SlideShare uma empresa Scribd logo
1 de 16
Good Neighbourly Relations
Committee
May 8, 2018
Update on work on the Jacques Cartier Bridge
(Montreal sector)
2
Agenda
Good Neighbourly Relations
Committee
+ Work on the steel structure
- Work status
- Planning for the coming weeks
- Noise mitigation measures
+ Other updates
+ Discussion period
+ Next meeting
3
Steel work 2017-2019
4
Work status
+ Contractor: Stellaire Construction
+ Work monitoring: WSC
+ Acoustic walls complete (80% of the site)
+ Reinforcement work has started
+ Work end date: December 2018
Acoustic panels on
De Maisonneuve Boulevard
5
Steel work schedule
+ Work planned for the coming weeks
- Installation of scaffolding (20% complete)
- Installation of noise mitigation measures
(20% complete)
• Boom lift, forklift and a tracked carrier at the site
- Steel repairs
• Removal of rivets during the day
• Reinforcement of steel towers
• Reinforcement of steel plates (night)
6
Steel work schedule
+ Work shifts
- Work shift from Monday to Friday until December
• 7:00 a.m. to 5:30 p.m. (10 workers)
- Work shift at night from Monday to Thursday
• 9:00 p.m. to 5:30 a.m. (10 workers)
• Night work consists of installing steel reinforcement
components
7
Current location of
sound level meters
De
Maisonneuve
Campion
8
Noise management
Noise management plan – steelwork site
+ Ongoing – Installation of acoustic barriers + noise
screens (80% complete)
+ Strict oversight of noise by the monitoring team
+ Optimization of work schedules (as much noisy
work as possible planned during the day)
9
Noise management
Measures have been monitored since start-up
+ Confinement of compressors (shelters made from plywood,
soundproofing panels and soundproofing wool)
+ Sound barrier installed near 2004 De Maisonneuve
+ Low-noise generator
10
Noise management
Measures have been monitored since start-up
+ Optimization of the work area
+ Attention paid to the choice and position of
temporary lighting
+ Contractor's work method
+ Site set up to reduce backing up of gangway
delivery truck
+ Boom lift with a white-noise back-up alarm
+ Forklift truck with a white-noise back-up alarm or
flagger used
+ Prebuilt gangway
+ Screws used as much as possible instead of nails
11
Upcoming steel work
Start-up in August 2018
between Ste-Catherine and Falardeau
12
Other work
+ Jacques Cartier Bridge multipurpose
path: opened April 2
+ Replacement of 266 guard-rail
sections on the multipurpose path
side: ongoing
+ Replacement of 266 guard rails on
the sidewalk side: ongoing
+ Results of the pilot winter
maintenance project on the
multipurpose path: to be released at
the end of summer
13
Partners
+ Organization that recovers
bottles for deposit and recyclable
materials for people in a situation
of poverty
+ JCCBI has supported this cause
for several years and is loaning
out a piece of land free of charge
+ June to September 2018
+ 3 containers, a chemical toilet
and small tents at the site
Discussion period
15
Let’s stay connected!
Information and communication tools
+ Notices to residents
+ Work advisories available online and via e-mail alerts
+ Resource people
+ Good Neighbourly Relations Committee
+ Twitter account for the Jacques Cartier Bridge @pontJCBridge
+ www.JacquesCartierChamplain.ca
Questions or comments?
+ 450-651-8771
+ communications@pjcci.ca
Next meeting TBD (mid-June to mid-July)
Jacques Cartier Bridge Good Neighbourly Relations Committee - May 8, 2018

Mais conteúdo relacionado

Mais procurados

13351_sitematch_zcard
13351_sitematch_zcard13351_sitematch_zcard
13351_sitematch_zcard
Samuel Blake
 
Project - WTS Concrete
Project - WTS ConcreteProject - WTS Concrete
Project - WTS Concrete
Damian Brandon
 
Russell Noanoa resume for 2015
Russell Noanoa resume for 2015Russell Noanoa resume for 2015
Russell Noanoa resume for 2015
Russell Noanoa
 
Syzygy Renewables_Company_Info_August 2016
Syzygy Renewables_Company_Info_August 2016Syzygy Renewables_Company_Info_August 2016
Syzygy Renewables_Company_Info_August 2016
Andrew Hancock
 
City council august 20, 2013 agenda item 13 river project
City council august 20, 2013 agenda item 13 river projectCity council august 20, 2013 agenda item 13 river project
City council august 20, 2013 agenda item 13 river project
City of San Angelo Texas
 
Share with Pride IP Wales Tonfanau Rev1 - Revised
Share with Pride IP Wales  Tonfanau Rev1 - RevisedShare with Pride IP Wales  Tonfanau Rev1 - Revised
Share with Pride IP Wales Tonfanau Rev1 - Revised
Kane Evans
 

Mais procurados (13)

13351_sitematch_zcard
13351_sitematch_zcard13351_sitematch_zcard
13351_sitematch_zcard
 
Illumination of the Jacques Cartier Bridge
Illumination of the Jacques Cartier BridgeIllumination of the Jacques Cartier Bridge
Illumination of the Jacques Cartier Bridge
 
Project - WTS Concrete
Project - WTS ConcreteProject - WTS Concrete
Project - WTS Concrete
 
Russell Noanoa resume for 2015
Russell Noanoa resume for 2015Russell Noanoa resume for 2015
Russell Noanoa resume for 2015
 
Job layout per
Job layout perJob layout per
Job layout per
 
Syzygy Renewables_Company_Info_August 2016
Syzygy Renewables_Company_Info_August 2016Syzygy Renewables_Company_Info_August 2016
Syzygy Renewables_Company_Info_August 2016
 
Ian Fawthrop - Waste Data
Ian Fawthrop - Waste DataIan Fawthrop - Waste Data
Ian Fawthrop - Waste Data
 
City council august 20, 2013 agenda item 13 river project
City council august 20, 2013 agenda item 13 river projectCity council august 20, 2013 agenda item 13 river project
City council august 20, 2013 agenda item 13 river project
 
2018 MATC Intern Program - Rodrigo Quintero Paez
2018 MATC Intern Program - Rodrigo Quintero Paez2018 MATC Intern Program - Rodrigo Quintero Paez
2018 MATC Intern Program - Rodrigo Quintero Paez
 
Maximizing Solid Alternative Fuels
Maximizing Solid Alternative FuelsMaximizing Solid Alternative Fuels
Maximizing Solid Alternative Fuels
 
02 tsl from tender until rfc by pablo arecco
02 tsl from tender until rfc by pablo arecco02 tsl from tender until rfc by pablo arecco
02 tsl from tender until rfc by pablo arecco
 
Share with Pride IP Wales Tonfanau Rev1 - Revised
Share with Pride IP Wales  Tonfanau Rev1 - RevisedShare with Pride IP Wales  Tonfanau Rev1 - Revised
Share with Pride IP Wales Tonfanau Rev1 - Revised
 
Alhagueces Overview Nov08-Jun09
Alhagueces Overview Nov08-Jun09Alhagueces Overview Nov08-Jun09
Alhagueces Overview Nov08-Jun09
 

Semelhante a Jacques Cartier Bridge Good Neighbourly Relations Committee - May 8, 2018

Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Crosstown TO
 
Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017
Crosstown TO
 

Semelhante a Jacques Cartier Bridge Good Neighbourly Relations Committee - May 8, 2018 (20)

Good Neighbourly Relations Committee - Jacques Cartier Bridge - February 6, 2018
Good Neighbourly Relations Committee - Jacques Cartier Bridge - February 6, 2018Good Neighbourly Relations Committee - Jacques Cartier Bridge - February 6, 2018
Good Neighbourly Relations Committee - Jacques Cartier Bridge - February 6, 2018
 
2018 Planning
2018 Planning2018 Planning
2018 Planning
 
2017 Planning: Presentation of major projects
2017 Planning: Presentation of major projects2017 Planning: Presentation of major projects
2017 Planning: Presentation of major projects
 
Jacques Cartier Bicycle Path Network - Advisory Committee - October 4, 2017
Jacques Cartier Bicycle Path Network - Advisory Committee - October 4, 2017Jacques Cartier Bicycle Path Network - Advisory Committee - October 4, 2017
Jacques Cartier Bicycle Path Network - Advisory Committee - October 4, 2017
 
Good Neighbourly Relations Committee Meeting - Brossard - November 15, 2017
Good Neighbourly Relations Committee Meeting - Brossard - November 15, 2017Good Neighbourly Relations Committee Meeting - Brossard - November 15, 2017
Good Neighbourly Relations Committee Meeting - Brossard - November 15, 2017
 
Meeting of the brossard good neighbourly relations committee september 21 2016
Meeting of the brossard good neighbourly relations committee   september 21 2016Meeting of the brossard good neighbourly relations committee   september 21 2016
Meeting of the brossard good neighbourly relations committee september 21 2016
 
Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...
Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...
Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...
 
Good neighbourly relations committee meeting - Brossard - January 25, 2017
Good neighbourly relations committee meeting - Brossard - January 25, 2017Good neighbourly relations committee meeting - Brossard - January 25, 2017
Good neighbourly relations committee meeting - Brossard - January 25, 2017
 
Review of work in 2016
Review of work in 2016Review of work in 2016
Review of work in 2016
 
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  finalCollege Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 final
 
Brossard Good Neighbourly Relations Committee - May 17, 2017
Brossard Good Neighbourly Relations Committee - May 17, 2017Brossard Good Neighbourly Relations Committee - May 17, 2017
Brossard Good Neighbourly Relations Committee - May 17, 2017
 
Good neighbourly relations committee City of Brossard - May 4, 2016
Good neighbourly relations committee City of Brossard - May 4, 2016Good neighbourly relations committee City of Brossard - May 4, 2016
Good neighbourly relations committee City of Brossard - May 4, 2016
 
Plan for major repairs and maintenance work on JCCBI structures
Plan for major repairs and maintenance work on JCCBI structuresPlan for major repairs and maintenance work on JCCBI structures
Plan for major repairs and maintenance work on JCCBI structures
 
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
 
Jacques Cartier Bicycle Path Network - Advisory Committee
Jacques Cartier Bicycle Path Network - Advisory CommitteeJacques Cartier Bicycle Path Network - Advisory Committee
Jacques Cartier Bicycle Path Network - Advisory Committee
 
Solution Bonaveture
Solution BonavetureSolution Bonaveture
Solution Bonaveture
 
Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee
Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations CommitteeMeeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee
Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee
 
Details of anti noise walls - june 15 2016 - nouveau pont champlain
Details of anti noise walls - june 15 2016 - nouveau pont champlainDetails of anti noise walls - june 15 2016 - nouveau pont champlain
Details of anti noise walls - june 15 2016 - nouveau pont champlain
 
The Millau Viaduct Project - An Engineering Marvel
The Millau Viaduct Project - An Engineering MarvelThe Millau Viaduct Project - An Engineering Marvel
The Millau Viaduct Project - An Engineering Marvel
 
Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017
 

Mais de Ponts Jacques Cartier + Champlain Bridges

Mais de Ponts Jacques Cartier + Champlain Bridges (20)

2018-06-19 - Réseau cyclable du pont Jacques-Cartier - Comité consultatif
2018-06-19 - Réseau cyclable du pont Jacques-Cartier - Comité consultatif2018-06-19 - Réseau cyclable du pont Jacques-Cartier - Comité consultatif
2018-06-19 - Réseau cyclable du pont Jacques-Cartier - Comité consultatif
 
2018-06-19 - Jacques Cartier Bicycle Path Network - Advisory Committee
2018-06-19 - Jacques Cartier Bicycle Path Network - Advisory Committee 2018-06-19 - Jacques Cartier Bicycle Path Network - Advisory Committee
2018-06-19 - Jacques Cartier Bicycle Path Network - Advisory Committee
 
Jacques Cartier Bicycle Path Network - Advisory Committee - April 30, 2018
Jacques Cartier Bicycle Path Network - Advisory Committee - April 30, 2018Jacques Cartier Bicycle Path Network - Advisory Committee - April 30, 2018
Jacques Cartier Bicycle Path Network - Advisory Committee - April 30, 2018
 
Comité consultatif - Réseau cyclable du pont Jacques-Cartier - 30 avril 2018
Comité consultatif - Réseau cyclable du pont Jacques-Cartier - 30 avril 2018Comité consultatif - Réseau cyclable du pont Jacques-Cartier - 30 avril 2018
Comité consultatif - Réseau cyclable du pont Jacques-Cartier - 30 avril 2018
 
Comité de bon voisinage du pont Jacques-Cartier - 8 mai 2018
Comité de bon voisinage du pont Jacques-Cartier - 8 mai 2018Comité de bon voisinage du pont Jacques-Cartier - 8 mai 2018
Comité de bon voisinage du pont Jacques-Cartier - 8 mai 2018
 
Jacques Cartier Bicycle Path Network - Advisory Committee - June 22, 2017
Jacques Cartier Bicycle Path Network - Advisory Committee - June 22, 2017Jacques Cartier Bicycle Path Network - Advisory Committee - June 22, 2017
Jacques Cartier Bicycle Path Network - Advisory Committee - June 22, 2017
 
Réseau cyclable du pont Jacques-Cartier - Comité consultatif - Rencontre du 2...
Réseau cyclable du pont Jacques-Cartier - Comité consultatif - Rencontre du 2...Réseau cyclable du pont Jacques-Cartier - Comité consultatif - Rencontre du 2...
Réseau cyclable du pont Jacques-Cartier - Comité consultatif - Rencontre du 2...
 
Réseau cyclable du pont Jacques-Cartier - Comité consultatif - Rencontre du 4...
Réseau cyclable du pont Jacques-Cartier - Comité consultatif - Rencontre du 4...Réseau cyclable du pont Jacques-Cartier - Comité consultatif - Rencontre du 4...
Réseau cyclable du pont Jacques-Cartier - Comité consultatif - Rencontre du 4...
 
Planification 2018
Planification 2018Planification 2018
Planification 2018
 
Comité de bon voisinage - pont Jacques-Cartier - 6 février 2018
Comité de bon voisinage - pont Jacques-Cartier - 6 février 2018Comité de bon voisinage - pont Jacques-Cartier - 6 février 2018
Comité de bon voisinage - pont Jacques-Cartier - 6 février 2018
 
Solution Bonaventure - Projet environnemental visant à protéger le fleuve Sai...
Solution Bonaventure - Projet environnemental visant à protéger le fleuve Sai...Solution Bonaventure - Projet environnemental visant à protéger le fleuve Sai...
Solution Bonaventure - Projet environnemental visant à protéger le fleuve Sai...
 
Réseau cyclable du pont Jacques-Cartier - Comité consultatif
Réseau cyclable du pont Jacques-Cartier - Comité consultatifRéseau cyclable du pont Jacques-Cartier - Comité consultatif
Réseau cyclable du pont Jacques-Cartier - Comité consultatif
 
Assemblée publique annuelle 2017 / Annual Public Meeting 2017
Assemblée publique annuelle 2017 / Annual Public Meeting 2017Assemblée publique annuelle 2017 / Annual Public Meeting 2017
Assemblée publique annuelle 2017 / Annual Public Meeting 2017
 
Planification 2017 : Présentation des chantiers majeurs
Planification 2017 : Présentation des chantiers majeursPlanification 2017 : Présentation des chantiers majeurs
Planification 2017 : Présentation des chantiers majeurs
 
Réseau cyclable et piétonnier 2016
Réseau cyclable et piétonnier  2016Réseau cyclable et piétonnier  2016
Réseau cyclable et piétonnier 2016
 
Bilan des travaux 2016 de PJCCI
Bilan des travaux 2016 de PJCCIBilan des travaux 2016 de PJCCI
Bilan des travaux 2016 de PJCCI
 
Annual Public Meeting 2016
Annual Public Meeting 2016Annual Public Meeting 2016
Annual Public Meeting 2016
 
Assemblée publique annuelle 2016
Assemblée publique annuelle 2016Assemblée publique annuelle 2016
Assemblée publique annuelle 2016
 
Solution Bonaventure
Solution BonaventureSolution Bonaventure
Solution Bonaventure
 
Planification des travaux de réfection et d'entretien majeur des structures P...
Planification des travaux de réfection et d'entretien majeur des structures P...Planification des travaux de réfection et d'entretien majeur des structures P...
Planification des travaux de réfection et d'entretien majeur des structures P...
 

Último

Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 

Último (20)

Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
Bridge Jacking Design Sample Calculation.pptx
Bridge Jacking Design Sample Calculation.pptxBridge Jacking Design Sample Calculation.pptx
Bridge Jacking Design Sample Calculation.pptx
 
Rums floating Omkareshwar FSPV IM_16112021.pdf
Rums floating Omkareshwar FSPV IM_16112021.pdfRums floating Omkareshwar FSPV IM_16112021.pdf
Rums floating Omkareshwar FSPV IM_16112021.pdf
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 

Jacques Cartier Bridge Good Neighbourly Relations Committee - May 8, 2018

  • 1. Good Neighbourly Relations Committee May 8, 2018 Update on work on the Jacques Cartier Bridge (Montreal sector)
  • 2. 2 Agenda Good Neighbourly Relations Committee + Work on the steel structure - Work status - Planning for the coming weeks - Noise mitigation measures + Other updates + Discussion period + Next meeting
  • 4. 4 Work status + Contractor: Stellaire Construction + Work monitoring: WSC + Acoustic walls complete (80% of the site) + Reinforcement work has started + Work end date: December 2018 Acoustic panels on De Maisonneuve Boulevard
  • 5. 5 Steel work schedule + Work planned for the coming weeks - Installation of scaffolding (20% complete) - Installation of noise mitigation measures (20% complete) • Boom lift, forklift and a tracked carrier at the site - Steel repairs • Removal of rivets during the day • Reinforcement of steel towers • Reinforcement of steel plates (night)
  • 6. 6 Steel work schedule + Work shifts - Work shift from Monday to Friday until December • 7:00 a.m. to 5:30 p.m. (10 workers) - Work shift at night from Monday to Thursday • 9:00 p.m. to 5:30 a.m. (10 workers) • Night work consists of installing steel reinforcement components
  • 7. 7 Current location of sound level meters De Maisonneuve Campion
  • 8. 8 Noise management Noise management plan – steelwork site + Ongoing – Installation of acoustic barriers + noise screens (80% complete) + Strict oversight of noise by the monitoring team + Optimization of work schedules (as much noisy work as possible planned during the day)
  • 9. 9 Noise management Measures have been monitored since start-up + Confinement of compressors (shelters made from plywood, soundproofing panels and soundproofing wool) + Sound barrier installed near 2004 De Maisonneuve + Low-noise generator
  • 10. 10 Noise management Measures have been monitored since start-up + Optimization of the work area + Attention paid to the choice and position of temporary lighting + Contractor's work method + Site set up to reduce backing up of gangway delivery truck + Boom lift with a white-noise back-up alarm + Forklift truck with a white-noise back-up alarm or flagger used + Prebuilt gangway + Screws used as much as possible instead of nails
  • 11. 11 Upcoming steel work Start-up in August 2018 between Ste-Catherine and Falardeau
  • 12. 12 Other work + Jacques Cartier Bridge multipurpose path: opened April 2 + Replacement of 266 guard-rail sections on the multipurpose path side: ongoing + Replacement of 266 guard rails on the sidewalk side: ongoing + Results of the pilot winter maintenance project on the multipurpose path: to be released at the end of summer
  • 13. 13 Partners + Organization that recovers bottles for deposit and recyclable materials for people in a situation of poverty + JCCBI has supported this cause for several years and is loaning out a piece of land free of charge + June to September 2018 + 3 containers, a chemical toilet and small tents at the site
  • 15. 15 Let’s stay connected! Information and communication tools + Notices to residents + Work advisories available online and via e-mail alerts + Resource people + Good Neighbourly Relations Committee + Twitter account for the Jacques Cartier Bridge @pontJCBridge + www.JacquesCartierChamplain.ca Questions or comments? + 450-651-8771 + communications@pjcci.ca Next meeting TBD (mid-June to mid-July)