SlideShare uma empresa Scribd logo
1 de 37
Construction Methods for Folsom Lake Dike Modification Presented by Matthew D. Marks Magnus Pacific Corporation Roseville, California
Overview Project Name - Dike 5 Embankment Modifications Engineer/Designer - Bureau of Reclamation’s Safety of Dams (SOD) Program Prime Contractor – DD-M Crane and Rigging Contract Value - $3,204,790 Project Location - Located on the north shore of Folsom Reservoir near the intersection of Auburn-Folsom Boulevard and Eureka Road in Granite Bay Construction Schedule - Construction performed between September 2008 and February 2009
Area Map FOLSOM  DAM FOLSOM  LAKE DIKE 5 SACRAMENTO AREA
Project Summary Scope of Work Project involved the partial removal of the downstream face of the existing dike to construct new sand and gravel drains to control internal erosion Change Orders No major change orders; several quantity variations (overruns and underruns) By the Numbers 40,000 CY excavation for existing downstream face 3,500 CY excavation for new toe drain and out fall trench Installed 1,500 LF of 15” HDPE toe drain pipe Installed 18,000 CY (28,000 TN) of fine filter (sand) and 2,500 CY (4,000 TN) of coarse filter (gravel) 85,000 CY replacement of stockpiled and onsite borrow  soils
Scope of Work Site preparations including recreation trail detour Stripping top soil and excavation of downstream face from 2.25H:1V to 2H:1V slope Excavation of toe drain and outfall trench Installation of toe drain and outfall piping and manhole Toe drain backfill using coarse filter (gravel) and chimney drain using fine filter (sand) Reconstruct downstream face to 2.5H:1V slope using stockpiled and onsite borrow materials Replace topsoil and site restoration
Schedule Began site preparations in mid August 2008 Restricted to no heavy construction work until after Labor Day 2008 Excavation work approximately 4 weeks at average rate of 3,000 CY per day Concurrent placement of backfill materials including toe drain pipe, fine filter, coarse filter, and shell fill (average 100 TN coarse filter, 500 TN fine filter and 2,000 CY shell fill per day) over 3 to 4 month period Performed backfill and restoration work through first half of rainy season Completed work in February 2009 (Contractual Completion Date in March 2009)
Embankment Fill Diagram ~ EL. 480 2.5 h 1 v 1 v 2 h ~ EL. 380 Typical Embankment Fill Detail with Toe Drain
Toe Drain Diagram Typical Toe Drain Detail with Pipe
Conventional Equipment Excavation & Hauling Equipment PC 400 Excavator PC 300 Excavator CAT D9 Dozer (rock ripping) 35 TN Articulated Haul Trucks (3 EA) Komatsu 450 Front End Loader Backfill & Grading Equipment CAT D6 Dozer (2 EA – GPS) CAT 815 Compactor CAT 140 Motor Grader 48” Smooth Drum Roller (2 EA)
Specialized Equipment Material Delivery System Drive Over End Dump Truck Unloader 30 TN Surge Hopper/Conveyor Total 70 TN Onsite Storage Capacity Direct Load Conveyor Trucks
Specialized Equipment Conveyor Trucks CAD (Conveyored Aggregate Delivery) Ability to place materials with accuracy and reduced waste Output approximately 250 to 500 TN / DY
Construction Materials Shell Fill Onsite Material (Decomposed Granite) Existing Dike Embankment Borrow Site within Folsom Reservoir 3” Minus Fine Filter Imported Material Clean Washed Sand 3/8” Minus 0 – 3% Passing No. 200 Sieve Coarse Filter Imported Material Clean Washed Gravel 1” Minus 0 – 5% Passing No. 8 Sieve
Pre-Construction Existing Downstream Face
Pre-Construction Existing Top of Slope
Downstream Face Excavation Excavated Face and Toe Drain (and view of Blanket Drain)
Toe Drain Excavation Toe Drain Excavation and Dewatering
Borrow Site Excavation Stockpiled Shell Fill in Folsom Reservoir
Toe Drain Compaction Testing Fine Filter Material
Toe Drain Toe Drain Backfill with Fine and Coarse Filter Material
Shell Fill Shell Fill Placement on New Downstream Face
Shell Fill Shell Fill Placement and Compaction
Shell Fill Fine Filter and Shell Fill Placement
Shell Fill Shell Fill Grading (and Material Delivery System)
“The Big Picture” Fine Filter and Shell Fill Placement
Chimney Drain Fine Filter Placement with Conveyor Truck
Chimney Drain Fine Filter Placement (Non-compacted Loose Lift)
Chimney Drain Fine Filter Placement Near Top of Downstream Face
Chimney Drain New Blanket Drain on Upper Slope
Finishing Excavator Pulling Up Slope Near Top of Dike
Finishing Top of Chimney Drain and Shell Fill Placement
Finishing Final Gravel Road on Crest of Dike
Finishing Finish Slope Grading and Topsoil (Dredge Tailings) Placement
Finishing  Finished Slope (In Progress)
Finishing Finished Grade and Hydroseeding
Project Highlights Excavation on face of dike and rock ripping Excavated with CAT D6 GPS Dozers pushing down slope; load out with Komatsu PC400 Excavator and Articulated Haul Trucks Rock ripping in Borrow Site and Toe Drain using CAT D9 Dozer with rippers; intensely weathered granitic rock with uniaxial compressive strength ranging from about 330 to 850 psi   Placement of coarse and fine filter material without cross blending or waste Material Delivery System replaced managing stockpiles and waste on ground Conveyor Trucks allowed precise placement of coarse and fine filter with less than 1% waste Achieved placement of 28,000 TN of fine filter without any failing tests for No. 200 sieve; material tested in place after compaction Determination of proper compaction equipment and methods Test sections on fine filter to determine proper equipment to minimize break down of material Moisture conditioning fine filter and shell fill
Project Highlights (cont.) Managing site logistics, equipment access and coordination Heavy equipment traffic patterns; one way traffic through work areas Working in limited work space; steep slopes Weather related impacts and site storm water control Most backfill work performed during rainy season Installation and maintenance of site SWPPP controls Effects of rain on site conditions Construction survey control for asbuilt and payment Utilized GPS machine control on CAT D6 Dozer for excavation and backfill; achieved specified tolerances Maintained full time surveyor onsite to survey asbuilt conditions Organization of data and volume calculations Health and Safety Completed the project with no injury or accidents Minor incident involving propane powered fence post pounder; caught fire due to a manufacturer defect; product was recalled
Questions Any questions? DD-M Crane & Rigging 2900 Main St., Suite 103 Alameda, CA 94501 (510) 769-8707 (510) 769-8711 fax P.O. Box 520/160 River Rd Rio Vista, CA 94571 (707) 374-2000 (707) 374-2728 fax Denise Maurer - President Magnus Pacific Corporation 3001 Lava Ridge Court, Suite 240 Roseville, CA 95661 (916) 233-1139 (916) 783-0215 fax Louay Owaidat - President

Mais conteúdo relacionado

Mais procurados

2006 AEG Godwin presentation
2006 AEG Godwin presentation2006 AEG Godwin presentation
2006 AEG Godwin presentationWilliam Godwin
 
Resume Dwyer 9-16
Resume Dwyer 9-16Resume Dwyer 9-16
Resume Dwyer 9-16Don Dwyer
 
B2 - FIALE GEOTHERMAL EXPLORATION PROJECT Djibouti
B2 - FIALE GEOTHERMAL EXPLORATION PROJECT DjiboutiB2 - FIALE GEOTHERMAL EXPLORATION PROJECT Djibouti
B2 - FIALE GEOTHERMAL EXPLORATION PROJECT DjiboutiIceland Geothermal
 
Expo Presentation Poster FINAL
Expo Presentation Poster FINALExpo Presentation Poster FINAL
Expo Presentation Poster FINALBenjamin Kramka
 
Presentation fot Coal Loading Operation
Presentation fot Coal Loading OperationPresentation fot Coal Loading Operation
Presentation fot Coal Loading OperationAdi Sumanto
 
BCPC LOADING JETTY AND STOCK PILE Presentation
BCPC  LOADING JETTY AND STOCK PILE  PresentationBCPC  LOADING JETTY AND STOCK PILE  Presentation
BCPC LOADING JETTY AND STOCK PILE PresentationAdi Sumanto
 
Dr. Malek Smadi, Ph.D. thesis lateral deformation and associated settlement r...
Dr. Malek Smadi, Ph.D. thesis lateral deformation and associated settlement r...Dr. Malek Smadi, Ph.D. thesis lateral deformation and associated settlement r...
Dr. Malek Smadi, Ph.D. thesis lateral deformation and associated settlement r...Dr. Malek Smadi
 
Stone Edge Consulting Ltd. Corporate Resume
Stone Edge Consulting Ltd. Corporate ResumeStone Edge Consulting Ltd. Corporate Resume
Stone Edge Consulting Ltd. Corporate ResumeBarry Lunseth
 
The design evolution of replacement motorway bridge approach embankments
The design evolution of replacement motorway bridge approach embankmentsThe design evolution of replacement motorway bridge approach embankments
The design evolution of replacement motorway bridge approach embankmentsChris Bridges
 
Brooks Road Landfill Vertical Capacity Expansion Environmental Assessment Pub...
Brooks Road Landfill Vertical Capacity Expansion Environmental Assessment Pub...Brooks Road Landfill Vertical Capacity Expansion Environmental Assessment Pub...
Brooks Road Landfill Vertical Capacity Expansion Environmental Assessment Pub...brooksroadenvironmental
 
General Geotechnical Presentation
General Geotechnical PresentationGeneral Geotechnical Presentation
General Geotechnical Presentationandroid9999
 
Pavel Samec - Predictions of changes in properties of forest soils
Pavel Samec - Predictions of changes in properties of forest soilsPavel Samec - Predictions of changes in properties of forest soils
Pavel Samec - Predictions of changes in properties of forest soilsswenney
 
19-07-06 Scheme Description details
19-07-06 Scheme Description details19-07-06 Scheme Description details
19-07-06 Scheme Description detailsAonghus Murray
 
Quay failure in barcelona harbour
Quay failure in barcelona harbourQuay failure in barcelona harbour
Quay failure in barcelona harbourFHRahman1
 

Mais procurados (20)

Gude landfill remediation 161019
Gude landfill remediation 161019Gude landfill remediation 161019
Gude landfill remediation 161019
 
2006 AEG Godwin presentation
2006 AEG Godwin presentation2006 AEG Godwin presentation
2006 AEG Godwin presentation
 
Resume Dwyer 9-16
Resume Dwyer 9-16Resume Dwyer 9-16
Resume Dwyer 9-16
 
B2 - FIALE GEOTHERMAL EXPLORATION PROJECT Djibouti
B2 - FIALE GEOTHERMAL EXPLORATION PROJECT DjiboutiB2 - FIALE GEOTHERMAL EXPLORATION PROJECT Djibouti
B2 - FIALE GEOTHERMAL EXPLORATION PROJECT Djibouti
 
Expo Presentation Poster FINAL
Expo Presentation Poster FINALExpo Presentation Poster FINAL
Expo Presentation Poster FINAL
 
Presentation fot Coal Loading Operation
Presentation fot Coal Loading OperationPresentation fot Coal Loading Operation
Presentation fot Coal Loading Operation
 
BCPC LOADING JETTY AND STOCK PILE Presentation
BCPC  LOADING JETTY AND STOCK PILE  PresentationBCPC  LOADING JETTY AND STOCK PILE  Presentation
BCPC LOADING JETTY AND STOCK PILE Presentation
 
Dr. Malek Smadi, Ph.D. thesis lateral deformation and associated settlement r...
Dr. Malek Smadi, Ph.D. thesis lateral deformation and associated settlement r...Dr. Malek Smadi, Ph.D. thesis lateral deformation and associated settlement r...
Dr. Malek Smadi, Ph.D. thesis lateral deformation and associated settlement r...
 
Stone Edge Consulting Ltd. Corporate Resume
Stone Edge Consulting Ltd. Corporate ResumeStone Edge Consulting Ltd. Corporate Resume
Stone Edge Consulting Ltd. Corporate Resume
 
The design evolution of replacement motorway bridge approach embankments
The design evolution of replacement motorway bridge approach embankmentsThe design evolution of replacement motorway bridge approach embankments
The design evolution of replacement motorway bridge approach embankments
 
KFW - TAS Resume
KFW - TAS ResumeKFW - TAS Resume
KFW - TAS Resume
 
Brooks Road Landfill Vertical Capacity Expansion Environmental Assessment Pub...
Brooks Road Landfill Vertical Capacity Expansion Environmental Assessment Pub...Brooks Road Landfill Vertical Capacity Expansion Environmental Assessment Pub...
Brooks Road Landfill Vertical Capacity Expansion Environmental Assessment Pub...
 
General Geotechnical Presentation
General Geotechnical PresentationGeneral Geotechnical Presentation
General Geotechnical Presentation
 
Pavel Samec - Predictions of changes in properties of forest soils
Pavel Samec - Predictions of changes in properties of forest soilsPavel Samec - Predictions of changes in properties of forest soils
Pavel Samec - Predictions of changes in properties of forest soils
 
Geotechnical Investigation
Geotechnical InvestigationGeotechnical Investigation
Geotechnical Investigation
 
ASCE OC Geo-Institute Luncheon - ARTIC: Anaheim Regional Transportation Inter...
ASCE OC Geo-Institute Luncheon - ARTIC: Anaheim Regional Transportation Inter...ASCE OC Geo-Institute Luncheon - ARTIC: Anaheim Regional Transportation Inter...
ASCE OC Geo-Institute Luncheon - ARTIC: Anaheim Regional Transportation Inter...
 
19-07-06 Scheme Description details
19-07-06 Scheme Description details19-07-06 Scheme Description details
19-07-06 Scheme Description details
 
Environmental Challenges in Oil and Gas Production by Gary E. Slagel
Environmental Challenges in Oil and Gas Production by Gary E. Slagel Environmental Challenges in Oil and Gas Production by Gary E. Slagel
Environmental Challenges in Oil and Gas Production by Gary E. Slagel
 
Quay failure in barcelona harbour
Quay failure in barcelona harbourQuay failure in barcelona harbour
Quay failure in barcelona harbour
 
G012433741
G012433741G012433741
G012433741
 

Semelhante a Construction Methods for Folsom Lake Dike Modification

2016-08-18-DCCR Presentation for DOT rev2
2016-08-18-DCCR Presentation for DOT rev22016-08-18-DCCR Presentation for DOT rev2
2016-08-18-DCCR Presentation for DOT rev2Ismael Vazquez, LSIT
 
Practical Application of GI Technique Rev 0 HAKI pdf
Practical Application of GI Technique Rev 0 HAKI pdfPractical Application of GI Technique Rev 0 HAKI pdf
Practical Application of GI Technique Rev 0 HAKI pdfKeat Wei, Gavin Chung
 
The Role of Geotechnical Site Investigations of Lekki Toll Road Infrastructur...
The Role of Geotechnical Site Investigations of Lekki Toll Road Infrastructur...The Role of Geotechnical Site Investigations of Lekki Toll Road Infrastructur...
The Role of Geotechnical Site Investigations of Lekki Toll Road Infrastructur...Christian Olele
 
Navy Presentation on Site 27 to Moffett RAB July 17, 2008
Navy Presentation on Site 27 to Moffett RAB July 17, 2008Navy Presentation on Site 27 to Moffett RAB July 17, 2008
Navy Presentation on Site 27 to Moffett RAB July 17, 2008Steve Williams
 
4P - CAPSTONE FINAL POWERPOINT
4P - CAPSTONE FINAL POWERPOINT4P - CAPSTONE FINAL POWERPOINT
4P - CAPSTONE FINAL POWERPOINTThomas Bryce
 
The Former Avenue Coking Works and Chemical Plant: Remediation Scheme and Ver...
The Former Avenue Coking Works and Chemical Plant: Remediation Scheme and Ver...The Former Avenue Coking Works and Chemical Plant: Remediation Scheme and Ver...
The Former Avenue Coking Works and Chemical Plant: Remediation Scheme and Ver...IES / IAQM
 
Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...Angelo Indelicato
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
FINAL The Owens Lake Turnout Facility End Cap Budget and Schedule
FINAL The Owens Lake Turnout Facility End Cap Budget and ScheduleFINAL The Owens Lake Turnout Facility End Cap Budget and Schedule
FINAL The Owens Lake Turnout Facility End Cap Budget and ScheduleKook Dean
 
Cameron Run Tributary At La Vista Drive: Stream Restoration
Cameron Run Tributary At La Vista Drive: Stream RestorationCameron Run Tributary At La Vista Drive: Stream Restoration
Cameron Run Tributary At La Vista Drive: Stream RestorationFairfax County
 
20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptx20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptxAmirShafiq25
 
OC harbor brook wetlands stakeholder 6 15-11 final-1
OC harbor brook wetlands stakeholder 6 15-11 final-1OC harbor brook wetlands stakeholder 6 15-11 final-1
OC harbor brook wetlands stakeholder 6 15-11 final-1Onondaga County Save the Rain
 
Sne closure turf presentation combined
Sne closure turf presentation combinedSne closure turf presentation combined
Sne closure turf presentation combinedMassRecycle .
 
Armoured Ford construction calculator v15
Armoured Ford construction calculator v15Armoured Ford construction calculator v15
Armoured Ford construction calculator v15Eric Lestock Kay
 
Hank Zielinski, Northhampton Generating Company, “Excellence in Surface Coal ...
Hank Zielinski, Northhampton Generating Company, “Excellence in Surface Coal ...Hank Zielinski, Northhampton Generating Company, “Excellence in Surface Coal ...
Hank Zielinski, Northhampton Generating Company, “Excellence in Surface Coal ...Michael Hewitt, GISP
 
Terrett Court Storm Drainage Improvements
Terrett Court Storm Drainage ImprovementsTerrett Court Storm Drainage Improvements
Terrett Court Storm Drainage ImprovementsFairfax County
 

Semelhante a Construction Methods for Folsom Lake Dike Modification (20)

2016-08-18-DCCR Presentation for DOT rev2
2016-08-18-DCCR Presentation for DOT rev22016-08-18-DCCR Presentation for DOT rev2
2016-08-18-DCCR Presentation for DOT rev2
 
Practical Application of GI Technique Rev 0 HAKI pdf
Practical Application of GI Technique Rev 0 HAKI pdfPractical Application of GI Technique Rev 0 HAKI pdf
Practical Application of GI Technique Rev 0 HAKI pdf
 
The Role of Geotechnical Site Investigations of Lekki Toll Road Infrastructur...
The Role of Geotechnical Site Investigations of Lekki Toll Road Infrastructur...The Role of Geotechnical Site Investigations of Lekki Toll Road Infrastructur...
The Role of Geotechnical Site Investigations of Lekki Toll Road Infrastructur...
 
Navy Presentation on Site 27 to Moffett RAB July 17, 2008
Navy Presentation on Site 27 to Moffett RAB July 17, 2008Navy Presentation on Site 27 to Moffett RAB July 17, 2008
Navy Presentation on Site 27 to Moffett RAB July 17, 2008
 
4P - CAPSTONE FINAL POWERPOINT
4P - CAPSTONE FINAL POWERPOINT4P - CAPSTONE FINAL POWERPOINT
4P - CAPSTONE FINAL POWERPOINT
 
Tremie
TremieTremie
Tremie
 
The Former Avenue Coking Works and Chemical Plant: Remediation Scheme and Ver...
The Former Avenue Coking Works and Chemical Plant: Remediation Scheme and Ver...The Former Avenue Coking Works and Chemical Plant: Remediation Scheme and Ver...
The Former Avenue Coking Works and Chemical Plant: Remediation Scheme and Ver...
 
Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
FINAL The Owens Lake Turnout Facility End Cap Budget and Schedule
FINAL The Owens Lake Turnout Facility End Cap Budget and ScheduleFINAL The Owens Lake Turnout Facility End Cap Budget and Schedule
FINAL The Owens Lake Turnout Facility End Cap Budget and Schedule
 
Cameron Run Tributary At La Vista Drive: Stream Restoration
Cameron Run Tributary At La Vista Drive: Stream RestorationCameron Run Tributary At La Vista Drive: Stream Restoration
Cameron Run Tributary At La Vista Drive: Stream Restoration
 
20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptx20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptx
 
OC harbor brook wetlands stakeholder 6 15-11 final-1
OC harbor brook wetlands stakeholder 6 15-11 final-1OC harbor brook wetlands stakeholder 6 15-11 final-1
OC harbor brook wetlands stakeholder 6 15-11 final-1
 
Sne closure turf presentation combined
Sne closure turf presentation combinedSne closure turf presentation combined
Sne closure turf presentation combined
 
2017 05-18 Etobicoke Creek Nort Trail panels final
2017 05-18 Etobicoke Creek Nort Trail panels final2017 05-18 Etobicoke Creek Nort Trail panels final
2017 05-18 Etobicoke Creek Nort Trail panels final
 
Armoured Ford construction calculator v15
Armoured Ford construction calculator v15Armoured Ford construction calculator v15
Armoured Ford construction calculator v15
 
Rd cs steele_county
Rd cs steele_countyRd cs steele_county
Rd cs steele_county
 
Hank Zielinski, Northhampton Generating Company, “Excellence in Surface Coal ...
Hank Zielinski, Northhampton Generating Company, “Excellence in Surface Coal ...Hank Zielinski, Northhampton Generating Company, “Excellence in Surface Coal ...
Hank Zielinski, Northhampton Generating Company, “Excellence in Surface Coal ...
 
Terrett Court Storm Drainage Improvements
Terrett Court Storm Drainage ImprovementsTerrett Court Storm Drainage Improvements
Terrett Court Storm Drainage Improvements
 

Mais de SAME 2009 California Water Conference

Mais de SAME 2009 California Water Conference (20)

W Wright Sess8 102709
W Wright Sess8 102709W Wright Sess8 102709
W Wright Sess8 102709
 
Wise Sess11 102509
Wise Sess11 102509Wise Sess11 102509
Wise Sess11 102509
 
Wijsman Sess2 102309
Wijsman Sess2 102309Wijsman Sess2 102309
Wijsman Sess2 102309
 
V Wright Sess2 102109
V Wright Sess2 102109V Wright Sess2 102109
V Wright Sess2 102109
 
Travis Tuesdaynoon 102709
Travis Tuesdaynoon 102709Travis Tuesdaynoon 102709
Travis Tuesdaynoon 102709
 
Tibbitts Sess14 102009
Tibbitts Sess14 102009Tibbitts Sess14 102009
Tibbitts Sess14 102009
 
Suedel Sess5 102309[1]
Suedel Sess5 102309[1]Suedel Sess5 102309[1]
Suedel Sess5 102309[1]
 
Stockton Wednesday8am 102809
Stockton Wednesday8am 102809Stockton Wednesday8am 102809
Stockton Wednesday8am 102809
 
Stockton Wed Am 102809
Stockton Wed Am 102809Stockton Wed Am 102809
Stockton Wed Am 102809
 
Sorci Sess7 101309
Sorci Sess7 101309Sorci Sess7 101309
Sorci Sess7 101309
 
Shewbridge Sess05 101309
Shewbridge Sess05 101309Shewbridge Sess05 101309
Shewbridge Sess05 101309
 
Seed Wed Am 102109
Seed Wed Am 102109Seed Wed Am 102109
Seed Wed Am 102109
 
Sabol Sess3 100909
Sabol Sess3 100909Sabol Sess3 100909
Sabol Sess3 100909
 
Riley Sess3 101309
Riley Sess3 101309Riley Sess3 101309
Riley Sess3 101309
 
Ragain Sess1 102209
Ragain Sess1 102209Ragain Sess1 102209
Ragain Sess1 102209
 
Mullins Sess8 101509
Mullins Sess8 101509Mullins Sess8 101509
Mullins Sess8 101509
 
Mc Knight Sess13 102309
Mc Knight Sess13 102309Mc Knight Sess13 102309
Mc Knight Sess13 102309
 
Millet Sess5 102709
Millet Sess5 102709Millet Sess5 102709
Millet Sess5 102709
 
Mc Quirk Sess1 101509
Mc Quirk Sess1 101509Mc Quirk Sess1 101509
Mc Quirk Sess1 101509
 
Mayer Wed Am 102809
Mayer Wed Am 102809Mayer Wed Am 102809
Mayer Wed Am 102809
 

Último

Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfPaul Menig
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...Any kyc Account
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxWorkforce Group
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangaloreamitlee9823
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communicationskarancommunications
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...Aggregage
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...lizamodels9
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with CultureSeta Wicaksana
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataExhibitors Data
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 

Último (20)

unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdf
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors Data
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 

Construction Methods for Folsom Lake Dike Modification

  • 1. Construction Methods for Folsom Lake Dike Modification Presented by Matthew D. Marks Magnus Pacific Corporation Roseville, California
  • 2. Overview Project Name - Dike 5 Embankment Modifications Engineer/Designer - Bureau of Reclamation’s Safety of Dams (SOD) Program Prime Contractor – DD-M Crane and Rigging Contract Value - $3,204,790 Project Location - Located on the north shore of Folsom Reservoir near the intersection of Auburn-Folsom Boulevard and Eureka Road in Granite Bay Construction Schedule - Construction performed between September 2008 and February 2009
  • 3. Area Map FOLSOM DAM FOLSOM LAKE DIKE 5 SACRAMENTO AREA
  • 4. Project Summary Scope of Work Project involved the partial removal of the downstream face of the existing dike to construct new sand and gravel drains to control internal erosion Change Orders No major change orders; several quantity variations (overruns and underruns) By the Numbers 40,000 CY excavation for existing downstream face 3,500 CY excavation for new toe drain and out fall trench Installed 1,500 LF of 15” HDPE toe drain pipe Installed 18,000 CY (28,000 TN) of fine filter (sand) and 2,500 CY (4,000 TN) of coarse filter (gravel) 85,000 CY replacement of stockpiled and onsite borrow soils
  • 5. Scope of Work Site preparations including recreation trail detour Stripping top soil and excavation of downstream face from 2.25H:1V to 2H:1V slope Excavation of toe drain and outfall trench Installation of toe drain and outfall piping and manhole Toe drain backfill using coarse filter (gravel) and chimney drain using fine filter (sand) Reconstruct downstream face to 2.5H:1V slope using stockpiled and onsite borrow materials Replace topsoil and site restoration
  • 6. Schedule Began site preparations in mid August 2008 Restricted to no heavy construction work until after Labor Day 2008 Excavation work approximately 4 weeks at average rate of 3,000 CY per day Concurrent placement of backfill materials including toe drain pipe, fine filter, coarse filter, and shell fill (average 100 TN coarse filter, 500 TN fine filter and 2,000 CY shell fill per day) over 3 to 4 month period Performed backfill and restoration work through first half of rainy season Completed work in February 2009 (Contractual Completion Date in March 2009)
  • 7. Embankment Fill Diagram ~ EL. 480 2.5 h 1 v 1 v 2 h ~ EL. 380 Typical Embankment Fill Detail with Toe Drain
  • 8. Toe Drain Diagram Typical Toe Drain Detail with Pipe
  • 9. Conventional Equipment Excavation & Hauling Equipment PC 400 Excavator PC 300 Excavator CAT D9 Dozer (rock ripping) 35 TN Articulated Haul Trucks (3 EA) Komatsu 450 Front End Loader Backfill & Grading Equipment CAT D6 Dozer (2 EA – GPS) CAT 815 Compactor CAT 140 Motor Grader 48” Smooth Drum Roller (2 EA)
  • 10. Specialized Equipment Material Delivery System Drive Over End Dump Truck Unloader 30 TN Surge Hopper/Conveyor Total 70 TN Onsite Storage Capacity Direct Load Conveyor Trucks
  • 11. Specialized Equipment Conveyor Trucks CAD (Conveyored Aggregate Delivery) Ability to place materials with accuracy and reduced waste Output approximately 250 to 500 TN / DY
  • 12. Construction Materials Shell Fill Onsite Material (Decomposed Granite) Existing Dike Embankment Borrow Site within Folsom Reservoir 3” Minus Fine Filter Imported Material Clean Washed Sand 3/8” Minus 0 – 3% Passing No. 200 Sieve Coarse Filter Imported Material Clean Washed Gravel 1” Minus 0 – 5% Passing No. 8 Sieve
  • 15. Downstream Face Excavation Excavated Face and Toe Drain (and view of Blanket Drain)
  • 16. Toe Drain Excavation Toe Drain Excavation and Dewatering
  • 17. Borrow Site Excavation Stockpiled Shell Fill in Folsom Reservoir
  • 18. Toe Drain Compaction Testing Fine Filter Material
  • 19. Toe Drain Toe Drain Backfill with Fine and Coarse Filter Material
  • 20. Shell Fill Shell Fill Placement on New Downstream Face
  • 21. Shell Fill Shell Fill Placement and Compaction
  • 22. Shell Fill Fine Filter and Shell Fill Placement
  • 23. Shell Fill Shell Fill Grading (and Material Delivery System)
  • 24. “The Big Picture” Fine Filter and Shell Fill Placement
  • 25. Chimney Drain Fine Filter Placement with Conveyor Truck
  • 26. Chimney Drain Fine Filter Placement (Non-compacted Loose Lift)
  • 27. Chimney Drain Fine Filter Placement Near Top of Downstream Face
  • 28. Chimney Drain New Blanket Drain on Upper Slope
  • 29. Finishing Excavator Pulling Up Slope Near Top of Dike
  • 30. Finishing Top of Chimney Drain and Shell Fill Placement
  • 31. Finishing Final Gravel Road on Crest of Dike
  • 32. Finishing Finish Slope Grading and Topsoil (Dredge Tailings) Placement
  • 33. Finishing Finished Slope (In Progress)
  • 34. Finishing Finished Grade and Hydroseeding
  • 35. Project Highlights Excavation on face of dike and rock ripping Excavated with CAT D6 GPS Dozers pushing down slope; load out with Komatsu PC400 Excavator and Articulated Haul Trucks Rock ripping in Borrow Site and Toe Drain using CAT D9 Dozer with rippers; intensely weathered granitic rock with uniaxial compressive strength ranging from about 330 to 850 psi Placement of coarse and fine filter material without cross blending or waste Material Delivery System replaced managing stockpiles and waste on ground Conveyor Trucks allowed precise placement of coarse and fine filter with less than 1% waste Achieved placement of 28,000 TN of fine filter without any failing tests for No. 200 sieve; material tested in place after compaction Determination of proper compaction equipment and methods Test sections on fine filter to determine proper equipment to minimize break down of material Moisture conditioning fine filter and shell fill
  • 36. Project Highlights (cont.) Managing site logistics, equipment access and coordination Heavy equipment traffic patterns; one way traffic through work areas Working in limited work space; steep slopes Weather related impacts and site storm water control Most backfill work performed during rainy season Installation and maintenance of site SWPPP controls Effects of rain on site conditions Construction survey control for asbuilt and payment Utilized GPS machine control on CAT D6 Dozer for excavation and backfill; achieved specified tolerances Maintained full time surveyor onsite to survey asbuilt conditions Organization of data and volume calculations Health and Safety Completed the project with no injury or accidents Minor incident involving propane powered fence post pounder; caught fire due to a manufacturer defect; product was recalled
  • 37. Questions Any questions? DD-M Crane & Rigging 2900 Main St., Suite 103 Alameda, CA 94501 (510) 769-8707 (510) 769-8711 fax P.O. Box 520/160 River Rd Rio Vista, CA 94571 (707) 374-2000 (707) 374-2728 fax Denise Maurer - President Magnus Pacific Corporation 3001 Lava Ridge Court, Suite 240 Roseville, CA 95661 (916) 233-1139 (916) 783-0215 fax Louay Owaidat - President