SlideShare uma empresa Scribd logo
1 de 51
Baixar para ler offline
BUILDING
CONSTRUCTION-1SUB CODE- ARC 1523
ASSIGNMENT 1 - EXPERIENCING CONSTRUCTION
(EXPERIENCING, DOCUMENTING AND ANALYSING THE CONSTRUCTION PROCESS)
TUTOR – Ar. ALICE LIM LI YUEN
Content
1.0 Introduction and Group members detail. (SI*)
1.1 Introduction to site
2.0 Site and Safety (MM*)
2.1 Plants and Machinery
3.0 External Work (SV*)
4.0 Foundation (MNA*)
4.1 Foundation type and construction process (from site visit)
5.0 Superstructure (from site visit and reference)
5.1 Beam and Column (SI*)
5.2 Slab (MNA*)
5.3 Wall (PZ*)
5.4 Staircase (JE*)
6.0 Doors and Windows (PZ*)
7.0 Roof (LZH*)
7.1 Roof type and construction process (from site visit)
8.0 Summary
8.1 References
(SI*) Saurabha Iyer
(MM*) Muhammad Mubarak
(SV*) Saravanan Vytelingum
(MNA*) Muhammad Nabeel Ali Joomun
(PZ*) Prisha Zenia
(JE*) Jonathan Edwards
(LZH*) Lim Zhi Hong
Page
1
2-6
7-8
9-16
17-24
25
26-30
31
32-34
35-40
41
42-46
47
48
Introduction to site
• Location – Megan Salak park, Jalan 1/125E ,
Desa Pedaling ,57100 Kuala Lumpur
• date of approval- 11 July 2013
• Date of completion – January 2016
• Developer- Chico Development Sdn Bhd
• Architect- Akitek Akiprima SDN BHD
• Landscape architect- Primeclass Landscaping
SDN BDH
• Contractor- Suncity Trading and Construction
SDN BHD
• House type- 3story semi d
• Land tenure – freehold
• 115 units
Introduction to the group members
Saravanan Vytelingum 0320563
Muhammad Nabeel Ali Joomun 0320583
Muhammad Mubarak 0319984
Saurabha Iyer 0320569
Prisha Zenia 0320762
Jonathan Edwards Woe 0320458
Lim Zhi Hong 0304547
4
Site and Safety
5
Importance of following safety site rules
Accident rates are
higher in construction
sites because people
doesn’t pay much
attention to the
surrounding and the
warning signboards
that is placed outside
of the construction
site.
Personal Protective Equipment (PPE)
• All refers to protective clothing,
helmet, goggles or other garments
or equipment designed to protect
the wearer’s body from injury.
• Staffs and workers must wear and
use PPE as appropriate.
• Sub-con and their workers must
not wear short pants/slipper to
work.
6
Site safety rules:
• To prevent any injuries on
the head as it is the most
dangerous part.
• To prevent dust particals
from the construction site
to draw on the head.
• To prevent from any ear damage due to
drilling and construction work
Foot protection
should be worn
in this area
Safety helmets must be worn:
Hearing protection must be worn
• To prevent danger of
foot injuries due to
falling or rolling objects
or objects piercing the
sole and where such
employee’s feet are
exposed to electrical
hazards
No person who is under the influence of
alcohol or drugs are allowed in the site
• as a drunk person may not be
conscious , it may be dangerous
as they could walk to buildings
which are not complete which
are full of metal bars therefore
it will be dangerous
• To reduce electrical shock
hazard when near exposed
electrical conductors which
could contact the head.
No unauthorized entry
• All visitors must report to
the office
• Management or workers
may not be responsible for
any accidents.
7
High visibility clothing
must be worn in this area
• So that when to
construction work is
going on’ it will be easier
to be noticed by the
bright color of the
clothing to prevent any
accidents from happening
Safety googles must be worn.
• The dust particles at the site
may be harmful to the eye
therefore by wearing a
safety google it can prevent
the dust from entering the
eye. Eg flying particles,
molten metals, liquid
chemicals or acids.
First aid box
• First aid equipment is
kept in the site
managers office as it is
easier and faster
access in case of
emergency
Children must not
play in the site
• When the construction
activity is going on, it will
be dangerous for the
children as any accidents
might happen such as
getting hit by vehicles or
falling object
Hand glove must be
worn • to protect the
employee hand
from bruise
• To protect hands
from hazardous
substance
Scaffolding
platform
• Helps to minimize the
risk of fall when a
worker is doing the
construction work
high up the building
8
Reasons for using
construction plant.
• High output - Complete work volume
in time.
• Quality work - Accuracy and
consistency.
• Economy - Cost effectiveness.
• Nature of work - Dangerous if do the
task manually.
TYPES OF PLANT AND
EQUIPMENT
1. Excavating and earth- moving
equipment:
• Backhoe-loaders
• Excavators
• Loaders
• Trucks and hauling equipment
• Vacuum excavators
2. Lifting and vertical transportation
equipment
• Mobile cranes
• Tower cranes
• Goods hoists
• Passengers hoists
3) Bulldozers
4) Scrapers
5) Concrete plant and equipment
• Concrete trucks
• Concrete mixing plant
• Concrete pumps
Plants and Machinery
9
Backhoe-loader
Backhoe loader is engineering vehicle, which consist of a
tractor, fitted with a shovel or bucket on the front and a
small backhoe on the back.
Uses:
• Digging shallow excavations
• Digging trenches
• General grading
• Lifting loads
• Loading and carrying materials
Excavators
Uses of excavators:
• Excavating below or above natural surface of ground
on which machine rests.
• Digging bigger trenches.
• Digging pits for basements,
• General grading work.
• Loading onto haul units (dumper trucks)
• Lifting
Other uses:
Excavator bucket can be replaced with a breaker or
hammer turning the unit into a demolition machine.
Construction equipment found on site
10
Mobile crane
• A full revolving superstructure mounted on a truck with multi section-
telescoping boom.
• These cranes can travel on public roads between projects under own
power with minimum or no dismantling and reassembling.
• Therefore very suitable if a job requires crane utilization for a few hours
to a couple of days.
Uses:
To hoist materials and machineries.
Vibrating smooth wheel roller
Vibratory road roller can be equipped with
single drum or double drum.
Uses:
• Rolling aggregates
• Compaction of clay and sand
• Proof rolling of subgrades and in
compacting asphalt pavements.
11
3.0 External work
12
• External works on our construction site are mainly:
• Setting out
• Signage
• Site boundary
• Temporary shelters
• Earthworks
• Drainage
• Sloping
13
Setting Out
Starting period : Semptember
2013
Construction start :
March 2014
Handing Over : January 2016
Site Area : 18 Hectares
Functional external features may take the form of
access requirements where security may be an
issue. To enhance security on any project fencing
could be used to separate the site from adjacent
properties and land. Any from of fencing, whether
it be full permimeter fencing or partial fencing
installed at key areas of the site, can stop or cut
down any unwanted pedestrian or vehicular
access.
The primary form of fencing present on our site is
mainly metal hoardings placed moslty around the
whole site boundary except around the
hillside.Another form of protection at our site
boundary would be the retaining wall (R.E Wall) or
Retaining Concrete Wall (R.C Wall).
Site boundary
Retaining wall R.C wall
Metal hoarding 14
Storage of material and temporary shelters
They are actually small housing shelters for storing site equipments and for construction workers to rest.
15
Earthworks
Earthworks are engineering works created through the
moving or processing of parts of the earth's surface
involving quantities of soil or unformed rock. The earth may
be moved to another location and formed into a desired
shape for a purpose. Much of earthworks involves machine
excavation and fill or backfill.
Excavation may be classified by type of material:
• Topsoil excavation
• Earth excavation
• Rock excavation
• Muck excavation - this usually contains excess water and
unsuitable soil
• Unclassified excavation - this is any combination of
material types
Excavation may be classified by the purpose:
Stripping
• Roadway excavation
• Drainage or structure excavation
• Bridge excavation
• Channel excavation
• Footing excavation
• Borrow excavation
• Dredge excavation
• Underground Excavation
Typical earthworks include roads, railway beds, causeways, dams, levees, canals,
and berms. Other common earthworks are land grading to reconfigure the
topography of a site, or to stabilize slopes.
Earth-moving machines such as the loader, production trucks, the grader, the
bulldozer, the backhoe, and the dragline excavator.
16
Sloping
One unique and very ingenios way of using waste concrete to prevent soil erosion and provide
slope protection is by graniting.This method is implemeted by fitting pipes into the slopes to carry
accumulated water from the top away while the face of the slope is sprayed with waste concrete
from construction also helping to save on material cost.
This method of sloping is aesthetically pleasing, economical and prevents materials wastage.
17
Drainage
Drainage is the natural or artificial removal of surface and sub-surface water from an area.
The drainage system on the site is essential as it carries away waste water from the site to
its respective destination.
Civil engineers and construction managers work alongside architects and supervisors,
planners, quantity surveyors, the general workforce, as well as subcontractors.
Drainage options for the construction industry include:
• Point drainage
It intercepts water at gullies (points). Gullies connect to drainage pipes beneath the ground
surface and deep excavation is required to facilitate this system. Support for deep trenches
is required in the shape of planking, strutting or shoring.
• Channel drainage
It intercepts water along the entire run of the channel. Channel drainage is typically
manufactured from concrete, steel, polymer or composites. The interception rate of
channel drainage is greater than point drainage and the excavation required is usually much
less deep.
The surface opening of channel drainage usually comes in the form of gratings (polymer,
plastic, steel or iron) or a single slot (slot drain) that runs along the ground surface (typically
manufactured from steel or iron).
18
Street Furniture
Street furniture represents a large and
diverse subcategory of external works. It can
be used to create subtle themes within city
centres, whether it be a traditional or
contemporary theme. Elements of street
furniture may comprise seating, lighting,
signage and litter management. The layout
of street furniture can be used to create
strong visual effects within a city
environment.
Examples:
• Benches and seats
• Cast iron seating
Paving
They can be obtained in a wide variety
of colours and finishes.
Types:
• Concrete paving stones
They are seen as a cost effective
alternative to traditional clay block
pavers, especially if large numbers are
required for driveway and access road
construction. In industrial
environments reinforced concrete is
favoured for access roads and loading
bays to take the strain of heavy goods
vehicles.
• Tarmac
It can also be used to cover large
areas, such as car parks, as it has the
ability to accommodate small
settlements without cracking.
Specialist road surfacing contractors
will be able to advise on specifications
to withstand intended usage.
Hardstanding areas within residential
garden areas may need to be more
aesthetically pleasing.
To fulfil this requirement products
such as timber decking have been
developed to provide eye catching
functional features within gardens.
Wooden decking can be constructed
to suit most situations with anti slip
surfaces available, along with
accompanying handrails
and balustrades.
Patios, also suited to garden
locations, may typically be
constructed from concrete or
concrete paving slabs.
Landscaping
19
4.0 Foundation
20
The foundation is the substructure constructed
below or partly below the surface of the
ground. It anchors the superstructure by
distributing the load safely into the ground.
Settlement is the downward compression of the
soil due to the load of the building on the
foundation. Therefore the foundation is
designed so as to limit the settlement and make
it uniform.
4.0 Introduction to Foundation
Uniform settlement Tipping settlement Differential settlement
Foundation system
Ground
Foundation
Building
Factors considered when choosing foundation
types:
1. Load of building
2. Ground conditions
3. Types of soil
4. Types of structure in neighbourhood
21
4.0 Types of Foundation
Pile foundation
This one takes the load of the
building through made-up ground
or weak soil to load bearing strata.
Building loads is transferred to the
beam through ground beams.
Raft foundation
This reinforced foundation
distributes the load over the whole
building area reducing the load per
unit area. Raft foundations are
used where building loads are high
or when ground conditions are
poor
Reasons for using this foundation.
- The ground is quite weak and
in poor condition
- The buildings are 3 storey high
which makes it heavy,
therefore requiring a raft
foundation to distribute the
load uniformly on the weak
ground.
Reasons for using this foundation.
- This is used in sloppy areas of the site
- Best foundation to hold the load of the
whole building on the slope having a
ground which is also weak.
22
Pile foundation
4.1 Pile Foundation (from site visit)
Pile foundation is used at the
slopes of the hill. It is more
suitable for this terrain because
the soil here is quite soft and
weak. The load is also well
distributed and thus keeping the
building stable and well
balanced.
65 cm 65 cm
160 cm
160 cm
130 cm
111 cm
130 cm
Pile cap
Column
Pile
23
4.1 Pile Foundation construction process (from site visit)
1. The area where the foundation
will be is excavated.
2. Borehole is drilled using
an auger
3. The reinforcement cage is
placed inside the borehole and
then filled with concrete
4. The reinforcement of the pile
cap is then placed inside. There is
also the reinforcement for the
column attached to it
5. Formworks are placed around,
and it is then filled with concrete
6. The column is also finished using
the same way and then the pile
cap is covered with soil
Auger
Borehole
24
4.1 Solid Slab Raft Foundation (from site visit)
Raft foundation
Raft foundation is used on the
flat surface.
Upper reinforcement
Upper reinforcement
Hairpin bar
Plastic spacer
25
4.1 Raft Foundation construction process (from site visit)
The ground is excavated 40 cm
deep and then levelled
Wood is used as the formwork
to hold the concrete in shape
Concrete is then poured into the
formwork, levelled and then left
to dry.
15 cm
40 cm
A compacted hardcore layer
(Used as solid working base) and
a blinding layer (Used to prevent
wet concrete from running
down the hardcore) is added
inside
Reinforcements are added. This
will give more strength to the
foundation
Compacted hardcore
15 cm thick
Sand blinding
Steel mesh
Steel bar
Concrete
Brace
Vertical
Wood formwork
Reinforcement
Then the soil is added to fil
the gap between the
foundation and the soil
40 cm
Levelled ground
Ground beam
Wood formwork
26
Original slope
4.1 Stepped Raft Foundation construction process (from site
visit)
Hard core layer
Levelled groundThe slope is excavated into steps
which are then levelled. This is
done so as to get flat surfaces
instead of a slope
The surface is then covered with
compacted hardcore and a
blinding layer
The reinforcements which
consists of steel meshes and
steel bars are added.
The wood formworks are placed
and concrete is poured inside.
Blinding layer
Steel mesh
Steel bar
Wood formwork
Concrete
50 cm
27
5.0 Superstructure
28
SUPERSTRUCTURE
• Superstructure of a building is the portion of the structure above the foundation. It provides the necessary utility of the building with
comfort, structural safety, ventilation, etc.
SUPERSTRUCTURES IN OUR SITE
• Beam
1. Simply supported beam
2. Fixed beam
3. Cantilever beam
4. Continuous beam
• Columns
• Slab
• walls
• staircase
29
BEAM
• Beam is the horizontal member of a structure, carrying transverse loads. Beam is rectangular in cross-section.
Beam carry the floor slab or the roof slab. Beam transfer all the loads including its self-weight to the columns or
walls.
1. Fix the
reinforcement bar of
the beam
2.Fix the wooden
framework for the
concrete beam and
pour the concrete
3.Let it dry up and
remove the
formwork and you
have your rcc beam
CONSTRUCTION OF A RCC BEAM
• The beam in the basement of
our building is attached to
the foundation slab.
• For the ground floor, 1ST and
2nd floor they cast the beam
with the slab since it was not
possible to cast the slab later.
• The ground, 1st and 2nd floor
beam rest on the various
collumns on the basement,
ground and 1st floor
respectively.
• The 2nd floor beam is cast
with the roof slab at our site.
30
DIFFERENT KINDS OF BEAMS AT OUR SITE
SIMPLY SUPPORTED BEAM
FIXED BEAM
CONTINUOUS BEAM
CANTILIVER BEAM
31
COLUMNS• Columns is a vertical structural member. It transmits the load from ceiling/roof slab and beam, including its self-weight to
the foundation.
• Columns may be subjected to a pure compressive load. R.C.C columns are the most widely used now days.
Fix the
reinforceme
nt bars for
the
columns
Built the wooden
form work around
the reinforcement
and pour concrete
and leave it to dry
Remove the wooden
form work after the
mixture dries and
there we get our
column
CONSTRUCTION OF A RCC COLUMN
Section of
a RCC
column
32
The columns of
the basement
has its
reinforcements
coming from the
foundation
The reinforcements of the
columns of the ground
floor run from the
columns of the basement
they are smaller in
dimensions compared to
the columns in the
basement yet have the
same center.
The reinforcements of
the columns of the first
floor run from the
columns of the ground
floor, they are smaller in
dimensions compared
to the ground floor yet
have the same center
The reinforcements of the
columns of the second floor
run from the columns of the
first floor, they are smaller in
dimensions compared to the
first floor with the same center.
We even see that in this floor
the numbers of columns also
reduce since it is the last floor
and has no load of further
floors
33
5.2 Slab
Type of slab used in our site:
Two way slab (with beam)
This type of slab is supported on four sides by beams and columns. This
is because the ratio of length to width is less than two. The load is
carried in two directions. The reinforcement is arranged to support the
slab in two directions.
Advantage:
• Framing of beams with column
• Versatile
Disadvantage:
• Beams dropping from ceiling are visible
The formwork is assembled over
the columns and is supported by
scaffoldings.
More wood is added to the
formwork so as to look like this.
Then the reinforcement cage
for the beam is placed inside
the gaps
Steel meshes are inserted,
this will give strength to the
slab.
Concrete is then poured inside
and left to dry.
Section cut
45 cm
15 cm
Construction process:
34
5.3 Walls
Wall is the vertical plane of a building, it defines an enclosed space or acts as a division. Walls
are made to provide shelter from weathering, safety and privacy. It can be either load bearing
or non-load bearing. The types of structural walls found on the building are: building wall,
partition wall, party wall, and retaining wall.
Types of building materials used : Masonry bricks and Reinforced concrete.
Clay brick sand brick
R.C wall Concrete retaining wallR.C wall
Clay brick
35
36
Reinforced concrete wood formwork
37
5.4 Staircase
38
5.4 Staircase
39
Staircase
A staircase is a construction designed to link a large vertical
distance by dividing it into smaller vertical distances which
is called steps. It allows easy movement between the
different levels of design.
Aspect that should be considered when designing a
staircase is the placement of stairs, ease to travel and most
importantly the safety. Also, the design of a staircase should
take proper consideration of the width, landings, handrail,
guardrails, treads, rises, and nosing which are the
requirements of a staircase.
Concrete staircase
Concrete staircase are often specified
for their strength, durability, the
protection, food resistance and sound
reduction properties
Concrete Quarter landing staircase
Quarter Landing Stairs represent a variety of straight stairs, which
also include a landing. But here the landing is needed to change a
direction of the flight by 90 degrees and at the same time it serves
as a place for rest when moving. The landing may change its
position in the flight from its beginning and up to its end. Staircases
of this type are more convenient and safe than straight staircases
37
Advantages of quarter landing stairs shaped Stairs:
1. Quarter landing stairs can be more visually interesting.
2. They provide a visual barrier between floors so they can add some privacy.
3. Also quarter landing stairs can help somewhat with sound transmission between floors if the stairs are contained within
walls.
4. Some believe they are safer than straight stairs as the central landing reduces the number of treads one could fall in a
given flight.
5. The landing can provide a place to stop and rest while ascending.
6. They can be located in a corner of a room if this works better for your design.
Disadvantages of quarter landing stairs shaped Stairs:
1. Quarter landing stairs are a bit more difficult to build.
2. A support is typically required for the landing in a quarter landing stairs. Often this is built into the surrounding walls
so it goes unnoticed. In modern dwellings however it is usually desirable to open up the space leaving the stair
structure visible. In these cases the supporting structure can be visually minimized by taking advantage of the strength
of steel to create slim supporting members. Through careful engineering,it is possible to eliminate the landing support
all together.
3. Handrails for these types of stairs require more skill and planning to construct.
4. In climates where basements are used, stairs are typically stacked over each other for efficient use of space. Since
basements are often used for storage, large items can be difficult to move in and out of the basement.
38
procedure of constructing concrete staircase
step 1 : calculate the stairs dimension
measure the height of one floor to
the other. Divide the height with 7
inches (standard measurement of
rise) to get the number of steps.
measure the horizontal distance the
staircase will span and me sure the
width of staircase from left to right.
step 2 : determine the foundation
dimension
the dimension of the staircase’s
foundation are the total length of run
and total width of staircase as
measured in step 1
step 3 : build the formwork around
the reinforcement using either
plywood or framing lumber to build
the form. Cut the side forms
according to the tread and riser
calculations.
step 4 : prepare the concrete
produce sufficient and well-mixed
mortar with a portable cement
mixer.
step 5 : pour the mortar
start at the bottom and pour one
step at a time. make sure the
mortars are spread evenly. use a
spade to remove the trapped air
bubbles.
step 6 : add finishing touches
use a simple wood float to clean
and smooth the surface of the
mortars.
step 7 : leave and wait
spray the stairs with cur in
compound and cover it with burlap.
after a week, remove from the
lumber.
39
Rectangle stainless steel handrails
50 x 25mm and 50 x 10mm rectangle stainless steel tube and
fittings can be used to create a modern stainless steel rail which is
suitable for both internal and external use.
Advantages of stainless steel handrail
1. Easy to clean
2. The finishing (satin or mirror) look valuable
3. Not easy rusty
4. Not easy contaminated
5. Very strong in structure
6. Stainless steel look simple but luxury
7 .Stainless steel easy match to some other material such as glass and wood
8. Stainless steel have more accessories to fit with
9. Stainless steel is majority part fabricating onsite, instead of fabricating offsite at the factories
then go onsite to install. Therefore, the job done is more precisely.
10. handrail using stainless steel material to fabricate always look better than other materials as
no requirement of painting or powder coating as steel or aluminium. Fabricator can polish onsite
when install the job. Even some balustrades need to fit or re-fabricated, then the fabricator can
easily re-polish the finishing.
1. higher cost compare to other material.
2. require higher skill to weld and must have proper skill of polishing the stainless steel.
3. need properly maintain when it install at outside.
4. it is not easy to distinguish the material of stainless steel.
Disadvantages of stainless steel handrail
40
6.0 Windows and doors
Hinged: side hung
Types of windows
Fixed window
Installation of windows:
The above picture shows the
frame fixed onto the walls after
being plastered and skim
coated.
Then the aluminium window
frames are fixed onto it.
Installation of doors:
The frame of the door is fitted
The opening made into the
wall. Then the door is fixed on
This frame using a hinge.
Type of door on site
Side hung timber flush door
44
7.0 Roofs
45
Roof
Roofing Introduction
Flat roof has a pitch of less than 5’. However, flat roof
structures are suitable for shallow pitched roof (up to
25’), although the building materials must be
adequately protected against slippage. The top section
of the flat roof is the roof covering, known as the roof
weatherproofing or waterproofing.
Layers of structural elements
Flat roofs can have various functional layers, which
must be matched to each other. It is essential that
the layers sequence provide adequate insulation
against heat and noise. Building materials must be
compatible with each other.
-under course
-bonding course
-leveling course
-separating course
-vapor barrier
-thermal insulation
-vapor pressure compensation course
-roof waterproofing
-filter course
-surface protection
-accessible coverings
Structural element courses
according to the guidelines laid
down by the Zentrolverband des
Deutshen Dachdeckerhandwerks:
Flat roof guidelines.
46
Roof edging
Flat roof can be finished as projecting flat roofs at the
point they meet the façade, or with an upstand. Current
practice is to finish the roof with a parapet or an edge
trim but we are focusing on roof edge with parapet as
we can see in our site
Roof Structure: roof waterproofing, single course,
vapor pressure, compensation course,
thermal insulation, vapor barrier, leveling course
preliminary coating, reinforced concrete
slab
Wall structure: façade slabs, air space, thermal
insulation calcium silicate mansonary
47
Components for roof edge with parapet
48
Flat roof is not perfectly flat , the
rafters are laid at slight angle to allow
the rain water to flow. Sheathing and
roofing are applied to the top of the
rafters
The hip roof slopes at all sides,
results in an even overhang all
around the building. This roof is
popular due to its low maintenance
Curved roof is known for their
aesthetic appeal. A curved roof also
may help to reduce resistance to wind
Most of the roofs in Malaysia are
flat roof and it is slowly becoming
popular compared to hip roof
Famous for its low maintenance
but users think that it is too old
fashioned
This kind of roof is not suitable or
housing or commercial
Flat roofs are quicker to apply thus
saves time and money
Hip roof takes more time to apply
thus cost more money but the
maintenance is low
Even more time consuming to build
curved panel roof
Comparison between flat roofs and other types of roof
49
Summary
To conclude throughout all these site visit we have definitely learnt a lot from this experience. From basic structure
theories to being able to indentify construction flaws. We visited one site in Kuala Lumpur (Desa Petaling , Desa hill
villa ) it had 165 unit at different construction levels we saw houses at extraction level, foundation level, basic
framework level, super structures level, completion level and with the final touches. Through this project we
understood how one should go about contracting a three storey house.
We learnt that to start any project we first need to do external works that is setting out boundaries surveying the land
setting out earth works. The next stage is site safety and security. After all this on the basis of land survey we excavate
the land for the foundation. We learnt about two different kinds of foundation at our site i.e. pile foundation and raft
foundation.
After setting out the foundation we studied the placing and construction of the various superstructures i.e. the columns,
beams, slabs, staircase and wall. Later followed by the construction of the roof. After this the building is checked for
water proofing .
After that we set up the services and the electrical work and fill up the walls .
The stage after this is the placing and installation of the doors and windows. We studied the different kinds of windows
and doors at our site. After all this we see a final wall finishing that consists of plastering followed by smoothing and
leveling which is followed by painting.
After this we need to add up the final touches to the house that is the final paint coat the doors and window knobs
furniture and that is how we construct or house.
507
Reference
• Engineering intro. Rollers.
http://www.engineeringintro.com/all-about-construction-equipments/rollers-types-of-roller-characteristics/
• BuildingHow. Raft foundation.
http://www.buildinghow.com/en-us/Products/Books/Volume-A/The-reinforcement-II/Foundation/Raft-foundation
• King Saud University. Two way slabs.
http://faculty.ksu.edu.sa/charif/Documents/Two%20way%20slabs.pdf
• External wall construction.
http://www.bca.gov.sg/professionals/iquas/..%5CIquas%5Cgpgs%5CWEWall%5CWEWChpt5.pdf
• http://www.buildingscience.com/documents/digests/bsd-102-understanding-attic-ventilation
• http://constructionstudiesq1.weebly.com/uploads/1/6/4/9/16490624/1364418771.jpg
• http://www.greenspec.co.uk/images/web/refurb/timflatroof/warmtimbflatroof.png
• Tanja Brotruck, 2007 Birkhauser, Roof Construction, Publishers for Architecture, P.O. Box133,
CH-4010 Basel, Switzerland.
• Barry’s introduction to building construction. Stephen Emmitt, Christopher A. Gorse. Jan 2010
• Different types of beams. http://www.slideshare.net/mbrsalman/civil-engineering-beamscolumns
• Construction of columns and beams from site
Everything else from site information
48

Mais conteúdo relacionado

Mais procurados

Bcon final
Bcon finalBcon final
Bcon finaldicky177
 
Building construction ii report (1)
Building construction ii report  (1)Building construction ii report  (1)
Building construction ii report (1)Chong jiayi
 
BUILDING CONSTRUCTION PROJECT 1
BUILDING CONSTRUCTION PROJECT 1BUILDING CONSTRUCTION PROJECT 1
BUILDING CONSTRUCTION PROJECT 1Cryslyn Tan
 
BUILDING CONSTRUCTION 1
BUILDING CONSTRUCTION 1BUILDING CONSTRUCTION 1
BUILDING CONSTRUCTION 1Alexis Wei
 
Building construction I project 1 report
Building construction I project 1 reportBuilding construction I project 1 report
Building construction I project 1 reportAmos Tan
 
Project 01 - Experiencing Construction
Project 01 - Experiencing ConstructionProject 01 - Experiencing Construction
Project 01 - Experiencing ConstructionLek Yuen
 
GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...
GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...
GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...Firdaurs Abdullah
 
Building Construction
Building ConstructionBuilding Construction
Building ConstructionWilden How
 
Final slides
Final slidesFinal slides
Final slideshongbinng
 
Bcon revised
Bcon revisedBcon revised
Bcon revisedKen Wong
 
Building Construction II Report
Building Construction II ReportBuilding Construction II Report
Building Construction II ReportBolin Loong
 
Building Construction 1: Project 1
Building Construction 1: Project 1Building Construction 1: Project 1
Building Construction 1: Project 1KohSungJie
 
Building Construction Report
Building Construction ReportBuilding Construction Report
Building Construction ReportSheau Hui Tan
 

Mais procurados (15)

Bcon final
Bcon finalBcon final
Bcon final
 
Building construction ii report (1)
Building construction ii report  (1)Building construction ii report  (1)
Building construction ii report (1)
 
BUILDING CONSTRUCTION PROJECT 1
BUILDING CONSTRUCTION PROJECT 1BUILDING CONSTRUCTION PROJECT 1
BUILDING CONSTRUCTION PROJECT 1
 
BUILDING CONSTRUCTION 1
BUILDING CONSTRUCTION 1BUILDING CONSTRUCTION 1
BUILDING CONSTRUCTION 1
 
Building construction I project 1 report
Building construction I project 1 reportBuilding construction I project 1 report
Building construction I project 1 report
 
B.Con Project 1
B.Con Project 1B.Con Project 1
B.Con Project 1
 
Project 01 - Experiencing Construction
Project 01 - Experiencing ConstructionProject 01 - Experiencing Construction
Project 01 - Experiencing Construction
 
GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...
GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...
GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...
 
Building Construction
Building ConstructionBuilding Construction
Building Construction
 
Final slides
Final slidesFinal slides
Final slides
 
Bcon revised
Bcon revisedBcon revised
Bcon revised
 
Bcon
BconBcon
Bcon
 
Building Construction II Report
Building Construction II ReportBuilding Construction II Report
Building Construction II Report
 
Building Construction 1: Project 1
Building Construction 1: Project 1Building Construction 1: Project 1
Building Construction 1: Project 1
 
Building Construction Report
Building Construction ReportBuilding Construction Report
Building Construction Report
 

Destaque

İmam gazali i̇lahi nizam
İmam gazali   i̇lahi nizamİmam gazali   i̇lahi nizam
İmam gazali i̇lahi nizamSelçuk Sarıcı
 
2016 Ward Newsletter
2016 Ward Newsletter2016 Ward Newsletter
2016 Ward NewsletterKim Phan
 
Geraldine valencia bedoya 8 2 trabajo final de word
Geraldine valencia bedoya 8 2 trabajo final de wordGeraldine valencia bedoya 8 2 trabajo final de word
Geraldine valencia bedoya 8 2 trabajo final de wordgeralvalencia
 
Newsletter Mayo LupaMotors
Newsletter Mayo LupaMotorsNewsletter Mayo LupaMotors
Newsletter Mayo LupaMotorsLupaMotors
 
Brasil vive desindustrialização
Brasil vive desindustrializaçãoBrasil vive desindustrialização
Brasil vive desindustrializaçãoFabricio Rocha
 
Katalog
KatalogKatalog
Katalogoanblc
 
P'ti mag - 11.12.15
P'ti mag - 11.12.15P'ti mag - 11.12.15
P'ti mag - 11.12.15Marsatwork
 
Huesos del cuerpo humano
Huesos del cuerpo humanoHuesos del cuerpo humano
Huesos del cuerpo humanoChristian Supe
 
Foro, Webquest, Wesblesson y el correo Electronico
Foro, Webquest, Wesblesson y el correo ElectronicoForo, Webquest, Wesblesson y el correo Electronico
Foro, Webquest, Wesblesson y el correo ElectronicoYelissa Cabrera Caba
 
Innovazione e tecnologia nello studio professionale
Innovazione e tecnologia nello studio professionaleInnovazione e tecnologia nello studio professionale
Innovazione e tecnologia nello studio professionaleroberto spaggiari
 
Treatment related complications from Chemothearpy
Treatment related complications from ChemothearpyTreatment related complications from Chemothearpy
Treatment related complications from ChemothearpyNaglaa Mahmoud
 
เฉลย O net 53
เฉลย O net 53เฉลย O net 53
เฉลย O net 53visuttithep
 

Destaque (20)

İmam gazali i̇lahi nizam
İmam gazali   i̇lahi nizamİmam gazali   i̇lahi nizam
İmam gazali i̇lahi nizam
 
Corso gNe 2016
Corso gNe 2016Corso gNe 2016
Corso gNe 2016
 
2016 Ward Newsletter
2016 Ward Newsletter2016 Ward Newsletter
2016 Ward Newsletter
 
Presentacion curso computacion
Presentacion curso computacionPresentacion curso computacion
Presentacion curso computacion
 
Geraldine valencia bedoya 8 2 trabajo final de word
Geraldine valencia bedoya 8 2 trabajo final de wordGeraldine valencia bedoya 8 2 trabajo final de word
Geraldine valencia bedoya 8 2 trabajo final de word
 
Silabo rshd
Silabo rshdSilabo rshd
Silabo rshd
 
Newsletter Mayo LupaMotors
Newsletter Mayo LupaMotorsNewsletter Mayo LupaMotors
Newsletter Mayo LupaMotors
 
Brasil vive desindustrialização
Brasil vive desindustrializaçãoBrasil vive desindustrialização
Brasil vive desindustrialização
 
Katalog
KatalogKatalog
Katalog
 
P'ti mag - 11.12.15
P'ti mag - 11.12.15P'ti mag - 11.12.15
P'ti mag - 11.12.15
 
Recursos y medios
Recursos y mediosRecursos y medios
Recursos y medios
 
Huesos del cuerpo humano
Huesos del cuerpo humanoHuesos del cuerpo humano
Huesos del cuerpo humano
 
Foro, Webquest, Wesblesson y el correo Electronico
Foro, Webquest, Wesblesson y el correo ElectronicoForo, Webquest, Wesblesson y el correo Electronico
Foro, Webquest, Wesblesson y el correo Electronico
 
Innovazione e tecnologia nello studio professionale
Innovazione e tecnologia nello studio professionaleInnovazione e tecnologia nello studio professionale
Innovazione e tecnologia nello studio professionale
 
4 dudas existenciales sobre la eficiencia energética
4 dudas existenciales sobre la eficiencia energética4 dudas existenciales sobre la eficiencia energética
4 dudas existenciales sobre la eficiencia energética
 
Treatment related complications from Chemothearpy
Treatment related complications from ChemothearpyTreatment related complications from Chemothearpy
Treatment related complications from Chemothearpy
 
เฉลย O net 53
เฉลย O net 53เฉลย O net 53
เฉลย O net 53
 
Dissertation
DissertationDissertation
Dissertation
 
Reitz Football
Reitz FootballReitz Football
Reitz Football
 
Factura 517
Factura 517Factura 517
Factura 517
 

Semelhante a Report 150720083151-lva1-app6892

B.con slide
B.con slideB.con slide
B.con slideTeh Yang
 
final report last.pdf
final report last.pdffinal report last.pdf
final report last.pdfwzhen77
 
Construction site
Construction siteConstruction site
Construction siteTimun Loh
 
Building construction 1 experiencing construction (zone innovation park klang)
Building construction 1 experiencing construction (zone innovation park klang)Building construction 1 experiencing construction (zone innovation park klang)
Building construction 1 experiencing construction (zone innovation park klang)Chow Hong Da
 
Experiencing Construction
Experiencing ConstructionExperiencing Construction
Experiencing ConstructionSNLim125
 
Building Construction 1 - Experiencing Construction
Building Construction 1 - Experiencing ConstructionBuilding Construction 1 - Experiencing Construction
Building Construction 1 - Experiencing Constructionjisunfoo
 
Demolition of building and blasting equipment
Demolition of building and blasting equipmentDemolition of building and blasting equipment
Demolition of building and blasting equipmentChetan Karwa
 
site visit report (final)
site visit report (final)site visit report (final)
site visit report (final)Jia Hong Mui
 
Civil Engineering Technology (Fawzan Fahry)
Civil Engineering Technology  (Fawzan Fahry)Civil Engineering Technology  (Fawzan Fahry)
Civil Engineering Technology (Fawzan Fahry)FAwzan Mohamad
 
Introduction to Underground Structures _ Building Structures
Introduction to Underground Structures _ Building StructuresIntroduction to Underground Structures _ Building Structures
Introduction to Underground Structures _ Building Structureshegdenisarga23
 
Site visit report
Site visit reportSite visit report
Site visit reportDoreen Yeo
 
Ctw site report(pg 1 to 8, 14)
Ctw site report(pg 1 to 8, 14)Ctw site report(pg 1 to 8, 14)
Ctw site report(pg 1 to 8, 14)Chin Tze Wei
 
Ct2 presentation
Ct2 presentationCt2 presentation
Ct2 presentationqayyum23
 
Project SlideShare
Project SlideShareProject SlideShare
Project SlideShareYung Kai
 
BUILDING CONSTRUCTION
BUILDING CONSTRUCTION BUILDING CONSTRUCTION
BUILDING CONSTRUCTION Eric Lo
 

Semelhante a Report 150720083151-lva1-app6892 (20)

B.con slide
B.con slideB.con slide
B.con slide
 
B.con slide
B.con slideB.con slide
B.con slide
 
final report last.pdf
final report last.pdffinal report last.pdf
final report last.pdf
 
Construction site
Construction siteConstruction site
Construction site
 
Building construction 1 experiencing construction (zone innovation park klang)
Building construction 1 experiencing construction (zone innovation park klang)Building construction 1 experiencing construction (zone innovation park klang)
Building construction 1 experiencing construction (zone innovation park klang)
 
MCB Final report
MCB Final reportMCB Final report
MCB Final report
 
Ez
EzEz
Ez
 
BCON PJT 1
BCON PJT 1BCON PJT 1
BCON PJT 1
 
Experiencing Construction
Experiencing ConstructionExperiencing Construction
Experiencing Construction
 
Building Construction 1 - Experiencing Construction
Building Construction 1 - Experiencing ConstructionBuilding Construction 1 - Experiencing Construction
Building Construction 1 - Experiencing Construction
 
Demolition of building and blasting equipment
Demolition of building and blasting equipmentDemolition of building and blasting equipment
Demolition of building and blasting equipment
 
site visit report (final)
site visit report (final)site visit report (final)
site visit report (final)
 
Civil Engineering Technology (Fawzan Fahry)
Civil Engineering Technology  (Fawzan Fahry)Civil Engineering Technology  (Fawzan Fahry)
Civil Engineering Technology (Fawzan Fahry)
 
Introduction to Underground Structures _ Building Structures
Introduction to Underground Structures _ Building StructuresIntroduction to Underground Structures _ Building Structures
Introduction to Underground Structures _ Building Structures
 
Site visit report
Site visit reportSite visit report
Site visit report
 
Ctw site report(pg 1 to 8, 14)
Ctw site report(pg 1 to 8, 14)Ctw site report(pg 1 to 8, 14)
Ctw site report(pg 1 to 8, 14)
 
Ct2 presentation
Ct2 presentationCt2 presentation
Ct2 presentation
 
Project SlideShare
Project SlideShareProject SlideShare
Project SlideShare
 
BUILDING CONSTRUCTION
BUILDING CONSTRUCTION BUILDING CONSTRUCTION
BUILDING CONSTRUCTION
 
Final slides
Final slidesFinal slides
Final slides
 

Mais de Sumit Modi

Seismicretrofittingtechniques 111111013537-phpapp01
Seismicretrofittingtechniques 111111013537-phpapp01Seismicretrofittingtechniques 111111013537-phpapp01
Seismicretrofittingtechniques 111111013537-phpapp01Sumit Modi
 
Seismicretrofitmethods 100415085521-phpapp01
Seismicretrofitmethods 100415085521-phpapp01Seismicretrofitmethods 100415085521-phpapp01
Seismicretrofitmethods 100415085521-phpapp01Sumit Modi
 
Recyledaggregates 140110194229-phpapp01
Recyledaggregates 140110194229-phpapp01Recyledaggregates 140110194229-phpapp01
Recyledaggregates 140110194229-phpapp01Sumit Modi
 
Prevent the application has failed to start because its side by-side config...
Prevent  the application has failed to start because its  side by-side config...Prevent  the application has failed to start because its  side by-side config...
Prevent the application has failed to start because its side by-side config...Sumit Modi
 
Plume classification
Plume classificationPlume classification
Plume classificationSumit Modi
 
Civilproject 130806034227-phpapp01
Civilproject 130806034227-phpapp01Civilproject 130806034227-phpapp01
Civilproject 130806034227-phpapp01Sumit Modi
 
Earthquakeresistantlowrisebuilding 140428000944-phpapp02
Earthquakeresistantlowrisebuilding 140428000944-phpapp02Earthquakeresistantlowrisebuilding 140428000944-phpapp02
Earthquakeresistantlowrisebuilding 140428000944-phpapp02Sumit Modi
 

Mais de Sumit Modi (8)

Seismicretrofittingtechniques 111111013537-phpapp01
Seismicretrofittingtechniques 111111013537-phpapp01Seismicretrofittingtechniques 111111013537-phpapp01
Seismicretrofittingtechniques 111111013537-phpapp01
 
Seismicretrofitmethods 100415085521-phpapp01
Seismicretrofitmethods 100415085521-phpapp01Seismicretrofitmethods 100415085521-phpapp01
Seismicretrofitmethods 100415085521-phpapp01
 
Recyledaggregates 140110194229-phpapp01
Recyledaggregates 140110194229-phpapp01Recyledaggregates 140110194229-phpapp01
Recyledaggregates 140110194229-phpapp01
 
Prevent the application has failed to start because its side by-side config...
Prevent  the application has failed to start because its  side by-side config...Prevent  the application has failed to start because its  side by-side config...
Prevent the application has failed to start because its side by-side config...
 
Plume classification
Plume classificationPlume classification
Plume classification
 
Ejaz 2
Ejaz 2Ejaz 2
Ejaz 2
 
Civilproject 130806034227-phpapp01
Civilproject 130806034227-phpapp01Civilproject 130806034227-phpapp01
Civilproject 130806034227-phpapp01
 
Earthquakeresistantlowrisebuilding 140428000944-phpapp02
Earthquakeresistantlowrisebuilding 140428000944-phpapp02Earthquakeresistantlowrisebuilding 140428000944-phpapp02
Earthquakeresistantlowrisebuilding 140428000944-phpapp02
 

Último

What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catcherssdickerson1
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncssuser2ae721
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 

Último (20)

What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 

Report 150720083151-lva1-app6892

  • 1. BUILDING CONSTRUCTION-1SUB CODE- ARC 1523 ASSIGNMENT 1 - EXPERIENCING CONSTRUCTION (EXPERIENCING, DOCUMENTING AND ANALYSING THE CONSTRUCTION PROCESS) TUTOR – Ar. ALICE LIM LI YUEN
  • 2.
  • 3. Content 1.0 Introduction and Group members detail. (SI*) 1.1 Introduction to site 2.0 Site and Safety (MM*) 2.1 Plants and Machinery 3.0 External Work (SV*) 4.0 Foundation (MNA*) 4.1 Foundation type and construction process (from site visit) 5.0 Superstructure (from site visit and reference) 5.1 Beam and Column (SI*) 5.2 Slab (MNA*) 5.3 Wall (PZ*) 5.4 Staircase (JE*) 6.0 Doors and Windows (PZ*) 7.0 Roof (LZH*) 7.1 Roof type and construction process (from site visit) 8.0 Summary 8.1 References (SI*) Saurabha Iyer (MM*) Muhammad Mubarak (SV*) Saravanan Vytelingum (MNA*) Muhammad Nabeel Ali Joomun (PZ*) Prisha Zenia (JE*) Jonathan Edwards (LZH*) Lim Zhi Hong Page 1 2-6 7-8 9-16 17-24 25 26-30 31 32-34 35-40 41 42-46 47 48
  • 4. Introduction to site • Location – Megan Salak park, Jalan 1/125E , Desa Pedaling ,57100 Kuala Lumpur • date of approval- 11 July 2013 • Date of completion – January 2016 • Developer- Chico Development Sdn Bhd • Architect- Akitek Akiprima SDN BHD • Landscape architect- Primeclass Landscaping SDN BDH • Contractor- Suncity Trading and Construction SDN BHD • House type- 3story semi d • Land tenure – freehold • 115 units Introduction to the group members Saravanan Vytelingum 0320563 Muhammad Nabeel Ali Joomun 0320583 Muhammad Mubarak 0319984 Saurabha Iyer 0320569 Prisha Zenia 0320762 Jonathan Edwards Woe 0320458 Lim Zhi Hong 0304547 4
  • 6. Importance of following safety site rules Accident rates are higher in construction sites because people doesn’t pay much attention to the surrounding and the warning signboards that is placed outside of the construction site. Personal Protective Equipment (PPE) • All refers to protective clothing, helmet, goggles or other garments or equipment designed to protect the wearer’s body from injury. • Staffs and workers must wear and use PPE as appropriate. • Sub-con and their workers must not wear short pants/slipper to work. 6
  • 7. Site safety rules: • To prevent any injuries on the head as it is the most dangerous part. • To prevent dust particals from the construction site to draw on the head. • To prevent from any ear damage due to drilling and construction work Foot protection should be worn in this area Safety helmets must be worn: Hearing protection must be worn • To prevent danger of foot injuries due to falling or rolling objects or objects piercing the sole and where such employee’s feet are exposed to electrical hazards No person who is under the influence of alcohol or drugs are allowed in the site • as a drunk person may not be conscious , it may be dangerous as they could walk to buildings which are not complete which are full of metal bars therefore it will be dangerous • To reduce electrical shock hazard when near exposed electrical conductors which could contact the head. No unauthorized entry • All visitors must report to the office • Management or workers may not be responsible for any accidents. 7
  • 8. High visibility clothing must be worn in this area • So that when to construction work is going on’ it will be easier to be noticed by the bright color of the clothing to prevent any accidents from happening Safety googles must be worn. • The dust particles at the site may be harmful to the eye therefore by wearing a safety google it can prevent the dust from entering the eye. Eg flying particles, molten metals, liquid chemicals or acids. First aid box • First aid equipment is kept in the site managers office as it is easier and faster access in case of emergency Children must not play in the site • When the construction activity is going on, it will be dangerous for the children as any accidents might happen such as getting hit by vehicles or falling object Hand glove must be worn • to protect the employee hand from bruise • To protect hands from hazardous substance Scaffolding platform • Helps to minimize the risk of fall when a worker is doing the construction work high up the building 8
  • 9. Reasons for using construction plant. • High output - Complete work volume in time. • Quality work - Accuracy and consistency. • Economy - Cost effectiveness. • Nature of work - Dangerous if do the task manually. TYPES OF PLANT AND EQUIPMENT 1. Excavating and earth- moving equipment: • Backhoe-loaders • Excavators • Loaders • Trucks and hauling equipment • Vacuum excavators 2. Lifting and vertical transportation equipment • Mobile cranes • Tower cranes • Goods hoists • Passengers hoists 3) Bulldozers 4) Scrapers 5) Concrete plant and equipment • Concrete trucks • Concrete mixing plant • Concrete pumps Plants and Machinery 9
  • 10. Backhoe-loader Backhoe loader is engineering vehicle, which consist of a tractor, fitted with a shovel or bucket on the front and a small backhoe on the back. Uses: • Digging shallow excavations • Digging trenches • General grading • Lifting loads • Loading and carrying materials Excavators Uses of excavators: • Excavating below or above natural surface of ground on which machine rests. • Digging bigger trenches. • Digging pits for basements, • General grading work. • Loading onto haul units (dumper trucks) • Lifting Other uses: Excavator bucket can be replaced with a breaker or hammer turning the unit into a demolition machine. Construction equipment found on site 10
  • 11. Mobile crane • A full revolving superstructure mounted on a truck with multi section- telescoping boom. • These cranes can travel on public roads between projects under own power with minimum or no dismantling and reassembling. • Therefore very suitable if a job requires crane utilization for a few hours to a couple of days. Uses: To hoist materials and machineries. Vibrating smooth wheel roller Vibratory road roller can be equipped with single drum or double drum. Uses: • Rolling aggregates • Compaction of clay and sand • Proof rolling of subgrades and in compacting asphalt pavements. 11
  • 13. • External works on our construction site are mainly: • Setting out • Signage • Site boundary • Temporary shelters • Earthworks • Drainage • Sloping 13
  • 14. Setting Out Starting period : Semptember 2013 Construction start : March 2014 Handing Over : January 2016 Site Area : 18 Hectares Functional external features may take the form of access requirements where security may be an issue. To enhance security on any project fencing could be used to separate the site from adjacent properties and land. Any from of fencing, whether it be full permimeter fencing or partial fencing installed at key areas of the site, can stop or cut down any unwanted pedestrian or vehicular access. The primary form of fencing present on our site is mainly metal hoardings placed moslty around the whole site boundary except around the hillside.Another form of protection at our site boundary would be the retaining wall (R.E Wall) or Retaining Concrete Wall (R.C Wall). Site boundary Retaining wall R.C wall Metal hoarding 14
  • 15. Storage of material and temporary shelters They are actually small housing shelters for storing site equipments and for construction workers to rest. 15
  • 16. Earthworks Earthworks are engineering works created through the moving or processing of parts of the earth's surface involving quantities of soil or unformed rock. The earth may be moved to another location and formed into a desired shape for a purpose. Much of earthworks involves machine excavation and fill or backfill. Excavation may be classified by type of material: • Topsoil excavation • Earth excavation • Rock excavation • Muck excavation - this usually contains excess water and unsuitable soil • Unclassified excavation - this is any combination of material types Excavation may be classified by the purpose: Stripping • Roadway excavation • Drainage or structure excavation • Bridge excavation • Channel excavation • Footing excavation • Borrow excavation • Dredge excavation • Underground Excavation Typical earthworks include roads, railway beds, causeways, dams, levees, canals, and berms. Other common earthworks are land grading to reconfigure the topography of a site, or to stabilize slopes. Earth-moving machines such as the loader, production trucks, the grader, the bulldozer, the backhoe, and the dragline excavator. 16
  • 17. Sloping One unique and very ingenios way of using waste concrete to prevent soil erosion and provide slope protection is by graniting.This method is implemeted by fitting pipes into the slopes to carry accumulated water from the top away while the face of the slope is sprayed with waste concrete from construction also helping to save on material cost. This method of sloping is aesthetically pleasing, economical and prevents materials wastage. 17
  • 18. Drainage Drainage is the natural or artificial removal of surface and sub-surface water from an area. The drainage system on the site is essential as it carries away waste water from the site to its respective destination. Civil engineers and construction managers work alongside architects and supervisors, planners, quantity surveyors, the general workforce, as well as subcontractors. Drainage options for the construction industry include: • Point drainage It intercepts water at gullies (points). Gullies connect to drainage pipes beneath the ground surface and deep excavation is required to facilitate this system. Support for deep trenches is required in the shape of planking, strutting or shoring. • Channel drainage It intercepts water along the entire run of the channel. Channel drainage is typically manufactured from concrete, steel, polymer or composites. The interception rate of channel drainage is greater than point drainage and the excavation required is usually much less deep. The surface opening of channel drainage usually comes in the form of gratings (polymer, plastic, steel or iron) or a single slot (slot drain) that runs along the ground surface (typically manufactured from steel or iron). 18
  • 19. Street Furniture Street furniture represents a large and diverse subcategory of external works. It can be used to create subtle themes within city centres, whether it be a traditional or contemporary theme. Elements of street furniture may comprise seating, lighting, signage and litter management. The layout of street furniture can be used to create strong visual effects within a city environment. Examples: • Benches and seats • Cast iron seating Paving They can be obtained in a wide variety of colours and finishes. Types: • Concrete paving stones They are seen as a cost effective alternative to traditional clay block pavers, especially if large numbers are required for driveway and access road construction. In industrial environments reinforced concrete is favoured for access roads and loading bays to take the strain of heavy goods vehicles. • Tarmac It can also be used to cover large areas, such as car parks, as it has the ability to accommodate small settlements without cracking. Specialist road surfacing contractors will be able to advise on specifications to withstand intended usage. Hardstanding areas within residential garden areas may need to be more aesthetically pleasing. To fulfil this requirement products such as timber decking have been developed to provide eye catching functional features within gardens. Wooden decking can be constructed to suit most situations with anti slip surfaces available, along with accompanying handrails and balustrades. Patios, also suited to garden locations, may typically be constructed from concrete or concrete paving slabs. Landscaping 19
  • 21. The foundation is the substructure constructed below or partly below the surface of the ground. It anchors the superstructure by distributing the load safely into the ground. Settlement is the downward compression of the soil due to the load of the building on the foundation. Therefore the foundation is designed so as to limit the settlement and make it uniform. 4.0 Introduction to Foundation Uniform settlement Tipping settlement Differential settlement Foundation system Ground Foundation Building Factors considered when choosing foundation types: 1. Load of building 2. Ground conditions 3. Types of soil 4. Types of structure in neighbourhood 21
  • 22. 4.0 Types of Foundation Pile foundation This one takes the load of the building through made-up ground or weak soil to load bearing strata. Building loads is transferred to the beam through ground beams. Raft foundation This reinforced foundation distributes the load over the whole building area reducing the load per unit area. Raft foundations are used where building loads are high or when ground conditions are poor Reasons for using this foundation. - The ground is quite weak and in poor condition - The buildings are 3 storey high which makes it heavy, therefore requiring a raft foundation to distribute the load uniformly on the weak ground. Reasons for using this foundation. - This is used in sloppy areas of the site - Best foundation to hold the load of the whole building on the slope having a ground which is also weak. 22
  • 23. Pile foundation 4.1 Pile Foundation (from site visit) Pile foundation is used at the slopes of the hill. It is more suitable for this terrain because the soil here is quite soft and weak. The load is also well distributed and thus keeping the building stable and well balanced. 65 cm 65 cm 160 cm 160 cm 130 cm 111 cm 130 cm Pile cap Column Pile 23
  • 24. 4.1 Pile Foundation construction process (from site visit) 1. The area where the foundation will be is excavated. 2. Borehole is drilled using an auger 3. The reinforcement cage is placed inside the borehole and then filled with concrete 4. The reinforcement of the pile cap is then placed inside. There is also the reinforcement for the column attached to it 5. Formworks are placed around, and it is then filled with concrete 6. The column is also finished using the same way and then the pile cap is covered with soil Auger Borehole 24
  • 25. 4.1 Solid Slab Raft Foundation (from site visit) Raft foundation Raft foundation is used on the flat surface. Upper reinforcement Upper reinforcement Hairpin bar Plastic spacer 25
  • 26. 4.1 Raft Foundation construction process (from site visit) The ground is excavated 40 cm deep and then levelled Wood is used as the formwork to hold the concrete in shape Concrete is then poured into the formwork, levelled and then left to dry. 15 cm 40 cm A compacted hardcore layer (Used as solid working base) and a blinding layer (Used to prevent wet concrete from running down the hardcore) is added inside Reinforcements are added. This will give more strength to the foundation Compacted hardcore 15 cm thick Sand blinding Steel mesh Steel bar Concrete Brace Vertical Wood formwork Reinforcement Then the soil is added to fil the gap between the foundation and the soil 40 cm Levelled ground Ground beam Wood formwork 26
  • 27. Original slope 4.1 Stepped Raft Foundation construction process (from site visit) Hard core layer Levelled groundThe slope is excavated into steps which are then levelled. This is done so as to get flat surfaces instead of a slope The surface is then covered with compacted hardcore and a blinding layer The reinforcements which consists of steel meshes and steel bars are added. The wood formworks are placed and concrete is poured inside. Blinding layer Steel mesh Steel bar Wood formwork Concrete 50 cm 27
  • 29. SUPERSTRUCTURE • Superstructure of a building is the portion of the structure above the foundation. It provides the necessary utility of the building with comfort, structural safety, ventilation, etc. SUPERSTRUCTURES IN OUR SITE • Beam 1. Simply supported beam 2. Fixed beam 3. Cantilever beam 4. Continuous beam • Columns • Slab • walls • staircase 29
  • 30. BEAM • Beam is the horizontal member of a structure, carrying transverse loads. Beam is rectangular in cross-section. Beam carry the floor slab or the roof slab. Beam transfer all the loads including its self-weight to the columns or walls. 1. Fix the reinforcement bar of the beam 2.Fix the wooden framework for the concrete beam and pour the concrete 3.Let it dry up and remove the formwork and you have your rcc beam CONSTRUCTION OF A RCC BEAM • The beam in the basement of our building is attached to the foundation slab. • For the ground floor, 1ST and 2nd floor they cast the beam with the slab since it was not possible to cast the slab later. • The ground, 1st and 2nd floor beam rest on the various collumns on the basement, ground and 1st floor respectively. • The 2nd floor beam is cast with the roof slab at our site. 30
  • 31. DIFFERENT KINDS OF BEAMS AT OUR SITE SIMPLY SUPPORTED BEAM FIXED BEAM CONTINUOUS BEAM CANTILIVER BEAM 31
  • 32. COLUMNS• Columns is a vertical structural member. It transmits the load from ceiling/roof slab and beam, including its self-weight to the foundation. • Columns may be subjected to a pure compressive load. R.C.C columns are the most widely used now days. Fix the reinforceme nt bars for the columns Built the wooden form work around the reinforcement and pour concrete and leave it to dry Remove the wooden form work after the mixture dries and there we get our column CONSTRUCTION OF A RCC COLUMN Section of a RCC column 32
  • 33. The columns of the basement has its reinforcements coming from the foundation The reinforcements of the columns of the ground floor run from the columns of the basement they are smaller in dimensions compared to the columns in the basement yet have the same center. The reinforcements of the columns of the first floor run from the columns of the ground floor, they are smaller in dimensions compared to the ground floor yet have the same center The reinforcements of the columns of the second floor run from the columns of the first floor, they are smaller in dimensions compared to the first floor with the same center. We even see that in this floor the numbers of columns also reduce since it is the last floor and has no load of further floors 33
  • 34. 5.2 Slab Type of slab used in our site: Two way slab (with beam) This type of slab is supported on four sides by beams and columns. This is because the ratio of length to width is less than two. The load is carried in two directions. The reinforcement is arranged to support the slab in two directions. Advantage: • Framing of beams with column • Versatile Disadvantage: • Beams dropping from ceiling are visible The formwork is assembled over the columns and is supported by scaffoldings. More wood is added to the formwork so as to look like this. Then the reinforcement cage for the beam is placed inside the gaps Steel meshes are inserted, this will give strength to the slab. Concrete is then poured inside and left to dry. Section cut 45 cm 15 cm Construction process: 34
  • 35. 5.3 Walls Wall is the vertical plane of a building, it defines an enclosed space or acts as a division. Walls are made to provide shelter from weathering, safety and privacy. It can be either load bearing or non-load bearing. The types of structural walls found on the building are: building wall, partition wall, party wall, and retaining wall. Types of building materials used : Masonry bricks and Reinforced concrete. Clay brick sand brick R.C wall Concrete retaining wallR.C wall Clay brick 35
  • 36. 36
  • 40. Staircase A staircase is a construction designed to link a large vertical distance by dividing it into smaller vertical distances which is called steps. It allows easy movement between the different levels of design. Aspect that should be considered when designing a staircase is the placement of stairs, ease to travel and most importantly the safety. Also, the design of a staircase should take proper consideration of the width, landings, handrail, guardrails, treads, rises, and nosing which are the requirements of a staircase. Concrete staircase Concrete staircase are often specified for their strength, durability, the protection, food resistance and sound reduction properties Concrete Quarter landing staircase Quarter Landing Stairs represent a variety of straight stairs, which also include a landing. But here the landing is needed to change a direction of the flight by 90 degrees and at the same time it serves as a place for rest when moving. The landing may change its position in the flight from its beginning and up to its end. Staircases of this type are more convenient and safe than straight staircases 37
  • 41. Advantages of quarter landing stairs shaped Stairs: 1. Quarter landing stairs can be more visually interesting. 2. They provide a visual barrier between floors so they can add some privacy. 3. Also quarter landing stairs can help somewhat with sound transmission between floors if the stairs are contained within walls. 4. Some believe they are safer than straight stairs as the central landing reduces the number of treads one could fall in a given flight. 5. The landing can provide a place to stop and rest while ascending. 6. They can be located in a corner of a room if this works better for your design. Disadvantages of quarter landing stairs shaped Stairs: 1. Quarter landing stairs are a bit more difficult to build. 2. A support is typically required for the landing in a quarter landing stairs. Often this is built into the surrounding walls so it goes unnoticed. In modern dwellings however it is usually desirable to open up the space leaving the stair structure visible. In these cases the supporting structure can be visually minimized by taking advantage of the strength of steel to create slim supporting members. Through careful engineering,it is possible to eliminate the landing support all together. 3. Handrails for these types of stairs require more skill and planning to construct. 4. In climates where basements are used, stairs are typically stacked over each other for efficient use of space. Since basements are often used for storage, large items can be difficult to move in and out of the basement. 38
  • 42. procedure of constructing concrete staircase step 1 : calculate the stairs dimension measure the height of one floor to the other. Divide the height with 7 inches (standard measurement of rise) to get the number of steps. measure the horizontal distance the staircase will span and me sure the width of staircase from left to right. step 2 : determine the foundation dimension the dimension of the staircase’s foundation are the total length of run and total width of staircase as measured in step 1 step 3 : build the formwork around the reinforcement using either plywood or framing lumber to build the form. Cut the side forms according to the tread and riser calculations. step 4 : prepare the concrete produce sufficient and well-mixed mortar with a portable cement mixer. step 5 : pour the mortar start at the bottom and pour one step at a time. make sure the mortars are spread evenly. use a spade to remove the trapped air bubbles. step 6 : add finishing touches use a simple wood float to clean and smooth the surface of the mortars. step 7 : leave and wait spray the stairs with cur in compound and cover it with burlap. after a week, remove from the lumber. 39
  • 43. Rectangle stainless steel handrails 50 x 25mm and 50 x 10mm rectangle stainless steel tube and fittings can be used to create a modern stainless steel rail which is suitable for both internal and external use. Advantages of stainless steel handrail 1. Easy to clean 2. The finishing (satin or mirror) look valuable 3. Not easy rusty 4. Not easy contaminated 5. Very strong in structure 6. Stainless steel look simple but luxury 7 .Stainless steel easy match to some other material such as glass and wood 8. Stainless steel have more accessories to fit with 9. Stainless steel is majority part fabricating onsite, instead of fabricating offsite at the factories then go onsite to install. Therefore, the job done is more precisely. 10. handrail using stainless steel material to fabricate always look better than other materials as no requirement of painting or powder coating as steel or aluminium. Fabricator can polish onsite when install the job. Even some balustrades need to fit or re-fabricated, then the fabricator can easily re-polish the finishing. 1. higher cost compare to other material. 2. require higher skill to weld and must have proper skill of polishing the stainless steel. 3. need properly maintain when it install at outside. 4. it is not easy to distinguish the material of stainless steel. Disadvantages of stainless steel handrail 40
  • 44. 6.0 Windows and doors Hinged: side hung Types of windows Fixed window Installation of windows: The above picture shows the frame fixed onto the walls after being plastered and skim coated. Then the aluminium window frames are fixed onto it. Installation of doors: The frame of the door is fitted The opening made into the wall. Then the door is fixed on This frame using a hinge. Type of door on site Side hung timber flush door 44
  • 46. Roof Roofing Introduction Flat roof has a pitch of less than 5’. However, flat roof structures are suitable for shallow pitched roof (up to 25’), although the building materials must be adequately protected against slippage. The top section of the flat roof is the roof covering, known as the roof weatherproofing or waterproofing. Layers of structural elements Flat roofs can have various functional layers, which must be matched to each other. It is essential that the layers sequence provide adequate insulation against heat and noise. Building materials must be compatible with each other. -under course -bonding course -leveling course -separating course -vapor barrier -thermal insulation -vapor pressure compensation course -roof waterproofing -filter course -surface protection -accessible coverings Structural element courses according to the guidelines laid down by the Zentrolverband des Deutshen Dachdeckerhandwerks: Flat roof guidelines. 46
  • 47. Roof edging Flat roof can be finished as projecting flat roofs at the point they meet the façade, or with an upstand. Current practice is to finish the roof with a parapet or an edge trim but we are focusing on roof edge with parapet as we can see in our site Roof Structure: roof waterproofing, single course, vapor pressure, compensation course, thermal insulation, vapor barrier, leveling course preliminary coating, reinforced concrete slab Wall structure: façade slabs, air space, thermal insulation calcium silicate mansonary 47
  • 48. Components for roof edge with parapet 48
  • 49. Flat roof is not perfectly flat , the rafters are laid at slight angle to allow the rain water to flow. Sheathing and roofing are applied to the top of the rafters The hip roof slopes at all sides, results in an even overhang all around the building. This roof is popular due to its low maintenance Curved roof is known for their aesthetic appeal. A curved roof also may help to reduce resistance to wind Most of the roofs in Malaysia are flat roof and it is slowly becoming popular compared to hip roof Famous for its low maintenance but users think that it is too old fashioned This kind of roof is not suitable or housing or commercial Flat roofs are quicker to apply thus saves time and money Hip roof takes more time to apply thus cost more money but the maintenance is low Even more time consuming to build curved panel roof Comparison between flat roofs and other types of roof 49
  • 50. Summary To conclude throughout all these site visit we have definitely learnt a lot from this experience. From basic structure theories to being able to indentify construction flaws. We visited one site in Kuala Lumpur (Desa Petaling , Desa hill villa ) it had 165 unit at different construction levels we saw houses at extraction level, foundation level, basic framework level, super structures level, completion level and with the final touches. Through this project we understood how one should go about contracting a three storey house. We learnt that to start any project we first need to do external works that is setting out boundaries surveying the land setting out earth works. The next stage is site safety and security. After all this on the basis of land survey we excavate the land for the foundation. We learnt about two different kinds of foundation at our site i.e. pile foundation and raft foundation. After setting out the foundation we studied the placing and construction of the various superstructures i.e. the columns, beams, slabs, staircase and wall. Later followed by the construction of the roof. After this the building is checked for water proofing . After that we set up the services and the electrical work and fill up the walls . The stage after this is the placing and installation of the doors and windows. We studied the different kinds of windows and doors at our site. After all this we see a final wall finishing that consists of plastering followed by smoothing and leveling which is followed by painting. After this we need to add up the final touches to the house that is the final paint coat the doors and window knobs furniture and that is how we construct or house. 507
  • 51. Reference • Engineering intro. Rollers. http://www.engineeringintro.com/all-about-construction-equipments/rollers-types-of-roller-characteristics/ • BuildingHow. Raft foundation. http://www.buildinghow.com/en-us/Products/Books/Volume-A/The-reinforcement-II/Foundation/Raft-foundation • King Saud University. Two way slabs. http://faculty.ksu.edu.sa/charif/Documents/Two%20way%20slabs.pdf • External wall construction. http://www.bca.gov.sg/professionals/iquas/..%5CIquas%5Cgpgs%5CWEWall%5CWEWChpt5.pdf • http://www.buildingscience.com/documents/digests/bsd-102-understanding-attic-ventilation • http://constructionstudiesq1.weebly.com/uploads/1/6/4/9/16490624/1364418771.jpg • http://www.greenspec.co.uk/images/web/refurb/timflatroof/warmtimbflatroof.png • Tanja Brotruck, 2007 Birkhauser, Roof Construction, Publishers for Architecture, P.O. Box133, CH-4010 Basel, Switzerland. • Barry’s introduction to building construction. Stephen Emmitt, Christopher A. Gorse. Jan 2010 • Different types of beams. http://www.slideshare.net/mbrsalman/civil-engineering-beamscolumns • Construction of columns and beams from site Everything else from site information 48