk
Insurance (CAR) policy which is made a condition precedent to the commencement of any work
under the Contract. In practice, the contractor would normally submit an insurance cover note to the
architect a week or two after the Date of Commencement pending the preparation of an insurance
policy. It is normal practice for contractor to work out with the requirements of the detailed
contractor’s All Risk (CAR) insurance policy.
Clause 20.A.1 stipulates that the duration of cover of the insurance policies to be valid up to the
Completion Date and the extended maintenance cover shall be constitute Defects Liability Period plus
a further three months. If the contractor failed and cannot complete within the insured period, there is
a delay and contractor shall ensure insurance is accordingly extended and the extension of insurance
cover not less than one month before the expiry of the insurance cover.
Clause 20.A.3 gives default powers to Employer to purchase the insurance on behalf of the Contractor
if the Contractor fails to effect and extend the insurance. The employer can set- off a reasonable
insurance premium for the period of cover against any sum due to the contractor or from the
contractor’s Performance Bond. On behalf of the contractor’s default, the employer’s premium paid
shall be recovered through a set-off under Clause 30.4. The employer shall be entitled to set-off all
cost incurred and loss and expense due to Contractor under Contract and/or from the Performance
Bond. The set-off is subject to either agreement of the contractor or adjudication where the employer
has to present his case to get the same order.
In this case, the contractor fails to purchase the Contractor All Risk Insurance(CAR) and it is a breach
of contractor. The employer’s premium paid shall be recovered through set-off as a debt from
Contractor under the Contract and/or the Performance Bond. Therefore, the insurance which increased
by employer from RM 160,000.00 to RM 180,000.00 is allowed. The final price for the said insurance
will be RM 180,000.00.
(b) Contractor is required to provide a desktop computer in the Preliminaries section for the
Resident Engineer’s use but this item was left unpriced, i.e. BQ item was left blank in the
rate/amount column in the contract document. However the Architect instructed the Contractor
to provide a laptop computer costing RM10,000.00 for the Resident Engineer instead of the
desktop computer as specified in the Preliminaries. (10 marks)
There are no specific rules or standard methods stated that all elements mentioned in the preliminaries
must be priced. As the desktop computer was left unpriced in the preliminaries section, it shall be
deemed that the rates and prices of the desktop computer had been included in the Bills of Quantities
by contractor.
Under PAM Contract 2006 Clause 11.6, it stated that the valuation of variations and work executed by
the Contractor for which Provisional Quantity is included in the Contract and the expenditure of
Provisional Sums (other than for work for which a tender had been accepted under Clause 27.14) shall
be made in accordance with the following rules :
Based on Clause 11.6(e), it stated that the rate and price of desktop computer which priced in
somewhere else should be determined and omitted. This clause can be supported by Clause 11.6(a), it
says that where work is of a similar character to, is executed under similar condition as, and does not
significantly change the quantity of work as set out in the Contract Documents, the rates and prices in
the Schedule of Rates shall determine the valuation. Which means that the Quantity Surveyor shall
omit the price of desktop computer based on fair market price which can be obtained from the
previous similar Contract Document or quotation from supplier. While the price of laptop computer
costing RM10,000.00 shall be added in the Contract Document.
(c) A wash trough as required and priced in the Preliminaries section was not constructed due
to site constraints imposed later by the Employer. However, the vehicles leaving the site during
construction were always kept clean including the public roads using water jet washing and
full-timed workers. (10 marks)
PAM Contract 2006 Clause 11.1(d)(iii) says that a Variation of any changes to the provisions in the
Contract with regards to access to or utilisation of any specific part of the Site. In this case, the wash
trough which has been priced in Preliminaries should be constructed at site but was not constructed
due to site constraints and replaced with water jet washing and full-time workers. Thus, it is
considered a change to provision in the Contract Document.
Therefore, under Clause 11.6(e), the price of wash trough should be omitted in the Contract
Document. While under Clause 11.6(a) for items with a similar character and conditions, the price of
water jet washing should be added into the Contract Document.
Clause 11.6(d) is a valuation of Variations where the work cannot be properly measured and valued
by using daywork rates or actual cost plus 15%. This method is only using when meets certain
per-condition when the work cannot be properly measured and valued.
The quantity of cleaning water cannot be properly measured and contractor cannot get the compensate
for actual costs incurred. Next, day work rate is mentioned in the contract which is used for labour,
plant and materials. Site staff must record and verified the daywork and send it to the architect and
also the consultants.
(d) Mistake was made in the price for excavation through rocks at RM50 per m3. Item was not
rationalised during contract documentation. However, original quantity in BQ is 100 m3 but
re-measured as-built quantity was 20,000 m3. The Contractor submitted a claim for revised
rates of RM 150 per m3 for the total quantity of 20,000 m3. (10 marks)
According to PAM Contract 2006 (With Quantities) Clause 11.6 stated 6 rules to be applied under
different situation of Variations. It is use to satisfy the terms of Variation and Architect’s Instructions
under Clause 11.1. In this clause, it defines variation as the alteration or modification of the design,
quality or quantity of the Works. But, Architect should be mindful not to instruct variation beyond the
contractual ambit, as such act could be regarded as “ultra vires” and could expose the Architect
directly liable under tort. Reversely, if such instruction calls for variation to the contractual provision,
the contractor cannot look for the Employer for compensation.
Under clause 11.6(b), where work is of similar character to work as set out in the Contract Documents
but is not executed under similar conditions or is executed under similar conditions but there is a
significant change in the quantity of work carried out, the rates and prices in the Contract Documents
shall be the basis for determining the valuation which shall include a fair adjustment in the rates to
take into account such difference by Quantity Surveyor.
In the situation provided in the question above, there is a significant change of quantity with similar
character of work from the original quantity of 100 m3 to 20,000 m3 in the contract BQ for the
excavation through rocks. In this case, Quantity Surveyor has to make a fair adjustment for the
differences of varied work (PAM Contract with Quantities under Clause 11.6b). The submitted rate
for the works by Contractor might be base on the work done in the contract, but when there are huge
varied work, the rate and price will be revise accordingly. In this case, Quantity Surveyor should take
the original contract rates and price as stated in the contract to create a reference of the new
adjustment.

Mais conteúdo relacionado

Mais procurados

Construction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's UniversityConstruction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's UniversityPang Khai Shuen
 
PP2 Assignment: Group
PP2 Assignment: GroupPP2 Assignment: Group
PP2 Assignment: GroupFarah Sham
 
Professional practice 1 (QS)
Professional practice 1 (QS)Professional practice 1 (QS)
Professional practice 1 (QS)Hasif Alias
 
PP2 final report
PP2 final reportPP2 final report
PP2 final reportArissa Loh
 
PP2 - Assignment
PP2 - AssignmentPP2 - Assignment
PP2 - AssignmentQuo Ming
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1Lee Pei Gie
 
Professional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentProfessional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentHaziq1511
 
Seminar - Partial Possession by Employer
Seminar - Partial Possession by EmployerSeminar - Partial Possession by Employer
Seminar - Partial Possession by EmployerKai Yun Pang
 
Sectional completion and partial possession by employer PP2 Coursework 1
Sectional completion and partial possession by employer PP2 Coursework 1Sectional completion and partial possession by employer PP2 Coursework 1
Sectional completion and partial possession by employer PP2 Coursework 1Arissa Loh
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment마 이환
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-finalashleyyeap
 
Payments in the construction industry
Payments in the construction industryPayments in the construction industry
Payments in the construction industryKheng Hoe Advocates
 
ECA Presentation slide
ECA Presentation slideECA Presentation slide
ECA Presentation slideseenyeeyong
 
Pp2 coursework 2 201808
Pp2 coursework 2   201808Pp2 coursework 2   201808
Pp2 coursework 2 201808Arissa Loh
 
Pp group assignment
Pp group assignmentPp group assignment
Pp group assignmentwendyteosy
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2ahmong4
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006Melvin Lim
 

Mais procurados (20)

Construction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's UniversityConstruction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's University
 
PP2 Assignment: Group
PP2 Assignment: GroupPP2 Assignment: Group
PP2 Assignment: Group
 
Professional practice 1 (QS)
Professional practice 1 (QS)Professional practice 1 (QS)
Professional practice 1 (QS)
 
Pp2 final report
Pp2 final reportPp2 final report
Pp2 final report
 
PP2 final report
PP2 final reportPP2 final report
PP2 final report
 
PP2 - Assignment
PP2 - AssignmentPP2 - Assignment
PP2 - Assignment
 
PP1 report
PP1 reportPP1 report
PP1 report
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
 
Professional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentProfessional Practice 1 Group Assignment
Professional Practice 1 Group Assignment
 
Seminar - Partial Possession by Employer
Seminar - Partial Possession by EmployerSeminar - Partial Possession by Employer
Seminar - Partial Possession by Employer
 
Sectional completion and partial possession by employer PP2 Coursework 1
Sectional completion and partial possession by employer PP2 Coursework 1Sectional completion and partial possession by employer PP2 Coursework 1
Sectional completion and partial possession by employer PP2 Coursework 1
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-final
 
Payments in the construction industry
Payments in the construction industryPayments in the construction industry
Payments in the construction industry
 
ECA Presentation slide
ECA Presentation slideECA Presentation slide
ECA Presentation slide
 
Pp2 coursework 2 201808
Pp2 coursework 2   201808Pp2 coursework 2   201808
Pp2 coursework 2 201808
 
Pp group assignment
Pp group assignmentPp group assignment
Pp group assignment
 
Pp1 seminar
Pp1 seminarPp1 seminar
Pp1 seminar
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006
 

Semelhante a Pp2 coursework 2

Professional Practice II
Professional Practice IIProfessional Practice II
Professional Practice IIseenyeeyong
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2Shze Hwa Lee
 
Assignment - Final Account
Assignment - Final AccountAssignment - Final Account
Assignment - Final AccountKai Yun Pang
 
Assignmenr for pp2 final account
Assignmenr for pp2 final accountAssignmenr for pp2 final account
Assignmenr for pp2 final accountahmong4
 
Pp2 assignment
Pp2 assignmentPp2 assignment
Pp2 assignmentfareezsham
 
Pp2 group assignment
Pp2 group assignmentPp2 group assignment
Pp2 group assignmentlohwenjun
 
PP2 - Group Assignment
PP2 - Group AssignmentPP2 - Group Assignment
PP2 - Group AssignmentLin Hui
 
A Claim submitted by the contractor during for slides.pptx
A Claim submitted by the contractor during for slides.pptxA Claim submitted by the contractor during for slides.pptx
A Claim submitted by the contractor during for slides.pptxMahSobeh
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - ReportKai Yun Pang
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7Farah Sham
 
Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...
Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...
Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...tdartnell
 
Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)Yee Len Wan
 
Pp2 coursework 2 brief
Pp2 coursework 2  briefPp2 coursework 2  brief
Pp2 coursework 2 briefDoreen Yeo
 
Pp2 coursework 2 BRIEF 201708
Pp2 coursework 2  BRIEF  201708Pp2 coursework 2  BRIEF  201708
Pp2 coursework 2 BRIEF 201708Pang Khai Shuen
 
Cbb512 examination november_2011
Cbb512 examination november_2011Cbb512 examination november_2011
Cbb512 examination november_2011Maatla Moadi
 
Presentation 7-pp-final
Presentation 7-pp-finalPresentation 7-pp-final
Presentation 7-pp-finalWan Nee
 

Semelhante a Pp2 coursework 2 (20)

PP2 - Assignment
PP2 - Assignment PP2 - Assignment
PP2 - Assignment
 
Professional Practice II
Professional Practice IIProfessional Practice II
Professional Practice II
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
Assignment - Final Account
Assignment - Final AccountAssignment - Final Account
Assignment - Final Account
 
Assignmenr for pp2 final account
Assignmenr for pp2 final accountAssignmenr for pp2 final account
Assignmenr for pp2 final account
 
PP2 COMPILCATION
PP2 COMPILCATIONPP2 COMPILCATION
PP2 COMPILCATION
 
Pp2 asignment-1
Pp2 asignment-1Pp2 asignment-1
Pp2 asignment-1
 
Pp2 assignment
Pp2 assignmentPp2 assignment
Pp2 assignment
 
Pp2 group assignment
Pp2 group assignmentPp2 group assignment
Pp2 group assignment
 
PP2 - Group Assignment
PP2 - Group AssignmentPP2 - Group Assignment
PP2 - Group Assignment
 
A Claim submitted by the contractor during for slides.pptx
A Claim submitted by the contractor during for slides.pptxA Claim submitted by the contractor during for slides.pptx
A Claim submitted by the contractor during for slides.pptx
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - Report
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
 
Cl report final
Cl report finalCl report final
Cl report final
 
Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...
Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...
Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...
 
Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)
 
Pp2 coursework 2 brief
Pp2 coursework 2  briefPp2 coursework 2  brief
Pp2 coursework 2 brief
 
Pp2 coursework 2 BRIEF 201708
Pp2 coursework 2  BRIEF  201708Pp2 coursework 2  BRIEF  201708
Pp2 coursework 2 BRIEF 201708
 
Cbb512 examination november_2011
Cbb512 examination november_2011Cbb512 examination november_2011
Cbb512 examination november_2011
 
Presentation 7-pp-final
Presentation 7-pp-finalPresentation 7-pp-final
Presentation 7-pp-final
 

Mais de tfkc1212

Building economic
Building economicBuilding economic
Building economictfkc1212
 
Financial management (group assignment)
Financial management (group assignment)Financial management (group assignment)
Financial management (group assignment)tfkc1212
 
Pp2 presentation
Pp2 presentationPp2 presentation
Pp2 presentationtfkc1212
 
Measurement iv
Measurement ivMeasurement iv
Measurement ivtfkc1212
 
Estimating presentation (1)
Estimating presentation (1)Estimating presentation (1)
Estimating presentation (1)tfkc1212
 
Professional practice 1
Professional practice 1Professional practice 1
Professional practice 1tfkc1212
 
Professional practice 1 (1)
Professional practice 1 (1)Professional practice 1 (1)
Professional practice 1 (1)tfkc1212
 
Estimating presentation
Estimating presentationEstimating presentation
Estimating presentationtfkc1212
 
People dynamic
People dynamicPeople dynamic
People dynamictfkc1212
 
Safety 2doc
Safety 2docSafety 2doc
Safety 2doctfkc1212
 
The issues of electrical hazards at site and steps to prevent.
The issues of electrical hazards at site  and steps to prevent.The issues of electrical hazards at site  and steps to prevent.
The issues of electrical hazards at site and steps to prevent.tfkc1212
 
Bs assignment
Bs assignmentBs assignment
Bs assignmenttfkc1212
 
Managementscienceassignment (2)
Managementscienceassignment (2)Managementscienceassignment (2)
Managementscienceassignment (2)tfkc1212
 
Installation of hot water supply for hotel (recovered)
Installation of hot water supply for hotel (recovered)Installation of hot water supply for hotel (recovered)
Installation of hot water supply for hotel (recovered)tfkc1212
 
Levelling report-1
Levelling report-1Levelling report-1
Levelling report-1tfkc1212
 
1bici updated-141129071811-conversion-gate01
1bici updated-141129071811-conversion-gate011bici updated-141129071811-conversion-gate01
1bici updated-141129071811-conversion-gate01tfkc1212
 
Enbe project2
Enbe project2Enbe project2
Enbe project2tfkc1212
 
Enbe.doc99
Enbe.doc99Enbe.doc99
Enbe.doc99tfkc1212
 
Project2designprocessresearchanalysis 141209223425-conversion-gate02
Project2designprocessresearchanalysis 141209223425-conversion-gate02Project2designprocessresearchanalysis 141209223425-conversion-gate02
Project2designprocessresearchanalysis 141209223425-conversion-gate02tfkc1212
 
Project03finalprojectbriefing 141217105844-conversion-gate01
Project03finalprojectbriefing 141217105844-conversion-gate01Project03finalprojectbriefing 141217105844-conversion-gate01
Project03finalprojectbriefing 141217105844-conversion-gate01tfkc1212
 

Mais de tfkc1212 (20)

Building economic
Building economicBuilding economic
Building economic
 
Financial management (group assignment)
Financial management (group assignment)Financial management (group assignment)
Financial management (group assignment)
 
Pp2 presentation
Pp2 presentationPp2 presentation
Pp2 presentation
 
Measurement iv
Measurement ivMeasurement iv
Measurement iv
 
Estimating presentation (1)
Estimating presentation (1)Estimating presentation (1)
Estimating presentation (1)
 
Professional practice 1
Professional practice 1Professional practice 1
Professional practice 1
 
Professional practice 1 (1)
Professional practice 1 (1)Professional practice 1 (1)
Professional practice 1 (1)
 
Estimating presentation
Estimating presentationEstimating presentation
Estimating presentation
 
People dynamic
People dynamicPeople dynamic
People dynamic
 
Safety 2doc
Safety 2docSafety 2doc
Safety 2doc
 
The issues of electrical hazards at site and steps to prevent.
The issues of electrical hazards at site  and steps to prevent.The issues of electrical hazards at site  and steps to prevent.
The issues of electrical hazards at site and steps to prevent.
 
Bs assignment
Bs assignmentBs assignment
Bs assignment
 
Managementscienceassignment (2)
Managementscienceassignment (2)Managementscienceassignment (2)
Managementscienceassignment (2)
 
Installation of hot water supply for hotel (recovered)
Installation of hot water supply for hotel (recovered)Installation of hot water supply for hotel (recovered)
Installation of hot water supply for hotel (recovered)
 
Levelling report-1
Levelling report-1Levelling report-1
Levelling report-1
 
1bici updated-141129071811-conversion-gate01
1bici updated-141129071811-conversion-gate011bici updated-141129071811-conversion-gate01
1bici updated-141129071811-conversion-gate01
 
Enbe project2
Enbe project2Enbe project2
Enbe project2
 
Enbe.doc99
Enbe.doc99Enbe.doc99
Enbe.doc99
 
Project2designprocessresearchanalysis 141209223425-conversion-gate02
Project2designprocessresearchanalysis 141209223425-conversion-gate02Project2designprocessresearchanalysis 141209223425-conversion-gate02
Project2designprocessresearchanalysis 141209223425-conversion-gate02
 
Project03finalprojectbriefing 141217105844-conversion-gate01
Project03finalprojectbriefing 141217105844-conversion-gate01Project03finalprojectbriefing 141217105844-conversion-gate01
Project03finalprojectbriefing 141217105844-conversion-gate01
 

Último

办理萨省大学毕业证成绩单|购买加拿大USASK文凭证书
办理萨省大学毕业证成绩单|购买加拿大USASK文凭证书办理萨省大学毕业证成绩单|购买加拿大USASK文凭证书
办理萨省大学毕业证成绩单|购买加拿大USASK文凭证书zdzoqco
 
如何办理(UQ毕业证书)昆士兰大学毕业证毕业证成绩单原版一比一
如何办理(UQ毕业证书)昆士兰大学毕业证毕业证成绩单原版一比一如何办理(UQ毕业证书)昆士兰大学毕业证毕业证成绩单原版一比一
如何办理(UQ毕业证书)昆士兰大学毕业证毕业证成绩单原版一比一hnfusn
 
Can't Roll Up Your Audi A4 Power Window Let's Uncover the Issue!
Can't Roll Up Your Audi A4 Power Window Let's Uncover the Issue!Can't Roll Up Your Audi A4 Power Window Let's Uncover the Issue!
Can't Roll Up Your Audi A4 Power Window Let's Uncover the Issue!Mint Automotive
 
What Causes The key not detected Message In Mercedes Cars
What Causes The key not detected Message In Mercedes CarsWhat Causes The key not detected Message In Mercedes Cars
What Causes The key not detected Message In Mercedes CarsGermany's Best Inc
 
办理学位证(MLU文凭证书)哈勒 维滕贝格大学毕业证成绩单原版一模一样
办理学位证(MLU文凭证书)哈勒 维滕贝格大学毕业证成绩单原版一模一样办理学位证(MLU文凭证书)哈勒 维滕贝格大学毕业证成绩单原版一模一样
办理学位证(MLU文凭证书)哈勒 维滕贝格大学毕业证成绩单原版一模一样umasea
 
(Griffith毕业证)格里菲斯大学毕业证毕业证成绩单修改留信学历认证原版一比一
(Griffith毕业证)格里菲斯大学毕业证毕业证成绩单修改留信学历认证原版一比一(Griffith毕业证)格里菲斯大学毕业证毕业证成绩单修改留信学历认证原版一比一
(Griffith毕业证)格里菲斯大学毕业证毕业证成绩单修改留信学历认证原版一比一ejgeojhg
 
原版工艺美国普林斯顿大学毕业证Princeton毕业证成绩单修改留信学历认证
原版工艺美国普林斯顿大学毕业证Princeton毕业证成绩单修改留信学历认证原版工艺美国普林斯顿大学毕业证Princeton毕业证成绩单修改留信学历认证
原版工艺美国普林斯顿大学毕业证Princeton毕业证成绩单修改留信学历认证jjrehjwj11gg
 
原版1:1定制(IC大学毕业证)帝国理工学院大学毕业证国外文凭复刻成绩单#电子版制作#留信入库#多年经营绝对保证质量
原版1:1定制(IC大学毕业证)帝国理工学院大学毕业证国外文凭复刻成绩单#电子版制作#留信入库#多年经营绝对保证质量原版1:1定制(IC大学毕业证)帝国理工学院大学毕业证国外文凭复刻成绩单#电子版制作#留信入库#多年经营绝对保证质量
原版1:1定制(IC大学毕业证)帝国理工学院大学毕业证国外文凭复刻成绩单#电子版制作#留信入库#多年经营绝对保证质量208367051
 
Digamma - CertiCon Team Skills and Qualifications
Digamma - CertiCon Team Skills and QualificationsDigamma - CertiCon Team Skills and Qualifications
Digamma - CertiCon Team Skills and QualificationsMihajloManjak
 
办理阳光海岸大学毕业证成绩单原版一比一
办理阳光海岸大学毕业证成绩单原版一比一办理阳光海岸大学毕业证成绩单原版一比一
办理阳光海岸大学毕业证成绩单原版一比一F La
 
办理(PITT毕业证书)美国匹兹堡大学毕业证成绩单原版一比一
办理(PITT毕业证书)美国匹兹堡大学毕业证成绩单原版一比一办理(PITT毕业证书)美国匹兹堡大学毕业证成绩单原版一比一
办理(PITT毕业证书)美国匹兹堡大学毕业证成绩单原版一比一F La
 
(办理原版一样)Flinders毕业证弗林德斯大学毕业证学位证留信学历认证成绩单补办
(办理原版一样)Flinders毕业证弗林德斯大学毕业证学位证留信学历认证成绩单补办(办理原版一样)Flinders毕业证弗林德斯大学毕业证学位证留信学历认证成绩单补办
(办理原版一样)Flinders毕业证弗林德斯大学毕业证学位证留信学历认证成绩单补办fqiuho152
 
原版1:1复刻俄亥俄州立大学毕业证OSU毕业证留信学历认证
原版1:1复刻俄亥俄州立大学毕业证OSU毕业证留信学历认证原版1:1复刻俄亥俄州立大学毕业证OSU毕业证留信学历认证
原版1:1复刻俄亥俄州立大学毕业证OSU毕业证留信学历认证jdkhjh
 
call girls in G.T.B. Nagar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in  G.T.B. Nagar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in  G.T.B. Nagar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in G.T.B. Nagar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
2024 WRC Hyundai World Rally Team’s i20 N Rally1 Hybrid
2024 WRC Hyundai World Rally Team’s i20 N Rally1 Hybrid2024 WRC Hyundai World Rally Team’s i20 N Rally1 Hybrid
2024 WRC Hyundai World Rally Team’s i20 N Rally1 HybridHyundai Motor Group
 
2024 TOP 10 most fuel-efficient vehicles according to the US agency
2024 TOP 10 most fuel-efficient vehicles according to the US agency2024 TOP 10 most fuel-efficient vehicles according to the US agency
2024 TOP 10 most fuel-efficient vehicles according to the US agencyHyundai Motor Group
 
What Could Cause A VW Tiguan's Radiator Fan To Stop Working
What Could Cause A VW Tiguan's Radiator Fan To Stop WorkingWhat Could Cause A VW Tiguan's Radiator Fan To Stop Working
What Could Cause A VW Tiguan's Radiator Fan To Stop WorkingEscondido German Auto
 
原版1:1定制阳光海岸大学毕业证(JCU毕业证)#文凭成绩单#真实留信学历认证永久存档
原版1:1定制阳光海岸大学毕业证(JCU毕业证)#文凭成绩单#真实留信学历认证永久存档原版1:1定制阳光海岸大学毕业证(JCU毕业证)#文凭成绩单#真实留信学历认证永久存档
原版1:1定制阳光海岸大学毕业证(JCU毕业证)#文凭成绩单#真实留信学历认证永久存档208367051
 
(办理学位证)墨尔本大学毕业证(Unimelb毕业证书)成绩单留信学历认证原版一模一样
(办理学位证)墨尔本大学毕业证(Unimelb毕业证书)成绩单留信学历认证原版一模一样(办理学位证)墨尔本大学毕业证(Unimelb毕业证书)成绩单留信学历认证原版一模一样
(办理学位证)墨尔本大学毕业证(Unimelb毕业证书)成绩单留信学历认证原版一模一样whjjkkk
 
EPA Funding Opportunities for Equitable Electric Transportation by Mike Moltzen
EPA Funding Opportunities for Equitable Electric Transportationby Mike MoltzenEPA Funding Opportunities for Equitable Electric Transportationby Mike Moltzen
EPA Funding Opportunities for Equitable Electric Transportation by Mike MoltzenForth
 

Último (20)

办理萨省大学毕业证成绩单|购买加拿大USASK文凭证书
办理萨省大学毕业证成绩单|购买加拿大USASK文凭证书办理萨省大学毕业证成绩单|购买加拿大USASK文凭证书
办理萨省大学毕业证成绩单|购买加拿大USASK文凭证书
 
如何办理(UQ毕业证书)昆士兰大学毕业证毕业证成绩单原版一比一
如何办理(UQ毕业证书)昆士兰大学毕业证毕业证成绩单原版一比一如何办理(UQ毕业证书)昆士兰大学毕业证毕业证成绩单原版一比一
如何办理(UQ毕业证书)昆士兰大学毕业证毕业证成绩单原版一比一
 
Can't Roll Up Your Audi A4 Power Window Let's Uncover the Issue!
Can't Roll Up Your Audi A4 Power Window Let's Uncover the Issue!Can't Roll Up Your Audi A4 Power Window Let's Uncover the Issue!
Can't Roll Up Your Audi A4 Power Window Let's Uncover the Issue!
 
What Causes The key not detected Message In Mercedes Cars
What Causes The key not detected Message In Mercedes CarsWhat Causes The key not detected Message In Mercedes Cars
What Causes The key not detected Message In Mercedes Cars
 
办理学位证(MLU文凭证书)哈勒 维滕贝格大学毕业证成绩单原版一模一样
办理学位证(MLU文凭证书)哈勒 维滕贝格大学毕业证成绩单原版一模一样办理学位证(MLU文凭证书)哈勒 维滕贝格大学毕业证成绩单原版一模一样
办理学位证(MLU文凭证书)哈勒 维滕贝格大学毕业证成绩单原版一模一样
 
(Griffith毕业证)格里菲斯大学毕业证毕业证成绩单修改留信学历认证原版一比一
(Griffith毕业证)格里菲斯大学毕业证毕业证成绩单修改留信学历认证原版一比一(Griffith毕业证)格里菲斯大学毕业证毕业证成绩单修改留信学历认证原版一比一
(Griffith毕业证)格里菲斯大学毕业证毕业证成绩单修改留信学历认证原版一比一
 
原版工艺美国普林斯顿大学毕业证Princeton毕业证成绩单修改留信学历认证
原版工艺美国普林斯顿大学毕业证Princeton毕业证成绩单修改留信学历认证原版工艺美国普林斯顿大学毕业证Princeton毕业证成绩单修改留信学历认证
原版工艺美国普林斯顿大学毕业证Princeton毕业证成绩单修改留信学历认证
 
原版1:1定制(IC大学毕业证)帝国理工学院大学毕业证国外文凭复刻成绩单#电子版制作#留信入库#多年经营绝对保证质量
原版1:1定制(IC大学毕业证)帝国理工学院大学毕业证国外文凭复刻成绩单#电子版制作#留信入库#多年经营绝对保证质量原版1:1定制(IC大学毕业证)帝国理工学院大学毕业证国外文凭复刻成绩单#电子版制作#留信入库#多年经营绝对保证质量
原版1:1定制(IC大学毕业证)帝国理工学院大学毕业证国外文凭复刻成绩单#电子版制作#留信入库#多年经营绝对保证质量
 
Digamma - CertiCon Team Skills and Qualifications
Digamma - CertiCon Team Skills and QualificationsDigamma - CertiCon Team Skills and Qualifications
Digamma - CertiCon Team Skills and Qualifications
 
办理阳光海岸大学毕业证成绩单原版一比一
办理阳光海岸大学毕业证成绩单原版一比一办理阳光海岸大学毕业证成绩单原版一比一
办理阳光海岸大学毕业证成绩单原版一比一
 
办理(PITT毕业证书)美国匹兹堡大学毕业证成绩单原版一比一
办理(PITT毕业证书)美国匹兹堡大学毕业证成绩单原版一比一办理(PITT毕业证书)美国匹兹堡大学毕业证成绩单原版一比一
办理(PITT毕业证书)美国匹兹堡大学毕业证成绩单原版一比一
 
(办理原版一样)Flinders毕业证弗林德斯大学毕业证学位证留信学历认证成绩单补办
(办理原版一样)Flinders毕业证弗林德斯大学毕业证学位证留信学历认证成绩单补办(办理原版一样)Flinders毕业证弗林德斯大学毕业证学位证留信学历认证成绩单补办
(办理原版一样)Flinders毕业证弗林德斯大学毕业证学位证留信学历认证成绩单补办
 
原版1:1复刻俄亥俄州立大学毕业证OSU毕业证留信学历认证
原版1:1复刻俄亥俄州立大学毕业证OSU毕业证留信学历认证原版1:1复刻俄亥俄州立大学毕业证OSU毕业证留信学历认证
原版1:1复刻俄亥俄州立大学毕业证OSU毕业证留信学历认证
 
call girls in G.T.B. Nagar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in  G.T.B. Nagar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in  G.T.B. Nagar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in G.T.B. Nagar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
2024 WRC Hyundai World Rally Team’s i20 N Rally1 Hybrid
2024 WRC Hyundai World Rally Team’s i20 N Rally1 Hybrid2024 WRC Hyundai World Rally Team’s i20 N Rally1 Hybrid
2024 WRC Hyundai World Rally Team’s i20 N Rally1 Hybrid
 
2024 TOP 10 most fuel-efficient vehicles according to the US agency
2024 TOP 10 most fuel-efficient vehicles according to the US agency2024 TOP 10 most fuel-efficient vehicles according to the US agency
2024 TOP 10 most fuel-efficient vehicles according to the US agency
 
What Could Cause A VW Tiguan's Radiator Fan To Stop Working
What Could Cause A VW Tiguan's Radiator Fan To Stop WorkingWhat Could Cause A VW Tiguan's Radiator Fan To Stop Working
What Could Cause A VW Tiguan's Radiator Fan To Stop Working
 
原版1:1定制阳光海岸大学毕业证(JCU毕业证)#文凭成绩单#真实留信学历认证永久存档
原版1:1定制阳光海岸大学毕业证(JCU毕业证)#文凭成绩单#真实留信学历认证永久存档原版1:1定制阳光海岸大学毕业证(JCU毕业证)#文凭成绩单#真实留信学历认证永久存档
原版1:1定制阳光海岸大学毕业证(JCU毕业证)#文凭成绩单#真实留信学历认证永久存档
 
(办理学位证)墨尔本大学毕业证(Unimelb毕业证书)成绩单留信学历认证原版一模一样
(办理学位证)墨尔本大学毕业证(Unimelb毕业证书)成绩单留信学历认证原版一模一样(办理学位证)墨尔本大学毕业证(Unimelb毕业证书)成绩单留信学历认证原版一模一样
(办理学位证)墨尔本大学毕业证(Unimelb毕业证书)成绩单留信学历认证原版一模一样
 
EPA Funding Opportunities for Equitable Electric Transportation by Mike Moltzen
EPA Funding Opportunities for Equitable Electric Transportationby Mike MoltzenEPA Funding Opportunities for Equitable Electric Transportationby Mike Moltzen
EPA Funding Opportunities for Equitable Electric Transportation by Mike Moltzen
 

Pp2 coursework 2

  • 1.   SCHOOL OF ARCHITECTURE, BUILD AND DESIGN BACHELOR OF QUANTITY SURVEYING (HONOURS) PROFESSIONAL PRACTICE 2 (QSB 60904) Coursework 2 NAME STUDENT ID Hing Pui Kei 0325961 Le Jia Nian 0319957 Lim Ting Le 0320028 Ng Huoy Miin 0319097 Sylvester Tang Kiok Heng 0325152 Wong Qin Kai 0320024 Charanjeev Gunputh 0323942
  • 2. TABLE OF CONTENT DESCRIPTION PAGE 1.0 Question 1 2.0 Question 2 3.0 Question 3 4.0 Question 4 4.1 Question 4 (a) 4.2 Question 4 (b) 4.3 Question 4 (c) 4.4 Question 4 (d)
  • 3. Question 1. You are required to prepare a report to your director, explaining briefly the adjustments of the essential elements in your preparation of this project’s final account. (15 marks) According to the clause 30.11 in the PAM Contract 2006 (with quantities), the work adjustment made to the contract sum must be shown in the final account. The final account shall be conclusive and deemed agreed by the parties otherwise any outstanding items to be resolved separately among the employer and the contractor. In this project final account, the following essential element will be: 1.Variation works -Under clause 11.1, works being executed will be defined as variation works. Next, the rules of valuation will be based on clause 11.6(a) to 11.6(d) if it is an additional works. Whereas, the rules of valuation will be based on clause 11.6(e) if it is an omission works, stating that the contract rates and price will be used for omission. 2.Remeasurement of provisional quantities -A need in re-measured of the provisional quantities under clause 30.10 says that documents shall contain details of quantities. Architect must re-measured items in the contract bills which are provisional quantities based on the actual quantities executed. Based on clause 11.6(f), the rates and prices in the schedule of rates shall determine their valuations. 3.Omission of prime cost and provisional sum -Final account shall show the omission of all prime cost sums and the related profits provided by the contractor in the contract document stated in clause 30.11(c). Moreover, some items which are allowed in the provisional sum will not be added back into the final account, example the contingency sum. Hence, the omission of the prime cost and provisional sum is for the amount that will need to be re-measured based on the tender price.
  • 4. 4. Adding back of NSC and NS final account -Under the clause 30.11(c), the final account of the NSC for the prime cost sum and provisional sum should be added back to the final account as the figure in the contract sum may not be the actual sum incurred. 5.Adjustment of profit and attendance -The contractor will be given profit and attendance with the basics of NSC and NS final account according to the clause 30.11(c). If the provisional sums item is executed by the contractor themself, profit and attendance will not be given. 6.Adjustment of provisional sum based on actual expended and omitted if not expended -Provisional will be adjusted based on actual expended and will be omitted if not expended stated in the clause 30.11(d). Whereas for some provisional sum that is executed by the NSC, the contractor will be given profit and attendance. 7.Additional expenses claims -Clause 11.7 stated that any additional expenses caused by the variation that the contractor will not be paid under any provisions in clause 11.6 can be claimed. 8.Loss and expense claims -According to the clause 24.1, claim can be made by contractor for matters referred in clause 24.3. Moreover, contractor must have actually incurred a loss and expense. Based on clause 24.4, any amount of loss and expense shall be added to the contract sum. Final account has to include the loss and expenses incurred by the contractor.
  • 5. Question 2. The tender drawings shows that the apartment has an entrance porch on the layout but no details were provided sufficiently for measurement of quantities. The Quantity Surveyor then had suggested that these items be listed as Provisional Sum. However you have forgot about this item and did not include it in your tender document. The contract was awarded without it. Your director would also like to know the significance and contractual implications of this omission.(10 marks) Being omitted from the tender document, the entrance porch is not within the Contractor’s obligation under the contract. Under Clause 12.2, this issue of omission can be corrected by the Architect or Consultant without voiding the contract itself which is a benefit for the Employer. The Architect can issue an AI ordering a Variation under Clause 11.1(a) which refers to the entrance porch being an additional provisional sum to the contract. The employer is protected by the Clause 11.2 which states that no Variations issued by the Architect shall vitiate the contract. Being a provisional sum which has been added later, a new contract sum which takes the entrance porch into account will be calculated. Being a provisional sum, it implies that the exact cost of the works could not be calculated at the start due to lack of information. The cost of works will be included in the Interim Certificate. In the interim certificate, the works related with the entrance porch will be measured and placed under variations, and will be valued according to clause 11.6(b) which uses rates and prices in the Contract Document. Part of the cost will be retained as retention sum for the Defect Liability Period. Throughout the projects, cost of the entrance porch will be included in the Interim Certificates until all the related works are completed. There will be an increase in contract sum compared to the original one, but the sum stated as provisional sum is generally an overestimate of the cost of the related works.
  • 6. Question 3. In accordance with clause 30.10 of the contract, the contractor duly submitted his Final Accounts within 6 months after the issuance of the Certificate of Practical Completion. You are then required to assess this application and prepare the Final Account for the apartment project based of the following valuations and adjustments made to the Contract Sum: (35 marks)
  • 7. Project: ​Apartment project Employer: Contractor: STATEMENT OF FINAL ACCOUNT 1.0 Original Contract Sum 71,800,000.00 2.0 ​Less​: P.C & Provisional Sums (9,600,000.00) ​Total Builder’s Works 62,200,000.00 3.0 ​Add​: Variation works (V.O. Nos 1-4) Total Additions 1,200,000.00 Total Omissions 586,000.00 Nett Additions ​ 614,000.00 ​614,000.00 ​62,814,000.00 4.0 ​Add​: NSC’s final account 4.1 Lift Services 1,700,000.00 4.2 Air Conditioning Services 2,000,000.00 4.3 Electrical Services 2,700,000.00 4.4 Entrance Porch 1,250,000.00 ​ 7,650,000.00 7,650,000.00 4.5 Profit and Attendance a. Profit @ 2% of RM7,650,000.00 153,000.00 b. Attendance @ lump sum 151,000.00 ​ 304,000.00 304,000.00 5.0 Contractual Claims: 5.1 Loss and Expenses 10,000.00 ​ 10,000.00 10,000.00
  • 8. FINAL CONTRACT VALUE SUMMARY OF ORIGINAL CONTRACT SUM Item Description Omission (RM) Addition (RM) Nett Addition/ Omission (RM) 1 2 3 4 Preliminaries Building Works Local Infrastructure Works P.C. and Provisional Sums 5,250,000.00 50,450,000.00 6,500,000.00 9,600,000.00 - - - - 5,250,000.00 50,450,000.00 6,500,000.00 9,600,000.00 TOTAL CARRIED TO STATEMENT OF FINAL ACCOUNT 71,800,000.00 71,800,000.00
  • 9. SUMMARY OF VARIATION WORKS Variation item Description Omission (RM) Addition (RM) Nett Addition/ Omission (RM) VO/1 VO/2 VO/3 VO/4 Changes of entrance lobby from floor tiles to granite floor New guard house Changes from concrete block drains to precast concrete culverts Omission of hand railing to yard 300,000.00 - 200,000.00 86,000.00 500,000.00 300,000.00 400,000.00 - 200,000.00 300,000.00 200,000.00 (86,000.00) TOTAL CARRIED TO STATEMENT OF FINAL ACCOUNT 586,000.00 1,200,000.00 614,000.00
  • 10. SUMMARY OF NSC FINAL ACCOUNTS Variation item Description Omission (RM) Addition (RM) Nett Addition/ Omission (RM) NSC/1 NSC/2 NSC/3 NSC/4 Lift Services Profit @ 2% Attendance as item Air Conditioning Services Profit @ 2% Attendance as item Electrical Services Profit @ 2% Attendance as item Provisional Profit @ 2% Attendance as item 1,500,000.00 30,000.00 30,000.00 2,200,000.00 44,000.00 44,000.00 2,600,000.00 52,000.00 52,000.00 1,700,000.00 34,000.00 30,000.00 2,000,000.00 40,000.00 44,000.00 2,700,000.00 54,000.00 52,000.00 1,250,000.00 25,000.00 25,000.00 204,000.00 (204,000.00) 102,000.00 1,3000,000.00 TOTAL CARRIED TO STATEMENT OF FINAL ACCOUNT 6,552,000.00 7,954,000.00 13,102,000.00 Total NSC Final Account 6,300,000.00 7,650,000.00 Total Profit 126,000.00 153,000.00
  • 11. Total Attendance 126,000.00 151,000.00 SUMMARY OF LOSS AND EXPENSES Variation Item Description Omision (RM) Addition (RM) Nett addition/ Omission(RM) 1. Additional expenses for insurance premium 10,000.00 10,000.00 TOTAL CARRIED TO STATEMENT OF FINAL ACCOUNT 10,000.00 10,000.00
  • 12. Question 4. On a different project, you were asked to explain the basis on how the following variations may be finalised and priced during the Final Account stage: (a) The Contractor had priced RM 160,000.00 for the Contractor All Risk Insurance policy in the Preliminaries Bills. The Contractor failed to purchase this insurance when the works commence. The Employer, then, bought and paid for the said insurance for RM 180,000.00 on behalf of the Contractor. (10 marks) Under Clause 20.A.1 in PAM Contract 2006 (With Quantities), It stated the insurance of new buildings and works with contractor’s risks. Clause 20.A.1 provides the contractor’s All Risk Insurance (CAR) policy which is made a condition precedent to the commencement of any work under the Contract. In practice, the contractor would normally submit an insurance cover note to the architect a week or two after the Date of Commencement pending the preparation of an insurance policy. It is normal practice for contractor to work out with the requirements of the detailed contractor’s All Risk (CAR) insurance policy. Clause 20.A.1 stipulates that the duration of cover of the insurance policies to be valid up to the Completion Date and the extended maintenance cover shall be constitute Defects Liability Period plus a further three months. If the contractor failed and cannot complete within the insured period, there is a delay and contractor shall ensure insurance is accordingly extended and the extension of insurance cover not less than one month before the expiry of the insurance cover. Clause 20.A.3 gives default powers to Employer to purchase the insurance on behalf of the Contractor if the Contractor fails to effect and extend the insurance. The employer can set- off a reasonable insurance premium for the period of cover against any sum due to the contractor or from the contractor’s Performance Bond. On behalf of the contractor’s default, the employer’s premium paid shall be recovered through a set-off under Clause 30.4. The employer shall be entitled to set-off all cost incurred and loss and expense due to Contractor under Contract and/or from the Performance Bond. The set-off is subject to either agreement of the contractor or adjudication where the employer has to present his case to get the same order. In this case, the contractor fails to purchase the Contractor All Risk Insurance(CAR) and it is a breach of contractor. The employer’s premium paid shall be recovered through set-off as a debt from
  • 13. Contractor under the Contract and/or the Performance Bond. Therefore, the insurance which increased by employer from RM 160,000.00 to RM 180,000.00 is allowed. The final price for the said insurance will be RM 180,000.00. (b) Contractor is required to provide a desktop computer in the Preliminaries section for the Resident Engineer’s use but this item was left unpriced, i.e. BQ item was left blank in the rate/amount column in the contract document. However the Architect instructed the Contractor to provide a laptop computer costing RM10,000.00 for the Resident Engineer instead of the desktop computer as specified in the Preliminaries. (10 marks) There are no specific rules or standard methods stated that all elements mentioned in the preliminaries must be priced. As the desktop computer was left unpriced in the preliminaries section, it shall be deemed that the rates and prices of the desktop computer had been included in the Bills of Quantities by contractor. Under PAM Contract 2006 Clause 11.6, it stated that the valuation of variations and work executed by the Contractor for which Provisional Quantity is included in the Contract and the expenditure of Provisional Sums (other than for work for which a tender had been accepted under Clause 27.14) shall be made in accordance with the following rules : Based on Clause 11.6(e), it stated that the rate and price of desktop computer which priced in somewhere else should be determined and omitted. This clause can be supported by Clause 11.6(a), it says that where work is of a similar character to, is executed under similar condition as, and does not significantly change the quantity of work as set out in the Contract Documents, the rates and prices in the Schedule of Rates shall determine the valuation. Which means that the Quantity Surveyor shall omit the price of desktop computer based on fair market price which can be obtained from the previous similar Contract Document or quotation from supplier. While the price of laptop computer costing RM10,000.00 shall be added in the Contract Document. (c) A wash trough as required and priced in the Preliminaries section was not constructed due to site constraints imposed later by the Employer. However, the vehicles leaving the site during construction were always kept clean including the public roads using water jet washing and full-timed workers. (10 marks) PAM Contract 2006 Clause 11.1(d)(iii) says that a Variation of any changes to the provisions in the Contract with regards to access to or utilisation of any specific part of the Site. In this case, the wash trough which has been priced in Preliminaries should be constructed at site but was not constructed due to site constraints and replaced with water jet washing and full-time workers. Thus, it is considered a change to provision in the Contract Document. Therefore, under Clause 11.6(e), the price of wash trough should be omitted in the Contract Document. While under Clause 11.6(a) for items with a similar character and conditions, the price of water jet washing should be added into the Contract Document.
  • 14. Clause 11.6(d) is a valuation of Variations where the work cannot be properly measured and valued by using daywork rates or actual cost plus 15%. This method is only using when meets certain per-condition when the work cannot be properly measured and valued. The quantity of cleaning water cannot be properly measured and contractor cannot get the compensate for actual costs incurred. Next, day work rate is mentioned in the contract which is used for labour, plant and materials. Site staff must record and verified the daywork and send it to the architect and also the consultants. (d) Mistake was made in the price for excavation through rocks at RM50 per m3. Item was not rationalised during contract documentation. However, original quantity in BQ is 100 m3 but re-measured as-built quantity was 20,000 m3. The Contractor submitted a claim for revised rates of RM 150 per m3 for the total quantity of 20,000 m3. (10 marks) According to PAM Contract 2006 (With Quantities) Clause 11.6 stated 6 rules to be applied under different situation of Variations. It is use to satisfy the terms of Variation and Architect’s Instructions under Clause 11.1. In this clause, it defines variation as the alteration or modification of the design, quality or quantity of the Works. But, Architect should be mindful not to instruct variation beyond the contractual ambit, as such act could be regarded as “ultra vires” and could expose the Architect directly liable under tort. Reversely, if such instruction calls for variation to the contractual provision, the contractor cannot look for the Employer for compensation. Under clause 11.6(b), where work is of similar character to work as set out in the Contract Documents but is not executed under similar conditions or is executed under similar conditions but there is a significant change in the quantity of work carried out, the rates and prices in the Contract Documents shall be the basis for determining the valuation which shall include a fair adjustment in the rates to take into account such difference by Quantity Surveyor. In the situation provided in the question above, there is a significant change of quantity with similar character of work from the original quantity of 100 m3 to 20,000 m3 in the contract BQ for the excavation through rocks. In this case, Quantity Surveyor has to make a fair adjustment for the differences of varied work (PAM Contract with Quantities under Clause 11.6b). The submitted rate for the works by Contractor might be base on the work done in the contract, but when there are huge varied work, the rate and price will be revise accordingly. In this case, Quantity Surveyor should take the original contract rates and price as stated in the contract to create a reference of the new adjustment.