2. 2
Agenda
Good Neighbourly Relations
Committee
+ Work on the steel structure
- Work status
- Planning for the coming weeks
- Noise mitigation measures
+ Other updates
+ Discussion period
+ Next meeting
4. 4
Work status
+ Contractor: Stellaire Construction
+ Work monitoring: WSC
+ Acoustic walls complete (80% of the site)
+ Reinforcement work has started
+ Work end date: December 2018
Acoustic panels on
De Maisonneuve Boulevard
5. 5
Steel work schedule
+ Work planned for the coming weeks
- Installation of scaffolding (20% complete)
- Installation of noise mitigation measures
(20% complete)
• Boom lift, forklift and a tracked carrier at the site
- Steel repairs
• Removal of rivets during the day
• Reinforcement of steel towers
• Reinforcement of steel plates (night)
6. 6
Steel work schedule
+ Work shifts
- Work shift from Monday to Friday until December
• 7:00 a.m. to 5:30 p.m. (10 workers)
- Work shift at night from Monday to Thursday
• 9:00 p.m. to 5:30 a.m. (10 workers)
• Night work consists of installing steel reinforcement
components
8. 8
Noise management
Noise management plan – steelwork site
+ Ongoing – Installation of acoustic barriers + noise
screens (80% complete)
+ Strict oversight of noise by the monitoring team
+ Optimization of work schedules (as much noisy
work as possible planned during the day)
9. 9
Noise management
Measures have been monitored since start-up
+ Confinement of compressors (shelters made from plywood,
soundproofing panels and soundproofing wool)
+ Sound barrier installed near 2004 De Maisonneuve
+ Low-noise generator
10. 10
Noise management
Measures have been monitored since start-up
+ Optimization of the work area
+ Attention paid to the choice and position of
temporary lighting
+ Contractor's work method
+ Site set up to reduce backing up of gangway
delivery truck
+ Boom lift with a white-noise back-up alarm
+ Forklift truck with a white-noise back-up alarm or
flagger used
+ Prebuilt gangway
+ Screws used as much as possible instead of nails
12. 12
Other work
+ Jacques Cartier Bridge multipurpose
path: opened April 2
+ Replacement of 266 guard-rail
sections on the multipurpose path
side: ongoing
+ Replacement of 266 guard rails on
the sidewalk side: ongoing
+ Results of the pilot winter
maintenance project on the
multipurpose path: to be released at
the end of summer
13. 13
Partners
+ Organization that recovers
bottles for deposit and recyclable
materials for people in a situation
of poverty
+ JCCBI has supported this cause
for several years and is loaning
out a piece of land free of charge
+ June to September 2018
+ 3 containers, a chemical toilet
and small tents at the site
15. 15
Let’s stay connected!
Information and communication tools
+ Notices to residents
+ Work advisories available online and via e-mail alerts
+ Resource people
+ Good Neighbourly Relations Committee
+ Twitter account for the Jacques Cartier Bridge @pontJCBridge
+ www.JacquesCartierChamplain.ca
Questions or comments?
+ 450-651-8771
+ communications@pjcci.ca
Next meeting TBD (mid-June to mid-July)