SlideShare uma empresa Scribd logo
1 de 19
5
5.1 MATERIAL BALNCE
MATERIAL BALNCE ON STEEPING TANK
1.1
5. MATERIAL AND ENERGY BALNCE
6. Energy balance on dryer
• Solid matter in Dry starch and wet starch = 2441 kg/day
• Initial air condition = T= 20o
C (h0=30kJ/kg), and 50% RH, H1 =0.0074 kg of water/ kg dry air
• Product temperature when it leaves drier =450
c
• Heated air entering in to the drier = 400
C at 25% RH, enthalpy of in let air (ha1)
ha1=71Kj/kg dry air, where RH= relative humidity
• Enthalpy required to heat the air = ha1 – h0 = 71-30 = 41kJ/kg
• Air temperature leaving the drier = 35 0
C
• Latent heat of vaporization at 0 0
C = 2507KJ/kg
• Specific heat of air (Cp,a) = 0.24 + 0.46 (H)
• Specific heat of solid matter of the product (Cp,e) =2.32 kJ/kg0
c
• Specific heat of water (Cw) = 4.2 kJ/kg0
C
• Energy estimated to be released in order to dry the starch.
• Feed temperature = 250
C
• H1& H2 is absolute humidity of air
• A = is flow rate of air
• Enthalpy of Feed = hwe
• Enthalpy of product = hde
• Enthalpy of inlet air = ha1
• Enthalpy of out let air = ha2
A(H2-H1)= 2441-1666 = 775 kg /day ........................................1
mwet starch(hwe) + A (ha1) = mdry starch (hde) + A (ha2) ---------------------------- [2]
1.hwe = Cpstarch* ΔT + W1 .CpH2O. ΔT
hwe = 1.75 kJ/kg0
C (250
c) + 0.25(4.2)( 250
c)
hwe=70 kJ/kg
2. hde = CpstarchΔT + Ws2*CpH2O * ΔT
hde = 1.75 kJ/kg (45) + 0.052(4.2)(45)
hde = 88.75 kJ/kg
3. ha2 = Cs ΔT + λ H2
ha2 = (0.24 +0.46H2) (35) + 2507.4H2
ha2 = 8.4 +2523.5H2---------------------------------------------- [3]
Inserting eq. 3 in eq.2
2441(70) + A (71.0) = 1666(88.75) + A (8.4 +2523.5H2)
170,870+A (71.0) =147,857+ 2523.5AH2----------------------- [4]
Taking Eq. [1] and inserting it in eq. [4]
from Eq. [1]
AH2=775+AH1=775+A( 0.012 Kg/ kg dry air)
then Eq. [4]
170870+A (71.0) =147,857+ 2523.5(775+A( 0.012 ))
170870+A (71.0) =147,857+1,302,050.3+A(30.2)
A=3,1196 kg/day
Inserting A in eq.1
A (H2 - H1) =775 kg/day
H2=(775 +31196 *0.012) /31196
H2=0.0368 Kg/ kg dry air
Inserting H2 in eqution3.
ha2 = 8.4 + 2523.5 (0.0368kg/kg dry air)
ha2 = 101.37kJ/Kg
Table 6.1: Specification Equipments
Equipments quantity type capacity Power needed
for driving
Centrifuge Separator 1 Vertical Cylinder 0.186m3
/hr 65kw/hr
Dryer 2 Flash pan type 4.04m2
125kwhr
Heat Exchanger 3 Plate type 0.5m2
75kw/hr
Pump 3 centrifuge 0.396m3
/hr 1.5kwhr
Air filter 1 Vertical Basket 10m3
/hr 50kw/hr
Belt conveyer 1 horizontal 3m 15kw/hr
Packing machine 1 general 25packets/min 95kw/hr
Total 426.5kw/hr
Source; Coulson and Sinnot volume-6 and www.machte.com
The total annual total energy consumption to drive each equipment’s, assuming the will be 300
working days.
=426.5kw/hr *24hr *300
=3,070800kw/year
Also by approximation for lighting and other related services around 20,000kw per year
consumed. Therefore the total electric energy consumed is the sum total energy needed for
equipments and for lighting.
=3,070800kw +20,000kw
= 3090800kw/year
Process flow diagram
7. ECONOMIC EVALUATION OF THE PROJECT
7.1 PLANT CAPACITY AND PROPOSED LOCATION
Based on the market study, the envisaged plant is proposed to have annual production capacity of
500 tones. The plant will operate in a single shift of 8 hours a day, and for 300 days a year.
CORN STARCH is mainly consumed by the Pharmaceutical industry, food industry , textile
industry….. The location for the plant is a compromise between the availability of major raw
material corn/ maize and market for the finished product starch and modified starch. The
availability of the basic infrastructure like electricity, water, and road which are vital for the
smooth operation of the plant.
7.2. Estimation of equipment costs
Assuming new equipment is similar to a base item where cost data is available, Equation below
explains the equipment cost estimation process, where EPC is Equipment Purchased Cost, Q and
QO are the new and base equipment capacities, respectively, and a is the exponent of the power
law function given by the user. By default, this exponent is set as 0.6 for estimating new
equipment cost (Whiteside, 2007 and Harriso, 2003).The cost of major equipment was evaluated
based on cost data on 1997, 2000 and 2004 and bring back to equivalent cost to 2014 applying
cost index techniques.
EPC = Co (Q/Qo) a
Where, EPC= Cost of purchased equipment
Co= cost of base line equipment
Q= capacity purchased equipment
Qo= capacity baseline equipment
Calculating using above equation the equipment’s costs as summarized in table 7.1
Table 7.1: Specification and costs of the major equipment’s
No Name Size Unit Unit cost
($)
Total ($)
1 Raw material
storage
77(m3
) 1 2000 40000
2 Steeping tank 9.3(m3
) 3 1500 90000
3 De germination 6 (m3
) 1 3500 70000
4 Grinding 2ft? 1 1200 24000
5 Centrifuge 2m(diameter) 1 1200 24000
6 Separation unit 2m(diameter) 1 500 10000
7 Dryer 4tf2
2 3500 140000
8 Modification
tank
1.5(m3
) 2 2500 100000
9 Storage tank 10.5(m3
) 1 1000 20000
Tota
l
710,000 ETB
Source; A=coulsen and Sinnot volume-6, B= www.machte.com and www.alibaba.com,
C=Whitesides, W., 2007,D= Plant design and Economics, fourth edition
Estimation of total capital investment Cost
SINCE WE KNOW THE COSTS OF PURCHASED EQUIPMENT:
PEC = 25% OF FCI(FIXED CAPITAL INVESTMENT)
SO WE CAN CALCULATE THE FCI AND IT WILL BE
710,000 ETB /0.25 = 2,840,000 ETB
Items Cost (ETB)
Purchased Equipment costs (FCI) 710,000
Installation 9%FCI 255,600
Processing piping 8%FCI 227,200
Instrumentation7% FCI 198,800
Electrical 10% FCI 284,000
Buildings 6% FCI 170,400
Yard improvements 3% FCI 85,200
Auxiliary Facility 25%FCI 710,000
Total Direct Costs (DC) 2,641,200
Total Indirect Costs (IC):
Engineering 8% FCI 227,200
Construction 10% FCI 284,000
Total Indirect costs (IC) 511,200
Other Costs (OC)
Contractor’s Fee 3% FCI 85,200
Contingency 5% FCI 142,000
Total other costs (OC) 227,200
Fixed Capital Investment (FCI) Costs 2,868,400 ETB
Working capital (25%FC) 573,680
Total capital investment (TCI) 3,442,080
Estimation of total production or operation cost (TPC)
The production cost divide into manufacturing costs and general expenses cost. Total production
cost is the sum manufacturing and general expenses.
1.1.1. MANUFACTURING COSTS (MC)
MC =Direct Manufacturing Costs (DMC) +Fixed Manufacturing Costs (FMC) + Plant over
head cost (POC)
i. Direct manufacturing cost (DMC)
Direct production costs are calculated and equal the sum of the following items as specified
within the processes: Raw materials, operating Labor, direct supervisor and clerical labor,
Laboratory, Utilities and operating supplies.
Raw materials (CRM): two different major raw materials are used in the corn starch production
process in this project for economic purposes: corn/maize and water. Itemized raw material costs
are summarized and listed in Table 7.2
Table 7.2: Raw materials
Raw materials unit cost (ETB/kg) Annual amount (kg/year) Annual cost (ETB/year)
Corn /maize 5 819,600Kg/year 4,098,000
Water(m3
) 0.86 ETB 1,393.2 (m3
) 1200
Total 4,099,200
Source: material balance on steeping section 5.1
Utilities (CUT): three different utilities are examined in the CORN STARCH production process
in this project for economic purposes: electricity, Lubricating oil and cooling water. Itemized
utility costs are summarized and listed in Table 7.3.
Table 7.3 Utility costs for sodium bicarbonate production
Utility unit cost (ETB/unit) Annual amount Annual cost(ETB)
Electricity (Kw/year) .45 3090800 1390860
Lubricating oil (lt.) 6.2 4838.75 30,000
water (m3
) 4.3 *10-3
2786400kg/year 240
Total 1421100 ETB
Sources: materials and energy balance calculation section 5.1and 5.2
Operating Labor (COL)
The plant requires 35 workers, and their annual expenditure, including fringe benefits, is
estimated at Birr 336,960 ETB. For details see Table 7.4 below.
Table 7.4 Manpower requirement and annual labor cost
Sr.
No.
Description Req.
No.
Salary, (Birr)
Monthly Annual
1 Plant manager 1 4,500 54,000
2 Secretary 1 1000 12,000
3 Accountant 1 1200 14,400
4 Production head 1 1,800 21,600
5 Operator 6 6,000 72,000
6 Assistant
operators
3 3,600 43,200
7 Mechanic 1 1,200 14,400
8 Electrician 1 1200 14,400
9 Store keeper 1 500 6,000
10 Purchaser 1 1000 12,000
11 Sales man 1 1000 12,000
12 Personnel 1 900 10,800
13 Time keeper 1 400 4,800
15 Driver 2 700 16800
17 Guard 2 500 6,000
18 Cleaner 1 400 4,800
Sub-total 25 22,300 280,800
Employee benefit
(10% BS)
2808
Total 336,960 ETB
Direct supervisor and clerical labor (CSC); the cost of supervisor and clerical labor is estimated
CSC = aSCCOL ( aSC = 0.18)
=18% of operating labor (COL)
= 0.18 *336,960= 60,653
Maintenance and repairs (CMR)
CMR = aMRFCI (aMR = 0.06)
= 0.06 * fixed capital investment (FCI)
=0.06*2,868,400
= 172,104
Laboratory charges (CLC)
CLC = aLCCOL (aLC = 0.15)
=15% of operating labor (COL)
=0.15*336,960
=50,544
Patents/royalties, CPR= aPRTPC (aLC = 0.03)
= 0.03TPC
Direct production cost (DMC)
DMC=CRM + CUT + 1.33 COL+ 0.03 TPC + 0.069 FCI
= 4,917,720+578,080 +1.33*336,960 +0.069*$2,868,400 +0.03TPC
=6,141875 +0.03TPC
ii. Fixed Manufacturing Costs (FMC).
This costs the sum of depreciation, insurance and taxes
The depreciation (DEP) item is calculated using a straight-line depreciation method,
considering a salvage value fraction (f) of the fixed capital investment (FCI), which is assumed
10 % in this analysis by default. The depreciation period (n) is set to ten years by default.
Equation 6.4 is used to calculate depreciation:
DEP=
= ………………2,868,400*(1-
0.1)/10
258,156
FMC = CTI + CDEP = 0.32 FCI +CDEP
= 0.32*2,868,400 +258,156
=1,176,044
7.4.2 GENERAL EXPENSES (GE)
GE = Administrative Cost (AC) +Other Costs (OC)
Administrative (AC) expenses include costs for executive and clerical wages, office supplies,
engineering and legal expenses, upkeep on office buildings, and general communications.
Other costs (OC); includes distribution, selling, research and development costs
GE=Administrative Cost (AC) +Other Costs (OC) =50 %( operating labor + supervision +
Maintenance)
Administration costs (CAD)
CAD = aAD (COL +CSC + CMR); (aAD = 0.15)
CAD = aAD (COL + 0.18COL + 0.06 FCI) = 0.177 COL + 0.009 FCI
Distribution and sales costs (CDS)
CDS = aDS TPC =0.11 TPC ; (aDS = 0.11)
R&D (CRD)
CRD = aRD TPC = 0.05 TPC ; (aRD = 0.05)
Financing costs=0.04 FCI
GE =CAD +CDS +CRD +CF
GE = 0.177 COL + 0.009 FCI + 0.11TPC + 0.05TPC + 0.04 FCI
GE = 0.177 COL + 0.049 FCI + 0.16TPC
= 0.177*336,960 +0.049*2,868,400+0.16TPC
=200,194 +0.16TPC
TPC = MC + GE = (DMC+ FMC ) + (AC +OC)
TPC = CRM+CUT +1.33 COL+ 0.03 TPC+ 0.069 FCI + 0.032 FCI +CDEP +0. 708 COL + 0.032
FCI + 0.177 COL + 0.009FCI + 0.16 TPC
TPC = 1.24(CRM+CUT +CDEP) + 2.74 COL + 0.23 FCI
= 1.24*(4,917,720+578,080 +258,156) +2.74*336,960 + 0.23*2,868,400
=$1,369,503.8……(6,717,908 ETB)
Therefore;
DMC=6,141875 +0.03TPC
=6,141875 + 0.03 *6,717,908
= 6,343,412
GE=200,194 +0.16TPC
=200,194 +0.03*6,717,908
= 401,731
Unit Cost Analysis
The unit costs for corn starch production are calculated as the quotient of the annual operating
cost divided by the annual production rate.
Unit cost (ETB/kg) =
= = 6,717,908 /500,000 /
=13.5 ETB/kg
Corn starch selling Price
In order to conduct the profitability analysis, the selling price for corn starch must be first
identified. From local?26? market of the current corn starch price is 15?? per kilogram and
international selling price is $0.76 per kilogram of corn starch. So the unit corn starch price per
kilogram is calculated and equals ETB13.5/kg. For profitability let it will sell with current local
market value.
Profitability Analysis
According to the projected income statement, the project will start generating profit in the first
year of operation. Important ratios such as profit to total sales, net profit to equity (Return on
equity) and net profit plus interest on total investment (return on total investment) show an
increasing trend during the life-time of the project. To calculate the gross profit let we calculate
the sales value per annual.
i. Sales (Sales Revenue)
Sales= unit cost * annual capacity
=13.3??$/kg*500,000kg/year
6750000 ETB /year if 14
7,000,000 ETB
ii. Gross profit (GP)
Gross profit (GP) = Sales – TPC
=7,000,000-$8,717,908
=880,496.2 32,092 = 282092
iii. Netprofit (NP)
Net profit=Gp-[sales –TPC]*tax rate
=Gp-Gp*0.35
=Gp [1-0.35]
= 282092*0.65
=183,360 ETB
iv. Turn over Ratio
Turnover ratio is defined as the ratio of gross annual sales to the fixed-capital investment where
the product of the annual production rate and the average selling price of the commodities are the
gross annual sales figures. The reciprocal of the turnover ratio is sometimes defined as the
capital ratio or the investment ratio. Turnover ratios of up to 5 are common for some business
establishments and some are as low as 0.2. For the chemical industry, as a very rough rule of
thumb, the ratio can be approximated as 1.
Turnover=
7,000,000 /2,868,400
=
= 2.444
So, our project acceptable to establishment since turn ratio between the maximum and minimum
range [0.2-5]
7.61 PAYBACK PERIOD
The payback period is a simple indicator measuring how long it takes to recover the initial
investment in the corn starch production plants. When choosing among a few mutually exclusive
projects, the project with the quickest payback is preferred. The payback period is calculated as
the quotient of the total capital investment divided by the net profit as shown in equation below.
Payback period =
8,717,908/183,360 = 36?????
=
=3.6years
1.1.1. CASH FLOW
Table 7.5: cash flow of sodium bicarbonate Production
Year Fixed
capital
Working
capital
sales Total
operating
cost
Gross
profit
Depreciation Taxes N
-2 -1,661,404 0 0 0 0 0 0 0
-1 - 1,661,404 0 0 0 0 0 0 0
0 0 -415,351 0 0 0 0 0 0
1 0 0 2,250,000 1,369,503.8 880,496.2 149,526.4 308,173.7 5
2 0 0 2,250,000 1,369,503.8 880,496.2 149,526.4 308,173.7 5
3 0 0 2,250,000 1,369,503.8 880,496.2 149,526.4 308,173.7 5
4 0 0 2,250,000 1,369,503.8 880,496.2 149,526.4 308,173.7 5
5 0 0 2,250,000 1,369,503.8 880,496.2 149,526.4 308,173.7 5
6 0 0 2,250,000 1,369,503.8 880,496.2 149,526.4 308,173.7 5
7 0 0 2,250,000 1,369,503.8 880,496.2 149,526.4 308,173.7 5
8 0 0 2,250,000 1,369,503.8 880,496.2 149,526.4 308,173.7 5
9 0 0 2,250,000 1,369,503.81 880,496.2 149,526.4 308,173.7 5
10 0 0 2,250,000 1,369,503.8 880,496.2 149,526.4 308,173.7 5
Source: “Economic evaluation report” and “Cash flow analysis report” from Plant design and
Economics for chemical engineers, Fourth edition and Sinnott, 1993 and sodium bicarbonate
production data.
7.62BREAKEVEN POINT ANALYSIS (BEP)
Breakeven point is the point when total annual production cost equals total annual sales. That is
the point where profit equals zero. The breakeven point is determined from the relation:
BEP =
Where Sup=Selling price per unit of production
Vcup = Variable costs per unit of production
vcup=
=
=2.71$/kg
BEP =
=
=116,297kg/year
BEP(%) = *100%
= 38.7%

Mais conteúdo relacionado

Mais procurados (20)

Sedimentation
SedimentationSedimentation
Sedimentation
 
Evaporator performance
Evaporator performanceEvaporator performance
Evaporator performance
 
Fluidization
FluidizationFluidization
Fluidization
 
Rotary dryer
Rotary dryerRotary dryer
Rotary dryer
 
01 kern's method.
01 kern's method.01 kern's method.
01 kern's method.
 
Liquid-Liquid Extraction
Liquid-Liquid Extraction Liquid-Liquid Extraction
Liquid-Liquid Extraction
 
Liquid mixing
Liquid mixingLiquid mixing
Liquid mixing
 
Drying rate
Drying rateDrying rate
Drying rate
 
Supercritical Fluid extraction
Supercritical Fluid extraction Supercritical Fluid extraction
Supercritical Fluid extraction
 
Supercritical fluid extraction
Supercritical fluid extractionSupercritical fluid extraction
Supercritical fluid extraction
 
Recycling and bypassing operation
Recycling and bypassing operationRecycling and bypassing operation
Recycling and bypassing operation
 
[W f stoecker]_refrigeration_and_a_ir_conditioning_(book_zz.org)
[W f stoecker]_refrigeration_and_a_ir_conditioning_(book_zz.org)[W f stoecker]_refrigeration_and_a_ir_conditioning_(book_zz.org)
[W f stoecker]_refrigeration_and_a_ir_conditioning_(book_zz.org)
 
Discussion for microbial growth
Discussion for microbial growthDiscussion for microbial growth
Discussion for microbial growth
 
Evaporation
EvaporationEvaporation
Evaporation
 
mel709-23.ppt
mel709-23.pptmel709-23.ppt
mel709-23.ppt
 
Full report gas absorption
Full report gas  absorptionFull report gas  absorption
Full report gas absorption
 
Aeration unit Lab Report(Separation Lab)
Aeration unit Lab Report(Separation Lab)Aeration unit Lab Report(Separation Lab)
Aeration unit Lab Report(Separation Lab)
 
Plate and Frame Filter Press Lab 1 Report
Plate and Frame Filter Press Lab 1 ReportPlate and Frame Filter Press Lab 1 Report
Plate and Frame Filter Press Lab 1 Report
 
Design 1
Design 1Design 1
Design 1
 
Distillation
DistillationDistillation
Distillation
 

Semelhante a Energy+balance++by+tes

Manufacturing cost estimation
Manufacturing cost estimationManufacturing cost estimation
Manufacturing cost estimationvineethgoud6
 
Boiler Efficiency Improvement through Analysis of Losses
Boiler Efficiency Improvement through Analysis of LossesBoiler Efficiency Improvement through Analysis of Losses
Boiler Efficiency Improvement through Analysis of Lossesijsrd.com
 
2016.12.14 DryFining Coal Gen presentation FINAL
2016.12.14 DryFining Coal Gen presentation FINAL2016.12.14 DryFining Coal Gen presentation FINAL
2016.12.14 DryFining Coal Gen presentation FINALSandra Broekema
 
A109211401 thermalscience1
A109211401 thermalscience1A109211401 thermalscience1
A109211401 thermalscience1jntuworld
 
Dimethyl Ether Production
Dimethyl Ether ProductionDimethyl Ether Production
Dimethyl Ether ProductionAziz Albattah
 
Costing assignment.docx
Costing assignment.docxCosting assignment.docx
Costing assignment.docxssuserdcbf4e
 
Airah Natural Refrigerants Special Interest Group Sydney 30 October 2008
Airah Natural Refrigerants Special Interest Group Sydney 30 October 2008Airah Natural Refrigerants Special Interest Group Sydney 30 October 2008
Airah Natural Refrigerants Special Interest Group Sydney 30 October 2008rhysemo
 
Airah Natural Refrigerants Special Interest Group Sydney 30 October 2008
Airah Natural Refrigerants Special Interest Group Sydney 30 October 2008Airah Natural Refrigerants Special Interest Group Sydney 30 October 2008
Airah Natural Refrigerants Special Interest Group Sydney 30 October 2008rhysemo
 
New ton presentation_c
New ton  presentation_cNew ton  presentation_c
New ton presentation_cEUROPAGES
 
Me2202 engineering thermodynamics uq - may june 2014
Me2202 engineering thermodynamics   uq - may june 2014Me2202 engineering thermodynamics   uq - may june 2014
Me2202 engineering thermodynamics uq - may june 2014BIBIN CHIDAMBARANATHAN
 
Design and Simulation of Divided Wall Column - Design of the Column
Design and Simulation of Divided Wall Column - Design of the ColumnDesign and Simulation of Divided Wall Column - Design of the Column
Design and Simulation of Divided Wall Column - Design of the ColumnHariKirant29
 

Semelhante a Energy+balance++by+tes (20)

Manufacturing cost estimation
Manufacturing cost estimationManufacturing cost estimation
Manufacturing cost estimation
 
CBE480ProjectReport
CBE480ProjectReportCBE480ProjectReport
CBE480ProjectReport
 
Cost of production
Cost of productionCost of production
Cost of production
 
Boiler Efficiency Improvement through Analysis of Losses
Boiler Efficiency Improvement through Analysis of LossesBoiler Efficiency Improvement through Analysis of Losses
Boiler Efficiency Improvement through Analysis of Losses
 
2016.12.14 DryFining Coal Gen presentation FINAL
2016.12.14 DryFining Coal Gen presentation FINAL2016.12.14 DryFining Coal Gen presentation FINAL
2016.12.14 DryFining Coal Gen presentation FINAL
 
EXERGOECONOMIC ANALYSIS
EXERGOECONOMIC ANALYSISEXERGOECONOMIC ANALYSIS
EXERGOECONOMIC ANALYSIS
 
DG
DGDG
DG
 
A109211401 thermalscience1
A109211401 thermalscience1A109211401 thermalscience1
A109211401 thermalscience1
 
Gross turbine cycle_heat_rate_ch-8.2
Gross turbine cycle_heat_rate_ch-8.2Gross turbine cycle_heat_rate_ch-8.2
Gross turbine cycle_heat_rate_ch-8.2
 
Chapter no 8 EOQ
Chapter no 8 EOQChapter no 8 EOQ
Chapter no 8 EOQ
 
Dimethyl Ether Production
Dimethyl Ether ProductionDimethyl Ether Production
Dimethyl Ether Production
 
S.e 2003
S.e 2003S.e 2003
S.e 2003
 
Costing assignment.docx
Costing assignment.docxCosting assignment.docx
Costing assignment.docx
 
Topic 11
Topic 11Topic 11
Topic 11
 
Airah Natural Refrigerants Special Interest Group Sydney 30 October 2008
Airah Natural Refrigerants Special Interest Group Sydney 30 October 2008Airah Natural Refrigerants Special Interest Group Sydney 30 October 2008
Airah Natural Refrigerants Special Interest Group Sydney 30 October 2008
 
Airah Natural Refrigerants Special Interest Group Sydney 30 October 2008
Airah Natural Refrigerants Special Interest Group Sydney 30 October 2008Airah Natural Refrigerants Special Interest Group Sydney 30 October 2008
Airah Natural Refrigerants Special Interest Group Sydney 30 October 2008
 
New ton presentation_c
New ton  presentation_cNew ton  presentation_c
New ton presentation_c
 
Me2202 engineering thermodynamics uq - may june 2014
Me2202 engineering thermodynamics   uq - may june 2014Me2202 engineering thermodynamics   uq - may june 2014
Me2202 engineering thermodynamics uq - may june 2014
 
Design and Simulation of Divided Wall Column - Design of the Column
Design and Simulation of Divided Wall Column - Design of the ColumnDesign and Simulation of Divided Wall Column - Design of the Column
Design and Simulation of Divided Wall Column - Design of the Column
 
Idp presentation
Idp presentationIdp presentation
Idp presentation
 

Energy+balance++by+tes

  • 1. 5 5.1 MATERIAL BALNCE MATERIAL BALNCE ON STEEPING TANK 1.1 5. MATERIAL AND ENERGY BALNCE
  • 2. 6. Energy balance on dryer • Solid matter in Dry starch and wet starch = 2441 kg/day • Initial air condition = T= 20o C (h0=30kJ/kg), and 50% RH, H1 =0.0074 kg of water/ kg dry air • Product temperature when it leaves drier =450 c • Heated air entering in to the drier = 400 C at 25% RH, enthalpy of in let air (ha1) ha1=71Kj/kg dry air, where RH= relative humidity • Enthalpy required to heat the air = ha1 – h0 = 71-30 = 41kJ/kg • Air temperature leaving the drier = 35 0 C • Latent heat of vaporization at 0 0 C = 2507KJ/kg • Specific heat of air (Cp,a) = 0.24 + 0.46 (H) • Specific heat of solid matter of the product (Cp,e) =2.32 kJ/kg0 c • Specific heat of water (Cw) = 4.2 kJ/kg0 C • Energy estimated to be released in order to dry the starch. • Feed temperature = 250 C • H1& H2 is absolute humidity of air • A = is flow rate of air • Enthalpy of Feed = hwe • Enthalpy of product = hde • Enthalpy of inlet air = ha1 • Enthalpy of out let air = ha2 A(H2-H1)= 2441-1666 = 775 kg /day ........................................1 mwet starch(hwe) + A (ha1) = mdry starch (hde) + A (ha2) ---------------------------- [2] 1.hwe = Cpstarch* ΔT + W1 .CpH2O. ΔT hwe = 1.75 kJ/kg0 C (250 c) + 0.25(4.2)( 250 c) hwe=70 kJ/kg
  • 3. 2. hde = CpstarchΔT + Ws2*CpH2O * ΔT hde = 1.75 kJ/kg (45) + 0.052(4.2)(45) hde = 88.75 kJ/kg 3. ha2 = Cs ΔT + λ H2 ha2 = (0.24 +0.46H2) (35) + 2507.4H2 ha2 = 8.4 +2523.5H2---------------------------------------------- [3] Inserting eq. 3 in eq.2 2441(70) + A (71.0) = 1666(88.75) + A (8.4 +2523.5H2) 170,870+A (71.0) =147,857+ 2523.5AH2----------------------- [4] Taking Eq. [1] and inserting it in eq. [4] from Eq. [1] AH2=775+AH1=775+A( 0.012 Kg/ kg dry air) then Eq. [4] 170870+A (71.0) =147,857+ 2523.5(775+A( 0.012 )) 170870+A (71.0) =147,857+1,302,050.3+A(30.2) A=3,1196 kg/day Inserting A in eq.1 A (H2 - H1) =775 kg/day H2=(775 +31196 *0.012) /31196 H2=0.0368 Kg/ kg dry air Inserting H2 in eqution3. ha2 = 8.4 + 2523.5 (0.0368kg/kg dry air) ha2 = 101.37kJ/Kg
  • 4. Table 6.1: Specification Equipments Equipments quantity type capacity Power needed for driving Centrifuge Separator 1 Vertical Cylinder 0.186m3 /hr 65kw/hr Dryer 2 Flash pan type 4.04m2 125kwhr Heat Exchanger 3 Plate type 0.5m2 75kw/hr Pump 3 centrifuge 0.396m3 /hr 1.5kwhr Air filter 1 Vertical Basket 10m3 /hr 50kw/hr Belt conveyer 1 horizontal 3m 15kw/hr Packing machine 1 general 25packets/min 95kw/hr Total 426.5kw/hr Source; Coulson and Sinnot volume-6 and www.machte.com
  • 5. The total annual total energy consumption to drive each equipment’s, assuming the will be 300 working days. =426.5kw/hr *24hr *300 =3,070800kw/year Also by approximation for lighting and other related services around 20,000kw per year consumed. Therefore the total electric energy consumed is the sum total energy needed for equipments and for lighting. =3,070800kw +20,000kw = 3090800kw/year Process flow diagram
  • 6. 7. ECONOMIC EVALUATION OF THE PROJECT 7.1 PLANT CAPACITY AND PROPOSED LOCATION Based on the market study, the envisaged plant is proposed to have annual production capacity of 500 tones. The plant will operate in a single shift of 8 hours a day, and for 300 days a year. CORN STARCH is mainly consumed by the Pharmaceutical industry, food industry , textile industry….. The location for the plant is a compromise between the availability of major raw material corn/ maize and market for the finished product starch and modified starch. The availability of the basic infrastructure like electricity, water, and road which are vital for the smooth operation of the plant. 7.2. Estimation of equipment costs Assuming new equipment is similar to a base item where cost data is available, Equation below explains the equipment cost estimation process, where EPC is Equipment Purchased Cost, Q and QO are the new and base equipment capacities, respectively, and a is the exponent of the power law function given by the user. By default, this exponent is set as 0.6 for estimating new equipment cost (Whiteside, 2007 and Harriso, 2003).The cost of major equipment was evaluated based on cost data on 1997, 2000 and 2004 and bring back to equivalent cost to 2014 applying cost index techniques. EPC = Co (Q/Qo) a Where, EPC= Cost of purchased equipment Co= cost of base line equipment Q= capacity purchased equipment Qo= capacity baseline equipment Calculating using above equation the equipment’s costs as summarized in table 7.1 Table 7.1: Specification and costs of the major equipment’s
  • 7. No Name Size Unit Unit cost ($) Total ($) 1 Raw material storage 77(m3 ) 1 2000 40000 2 Steeping tank 9.3(m3 ) 3 1500 90000 3 De germination 6 (m3 ) 1 3500 70000 4 Grinding 2ft? 1 1200 24000 5 Centrifuge 2m(diameter) 1 1200 24000 6 Separation unit 2m(diameter) 1 500 10000 7 Dryer 4tf2 2 3500 140000 8 Modification tank 1.5(m3 ) 2 2500 100000 9 Storage tank 10.5(m3 ) 1 1000 20000 Tota l 710,000 ETB Source; A=coulsen and Sinnot volume-6, B= www.machte.com and www.alibaba.com, C=Whitesides, W., 2007,D= Plant design and Economics, fourth edition Estimation of total capital investment Cost SINCE WE KNOW THE COSTS OF PURCHASED EQUIPMENT: PEC = 25% OF FCI(FIXED CAPITAL INVESTMENT) SO WE CAN CALCULATE THE FCI AND IT WILL BE 710,000 ETB /0.25 = 2,840,000 ETB Items Cost (ETB) Purchased Equipment costs (FCI) 710,000 Installation 9%FCI 255,600 Processing piping 8%FCI 227,200 Instrumentation7% FCI 198,800 Electrical 10% FCI 284,000 Buildings 6% FCI 170,400
  • 8. Yard improvements 3% FCI 85,200 Auxiliary Facility 25%FCI 710,000 Total Direct Costs (DC) 2,641,200 Total Indirect Costs (IC): Engineering 8% FCI 227,200 Construction 10% FCI 284,000 Total Indirect costs (IC) 511,200 Other Costs (OC) Contractor’s Fee 3% FCI 85,200 Contingency 5% FCI 142,000 Total other costs (OC) 227,200 Fixed Capital Investment (FCI) Costs 2,868,400 ETB Working capital (25%FC) 573,680 Total capital investment (TCI) 3,442,080 Estimation of total production or operation cost (TPC) The production cost divide into manufacturing costs and general expenses cost. Total production cost is the sum manufacturing and general expenses. 1.1.1. MANUFACTURING COSTS (MC) MC =Direct Manufacturing Costs (DMC) +Fixed Manufacturing Costs (FMC) + Plant over head cost (POC) i. Direct manufacturing cost (DMC) Direct production costs are calculated and equal the sum of the following items as specified within the processes: Raw materials, operating Labor, direct supervisor and clerical labor, Laboratory, Utilities and operating supplies.
  • 9. Raw materials (CRM): two different major raw materials are used in the corn starch production process in this project for economic purposes: corn/maize and water. Itemized raw material costs are summarized and listed in Table 7.2 Table 7.2: Raw materials Raw materials unit cost (ETB/kg) Annual amount (kg/year) Annual cost (ETB/year) Corn /maize 5 819,600Kg/year 4,098,000 Water(m3 ) 0.86 ETB 1,393.2 (m3 ) 1200 Total 4,099,200 Source: material balance on steeping section 5.1 Utilities (CUT): three different utilities are examined in the CORN STARCH production process in this project for economic purposes: electricity, Lubricating oil and cooling water. Itemized utility costs are summarized and listed in Table 7.3.
  • 10. Table 7.3 Utility costs for sodium bicarbonate production Utility unit cost (ETB/unit) Annual amount Annual cost(ETB) Electricity (Kw/year) .45 3090800 1390860 Lubricating oil (lt.) 6.2 4838.75 30,000 water (m3 ) 4.3 *10-3 2786400kg/year 240 Total 1421100 ETB Sources: materials and energy balance calculation section 5.1and 5.2 Operating Labor (COL) The plant requires 35 workers, and their annual expenditure, including fringe benefits, is estimated at Birr 336,960 ETB. For details see Table 7.4 below. Table 7.4 Manpower requirement and annual labor cost Sr. No. Description Req. No. Salary, (Birr) Monthly Annual 1 Plant manager 1 4,500 54,000 2 Secretary 1 1000 12,000 3 Accountant 1 1200 14,400 4 Production head 1 1,800 21,600 5 Operator 6 6,000 72,000 6 Assistant operators 3 3,600 43,200 7 Mechanic 1 1,200 14,400 8 Electrician 1 1200 14,400 9 Store keeper 1 500 6,000 10 Purchaser 1 1000 12,000 11 Sales man 1 1000 12,000 12 Personnel 1 900 10,800 13 Time keeper 1 400 4,800 15 Driver 2 700 16800
  • 11. 17 Guard 2 500 6,000 18 Cleaner 1 400 4,800 Sub-total 25 22,300 280,800 Employee benefit (10% BS) 2808 Total 336,960 ETB Direct supervisor and clerical labor (CSC); the cost of supervisor and clerical labor is estimated CSC = aSCCOL ( aSC = 0.18) =18% of operating labor (COL) = 0.18 *336,960= 60,653 Maintenance and repairs (CMR) CMR = aMRFCI (aMR = 0.06) = 0.06 * fixed capital investment (FCI) =0.06*2,868,400 = 172,104 Laboratory charges (CLC) CLC = aLCCOL (aLC = 0.15) =15% of operating labor (COL) =0.15*336,960 =50,544 Patents/royalties, CPR= aPRTPC (aLC = 0.03) = 0.03TPC Direct production cost (DMC) DMC=CRM + CUT + 1.33 COL+ 0.03 TPC + 0.069 FCI = 4,917,720+578,080 +1.33*336,960 +0.069*$2,868,400 +0.03TPC =6,141875 +0.03TPC
  • 12. ii. Fixed Manufacturing Costs (FMC). This costs the sum of depreciation, insurance and taxes The depreciation (DEP) item is calculated using a straight-line depreciation method, considering a salvage value fraction (f) of the fixed capital investment (FCI), which is assumed 10 % in this analysis by default. The depreciation period (n) is set to ten years by default. Equation 6.4 is used to calculate depreciation: DEP= = ………………2,868,400*(1- 0.1)/10 258,156 FMC = CTI + CDEP = 0.32 FCI +CDEP = 0.32*2,868,400 +258,156
  • 13. =1,176,044 7.4.2 GENERAL EXPENSES (GE) GE = Administrative Cost (AC) +Other Costs (OC) Administrative (AC) expenses include costs for executive and clerical wages, office supplies, engineering and legal expenses, upkeep on office buildings, and general communications. Other costs (OC); includes distribution, selling, research and development costs GE=Administrative Cost (AC) +Other Costs (OC) =50 %( operating labor + supervision + Maintenance) Administration costs (CAD) CAD = aAD (COL +CSC + CMR); (aAD = 0.15) CAD = aAD (COL + 0.18COL + 0.06 FCI) = 0.177 COL + 0.009 FCI Distribution and sales costs (CDS) CDS = aDS TPC =0.11 TPC ; (aDS = 0.11) R&D (CRD) CRD = aRD TPC = 0.05 TPC ; (aRD = 0.05) Financing costs=0.04 FCI GE =CAD +CDS +CRD +CF GE = 0.177 COL + 0.009 FCI + 0.11TPC + 0.05TPC + 0.04 FCI GE = 0.177 COL + 0.049 FCI + 0.16TPC = 0.177*336,960 +0.049*2,868,400+0.16TPC =200,194 +0.16TPC TPC = MC + GE = (DMC+ FMC ) + (AC +OC) TPC = CRM+CUT +1.33 COL+ 0.03 TPC+ 0.069 FCI + 0.032 FCI +CDEP +0. 708 COL + 0.032 FCI + 0.177 COL + 0.009FCI + 0.16 TPC TPC = 1.24(CRM+CUT +CDEP) + 2.74 COL + 0.23 FCI
  • 14. = 1.24*(4,917,720+578,080 +258,156) +2.74*336,960 + 0.23*2,868,400 =$1,369,503.8……(6,717,908 ETB) Therefore; DMC=6,141875 +0.03TPC =6,141875 + 0.03 *6,717,908 = 6,343,412 GE=200,194 +0.16TPC =200,194 +0.03*6,717,908 = 401,731 Unit Cost Analysis The unit costs for corn starch production are calculated as the quotient of the annual operating cost divided by the annual production rate. Unit cost (ETB/kg) = = = 6,717,908 /500,000 / =13.5 ETB/kg Corn starch selling Price In order to conduct the profitability analysis, the selling price for corn starch must be first identified. From local?26? market of the current corn starch price is 15?? per kilogram and international selling price is $0.76 per kilogram of corn starch. So the unit corn starch price per
  • 15. kilogram is calculated and equals ETB13.5/kg. For profitability let it will sell with current local market value. Profitability Analysis According to the projected income statement, the project will start generating profit in the first year of operation. Important ratios such as profit to total sales, net profit to equity (Return on equity) and net profit plus interest on total investment (return on total investment) show an increasing trend during the life-time of the project. To calculate the gross profit let we calculate the sales value per annual. i. Sales (Sales Revenue) Sales= unit cost * annual capacity =13.3??$/kg*500,000kg/year 6750000 ETB /year if 14 7,000,000 ETB ii. Gross profit (GP) Gross profit (GP) = Sales – TPC =7,000,000-$8,717,908 =880,496.2 32,092 = 282092 iii. Netprofit (NP) Net profit=Gp-[sales –TPC]*tax rate =Gp-Gp*0.35 =Gp [1-0.35] = 282092*0.65 =183,360 ETB
  • 16. iv. Turn over Ratio Turnover ratio is defined as the ratio of gross annual sales to the fixed-capital investment where the product of the annual production rate and the average selling price of the commodities are the gross annual sales figures. The reciprocal of the turnover ratio is sometimes defined as the capital ratio or the investment ratio. Turnover ratios of up to 5 are common for some business establishments and some are as low as 0.2. For the chemical industry, as a very rough rule of thumb, the ratio can be approximated as 1. Turnover= 7,000,000 /2,868,400 = = 2.444 So, our project acceptable to establishment since turn ratio between the maximum and minimum range [0.2-5]
  • 17. 7.61 PAYBACK PERIOD The payback period is a simple indicator measuring how long it takes to recover the initial investment in the corn starch production plants. When choosing among a few mutually exclusive projects, the project with the quickest payback is preferred. The payback period is calculated as the quotient of the total capital investment divided by the net profit as shown in equation below. Payback period = 8,717,908/183,360 = 36????? = =3.6years 1.1.1. CASH FLOW Table 7.5: cash flow of sodium bicarbonate Production Year Fixed capital Working capital sales Total operating cost Gross profit Depreciation Taxes N -2 -1,661,404 0 0 0 0 0 0 0
  • 18. -1 - 1,661,404 0 0 0 0 0 0 0 0 0 -415,351 0 0 0 0 0 0 1 0 0 2,250,000 1,369,503.8 880,496.2 149,526.4 308,173.7 5 2 0 0 2,250,000 1,369,503.8 880,496.2 149,526.4 308,173.7 5 3 0 0 2,250,000 1,369,503.8 880,496.2 149,526.4 308,173.7 5 4 0 0 2,250,000 1,369,503.8 880,496.2 149,526.4 308,173.7 5 5 0 0 2,250,000 1,369,503.8 880,496.2 149,526.4 308,173.7 5 6 0 0 2,250,000 1,369,503.8 880,496.2 149,526.4 308,173.7 5 7 0 0 2,250,000 1,369,503.8 880,496.2 149,526.4 308,173.7 5 8 0 0 2,250,000 1,369,503.8 880,496.2 149,526.4 308,173.7 5 9 0 0 2,250,000 1,369,503.81 880,496.2 149,526.4 308,173.7 5 10 0 0 2,250,000 1,369,503.8 880,496.2 149,526.4 308,173.7 5 Source: “Economic evaluation report” and “Cash flow analysis report” from Plant design and Economics for chemical engineers, Fourth edition and Sinnott, 1993 and sodium bicarbonate production data. 7.62BREAKEVEN POINT ANALYSIS (BEP) Breakeven point is the point when total annual production cost equals total annual sales. That is the point where profit equals zero. The breakeven point is determined from the relation: BEP = Where Sup=Selling price per unit of production Vcup = Variable costs per unit of production vcup= = =2.71$/kg