SlideShare uma empresa Scribd logo
1 de 32
Baixar para ler offline
(EVM-1848)
CIS "Utilization of Earned Value
Management for Monitoring Production
Facilities"
Dmitriy Skorobogatov
Elena Rybina
BIO of Elena Rybina
• Degree
Specialist Degree (Developing spacecraft and upper stages)
• University
Bauman Moscow Technical State University (Graduate)
• Years of experience
8 years in professional fields listed below
• Professional fields
Project management, software development, cost control
• Something what you do not know about me
I worked in Siberia in winter
2
BIO of Dmitriy Skorobogatov
• Degree
Specialist Degree (Theoretical and Experimental Physics of
Nuclear Reactors)
• University
National Research Nuclear University MEPhI, Moscow (Graduate)
Institute of Control Sciences V.A. Trapeznikov , Moscow (Ph.D-student)
• Years of experience
7 years in professional fields listed below
• Professional fields
Project management, consulting
• Something what you do not know about me
My experience in nuclear science and barmen skills help me
to figure out EVM
3
SETTING THE OBJECTIVES
4
5
• This presentation identifies major features, which have
significant impact on using Earned Value Management
in these projects:
The major
features
Technology intensive equipment
Plenty of utility networks
Technology intensive nature of a
schedule
Severe constraints on
commissioning dates
6
• The presentation identifies 3 key points:The key points
Measuring project progress in the context of
contractor data manipulation
Calculating EVM indices in technology
intensive projects where major equipment
represents a substantial part of the project
budget
Forecasting project execution dates and
utilizing EMV indices.
APPLYING EVM FOR EQUIPMENT
7
8
• Project progress is mainly
determined by progress of the
complete cycle: design – fabrication
– delivery – installation –
commissioning of equipment
• Delivery of equipment to the stock
does not weigh much in terms of the
project overall progress. Installation
and commissioning activities are
much more important for this
equipment.
• Current situation allows the
Contractor to manipulate with earned
value indices. To demonstrate
greater earned value and project
progress the Contractor will try to
deliver equipment as soon as
possible to ensure higher EVM
indicators
9
Activity Name Activity Type in Primavera Step Weight
Procurement request Milestone 0%
Execution of a vendor contract Task dependent activity 10%
Development of equipment drawings Task dependent activity 25%
Approval of equipment drawings Milestone 0%
Equipment fabrication Task dependent activity 45%
Acceptance of equipment by the Customer
at the fabrication company premises
Milestone 0%
Ex-works shipment Task dependent activity 5%
Delivery to the site Task dependent activity 10%
Equipment is delivered Milestone 0%
Spare part delivery Task dependent activity 2%
Documents delivery Task dependent activity 3%
• Planned cost of equipment is split into two parts: 20% of the overall cost of
equipment
is split into activities on design-fabrication-delivery and 80% - into installation
and commissioning activities.
• Cost of design-fabrication-delivery cycle is distributed through
standard series of steps in accordance with their ‘unit weight
10
Before After
Current situation allows the Contractor
to manipulate with earned value indices.
the Customer incurs financial losses,
wastes time
and does not have objective reporting
data on the project progress execution.
A ‘smooth’ S-curve is generated to reflect
the project overall progress and to
demonstrate progress for the whole cycle:
design – fabrication – delivery – installation
– commissioning.
It is no longer possible to manipulate with
EVM indices by the Contractor .
EVALUATION OF PROJECT PROGRESS IN
CONTEXT OF MANIPULATION BY THE
CONTRACTOR
11
12
• The main way of manipulation is early implementation of expensive or simple
activities contrary to the previously agreed schedule and work processes.
• The activities with lowest cost values and significant restrictions on the ultimate
intensity of work performance were deferred to the end
• Project financing is affected on an annual basis and can be adjusted quarterly,
thus earned value for the previous periods is one of the major indices taken into
account when determining the scope of finance for the next year
13
High rate of works performance (SPI>1) in
the first half of the project, and from these
data the Customer expected that the
project would be finished on time or earlier
than the planned date, but then there
happened a dramatic drop in earned value
rates, which did not change significantly
later. Finally, this project was executed
with considerable schedule delays though
the Customer could not foresee that and
timely take administrative measures
(including the decision to replace the
Contractor).
CD FD
EV
PV(t)
0
14
EV ≠0
PV=0
mEV is different from traditional earned value since it takes into account
only earned value, which occurred within the planned dates or later
15
if 𝑃𝑉𝑡 = 0
then: 𝑀𝐸𝑉𝑡 = 0
if 𝑃𝑉𝑡 ≠ 0 𝑖=0
𝑡
𝐸𝑉𝑖 = 0
𝑀𝐸𝑉𝑡 = 𝐸𝑉𝑡
if 𝑃𝑉𝑡 ≠ 0 𝑖=0
𝑡
𝐸𝑉𝑖 ≠ 0
𝑀𝐸𝑉𝑡 = 𝑖=0
𝑡
𝐸𝑉𝑖
16
*However, there is a significant condition of using mEVt index and respective derived
indices. If the activity is critical or near critical (i.e. its positive float is =<5 days) then for
such activities: 𝑀𝐸𝑉𝑡 = 𝐸𝑉𝑡
17
Before (classical EVt) After (mEVt)
CD FD
EV
time
PV(t)
0
mEV(t)
Contractor manipulates with
earned value indices.
The project was executed with
considerable schedule delays though
the Customer could not foresee that and
timely take administrative measures
CD FD
EV
PV(t)
0
Minimize the attempts of
changing the previously approved
processes of activities performance.
18
Optimistic: 𝑆𝑃𝐼 = 𝐸𝑉/𝑃𝑉
𝑃𝑒𝑠𝑠𝑖𝑚𝑖𝑠𝑡𝑖𝑐: 𝑝𝑆𝑃𝐼 = 𝑚𝐸𝑉/𝑃𝑉
𝑅𝑒𝑎𝑙𝑖𝑠𝑡𝑖𝑐: 𝑟𝑆𝑃𝐼 = (𝑆𝑃𝐼 + 𝑝𝑆𝑃𝐼)/2
19
Optimistic forecast, which is based on EV index and demonstrates optimistic
situation on earned value rates at earlier stages of the project execution
Pessimistic forecast, which is based on mEV index and demonstrates pessimistic
situation on earned value rates at earlier stages of the project execution
CD pFD time
cost
PV(t)
0
mEV(t)
EV(t)
eFD
20
• Develop real reporting on the project execution progress. This index takes into
account only the activities performed according to the plan or earlier. This allows
avoiding the situations when the Contractor intentionally tries to perform the most
expensive and quickest activities at earlier stages and deferred activities at later stages
of the project and significantly decrease the earned value rates.
• Minimize the attempts of changing the previously approved processes of
activities performance. If changing the processes of activities performance is a coercive
measure then planned earned value indices shall be repeatedly agreed with the
Customer taking into account a new schedule.
• Motivate the Contractor for real instead of falsified reduction of project
execution dates.
FORECASTING ESTIMATE COMPLETION
DATES
21
22
SPI can be calculated at any level of aggregation: both for an individual activity
and for work packages combined on the ground of various analytical attributes.
Moreover, this index can be calculated at any required level of details along the timeline,
provided that the interval to determine this index is not less than the frequency of
gathering EV actuals. The next step is proper extrapolation of this index to the remaining
scope of work.
Calculating SPI for each
Contractor
Calculating SPI for main types
of activities
23
Advantages
• Often a Contractor performs a series of
activities (i.e. various types of activities)
in a project for a long period of time, that
is why to calculate SPI index, a vast
scope of data can be used and forecasts
can be built for a long time ahead (for the
whole remaining scope of work of this
Contractor).
• The calculated SPI index allows
evaluation of a Contractor from the
viewpoint of meeting the construction
dates. Then management decisions are
made with respect to certain Contractors,
even replace the Contractor, if required.
• This technique allows maintaining a
Dictionary of involved Contractors and
their respective SPI indices. This
information can be taken into account for
future projects.
Disadvantages
• In practice, the accuracy of
planning and the degree of meeting
the planned dates mainly depends on
the type of activity and project type, not
on the Contractor.
• If a major Contractor needs to be
selected then this technique means
only averaging SPI index for all project
activities, which negatively affects the
accuracy of forecasting.
• Specialties of Business in Russia and
Commonwealth of Independent States
countries requires that many similar
projects are executed in remote areas.
Moreover, large territory of countries
makes it impossible to mobilize a lot of
the Contractor’s full-time staff and
equipment to the site.
24
Advantages
• In practice, the accuracy of planning and
the degree of meeting the planned dates
mainly depends on the type of activity and
project type, not on the Contractor.
Therefore, use of activity-related SPI index
gives more accuracy during forecasting.
• This technique allows maintaining one in-
house dictionary of activity types and apply
it at all project stages for forecasting real
dates of activities performance, which are
not contractor-related. It can be applied at
the earliest project stages when the
Contractor is not selected yet.
• This technique is efficiently applied when
one major Contractor is involved
Disadvantages
• Many efforts need to be invested to
develop and update one dictionary of
activity types with respective SPI
indices.
• Types of activities in a project are very
tightly localized in one time period,
therefore accuracy of forecasting
decreases, since forecast for a specific
type of activities can be built correctly
only before activities of this type are
completed.
• It is more difficult to make management
decisions with respect to certain
Contractors based on activity-related
SPI indices. Additional reports need to
be generated to evaluate performance
of each Contractor.
25
𝑎𝑆𝑃𝐼 𝑥 =
1
𝑐𝑇
∗
𝑡=1
𝑐𝑇
𝑎𝑆𝑃𝐼 𝑥𝑡
𝑎𝑝𝑆𝑃𝐼 𝑥=
1
𝑐𝑇
∗
𝑡=1
𝑐𝑇
𝑎𝑝𝑆𝑃𝐼 𝑥𝑡
arSPI 𝑥=(aSPI 𝑥+apSPI 𝑥)/2
cT – number of time periods from the start of activities performance to the data date
aSPIxt – contractor-averaged SPI for the ‘t’ time period.
apSPIxt - contractor-averaged pSPI for the ‘t’ time period.
arSPI 𝑥 for each ‘x’ Contractor the schedule performance index, averaged for all reporting
time periods from the project start
26
Software package, which includes Oracle® Primavera P6™“.and PM.BI
solutions, is used to forecast the project execution dates.
Oracle® Primavera P6™“.is used to develop the initial project schedule, to enter the
activities planned dates and cost, to update schedules, and to calculate EVM
traditional indices. Oracle Primavera P6® defines the following parameters for each
activity of the schedule
• Planned dates of performance
• Planned cost of activity
• Contractor for activity
performance
• Type of activity (in accordance
with in-house dictionary of
activity types)
• If project activity is critical or
near critical.
• EV value is determined during the
schedule update for all reporting
time periods from the project
start
27
I𝑚𝑝𝑜𝑟𝑡 𝑑𝑎𝑡𝑎 𝑓𝑟𝑜𝑚 𝑂𝑟𝑎𝑐𝑙𝑒 𝑃𝑟𝑖𝑚𝑎𝑣𝑒𝑟𝑎
𝐶𝑎𝑙𝑐𝑢𝑙𝑎𝑡𝑒 𝒎𝑬𝑽, for all activities and for all time periods to the data
date
arSPIx value for each ‘x’ Contractor
If the Contractor for performance of the future activities is either not
selected yet or selected but no actuals were available to calculate its
arSPI index
𝒂𝒓𝑺𝑷𝑰 =
1
𝑋
∗ 𝑥=1
𝑋
𝑎𝑟𝑆𝑃𝐼 𝑥 , arSPI –arSPIx index averaged for all
Contractors
X – overall quantity of project Contractors, for which actuals are
sufficient to calculate arSPIx index.Import data arSPIx values to Oracle Primavera
Calculate eDix=pDix* arSPIx
eDix – forecasted duration of future ‘i’ activity, performed by ‘x’
Contractor, pDix - planned duration of future ‘i’ activity, performed by
‘x’ Contractor
28
PV (t) – planned earned value curve;
EV (t) – actual earned value curve (optimistic);
mEV (t) – actual modernized earned value curve (pessimistic);
ceEV (t) – forecasted earned value curve for current plan, not taking SPI indices into
account
eEV (t) – forecasted modernized earned value curve, taking into account extrapolation of
arSPIx index to the remaining scope of project work.
CONCLUSION
29
30
Planning and monitoring of the whole design-fabrication-delivery
cycle of major equipment. ‘Smoothened’ earned value progress S-
curve, which makes it possible to calculate SPI index broken down
into the time periods.
Use of modified earned value index – mEV. This index provides
the manager an objective picture on project progress, excluding
possible attempts of manipulation with traditional EVM indices by
the Contractor. Moreover, this index calculates realistic SPI index.
Forecasting project execution dates taking into account current
dynamics of project execution. Forecasting is based on calculating
SPI index of performed activities with respect to Contractors or
activity types and further extrapolation of this index to the
remaining scope of work.
31
Project stakeholders receive unbiased information on project
progress.
Contractor is motivated to adhere to the agreed approach of
activities performance and to the agreed plans
Contractor is motivated to gain real reduction of project execution
dates instead of reduction falsified at early project stages.
QUESTIONS/COMMENTS?
(PLEASE USE MICROPHONE)
32

Mais conteúdo relacionado

Mais procurados

Project cost management a simplified approach ppt - Oracle Primavera Collab...
Project cost management   a simplified approach ppt - Oracle Primavera Collab...Project cost management   a simplified approach ppt - Oracle Primavera Collab...
Project cost management a simplified approach ppt - Oracle Primavera Collab...p6academy
 
Cost estimation techniques
Cost estimation techniquesCost estimation techniques
Cost estimation techniqueslokareminakshi
 
How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2Abdelhay Ghanem
 
Project Controls Expo 09/10 Nov London 2011 - An Introduction to Performance ...
Project Controls Expo 09/10 Nov London 2011 - An Introduction to Performance ...Project Controls Expo 09/10 Nov London 2011 - An Introduction to Performance ...
Project Controls Expo 09/10 Nov London 2011 - An Introduction to Performance ...Project Controls Expo
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-controleidalin95
 
Project controls
Project controlsProject controls
Project controlsAshok Kumar
 
Project cost & control
Project cost & controlProject cost & control
Project cost & controlAMARAYYA
 
Economics of project evaluation cpm module2
Economics of project evaluation cpm module2Economics of project evaluation cpm module2
Economics of project evaluation cpm module2ahsanrabbani
 
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJCOST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJTapesh Ajmera
 
VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesThe Vertex Companies, LLC
 
Project Controls Technician Apprentice - Joining the puzzle together by "Shan...
Project Controls Technician Apprentice - Joining the puzzle together by "Shan...Project Controls Technician Apprentice - Joining the puzzle together by "Shan...
Project Controls Technician Apprentice - Joining the puzzle together by "Shan...Project Controls Expo
 
CV_Tarun Kumar Behera
CV_Tarun Kumar BeheraCV_Tarun Kumar Behera
CV_Tarun Kumar BeheraTarun Behera
 
Critical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateCritical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateSHAZEBALIKHAN1
 

Mais procurados (20)

Project cost management
Project cost managementProject cost management
Project cost management
 
Outage planning
Outage planningOutage planning
Outage planning
 
Project cost management a simplified approach ppt - Oracle Primavera Collab...
Project cost management   a simplified approach ppt - Oracle Primavera Collab...Project cost management   a simplified approach ppt - Oracle Primavera Collab...
Project cost management a simplified approach ppt - Oracle Primavera Collab...
 
Cost estimation techniques
Cost estimation techniquesCost estimation techniques
Cost estimation techniques
 
How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2
 
Project Controls Expo 09/10 Nov London 2011 - An Introduction to Performance ...
Project Controls Expo 09/10 Nov London 2011 - An Introduction to Performance ...Project Controls Expo 09/10 Nov London 2011 - An Introduction to Performance ...
Project Controls Expo 09/10 Nov London 2011 - An Introduction to Performance ...
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-control
 
Project controls
Project controlsProject controls
Project controls
 
Project cost & control
Project cost & controlProject cost & control
Project cost & control
 
Economics of project evaluation cpm module2
Economics of project evaluation cpm module2Economics of project evaluation cpm module2
Economics of project evaluation cpm module2
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
 
ACH 216 Lecture 07 (Project Funding)
ACH 216 Lecture 07 (Project Funding)ACH 216 Lecture 07 (Project Funding)
ACH 216 Lecture 07 (Project Funding)
 
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJCOST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
 
Session B2 - Project Cost Control
Session B2 - Project Cost ControlSession B2 - Project Cost Control
Session B2 - Project Cost Control
 
VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule Analyses
 
Project Controls Technician Apprentice - Joining the puzzle together by "Shan...
Project Controls Technician Apprentice - Joining the puzzle together by "Shan...Project Controls Technician Apprentice - Joining the puzzle together by "Shan...
Project Controls Technician Apprentice - Joining the puzzle together by "Shan...
 
Chap013 4er1
Chap013 4er1Chap013 4er1
Chap013 4er1
 
005 benchmarking-kpi's
005 benchmarking-kpi's005 benchmarking-kpi's
005 benchmarking-kpi's
 
CV_Tarun Kumar Behera
CV_Tarun Kumar BeheraCV_Tarun Kumar Behera
CV_Tarun Kumar Behera
 
Critical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateCritical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel Template
 

Semelhante a (Presentation) Cis utilization of earned value management for monitoring production facilities

(Technical paper) Cis utilization of earned value management for monitoring p...
(Technical paper) Cis utilization of earned value management for monitoring p...(Technical paper) Cis utilization of earned value management for monitoring p...
(Technical paper) Cis utilization of earned value management for monitoring p...Скоробогатов Дмитрий
 
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...IRJET Journal
 
Topic 10 - Project Performance Management.pdf
Topic 10 - Project Performance Management.pdfTopic 10 - Project Performance Management.pdf
Topic 10 - Project Performance Management.pdfHuyNguyen657394
 
Tracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value ManagementTracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value ManagementIRJET Journal
 
Software project plannings
Software project planningsSoftware project plannings
Software project planningsAman Adhikari
 
Software project plannings
Software project planningsSoftware project plannings
Software project planningsAman Adhikari
 
Quantitative analysis for business decision- Program Evaluation and Review Te...
Quantitative analysis for business decision- Program Evaluation and Review Te...Quantitative analysis for business decision- Program Evaluation and Review Te...
Quantitative analysis for business decision- Program Evaluation and Review Te...Chandra Shekar Immani
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueChris Carson
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueChris Carson
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..pptPedadaSaikumar
 
A760535773_16727_28_2018_u6.ppt
A760535773_16727_28_2018_u6.pptA760535773_16727_28_2018_u6.ppt
A760535773_16727_28_2018_u6.pptRajnikantPatel45
 
EVM Without Quality is Unsuitable for Software Project & Program Management
EVM Without Quality is Unsuitable for Software Project & Program ManagementEVM Without Quality is Unsuitable for Software Project & Program Management
EVM Without Quality is Unsuitable for Software Project & Program ManagementIRJET Journal
 
Virtual design and construction
Virtual design and constructionVirtual design and construction
Virtual design and constructionAnkit Singhai
 
Time Cost Trade Off
Time Cost Trade OffTime Cost Trade Off
Time Cost Trade Offssuserfe1b72
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.pptTinotendaChivese
 
Advanced Scheduling for Large, Complex Industrial Projects
Advanced Scheduling for Large, Complex Industrial ProjectsAdvanced Scheduling for Large, Complex Industrial Projects
Advanced Scheduling for Large, Complex Industrial ProjectsJeremie Averous
 
Monitoring and information systems
Monitoring and information systemsMonitoring and information systems
Monitoring and information systemsLibra chudry
 
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...CCT International
 

Semelhante a (Presentation) Cis utilization of earned value management for monitoring production facilities (20)

(Technical paper) Cis utilization of earned value management for monitoring p...
(Technical paper) Cis utilization of earned value management for monitoring p...(Technical paper) Cis utilization of earned value management for monitoring p...
(Technical paper) Cis utilization of earned value management for monitoring p...
 
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
 
Topic 10 - Project Performance Management.pdf
Topic 10 - Project Performance Management.pdfTopic 10 - Project Performance Management.pdf
Topic 10 - Project Performance Management.pdf
 
Tracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value ManagementTracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value Management
 
Software project plannings
Software project planningsSoftware project plannings
Software project plannings
 
Software project plannings
Software project planningsSoftware project plannings
Software project plannings
 
Quantitative analysis for business decision- Program Evaluation and Review Te...
Quantitative analysis for business decision- Program Evaluation and Review Te...Quantitative analysis for business decision- Program Evaluation and Review Te...
Quantitative analysis for business decision- Program Evaluation and Review Te...
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned Value
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned Value
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
 
A760535773_16727_28_2018_u6.ppt
A760535773_16727_28_2018_u6.pptA760535773_16727_28_2018_u6.ppt
A760535773_16727_28_2018_u6.ppt
 
Performing against the wall - SPI after completion
Performing against the wall - SPI after completionPerforming against the wall - SPI after completion
Performing against the wall - SPI after completion
 
EVM Without Quality is Unsuitable for Software Project & Program Management
EVM Without Quality is Unsuitable for Software Project & Program ManagementEVM Without Quality is Unsuitable for Software Project & Program Management
EVM Without Quality is Unsuitable for Software Project & Program Management
 
Virtual design and construction
Virtual design and constructionVirtual design and construction
Virtual design and construction
 
1587310189-week6.pptx
1587310189-week6.pptx1587310189-week6.pptx
1587310189-week6.pptx
 
Time Cost Trade Off
Time Cost Trade OffTime Cost Trade Off
Time Cost Trade Off
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
 
Advanced Scheduling for Large, Complex Industrial Projects
Advanced Scheduling for Large, Complex Industrial ProjectsAdvanced Scheduling for Large, Complex Industrial Projects
Advanced Scheduling for Large, Complex Industrial Projects
 
Monitoring and information systems
Monitoring and information systemsMonitoring and information systems
Monitoring and information systems
 
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...
 

Último

Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...amitlee9823
 
Call Girls In Majnu Ka Tilla 959961~3876 Shot 2000 Night 8000
Call Girls In Majnu Ka Tilla 959961~3876 Shot 2000 Night 8000Call Girls In Majnu Ka Tilla 959961~3876 Shot 2000 Night 8000
Call Girls In Majnu Ka Tilla 959961~3876 Shot 2000 Night 8000dlhescort
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with CultureSeta Wicaksana
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...daisycvs
 
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...amitlee9823
 
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort ServiceMalegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort ServiceDamini Dixit
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876dlhescort
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...amitlee9823
 
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableCall Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableSeo
 
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...lizamodels9
 
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort ServiceEluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort ServiceDamini Dixit
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...lizamodels9
 
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentationuneakwhite
 
Business Model Canvas (BMC)- A new venture concept
Business Model Canvas (BMC)-  A new venture conceptBusiness Model Canvas (BMC)-  A new venture concept
Business Model Canvas (BMC)- A new venture conceptP&CO
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfAdmir Softic
 
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLBAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLkapoorjyoti4444
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Centuryrwgiffor
 
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...amitlee9823
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityEric T. Tung
 

Último (20)

Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
 
Call Girls In Majnu Ka Tilla 959961~3876 Shot 2000 Night 8000
Call Girls In Majnu Ka Tilla 959961~3876 Shot 2000 Night 8000Call Girls In Majnu Ka Tilla 959961~3876 Shot 2000 Night 8000
Call Girls In Majnu Ka Tilla 959961~3876 Shot 2000 Night 8000
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
 
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort ServiceMalegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investors
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableCall Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
 
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
 
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort ServiceEluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
 
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentation
 
Business Model Canvas (BMC)- A new venture concept
Business Model Canvas (BMC)-  A new venture conceptBusiness Model Canvas (BMC)-  A new venture concept
Business Model Canvas (BMC)- A new venture concept
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLBAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 

(Presentation) Cis utilization of earned value management for monitoring production facilities

  • 1. (EVM-1848) CIS "Utilization of Earned Value Management for Monitoring Production Facilities" Dmitriy Skorobogatov Elena Rybina
  • 2. BIO of Elena Rybina • Degree Specialist Degree (Developing spacecraft and upper stages) • University Bauman Moscow Technical State University (Graduate) • Years of experience 8 years in professional fields listed below • Professional fields Project management, software development, cost control • Something what you do not know about me I worked in Siberia in winter 2
  • 3. BIO of Dmitriy Skorobogatov • Degree Specialist Degree (Theoretical and Experimental Physics of Nuclear Reactors) • University National Research Nuclear University MEPhI, Moscow (Graduate) Institute of Control Sciences V.A. Trapeznikov , Moscow (Ph.D-student) • Years of experience 7 years in professional fields listed below • Professional fields Project management, consulting • Something what you do not know about me My experience in nuclear science and barmen skills help me to figure out EVM 3
  • 5. 5 • This presentation identifies major features, which have significant impact on using Earned Value Management in these projects: The major features Technology intensive equipment Plenty of utility networks Technology intensive nature of a schedule Severe constraints on commissioning dates
  • 6. 6 • The presentation identifies 3 key points:The key points Measuring project progress in the context of contractor data manipulation Calculating EVM indices in technology intensive projects where major equipment represents a substantial part of the project budget Forecasting project execution dates and utilizing EMV indices.
  • 7. APPLYING EVM FOR EQUIPMENT 7
  • 8. 8 • Project progress is mainly determined by progress of the complete cycle: design – fabrication – delivery – installation – commissioning of equipment • Delivery of equipment to the stock does not weigh much in terms of the project overall progress. Installation and commissioning activities are much more important for this equipment. • Current situation allows the Contractor to manipulate with earned value indices. To demonstrate greater earned value and project progress the Contractor will try to deliver equipment as soon as possible to ensure higher EVM indicators
  • 9. 9 Activity Name Activity Type in Primavera Step Weight Procurement request Milestone 0% Execution of a vendor contract Task dependent activity 10% Development of equipment drawings Task dependent activity 25% Approval of equipment drawings Milestone 0% Equipment fabrication Task dependent activity 45% Acceptance of equipment by the Customer at the fabrication company premises Milestone 0% Ex-works shipment Task dependent activity 5% Delivery to the site Task dependent activity 10% Equipment is delivered Milestone 0% Spare part delivery Task dependent activity 2% Documents delivery Task dependent activity 3% • Planned cost of equipment is split into two parts: 20% of the overall cost of equipment is split into activities on design-fabrication-delivery and 80% - into installation and commissioning activities. • Cost of design-fabrication-delivery cycle is distributed through standard series of steps in accordance with their ‘unit weight
  • 10. 10 Before After Current situation allows the Contractor to manipulate with earned value indices. the Customer incurs financial losses, wastes time and does not have objective reporting data on the project progress execution. A ‘smooth’ S-curve is generated to reflect the project overall progress and to demonstrate progress for the whole cycle: design – fabrication – delivery – installation – commissioning. It is no longer possible to manipulate with EVM indices by the Contractor .
  • 11. EVALUATION OF PROJECT PROGRESS IN CONTEXT OF MANIPULATION BY THE CONTRACTOR 11
  • 12. 12 • The main way of manipulation is early implementation of expensive or simple activities contrary to the previously agreed schedule and work processes. • The activities with lowest cost values and significant restrictions on the ultimate intensity of work performance were deferred to the end • Project financing is affected on an annual basis and can be adjusted quarterly, thus earned value for the previous periods is one of the major indices taken into account when determining the scope of finance for the next year
  • 13. 13 High rate of works performance (SPI>1) in the first half of the project, and from these data the Customer expected that the project would be finished on time or earlier than the planned date, but then there happened a dramatic drop in earned value rates, which did not change significantly later. Finally, this project was executed with considerable schedule delays though the Customer could not foresee that and timely take administrative measures (including the decision to replace the Contractor). CD FD EV PV(t) 0
  • 14. 14 EV ≠0 PV=0 mEV is different from traditional earned value since it takes into account only earned value, which occurred within the planned dates or later
  • 15. 15 if 𝑃𝑉𝑡 = 0 then: 𝑀𝐸𝑉𝑡 = 0 if 𝑃𝑉𝑡 ≠ 0 𝑖=0 𝑡 𝐸𝑉𝑖 = 0 𝑀𝐸𝑉𝑡 = 𝐸𝑉𝑡 if 𝑃𝑉𝑡 ≠ 0 𝑖=0 𝑡 𝐸𝑉𝑖 ≠ 0 𝑀𝐸𝑉𝑡 = 𝑖=0 𝑡 𝐸𝑉𝑖
  • 16. 16 *However, there is a significant condition of using mEVt index and respective derived indices. If the activity is critical or near critical (i.e. its positive float is =<5 days) then for such activities: 𝑀𝐸𝑉𝑡 = 𝐸𝑉𝑡
  • 17. 17 Before (classical EVt) After (mEVt) CD FD EV time PV(t) 0 mEV(t) Contractor manipulates with earned value indices. The project was executed with considerable schedule delays though the Customer could not foresee that and timely take administrative measures CD FD EV PV(t) 0 Minimize the attempts of changing the previously approved processes of activities performance.
  • 18. 18 Optimistic: 𝑆𝑃𝐼 = 𝐸𝑉/𝑃𝑉 𝑃𝑒𝑠𝑠𝑖𝑚𝑖𝑠𝑡𝑖𝑐: 𝑝𝑆𝑃𝐼 = 𝑚𝐸𝑉/𝑃𝑉 𝑅𝑒𝑎𝑙𝑖𝑠𝑡𝑖𝑐: 𝑟𝑆𝑃𝐼 = (𝑆𝑃𝐼 + 𝑝𝑆𝑃𝐼)/2
  • 19. 19 Optimistic forecast, which is based on EV index and demonstrates optimistic situation on earned value rates at earlier stages of the project execution Pessimistic forecast, which is based on mEV index and demonstrates pessimistic situation on earned value rates at earlier stages of the project execution CD pFD time cost PV(t) 0 mEV(t) EV(t) eFD
  • 20. 20 • Develop real reporting on the project execution progress. This index takes into account only the activities performed according to the plan or earlier. This allows avoiding the situations when the Contractor intentionally tries to perform the most expensive and quickest activities at earlier stages and deferred activities at later stages of the project and significantly decrease the earned value rates. • Minimize the attempts of changing the previously approved processes of activities performance. If changing the processes of activities performance is a coercive measure then planned earned value indices shall be repeatedly agreed with the Customer taking into account a new schedule. • Motivate the Contractor for real instead of falsified reduction of project execution dates.
  • 22. 22 SPI can be calculated at any level of aggregation: both for an individual activity and for work packages combined on the ground of various analytical attributes. Moreover, this index can be calculated at any required level of details along the timeline, provided that the interval to determine this index is not less than the frequency of gathering EV actuals. The next step is proper extrapolation of this index to the remaining scope of work. Calculating SPI for each Contractor Calculating SPI for main types of activities
  • 23. 23 Advantages • Often a Contractor performs a series of activities (i.e. various types of activities) in a project for a long period of time, that is why to calculate SPI index, a vast scope of data can be used and forecasts can be built for a long time ahead (for the whole remaining scope of work of this Contractor). • The calculated SPI index allows evaluation of a Contractor from the viewpoint of meeting the construction dates. Then management decisions are made with respect to certain Contractors, even replace the Contractor, if required. • This technique allows maintaining a Dictionary of involved Contractors and their respective SPI indices. This information can be taken into account for future projects. Disadvantages • In practice, the accuracy of planning and the degree of meeting the planned dates mainly depends on the type of activity and project type, not on the Contractor. • If a major Contractor needs to be selected then this technique means only averaging SPI index for all project activities, which negatively affects the accuracy of forecasting. • Specialties of Business in Russia and Commonwealth of Independent States countries requires that many similar projects are executed in remote areas. Moreover, large territory of countries makes it impossible to mobilize a lot of the Contractor’s full-time staff and equipment to the site.
  • 24. 24 Advantages • In practice, the accuracy of planning and the degree of meeting the planned dates mainly depends on the type of activity and project type, not on the Contractor. Therefore, use of activity-related SPI index gives more accuracy during forecasting. • This technique allows maintaining one in- house dictionary of activity types and apply it at all project stages for forecasting real dates of activities performance, which are not contractor-related. It can be applied at the earliest project stages when the Contractor is not selected yet. • This technique is efficiently applied when one major Contractor is involved Disadvantages • Many efforts need to be invested to develop and update one dictionary of activity types with respective SPI indices. • Types of activities in a project are very tightly localized in one time period, therefore accuracy of forecasting decreases, since forecast for a specific type of activities can be built correctly only before activities of this type are completed. • It is more difficult to make management decisions with respect to certain Contractors based on activity-related SPI indices. Additional reports need to be generated to evaluate performance of each Contractor.
  • 25. 25 𝑎𝑆𝑃𝐼 𝑥 = 1 𝑐𝑇 ∗ 𝑡=1 𝑐𝑇 𝑎𝑆𝑃𝐼 𝑥𝑡 𝑎𝑝𝑆𝑃𝐼 𝑥= 1 𝑐𝑇 ∗ 𝑡=1 𝑐𝑇 𝑎𝑝𝑆𝑃𝐼 𝑥𝑡 arSPI 𝑥=(aSPI 𝑥+apSPI 𝑥)/2 cT – number of time periods from the start of activities performance to the data date aSPIxt – contractor-averaged SPI for the ‘t’ time period. apSPIxt - contractor-averaged pSPI for the ‘t’ time period. arSPI 𝑥 for each ‘x’ Contractor the schedule performance index, averaged for all reporting time periods from the project start
  • 26. 26 Software package, which includes Oracle® Primavera P6™“.and PM.BI solutions, is used to forecast the project execution dates. Oracle® Primavera P6™“.is used to develop the initial project schedule, to enter the activities planned dates and cost, to update schedules, and to calculate EVM traditional indices. Oracle Primavera P6® defines the following parameters for each activity of the schedule • Planned dates of performance • Planned cost of activity • Contractor for activity performance • Type of activity (in accordance with in-house dictionary of activity types) • If project activity is critical or near critical. • EV value is determined during the schedule update for all reporting time periods from the project start
  • 27. 27 I𝑚𝑝𝑜𝑟𝑡 𝑑𝑎𝑡𝑎 𝑓𝑟𝑜𝑚 𝑂𝑟𝑎𝑐𝑙𝑒 𝑃𝑟𝑖𝑚𝑎𝑣𝑒𝑟𝑎 𝐶𝑎𝑙𝑐𝑢𝑙𝑎𝑡𝑒 𝒎𝑬𝑽, for all activities and for all time periods to the data date arSPIx value for each ‘x’ Contractor If the Contractor for performance of the future activities is either not selected yet or selected but no actuals were available to calculate its arSPI index 𝒂𝒓𝑺𝑷𝑰 = 1 𝑋 ∗ 𝑥=1 𝑋 𝑎𝑟𝑆𝑃𝐼 𝑥 , arSPI –arSPIx index averaged for all Contractors X – overall quantity of project Contractors, for which actuals are sufficient to calculate arSPIx index.Import data arSPIx values to Oracle Primavera Calculate eDix=pDix* arSPIx eDix – forecasted duration of future ‘i’ activity, performed by ‘x’ Contractor, pDix - planned duration of future ‘i’ activity, performed by ‘x’ Contractor
  • 28. 28 PV (t) – planned earned value curve; EV (t) – actual earned value curve (optimistic); mEV (t) – actual modernized earned value curve (pessimistic); ceEV (t) – forecasted earned value curve for current plan, not taking SPI indices into account eEV (t) – forecasted modernized earned value curve, taking into account extrapolation of arSPIx index to the remaining scope of project work.
  • 30. 30 Planning and monitoring of the whole design-fabrication-delivery cycle of major equipment. ‘Smoothened’ earned value progress S- curve, which makes it possible to calculate SPI index broken down into the time periods. Use of modified earned value index – mEV. This index provides the manager an objective picture on project progress, excluding possible attempts of manipulation with traditional EVM indices by the Contractor. Moreover, this index calculates realistic SPI index. Forecasting project execution dates taking into account current dynamics of project execution. Forecasting is based on calculating SPI index of performed activities with respect to Contractors or activity types and further extrapolation of this index to the remaining scope of work.
  • 31. 31 Project stakeholders receive unbiased information on project progress. Contractor is motivated to adhere to the agreed approach of activities performance and to the agreed plans Contractor is motivated to gain real reduction of project execution dates instead of reduction falsified at early project stages.