PROJECT MANAGEMENT                                                                     JAN, 2012

    ACTIVITY:
       i.     identify a specific project title
      ii.     list out the different tasks to be completed to finish the project
     iii.     estimate the duration of each of each of the activities
      iv.     find out the logical relationship
       v.     construct the network diagram
      vi.     find a project completion time
     vii.     carry out time crashing /take own assumptions
    viii.     estimate resource requirement
      ix.     apply project leveling
    1. MANUFACTURING SPECTROPHOTOMETER

This project is to construct a spectrophotometer: Adjoining is a list and description of
activities for a project constructing (building) a spectrophotometer.

Activity description         Activity     Preceding    Duration              Man power     Crashing
                                                       (days)     Normal
(spectrophotometer design)                activities                         required/da
                                                                  cost(Br)                 Time       Cost (Br)
                                                       Normal
                                                                             y
                                                       time                                (days)

design optical sensor        A            -            7          1000       8             2          1480
Prepare light source         B            -            3          800        3             2          860
design signal processor      C            A            9          1540       3             7          1580
&scanning device
obtain optical sensor        D            A            6          800        2             3          935
design prism and slit        E            A            6          500        3             3          590
obtain signal processor      F            C            5          700        4             4          790
obtain scanning device       G            C            4          750        2             2          850
design softwares             H            C            5          720        2             4          840
accessories
prepare optical sensor       I            B,D          6          600        2             4          712
connect prosessor and        J            F,I          2          300        3             1          330
scanning device
connect optical senor        K            E,H,G,J      2          400        5             1          440
obtain prisms, slits and     L            E,H          4          600        3             3          670
softwares vs. accessories
connect prism, slits         M            L,K          2          200        8             1          240


                                                                                                      1
PROJECT MANAGEMENT                                                                    JAN, 2012

Time related overhead expense, fixed cost, for this project is Birr 270 per day.

And there is only 8 man power to be allocated.



                                    Normal Day /Man
THE NET WPRK DIAGRAM

                                           5
                            6/3 E
                    2
         A7/8                       5/2 H                     L4/3
 1
                  D 6/2 9/3     C               Dummy         0
                                    4
           B3/4                             4/2 G                 7      2/5K     8       2/8   M   9
                                        F 5/4       2/3   J
                3
                                                6
                        6/2 I

     -   Identify the status of paths

Paths                               Duration (days)                   State

B-I-J-K-M                           15                                Non-critical path

A-D-I-J-K-M                         25                                Non-critical path

A-C-F-J-K-M                         27                                Critical path

A-C-G-K-M                           24                                Non-critical path

A-C-H-L-M                           27                                Critical path

A-E-L-M                             19                                Non-critical path




     -   Project completion time = 27 days

     -   Critical paths = A-C-F-J-K-M and A-C-H-L-M




                                                                                                    2
PROJECT MANAGEMENT                                                             JAN, 2012


         I.      Project time crashing

               Step 1: establish time- cost relationship
       Crashing Cost – time slope = Crashing cost – Normal cost
                                     Normal time - crashing time


Max. Time that an activity to be crashed = normal cost –crashing cost

Activities        A       B     C      D     E       F      G    H   I    J     K    L     M

Normal            7       3     9      6     6       5      4    5   6    2     2    4     2
time(days)

Normal poj.       1000 800 1540 800 500 700 750                  720 600 300 400 600 200
Cost(Br)

Crashing          4       2     7      3     3       4      2    4   4    1     1    3     1
time(days)

Crashing          1288 800 1580 935 590 790 850                  840 712 330 440 670 240
cost(Br)

Max.time an       3       1     2      3     3       1      2    1   2    1     1    1     1
activity to be
crashed(days)

Crash cost –      96      60    20     45    30      90     50   120 56   30    40   70    40
time
slope(Br/day)




               Step 2: Identifying critical paths




                                                                                           3
PROJECT MANAGEMENT                                                               JAN, 2012


Paths                           Duration (days)                  State

B-I-J-K-M                       15                               Non-critical path

A-D-I-J-K-M                     25                               Non-critical path

A-C-F-J-K-M                     27                               Critical path

A-C-G-K-M                       24                               Non-critical path

A-C-H-L-M                       27                               Critical path

A-E-L-M                         19                               Non-critical path




             Step 3: computing PCT and costs

   -    Normal Project time = 27 days

   -    Total normal cost =∑( Normal poject Cost(Br)) = 8910

   -    Total fixe cost (Br)= 27*270 = 7290

   -    Crash cost = 0

   -    Therefore, TOTAL COST = 8910+7290= 16200

             Step 4: identify the non critical path with maximum durations next to critical
               path. So, A-D-I-J-K-M is the required one with 25 days durations.

   -    Crash the crtitical paths by 27-25=2 days

   -    In the critical paths, A-C-F-J-K-M and A-C-H-L-M activity A, C and M are the
        common to both activities. But, C has least crashing cost per days and has to be
        crashed by 27-25=2 days or its maximum crashing period. And another option is
        crashing one activity from each path.

   -    Computing costs,




                                                                                               4
PROJECT MANAGEMENT                                                                           JAN, 2012


             TOTAL COST = 16200 +2*20 - 2*270 = 15700 Birr

             PCT = 25 days

     -       Updating the time net work diagram



                                                    5
                                   E6
                          2
             A7                             5   H                      L4
 1
                      D 6     C7                            Dummy       0
                                        4
         B        3                                     G 4                7       K 2   8       M 2     9
                                                F       5     J2
                      3
                                                        6
                               I    6

     -       Now there are three critical paths

Paths                                   Duration (days)            State

B-I-J-K-M                               15                         Non-critical path

A-D-I-J-K-M                             25                         critical path

A-C-F-J-K-M                             25                         Critical path

A-C-G- K-M                              22                         Non-critical path

A-C-H-L-M                               25                         Critical path

A-E-L-M                                 19                         Non-critical path

     -       A-C-G-K-M is the first non critical path next to critical in duration

     -       Critical paths, A-D-I-J-K-M, A-C-F-J-K-M and A-C-H-L-M have to be crashed by
             25-22 =3 day. Among the activities A and M are the common activities. But, M is
             with low crashing cost per day.

     -       So now crash M

                                                                                                         5
PROJECT MANAGEMENT                                                                   JAN, 2012

     -

     -   Total cost 15700 + 1*40 – 1*270 = 15470

     -   PCT = 24 days

                             6E                 5

                    2
         A7                               5   H                  L4
 1
                D 6      C7                         Dummy
                                      4
           B3                                       4G              7       2K   8       1 M     9
                                           F5               J2
                3
                                                    6
                         I        6

# Now A-C-G- K-M is the first non critical path next to critical paths.

     -   And the critical paths have to be crashed by a maximum number of days = 24 -21 = 3
         days. Here, the common activity A has to be crashed since M has been already
         crashed.

Paths                                 Duration (days)       State

B-I-J-K-M                             13                    Non-critical path

A-D-I-J-K-M                           24                    critical path

A-C-F-J-K-M                           24                    Critical path

A-C-G- K-M                            21                    critical path

A-C-H-L-M                             24                    Critical path

A-E-L-M                               15                    Non-critical path




     -   TOTAL COST = 15470 + 3*96 - 3*270 = 14948

     -   Now PCT = 21 days

                                                                                                 6
PROJECT MANAGEMENT                                                                    JAN, 2012




     -   updating net work diagram
                                             5
                              6E
                    2
         A4                            5   H                  L4
 1
                D 6      C7                      Dummy
                                   4
           B3                                    4G              7       2K       8       1 M         9
                                        F5               J2
                3
                                                 6
                           I 6

Paths                              Duration (days)       State

B-I-J-K-M                          13                    Non-critical path

A-D-I-J-K-M                        21                    critical path

A-C-F-J-K-M                        21                    Critical path

A-C-G- K-M                         21                    Critical path

A-C-H-L-M                          21                    Critical path

A-E-L-M                            15                    Non-critical path




     -   Now A-C-G-K-M is critical path too. And A-E-L-M, takes 15 days, is the first long
         non critical path next to citicals and it has to be crashed.

     -   So crash critical paths by 21-15 =6 days. But it is difficult to crash a critical activity
         by once by 6 days. Commonly, all critical activities must be crashed by same number
         of days.




                                                                                                      7
PROJECT MANAGEMENT                                                                JAN, 2012


critical              Activities to      MAX. Time    Cash cost per day    TOTAL          Selected
                                                                           maximum        activities
activities            be crashed         to crash
                                                                           crashing
                                                                           days
A-D-I-J-K-M           D                  3            45                   7              J&K

                      I                  2            56

                      J                  1            30

                      K                  1            40

A-C-F-J-K-M           F                  1            90                   3              J&K

                      J                  1            30

                      K                  1            40

  A-C-H-L-M           H                  1            120                  2              H &L

                      L                  1            70


                      G                  2            50                   3              G &K
     A-C-G-K-M
                      K                  1            40

           -   Since the maximum crashing days of path A-C-H-L-M is to be 2 days, the project can
               be crashed by 2 days now. Common activities are given priority for crashing so as to
               minimize crashing cost.


           -   In A-C-G-K-M, G is only crashed for 1 day.
           -   PCT = 19 days.




                                                                                                       8
PROJECT MANAGEMENT                                                                                  JAN, 2012



                                                   5
                                   6 E
                      2
         A2                                  4   H                      L3
 1
                  D 6         C7                       Dummy
                                         4
             B3                                        3G                7            1K        8        1 M    9
                                              F5               J1
                  3
                                                       6
                               I 6

     -   PCT = 19 days.

     -   To analysis the cost, the crashed activities each for 1 day H, L, G, J and K must be
         considered.

     -   Total cost = 14948+ 1*(120 +70+50+30+40) -2*270

                         = 14948 + 310 -540

                         = 14718 Birr

          Therefore, Total cost = 14718 Birr

     -   Since the critical activities in the path A-C-H-L-M are all crashed, the project can’t be
         further crashed. So the optimal cost is Birr 14718.

                             Project cost

                                         16200                                                      .

                                         15700                                             .

                                     15470                                        .

                                         14918                               .

                                     14718                          .

                                                                19           21   24       25       27

                                                                                                                9
PROJECT MANAGEMENT                                                                    JAN, 2012

Normal project completion time and its corresponding cost are 27 days and Birr 16200,
respectively.

The project crashing time and optimal time is same, 19 days. As a result, the optimal cost and
maximum crashing cost are equal =14718.




        II.           Resource levelling – in levelling time – scale graph and resource
                      histogram are used.

                            Hence, the resource is tried to be leveled before crashing. To do so,
                                 steps followed are:

                   draw critical paths on the straight lines on time – scale graph before levelling

                   draw the non criticals below the criticals

                   Draw the resource histogram before levelling.

                   Apply levelling to methods of levelling such as delay non critical activities,
                      splitting non critical activities in to non sequential.

                   And draw activities on the time scale graph after levelling

                   Draw the resource histogram after levelling (the graph below is represented as
                      follow and the histogram is given in rectangular form below each time scale
                      graph).

Resource availability




                  1    2         3                            time

              8        8     8                         resource requirement




                                                                                                     10
PROJECT MANAGEMENT                                                                                                        JAN, 2012

                  A   8                                 C    3                                     F    4             J   3        5   K       8   M
1                                     2                                              4                            6            7           8            9


          B   3   …   .   .   .       .   .   ..   ..   ..   ..                          I    2         ..   ..
1                                                                 3
                                              D    2
                                  2
                                                                                                   H    2                          L   3
                                                                                     4                                5
                                              E    3                  ..   ..   ..       ..   ..   ..   ..   ..
                                  2
                                                                                                   G    2
                                                                                     4
    1     2   3   4   5   6   7       8   9   1    1    1    1        1    1    1        1    1    1    2    2        2   2        2   2       2   2
                                              0    1    2    3        4    5    6        7    8    9    0    1        2   3        4   5       6   7


    1     1   1   8   8   8   8       8   8   8    8    8    8        5    5    5        1    1    1    8    6        6   6        8   8       8   8
    1     1   1                                                                          0    0    0


    before levelling time scale graph above and resource histogram below are given

    1
    011


    8
    10
    6
    8
    5
    6

    5
    1     2   3   4   5   6   7       8   9   0    1    2    3        4    5    6        7    8    9    0    1        2   3        4   5       6   7


                  A   8                            C    3                                     F    4                  3   J        5   K       8   M
1                                 2                                                  4                            6           7            8            9
                                                   3    B                                I    2
1                                                                 3
                                              D    2                                          H    2                               L   3
                                  2                                                  4                                5
                                                                                                                          O

                                                                                                                      5

                                                        E                  3
                                  2
                                                                                                             G        2
                                                                                     4
    8     8   8   8   8   8   8       8   8   8    8    8    8        8    8    8        8    8    8    8    8        8   8        8   8       8   8


    8                                                   LEVELLED HISTOGRAM
    FG
    5
                                                                                                                                                   11

Mais conteúdo relacionado

Semelhante a Project management project scheduling

Pma individual assignment ii
Pma  individual assignment iiPma  individual assignment ii
Pma individual assignment iichandraswami
 
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docxdrennanmicah
 
CPM-PERT-Examples .pptx
CPM-PERT-Examples .pptxCPM-PERT-Examples .pptx
CPM-PERT-Examples .pptxssuser9b876d
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project managementRahul Dubey
 
Network diagram problems
Network diagram problemsNetwork diagram problems
Network diagram problemsSubhra Mishra
 
Design of RCC Beam By using C Programming
Design of RCC Beam By using C ProgrammingDesign of RCC Beam By using C Programming
Design of RCC Beam By using C ProgrammingIRJET Journal
 
Lecture7_2021_v2.pdf
Lecture7_2021_v2.pdfLecture7_2021_v2.pdf
Lecture7_2021_v2.pdfssuserc9da59
 
Cpm (critical path method)
Cpm (critical path method)Cpm (critical path method)
Cpm (critical path method)El Moro
 
Scheduling Problems Complete the following problems covering pro.docx
Scheduling Problems Complete the following problems covering pro.docxScheduling Problems Complete the following problems covering pro.docx
Scheduling Problems Complete the following problems covering pro.docxkenjordan97598
 
AIFrienz_Webinar_Tomomi_Research_Inc).pdf
AIFrienz_Webinar_Tomomi_Research_Inc).pdfAIFrienz_Webinar_Tomomi_Research_Inc).pdf
AIFrienz_Webinar_Tomomi_Research_Inc).pdfSeong-Hun Choe
 
STAAD PRO CONNECT EDITION (SUMMER INTERNSHIP TRAINING)
STAAD PRO CONNECT EDITION (SUMMER INTERNSHIP TRAINING)STAAD PRO CONNECT EDITION (SUMMER INTERNSHIP TRAINING)
STAAD PRO CONNECT EDITION (SUMMER INTERNSHIP TRAINING)VishalKumar65606
 

Semelhante a Project management project scheduling (20)

Pma individual assignment ii
Pma  individual assignment iiPma  individual assignment ii
Pma individual assignment ii
 
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx
 
CPM-PERT-Examples .pptx
CPM-PERT-Examples .pptxCPM-PERT-Examples .pptx
CPM-PERT-Examples .pptx
 
Cm exercise 7
Cm exercise 7Cm exercise 7
Cm exercise 7
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
Network diagram problems
Network diagram problemsNetwork diagram problems
Network diagram problems
 
UNIT-2.pptx
UNIT-2.pptxUNIT-2.pptx
UNIT-2.pptx
 
Network analysis & cpm
Network analysis & cpmNetwork analysis & cpm
Network analysis & cpm
 
Time cost-trade-off
Time cost-trade-offTime cost-trade-off
Time cost-trade-off
 
Cm exercise 4
Cm exercise 4Cm exercise 4
Cm exercise 4
 
Design of RCC Beam By using C Programming
Design of RCC Beam By using C ProgrammingDesign of RCC Beam By using C Programming
Design of RCC Beam By using C Programming
 
Lecture7_2021_v2.pdf
Lecture7_2021_v2.pdfLecture7_2021_v2.pdf
Lecture7_2021_v2.pdf
 
Cpm (critical path method)
Cpm (critical path method)Cpm (critical path method)
Cpm (critical path method)
 
Critical path analysis
Critical path analysisCritical path analysis
Critical path analysis
 
04 b50d01
04 b50d0104 b50d01
04 b50d01
 
Cpmprt
CpmprtCpmprt
Cpmprt
 
Scheduling Problems Complete the following problems covering pro.docx
Scheduling Problems Complete the following problems covering pro.docxScheduling Problems Complete the following problems covering pro.docx
Scheduling Problems Complete the following problems covering pro.docx
 
AIFrienz_Webinar_Tomomi_Research_Inc).pdf
AIFrienz_Webinar_Tomomi_Research_Inc).pdfAIFrienz_Webinar_Tomomi_Research_Inc).pdf
AIFrienz_Webinar_Tomomi_Research_Inc).pdf
 
STAAD PRO CONNECT EDITION (SUMMER INTERNSHIP TRAINING)
STAAD PRO CONNECT EDITION (SUMMER INTERNSHIP TRAINING)STAAD PRO CONNECT EDITION (SUMMER INTERNSHIP TRAINING)
STAAD PRO CONNECT EDITION (SUMMER INTERNSHIP TRAINING)
 
Critical path method
Critical path methodCritical path method
Critical path method
 

Último

Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...lizamodels9
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxWorkforce Group
 
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...lizamodels9
 
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...allensay1
 
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...amitlee9823
 
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentationuneakwhite
 
JAYNAGAR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
JAYNAGAR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLJAYNAGAR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
JAYNAGAR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLkapoorjyoti4444
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...Aggregage
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptxnandhinijagan9867
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangaloreamitlee9823
 
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876dlhescort
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwaitdaisycvs
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756dollysharma2066
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataExhibitors Data
 
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...Sheetaleventcompany
 
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...rajveerescorts2022
 
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 MonthsSEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 MonthsIndeedSEO
 

Último (20)

Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
 
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
 
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
 
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentation
 
JAYNAGAR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
JAYNAGAR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLJAYNAGAR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
JAYNAGAR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
 
Falcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in indiaFalcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in india
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptx
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
 
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors Data
 
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
 
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
 
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 MonthsSEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
 

Project management project scheduling

  • 1. PROJECT MANAGEMENT JAN, 2012 PROJECT MANAGEMENT BY: TADELE ASMARE Phone: +251920774757 E_mail:tadeleasmare@yahoo.com JAN, 2012 0
  • 2. PROJECT MANAGEMENT JAN, 2012 ACTIVITY: i. identify a specific project title ii. list out the different tasks to be completed to finish the project iii. estimate the duration of each of each of the activities iv. find out the logical relationship v. construct the network diagram vi. find a project completion time vii. carry out time crashing /take own assumptions viii. estimate resource requirement ix. apply project leveling 1. MANUFACTURING SPECTROPHOTOMETER This project is to construct a spectrophotometer: Adjoining is a list and description of activities for a project constructing (building) a spectrophotometer. Activity description Activity Preceding Duration Man power Crashing (days) Normal (spectrophotometer design) activities required/da cost(Br) Time Cost (Br) Normal y time (days) design optical sensor A - 7 1000 8 2 1480 Prepare light source B - 3 800 3 2 860 design signal processor C A 9 1540 3 7 1580 &scanning device obtain optical sensor D A 6 800 2 3 935 design prism and slit E A 6 500 3 3 590 obtain signal processor F C 5 700 4 4 790 obtain scanning device G C 4 750 2 2 850 design softwares H C 5 720 2 4 840 accessories prepare optical sensor I B,D 6 600 2 4 712 connect prosessor and J F,I 2 300 3 1 330 scanning device connect optical senor K E,H,G,J 2 400 5 1 440 obtain prisms, slits and L E,H 4 600 3 3 670 softwares vs. accessories connect prism, slits M L,K 2 200 8 1 240 1
  • 3. PROJECT MANAGEMENT JAN, 2012 Time related overhead expense, fixed cost, for this project is Birr 270 per day. And there is only 8 man power to be allocated. Normal Day /Man THE NET WPRK DIAGRAM 5 6/3 E 2 A7/8 5/2 H L4/3 1 D 6/2 9/3 C Dummy 0 4 B3/4 4/2 G 7 2/5K 8 2/8 M 9 F 5/4 2/3 J 3 6 6/2 I - Identify the status of paths Paths Duration (days) State B-I-J-K-M 15 Non-critical path A-D-I-J-K-M 25 Non-critical path A-C-F-J-K-M 27 Critical path A-C-G-K-M 24 Non-critical path A-C-H-L-M 27 Critical path A-E-L-M 19 Non-critical path - Project completion time = 27 days - Critical paths = A-C-F-J-K-M and A-C-H-L-M 2
  • 4. PROJECT MANAGEMENT JAN, 2012 I. Project time crashing  Step 1: establish time- cost relationship Crashing Cost – time slope = Crashing cost – Normal cost Normal time - crashing time Max. Time that an activity to be crashed = normal cost –crashing cost Activities A B C D E F G H I J K L M Normal 7 3 9 6 6 5 4 5 6 2 2 4 2 time(days) Normal poj. 1000 800 1540 800 500 700 750 720 600 300 400 600 200 Cost(Br) Crashing 4 2 7 3 3 4 2 4 4 1 1 3 1 time(days) Crashing 1288 800 1580 935 590 790 850 840 712 330 440 670 240 cost(Br) Max.time an 3 1 2 3 3 1 2 1 2 1 1 1 1 activity to be crashed(days) Crash cost – 96 60 20 45 30 90 50 120 56 30 40 70 40 time slope(Br/day)  Step 2: Identifying critical paths 3
  • 5. PROJECT MANAGEMENT JAN, 2012 Paths Duration (days) State B-I-J-K-M 15 Non-critical path A-D-I-J-K-M 25 Non-critical path A-C-F-J-K-M 27 Critical path A-C-G-K-M 24 Non-critical path A-C-H-L-M 27 Critical path A-E-L-M 19 Non-critical path  Step 3: computing PCT and costs - Normal Project time = 27 days - Total normal cost =∑( Normal poject Cost(Br)) = 8910 - Total fixe cost (Br)= 27*270 = 7290 - Crash cost = 0 - Therefore, TOTAL COST = 8910+7290= 16200  Step 4: identify the non critical path with maximum durations next to critical path. So, A-D-I-J-K-M is the required one with 25 days durations. - Crash the crtitical paths by 27-25=2 days - In the critical paths, A-C-F-J-K-M and A-C-H-L-M activity A, C and M are the common to both activities. But, C has least crashing cost per days and has to be crashed by 27-25=2 days or its maximum crashing period. And another option is crashing one activity from each path. - Computing costs, 4
  • 6. PROJECT MANAGEMENT JAN, 2012 TOTAL COST = 16200 +2*20 - 2*270 = 15700 Birr PCT = 25 days - Updating the time net work diagram 5 E6 2 A7 5 H L4 1 D 6 C7 Dummy 0 4 B 3 G 4 7 K 2 8 M 2 9 F 5 J2 3 6 I 6 - Now there are three critical paths Paths Duration (days) State B-I-J-K-M 15 Non-critical path A-D-I-J-K-M 25 critical path A-C-F-J-K-M 25 Critical path A-C-G- K-M 22 Non-critical path A-C-H-L-M 25 Critical path A-E-L-M 19 Non-critical path - A-C-G-K-M is the first non critical path next to critical in duration - Critical paths, A-D-I-J-K-M, A-C-F-J-K-M and A-C-H-L-M have to be crashed by 25-22 =3 day. Among the activities A and M are the common activities. But, M is with low crashing cost per day. - So now crash M 5
  • 7. PROJECT MANAGEMENT JAN, 2012 - - Total cost 15700 + 1*40 – 1*270 = 15470 - PCT = 24 days 6E 5 2 A7 5 H L4 1 D 6 C7 Dummy 4 B3 4G 7 2K 8 1 M 9 F5 J2 3 6 I 6 # Now A-C-G- K-M is the first non critical path next to critical paths. - And the critical paths have to be crashed by a maximum number of days = 24 -21 = 3 days. Here, the common activity A has to be crashed since M has been already crashed. Paths Duration (days) State B-I-J-K-M 13 Non-critical path A-D-I-J-K-M 24 critical path A-C-F-J-K-M 24 Critical path A-C-G- K-M 21 critical path A-C-H-L-M 24 Critical path A-E-L-M 15 Non-critical path - TOTAL COST = 15470 + 3*96 - 3*270 = 14948 - Now PCT = 21 days 6
  • 8. PROJECT MANAGEMENT JAN, 2012 - updating net work diagram 5 6E 2 A4 5 H L4 1 D 6 C7 Dummy 4 B3 4G 7 2K 8 1 M 9 F5 J2 3 6 I 6 Paths Duration (days) State B-I-J-K-M 13 Non-critical path A-D-I-J-K-M 21 critical path A-C-F-J-K-M 21 Critical path A-C-G- K-M 21 Critical path A-C-H-L-M 21 Critical path A-E-L-M 15 Non-critical path - Now A-C-G-K-M is critical path too. And A-E-L-M, takes 15 days, is the first long non critical path next to citicals and it has to be crashed. - So crash critical paths by 21-15 =6 days. But it is difficult to crash a critical activity by once by 6 days. Commonly, all critical activities must be crashed by same number of days. 7
  • 9. PROJECT MANAGEMENT JAN, 2012 critical Activities to MAX. Time Cash cost per day TOTAL Selected maximum activities activities be crashed to crash crashing days A-D-I-J-K-M D 3 45 7 J&K I 2 56 J 1 30 K 1 40 A-C-F-J-K-M F 1 90 3 J&K J 1 30 K 1 40 A-C-H-L-M H 1 120 2 H &L L 1 70 G 2 50 3 G &K A-C-G-K-M K 1 40 - Since the maximum crashing days of path A-C-H-L-M is to be 2 days, the project can be crashed by 2 days now. Common activities are given priority for crashing so as to minimize crashing cost. - In A-C-G-K-M, G is only crashed for 1 day. - PCT = 19 days. 8
  • 10. PROJECT MANAGEMENT JAN, 2012 5 6 E 2 A2 4 H L3 1 D 6 C7 Dummy 4 B3 3G 7 1K 8 1 M 9 F5 J1 3 6 I 6 - PCT = 19 days. - To analysis the cost, the crashed activities each for 1 day H, L, G, J and K must be considered. - Total cost = 14948+ 1*(120 +70+50+30+40) -2*270  = 14948 + 310 -540  = 14718 Birr  Therefore, Total cost = 14718 Birr - Since the critical activities in the path A-C-H-L-M are all crashed, the project can’t be further crashed. So the optimal cost is Birr 14718. Project cost 16200 . 15700 . 15470 . 14918 . 14718 . 19 21 24 25 27 9
  • 11. PROJECT MANAGEMENT JAN, 2012 Normal project completion time and its corresponding cost are 27 days and Birr 16200, respectively. The project crashing time and optimal time is same, 19 days. As a result, the optimal cost and maximum crashing cost are equal =14718. II. Resource levelling – in levelling time – scale graph and resource histogram are used.  Hence, the resource is tried to be leveled before crashing. To do so, steps followed are:  draw critical paths on the straight lines on time – scale graph before levelling  draw the non criticals below the criticals  Draw the resource histogram before levelling.  Apply levelling to methods of levelling such as delay non critical activities, splitting non critical activities in to non sequential.  And draw activities on the time scale graph after levelling  Draw the resource histogram after levelling (the graph below is represented as follow and the histogram is given in rectangular form below each time scale graph). Resource availability 1 2 3 time 8 8 8 resource requirement 10
  • 12. PROJECT MANAGEMENT JAN, 2012 A 8 C 3 F 4 J 3 5 K 8 M 1 2 4 6 7 8 9 B 3 … . . . . . .. .. .. .. I 2 .. .. 1 3 D 2 2 H 2 L 3 4 5 E 3 .. .. .. .. .. .. .. .. 2 G 2 4 1 2 3 4 5 6 7 8 9 1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 1 1 1 8 8 8 8 8 8 8 8 8 8 5 5 5 1 1 1 8 6 6 6 8 8 8 8 1 1 1 0 0 0 before levelling time scale graph above and resource histogram below are given 1 011 8 10 6 8 5 6 5 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 A 8 C 3 F 4 3 J 5 K 8 M 1 2 4 6 7 8 9 3 B I 2 1 3 D 2 H 2 L 3 2 4 5 O 5 E 3 2 G 2 4 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 LEVELLED HISTOGRAM FG 5 11