TellusVenture
Associates
®
Maintaining control of
wireless permits and
adapting to AB 57
requirements
8 March 2016
Shot clocks designed
for fast decisions: yes
or no
• Same rules but new process

• Requires change of culture

• 150 day clock = less than 90 days
working time

• Assume colocations fall under 60-day
clock

• No more back and forth with
applicants
TellusVenture Associates
Front load application
process
• Justification for less than 150-day window

• All state & federal permits, licenses done

• Photo simulations, including future modifications

• CEQA studies, including seasonal bio surveys

• All information for all local permits, e.g.
encroachment

• Valid permit for existing structures

• Neighborhood meeting
TellusVenture Associates
Encourage
pre-application
consultation
• Allow waivers for favored designs,
locations such as facade mounts, light
poles

• Fast track city property, ROW

• If OK waive neighborhood meeting,
allow negative declaration

• Denial of waiver is denial of application
TellusVenture Associates
Set up review for
quick initial decision
• Publish detailed checklist

• Request additional info within 30 days

• Administrative approval/denial without
hearing

• Incomplete application, design
changes grounds for denial

• No additions, changes, amendments
without mutual agreement to pause
(toll)
TellusVenture Associates
Automatic appeal of denials
to city council
5 days to appeal approvals,
assume clock keeps running
TellusVenture Associates
Establish stringent standard
permit conditions
Waivers only possible by
affirmative grant
TellusVenture Associates
TellusVenture
Associates
®
TellusVenture Associates
Contact:

Steve Blum

Tellus Venture Associates

+1-831-582-0700

steveblum@tellusventure.com

www.tellusventure.com
Adapting to AB 57 requirements
8 March 2016

Mais conteúdo relacionado

Destaque

Five Broadband Trends Shaping Communities, Urban Land Institute Summary, 16 M...
Five Broadband Trends Shaping Communities, Urban Land Institute Summary, 16 M...Five Broadband Trends Shaping Communities, Urban Land Institute Summary, 16 M...
Five Broadband Trends Shaping Communities, Urban Land Institute Summary, 16 M...Stephen Blum
 
Economics of municipal wireless Internet utilities
Economics of municipal wireless Internet utilitiesEconomics of municipal wireless Internet utilities
Economics of municipal wireless Internet utilitiesStephen Blum
 
Five Broadband Trends Shaping Communities, 19 September 2013
Five Broadband Trends Shaping Communities, 19 September 2013Five Broadband Trends Shaping Communities, 19 September 2013
Five Broadband Trends Shaping Communities, 19 September 2013Stephen Blum
 
East Bay Broadband Infrastructure Report Card
East Bay Broadband Infrastructure Report CardEast Bay Broadband Infrastructure Report Card
East Bay Broadband Infrastructure Report CardStephen Blum
 
Taft community broadband planning workshop
Taft community broadband planning workshopTaft community broadband planning workshop
Taft community broadband planning workshopStephen Blum
 
Operations-based financial analysis of FTTH system proposals
Operations-based financial analysis of FTTH system proposalsOperations-based financial analysis of FTTH system proposals
Operations-based financial analysis of FTTH system proposalsStephen Blum
 
Control of the Courtroom
Control of the CourtroomControl of the Courtroom
Control of the CourtroomKelly Croy
 
Forensic Linguistics:The Practical Applications
Forensic Linguistics:The Practical ApplicationsForensic Linguistics:The Practical Applications
Forensic Linguistics:The Practical Applicationsdahveed123
 

Destaque (10)

Five Broadband Trends Shaping Communities, Urban Land Institute Summary, 16 M...
Five Broadband Trends Shaping Communities, Urban Land Institute Summary, 16 M...Five Broadband Trends Shaping Communities, Urban Land Institute Summary, 16 M...
Five Broadband Trends Shaping Communities, Urban Land Institute Summary, 16 M...
 
Economics of municipal wireless Internet utilities
Economics of municipal wireless Internet utilitiesEconomics of municipal wireless Internet utilities
Economics of municipal wireless Internet utilities
 
Five Broadband Trends Shaping Communities, 19 September 2013
Five Broadband Trends Shaping Communities, 19 September 2013Five Broadband Trends Shaping Communities, 19 September 2013
Five Broadband Trends Shaping Communities, 19 September 2013
 
East Bay Broadband Infrastructure Report Card
East Bay Broadband Infrastructure Report CardEast Bay Broadband Infrastructure Report Card
East Bay Broadband Infrastructure Report Card
 
Taft community broadband planning workshop
Taft community broadband planning workshopTaft community broadband planning workshop
Taft community broadband planning workshop
 
Operations-based financial analysis of FTTH system proposals
Operations-based financial analysis of FTTH system proposalsOperations-based financial analysis of FTTH system proposals
Operations-based financial analysis of FTTH system proposals
 
Control of the Courtroom
Control of the CourtroomControl of the Courtroom
Control of the Courtroom
 
Eat That Frog!
Eat That Frog!Eat That Frog!
Eat That Frog!
 
Eat That Frog
Eat That FrogEat That Frog
Eat That Frog
 
Forensic Linguistics:The Practical Applications
Forensic Linguistics:The Practical ApplicationsForensic Linguistics:The Practical Applications
Forensic Linguistics:The Practical Applications
 

Semelhante a Maintain control of wireless permits and adapting to AB 57 requirements

Solar-friendly Permitting and Zoning
Solar-friendly Permitting and ZoningSolar-friendly Permitting and Zoning
Solar-friendly Permitting and ZoningSolarizeWC
 
As9104 1 changes auditing tim lee 3-12-12
As9104 1 changes auditing  tim lee 3-12-12As9104 1 changes auditing  tim lee 3-12-12
As9104 1 changes auditing tim lee 3-12-12QualityGuy5
 
TWCA Annual Convention: TWCA Contested Case Hearing Reform, Derek Seal
TWCA Annual Convention: TWCA Contested Case Hearing Reform, Derek SealTWCA Annual Convention: TWCA Contested Case Hearing Reform, Derek Seal
TWCA Annual Convention: TWCA Contested Case Hearing Reform, Derek SealTWCA
 
Facilities 101...be an insider
Facilities 101...be an insiderFacilities 101...be an insider
Facilities 101...be an insiderrichlandcollegetx
 
Arfat Resume 15-03-2016
Arfat Resume 15-03-2016Arfat Resume 15-03-2016
Arfat Resume 15-03-2016Arfat Khan
 
Partnering For Success In 2015
Partnering For Success In 2015Partnering For Success In 2015
Partnering For Success In 2015Lance Moseley
 
The Land Development Life Cycle
The Land Development Life CycleThe Land Development Life Cycle
The Land Development Life CycleFairfax County
 
Richard Nussbaum, PE, RG, MDNR, Hazardous Waste Program Permits Section Updat...
Richard Nussbaum, PE, RG, MDNR, Hazardous Waste Program Permits Section Updat...Richard Nussbaum, PE, RG, MDNR, Hazardous Waste Program Permits Section Updat...
Richard Nussbaum, PE, RG, MDNR, Hazardous Waste Program Permits Section Updat...Kevin Perry
 
Greg Southorn CV 2017
Greg Southorn CV 2017Greg Southorn CV 2017
Greg Southorn CV 2017Greg Southorn
 
Maintaining Business Continuity During Your Lab Relocation
Maintaining Business Continuity During Your Lab RelocationMaintaining Business Continuity During Your Lab Relocation
Maintaining Business Continuity During Your Lab RelocationTriumvirate Environmental
 
How to start a Factory or Manufacturing business in India
How to start a Factory or Manufacturing business in IndiaHow to start a Factory or Manufacturing business in India
How to start a Factory or Manufacturing business in Indiastartupscratch
 
General guidelines for building commissioning ppt
General guidelines  for building  commissioning pptGeneral guidelines  for building  commissioning ppt
General guidelines for building commissioning pptDayasagar Govidaraju
 
General guidelines for building commissioning ppt.pptx
General guidelines  for building  commissioning ppt.pptxGeneral guidelines  for building  commissioning ppt.pptx
General guidelines for building commissioning ppt.pptxDayasagar Govidaraju
 

Semelhante a Maintain control of wireless permits and adapting to AB 57 requirements (20)

Accela 2015 - Inspection Scheduling
Accela 2015 - Inspection SchedulingAccela 2015 - Inspection Scheduling
Accela 2015 - Inspection Scheduling
 
Solar-friendly Permitting and Zoning
Solar-friendly Permitting and ZoningSolar-friendly Permitting and Zoning
Solar-friendly Permitting and Zoning
 
As9104 1 changes auditing tim lee 3-12-12
As9104 1 changes auditing  tim lee 3-12-12As9104 1 changes auditing  tim lee 3-12-12
As9104 1 changes auditing tim lee 3-12-12
 
Claims
ClaimsClaims
Claims
 
TWCA Annual Convention: TWCA Contested Case Hearing Reform, Derek Seal
TWCA Annual Convention: TWCA Contested Case Hearing Reform, Derek SealTWCA Annual Convention: TWCA Contested Case Hearing Reform, Derek Seal
TWCA Annual Convention: TWCA Contested Case Hearing Reform, Derek Seal
 
Facilities 101...be an insider
Facilities 101...be an insiderFacilities 101...be an insider
Facilities 101...be an insider
 
Arfat Resume 15-03-2016
Arfat Resume 15-03-2016Arfat Resume 15-03-2016
Arfat Resume 15-03-2016
 
Partnering For Success In 2015
Partnering For Success In 2015Partnering For Success In 2015
Partnering For Success In 2015
 
The Land Development Life Cycle
The Land Development Life CycleThe Land Development Life Cycle
The Land Development Life Cycle
 
DreamNotion Innovations - How We Work
DreamNotion Innovations - How We WorkDreamNotion Innovations - How We Work
DreamNotion Innovations - How We Work
 
Richard Nussbaum, PE, RG, MDNR, Hazardous Waste Program Permits Section Updat...
Richard Nussbaum, PE, RG, MDNR, Hazardous Waste Program Permits Section Updat...Richard Nussbaum, PE, RG, MDNR, Hazardous Waste Program Permits Section Updat...
Richard Nussbaum, PE, RG, MDNR, Hazardous Waste Program Permits Section Updat...
 
Greg Southorn CV 2017
Greg Southorn CV 2017Greg Southorn CV 2017
Greg Southorn CV 2017
 
Maintaining Business Continuity During Your Lab Relocation
Maintaining Business Continuity During Your Lab RelocationMaintaining Business Continuity During Your Lab Relocation
Maintaining Business Continuity During Your Lab Relocation
 
2018 Leadership Training Chapter 36 101
2018 Leadership Training Chapter 36 1012018 Leadership Training Chapter 36 101
2018 Leadership Training Chapter 36 101
 
Concurrency Developer's Forum 11/2015
Concurrency Developer's Forum 11/2015Concurrency Developer's Forum 11/2015
Concurrency Developer's Forum 11/2015
 
How to start a Factory or Manufacturing business in India
How to start a Factory or Manufacturing business in IndiaHow to start a Factory or Manufacturing business in India
How to start a Factory or Manufacturing business in India
 
General guidelines for building commissioning ppt
General guidelines  for building  commissioning pptGeneral guidelines  for building  commissioning ppt
General guidelines for building commissioning ppt
 
General guidelines for building commissioning ppt.pptx
General guidelines  for building  commissioning ppt.pptxGeneral guidelines  for building  commissioning ppt.pptx
General guidelines for building commissioning ppt.pptx
 
Ashrae standards development
Ashrae standards development Ashrae standards development
Ashrae standards development
 
Beeville MLT_ Chapter 36 Fundamentals_Bill Dugat
Beeville MLT_ Chapter 36 Fundamentals_Bill DugatBeeville MLT_ Chapter 36 Fundamentals_Bill Dugat
Beeville MLT_ Chapter 36 Fundamentals_Bill Dugat
 

Último

Android Application Components with Implementation & Examples
Android Application Components with Implementation & ExamplesAndroid Application Components with Implementation & Examples
Android Application Components with Implementation & ExamplesChandrakantDivate1
 
Mobile Application Development-Android and It’s Tools
Mobile Application Development-Android and It’s ToolsMobile Application Development-Android and It’s Tools
Mobile Application Development-Android and It’s ToolsChandrakantDivate1
 
Satara Call girl escort *74796//13122* Call me punam call girls 24*7hour avai...
Satara Call girl escort *74796//13122* Call me punam call girls 24*7hour avai...Satara Call girl escort *74796//13122* Call me punam call girls 24*7hour avai...
Satara Call girl escort *74796//13122* Call me punam call girls 24*7hour avai...nishasame66
 
Mobile Application Development-Components and Layouts
Mobile Application Development-Components and LayoutsMobile Application Development-Components and Layouts
Mobile Application Development-Components and LayoutsChandrakantDivate1
 
Mobile App Penetration Testing Bsides312
Mobile App Penetration Testing Bsides312Mobile App Penetration Testing Bsides312
Mobile App Penetration Testing Bsides312wphillips114
 

Último (6)

Android Application Components with Implementation & Examples
Android Application Components with Implementation & ExamplesAndroid Application Components with Implementation & Examples
Android Application Components with Implementation & Examples
 
Mobile Application Development-Android and It’s Tools
Mobile Application Development-Android and It’s ToolsMobile Application Development-Android and It’s Tools
Mobile Application Development-Android and It’s Tools
 
Satara Call girl escort *74796//13122* Call me punam call girls 24*7hour avai...
Satara Call girl escort *74796//13122* Call me punam call girls 24*7hour avai...Satara Call girl escort *74796//13122* Call me punam call girls 24*7hour avai...
Satara Call girl escort *74796//13122* Call me punam call girls 24*7hour avai...
 
Obat Penggugur Kandungan Di Apotik Kimia Farma (087776558899)
Obat Penggugur Kandungan Di Apotik Kimia Farma (087776558899)Obat Penggugur Kandungan Di Apotik Kimia Farma (087776558899)
Obat Penggugur Kandungan Di Apotik Kimia Farma (087776558899)
 
Mobile Application Development-Components and Layouts
Mobile Application Development-Components and LayoutsMobile Application Development-Components and Layouts
Mobile Application Development-Components and Layouts
 
Mobile App Penetration Testing Bsides312
Mobile App Penetration Testing Bsides312Mobile App Penetration Testing Bsides312
Mobile App Penetration Testing Bsides312
 

Maintain control of wireless permits and adapting to AB 57 requirements

  • 1. TellusVenture Associates ® Maintaining control of wireless permits and adapting to AB 57 requirements 8 March 2016
  • 2. Shot clocks designed for fast decisions: yes or no • Same rules but new process • Requires change of culture • 150 day clock = less than 90 days working time • Assume colocations fall under 60-day clock • No more back and forth with applicants TellusVenture Associates
  • 3. Front load application process • Justification for less than 150-day window • All state & federal permits, licenses done • Photo simulations, including future modifications • CEQA studies, including seasonal bio surveys • All information for all local permits, e.g. encroachment • Valid permit for existing structures • Neighborhood meeting TellusVenture Associates
  • 4. Encourage pre-application consultation • Allow waivers for favored designs, locations such as facade mounts, light poles • Fast track city property, ROW • If OK waive neighborhood meeting, allow negative declaration • Denial of waiver is denial of application TellusVenture Associates
  • 5. Set up review for quick initial decision • Publish detailed checklist • Request additional info within 30 days • Administrative approval/denial without hearing • Incomplete application, design changes grounds for denial • No additions, changes, amendments without mutual agreement to pause (toll) TellusVenture Associates
  • 6. Automatic appeal of denials to city council 5 days to appeal approvals, assume clock keeps running TellusVenture Associates
  • 7. Establish stringent standard permit conditions Waivers only possible by affirmative grant TellusVenture Associates
  • 8. TellusVenture Associates ® TellusVenture Associates Contact: Steve Blum Tellus Venture Associates +1-831-582-0700 steveblum@tellusventure.com www.tellusventure.com Adapting to AB 57 requirements 8 March 2016