SlideShare uma empresa Scribd logo
1 de 62
Lessens Learned from
3.11 Fukushima Nuclear Accident
Koichi Kitazawa
Private Sector Investigation Committee
on Fukushima Nuclear Accident
Japan Science council, energy policy options
Japan Science and Technology Agency
ISES 2013-Nuclear Energy, Trondheim June12-15, 2013
500km
Hokkaido
Tokyo
Sendai
The Great East
Japan Earthquake
3.11 2011
The largest ever in
Japan, mag. 9.0
Total casualties 18600.
97% due to Tsunami
Tsunami invaded
along 500km
coast with av.
1km into land
500km x 1km
5 of 17NPS
stations in the
Tsunami area
.
30% of total elec.
power generated
by NP.
Nuclear fission : a million times larger energy than chemical burning
→1kg fuel vs. 1000 tons/day/1GW power station
A BWR NPS
Tsunami →damage of sea water inlet + SBO
→Water supply stopped.→Severe Accident
10000 fuel rods
for nuclear fission
   
7% of heat from
residual radio-
activity even
after stopping
of fission
Cooling!!
Gasket sealant
Several t ons/h
H2
Suppression chamber
Reactor
container
Pressure
vessel
Spent fuel rod pool
BWR reactor of
Fukushima Daiichi
Loss of
Water
→ H2,
meltdown
Unit 1
2
3
4
Turbine bldg
Fukushima Daiichi Nuclear Power Plant
Discharge of Radioactive Substances
from the Fukushima Dai-ichi
Nuclear Power Station
• The second worst in the world history
• Level 7, the worst level ( INES )
• 1/7 of contamination of Chernobyl
• It could have been much more serious
or much less  ←  prepared?
Contamination
With
134Cs & 137Cs
2012 Nov. 5
Evacuation
< 20mSv/y area
20-50mSv/y area
>50mSv/y area
Tokyo
Sendai
80,000
evacuated
additional
80,000 on
own willKyoto
New regulations in the area of contamination
• De-contamination of radioactive substance
for earlier return to home
50-20mSv/y areas
to reduce anxiety of residents
1 ~ 20mSv/y areas
1mSv/y---conventional regulation level
Areas >50mSv/y: assigned for no-return area
within 5 yrs
Fukushima Daiichi Nuclear Accident
• It could have been much worse than the reality.
Fortuitous developments saved the
spent fuel pool of No.4 unit from loosing water.
Unit No.2 worried for possible explosion
of the reactor vessel ←Pressure went up.
• It could have been much less serious if proper
counter measures taken to introduce water
into the core earlier.
Unprepared against the “severe accident”
Too late!! when sea water was introduced.
Fukushima 50 still appreciated to have prevented
the further worsening of the reactors.
The worst case scenario
• Reactor unit #4 lost the building roof←H2 leak
• The spent fuel pool exposed directly to the air
No confinement vessel if radio activity leaks
• The sfp is much more radio active.
• The sfp needed water cooling.
• Dry up feared ← The cooling stopped ←SBO
• “after shock” feared
• Evacuation of 30M metropolitan people possible
• Unexpected water supply to sfp from neighbor.
Spent fuel rods for
ca. 10 years
stored.    
To introduce water
in emergency, the
pressure must
be released
by “vent”.
Gasket sealant
Several t ons/h
H2
Suppression chamber
Reactor
container
Pressure
vessel
Spent fuel rod pool
BWR reactor of
Fukushima Daiichi
Indirect/essential causes of the accident
• Lack of precautions for the severe accidents
better knowledge about the emergency cooling system
storage of supplementary batteries
matching of external electric power supplier cars
knowledge of manual vent systems
extension of the valve shaft for safer vent
lack of vent filter
rehearsal of residents to escape for evacuation
• Negligence of the regulatory agencies
safety guide no consideration necessary for long hour“
black-out” by the Nuclear Safety Commission
Oral regulation to avoid written specifications by
54 nuclear reactors in Japan
Only 2 on operation at the moment.
18
http://vitalsigns.worldwatch.org/vs-trend/global-nuclear-generation-capacity-falls
Three Mile Island
Pennsilvania
Fukushima
Chernobyl, Soviet Union
● : Nuclear reactors    
Location of earthquakes bigger than Mg 6.0 ●
   20% near Japan(50 times more frequent)  
Additional special condition in Japan
   
People’s desire of de-nuclearization if possible
Finite risk does remain. nuclear plant not “fail safe”
A gigantic risk →collapse of a whole country possible
+ Nuclear waste negative heritage >10000yrs
Are alternative energy sources feasible?
Fossil energy: coal, oil, natural gas, shale gas
Renewable energy: expensive initial cost
unstable (intermittent)
wide space needed
CO2 emission, depleting resource
Exceptions:
Hydro Stable
geothermal Low cost
Crude oil price & import
0
10000
20000
30000
40000
50000
60000
70000
1965
1966
1967
1968
1969
1970
1971
1972
1973
1974
1975
1976
1977
1978
1979
1980
1981
1982
1983
1984
1985
1986
1987
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2010
0
2
4
6
8
10
12
14
16
( / )原油価格 円 kℓ 原油輸入額(兆円)
円 /kℓ 兆円
年度
Energy White Paper 2011
1st
oil
shock
’79 2nd
oil shock ‘90 Gulf
war
‘05 3rd
oil shock
1980
1990
2000
2010
1970 Energy import of Japan: $2000/yr person
0
100
200
300
400
500
600
700
800
900
1,000
2010
2012
2016
2020
2030
2040
年度
TWh発電量()
0
100
200
300
400
500
600
700
800
900
1,000
2010
2012
2016
2020
2030
2040
年度
TWh発電量()
Japan Science Council Proposed options
for shift
Sept. 2011scenario  A scenario  B Scenario C
scenario  D scenario  E scenario  F
化石燃料
再生可能エネルギー
Fossil
RENuc
Hydrp 0
100
200
300
400
500
600
700
800
900
1,000
2010
2012
2016
2020
2030
2040
年度
TWh発電量()
0
100
200
300
400
500
600
700
800
900
1,000
2010
2012
2016
2020
2030
2040
年度
TWh発電量()
0
100
200
300
400
500
600
700
800
900
1,000
2010
2012
2016
2020
2030
2040
年度
TWh発電量()
0
100
200
300
400
500
600
700
800
900
1,000
2010
2012
2016
2010
2030
2040
年度
TWh発電量()
大規模水力 大規模水力
大規模水力 大規模水力 大規模水力
再生可能エネルギー
再生可能エネルギー
再生可能エネルギー
再生可能エネルギー
化石燃料 化石燃料 化石燃料
化石燃料
原子
力発電 原子力発電
原子力発電
原子力発電 原子力発電
2020
0
100
200
300
400
500
600
700
800
900
1,000
2010
2012
2016
2020
2030
年度
TWh発電量()
Nucl.30%
Fossile
Fuel 60%
Renewable 50%
FY
Dam hydro
9%
Energy
Saving
Electricpower(TWh)
1% GDP (500USD/yr/person)
investment needed for RE
To grow to 50% of elec. power
By 2020 to keep UN promise
Sci.Council J
2011
Efficiency improvement
The Empirical Rule by Kitazawa
 “ Land Area determines for nuclear or de-nuclear”
   Russia, China, US> India>(Chile)>Ukrain>
France>Spain>Sweden>(Ecuador)
Japan>Germany>Italy>Korea>Austria>
Switzerland>Taiwan>Belgium
 “ One Fukushima may destroy the whole
country”
 
   
     
Additional factors:
latent threat from other type of energy security
economic growth more urgent for developing countries
 
Japanese policy for future energy
Dec. 2012 General Election
• “Democrat party government” till the end of 2012
ex-nuclear at ca. 2030 by gradual decrease
• New Gov “Liberal Democratic party”
“decision suspended for 3-4 years”
“restart of the stopping nuclear plants as far
as their safety confirmed by
the new Nuclear Regulatory Authority”
“Efforts paid to introduce renewable energy”
Efficient energy conversion
and
energy saving
Now it is the time to pay every efforts for energy
saving the first.
•combined cycle power generator→triple cycle
•Energy saving
fuel cell +gas turbine +steam turbine
Carbon tax
to provide
comprehensive
incentives
final target
50(-80)%
by 2050
Manufacturing, transportation and daily life
cost of energy ↑by 2 energy saving to 1/2⇔
three important area for energy saving
Heat pumps
Thermal insulation
underground heat
LED
Heat pumps
Fuel cell +
water heating
(Enefarm)
IH heater
microwave
CAR WEIGHTCAR WEIGHT
kg
HYBRID CAR
EV, FC CAR
FUEL
CONSUMPTION
FOREIGN CAR
DOMESTIC CAR
Energy Saving with automobiles
1/4
ENERGY SAVING OF HOME REFREGERATOR
80% in 20 yrs
Heat pumps
(kWh/L/yr)
34
REN 2011
World Investment for Renewable E
Exceeding 200 B$ /yr
Becoming a gigantic world industry
B$
35
自然エネルギー白書 2012 より
http://www.map.ren21.net/GSR/GSR2012.pdf
36
http://www.isep.or.jp/images/press/Eneshift-ISEP20110614.pdf
  Wind power accumulated capacity → >100GW  
US,China: asset finance
Europe: Feed-in-tariff
China
US
Germ
Spain
India
Denm
Japan
 Capacity(MW)
 
37
38
http://en.wikipedia.org/wiki/Feed-in_tariff#Germany
Price of electricity by solar cells in Germany
0
10
20
30
40
50
60
70
80
90
2004 2005 2006 2007 2008 2009 2010 2010 2012
Rooftop >1MW
Rooftop <30kW
Japanese FIT
Yen/kWh
FY
Grid-parity at home
achieved in 2010
→no more FIT needed
German FIT
price
39 39
Stability of power supply
Pump-up hydro
+ Gas turbine
Batteries + Fuel cells
Typical solar cell output
Typical wind mill monthly output
fine
cloudy
rainy
Taking average by
connection of many
Power generators
desired
Red Eléctrica de España   HP より
Spanish example of adjusting for supply-demand gap
( CECRC ) 2009.12.31
Hydro
Nuclear
Oil/GasWind
Other renewables
export
0 O’clock 24 O’clock
RE/total electric consumption 40-60%
import
Japanese Feed-in-Tariff
• Started in 2012 July
3GW contracted for solar (doubling)
easy installation
0.5 GW with wind (← slow due to regulation)
      cost effectiveness highest
geothermal not yet (←national park law )
good because of stability, low cost
wave, tidal, ocean current: on R&D stage
42
Windy area
Weak power transmission lines in
north areas (Hokkaido and Tohoku)
Total
farmland
abandoned
House
land
Needed area to
support
total electricity
roof
Solar Panel Area Needed
3960km2
46100km2
21500
km24000km2
6550km2
63km2
20km 圏内
1820km2
43
Parking
area
land shortage problems→solar sharing
45 45
Hywind Floating Windmill
(Norway)
http://webronza.asahi.com/
global/2011041400011.html
Off-shore Floating Windmill
Wind lens type
with fish cultivation pool
Kyushu Univ. Prof.
Kyozuka
Lower noise by 10dB
Output enhancement 3X
No bird strike
fish culture pond
4646
0
250
500
750
1 ,000
1 ,250
1 ,500
1 ,750
2,000
2,250
2,500
2,750
3,000
2010
総
発
電
量
(
実
績
)
2010
原
子
力
(
実
績
)
太
陽
光
風
力
(陸
上
)
風
力
(洋
上
)
地
熱
中
小
水
力
等
環境省「平成 22 年度度再生可能エネルギー導入ポテンシャル調査」 か
ら試算
※ 原子力は資源エネルギー庁統計より
TWh
46
Electricity generated
2010
Nuclear 2010 Solar
W
ind
(land)
W
ind
(off shore)
Geotherm
al
Sm
all hydro
potential development of RE in Japan
Assumption:
The current legal
and cost status
(Ministry of
Environments)
Which direction to go?
• Japanese import of fossil fuel
max in 2008 $2,000/y/person
• Electric power total sales $1,300 (2010)
• Nuclear energy share (30%) $400
• Investment needed for RE $500 fast case
• Investment for transmission line $100
• Solar power: 30% for panels, 70% for the rest
• Population 125M GDP/person $45,000
• Total expenditure for amusement $8,000
• Education of children $500
• net income from overseas investment $1,000
What is worth to be paid? What do we live for?
RE industry?
Amusement?
Moral?, happiness?
land shortage problems
Ichihara-shi, Chiba Pref.
proposed by Nagashima
& Matsuoka
Solar sharing :Cell stripe and interval space
to leave enough light for agriculture 。
49
Growth rate
saturates
with light
intensity
Farm lands and solar cell
• Farm houses with wider roofs
• doubling of peasant’s income possible
14000$ →28000$ by 200m2 solar panel
good timing for Tohoku area restoration
←FIT, restoration policy
   pension plan for local enterprises
   low risk with 6% interest rate
→Fishery + wind mill
• JST (ALCA project for game changing tech.)
Japan Science and Technology Agency
• NEDO (road map R&D for commercialization)
New Energy Development Organization
Researches at universities
(game changing technologies)
Organic liquid Si
Prof. Shimoda (JAIST)
organic molecular thin film
solar cell Mitsubishi Chem. > 10%
Prof. E.Nakamura (Tokyo Univ)
Si painting?
Umena Y., Kawakami K., Shen J.-R., Kamiya N.
Nature:   473,Pages:55–60   (05 May 2011)
Crystal structure of oxygen-evolving photosystem II
(Okayama, Osaka city Univ) Distorted
Chair str.
Mn
Mn
M
Ca
O
O
O
O
O
Mn
PHOTOSYNTHESIS  ARTIFICIAL PHOTOSYNTHESIS
Efforts toward
artificial photo synthesis
• Tokyo Univ. Prof. Domen, Honda-Fujishima
H2 evolution photo-catalyst (TiO2)
• Tokyo Metropolitan Univ. Prof. Inoue
Organic complex photo-catalyst
Performance revolution in 2005 HTS cable
臨
界
電
流
x
線
材
長
さLxIc(77K)
Tc
20 years needed to enhance Ic
56
150
230
超電導ケーブル
150
管路
既存CV
ケーブル
600800
2100
340
水冷管
トラフ
洞道
~
66kV
HTS Cable
66kV
Switching
Station
66kV
Switching
Station
684MW
684kV
500kV
(Existing
Conduit)
Conventional
Cable
HTS Cable
100% shield
(New & Large
Diameter
Tunnel )
~
~
275kV
275kV
S/S
275kV
S/S
66kV
66kV
684MW
684MW
275kV
~
500kV Substation
mm
mm
(T. Hara et al., Advances in Superconductivity II, (1990) 1059.)
YOKOHAMA HTS Cable Project
HTS Cable Demonstration Project in Live Grid
•66kV - 2kA - 200MVA Bi2223 wire
• ~ 250 meter long, One cable-to-cable Joint
The 1st
practical superconducting cable
To be instaled in Sapporo in 2014.
Data center – power plant
Planned to extend the superconducting
Low-V large-I line to wind mills.
K. Kitazawa “Newton”   Jan. (2001)
Global Superconducting Grid
with natural renewable energy resources
Global superconducting grid
No loss in
transmission
(DC mode)
JR type MAGLEV
test since 1964
SC perp-
etual
magnet
Ground
coil(Cu)
Ground
Propul-
sion coil
levitation
propulsion
推進コイル
ガイドウェイ
超電導磁石
浮上・案内兼用コイル
Superconducting MAGLEV
Japan Railway Company
2025 Tokyo-Nagoya
Propulsion coil
Levitation and guide coil
Guide way
SC magnet
Perpetual current mode
☆No limit on traveling speed
    business speed : 500km/h
(2,000km/h possible under
depressurized atmosphere)
    Jet Aircraft: 1,000km/h
☆No exhaust gas
☆Quieter than automobiles
☆Energy saving: one-third of domestic airplanes
☆Safer than railways Floating clearance (10cm)
    Volume supported (not point contact)
☆Ease of maintenance: resistant to sand,
earthquakes, and snow
superconducting MAGLEV (JR)
Yamanashi test line

Mais conteúdo relacionado

Mais procurados

Nuclear Power Pros and Cons
Nuclear Power Pros and ConsNuclear Power Pros and Cons
Nuclear Power Pros and Cons
wintryblossom
 
09 10 Energy Sources Andie
09 10 Energy Sources Andie09 10 Energy Sources Andie
09 10 Energy Sources Andie
Teach5ch
 
09 10 Energy Sources Andie
09 10 Energy Sources Andie09 10 Energy Sources Andie
09 10 Energy Sources Andie
charsh
 
Jaitapur Nuclear Power Project
Jaitapur Nuclear Power Project Jaitapur Nuclear Power Project
Jaitapur Nuclear Power Project
khushboojain1992
 
Is nuclear energy solution to our power problems ?
Is nuclear energy solution to our power problems ?Is nuclear energy solution to our power problems ?
Is nuclear energy solution to our power problems ?
Harsh Gupta
 
Nat. resources, energy resources
Nat. resources, energy resourcesNat. resources, energy resources
Nat. resources, energy resources
Ms. Jones
 
Nonrenewable energy[1]
Nonrenewable energy[1]Nonrenewable energy[1]
Nonrenewable energy[1]
karisls
 
Nuclear power &_india
Nuclear power &_indiaNuclear power &_india
Nuclear power &_india
IndianInd
 
Nuclear Energy Lecture
Nuclear Energy LectureNuclear Energy Lecture
Nuclear Energy Lecture
Vishal Shukla
 

Mais procurados (20)

ThorCon CEO Explain Design [ICENES 2019]
ThorCon CEO Explain Design [ICENES 2019]ThorCon CEO Explain Design [ICENES 2019]
ThorCon CEO Explain Design [ICENES 2019]
 
Nuclear Power Station 2020
Nuclear Power Station  2020Nuclear Power Station  2020
Nuclear Power Station 2020
 
Nuclear Power Pros and Cons
Nuclear Power Pros and ConsNuclear Power Pros and Cons
Nuclear Power Pros and Cons
 
09 10 Energy Sources Andie
09 10 Energy Sources Andie09 10 Energy Sources Andie
09 10 Energy Sources Andie
 
09 10 Energy Sources Andie
09 10 Energy Sources Andie09 10 Energy Sources Andie
09 10 Energy Sources Andie
 
Nuclear power plants
Nuclear power plantsNuclear power plants
Nuclear power plants
 
Jaitapur Nuclear Power Project
Jaitapur Nuclear Power Project Jaitapur Nuclear Power Project
Jaitapur Nuclear Power Project
 
Is nuclear energy solution to our power problems ?
Is nuclear energy solution to our power problems ?Is nuclear energy solution to our power problems ?
Is nuclear energy solution to our power problems ?
 
Advantages of nuclear power
Advantages of nuclear powerAdvantages of nuclear power
Advantages of nuclear power
 
Nat. resources, energy resources
Nat. resources, energy resourcesNat. resources, energy resources
Nat. resources, energy resources
 
Positioning The Nuclear Sector In A Greener World Roger Emmott Jan 2009
Positioning The Nuclear Sector In A Greener World   Roger Emmott Jan 2009Positioning The Nuclear Sector In A Greener World   Roger Emmott Jan 2009
Positioning The Nuclear Sector In A Greener World Roger Emmott Jan 2009
 
Nonrenewable energy[1]
Nonrenewable energy[1]Nonrenewable energy[1]
Nonrenewable energy[1]
 
Nuclear power &_india
Nuclear power &_indiaNuclear power &_india
Nuclear power &_india
 
Nuclear Energy Myths and Realities by Soumya Dutta
Nuclear Energy Myths and Realities by Soumya DuttaNuclear Energy Myths and Realities by Soumya Dutta
Nuclear Energy Myths and Realities by Soumya Dutta
 
Nuclear Energy and sustainable development
Nuclear Energy and sustainable developmentNuclear Energy and sustainable development
Nuclear Energy and sustainable development
 
Nuclear Energy Lecture
Nuclear Energy LectureNuclear Energy Lecture
Nuclear Energy Lecture
 
Sustainable of Nuclear Energy
Sustainable of Nuclear EnergySustainable of Nuclear Energy
Sustainable of Nuclear Energy
 
Nuclear Energy Merit Badge for Boy Scouts
Nuclear Energy Merit Badge for Boy ScoutsNuclear Energy Merit Badge for Boy Scouts
Nuclear Energy Merit Badge for Boy Scouts
 
Nuclear power & india
Nuclear power & indiaNuclear power & india
Nuclear power & india
 
Save Our Environment, Stop Nuclear Energy Usage
Save Our Environment, Stop Nuclear Energy UsageSave Our Environment, Stop Nuclear Energy Usage
Save Our Environment, Stop Nuclear Energy Usage
 

Destaque

ISES 2013 - Day 1 - Connie Hedegaard (European Commissioner for Climate Actio...
ISES 2013 - Day 1 - Connie Hedegaard (European Commissioner for Climate Actio...ISES 2013 - Day 1 - Connie Hedegaard (European Commissioner for Climate Actio...
ISES 2013 - Day 1 - Connie Hedegaard (European Commissioner for Climate Actio...
Student Energy
 
ISES 2013 - Day 2 - Conveners Club Changemakers Panel
ISES 2013 - Day 2 - Conveners Club Changemakers Panel ISES 2013 - Day 2 - Conveners Club Changemakers Panel
ISES 2013 - Day 2 - Conveners Club Changemakers Panel
Student Energy
 

Destaque (9)

ISES 2013 - Day 2 - Dr. Gunnhild Stordalen( Chairman of Board, Greenudge) - ...
ISES 2013  - Day 2 - Dr. Gunnhild Stordalen( Chairman of Board, Greenudge) - ...ISES 2013  - Day 2 - Dr. Gunnhild Stordalen( Chairman of Board, Greenudge) - ...
ISES 2013 - Day 2 - Dr. Gunnhild Stordalen( Chairman of Board, Greenudge) - ...
 
Living Villages 2 - Energy Co-Ops
Living Villages 2 - Energy Co-OpsLiving Villages 2 - Energy Co-Ops
Living Villages 2 - Energy Co-Ops
 
ISES 2013 - Day 1 - Connie Hedegaard (European Commissioner for Climate Actio...
ISES 2013 - Day 1 - Connie Hedegaard (European Commissioner for Climate Actio...ISES 2013 - Day 1 - Connie Hedegaard (European Commissioner for Climate Actio...
ISES 2013 - Day 1 - Connie Hedegaard (European Commissioner for Climate Actio...
 
ISES 2013 - Day 2 - Conveners Club Changemakers Panel
ISES 2013 - Day 2 - Conveners Club Changemakers Panel ISES 2013 - Day 2 - Conveners Club Changemakers Panel
ISES 2013 - Day 2 - Conveners Club Changemakers Panel
 
ISES 2013 - Day 2 - Ole Grimsrud (Vice President Resource and Development, S...
ISES 2013  - Day 2 - Ole Grimsrud (Vice President Resource and Development, S...ISES 2013  - Day 2 - Ole Grimsrud (Vice President Resource and Development, S...
ISES 2013 - Day 2 - Ole Grimsrud (Vice President Resource and Development, S...
 
ISES 2013 - Day 2 - Nadine Bret Rouzaut (Director, Centre for Economics and ...
ISES 2013  - Day 2 - Nadine Bret Rouzaut (Director, Centre for Economics and ...ISES 2013  - Day 2 - Nadine Bret Rouzaut (Director, Centre for Economics and ...
ISES 2013 - Day 2 - Nadine Bret Rouzaut (Director, Centre for Economics and ...
 
ISES 2013 - Day 3 - Jane McRae (CEO, Sustainable Cities International) - Sus...
ISES 2013  - Day 3 - Jane McRae (CEO, Sustainable Cities International) - Sus...ISES 2013  - Day 3 - Jane McRae (CEO, Sustainable Cities International) - Sus...
ISES 2013 - Day 3 - Jane McRae (CEO, Sustainable Cities International) - Sus...
 
Harnessing the Power of Youth - UN SE4ALL Forum (June 4, 2014)
Harnessing the Power of Youth - UN SE4ALL Forum (June 4, 2014)Harnessing the Power of Youth - UN SE4ALL Forum (June 4, 2014)
Harnessing the Power of Youth - UN SE4ALL Forum (June 4, 2014)
 
ISES 2013 - Day 3 - Michel Orlhac (Vice President, Schneider-Electric) - Sus...
ISES 2013  - Day 3 - Michel Orlhac (Vice President, Schneider-Electric) - Sus...ISES 2013  - Day 3 - Michel Orlhac (Vice President, Schneider-Electric) - Sus...
ISES 2013 - Day 3 - Michel Orlhac (Vice President, Schneider-Electric) - Sus...
 

Semelhante a ISES 2013 - Day 1 - Prof. Koichi Kitazawa, Former Executive Director, Japan Science and Technology Agency - Nuclear Friend or Foe

Society automotive engineering
Society automotive engineeringSociety automotive engineering
Society automotive engineering
Air Fuel Synthesis
 
Saving Energy
Saving EnergySaving Energy
Saving Energy
mrconroy
 
Energy, climate change
Energy, climate changeEnergy, climate change
Energy, climate change
L
 
Nuclear energy powerpoint.
Nuclear energy powerpoint.Nuclear energy powerpoint.
Nuclear energy powerpoint.
Enigmatic You
 

Semelhante a ISES 2013 - Day 1 - Prof. Koichi Kitazawa, Former Executive Director, Japan Science and Technology Agency - Nuclear Friend or Foe (20)

Society automotive engineering
Society automotive engineeringSociety automotive engineering
Society automotive engineering
 
Economics of plutonium recycle 6 nov2015fvh
Economics of plutonium recycle 6 nov2015fvhEconomics of plutonium recycle 6 nov2015fvh
Economics of plutonium recycle 6 nov2015fvh
 
Climate Change: Are We Losing the Carbon-Free Energy Market to China
Climate Change: Are We Losing the Carbon-Free Energy Market to ChinaClimate Change: Are We Losing the Carbon-Free Energy Market to China
Climate Change: Are We Losing the Carbon-Free Energy Market to China
 
Climate change and the need for cheaper and stable energy
Climate change and the need for cheaper and stable energyClimate change and the need for cheaper and stable energy
Climate change and the need for cheaper and stable energy
 
Module-1 Non Conventional Energy sources
Module-1 Non Conventional Energy sourcesModule-1 Non Conventional Energy sources
Module-1 Non Conventional Energy sources
 
Summary Presentation for The Great Transition: Shifting from Fossil Fuels to ...
Summary Presentation for The Great Transition: Shifting from Fossil Fuels to ...Summary Presentation for The Great Transition: Shifting from Fossil Fuels to ...
Summary Presentation for The Great Transition: Shifting from Fossil Fuels to ...
 
Saving Energy
Saving EnergySaving Energy
Saving Energy
 
Energy, climate change
Energy, climate changeEnergy, climate change
Energy, climate change
 
The Green Path for Japan
The Green Path for JapanThe Green Path for Japan
The Green Path for Japan
 
Wind power PRESENTATION
Wind power PRESENTATIONWind power PRESENTATION
Wind power PRESENTATION
 
windpower11slides1-150319091424-conversion-gate01.pdf
windpower11slides1-150319091424-conversion-gate01.pdfwindpower11slides1-150319091424-conversion-gate01.pdf
windpower11slides1-150319091424-conversion-gate01.pdf
 
Non Conventional Energy Source, Introduction, Solar Radiation, and measurements
Non Conventional Energy Source, Introduction, Solar Radiation, and measurementsNon Conventional Energy Source, Introduction, Solar Radiation, and measurements
Non Conventional Energy Source, Introduction, Solar Radiation, and measurements
 
Global warming
Global warmingGlobal warming
Global warming
 
Nuclear energy powerpoint.
Nuclear energy powerpoint.Nuclear energy powerpoint.
Nuclear energy powerpoint.
 
Nuclear power
Nuclear powerNuclear power
Nuclear power
 
Suhasini
SuhasiniSuhasini
Suhasini
 
geothermal energy
geothermal energygeothermal energy
geothermal energy
 
Renewable energy resources
Renewable energy resourcesRenewable energy resources
Renewable energy resources
 
lec19.ppt
lec19.pptlec19.ppt
lec19.ppt
 
lec19.ppt
lec19.pptlec19.ppt
lec19.ppt
 

Mais de Student Energy

ISES 2013 - Day 1 - Richard H. Jones (Deputy Executive Director, Internationa...
ISES 2013 - Day 1 - Richard H. Jones (Deputy Executive Director, Internationa...ISES 2013 - Day 1 - Richard H. Jones (Deputy Executive Director, Internationa...
ISES 2013 - Day 1 - Richard H. Jones (Deputy Executive Director, Internationa...
Student Energy
 
ISES 2013 - Day 2 - Torstein Indrebø (Secretary General, International Gas U...
ISES 2013  - Day 2 - Torstein Indrebø (Secretary General, International Gas U...ISES 2013  - Day 2 - Torstein Indrebø (Secretary General, International Gas U...
ISES 2013 - Day 2 - Torstein Indrebø (Secretary General, International Gas U...
Student Energy
 
Ises 2013 day 3 - professor mike sandiford (professor, university of melbou...
Ises 2013   day 3 - professor mike sandiford (professor, university of melbou...Ises 2013   day 3 - professor mike sandiford (professor, university of melbou...
Ises 2013 day 3 - professor mike sandiford (professor, university of melbou...
Student Energy
 

Mais de Student Energy (20)

ISES 2013 - Day 1 - David Addison (Manager, Virgin Group Earth Challenge) - ...
ISES 2013  - Day 1 - David Addison (Manager, Virgin Group Earth Challenge) - ...ISES 2013  - Day 1 - David Addison (Manager, Virgin Group Earth Challenge) - ...
ISES 2013 - Day 1 - David Addison (Manager, Virgin Group Earth Challenge) - ...
 
ISES 2013 - Day 1 - Prof. Dr. Philos Kristian Fossheim (President, Royal Nor...
ISES 2013  - Day 1 - Prof. Dr. Philos Kristian Fossheim (President, Royal Nor...ISES 2013  - Day 1 - Prof. Dr. Philos Kristian Fossheim (President, Royal Nor...
ISES 2013 - Day 1 - Prof. Dr. Philos Kristian Fossheim (President, Royal Nor...
 
ISES 2013 - Day 1 - Dr. Jan-Gunnar Winther (Director, Worwegian Polar Instit...
ISES 2013  - Day 1 - Dr. Jan-Gunnar Winther (Director, Worwegian Polar Instit...ISES 2013  - Day 1 - Dr. Jan-Gunnar Winther (Director, Worwegian Polar Instit...
ISES 2013 - Day 1 - Dr. Jan-Gunnar Winther (Director, Worwegian Polar Instit...
 
ISES 2013 Day 1 - Ana Aguado (CEO, Friends of the Super Grid) - Future Grids
ISES 2013   Day 1 - Ana Aguado (CEO, Friends of the Super Grid) - Future GridsISES 2013   Day 1 - Ana Aguado (CEO, Friends of the Super Grid) - Future Grids
ISES 2013 Day 1 - Ana Aguado (CEO, Friends of the Super Grid) - Future Grids
 
ISES 2013 - Day 2 - Professor John M. Dhaw (Professor, University of Albert...
ISES 2013   - Day 2 - Professor John M. Dhaw (Professor, University of Albert...ISES 2013   - Day 2 - Professor John M. Dhaw (Professor, University of Albert...
ISES 2013 - Day 2 - Professor John M. Dhaw (Professor, University of Albert...
 
ISES 2013 - Day 2 - Tor-Eivind Moen (Technology Director, ABB) - Energy on N...
ISES 2013  - Day 2 - Tor-Eivind Moen (Technology Director, ABB) - Energy on N...ISES 2013  - Day 2 - Tor-Eivind Moen (Technology Director, ABB) - Energy on N...
ISES 2013 - Day 2 - Tor-Eivind Moen (Technology Director, ABB) - Energy on N...
 
ISES 2013 - Day 3 - Bjorn Lomborg - Crossroads to a Sustainable Future
ISES 2013  - Day 3 - Bjorn Lomborg - Crossroads to a Sustainable FutureISES 2013  - Day 3 - Bjorn Lomborg - Crossroads to a Sustainable Future
ISES 2013 - Day 3 - Bjorn Lomborg - Crossroads to a Sustainable Future
 
ISES 2013 - Day 2 - Professor Søren Hermansen (Director, Samsoe Energy Acade...
ISES 2013  - Day 2 - Professor Søren Hermansen (Director, Samsoe Energy Acade...ISES 2013  - Day 2 - Professor Søren Hermansen (Director, Samsoe Energy Acade...
ISES 2013 - Day 2 - Professor Søren Hermansen (Director, Samsoe Energy Acade...
 
ISES 2013 - Day 2 - Evan Mertens and Hermann Van Heist (Rural Spark) - Grass...
ISES 2013  - Day 2 - Evan Mertens and Hermann Van Heist (Rural Spark) - Grass...ISES 2013  - Day 2 - Evan Mertens and Hermann Van Heist (Rural Spark) - Grass...
ISES 2013 - Day 2 - Evan Mertens and Hermann Van Heist (Rural Spark) - Grass...
 
Ises 2013 day 3 - janet swim (professor of psychology, penn state) - the ps...
Ises 2013   day 3 - janet swim (professor of psychology, penn state) - the ps...Ises 2013   day 3 - janet swim (professor of psychology, penn state) - the ps...
Ises 2013 day 3 - janet swim (professor of psychology, penn state) - the ps...
 
ISES 2013 - Day 3 - Dr. Pierce Riemer (Director General, World Petroleum Cou...
ISES 2013  - Day 3 - Dr. Pierce Riemer (Director General, World Petroleum Cou...ISES 2013  - Day 3 - Dr. Pierce Riemer (Director General, World Petroleum Cou...
ISES 2013 - Day 3 - Dr. Pierce Riemer (Director General, World Petroleum Cou...
 
ISES 2013 - Day 3 - Stephen Roosa (Association of Energy Engineers) - The Tr...
ISES 2013  - Day 3 - Stephen Roosa (Association of Energy Engineers) - The Tr...ISES 2013  - Day 3 - Stephen Roosa (Association of Energy Engineers) - The Tr...
ISES 2013 - Day 3 - Stephen Roosa (Association of Energy Engineers) - The Tr...
 
ISES 2013 - Day 3 - Lisa Margonelli (Research Fellow, New America Foundation...
ISES 2013  - Day 3 - Lisa Margonelli (Research Fellow, New America Foundation...ISES 2013  - Day 3 - Lisa Margonelli (Research Fellow, New America Foundation...
ISES 2013 - Day 3 - Lisa Margonelli (Research Fellow, New America Foundation...
 
ISES 2013 - Day 3 - Unni Steinsmo (CEO, Sintef) - Innovation
ISES 2013  - Day 3 - Unni Steinsmo (CEO, Sintef) - InnovationISES 2013  - Day 3 - Unni Steinsmo (CEO, Sintef) - Innovation
ISES 2013 - Day 3 - Unni Steinsmo (CEO, Sintef) - Innovation
 
ISES 2013 - Day 1 - Michael Grubb (Professor, University of Cambridge) - Inve...
ISES 2013 - Day 1 - Michael Grubb (Professor, University of Cambridge) - Inve...ISES 2013 - Day 1 - Michael Grubb (Professor, University of Cambridge) - Inve...
ISES 2013 - Day 1 - Michael Grubb (Professor, University of Cambridge) - Inve...
 
ISES 2013 - Day 1 - Dr. Satyajit Bose (Earth Institute at Columbia Universit...
 ISES 2013 - Day 1 - Dr. Satyajit Bose (Earth Institute at Columbia Universit... ISES 2013 - Day 1 - Dr. Satyajit Bose (Earth Institute at Columbia Universit...
ISES 2013 - Day 1 - Dr. Satyajit Bose (Earth Institute at Columbia Universit...
 
ISES 2013 - Professor John M. Shaw (Professor, University of Alberta) - Ener...
ISES 2013  - Professor John M. Shaw (Professor, University of Alberta) - Ener...ISES 2013  - Professor John M. Shaw (Professor, University of Alberta) - Ener...
ISES 2013 - Professor John M. Shaw (Professor, University of Alberta) - Ener...
 
ISES 2013 - Day 1 - Richard H. Jones (Deputy Executive Director, Internationa...
ISES 2013 - Day 1 - Richard H. Jones (Deputy Executive Director, Internationa...ISES 2013 - Day 1 - Richard H. Jones (Deputy Executive Director, Internationa...
ISES 2013 - Day 1 - Richard H. Jones (Deputy Executive Director, Internationa...
 
ISES 2013 - Day 2 - Torstein Indrebø (Secretary General, International Gas U...
ISES 2013  - Day 2 - Torstein Indrebø (Secretary General, International Gas U...ISES 2013  - Day 2 - Torstein Indrebø (Secretary General, International Gas U...
ISES 2013 - Day 2 - Torstein Indrebø (Secretary General, International Gas U...
 
Ises 2013 day 3 - professor mike sandiford (professor, university of melbou...
Ises 2013   day 3 - professor mike sandiford (professor, university of melbou...Ises 2013   day 3 - professor mike sandiford (professor, university of melbou...
Ises 2013 day 3 - professor mike sandiford (professor, university of melbou...
 

Último

EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
Earley Information Science
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
Joaquim Jorge
 

Último (20)

Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CV
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUnderstanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path Mount
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonets
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 

ISES 2013 - Day 1 - Prof. Koichi Kitazawa, Former Executive Director, Japan Science and Technology Agency - Nuclear Friend or Foe

  • 1. Lessens Learned from 3.11 Fukushima Nuclear Accident Koichi Kitazawa Private Sector Investigation Committee on Fukushima Nuclear Accident Japan Science council, energy policy options Japan Science and Technology Agency ISES 2013-Nuclear Energy, Trondheim June12-15, 2013
  • 2. 500km Hokkaido Tokyo Sendai The Great East Japan Earthquake 3.11 2011 The largest ever in Japan, mag. 9.0
  • 3.
  • 4.
  • 6. Tsunami invaded along 500km coast with av. 1km into land 500km x 1km 5 of 17NPS stations in the Tsunami area . 30% of total elec. power generated by NP.
  • 7. Nuclear fission : a million times larger energy than chemical burning →1kg fuel vs. 1000 tons/day/1GW power station A BWR NPS Tsunami →damage of sea water inlet + SBO →Water supply stopped.→Severe Accident
  • 8. 10000 fuel rods for nuclear fission     7% of heat from residual radio- activity even after stopping of fission Cooling!! Gasket sealant Several t ons/h H2 Suppression chamber Reactor container Pressure vessel Spent fuel rod pool BWR reactor of Fukushima Daiichi Loss of Water → H2, meltdown
  • 9. Unit 1 2 3 4 Turbine bldg Fukushima Daiichi Nuclear Power Plant
  • 10. Discharge of Radioactive Substances from the Fukushima Dai-ichi Nuclear Power Station • The second worst in the world history • Level 7, the worst level ( INES ) • 1/7 of contamination of Chernobyl • It could have been much more serious or much less  ←  prepared?
  • 11. Contamination With 134Cs & 137Cs 2012 Nov. 5 Evacuation < 20mSv/y area 20-50mSv/y area >50mSv/y area Tokyo Sendai 80,000 evacuated additional 80,000 on own willKyoto
  • 12. New regulations in the area of contamination • De-contamination of radioactive substance for earlier return to home 50-20mSv/y areas to reduce anxiety of residents 1 ~ 20mSv/y areas 1mSv/y---conventional regulation level Areas >50mSv/y: assigned for no-return area within 5 yrs
  • 13. Fukushima Daiichi Nuclear Accident • It could have been much worse than the reality. Fortuitous developments saved the spent fuel pool of No.4 unit from loosing water. Unit No.2 worried for possible explosion of the reactor vessel ←Pressure went up. • It could have been much less serious if proper counter measures taken to introduce water into the core earlier. Unprepared against the “severe accident” Too late!! when sea water was introduced. Fukushima 50 still appreciated to have prevented the further worsening of the reactors.
  • 14. The worst case scenario • Reactor unit #4 lost the building roof←H2 leak • The spent fuel pool exposed directly to the air No confinement vessel if radio activity leaks • The sfp is much more radio active. • The sfp needed water cooling. • Dry up feared ← The cooling stopped ←SBO • “after shock” feared • Evacuation of 30M metropolitan people possible • Unexpected water supply to sfp from neighbor.
  • 15. Spent fuel rods for ca. 10 years stored.     To introduce water in emergency, the pressure must be released by “vent”. Gasket sealant Several t ons/h H2 Suppression chamber Reactor container Pressure vessel Spent fuel rod pool BWR reactor of Fukushima Daiichi
  • 16. Indirect/essential causes of the accident • Lack of precautions for the severe accidents better knowledge about the emergency cooling system storage of supplementary batteries matching of external electric power supplier cars knowledge of manual vent systems extension of the valve shaft for safer vent lack of vent filter rehearsal of residents to escape for evacuation • Negligence of the regulatory agencies safety guide no consideration necessary for long hour“ black-out” by the Nuclear Safety Commission Oral regulation to avoid written specifications by
  • 17. 54 nuclear reactors in Japan Only 2 on operation at the moment.
  • 19. ● : Nuclear reactors     Location of earthquakes bigger than Mg 6.0 ●    20% near Japan(50 times more frequent)   Additional special condition in Japan    
  • 20.
  • 21.
  • 22.
  • 23. People’s desire of de-nuclearization if possible Finite risk does remain. nuclear plant not “fail safe” A gigantic risk →collapse of a whole country possible + Nuclear waste negative heritage >10000yrs Are alternative energy sources feasible? Fossil energy: coal, oil, natural gas, shale gas Renewable energy: expensive initial cost unstable (intermittent) wide space needed CO2 emission, depleting resource Exceptions: Hydro Stable geothermal Low cost
  • 24. Crude oil price & import 0 10000 20000 30000 40000 50000 60000 70000 1965 1966 1967 1968 1969 1970 1971 1972 1973 1974 1975 1976 1977 1978 1979 1980 1981 1982 1983 1984 1985 1986 1987 1988 1989 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 0 2 4 6 8 10 12 14 16 ( / )原油価格 円 kℓ 原油輸入額(兆円) 円 /kℓ 兆円 年度 Energy White Paper 2011 1st oil shock ’79 2nd oil shock ‘90 Gulf war ‘05 3rd oil shock 1980 1990 2000 2010 1970 Energy import of Japan: $2000/yr person
  • 25. 0 100 200 300 400 500 600 700 800 900 1,000 2010 2012 2016 2020 2030 2040 年度 TWh発電量() 0 100 200 300 400 500 600 700 800 900 1,000 2010 2012 2016 2020 2030 2040 年度 TWh発電量() Japan Science Council Proposed options for shift Sept. 2011scenario  A scenario  B Scenario C scenario  D scenario  E scenario  F 化石燃料 再生可能エネルギー Fossil RENuc Hydrp 0 100 200 300 400 500 600 700 800 900 1,000 2010 2012 2016 2020 2030 2040 年度 TWh発電量() 0 100 200 300 400 500 600 700 800 900 1,000 2010 2012 2016 2020 2030 2040 年度 TWh発電量() 0 100 200 300 400 500 600 700 800 900 1,000 2010 2012 2016 2020 2030 2040 年度 TWh発電量() 0 100 200 300 400 500 600 700 800 900 1,000 2010 2012 2016 2010 2030 2040 年度 TWh発電量() 大規模水力 大規模水力 大規模水力 大規模水力 大規模水力 再生可能エネルギー 再生可能エネルギー 再生可能エネルギー 再生可能エネルギー 化石燃料 化石燃料 化石燃料 化石燃料 原子 力発電 原子力発電 原子力発電 原子力発電 原子力発電 2020
  • 26. 0 100 200 300 400 500 600 700 800 900 1,000 2010 2012 2016 2020 2030 年度 TWh発電量() Nucl.30% Fossile Fuel 60% Renewable 50% FY Dam hydro 9% Energy Saving Electricpower(TWh) 1% GDP (500USD/yr/person) investment needed for RE To grow to 50% of elec. power By 2020 to keep UN promise Sci.Council J 2011 Efficiency improvement
  • 27. The Empirical Rule by Kitazawa  “ Land Area determines for nuclear or de-nuclear”    Russia, China, US> India>(Chile)>Ukrain> France>Spain>Sweden>(Ecuador) Japan>Germany>Italy>Korea>Austria> Switzerland>Taiwan>Belgium  “ One Fukushima may destroy the whole country”             Additional factors: latent threat from other type of energy security economic growth more urgent for developing countries  
  • 28. Japanese policy for future energy Dec. 2012 General Election • “Democrat party government” till the end of 2012 ex-nuclear at ca. 2030 by gradual decrease • New Gov “Liberal Democratic party” “decision suspended for 3-4 years” “restart of the stopping nuclear plants as far as their safety confirmed by the new Nuclear Regulatory Authority” “Efforts paid to introduce renewable energy”
  • 29. Efficient energy conversion and energy saving Now it is the time to pay every efforts for energy saving the first. •combined cycle power generator→triple cycle •Energy saving fuel cell +gas turbine +steam turbine
  • 30. Carbon tax to provide comprehensive incentives final target 50(-80)% by 2050 Manufacturing, transportation and daily life cost of energy ↑by 2 energy saving to 1/2⇔ three important area for energy saving
  • 31. Heat pumps Thermal insulation underground heat LED Heat pumps Fuel cell + water heating (Enefarm) IH heater microwave
  • 32. CAR WEIGHTCAR WEIGHT kg HYBRID CAR EV, FC CAR FUEL CONSUMPTION FOREIGN CAR DOMESTIC CAR Energy Saving with automobiles 1/4
  • 33. ENERGY SAVING OF HOME REFREGERATOR 80% in 20 yrs Heat pumps (kWh/L/yr)
  • 34. 34 REN 2011 World Investment for Renewable E Exceeding 200 B$ /yr Becoming a gigantic world industry B$
  • 36. 36 http://www.isep.or.jp/images/press/Eneshift-ISEP20110614.pdf   Wind power accumulated capacity → >100GW   US,China: asset finance Europe: Feed-in-tariff China US Germ Spain India Denm Japan  Capacity(MW)  
  • 37. 37
  • 38. 38 http://en.wikipedia.org/wiki/Feed-in_tariff#Germany Price of electricity by solar cells in Germany 0 10 20 30 40 50 60 70 80 90 2004 2005 2006 2007 2008 2009 2010 2010 2012 Rooftop >1MW Rooftop <30kW Japanese FIT Yen/kWh FY Grid-parity at home achieved in 2010 →no more FIT needed German FIT price
  • 39. 39 39 Stability of power supply Pump-up hydro + Gas turbine Batteries + Fuel cells Typical solar cell output Typical wind mill monthly output fine cloudy rainy Taking average by connection of many Power generators desired
  • 40. Red Eléctrica de España   HP より Spanish example of adjusting for supply-demand gap ( CECRC ) 2009.12.31 Hydro Nuclear Oil/GasWind Other renewables export 0 O’clock 24 O’clock RE/total electric consumption 40-60% import
  • 41. Japanese Feed-in-Tariff • Started in 2012 July 3GW contracted for solar (doubling) easy installation 0.5 GW with wind (← slow due to regulation)       cost effectiveness highest geothermal not yet (←national park law ) good because of stability, low cost wave, tidal, ocean current: on R&D stage
  • 42. 42 Windy area Weak power transmission lines in north areas (Hokkaido and Tohoku)
  • 43. Total farmland abandoned House land Needed area to support total electricity roof Solar Panel Area Needed 3960km2 46100km2 21500 km24000km2 6550km2 63km2 20km 圏内 1820km2 43 Parking area
  • 45. 45 45 Hywind Floating Windmill (Norway) http://webronza.asahi.com/ global/2011041400011.html Off-shore Floating Windmill Wind lens type with fish cultivation pool Kyushu Univ. Prof. Kyozuka Lower noise by 10dB Output enhancement 3X No bird strike fish culture pond
  • 46. 4646 0 250 500 750 1 ,000 1 ,250 1 ,500 1 ,750 2,000 2,250 2,500 2,750 3,000 2010 総 発 電 量 ( 実 績 ) 2010 原 子 力 ( 実 績 ) 太 陽 光 風 力 (陸 上 ) 風 力 (洋 上 ) 地 熱 中 小 水 力 等 環境省「平成 22 年度度再生可能エネルギー導入ポテンシャル調査」 か ら試算 ※ 原子力は資源エネルギー庁統計より TWh 46 Electricity generated 2010 Nuclear 2010 Solar W ind (land) W ind (off shore) Geotherm al Sm all hydro potential development of RE in Japan Assumption: The current legal and cost status (Ministry of Environments)
  • 47. Which direction to go? • Japanese import of fossil fuel max in 2008 $2,000/y/person • Electric power total sales $1,300 (2010) • Nuclear energy share (30%) $400 • Investment needed for RE $500 fast case • Investment for transmission line $100 • Solar power: 30% for panels, 70% for the rest • Population 125M GDP/person $45,000 • Total expenditure for amusement $8,000 • Education of children $500 • net income from overseas investment $1,000 What is worth to be paid? What do we live for? RE industry? Amusement? Moral?, happiness?
  • 48.
  • 49. land shortage problems Ichihara-shi, Chiba Pref. proposed by Nagashima & Matsuoka Solar sharing :Cell stripe and interval space to leave enough light for agriculture 。 49 Growth rate saturates with light intensity
  • 50. Farm lands and solar cell • Farm houses with wider roofs • doubling of peasant’s income possible 14000$ →28000$ by 200m2 solar panel good timing for Tohoku area restoration ←FIT, restoration policy    pension plan for local enterprises    low risk with 6% interest rate →Fishery + wind mill
  • 51. • JST (ALCA project for game changing tech.) Japan Science and Technology Agency • NEDO (road map R&D for commercialization) New Energy Development Organization Researches at universities (game changing technologies)
  • 52. Organic liquid Si Prof. Shimoda (JAIST) organic molecular thin film solar cell Mitsubishi Chem. > 10% Prof. E.Nakamura (Tokyo Univ) Si painting?
  • 53. Umena Y., Kawakami K., Shen J.-R., Kamiya N. Nature:   473,Pages:55–60   (05 May 2011) Crystal structure of oxygen-evolving photosystem II (Okayama, Osaka city Univ) Distorted Chair str. Mn Mn M Ca O O O O O Mn PHOTOSYNTHESIS  ARTIFICIAL PHOTOSYNTHESIS
  • 54. Efforts toward artificial photo synthesis • Tokyo Univ. Prof. Domen, Honda-Fujishima H2 evolution photo-catalyst (TiO2) • Tokyo Metropolitan Univ. Prof. Inoue Organic complex photo-catalyst
  • 55. Performance revolution in 2005 HTS cable 臨 界 電 流 x 線 材 長 さLxIc(77K) Tc 20 years needed to enhance Ic
  • 56. 56 150 230 超電導ケーブル 150 管路 既存CV ケーブル 600800 2100 340 水冷管 トラフ 洞道 ~ 66kV HTS Cable 66kV Switching Station 66kV Switching Station 684MW 684kV 500kV (Existing Conduit) Conventional Cable HTS Cable 100% shield (New & Large Diameter Tunnel ) ~ ~ 275kV 275kV S/S 275kV S/S 66kV 66kV 684MW 684MW 275kV ~ 500kV Substation mm mm (T. Hara et al., Advances in Superconductivity II, (1990) 1059.) YOKOHAMA HTS Cable Project HTS Cable Demonstration Project in Live Grid •66kV - 2kA - 200MVA Bi2223 wire • ~ 250 meter long, One cable-to-cable Joint
  • 57. The 1st practical superconducting cable To be instaled in Sapporo in 2014. Data center – power plant Planned to extend the superconducting Low-V large-I line to wind mills.
  • 58. K. Kitazawa “Newton”   Jan. (2001) Global Superconducting Grid with natural renewable energy resources
  • 59. Global superconducting grid No loss in transmission (DC mode)
  • 60. JR type MAGLEV test since 1964 SC perp- etual magnet Ground coil(Cu) Ground Propul- sion coil levitation propulsion
  • 61. 推進コイル ガイドウェイ 超電導磁石 浮上・案内兼用コイル Superconducting MAGLEV Japan Railway Company 2025 Tokyo-Nagoya Propulsion coil Levitation and guide coil Guide way SC magnet Perpetual current mode
  • 62. ☆No limit on traveling speed     business speed : 500km/h (2,000km/h possible under depressurized atmosphere)     Jet Aircraft: 1,000km/h ☆No exhaust gas ☆Quieter than automobiles ☆Energy saving: one-third of domestic airplanes ☆Safer than railways Floating clearance (10cm)     Volume supported (not point contact) ☆Ease of maintenance: resistant to sand, earthquakes, and snow superconducting MAGLEV (JR) Yamanashi test line