SlideShare uma empresa Scribd logo
1 de 107
Baixar para ler offline
Overview of
Distribution Network
Distribution Network
SHANKER RAHMAN
WHAT IS A DISTRIBUTION SYSTEM?
- DEFINITION
- LOCATION
UNERSTANDING WHAT IS A DISTRIBUTION SYSTEM
- LOCATION
- FUNCTION
- COMPONENTS
- BUSINESS MODEL
CHAPTER 1
Distribution Network
By Definition
WHAT IS A DISTRIBUTION SYSTEM?
- DEFINITION
Definition
Distribution system composed of all electrical parts
that are required to distribute power from bulk
power sources to customers.
Generally Distribution System is referred to the
portion of the utility power system between
Transmission network and Customer’s service
entrance.
Location Within the Power System
Transmission:
Transmission line up to & inclusive of bulk power
substation (main intake or PMU) that consist of
transmission power transformer
Distribution:
Substations with distribution power transformer (PPU),
primary feeders, distribution switching station (SSU),
Substation with distribution transformer (PE), secondary
feeders and services
POWER FLOW DIAGRAM
GENERATION DISTRIBUTION
TRANSMISSION CONSUMER
- Hidro
- Steam
- Diesel
- C/Cycle
- O/head
- U/ground
- S/Marine
- Domestic
- Commercial
- LPC
MV & LV
SUB STATION
CABLE OVER HEAD METERING
12 kV 132kV
33kV
33kV
11kV
PPU
POWER
TRANSMISSION
LINE
U/G & O/H
SUBTRANSMISSION LINE
12 kV
132kV 11kV
415V/240V
415V/240V
PMU
POWER
STATION
PE
PE
PIMARY FEEDER (U/G & O/H)
SSU
SECONDARY FEEDER (U/G & O/H)
CHAPTER 2
Distribution Network
By Function
Function of Distribution System
To deliver electrical energy from the
transmission or small generating station
(embedded generation) to customers while
(embedded generation) to customers while
transforming to a suitable applications.
MAIN ACTIVITIES IN DISTRIBUTION
● DISTRIBUTION PLANNING
- Reinforcement of MV system (MSVT)
- New Supply
● DISTRIBUTION PROJECT
Focus on new-supply projects
- Cable (MV & LV) construction
- Overhead (MV & LV) construction
- Substation (MV & LV) construction
● DISTRIBUTION PROTECTION
- Protection coordination within TNB network
- Protection coordination between TNB and Customer
- Protection relay testing & calibration
MAIN ACTIVITIES IN DISTRIBUTION
● DISTRIBUTION OPERATION & MAINTENANCE
- Maintenance of Cable (MV & LV)
- Maintenance of Overhead (MV & LV)
- Maintenance of Substation (MV & LV)
- MSVR & MSVT projects
● METERING
- Installation of new meter (whole current meter, CT-meter)
- Schedule replacement of meter (whole current)
- Meter maintenance
- Meter testing and calibration
● DISTRIBUTION SERVICE
- LV Single phase (Overhead line, Five-foot-way)
- LV Three phase (Overhead line, Five-foot-way, Underground
cable))
MAIN ACTIVITIES IN DISTRIBUTION
● STREET LIGHTHING
- Installation
- Maintenance
● CUSTOMER SERVICE
- New supply application (individual, group)
- Meter reading & Billing
- Meter reading & Billing
- Collection & banking
- Change of tenancy
- Change of tariff
- Individual street light
- Credit control & disconnection
- Bank guarantee management
- Revenue assurance & Back-billing
CHAPTER 3
Distribution Network
By Components
Distribution System Components
Distribution System can be divided into three major
components:
Bulk power substations
Bulk power substations
It receives power from the transmission system and
transform it to a subtransmission voltage by means of
Transmission Power Transformer
Primary Feeder
It is the system between subtransmission line and
secondary feeder. Distribution Power Transformer
(33/11 kV) separates the primary feeder from
subtransmission line and; Distribution Transformer
(11/0.415 kV) separates the primary feeder from
secondary feeder.
Distribution System Components
secondary feeder.
Secondary Feeder
The secondary components of a distribution system
ends at the customer’s meter.
DISTRIBUTION VOLTAGES
THE DISTRIBUTION VOLTAGES ARE
• 33kV, 22kV, 11kV,
• 400V -3 phases
• 230V- single phase
• 230V- single phase
DISTRIBUTION SUBSTATION
● Distribution Bulk Substations – PMU (132/33kV, 132/11kV)
- Transformer capacity : 90MVA, 45MVA, 30MVA, 15MVA
- GIS substation
- AIS substation
● Distribution Primary Substations - PPU(33/11 kV, 33/22kV) & SSU
- Transformer capacity :7.5MVA, 15MVA, 30MVA,
- GIS substation
- AIS substation
- AIS substation
● Distribution Secondary Substations - PE(11/0.415 kV, 22/0.415kV)
– Transformer capacity :100kVA, 300kVA, 500kVA, 750kVA,
1MVA,
- Indoor substation
– Outdoor substation
– Pole mounted substation
– Compact substation
– Underground substation
DISTRIBUTION SUPPLY CATEGORY
1. Penc. Masuk Utama (PMU)
Transmission
Network.
275/33/11kV
132/33/11kV
132/11kV
500kV
275kV
132kV
2. Penc. Pemb. Utama (PPU)
3. Stesen Suis Utama (SSU)
4. Penc. Elektrik (PE)
LV Sys.
Dist. Sys.
33/11kV
22/11kV
33/.433kV
22/.433kV
11/.433kV
6.6/.433kV
PPU
PMU/PPU
P/E
EXAMPLE OF DISTRIBUTION NETWORK
P/E
P/E
P/E
PAT
TNB DISTRIBUTION SUBSTATION CATEGORY
1. Main Intake Substation – PMU
a. Distribution Bulk Power Substation that provide interfacing between
Transmission network and Distribution network where the Transmission
voltage is step down to Distribution voltage. PMU serves as main supply
source to:
i. First level of Distribution primary network (33kV, 11kV)
ii. Customer taking power supply at tariff-E3
b. Land size requirement - AIS 130.0 meter x 130.0 meter
b. Land size requirement - AIS 130.0 meter x 130.0 meter
- GIS 70meter x 80meter (2TX)
c. Building size requirement - Depending on requirements
d. Transformer size - 15 MVA, 30 MVA, 45MVA, 90 MVA
e. Average cost range - More than RM30 million depending
on Transformer
TNB DISTRIBUTION SUBSTATION CATEGORY
2. Main Distribution Substation – PPU
a. Distribution Primary Substation that distributes power by stepping down 33kV
voltage to 11kV or 22kV voltage as a second level of Distribution primary-
network.
i. 33kV/11kV
ii. 33kV/22kV
b. Land size requirement - 50.0 meter x 50.0 meter
c. Building size requirement -
d. Transformer size - 7.5 MVA, 15 MVA, 30MVA
e. Average cost range - RM7 Million – RM 10 Million depending
on Transformer size
TNB DISTRIBUTION SUBSTATION CATEGORY
3. Main Switching Station – SSU
a. Distribution Substation that further distributes power without voltage
transformation within the Distribution primary network (33kV, 22kV, 11kV). It
provides interfacing between various PMU and/or various PPU within the
Distribution primary network. PPU is established to facilitate:
i. Power supply to Customer buying electricity at tariff C1, C2, E1, or E2
ii. Reinforcement of Distribution supply network to ensure higher security
level
iii. Maintaining the scale of economic for power distribution at primary level
iii. Maintaining the scale of economic for power distribution at primary level
through a larger area
b. Land size requirement - 31.0 meter x 31.0 meter
c. Building size requirement - Depending on requirements
d. Transformer size - No transformer
e. Average cost range - RM 500 K to RM1 Million depending on
number of switchgear & voltage level
TNB DISTRIBUTION SUBSTATION CATEGORY
4. Low Voltage Substation – PE
a. Low Voltage Substation provides interfacing between primary network and
secondary network in Distribution system where the 11kV or 22kV voltage is
step down to 415V. It is the main source of power supply to Customer buying
electricity tariff A, B or D as well as for street lighting through LV network that
comprises of:
i. LV Board
ii. LV Feeder pillar
iii. LV Underground cable system
iii. LV Underground cable system
iv. LV Overhead line system
b. Land size requirement - single chamber
- double chamber
c. Building size requirement - Depending on requirements
d. Transformer size - 100kVA, 300kVA, 500kVA, 750kVA, 1MVA
e. Average cost range - RM 100K to RM 250K depending
on Transformer size and size of building
Pencawang Masuk Utama – PMU
(Main Intake)
DISTRIBUTION INTAKE
INDOOR SUBSTATION – DOUBLE CHAMBER
INDOOR SUBSTATION – DOUBLE CHAMBER
INDOOR SUBSTATION – SINGLE CHAMBER
OUTDOOR SUBSTATION
POLE MOUNTED SUBSTATION
POLE MOUNTED SUBSTATION
UNDERGROUND SUBSTATION
POLE MOUNTED SUBSTATION
COMPACT SUBSTATION
COMPACT SUBSTATION - Switchgear
COMPACT SUBSTATION – Low Voltage Board
11KV SUBSTATION CONSTRUCTION
Three main sections of electrical substation
1. Switchgear
- Ring Main Unit
(RMU with fuse)
- Circuit breaker
Single Line Diagram P/E
2. Distribution
Transformer
- Dyn11 11/0.415kV
3. Low Voltage
Distribution Board
SUBSTATION COMPONENT
BASIC COMPONENTS:-
SUBSTATION ENCLOSURE
• Substation building (for indoor substation)
• Fencing (for ground substation)
• Metal enclosed kiosk (for compact substation)
• Pole (for pole mounted substation)
HIGH VOLTAGE SWITCHGEAR
• Circuit breaker
• Main ring unit (c/w high voltage fuse)
• Isolator
LOW VOLTAGE SWITCHGEAR
• Low voltage distribution board
• Low voltage distribution board
• Low voltage high current fuse
DISTRIBUTION TRANSFORMER
• 3 Phase oil-filled transformer
CABLE
• High voltage cable
• Low voltage cable
EARTHING SYSTEM
• Earthing rod
• Lightning arrester
DIRECT CURRENT (DC) SYSTEM
• DC 110v
• DC 30v
DISTRIBUTION TRANSFORMER
DISTRIBUTION SWITCHGEARS
Vacuum circuit breaker (VCB)
Air circuit breaker (ACB)
Ring Main Unit (RMU)
MEDIUM VOLTAGE CABLES
• Underground
– Paper insulated cables (PILCDSTA)
– Cross linked polyethylene (XLPE)
– Oil filled
– Oil filled
• Aerial Bundled Cable
– Cross linked polyethylene (XLPE)
LOW VOLTAGE NETWORK
LV Board in 11/0.415kV Substation
250A
Feeder Pillar 1
Feeder Pillar 2
LV Under ground cable
(UGC) 300mmsq
LV -UGC
300mmsq 150A
150A
LOW VOLTAGE NETWORK
Feeder Pillar 1
LV -UGC
185mmsq
150A
150A
LV – Mains Overhead Line:
LV – Service Line:
- ABC wire
- PVC wire
LV – Mains Overhead Line:
- ABC wire
- Bare wire 200A
Terrace house
LV – Service Line:
- ABC wire
- PVC wire
LV – Service Line:
- ABC wire
- PVC wire
LV – Five Foot Way
- ABC wire
- PVC wire
160A
160A
100A
MEDIUM VOLTAGE PAPER INSULATED CABLE
(PILDSTA)
MEDIUM VOLTAGE XLPE UNDERGROUND CABLES
AERIAL XLPE
LV OVERHEAD LINES
• Bare aluminium conductors
• Aerial bundle cable
• PVC insulated conductors
RED
YELLOW
BLUE
415V
240V
240V
OVERHEAD CONDUCTORS INSULATED / BARE
BLUE
STREET LIGHTING
NEUTRAL
240V
240V
WOODEN/CONCRETE/
SPUNPOLE
LOW VOLTAGE LIVE LINE
Electrical Shock progressionE
• Slight sensation (1mA)
• Feel a “shock” but not painful (5mA)
• Painful, may invoke reflexes (10mA)
• Muscle contraction, breathing difficulty – possible
asphyxiation (50mA)
asphyxiation (50mA)
• Cardiac interference – possible fibrillation (100mA)
• Almost certain fibrillation, possible nerve damage
(1A)
• Cardiac arrest, severe burns (internal/external) (5A)
– (Note: 6A is operating parameters for Defibrillator)
5, 9, 12
CHAPTER 5
Distribution Network
By Business Model
Transmission Embedded
Generation
Supplier 1 Supplier 2
DISTRIBUTION BUSINESS MODEL
Distributio
n
Operation
s
Distributio
n Network
Operation
s
Operation
s
Electricity
Retail
Operation
s
Business
activity 1
Business
activity 2
Operation
s
Distributio
n Network
Operation
s
BUSINESS ACTIVITY 1
TNB Distribution plans, construct, operates, performs
repair & maintenance as well as manage the assets of
repair & maintenance as well as manage the assets of
the 33kV, 22kV 11kV and 415/240 Volts in Peninsula
Malaysia’s distribution network
BUSINESS ACTIVITY 2
TNB Distribution operates a network to purchase electricity from
Transmission network and from embedded generators;
Operation
s
Electricity
Retail
Operation
s
It markets and sell electricity by carrying out:
● connection of new supply
● providing customer services
● collection of revenue
● operating the call management centers
● providing supply restoration services
● cultivating strong customer and government relationships
DISTRIBUTION BUSINESS TERRITORY
High
Voltage
Customer
(Tariff E3)
Medium
Voltage
Customer
(Tariff C1,
C2, E1, E2)
Low
Voltage
Customer
(Tariff A, B,D)
Customer Segmentation
- based on meter category
Large Power Consumer (LPC):
All customers that take supply through CT-meter (normally
tariff B, C, D, E)
Ordinary Power Consumer (OPC):
All customers that take supply through whole-current-
meter (Tariff A & B)
Domestic customer:
Residential (Tariff A)
Commercial customer:
All business premises, Govt. offices, NGOs (Tariff B, C)
Industrial customer:
Customer Segmentation
- based on activity
Industrial customer:
All industrial premise premises (Tariff D, E)
Mining:
All mining activity (Tariff F)
Street lighting:
All street lighting, Flood lighting, Neon Lighting
Agriculture:
Specific agricultural activity (Tariff H)
System
voltage
Fault Level Maximum
Demand
Tariff
High
Voltage
275kV 40kA 19,030MVA E3
132kV 31.5kA 7,193.3MVA 25.0MVA<
Medium
Voltage
33kV 25kA 1,427.3MVA 25.0MVA E1, E2,
C1, C2,
F1, H1,
22kV 20kA 761.2MVA 10.0MVA
SERVICES PROVIDED FOR CUSTOMER
F1, H1,
H2
11kV 20kA 380.6MVA 5.0MVA
Low
Voltage
415V 31.5kA 22.6MVA 1.0MVA A, B, D, F,
G, G1, H
240V 31.5kA 13.1MVA 12kVA
GUARANTEE TO CUSTOMER
- RELIABILITY OF SERVICE
Voltage Level % Variation
415V & 240V -10% to +5%
6.6kV, 11kV, 22kV, 33kV ±6%
132kV & 275 kV -5% to +10%
Voltage Under Normal Condition
Voltage Level % Variation
415V & 240V ±10%
6.6kV, 11kV, 22kV, 33kV ±10%
132kV & 275 kV ±10%
Voltage Under Contingency Condition
Security Level for TNB Network
Security Level Average Restoration Period
Level 1 Less than 5 seconds
Level 2 Less than 15 minutes
Level 3 Less than 4 hours
GUARANTEE TO CUSTOMER
-RESPONSE TIME TO SERVICE INTERRUPTION
Level 4 Less than 24 hours
~ 132kV, 275kV and 500kV generally are designed to facilitate an average
supply restoration of less than 5 sec
~ 6.6kV, 11kV, 22kV, and 33kV generally are designed to facilitate an average
supply restoration of less than 4 hours
~ 240V and 415V the restoration period may vary beyond 4 hours depending
on the type of faults and/or traffic congestion level
Losses:
Non-technical losses
Revenue collection:
Average collection period
Bad debts collection
Revenue assurance & back-billing
Customer focus:
Customer complaints
BUSINESS CHALENGES
Customer complaints
Customer satisfaction
Retaining customer’s loyalty
Keeping the light on:
Reduce breakdown
Faster response to interruption
Cost per unit:
Managing CPU rise (2% - 3% annually)
Keeping CAPEX & OPEX reasonably low
POWER FLOW – IDEAL CONDITION
POWER FLOW – WITH LOSSES
CHAPTER 6
Electricity Billing
FUNDAMENTAL OF ELECTRICITY
Power Triangle
kVA
kVar
Apparent Power
Power withdrawn
from the grid
Reactive Power
Unused Power
stored in inductive
load at
kW
kVA
Active Power
Actual power
consumed to
perform work
at Customer’s
premise
load at
Customer’s premise
kVA2 = kW2 + kVar2
FUNDAMENTAL OF ELECTRICITY
x Time (hour) =
Power Energy
kW
kVA
kVar
kWh
kVarh
kVAh
kVA2 = kW2 + kVar2
kVAh2 = kWh2 + kVarh2
Power factor = kW / kVA = kWh / kVAh
ELECTRICITY BILLING COMPONENT
Bill element Tariff
A
Tariff
B
Tariff
C
Tarif
f
D
Tariff
E
Tariff
G
a Energy consumed √ √ √ √ √ √ Sales of energy usage
b Power (Max Demand) √ √ Charge for capacity
c Power factor √ √ √ √ Penalty for poor
c Power factor √ √ √ √ Penalty for poor
efficiency level of
electricity usage
d Welding charge √ Charge for capacity for
customer who does not
pay for Max demand
e Temporary supply √ Charge for supply
required for less than 6
months
ELECTRICITY BILLING COMPONENT
Bill element Tariff
A
Tariff
B
Tariff
C
Tarif
f
D
Tariff
E
Tariff
G
f Minimum monthly
charge (RM)
3.00 7.20 600.00 7.20 600.00 7.20 Minimum rental of infra if
no significant
consumption
g Connected load charge
(From second year
√ √ Charge for not meeting
declared max-demand
(From second year
onwards until 5th year) 1stFree, 2nd50%, 3rd50%,
4th75%, 5th75%
h 1% Renewable energy
charge
√ √ √ √ √ √ Charge for not meeting
declared max-demand
Free,50%,50%,75%,75%
SAMPLE DOMESTIC CONSUMPTION
Qty Power
(Watt)
Daily
usage
rate
(hour)
Daily
Energy
Consumed
(kWh)
Refrigerator 1 1200 24 28.8
Television 1 150 5 0.75
Air Conditioner 2 750 7 10.5
Iron 1 1000 0.5 0.5
Rice Cooker 1 730 0.75 0.5475
Rice Cooker 1 730 0.75 0.5475
Kettle 1 850 0.5 0.425
Washing
machine
1 850 0.75 0.6375
Standing fan 2 75 7 1.05
Lighting 12 36 5 2.16
Total daily kWh 45.37
Total monthly kWh (30days) 1361.1
SAMPLE DOMESTIC BILL
kWh Unit
Rate
(RM)
Energy
Cost
Block 1 200 0.2180 43.60
Block 2 100 0.3340 .33.40
Block 3 100 0.4000 40.00
Block 4 100 0.4020 40.20
Block 5 100 0.4160 41.60
Block 5 100 0.4160 41.60
Block 6 100 0.4260 42.60
Block 7 100 0.4370 43.70
Block 8 100 0.4530 45.30
Block 9 461.10 0.4540 209.34
Total bill (RM) 539.74
SAMPLE DOMESTIC BILL
What happen if the total bill exceed RM 600.00?
Possibilities
Increase in
consumption
connection
Unauthorize
d
connection
Billing error
Old
appliances
CHAPTER 7
e - CUSTOMER INFORMATION
BUSINESS SYSTEM
(e-CIBS)
Billing
Billing
Financial
Reporting
e-CIBS BUSINESS PROCESS
Spot Billing
Station Billing
RMR Reading
O Billing
ePOS Collection/
Agency
Debit/Credit Transfer
Banking
Bounced Cheque
Journal
Reconcile
Disconnection
Installment Plan
Stub LOA Posting Backbilling
Operational
Management
Basic SAP Navigation
System & Process Overview
Detail Transactions
SAP001
Basic SAP Navigation
ECIBS100
eCIBS Overview
e-CIBS SYSTEM & PROCESS OVERVIEW
Customer Service
(CS)
Financial
(FI)
Meter and Billing
(MB)
Workflow
(WF)
Reporting
(R)
Basic SAP Navigation
System & Process Overview
Detail Transactions
SAP001
Basic SAP Navigation
ECIBS100
eCIBS Overview
Customer Service Financial Meter and Billing Workflow Reporting
DETAILS OF CUSTOMER SERVICE
CS001
Customer Enquiry
For CS
CS102
Work Order
OPC
Customer Service
(CS)
Financial
(FI)
Meter and Billing
(MB)
Workflow
(WF)
Reporting
(R)
CS103
Work Order
LPC
CS105
Individual Street
Lighting & COTA
CS104
Group ID Contract
& Complaint Log
CS106
E-Government &
E-Services for CS
CS100
New
Connection
CS101
Change Of
Tenancy
Basic SAP Navigation
System & Process Overview
Detail Transactions
SAP001
Basic SAP Navigation
ECIBS100
eCIBS Overview
Customer Service Financial Meter and Billing Workflow Reporting
DETAILS OF FINANCIAL
FI101
Installment Plan
& Reports
FI001
Financial Overview
FI110
Disconnection
FI102
Manual Posting
& Approval
Customer Service
(CS)
Financial
(FI)
Meter and Billing
(MB)
Workflow
(WF)
Reporting
(R)
FI103
Interest on
Late Payment
FI100
Bank Guarantee
(Maintenance & Reports)
FI104
Back Billing
FI105
Banking
FI106
Refund
FI107
Stubs & Reports
FI108
Credit Control
FI109
Dunning
& Reports
FI111
Overall Epos
Processing
Basic SAP Navigation
System & Process Overview
Detail Transactions
SAP001
Basic SAP Navigation
ECIBS100
eCIBS Overview
Customer Service Financial Meter and Billing Workflow Reporting
DETAILS OF METER & BILLING
MB001
Meter Information Form
MB102
Load Profile &
Test Billable
MB107
Bill Cancellation
& Ave Cons
MB111
Substation Metering
MB112
Co-Gen
MB104
Landlords/Tenants
& Group ID
MB106
Group Billing
MB101
Unscheduled Meter
Inspection
MB103
Enhancement Sub
Metering for MS 2&3
MB105
Event & Carnival
Discounts
MB100
LPC Schedule
MB109
Remote Meter
Reading
MB108
Overall Reading Unit Processing
MB110
Station Billing & RMA Reporting
CS102 & CS103
Pre-requisite
Customer Service
(CS)
Financial
(FI)
Meter and Billing
(MB)
Workflow
(WF)
Reporting
(R)
Basic SAP Navigation
System & Process Overview
Detail Transactions
SAP001
Basic SAP Navigation
ECIBS100
eCIBS Overview
DETAILS OF METER & BILLING
eCIBS Overview
WF001
Workflow Process
WF002
Setup, Configuration
& Administration (Admin)
Customer Service
(CS)
Financial
(FI)
Meter and Billing
(MB)
Workflow
(WF)
Reporting
(R)
WF003
ABAP Query for Beginner
Basic SAP Navigation
System & Process Overview
Detail Transactions
SAP001
Basic SAP Navigation
ECIBS100
eCIBS Overview
DETAILS OF REPORTING
Customer Service
(CS)
Financial
(FI)
Meter and Billing
(MB)
Workflow
(WF)
Reporting
(R)
MR001
Management Reporting
MR001
Operational Reporting
Supply Application
Supply Application
Types of supply application
A. Supply applications – by load category
• Low Voltage Supply application for load up to 100 kVA without
substation (maximum processing period = 3 weeks provided way
leave is acquired)
• Low Voltage Supply application for load exceeding 100 kVA
requiring substation (maximum processing period = 3 month,
• Low Voltage Supply application for load exceeding 100 kVA
requiring substation (maximum processing period = 3 month,
provided way leave is acquired)
• Medium Voltage Supply (11kV & 33kV) application for load 1MVA –
25MVA (maximum processing period = 3 years, provided way
leave is acquired)
• High Voltage Supply (132kV) application for load exceeding
25MVA (processing period = 3 - 5years, provided way leave is
acquired)
Types of supply application
B Mode of supply application – by nature of supply
• New supply
i. Customers that require new service line from the existing supply
mains.
ii. Developers that require new supply mains and services in a
Supply Application
ii. Developers that require new supply mains and services in a
development area.
• Additional supply
Customer that require additional load from the existing supply
mains to cater for any extension.
• Change of tenancy
Termination of old supply contract and registration of new supply
contract at a particular premise with existing supply mains
available.
Types of supply application
B Mode of supply application – by nature of supply
• Temporary supply
Customer that require electricity supply for a period less than 6 months
only and intended for purposes of electricity supply for temporary work
site, festival and celebrations.
Supply Application
• Standby supply
Customer that generate electricity supply by themselves and require
synchronization with TNB for additional supply security.
• Co-Generation
Industrial consumers whose processes require electricity and heat or
steam, may plan cogeneration of such energies from suitable plant, and
request synchronization with TNB supply system.
Special features of new supply project
• Alternative source of supply
Customer that require an alternative source of supply for added
security.
• Additional feeder
Customer that require additional service feeder for added
Supply Application
Customer that require additional service feeder for added
security.
• HDD technique to lay underground cable
• Installation of compact substation
• Underground service cable design for housing project
Customer Service
Customer Service
Screen Overview
Customer Services
Customer Service
Customer Service
Module
Module
- Can be done thru TNB Kedai Tenaga or
internet Register
New Connection
Menu Path
New Connection Process
Individual Application
Stages
Group Application
Stages
New Connection Process
Application Type
Application Type
Choose the correct type of NC :
Individual Application :
New Connection Process
Application Type :
01 – Individual
07 – Rewiring
(for upgrading ie. 1Ǿ to 3Ǿ)
Project :
02 – Group
04 – Metered Street Light/ Tel Booth
light Group
Project Individual :
03 – Group Individual
05 - Metered Street Light/ Tel Booth
light Group Individual
How to create NC ?
New Connection Process
• Goto this Area
Menu.
• Double click
Step 1
• Enter <Station Code>
• Choose the correct
<Application Type>
New Connection Process
Note :
1.Group Reference Number
is referring to NC type 2 or
NC Type 4.
2.Customer number is
referring to customer
number created thru NC
Type 2 or NC Type 4.
• Step 2
• Choose the correct
Account Type.
New Connection Process
Note :
• 01 – Customer with New IC.
• 02 – Customer with Old
IC/Police ID/Army
ID/Passport
• Step 2
• Customer Request Date
– Defaulted to 23 working
days. Why ?
New Connection Process
days. Why ?
• Estimation – 7 days
• Service Installation after
connection charge
paid – 14 days
• Meter Installation after
deposit paid – 2 days
Step 2
– For temporary supply :
1.Tick temporary supply
check box.
New Connection Process
check box.
2.Enter Contract End Date
• Submit Date
– Date customer
submitted supply
application form.
Choose a valid
New Connection Process
Choose a valid
contactor number.
Note :
Only active
contractors
appears on the
selection list.
symbol is a
mandatory field.
Enter :
1.< Customer Name>
2.<IC Number New>
New Connection Process
2.<IC Number New>
3.<Premis Status>
4.<Premis Number>
5.<Street Number>
Note :
Please enter other
information for
reference.
Tab Concept
Bill can be sent
by Post. To send
check Bill By Post.
New Connection Process
check Bill By Post.
Enter postal
address
Tab Concept
Bill can be sent by
Post.
Enter postal address
New Connection Process
Enter postal address
Enter info in Ref
Contacts tab Director
Info tab.
Note : At least 1
director info must be
keyed in.
Site Visit is the stage where all
physical estimation is captured.
 Estimation value must be
entered correctly either thru LKKK
or BKKM.
New Connection Process
or BKKM.
 Connection charge must be
printed and served upon
completion of data entry for
customer to make payment.
At this stage the correct
info must be entered:
Type of work
Customer category
New Connection Process
Customer category
Business Code
Tariff Code
Supply Voltage Code
Average Consumption
After connection charge
paid by customer, service
installation must be made.
Work Order 10 for service
installation must be created
New Connection Process
installation must be created
and updated.
Allow user to maintain Work
Order without exiting NC.
Double click Work Order
number in blue color to
maintain Work Order
Deposit type divided
into 4:
i. Cash
ii. Bank Guarantee
iii. Cash  Bank
New Connection Process
iii. Cash  Bank
Guarantee
iv. Exempted
•Exempted Category
•Exempted Category
•Corporate Cust Class
New Connection Process
Exempted Category
 Staff – 8 digit Staff
Number and Corporate
Cust Class 9991 must be
entered.
 Free Unit – Corporate
Cust Class 9992 must be
entered.
Klik Save – Work Order 11 diwujudkan
New Connection Process
Klik Yes untuk kemaskini pesanan kerja
NC Report

Mais conteúdo relacionado

Mais procurados

Electric vehicles
Electric vehiclesElectric vehicles
Electric vehiclesYash Shinde
 
comparison of fuel cell based hybrid vehicles with other alternative systems
comparison of fuel cell based hybrid vehicles with other alternative systemscomparison of fuel cell based hybrid vehicles with other alternative systems
comparison of fuel cell based hybrid vehicles with other alternative systemsreddyprasad reddyvari
 
Activity file class 12.pdf
Activity file class 12.pdfActivity file class 12.pdf
Activity file class 12.pdfHaniSankhwar
 
Project Report for Solar Technology
Project Report for Solar TechnologyProject Report for Solar Technology
Project Report for Solar TechnologySOUMYA DATTA
 
Renewable Energy Sources in Pakistan
Renewable Energy Sources in PakistanRenewable Energy Sources in Pakistan
Renewable Energy Sources in PakistanEngineer Salman
 
Fuel cell vehicles and electric vehicles in futureby rai asad sahi
Fuel cell vehicles and electric vehicles in futureby rai asad sahiFuel cell vehicles and electric vehicles in futureby rai asad sahi
Fuel cell vehicles and electric vehicles in futureby rai asad sahiMuhammad Sahi
 
Basics of electric vehicle simulations using ansys
Basics of electric vehicle simulations using ansysBasics of electric vehicle simulations using ansys
Basics of electric vehicle simulations using ansysPasalaAnilKumarNaidu
 
Hydrogen Fuel Cell vehicles.pptx
Hydrogen Fuel Cell vehicles.pptxHydrogen Fuel Cell vehicles.pptx
Hydrogen Fuel Cell vehicles.pptxMaqboolPT
 
SOLAR ENERGY TRACKER SYSTEM SEMINAR REPORT
SOLAR ENERGY TRACKER SYSTEM  SEMINAR REPORTSOLAR ENERGY TRACKER SYSTEM  SEMINAR REPORT
SOLAR ENERGY TRACKER SYSTEM SEMINAR REPORTeeeraviriet
 
Super capacitors and Battery power management for Hybrid Vehicle Applications...
Super capacitors and Battery power management for Hybrid VehicleApplications...Super capacitors and Battery power management for Hybrid VehicleApplications...
Super capacitors and Battery power management for Hybrid Vehicle Applications...Pradeep Avanigadda
 
Electric Vehicle: A Power Engineer's Perspective
Electric Vehicle: A Power Engineer's PerspectiveElectric Vehicle: A Power Engineer's Perspective
Electric Vehicle: A Power Engineer's PerspectiveKrishnakumar R. Vasudevan
 
Batteries
BatteriesBatteries
Batteriesebabe
 
Regenerative breaking system
 Regenerative breaking system Regenerative breaking system
Regenerative breaking systemABIRAJ R
 
IMPLEMENTATION OF ENERGY MANAGEMENT SYSTEM TO IMPROVE ENERGY EFFICIENCY
IMPLEMENTATION OF ENERGY MANAGEMENT SYSTEM TO IMPROVE ENERGY EFFICIENCY IMPLEMENTATION OF ENERGY MANAGEMENT SYSTEM TO IMPROVE ENERGY EFFICIENCY
IMPLEMENTATION OF ENERGY MANAGEMENT SYSTEM TO IMPROVE ENERGY EFFICIENCY ZAINI ABDUL WAHAB
 
Hydrogen production using solar energy (PV cell)
Hydrogen production using solar energy (PV cell)Hydrogen production using solar energy (PV cell)
Hydrogen production using solar energy (PV cell)Mohamed Bn Younes
 

Mais procurados (20)

Electric vehicles
Electric vehiclesElectric vehicles
Electric vehicles
 
Hydrogen fuel cell
Hydrogen fuel cellHydrogen fuel cell
Hydrogen fuel cell
 
comparison of fuel cell based hybrid vehicles with other alternative systems
comparison of fuel cell based hybrid vehicles with other alternative systemscomparison of fuel cell based hybrid vehicles with other alternative systems
comparison of fuel cell based hybrid vehicles with other alternative systems
 
Activity file class 12.pdf
Activity file class 12.pdfActivity file class 12.pdf
Activity file class 12.pdf
 
Project Report for Solar Technology
Project Report for Solar TechnologyProject Report for Solar Technology
Project Report for Solar Technology
 
Fuel cell thermodynamics (2)
Fuel cell thermodynamics (2)Fuel cell thermodynamics (2)
Fuel cell thermodynamics (2)
 
Renewable Energy Sources in Pakistan
Renewable Energy Sources in PakistanRenewable Energy Sources in Pakistan
Renewable Energy Sources in Pakistan
 
Seminar Report on MPPT
Seminar Report on MPPTSeminar Report on MPPT
Seminar Report on MPPT
 
Fuel cell vehicles and electric vehicles in futureby rai asad sahi
Fuel cell vehicles and electric vehicles in futureby rai asad sahiFuel cell vehicles and electric vehicles in futureby rai asad sahi
Fuel cell vehicles and electric vehicles in futureby rai asad sahi
 
Basics of electric vehicle simulations using ansys
Basics of electric vehicle simulations using ansysBasics of electric vehicle simulations using ansys
Basics of electric vehicle simulations using ansys
 
Hydrogen Fuel Cell vehicles.pptx
Hydrogen Fuel Cell vehicles.pptxHydrogen Fuel Cell vehicles.pptx
Hydrogen Fuel Cell vehicles.pptx
 
Hybrid Electric Vehicle
Hybrid Electric VehicleHybrid Electric Vehicle
Hybrid Electric Vehicle
 
SOLAR ENERGY TRACKER SYSTEM SEMINAR REPORT
SOLAR ENERGY TRACKER SYSTEM  SEMINAR REPORTSOLAR ENERGY TRACKER SYSTEM  SEMINAR REPORT
SOLAR ENERGY TRACKER SYSTEM SEMINAR REPORT
 
Super capacitors and Battery power management for Hybrid Vehicle Applications...
Super capacitors and Battery power management for Hybrid VehicleApplications...Super capacitors and Battery power management for Hybrid VehicleApplications...
Super capacitors and Battery power management for Hybrid Vehicle Applications...
 
Electric Vehicle: A Power Engineer's Perspective
Electric Vehicle: A Power Engineer's PerspectiveElectric Vehicle: A Power Engineer's Perspective
Electric Vehicle: A Power Engineer's Perspective
 
Batteries
BatteriesBatteries
Batteries
 
Regenerative breaking system
 Regenerative breaking system Regenerative breaking system
Regenerative breaking system
 
SOLAR VEHICA
SOLAR VEHICASOLAR VEHICA
SOLAR VEHICA
 
IMPLEMENTATION OF ENERGY MANAGEMENT SYSTEM TO IMPROVE ENERGY EFFICIENCY
IMPLEMENTATION OF ENERGY MANAGEMENT SYSTEM TO IMPROVE ENERGY EFFICIENCY IMPLEMENTATION OF ENERGY MANAGEMENT SYSTEM TO IMPROVE ENERGY EFFICIENCY
IMPLEMENTATION OF ENERGY MANAGEMENT SYSTEM TO IMPROVE ENERGY EFFICIENCY
 
Hydrogen production using solar energy (PV cell)
Hydrogen production using solar energy (PV cell)Hydrogen production using solar energy (PV cell)
Hydrogen production using solar energy (PV cell)
 

Semelhante a it-lecture-distribution-rev-3-dec-2013.pdf

Transmission and distribution system of electricity
Transmission and distribution system of electricity Transmission and distribution system of electricity
Transmission and distribution system of electricity anjali s
 
Introduction to electric power transmission and distribution
Introduction to electric power transmission and distributionIntroduction to electric power transmission and distribution
Introduction to electric power transmission and distributionABDULRAHMANALGHANIM
 
NMRC Summer Tanning/Internship PPT(Anand Mohan )
NMRC Summer Tanning/Internship PPT(Anand Mohan )NMRC Summer Tanning/Internship PPT(Anand Mohan )
NMRC Summer Tanning/Internship PPT(Anand Mohan )AnandMohan271812
 
Design of substation
Design of substationDesign of substation
Design of substationSayanSarkar55
 
45 16255 ee543_2015_1__2_1_week_1_2
45 16255 ee543_2015_1__2_1_week_1_245 16255 ee543_2015_1__2_1_week_1_2
45 16255 ee543_2015_1__2_1_week_1_2Durga Prasada Rao M
 
Report on 220kv substation at Jassure
Report on 220kv substation at JassureReport on 220kv substation at Jassure
Report on 220kv substation at JassureShuvam Pathania
 
Electric power transmission full explanation and presentation
Electric power transmission full explanation and presentationElectric power transmission full explanation and presentation
Electric power transmission full explanation and presentationRakesh Gurjar
 
industrial-training-at-howrah-220-kv-substation.pptx
industrial-training-at-howrah-220-kv-substation.pptxindustrial-training-at-howrah-220-kv-substation.pptx
industrial-training-at-howrah-220-kv-substation.pptxShubhoDas5
 
Lab manual psd v sem experiment no 7
Lab manual psd v sem experiment no 7Lab manual psd v sem experiment no 7
Lab manual psd v sem experiment no 7Sachin Airan
 
LEC #01 INTRODUCTION to power distribution system
LEC #01 INTRODUCTION to power distribution systemLEC #01 INTRODUCTION to power distribution system
LEC #01 INTRODUCTION to power distribution systemMuhammadAliImran11
 
Report on industrial summer training on 220 kv substation
Report  on industrial summer training on 220 kv substationReport  on industrial summer training on 220 kv substation
Report on industrial summer training on 220 kv substationAshutosh Srivastava
 
m1-akm-distribution system design layout.pptx
m1-akm-distribution system design layout.pptxm1-akm-distribution system design layout.pptx
m1-akm-distribution system design layout.pptxmuhammadzaid733820
 
electrical power distribustion system
electrical   power  distribustion  systemelectrical   power  distribustion  system
electrical power distribustion systemSengotecholanS
 
Indoor &amp; outdoor substations, an overview
Indoor &amp; outdoor substations, an overviewIndoor &amp; outdoor substations, an overview
Indoor &amp; outdoor substations, an overviewH. Kheir
 
substation internship report
substation internship report substation internship report
substation internship report Arun Thapa
 
Basic Mechanical & Electrical Application in Construction Industry
Basic Mechanical & Electrical Application in Construction IndustryBasic Mechanical & Electrical Application in Construction Industry
Basic Mechanical & Electrical Application in Construction IndustryHassanulHadiZakaria
 

Semelhante a it-lecture-distribution-rev-3-dec-2013.pdf (20)

Transmission and distribution system of electricity
Transmission and distribution system of electricity Transmission and distribution system of electricity
Transmission and distribution system of electricity
 
Introduction to electric power transmission and distribution
Introduction to electric power transmission and distributionIntroduction to electric power transmission and distribution
Introduction to electric power transmission and distribution
 
NMRC Summer Tanning/Internship PPT(Anand Mohan )
NMRC Summer Tanning/Internship PPT(Anand Mohan )NMRC Summer Tanning/Internship PPT(Anand Mohan )
NMRC Summer Tanning/Internship PPT(Anand Mohan )
 
Design of substation
Design of substationDesign of substation
Design of substation
 
45 16255 ee543_2015_1__2_1_week_1_2
45 16255 ee543_2015_1__2_1_week_1_245 16255 ee543_2015_1__2_1_week_1_2
45 16255 ee543_2015_1__2_1_week_1_2
 
Report on 220kv substation at Jassure
Report on 220kv substation at JassureReport on 220kv substation at Jassure
Report on 220kv substation at Jassure
 
Electric power transmission full explanation and presentation
Electric power transmission full explanation and presentationElectric power transmission full explanation and presentation
Electric power transmission full explanation and presentation
 
industrial-training-at-howrah-220-kv-substation.pptx
industrial-training-at-howrah-220-kv-substation.pptxindustrial-training-at-howrah-220-kv-substation.pptx
industrial-training-at-howrah-220-kv-substation.pptx
 
Lab manual psd v sem experiment no 7
Lab manual psd v sem experiment no 7Lab manual psd v sem experiment no 7
Lab manual psd v sem experiment no 7
 
LEC #01 INTRODUCTION to power distribution system
LEC #01 INTRODUCTION to power distribution systemLEC #01 INTRODUCTION to power distribution system
LEC #01 INTRODUCTION to power distribution system
 
Report on industrial summer training on 220 kv substation
Report  on industrial summer training on 220 kv substationReport  on industrial summer training on 220 kv substation
Report on industrial summer training on 220 kv substation
 
m1-akm-distribution system design layout.pptx
m1-akm-distribution system design layout.pptxm1-akm-distribution system design layout.pptx
m1-akm-distribution system design layout.pptx
 
33kv substation
33kv substation33kv substation
33kv substation
 
electrical power distribustion system
electrical   power  distribustion  systemelectrical   power  distribustion  system
electrical power distribustion system
 
Indoor &amp; outdoor substations, an overview
Indoor &amp; outdoor substations, an overviewIndoor &amp; outdoor substations, an overview
Indoor &amp; outdoor substations, an overview
 
substation internship report
substation internship report substation internship report
substation internship report
 
Ashwani kumar
Ashwani kumarAshwani kumar
Ashwani kumar
 
finalseminar.docx
finalseminar.docxfinalseminar.docx
finalseminar.docx
 
Basic Mechanical & Electrical Application in Construction Industry
Basic Mechanical & Electrical Application in Construction IndustryBasic Mechanical & Electrical Application in Construction Industry
Basic Mechanical & Electrical Application in Construction Industry
 
Electric power grid
Electric power gridElectric power grid
Electric power grid
 

Último

UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01KreezheaRecto
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...SUHANI PANDEY
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringmulugeta48
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Christo Ananth
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLManishPatel169454
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 

Último (20)

UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 

it-lecture-distribution-rev-3-dec-2013.pdf

  • 2. WHAT IS A DISTRIBUTION SYSTEM? - DEFINITION - LOCATION UNERSTANDING WHAT IS A DISTRIBUTION SYSTEM - LOCATION - FUNCTION - COMPONENTS - BUSINESS MODEL
  • 4. WHAT IS A DISTRIBUTION SYSTEM? - DEFINITION Definition Distribution system composed of all electrical parts that are required to distribute power from bulk power sources to customers. Generally Distribution System is referred to the portion of the utility power system between Transmission network and Customer’s service entrance.
  • 5. Location Within the Power System Transmission: Transmission line up to & inclusive of bulk power substation (main intake or PMU) that consist of transmission power transformer Distribution: Substations with distribution power transformer (PPU), primary feeders, distribution switching station (SSU), Substation with distribution transformer (PE), secondary feeders and services
  • 6. POWER FLOW DIAGRAM GENERATION DISTRIBUTION TRANSMISSION CONSUMER - Hidro - Steam - Diesel - C/Cycle - O/head - U/ground - S/Marine - Domestic - Commercial - LPC MV & LV SUB STATION CABLE OVER HEAD METERING
  • 7. 12 kV 132kV 33kV 33kV 11kV PPU POWER TRANSMISSION LINE U/G & O/H SUBTRANSMISSION LINE 12 kV 132kV 11kV 415V/240V 415V/240V PMU POWER STATION PE PE PIMARY FEEDER (U/G & O/H) SSU SECONDARY FEEDER (U/G & O/H)
  • 9. Function of Distribution System To deliver electrical energy from the transmission or small generating station (embedded generation) to customers while (embedded generation) to customers while transforming to a suitable applications.
  • 10. MAIN ACTIVITIES IN DISTRIBUTION ● DISTRIBUTION PLANNING - Reinforcement of MV system (MSVT) - New Supply ● DISTRIBUTION PROJECT Focus on new-supply projects - Cable (MV & LV) construction - Overhead (MV & LV) construction - Substation (MV & LV) construction ● DISTRIBUTION PROTECTION - Protection coordination within TNB network - Protection coordination between TNB and Customer - Protection relay testing & calibration
  • 11. MAIN ACTIVITIES IN DISTRIBUTION ● DISTRIBUTION OPERATION & MAINTENANCE - Maintenance of Cable (MV & LV) - Maintenance of Overhead (MV & LV) - Maintenance of Substation (MV & LV) - MSVR & MSVT projects ● METERING - Installation of new meter (whole current meter, CT-meter) - Schedule replacement of meter (whole current) - Meter maintenance - Meter testing and calibration ● DISTRIBUTION SERVICE - LV Single phase (Overhead line, Five-foot-way) - LV Three phase (Overhead line, Five-foot-way, Underground cable))
  • 12. MAIN ACTIVITIES IN DISTRIBUTION ● STREET LIGHTHING - Installation - Maintenance ● CUSTOMER SERVICE - New supply application (individual, group) - Meter reading & Billing - Meter reading & Billing - Collection & banking - Change of tenancy - Change of tariff - Individual street light - Credit control & disconnection - Bank guarantee management - Revenue assurance & Back-billing
  • 14. Distribution System Components Distribution System can be divided into three major components: Bulk power substations Bulk power substations It receives power from the transmission system and transform it to a subtransmission voltage by means of Transmission Power Transformer
  • 15. Primary Feeder It is the system between subtransmission line and secondary feeder. Distribution Power Transformer (33/11 kV) separates the primary feeder from subtransmission line and; Distribution Transformer (11/0.415 kV) separates the primary feeder from secondary feeder. Distribution System Components secondary feeder. Secondary Feeder The secondary components of a distribution system ends at the customer’s meter.
  • 16. DISTRIBUTION VOLTAGES THE DISTRIBUTION VOLTAGES ARE • 33kV, 22kV, 11kV, • 400V -3 phases • 230V- single phase • 230V- single phase
  • 17. DISTRIBUTION SUBSTATION ● Distribution Bulk Substations – PMU (132/33kV, 132/11kV) - Transformer capacity : 90MVA, 45MVA, 30MVA, 15MVA - GIS substation - AIS substation ● Distribution Primary Substations - PPU(33/11 kV, 33/22kV) & SSU - Transformer capacity :7.5MVA, 15MVA, 30MVA, - GIS substation - AIS substation - AIS substation ● Distribution Secondary Substations - PE(11/0.415 kV, 22/0.415kV) – Transformer capacity :100kVA, 300kVA, 500kVA, 750kVA, 1MVA, - Indoor substation – Outdoor substation – Pole mounted substation – Compact substation – Underground substation
  • 18. DISTRIBUTION SUPPLY CATEGORY 1. Penc. Masuk Utama (PMU) Transmission Network. 275/33/11kV 132/33/11kV 132/11kV 500kV 275kV 132kV 2. Penc. Pemb. Utama (PPU) 3. Stesen Suis Utama (SSU) 4. Penc. Elektrik (PE) LV Sys. Dist. Sys. 33/11kV 22/11kV 33/.433kV 22/.433kV 11/.433kV 6.6/.433kV
  • 19. PPU PMU/PPU P/E EXAMPLE OF DISTRIBUTION NETWORK P/E P/E P/E PAT
  • 20. TNB DISTRIBUTION SUBSTATION CATEGORY 1. Main Intake Substation – PMU a. Distribution Bulk Power Substation that provide interfacing between Transmission network and Distribution network where the Transmission voltage is step down to Distribution voltage. PMU serves as main supply source to: i. First level of Distribution primary network (33kV, 11kV) ii. Customer taking power supply at tariff-E3 b. Land size requirement - AIS 130.0 meter x 130.0 meter b. Land size requirement - AIS 130.0 meter x 130.0 meter - GIS 70meter x 80meter (2TX) c. Building size requirement - Depending on requirements d. Transformer size - 15 MVA, 30 MVA, 45MVA, 90 MVA e. Average cost range - More than RM30 million depending on Transformer
  • 21. TNB DISTRIBUTION SUBSTATION CATEGORY 2. Main Distribution Substation – PPU a. Distribution Primary Substation that distributes power by stepping down 33kV voltage to 11kV or 22kV voltage as a second level of Distribution primary- network. i. 33kV/11kV ii. 33kV/22kV b. Land size requirement - 50.0 meter x 50.0 meter c. Building size requirement - d. Transformer size - 7.5 MVA, 15 MVA, 30MVA e. Average cost range - RM7 Million – RM 10 Million depending on Transformer size
  • 22. TNB DISTRIBUTION SUBSTATION CATEGORY 3. Main Switching Station – SSU a. Distribution Substation that further distributes power without voltage transformation within the Distribution primary network (33kV, 22kV, 11kV). It provides interfacing between various PMU and/or various PPU within the Distribution primary network. PPU is established to facilitate: i. Power supply to Customer buying electricity at tariff C1, C2, E1, or E2 ii. Reinforcement of Distribution supply network to ensure higher security level iii. Maintaining the scale of economic for power distribution at primary level iii. Maintaining the scale of economic for power distribution at primary level through a larger area b. Land size requirement - 31.0 meter x 31.0 meter c. Building size requirement - Depending on requirements d. Transformer size - No transformer e. Average cost range - RM 500 K to RM1 Million depending on number of switchgear & voltage level
  • 23. TNB DISTRIBUTION SUBSTATION CATEGORY 4. Low Voltage Substation – PE a. Low Voltage Substation provides interfacing between primary network and secondary network in Distribution system where the 11kV or 22kV voltage is step down to 415V. It is the main source of power supply to Customer buying electricity tariff A, B or D as well as for street lighting through LV network that comprises of: i. LV Board ii. LV Feeder pillar iii. LV Underground cable system iii. LV Underground cable system iv. LV Overhead line system b. Land size requirement - single chamber - double chamber c. Building size requirement - Depending on requirements d. Transformer size - 100kVA, 300kVA, 500kVA, 750kVA, 1MVA e. Average cost range - RM 100K to RM 250K depending on Transformer size and size of building
  • 24. Pencawang Masuk Utama – PMU (Main Intake)
  • 26. INDOOR SUBSTATION – DOUBLE CHAMBER
  • 27. INDOOR SUBSTATION – DOUBLE CHAMBER
  • 28. INDOOR SUBSTATION – SINGLE CHAMBER
  • 35. COMPACT SUBSTATION - Switchgear
  • 36. COMPACT SUBSTATION – Low Voltage Board
  • 37. 11KV SUBSTATION CONSTRUCTION Three main sections of electrical substation 1. Switchgear - Ring Main Unit (RMU with fuse) - Circuit breaker Single Line Diagram P/E 2. Distribution Transformer - Dyn11 11/0.415kV 3. Low Voltage Distribution Board
  • 38. SUBSTATION COMPONENT BASIC COMPONENTS:- SUBSTATION ENCLOSURE • Substation building (for indoor substation) • Fencing (for ground substation) • Metal enclosed kiosk (for compact substation) • Pole (for pole mounted substation) HIGH VOLTAGE SWITCHGEAR • Circuit breaker • Main ring unit (c/w high voltage fuse) • Isolator LOW VOLTAGE SWITCHGEAR • Low voltage distribution board • Low voltage distribution board • Low voltage high current fuse DISTRIBUTION TRANSFORMER • 3 Phase oil-filled transformer CABLE • High voltage cable • Low voltage cable EARTHING SYSTEM • Earthing rod • Lightning arrester DIRECT CURRENT (DC) SYSTEM • DC 110v • DC 30v
  • 39.
  • 41. DISTRIBUTION SWITCHGEARS Vacuum circuit breaker (VCB) Air circuit breaker (ACB) Ring Main Unit (RMU)
  • 42. MEDIUM VOLTAGE CABLES • Underground – Paper insulated cables (PILCDSTA) – Cross linked polyethylene (XLPE) – Oil filled – Oil filled • Aerial Bundled Cable – Cross linked polyethylene (XLPE)
  • 43. LOW VOLTAGE NETWORK LV Board in 11/0.415kV Substation 250A Feeder Pillar 1 Feeder Pillar 2 LV Under ground cable (UGC) 300mmsq LV -UGC 300mmsq 150A 150A
  • 44. LOW VOLTAGE NETWORK Feeder Pillar 1 LV -UGC 185mmsq 150A 150A LV – Mains Overhead Line: LV – Service Line: - ABC wire - PVC wire LV – Mains Overhead Line: - ABC wire - Bare wire 200A Terrace house LV – Service Line: - ABC wire - PVC wire LV – Service Line: - ABC wire - PVC wire LV – Five Foot Way - ABC wire - PVC wire 160A 160A 100A
  • 45. MEDIUM VOLTAGE PAPER INSULATED CABLE (PILDSTA)
  • 46. MEDIUM VOLTAGE XLPE UNDERGROUND CABLES
  • 48. LV OVERHEAD LINES • Bare aluminium conductors • Aerial bundle cable • PVC insulated conductors
  • 49. RED YELLOW BLUE 415V 240V 240V OVERHEAD CONDUCTORS INSULATED / BARE BLUE STREET LIGHTING NEUTRAL 240V 240V WOODEN/CONCRETE/ SPUNPOLE
  • 51. Electrical Shock progressionE • Slight sensation (1mA) • Feel a “shock” but not painful (5mA) • Painful, may invoke reflexes (10mA) • Muscle contraction, breathing difficulty – possible asphyxiation (50mA) asphyxiation (50mA) • Cardiac interference – possible fibrillation (100mA) • Almost certain fibrillation, possible nerve damage (1A) • Cardiac arrest, severe burns (internal/external) (5A) – (Note: 6A is operating parameters for Defibrillator) 5, 9, 12
  • 53. Transmission Embedded Generation Supplier 1 Supplier 2 DISTRIBUTION BUSINESS MODEL Distributio n Operation s Distributio n Network Operation s Operation s Electricity Retail Operation s Business activity 1 Business activity 2
  • 54. Operation s Distributio n Network Operation s BUSINESS ACTIVITY 1 TNB Distribution plans, construct, operates, performs repair & maintenance as well as manage the assets of repair & maintenance as well as manage the assets of the 33kV, 22kV 11kV and 415/240 Volts in Peninsula Malaysia’s distribution network
  • 55. BUSINESS ACTIVITY 2 TNB Distribution operates a network to purchase electricity from Transmission network and from embedded generators; Operation s Electricity Retail Operation s It markets and sell electricity by carrying out: ● connection of new supply ● providing customer services ● collection of revenue ● operating the call management centers ● providing supply restoration services ● cultivating strong customer and government relationships
  • 56. DISTRIBUTION BUSINESS TERRITORY High Voltage Customer (Tariff E3) Medium Voltage Customer (Tariff C1, C2, E1, E2) Low Voltage Customer (Tariff A, B,D)
  • 57. Customer Segmentation - based on meter category Large Power Consumer (LPC): All customers that take supply through CT-meter (normally tariff B, C, D, E) Ordinary Power Consumer (OPC): All customers that take supply through whole-current- meter (Tariff A & B)
  • 58. Domestic customer: Residential (Tariff A) Commercial customer: All business premises, Govt. offices, NGOs (Tariff B, C) Industrial customer: Customer Segmentation - based on activity Industrial customer: All industrial premise premises (Tariff D, E) Mining: All mining activity (Tariff F) Street lighting: All street lighting, Flood lighting, Neon Lighting Agriculture: Specific agricultural activity (Tariff H)
  • 59. System voltage Fault Level Maximum Demand Tariff High Voltage 275kV 40kA 19,030MVA E3 132kV 31.5kA 7,193.3MVA 25.0MVA< Medium Voltage 33kV 25kA 1,427.3MVA 25.0MVA E1, E2, C1, C2, F1, H1, 22kV 20kA 761.2MVA 10.0MVA SERVICES PROVIDED FOR CUSTOMER F1, H1, H2 11kV 20kA 380.6MVA 5.0MVA Low Voltage 415V 31.5kA 22.6MVA 1.0MVA A, B, D, F, G, G1, H 240V 31.5kA 13.1MVA 12kVA
  • 60. GUARANTEE TO CUSTOMER - RELIABILITY OF SERVICE Voltage Level % Variation 415V & 240V -10% to +5% 6.6kV, 11kV, 22kV, 33kV ±6% 132kV & 275 kV -5% to +10% Voltage Under Normal Condition Voltage Level % Variation 415V & 240V ±10% 6.6kV, 11kV, 22kV, 33kV ±10% 132kV & 275 kV ±10% Voltage Under Contingency Condition
  • 61. Security Level for TNB Network Security Level Average Restoration Period Level 1 Less than 5 seconds Level 2 Less than 15 minutes Level 3 Less than 4 hours GUARANTEE TO CUSTOMER -RESPONSE TIME TO SERVICE INTERRUPTION Level 4 Less than 24 hours ~ 132kV, 275kV and 500kV generally are designed to facilitate an average supply restoration of less than 5 sec ~ 6.6kV, 11kV, 22kV, and 33kV generally are designed to facilitate an average supply restoration of less than 4 hours ~ 240V and 415V the restoration period may vary beyond 4 hours depending on the type of faults and/or traffic congestion level
  • 62. Losses: Non-technical losses Revenue collection: Average collection period Bad debts collection Revenue assurance & back-billing Customer focus: Customer complaints BUSINESS CHALENGES Customer complaints Customer satisfaction Retaining customer’s loyalty Keeping the light on: Reduce breakdown Faster response to interruption Cost per unit: Managing CPU rise (2% - 3% annually) Keeping CAPEX & OPEX reasonably low
  • 63. POWER FLOW – IDEAL CONDITION
  • 64. POWER FLOW – WITH LOSSES
  • 65.
  • 67. FUNDAMENTAL OF ELECTRICITY Power Triangle kVA kVar Apparent Power Power withdrawn from the grid Reactive Power Unused Power stored in inductive load at kW kVA Active Power Actual power consumed to perform work at Customer’s premise load at Customer’s premise kVA2 = kW2 + kVar2
  • 68. FUNDAMENTAL OF ELECTRICITY x Time (hour) = Power Energy kW kVA kVar kWh kVarh kVAh kVA2 = kW2 + kVar2 kVAh2 = kWh2 + kVarh2 Power factor = kW / kVA = kWh / kVAh
  • 69. ELECTRICITY BILLING COMPONENT Bill element Tariff A Tariff B Tariff C Tarif f D Tariff E Tariff G a Energy consumed √ √ √ √ √ √ Sales of energy usage b Power (Max Demand) √ √ Charge for capacity c Power factor √ √ √ √ Penalty for poor c Power factor √ √ √ √ Penalty for poor efficiency level of electricity usage d Welding charge √ Charge for capacity for customer who does not pay for Max demand e Temporary supply √ Charge for supply required for less than 6 months
  • 70. ELECTRICITY BILLING COMPONENT Bill element Tariff A Tariff B Tariff C Tarif f D Tariff E Tariff G f Minimum monthly charge (RM) 3.00 7.20 600.00 7.20 600.00 7.20 Minimum rental of infra if no significant consumption g Connected load charge (From second year √ √ Charge for not meeting declared max-demand (From second year onwards until 5th year) 1stFree, 2nd50%, 3rd50%, 4th75%, 5th75% h 1% Renewable energy charge √ √ √ √ √ √ Charge for not meeting declared max-demand Free,50%,50%,75%,75%
  • 71. SAMPLE DOMESTIC CONSUMPTION Qty Power (Watt) Daily usage rate (hour) Daily Energy Consumed (kWh) Refrigerator 1 1200 24 28.8 Television 1 150 5 0.75 Air Conditioner 2 750 7 10.5 Iron 1 1000 0.5 0.5 Rice Cooker 1 730 0.75 0.5475 Rice Cooker 1 730 0.75 0.5475 Kettle 1 850 0.5 0.425 Washing machine 1 850 0.75 0.6375 Standing fan 2 75 7 1.05 Lighting 12 36 5 2.16 Total daily kWh 45.37 Total monthly kWh (30days) 1361.1
  • 72. SAMPLE DOMESTIC BILL kWh Unit Rate (RM) Energy Cost Block 1 200 0.2180 43.60 Block 2 100 0.3340 .33.40 Block 3 100 0.4000 40.00 Block 4 100 0.4020 40.20 Block 5 100 0.4160 41.60 Block 5 100 0.4160 41.60 Block 6 100 0.4260 42.60 Block 7 100 0.4370 43.70 Block 8 100 0.4530 45.30 Block 9 461.10 0.4540 209.34 Total bill (RM) 539.74
  • 73. SAMPLE DOMESTIC BILL What happen if the total bill exceed RM 600.00? Possibilities Increase in consumption connection Unauthorize d connection Billing error Old appliances
  • 74. CHAPTER 7 e - CUSTOMER INFORMATION BUSINESS SYSTEM (e-CIBS)
  • 75. Billing Billing Financial Reporting e-CIBS BUSINESS PROCESS Spot Billing Station Billing RMR Reading O Billing ePOS Collection/ Agency Debit/Credit Transfer Banking Bounced Cheque Journal Reconcile Disconnection Installment Plan Stub LOA Posting Backbilling Operational Management
  • 76. Basic SAP Navigation System & Process Overview Detail Transactions SAP001 Basic SAP Navigation ECIBS100 eCIBS Overview e-CIBS SYSTEM & PROCESS OVERVIEW Customer Service (CS) Financial (FI) Meter and Billing (MB) Workflow (WF) Reporting (R)
  • 77. Basic SAP Navigation System & Process Overview Detail Transactions SAP001 Basic SAP Navigation ECIBS100 eCIBS Overview Customer Service Financial Meter and Billing Workflow Reporting DETAILS OF CUSTOMER SERVICE CS001 Customer Enquiry For CS CS102 Work Order OPC Customer Service (CS) Financial (FI) Meter and Billing (MB) Workflow (WF) Reporting (R) CS103 Work Order LPC CS105 Individual Street Lighting & COTA CS104 Group ID Contract & Complaint Log CS106 E-Government & E-Services for CS CS100 New Connection CS101 Change Of Tenancy
  • 78. Basic SAP Navigation System & Process Overview Detail Transactions SAP001 Basic SAP Navigation ECIBS100 eCIBS Overview Customer Service Financial Meter and Billing Workflow Reporting DETAILS OF FINANCIAL FI101 Installment Plan & Reports FI001 Financial Overview FI110 Disconnection FI102 Manual Posting & Approval Customer Service (CS) Financial (FI) Meter and Billing (MB) Workflow (WF) Reporting (R) FI103 Interest on Late Payment FI100 Bank Guarantee (Maintenance & Reports) FI104 Back Billing FI105 Banking FI106 Refund FI107 Stubs & Reports FI108 Credit Control FI109 Dunning & Reports FI111 Overall Epos Processing
  • 79. Basic SAP Navigation System & Process Overview Detail Transactions SAP001 Basic SAP Navigation ECIBS100 eCIBS Overview Customer Service Financial Meter and Billing Workflow Reporting DETAILS OF METER & BILLING MB001 Meter Information Form MB102 Load Profile & Test Billable MB107 Bill Cancellation & Ave Cons MB111 Substation Metering MB112 Co-Gen MB104 Landlords/Tenants & Group ID MB106 Group Billing MB101 Unscheduled Meter Inspection MB103 Enhancement Sub Metering for MS 2&3 MB105 Event & Carnival Discounts MB100 LPC Schedule MB109 Remote Meter Reading MB108 Overall Reading Unit Processing MB110 Station Billing & RMA Reporting CS102 & CS103 Pre-requisite Customer Service (CS) Financial (FI) Meter and Billing (MB) Workflow (WF) Reporting (R)
  • 80. Basic SAP Navigation System & Process Overview Detail Transactions SAP001 Basic SAP Navigation ECIBS100 eCIBS Overview DETAILS OF METER & BILLING eCIBS Overview WF001 Workflow Process WF002 Setup, Configuration & Administration (Admin) Customer Service (CS) Financial (FI) Meter and Billing (MB) Workflow (WF) Reporting (R) WF003 ABAP Query for Beginner
  • 81. Basic SAP Navigation System & Process Overview Detail Transactions SAP001 Basic SAP Navigation ECIBS100 eCIBS Overview DETAILS OF REPORTING Customer Service (CS) Financial (FI) Meter and Billing (MB) Workflow (WF) Reporting (R) MR001 Management Reporting MR001 Operational Reporting
  • 83. Supply Application Types of supply application A. Supply applications – by load category • Low Voltage Supply application for load up to 100 kVA without substation (maximum processing period = 3 weeks provided way leave is acquired) • Low Voltage Supply application for load exceeding 100 kVA requiring substation (maximum processing period = 3 month, • Low Voltage Supply application for load exceeding 100 kVA requiring substation (maximum processing period = 3 month, provided way leave is acquired) • Medium Voltage Supply (11kV & 33kV) application for load 1MVA – 25MVA (maximum processing period = 3 years, provided way leave is acquired) • High Voltage Supply (132kV) application for load exceeding 25MVA (processing period = 3 - 5years, provided way leave is acquired)
  • 84. Types of supply application B Mode of supply application – by nature of supply • New supply i. Customers that require new service line from the existing supply mains. ii. Developers that require new supply mains and services in a Supply Application ii. Developers that require new supply mains and services in a development area. • Additional supply Customer that require additional load from the existing supply mains to cater for any extension. • Change of tenancy Termination of old supply contract and registration of new supply contract at a particular premise with existing supply mains available.
  • 85. Types of supply application B Mode of supply application – by nature of supply • Temporary supply Customer that require electricity supply for a period less than 6 months only and intended for purposes of electricity supply for temporary work site, festival and celebrations. Supply Application • Standby supply Customer that generate electricity supply by themselves and require synchronization with TNB for additional supply security. • Co-Generation Industrial consumers whose processes require electricity and heat or steam, may plan cogeneration of such energies from suitable plant, and request synchronization with TNB supply system.
  • 86. Special features of new supply project • Alternative source of supply Customer that require an alternative source of supply for added security. • Additional feeder Customer that require additional service feeder for added Supply Application Customer that require additional service feeder for added security. • HDD technique to lay underground cable • Installation of compact substation • Underground service cable design for housing project
  • 87. Customer Service Customer Service Screen Overview Customer Services Customer Service Customer Service Module Module
  • 88. - Can be done thru TNB Kedai Tenaga or internet Register New Connection
  • 91. Application Type Application Type Choose the correct type of NC : Individual Application : New Connection Process Application Type : 01 – Individual 07 – Rewiring (for upgrading ie. 1Ǿ to 3Ǿ) Project : 02 – Group 04 – Metered Street Light/ Tel Booth light Group Project Individual : 03 – Group Individual 05 - Metered Street Light/ Tel Booth light Group Individual
  • 92. How to create NC ? New Connection Process • Goto this Area Menu. • Double click
  • 93. Step 1 • Enter <Station Code> • Choose the correct <Application Type> New Connection Process Note : 1.Group Reference Number is referring to NC type 2 or NC Type 4. 2.Customer number is referring to customer number created thru NC Type 2 or NC Type 4.
  • 94. • Step 2 • Choose the correct Account Type. New Connection Process Note : • 01 – Customer with New IC. • 02 – Customer with Old IC/Police ID/Army ID/Passport
  • 95. • Step 2 • Customer Request Date – Defaulted to 23 working days. Why ? New Connection Process days. Why ? • Estimation – 7 days • Service Installation after connection charge paid – 14 days • Meter Installation after deposit paid – 2 days
  • 96. Step 2 – For temporary supply : 1.Tick temporary supply check box. New Connection Process check box. 2.Enter Contract End Date • Submit Date – Date customer submitted supply application form.
  • 97. Choose a valid New Connection Process Choose a valid contactor number. Note : Only active contractors appears on the selection list.
  • 98. symbol is a mandatory field. Enter : 1.< Customer Name> 2.<IC Number New> New Connection Process 2.<IC Number New> 3.<Premis Status> 4.<Premis Number> 5.<Street Number> Note : Please enter other information for reference.
  • 99. Tab Concept Bill can be sent by Post. To send check Bill By Post. New Connection Process check Bill By Post. Enter postal address
  • 100. Tab Concept Bill can be sent by Post. Enter postal address New Connection Process Enter postal address Enter info in Ref Contacts tab Director Info tab. Note : At least 1 director info must be keyed in.
  • 101. Site Visit is the stage where all physical estimation is captured. Estimation value must be entered correctly either thru LKKK or BKKM. New Connection Process or BKKM. Connection charge must be printed and served upon completion of data entry for customer to make payment.
  • 102. At this stage the correct info must be entered: Type of work Customer category New Connection Process Customer category Business Code Tariff Code Supply Voltage Code Average Consumption
  • 103. After connection charge paid by customer, service installation must be made. Work Order 10 for service installation must be created New Connection Process installation must be created and updated. Allow user to maintain Work Order without exiting NC. Double click Work Order number in blue color to maintain Work Order
  • 104. Deposit type divided into 4: i. Cash ii. Bank Guarantee iii. Cash Bank New Connection Process iii. Cash Bank Guarantee iv. Exempted •Exempted Category
  • 105. •Exempted Category •Corporate Cust Class New Connection Process Exempted Category Staff – 8 digit Staff Number and Corporate Cust Class 9991 must be entered. Free Unit – Corporate Cust Class 9992 must be entered.
  • 106. Klik Save – Work Order 11 diwujudkan New Connection Process Klik Yes untuk kemaskini pesanan kerja